HPBC Checklists 2024
HPBC Checklists 2024
Additional Comments:
✓ - OK / X - NO / NA - Not Applied
HPBC Representative Site Representative
Organization Owner Representative
(EIET) (PE-Construction)
Singnature
Name
Position
HIGH-RISE AND PUBLIC BUILDING PROJECTS COMMITTEE (HPBC)
2.CHECKLIST FOR INSTALLATION OF PRESS PILE
Project Date
Reg; No:
Location
Dwg Ref;
Piling No of
Contractor Storey
Checked by
No. Checked List Items Remark
Inspectors
1 Piling Company ; ----------------------
Geotechnical / Construction Engineer ; ----------------,PE -----------
Experienced engineer for supervision ;Name;-------------------
Surveyor ; Name ; -------------------
Skillful operator : Name ; ----------------------
Submission of Method Statement (MS)
2 SPECIFICATIONS OF PRESS PILING WORK
Pile Types (Square or Spun piles) : ------------------------
Total Numbers of Pile Points: ------------------------------
Finished numbers of Pile Points: --------------------------
Square pile sizes or Pile diameters, thickness (Spun pile)
Pile Lengths: --------------------
Concrete grade: ----------------------
Concrete Strength Test with adequate number of samples
Slump Test with adequate number of samples
Reinforcement Ex.:
1. Main ;------------------------- (ex. 25T4) T – 460 N/mm2
2. Link ;------------------------- (ex. T12 @ 150) Y = 410 N/mm2
Concrete cover ;-------------------------- mm R = 250 N/mm2
Additional Comments
✓ - OK / X - NO / NA - Not Applied
HPBC Owner
Site Representative
Organization Representative Representative
(PE -Construction)
(EIET)
Signature
Name
Position
HIGH-RISE AND PUBLIC BUILDING PROJECTS COMMITTEE (HPBC)
3.CHECKLIST FOR DEEP EXCAVATION
Project Date
Reg; No:
Location
Dwg Ref;
Piling No of
Contractor Storey
Checked
No. Checked List Items by Remark
Inspectors
1 SPECIFICATIONS OF DEEP EXCAVATION
ERSS Types
(the construction of walls shall be inspected by separate checklists) ok or
Not ok
Basement layers or depth:
Excavation dimensions: L x W (avg) -----------------------
Basement construction method: Top down or bottom up
Construction company:
Geotechnical designer: -------------------, PE----------------
Structural designer: -----------------------, PE----------------
National counterpart: , PE
National counterpart: , PE
Support types: Steel beams or concrete, --------------------
1. Steel beams (Size, shape and grade based on design)
2. Concrete beams (concrete grade, reinforcement steel grade
etc.)
Concrete Strength Test with adequate number of samples
Strength Test or specifications steel
2 TEMPORARY DRAINAGE
The contractor shall provide the temporary drainage
1. Provide proper settled pond to clean polluted water
2. Proper connection to public drainage lines
All filled ground shall be leveled to gradient to facilitate
the discharge of surface water runoff
All exposed cut and fill ground slope shall be covered by
the plastic sheet of suitable materials to protect the duct or rain water.
Additional Comments
✓ - OK / X - NO / NA - Not Applied
HPBC Owner
Site Representative
Organization Representative Representative
(PE -Construction)
(EIET)
Signature
Name
Position
HIGH-RISE AND PUBLIC BUILDING PROJECTS COMMITTEE (HPBC)
4.CHECKLIST FOR STATIC PILE LOAD TEST
Project Date
Reg; No:
Location
Dwg Ref;
Piling No of
Contractor Storey
Checked by
No. Checked List Items Remark
Inspectors
Optical
Correction for IRB ruler with equal distances
Check the proper conditions of Fixed datum;
Pile head Movement-ruler on pile
Reaction Pile Movement-ruler on pile
Ruler Arrangement; (tick below)
1. Increasing values - settlement
2. Decreasing value - settlement
Miscellaneous
Standardized stop watch or clock
Standardized leveling equipment
Proper arrangement of lighting in night measurement
6 CHECK THE CPACITY OF FRAME OR KENTLEDGE
Check the structural and geotechnical of reaction piles as
per MS or Estimate the weight of block
8 RECORDS
Additional Comments
✓ - OK / X - NO / NA - Not Applied
HPBC
Site Representative Owner
Organization Representative
(PE -Construction) Representative
(EIET)
Signature
Name
Position
HIGH-RISE AND PUBLIC BUILDING PROJECTS COMMITTEE (HPBC)
5.CHECKLIST FOR DYNAMIC PILE LOAD TEST
Project Date
Reg; No:
Location
Dwg Ref;
Piling No of
Contractor Storey
Checked
No. Checked List Items by Remark
Inspectors
1 Pile Test Company:
Geotechnical Engineer: ------------------------, PE----------------
Experienced engineer for supervision: Name; -------------------
Surveyor: Name; -------------------
Skillful operator: Name; -------------------
Submission of Method Statement (MS) of Dynamic Load Test
2 SPECIFICATIONS OF LOAD TEST
Type of pile load test: DLT: -----------------------------
Pile load test number: DLT-------------------------------
Pile diameter (bored) mm,
Square: ----------mm x mm
Pile length, m
Pile capacity tons
Maximum pile test load: ------------------tons, %
Pile integrity, Test result;
Check the full strength of concrete pile
3 TEST FOUNDATION PREPARATION
Check the excavate or fill surface level to the final pile
Photos
elevation (clear distance from ground surface );
Check the cleaning any disturbing material around the test pile;
Photos
Additional Comments
✓ - OK / X - NO / NA - Not Applied
HPBC
Site Representative Owner
Organization Representative
(PE -Construction) Representative
(EIET)
Signature
Name
Position
Checklists for INSPECTION
HPBC/INSP/001/2024
2 Adequate Bracing
3 Condition of Working Platforms
4 Guard up to working up
5 Catching Net for Falling Objects
Additional Comments:
✓ - OK / X - NO / NA - Not Applied
HPBC Representative Site Representative Owner
Organization
(EIET) (PE-Construction) Representative
Singnature
Name
Position
HPBC/INSP/002/2024
9 Lapping length
10 Location of spliced length
11 Coupler joint detail (if any)
12 Thermit welding joint detail (if any)
13 Adequate anchorage length
14 Rebar cleanliness
15 Rebar position (Possible to vibrate)
16 Trimming Bars
1 Trial Mixed Documents Provided
2 Mix Design Provided
3 Approved Concrete Supplier
4 Slump test / Workability
Before Concreting
✓ - OK / X - NO / NA - Not Applied
Singnature
Name
Position
HPBC/INSP/003/2024
1
Trucks
Accordingly
Sample Cubes are Kept in Proper Storage,
2
away from Direct Sun
Proper Sample Cubes Handling after Taking
3
out From Moulds
Additional Comments:
Singnature
Name
Position
HPBC/INSP/004/2024
1
Formwork
Proper Removal without Damaging the Concrete
2
Structure
Adequate Removal Time for Props of Structural
1
Members
PROPS
Additional Comments:
Singnature
Name
Position
HPBC/INSP/005/2024
2 Type of Bricks
Cleaning of work area before commencing masonary
3
work
4 Vertical plumb lines are in correct position
1 Horizontal Alignment
2 Vertical Alignment
Brick Installation
4 Stiffener Beams/Columns
6 Curing
Additional Comments:
Singnature
Name
Position
HPBC/INSP/006
Location: Stage:
Ladders &
2 Toolbox meetings 24 Temporary handrail installed
Stairs
Emergency program and phone
3 25 Temporary lighting installed
posted
4 Nobody to smoke in the site 26 All connections secure
Scaffolds
5 Chewing betel leave and spitting 27 Scaffold tied to structure
6 External Safety Net installed 28 Scaffolds erected on compacted area
7 Adequate lighting 29 Cross braces are completed
General
Signature
Name
Position
HPBC/INSP1
General Records
Additional Comments/Findings
Signature
Name
Position
HPBC/INSP2
Signature
Name
Position
Checklist for Architectural Discipline
HIGH-RISE AND PUBLIC BUILDING PROJECTS COMMITTEE (HPBC)
Inspection Checklist (Architectural Discipline)
Planning
1 Traffic Flow
2 Minimum Set Backs
3 Building Height
4 Permeable Area & Green Area
5 Car Parking Number s and Area
6 Space Provision For Water & Sanitation
7 Space Provision For M&E Services
8 Site Drainage System
Architectural Design
Singnature
Name
Position
Checklist for ACMV Discipline
HIGH-RISE AND PUBLIC BUILDING PROJECTS COMMITTEE (HPBC)
RN : Date of inspection :
Type of Building :
I. AIRCONDITION
Aircondition System
II. VENTILATION
Where space provided is not adeq uate the inspector's comments separate sheet may be used for all columns.
Signature
Name
Position
Checklist for Electrical Discipline
HIGH-RISE AND PUBLIC BUILDING PROJECTS COMMITTEE (HPBC)
RN : Date of inspection :
Type of Building :
(b) New drawing which shows details of loads and circuits are enclosed.Drawing No.---------------------
( Date: )
POWER SOURCE
2 Serial No.
Phase to Phase
Supply Voltage (V)
Phase to Earth
Rated KVA
Power Factor
Frequency (Hz)
Fuel Used
4.1 The type of earthing system for electrical installation supplied from generating set, is TN-S or T.T.
4.2 Main earthing terminal or bar is adequately sized and properly installed.
4.3 Earth inspection chamber is accessible for inspection.
4.4 Bonding of metallic parts, where applicable, is adequate.
5 GENERATING SET C NC NA
5.1 Barricaded to prevent access by non-authorized persons.
5.2 Adequate working space around generating set.
5.3 Access to generating set not impeded.
5.4 Generating set not installed in damp or exposed conditions.
5.5 Generating set not installed in hazardous location.
5.6 All live parts protected against direct contact.
5.7 Adequately sized earthing bar or terminal is provided.
5.8 Proper labelling of earthing conductors provided.
5.9 For 3Ø generator> 55 V, star-point is earthed.
5.10 For 1Ø generator> 55 V, neutral is earthed.
5.11 Engine frame and generator frame bonded to earth.
5.12 Bonding of metallic parts, where applicable, is adequate.
5.13 All outgoing supply cables provided with overcurrentand earth fault protection.
5.14 Protective devices are in operating condition.
6 MAINS INCOMING SUPPLY AND EARTH LEAKAGE PROTECTION C NC NA
6.1 For incoming supply ≤ 300 A 3Ø, a circuit breaker with residual current device is used.
For incoming supply > 300 A 3Ø, a circuit breaker with overcurrent and earth protective devices
6.2
are used.
Residual current circuit breaker with tripping current 100 mA operates within 0.1 s at rated tripping
6.3
current.
6.4 Earth fault loop impedance is tested for satisfactory operation against indirect contact.
6.5 Overall insulation resistance ≥ 1.0 MΩ
(a) phase to phase,
(b) phase to earth,
(c) phase to neutral,
(d) neutral to earth.
6.6 Earthing conductor is appropriately sized and properly terminated.
6.7 Warning signs are displayed at main generating set and main intake switchboard.
6.8 CPR Chart are displayed in main switch room
6.9 Rubber mat are laid beside MSB boards.
6.10 Fire extinguishers are installed in MSB room.
7 DISTRIBUTION BOARD (DB) C NC NA
7.7 No metal sheath or armour of any cable is used as circuit protective conductor.
8 FINAL CIRCUITS C NC NA
8.1 For final circuits ≤ 63 A, RCCB with tripping current ≤ 30 mA operates within 0.1 s.
For final circuits exceeding 63 A but not exceeding 100A, RCCB with tripping current ≤
8.2
300 mA operates within 0.1s.
8.3 For final circuits >100A,a RCD with tripping current not exceeding 500mA is provided.
8.6 All flexible cords,switches,plugs and socket outlets are in good and serviceable condition.
8.7 Rewireable fuses are not used except for socket-outlet incorporated with fuses.
All switches for 1Ø supply ≤ 230V shall be of double-pole type with protection in each live
8.8
conductor.
8.9 Colour codes of plug, socket-outlet and cable coupler of different operating voltages are correct.
9 SOCKET-OUTLET ASSEMBLY C NC NA
Each fixed socket-outlet protected by approved type residual current circuit breaker (RCCB),
9.5
current rating not exceeding 30 mA and a MCB.
10 ENVIRONMENTAL CONDITIONS C NC NA
11 Lightning Arrester C NC NA
Temporary Lightning Arrester installation is installed up to the building finished high-rise level
11.1
according to the code of practice as per guide line.
12 GENERAL OBSERVATIONS
(b) Proper Earthing system has been provided for the following stationery equipment such as :
HPBC Representative
Organization Site Representative Owner Representative
(EIET)
Signature
Name
Position
Checklist for WATSAN Discipline
Checklist for Building Plumbing and Sanitary Services
Mobilization phase:
(Before Construction:)
Construction phase:
(During Construction:)
1. Installation:
o Verify that plumbing installations adhere to the approved design and plans.
o Ensure proper installation of pipes, fixtures, and fittings to prevent leaks.
o Check for proper slope and alignment of drainage pipes to ensure efficient
flow.
o Ensure adequate support and anchoring of pipes and fixtures as per drawing,
shop drawing and codes.
2. Testing:
o Conduct pressure tests on water supply lines to check for leaks.
o Perform water flow tests to ensure adequate pressure and flow rates.
o Inspect drainage systems using smoke tests or cameras to check for blockages
or leaks.
3. Quality Control:
o Regularly inspect the quality of work to ensure compliance with standards.
o Ensure all materials used are as per specifications and free from defects.
o Maintain a record of inspections and tests conducted.
o Make sure proper slope to floor drain.
o Check for well functioning of floor drain.
4. Coordination:
o Coordinate with other trades (electrical, HVAC) to avoid conflicts.
o Ensure proper spacing and alignment of plumbing systems with other services.
5. Safety:
o Implement safety protocols and use appropriate personal protective equipment
(PPE).
o Ensure trenches and excavations are properly shored and safe for workers.
Winding up phase:
(After Construction:)
1. Final Inspections:
o Conduct a final inspection of all plumbing and sanitary installations.
o Ensure all fixtures and fittings are properly installed and operational.
o Verify that all systems are clean and free from debris.
o Ensure the installation follow the drawing or shop drawing.
2. System Testing:
o Perform a comprehensive system test, including pressure testing, flow testing,
and leak detection.
o Ensure all systems are functioning as intended without any issues.
3. Compliance and Documentation:
o Obtain final approval from local authorities and ensure compliance with all
regulations.
o Compile and store all documentation, including permits, inspection reports,
and test results.
4. User Training:
o Provide training to building occupants on the proper use and maintenance of
plumbing systems, firefighting system.
o Ensure occupants are aware of emergency shut-off locations and procedures,
by pass procedure and start up procedure.
5. Maintenance Plan:
o Develop a maintenance schedule for regular inspection and servicing of
plumbing systems including equipment.
o Provide a list of contacts for emergency repairs and maintenance services.
6. Warranty and Handover:
o Ensure all installed systems and materials come with warranties.
o Handover all manuals, warranties, and maintenance schedules to the building
owner or manager.
Mobilization phase:
(Before Construction:)
Design and Obtain detailed drawings, ensure compliance with codes, confirm []
Planning water supply and drainage plans. Obtain also design calculation and Complete
report.
Approvals and Obtain necessary permits and clearances from local authorities. []
Permits Complete
Material Select quality materials for pipes, fittings, fixtures, and valves and []
Selection equipment. Complete
Task Description Status
Site Preparation Conduct site survey, both horizontal and vertical plan excavation and []
safety measures, arrange temporary water/sanitation. Complete
Safety Planning Develop safety plan, train workers on safety procedures and []
emergency protocols and fire drill. Complete
Construction phase:
(During Construction:)
Testing Conduct pressure tests, water flow tests, and inspect drainage systems []
for blockages or leaks. Test for proper slope toward floor drain. Complete
Coordination Coordinate with other trades to avoid conflicts and ensure proper []
alignment and spacing. Complete
Winding up phase:
(After Construction:)
Warranty and Ensure all systems and materials come with warranties, catalog []
Handover handover manuals and schedules. Complete
This table can be used to track the progress and completion of essential tasks related to
building plumbing and sanitary services across different phases of construction.
Installation Checklist:
[]
5 Seal Joints Properly seal all joints to prevent leaks.
Complete
Testing Checklist:
Valve []
4 Test all valves for proper operation and sealing.
Operation Complete
Fixture []
5 Ensure all installed fixtures are functioning correctly.
Functionality Complete
[]
6 Leak Detection Check all connections and joints for signs of leaks.
Complete
[]
8 Leakage Test Test for leakage of water tank.
Complete
[]
9 Perimeter Drain Check water depth, velocity of perimeter drain.
Complete
Commissioning Checklist:
These checklists provide a detailed and structured approach to managing the installation,
testing, and commissioning phases of building plumbing and sanitary services, ensuring
thorough and systematic project management.
Acceptance Checklist for Installation of Plumbing and Sanitary Services
This standard acceptance checklist form ensures that all critical aspects of the installation of
plumbing and sanitary services are thoroughly inspected and verified before acceptance,
ensuring quality and compliance with design specifications.
1.4 Leak Detection Inspect all joints, connections, and fittings for leaks. [ ] Pass [ ] Fail
1.6 Testing of water tank Test for water tightness of structure. [ ] Pass [ ] Fail
2 Drainage System
2.5 Leak Detection Inspect all drainage pipes and connections for leaks. [ ] Pass [ ] Fail
No. Task Description Status Remarks
3 Fixture Functionality
Check that all sinks are securely installed, drain
3.1 Sinks [ ] Pass [ ] Fail
correctly, and faucets operate properly.
Test all toilets for proper flushing, refilling, and
3.2 Toilets [ ] Pass [ ] Fail
drainage.
Verify that all showers and bathtubs are draining
3.3 Showers and Bathtubs correctly and that showerheads function properly. [ ] Pass [ ] Fail
Check for flow toward floor drain.
Ensure water heaters are operating correctly, heating
3.4 Water Heaters [ ] Pass [ ] Fail
water to the desired temperature.
Test any installed pumps for proper operation and
3.5 Pumps (if applicable) [ ] Pass [ ] Fail
flow rates. Test for all automatic system.
4 Special Systems
Test irrigation systems for correct operation and
4.1 Irrigation Systems [ ] Pass [ ] Fail
coverage.
Water Treatment
Verify that water treatment plant and waste water
Plant and Waste
4.2 treatment plant systems are functioning properly and [ ] Pass [ ] Fail
Water Treatment
providing the desired quality.
Plant Systems
Check the structure is install at design location
(Horizontal and vertical).
Sewage treatment Check for water tightness of structure.
4.3 [ ] Pass [ ] Fail
system Check for proper function of equipment as per design.
Check for effluent quality which must be conform
with design specification.
5 General Inspection
Ensure all necessary documentation (manuals, []
5.1 Documentation
warranties, catalog etc.) is complete and available. Complete
Provide training on the operation and maintenance of
the plumbing and sanitary systems and firefighting []
5.2 User Training
drill, sewage treatment plant and waste water Complete
treatment plant operation and maintenance.
Inspector's Signature:
Date:
This standard form ensures that all functionality tests for plumbing and sanitary services are
thoroughly conducted and documented, verifying that each component of the system operates
correctly and meets design specifications.
Operation Test Standard Form for Plumbing and Sanitary Services
Project Information
Field Description
Project Name
Project Location
Inspection Date
Inspector Name
Inspector Contact
Water Supply
1
System
Main Water Supply Verify the main water supply valve operates
1.1 [ ] Pass [ ] Fail
Valve smoothly and seals properly.
Measure and record water pressure at various
1.2 Water Pressure [ ] Pass [ ] Fail
points; ensure it meets specifications.
Operate all water supply fixtures (faucets, showers,
1.3 Fixture Operation etc.) to ensure proper functionality, ensure it [ ] Pass [ ] Fail
produce design flow.
Inspect for leaks at all connections, joints, fixtures,
1.4 Leak Detection [ ] Pass [ ] Fail
water reservoir, equipment.
Test hot water availability and temperature at
1.5 Hot Water Supply [ ] Pass [ ] Fail
fixtures and check also quantity of flow.
2 Drainage System
Main Drainage Ensure main drainage system is clear and
2.1 [ ] Pass [ ] Fail
System functional, with no obstructions.
Test drainage flow at all fixtures to ensure efficient
2.2 Drain Flow [ ] Pass [ ] Fail
drainage without backups.
Check all traps for proper water seals to prevent
2.3 Trap Seals [ ] Pass [ ] Fail
sewer gas entry.
Verify that vent pipes are clear and functioning,
2.4 Vent System [ ] Pass [ ] Fail
allowing proper air circulation.
No. Task Description Status Remarks
5 General Inspection
Drain, []
5.1 Perimeter drain Check velocity, water depth of perimeter drain.
Complete
Inspector's Signature:
Date:
This operation test standard form ensures comprehensive testing and documentation of all
operational aspects of plumbing and sanitary services, verifying that each component
functions correctly and reliably.
Testing and Commissioning Standard Forms for Plumbing and Sanitary
Services
1. Testing Form
Project Information
Field Description
Project Name
Project Location
Test Date
Inspector Name
Inspector Contact
Testing Checklist
Water Supply
1
System
Perform pressure tests on water supply lines to check []
1.1 Pressure Test [ ] Fail
for leaks. Pass
Test water flow rates at various fixtures to ensure []
1.2 Flow Test [ ] Fail
adequate supply. Pass
Verify that all valves operate smoothly and seal []
1.3 Valve Functionality [ ] Fail
correctly. Pass
[]
1.4 Leak Detection Inspect all joints, connections, and fixtures for leaks. [ ] Fail
Pass
2 Drainage System
Ensure all drainage lines are free of obstructions and []
2.1 Drainage Flow Test [ ] Fail
flow properly. Pass
Verify that traps hold water and prevent sewer gas []
2.2 Trap Functionality [ ] Fail
entry. Pass
Test vent pipes to ensure proper air flow and prevent []
2.3 Ventilation System [ ] Fail
drainage issues. Pass
Test backflow prevention devices to ensure they are []
2.4 Backflow Prevention [ ] Fail
functioning correctly. Pass
3 Fixture Testing
[]
3.1 Sink Functionality Test all sinks for proper operation and drainage. [ ] Fail
Pass
Ensure all toilets flush properly, fill correctly, and do []
3.2 Toilet Functionality [ ] Fail
not leak. Pass
No. Task Description Status Remarks
2. Commissioning Form
Project Information
Field Description
Project Name
Project Location
Commissioning Date
Commissioning Engineer Name
Commissioning Engineer Contact
Commissioning Checklist
1 System Activation
Activate the plumbing system and verify all [] []
1.1 System Startup
components are operational. Complete Incomplete
Verify system pressure is within the acceptable [] []
1.2 Pressure Check
range. Complete Incomplete
Confirm that water flow rates are consistent [] []
1.3 Flow Check
with design specifications. Complete Incomplete
System
2
Functionality
No. Task Description Status Remarks
Signatures
Inspector
Commissioning Engineer
Project Manager
These forms provide a structured approach to documenting the testing and commissioning
processes for plumbing and sanitary systems, ensuring that all critical aspects are thoroughly
evaluated and verified.
HIGH - RISE AND PUBLIC BUILDING PROJECTS COMMITTEE (HPBC)
WATSAN CHECKLIST
RN Date
Project Name
Type of Location
Building
No. of Storey Company Name
The project was approved and recommended from HPBC.
After Structural skeleton work, Inspection team to be invited for the Finishing Stage of the project.
Check and compare with HPBC's recommended WATSAN Drawings.
Chapter 1. Design Phase
I. Source
No. Inspection Item Approved Installed Remarks
YCDC
(a) Distribution hours
1 (b) Flow
(c) Water pressure at the discharge point,
actual or currently tested result
Tube well
(a) Location of tube well
(b) Number of tube wells
(c) Diameter of tube wells
(d) Drilling depth of tube wells
(e) Yield of tube well /Safe yield
6
(d) Effluent quality