SL No 01
SL No 01
DISTRICT : COOCHBEHAR
BLOCK NAME : MEKHLIGANJ
ROAD NAME : Construction of Triple Cell Box
Culvert(4.0MX4.0M) At Ch.1845 M & CH.2280M
at Jamaldah pwd road to Dangerbari, under
Jamaldah GP within Mekhliganj Block, in the
district of Coochbehar
0 Km 4.9 Km
District: COOCHBEHAR
Block: Mekhliganj
Type of Work: Box Cell Culvert (3 Nos.x4.0mx4.0m)
Construction of Triple Cell Box Culvert(4.0MX4.0M) At
Ch.1845 M & CH.2280M at Jamaldah pwd road to
project name
Dangerbari, under Jamaldah GP within Mekhliganj
Block, in the district of Coochbehar
Work Chainage No. 1845M ,2280 M
Measurements
Sl No.
Brief Description of Item No. Unit Quantity Rate (Rs) Amount (Rs)
L (m) B (m) D (m)
the Engineer-in-charge
3.00
Measurements
Sl No.
Brief Description of Item No. Unit Quantity Rate (Rs) Amount (Rs)
L (m) B (m) D (m)
802, 803, 1202 & 1203 of Specification for Rural Roads (1st
Revision). using 250 kg cement, 0.48 cum coarse sand,
0.576 cum of 37.50mm stone aggregate, 0.288 cum 22.40
mm stone aggregate and 0.096 cum 11.20mm stone
aggregate and 4% for form work.
Brief Description of Item No. Unit Quantity Rate (Rs) Amount (Rs)
L (m) B (m) D (m)
Brief Description of Item No. Unit Quantity Rate (Rs) Amount (Rs)
L (m) B (m) D (m)
1106
300.1, 300.2 and IS 2720 Part VII including cost for proper
arrangement for stripping off the grass shods, weeds, quality
control, scarifying existing ground and original ground up to
the depth of 150 mm and rolling the existing ground as per
specification and direction of the Engineer-in-charge including
all taxes, royalties, cess, etc. incluiding cost of carriage by
head load/Truck, loading & Unloading when and where
necessary, lighting, guarding, and barricading, protecting etc.
complete.
ii) For embankment work with a lead up to 1000m at OMC to
meet 98% SPD
For Divertion Work:- 1 22.000 7.500 1.500 cum 247.500
Road Side Filling 2 20.000 7.000 3.000 cum 840.000
cum 1087.500 240.00 261,000.00
Reference to
MORD Spec.
Measurements
Sl No. Brief Description of Item No. Unit Quantity Rate (Rs) Amount (Rs)
L (m) B (m) D (m)
and stiching the gap with GI wires, closing both ends with GI
14.00
1000
Guard Post : Supply, fitting and fixing R.C. guard post 1.37
m. long with cement concrete 1:2:4 with graded stone chips
of 13.2 mm down (of approved quality) casting, curing
complete including cost of providing 4 Nos. of 12 mm dia MS
rods of length 1.54 m as main reinforcement and 6 Nos. of
round shaped 6 mm dia MS rods used as binders; the placing
of the 1st binder should be at 75 mm below the top finished
surface and the other 5 Nos. of binders should be placed at
245 mm C/C ; the guard post is of octagonal section with
inscribed circle of diameter 24 cm at the base tapering to
16.00
1600 1600
150 150
50 50 50 50
14.40
7.5
20.300
24.300
7.5
20.40
24.40
COST ESTIMATE FOR ALLIED WORKS
District COOCHBEHAR
BLOCK MEKHLIGANJ
project name Construction of Triple Cell Box Culvert(4.0MX4.0M) At Ch.1845 M & CH.2280M at
Jamaldah pwd road to Dangerbari, under Jamaldah GP within Mekhliganj Block,
in the district of Coochbehar
Measurements
Sl No.
Brief Description of Item No. Unit Quantity Rate (Rs) Amount (Rs)
L (m) B (m) D (m)
GSB-II materials
In Approach Road 2 30.00 3.750 0.075 cum 16.875
2 30.00 4.050 0.100 cum 24.300
Total = cum 41.175 1,348.45 55,522.43
18 Water Bound Macadam Sub-Base/Base (WBM Grading
II)
District COOCHBEHAR
BLOCK MEKHLIGANJ
project name Construction of Triple Cell Box Culvert(4.0MX4.0M) At Ch.1845 M & CH.2280M at
Jamaldah pwd road to Dangerbari, under Jamaldah GP within Mekhliganj Block,
in the district of Coochbehar
Measurements
Sl No.
Brief Description of Item No. Unit Quantity Rate (Rs) Amount (Rs)
L (m) B (m) D (m)
21
*Average lead (km) upto Project C.G considered in the analysis: At Site (Local) At Site (Local) At Site (Local)
Size of Aggregates
Item Unit Sand Sand
Unit (Coarse) (Medium)
Sand (Fine)
Size of Aggregates
aggregates (63-45
River bed Material
225mm to 150mm
Shingles 37.5mm
Stone Screening
Stone Screening
Bazree 22.4mm
Bazree 13.2mm
Bazree 11.2mm
aggregates (53-
Shingles 63mm
Grade-III Stone
above 225 mm
Grade-II Stone
Stone boulder
Stone boulder
Stone ballast
Stone ballast
Stone ballast
Stone ballast
Stone ballast
River 5.6mm
Stone chips
Stone chips
Stone chips
Stone chips
Stone Dust
River Grit
22.4 mm)
26.5mm
22.4mm
13.2mm
11.2mm
37.5mm
Type-A
Type-B
(RBM)
Item Unit
75mm
63mm
53mm
45mm
mm)
*Stone Materials at quarry (Table No: 02 & 04
Page 54 & 56 of WBSRDA Schedule of Rates cum 336.00 312.00 472.00 500.00 540.00 556.00 580.00 684.00 759.00 772.00 772.00 275.00 315.00 433.00 472.00 433.00 348.00 230.00 315.00 460.00 684.00 242.00 432.00 182.00
January 2019)
Carriage cost cum 859.00 859.00 859.00 859.00 859.00 859.00 859.00 859.00 859.00 859.00 859.00 739.00 739.00 739.00 739.00 739.00 739.00 739.00 739.00 739.00 739.00 859.00 859.00 859.00
Add Extra cost for void over loading, Unloading &
cum 157.42 157.42 78.71 78.71 78.71 78.71 78.71 78.71 78.71 78.71 78.71 68.71 68.71 68.71 68.71 68.71 68.71 68.71 68.71 68.71 68.71 134.93 78.71 78.71
Carriage
Rate at Site cum 1437.92 1413.92 1495.21 1523.21 1563.21 1579.21 1603.21 1707.21 1782.21 1795.21 1795.21 1168.21 1208.21 1326.21 1365.21 1326.21 1241.21 1123.21 1208.21 1353.21 1577.21 1321.43 1455.21 1205.21
District: coochbehar
BLOCK Mekhliganj
Project Name: Construction of Triple Cell Box Culvert(4.0MX4.0M) At Ch.1845 M & CH.2280M at Jamaldah pwd road to Dangerbari, under Jamaldah GP within Mekhliganj Block, in
the district of Coochbehar
Source-
Source of Material: Haldia Dhulagarh (on
NH-6)
Average lead (km) considered in the analysis: 760 669
Source-Haldia Source-Dhulagarh (on NH-6)
Bitumen Bitumen
Item Unit Bitumen Bulk Bitumen Cold Mix
Emulsion Emulsion
Grade VG-30 Emulsion Binder
Packed (RSI) Packed (MSI)
(60/70) [Haldia] Packed (SSI) Packed
Over head and Contractor's profit (@ 15% MT 40,803.15 38,525.00 40,825.00 41,975.00 43,125.00
25% less rate on the above loading and unloading items due to
stacking of the materials. (Page 4 of WBSRDA Schedule of MT 0.00 54.75 54.75 54.75 54.75
Rates January 2019)
Item Unit 300 dia NP3 450 dia NP3 600 dia NP3 1000 dia NP3 1200 dia NP3
Ex-outlet (incl. lap length) m 1,162.00 1,725.00 2,361.00 4,596.00 5,962.00
Deduct 25% less rate on loading of the material due to stacking (Page 5
2.75 2.75 2.75 6.50 6.50
of WBSRDA Schedule of Rates January 2019)
Deduct 25% less rate on loading of the material due to stacking (Page 5
20.00 20.00 20.00 32.00 32.00
of WBSRDA Schedule of Rates January 2019)
Carriage cost m 268.00 268.00 268.00 793.00 793.00
Rate at Site m 1,498.25 2,061.25 2,697.25 5,504.50 6,870.50
CARRIAGE OF PIPE:
Description (Carriage Cost of 300 mm / 450 mm / 600 mm dia pipe) Unit Distance (km) Rate (Rs) Amount (Rs) Remarks
a) Distance carried upto 5 km m 5.0 49.00 49.00
b) Distance carried exceeding 5 km but upto 10 km (per km) m 5.0 4.00 20.00
c) Distance carried exceeding 10 km but upto 20 km (per km) m 10.0 4.00 40.00 Sl No: 11 (a), Page 9
d) Distance carried exceeding 20 km but upto 50 km (per km) m 30.0 4.00 120.00 of WBSRDA Schedule
of Rates January 2019
e) Distance carried exceeding 50 km but upto 100 km (per km) m 13.0 3.00 39.00
f) Distance carried exceeding 100 km and upto any distance (per km) m 0.0 3.00 0.00
Total = m 63.0 268.00
Description Carriage Cost of 1000 mm / 1200 mm dia pipe) Unit Distance (km) Rate (Rs) Amount (Rs) Remarks
a) Distance carried upto 5 km m 5.0 148.00 148.00
b) Distance carried exceeding 5 km but upto 10 km (per km) m 5.0 13.00 65.00
c) Distance carried exceeding 10 km but upto 20 km (per km) m 10.0 12.00 120.00
Sl No: 11 (c), Page 9 of
d) Distance carried exceeding 20 km but upto 50 km (per km) m 30.0 11.00 330.00 WBSRDA Schedule of
Rates January 2019
e) Distance carried exceeding 50 km but upto 100 km (per km) m 13.0 10.00 130.00
WBSRDA Schedule of
Rates January 2019
f) Distance carried exceeding 100 km and upto any distance (per km) m 0.0 10.00 0.00
Total = m 63.0 793.00
0M at Jamaldah pwd road to Dangerbari, under Jamaldah GP within Mekhliganj Block, in the district of Coochbehar
TABLE 4: RATE ANALYSIS OF MATERIALS (STEEL) AT SITE
District: coochbehar
BLOCK Mekhligan
Project Name: Construction of Triple Cell Box Culvert(4.0MX4.0M) At Ch.1845 M & CH.2280M at Jamaldah pwd road to Dangerbari, under Jamaldah GP within
Mekhliganj Block, in the district of Coochbehar
Source of Material: Mekhliganj
Average lead (km) from Project CG 20
Over head and Contractor's profit (@ 15% MT 50,312.50 Over head and Contractor's profit (@ 15% MT 53,049.50
(ii) Unloading of Structural Steel, Steel Bars by manual means (ii) Unloading of Structural Steel, Steel Bars by manual means
MT 111 MT 111
including a lead upto 30 m including a lead upto 30 m
deduct 25% for no stacking MT 55.5 deduct 25% for no stacking MT 55.5
Cement Cement
Item Unit
(43 grade) (53 grade)
CARRIAGE OF CEMENT:
Amount
Description Unit Distance (km) Rate (Rs)
(Rs)
Remarks
(b) Distance carried exceeding 5 KM but not exceeding 10 KM for each additional 1 KM or part thereof. MT 5.0 7.00 35.00
(c) Distance carried exceeding 10 KM but not exceeding 20 KM for each additional 1 KM or part thereof. MT 2.0 7.00 14.00 Item No: 1(a), Page 7 of
WBSRDA Schedule of Rates
(d) Distance carried exceeding 20 KM but not exceeding 50 KM for each additional 1 KM or part thereof. MT 0.0 6.00 0.00 January 2019
(e) Distance carried exceeding 50 KM but not exceeding 100 KM for each additional 1 KM or part
MT 0.0 6.00 0.00
thereof.
(f) Distance carried exceeding 100 KM and upto any distance for each additional 1 KM or part thereof. MT 0.0 5.00 0.00
12 Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
2.5 (i) B
Unit Rate Item No. 2.5 (I) (B), Page 11 of WBSRDA Schedule of Rates January 2019
2
2.5 (i) C
Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
T&P and scaffolding wherever necessary, sorting the dismantled material, disposal
of unserviceable material and stacking the serviceable material with all lifts and lead
of 1000 m as per Technical Specification Clause 202 of Specifications for Rural
Roads.
(C) Reinforced Cement Concrete including cutting steel bars and seperating
and removing etc.
Unit = cum
Taking output = 1 cum (RCC)
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 1,113.00 1,113.00
profit @ 15.0%
Unit Rate Item No. 2.5 (I) (C), Page 11 of WBSRDA Schedule of Rates January
2019
42
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 266.00 266.00
profit @ 15.0%
Unit Rate Item No. 11.1, Page 41 of WBSRDA Schedule of Rates January 2019
802,
Sl
Reference
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
Construction wing will add cost of 250 kg cement, 0.48 cum coarse sand, 0.576 cum
of 37.50mm stone aggregate, 0.288 cum 22.40 mm stone aggregate and 0.096 cum
11.20mm stone aggregate and 4% for form work on materials cost for arriving
complete rate per cum
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 798.00 798.00
profit @ 15.0%
Unit Rate Item No. 11.4 I. (i), Page 41 of WBSRDA Schedule of Rates January 2019
(b) Materials
Cement kg 250.00 6.870 1,717.50
Coarse sand cum 0.480 809.00 388.32
37.5 mm (Shingles 37.5mm) cum 0.576 1,208.21 695.93
22.4 mm (Bazree 22.4mm) cum 0.288 1,326.21 381.95
11.2 mm (Bazree 11.2mm) cum 0.096 1,326.21 127.32
Add 4% for form work on material cost % 4.00 132.44
Providing and laying reinforced cement concrete in superstructure for height upto 5m
with coarse aggregates of appropriate nominal sizes and grading including
screening and cleaning, fine aggregate (sand) conforming to proper grading zone,
both of approved quality, cement and water reducing admixtures, as necessary and
mixing in concrete mixwe of suitable capacity and cost of curing with water, including
labour, including preparation of dsign mix approved of the same by the Engineer in
charge, cost for quality control, sampling, testing etc. including cost of form work and
staging upto 5m but excluding reinforcement complete as per drawings as per
drawing and technical specifications Clauses 800, 1401.4.1 and 1401.4.3 of
Specification for Rural Roads (1st Revision), MORD.
800, 1401.4.1 and 1401.4.3
For estimate purpose construction wing will add cost of 430 Kg cement, 0.45 cum.
Coarse sand, 0.54 cum 22.40 mm stone aggregate and 0.36 cum 11.20 mm stone
aggregate and add 20% for formwork and staging on cost of materials for height
13.1
upto 5 m. The work shall be executed as per actual quantity of materials from trial
and Mix Design at site / Laboratory to arrive at complete rate per cum.
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 968.00 968.00
profit @ 15.0%
Unit Rate Item No. 13.1 II. (i), Page 46 of WBSRDA Schedule of Rates January 2019
(b) Materials
Cement kg 400.00 6.870 2,748.00
Coarse sand cum 0.45 809.00 364.05
22.4 mm (stone aggregates) Stone Chips cum 0.54 1,782.21 962.39
11.2 mm (stone aggregates) Stone Chips cum 0.36 1,795.21 646.28
Add 20% for form work and staging on material cost % 20.00 944.14
Unit = t
Taking output = 1 t
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
MT 1.00 4,410.00 4,410.00
profit @ 15.0%
Unit Rate Item No. 13.2, Page 465of WBSRDA Schedule of Rates January 2019
(b) Materials
Steel (SAIL/TATA/RINL) MT 1.05 53,347.00 56,014.35
42
42
7
Construction wing wiil add cost of 275 kg cement, 0.48 cum coarse sand, 0.48 cum
37.50mm stone aggregate, 0.24 cum 22.40 mm stone aggregate and 0.08 cum
11.20 mm stone aggregate and add 4% for form work on materials cost for arriving
complete rate per cum
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 798.00 798.00
profit @ 15.0%
Unit Rate Item No. 11.4 II. (i), Page 41 of WBSRDA Schedule of Rates January 2019
(b) Materials
Cement kg 275.00 6.870 1,889.25
Coarse sand cum 0.480 809.00 388.32
37.5 mm (Shingles 37.5mm) cum 0.480 1,208.21 579.94
22.4 mm (Bazree 22.4mm) cum 0.240 1,326.21 318.29
11.2 mm (Bazree 11.2mm) cum 0.080 1,326.21 106.10
Add 4% for form work on material cost % 4.00 131.28
45
12.5 I (i)
Construction wing wiil add cost of 275 kg cement, 0.48 cum coarse sand, 0.48 cum
37.50mm stone aggregate, 0.24 cum 22.40 mm stone aggregate and 0.08 cum
11.20 mm stone aggregate followed by 10% cost on all materials per cum for form
work to arrive complete rate
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 844.00 844.00
profit @ 15.0%
Unit Rate Item No. 12.5 I. (i), Page 44 of WBSRDA Schedule of Rates January 2019
(b) Materials
Cement kg 275.00 6.870 1,889.25
Coarse sand cum 0.480 809.00 388.32
37.5 mm (Shingles 37.5mm) cum 0.480 1,208.21 579.94
22.4 mm (Bazree 22.4mm) cum 0.240 1,326.21 318.29
11.2 mm (Bazree 11.2mm) cum 0.080 1,326.21 106.10
Add 10% for form work on material cost % 10.00 328.19
9
Providing and laying cement concrete wearing course M 30 grade including
reinforcement shuttering and curing complete as per drawing and technical
specifications Clauses 800 and 1404.2 of Specification for Rural Roads (1st
Revision) and as per direction including cost and carriage of M.S. bar
Reinforcement.
Construction wing will add cost of 430 Kg cement, 0.45 cum. Coarse sand, 0.54 cum
22.40 mm stone aggregate and 0.36 cum 11.20mm stone aggregate and add 3% for
formwork and staging over cost of materials and 75 Kg of M.S. bar reinforcements to
arrive complete rate per cum.
Unit = cum
Taking output = 1 cum cum 1.00 807.00 807.00
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
profit @ 15.0%
Unit Rate Item No. 13.5, Page 45 of WBSRDA Schedule of Rates January 2019
Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
(b) Materials
Cement kg 430.00 6.870 2,954.10
Coarse sand cum 0.45 809.00 364.05
22.4 mm (stone chips) cum 0.54 1,782.21 962.39
11.2 mm (stone chips) cum 0.36 1,795.21 646.28
Add 3% for form work and staging on concrete cost % 3.00 267.84
M.S. Bar kg 75.00 53.347 4,001.03
Construction wing will add cost of medium sand at site @ 0.005 cum for cement
mortar for fixing of RCC pipes at site for arriving complete rate per metre.
1106
9.3
Unit = m
Taking output = 1 m
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
m 1.00 128.00 128.00
profit @ 15.0%
Unit Rate Item No. 9.3 B, Page 36 of WBSRDA Schedule of Rates January 2019
(b) Materials
Sand (Medium) cum 0.005 685.00 3.43
NP3 pipe (1000 mm dia) m 1.00 5,504.50 5,504.50
Sand filling in foundation trenches and at the back of abutment, wing walls etc. with
good local sand free from earth in layers not exceeding 150mm including inundating
each layer by profuse water and poking and ramming layer complete etc. as per
direction of Engineer in charge. I. Sand Filling
Construction wing will add cost of fine sand of 1.20 cum for arriving complete rate
per cum.
Unit = cum
Taking output = 1 cum cum 1.00 99.00 99.00
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
profit @ 15.0%
Unit Rate Item No. 11.2 I, Page 41 of WBSRDA Schedule of Rates January 2019
(b) Materials
Fine Sand cum 1.20 535.00 642.00
Rate per cum = 741.00
Construction of Embankment/Subgrade / Shoulder with materials obtained
14
12
3.4 (a), (b), (c ), (d)
(Payment will be made in cum on the finished work as per specifications on the
basis of the prework & postwork level section measurements. Royalty charges &
cess for earth @ 34.30 per cum work will be deducted under West Bengal Mines &
Mineral Acts).
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
profit @ 15.0%
Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
ii) For embankment work with a lead up to 1000m at OMC to meet 98% SPD cum 1.00 240.00 240.00
Unit Rate Item No. 3.4 (b), Page 13 of WBSRDA Schedule of Rates January 2019
49
13 Boulder Sausage
Proviing and placing of boulder apron laid in sausage wire crate of specified sizes
made of 4 mm dia GI wire net of 100mm x 100mm square mesh including required
lapping as directed of wire net, stiching with GI wire strongly, filling up the sausage
wire crate with approved stone / laterite boulders of minimum 40 Kg. each properly
@ 0.90 cum /cum and stiching the gap with GI wires, closing both ends with GI wire
net including lapping all sides as directed, including trimming and preparation of bed
by cutting or filling earth as required complete including cost of all materials and
labours and all incidential charges in this connection.
Constructing wing will add cost and carriage of 1.00 cum of stone with minimum size
of 200mm & 0.20 cum of stone spalls to obtain the complete rate per cum.
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 1255.00 1255.00
profit @ 15.0%
Unit Rate Item No 6, Page 49 of WBSRDA Schedule of Rates January 2019
(b) Materials
Boulder cum 1.00 1437.92 1437.92
stone spalls (37.5 mm Singles) cum 0.20 1208.21 241.64
1301
14 Boulder Apron
Proviing and placing of boulder apron laid in sausage wire crate of specified sizes
made of 4 mm dia GI wire net of 100mm x 100mm square mesh including required
lapping as directed of wire net, stiching with GI wire strongly, filling up the sausage
wire crate with approved stone / laterite boulders of minimum 40 Kg. each properly
@ 0.90 cum /cum and stiching the gap with GI wires, closing both ends with GI wire
net including lapping all sides as directed, including trimming and preparation of bed
by cutting or filling earth as required complete including cost of all materials and
labours and all incidential charges in this connection.
Constructing wing will add cost and carriage of 1.00 cum of stone with minimum size
of 200mm & 0.20 cum of stone spalls to obtain the complete rate per cum.
Unit = cum
Taking output = 1 cum cum 1.00 388.00 388.00
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
profit @ 15.0%
Unit Rate Item No. 14.1, Page 48 of WBSRDA Schedule of Rates January 2019
(b) Materials cum 1.00 1437.92 1437.92
Stone / Boulder (25kg minimum each) cum 0.20 1208.21 241.64
Stone spalls (37.5 mm singles)
12.9
614, 709
Weepholes
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete
abutment, wing wall, return wall with 100 mm dia PVC pipe extending through the
full width of the structures with slope of 1(V):20(H) towards outward face complete
as per drawing and technical specification Clauses 614, 709, 1206.3 of Specification
for Rural Roads (1st Revision) including curing complete.
Unit = Each
Taking output = 1 No. Each 1.00 190.00 190.00
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
profit @ 15.0%
Unit Rate Item No. 12.9, Page 44 of WBSRDA Schedule of Rates January 2019
Supply, fitting and fixing R.C. guard post 1.37 m. long with cement concrete 1:2:4
with graded stone chips of 13.2 mm down (of approved quality) casting, curing
complete including cost of providing 4 Nos. of 12 mm dia MS rods of length 1.54 m
as main reinforcement and 6 Nos. of round shaped 6 mm dia MS rods used as
binders; the placing of the 1st binder should be at 75 mm below the top finished
surface and the other 5 Nos. of binders should be placed at 245 mm C/C ; the guard
post is of octagonal section with inscribed circle of diameter 24 cm at the base
tapering to corresponding dimensions of 16 cm at the top including 2 coats of
painting with best quality synthetic enamel paint of approved make and brand to
form 6 Nos. horizontal alternate bands in white/tannery yellow and black to 90 cm.
New Item 2
Length standing up above ground after mending good damages if any during striking
270
the guard post in the same hole and repacking the earth thoroughly so as to keep
the guard post standing properly erect in correct position true to line and length
including carriage of R.C. guard post with due care to the site including loading into
the truck and unloading at site complete in all respect.
Unit = Each
Taking output = 1 No.
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
Each 1.00 698.00 698.00
profit @ 15.0%
Unit Rate Item No. 2, Page 40 of WBSRDA Schedule of Rates January 2019
17
4.1 (A) (ii)
(Location of density test as per page no. 256 of IRC-SP20.2002). For estimate
preparation, Construction wing will add cost and carriage (if allowable) of 1.20 Cum
(loose net volume) Well graded granular Sub-base materials for Grading I/II/III as
per Table No. 400.1 of Specifications for Rural Roads, MORD.
Unit Rate Item No. 4.1(A) (ii), Page 17 of WBSRDA Schedule of Rates January 2019
(b) Materials per cum
53 mm to 26.5 mm (rate of 37.5mm shingles) cum 0.360 1,208.21 434.96
26.5 mm to 4.75 mm (RBM) cum 0.420 1,123.21 471.75
4.75 mm below (av of coarse & medium sand) cum 0.420 747.00 313.74
18
4.7 2(A)
For estimate preparation,Construction wing will add cost and carriage of 1.21 cum of
Grading II aggregates (63mm size to 45mm size ) and 0.24 cum of Type B
Screening (5.6mm to 180 micron ) conforming to Table 400.9 of MoRD to arrive at
the complete rate( See table - 5 of this volume).
Unit = cum
Taking output = 1 cum
2(A) WBM Grading II, By Manual Means
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 351.00 351.00
profit @ 15.0%
Unit Rate Item No. 4.7 2(A), Page 17 of WBSRDA Schedule of Rates January 2019
(b) Materials per cum
North Bengal Variety, Grade-II (63 mm - 45mm) cum 1.210 1,353.21 1,637.38
Type B Screening cum 0.240 1,205.21 289.25
19
4.7 3 (A)
Providing, laying, spreading and compacting grading III stone aggregates of specific
sizes (53mm to 22.4mm) conforming to Table 400.8 of MORD for water bound
macadam including spreading in uniform thickness, hand packing, rolling with three
wheel 80-100 kN static roller in stages to proper grade and camber, applying
requisite type of screening/binding materials having Liquid limit (LL), Plasticity Index
(PI) and passing 75 micron less than 20, 6 and 10% respectively to fill-up the
interstices of coarse aggregate and brooming, watering and compacting to the
required density including cost of all materials including lighting, guarding,
barricading including cost for hire and operational charges of machinery, tools &
plants, including making necessary earthen bundh of one metre width on each side
to protect the edges and cost for quality control etc. complete as per technical
specification of clause 405 of Specification for Rural Roads, MORD.
For estimate preparation,Construction wing will add cost and carriage of 1.21 cum of
Grading III aggregates (53mm size to 22.4mm size ) and 0.24 cum of Type B
Screening (5.6mm to 180 micron ) conforming to Table 400.9 of MoRD to arrive at
the complete rate ( See table - 5 of this volume).
Note: 3mm thick layer of powdered lime should be spreaded as per direction of
Engineer - in - Charge in between two layers to facilitate checking of required
thickness of each layer and no additional cost for the same will be paid separetely
for this,
Unit = cum
Taking output = 1 cum
3(A) WBM Grading III, By Manual Means
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
cum 1.00 351.00 351.00
profit @ 15.0%
Unit Rate Item No. 4.7 3 (A), Page 18 of WBSRDA Schedule of Rates January 2019
(b) Materials per cum
North Bengal Variety, Grade-II (53 mm - 22.4mm) cum 1.210 1,577.21 1,908.42
Type B Screening cum 0.240 1,205.21 289.25
Providing and applying primer coat with bitumen emulsion (SS-1 grade) conforming
to IS:8887 on prepared surface of granular base (WBM/WMM) including cleaning of
road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical
means including cost and carriage of bitumen emulsion and all other incidental costs
of work complete as per Technical Specification Clause 502 of Specification for
Rural Roads (1st Revision), MORD
Construction wing will add cost and carriage of Bitumen Emulsion of approved
quality(grade) @ 0.85 kg/sqm to arrived at complete rate
Unit = sqm
Taking output = 1 sqm
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
Sqm 1.00 2.00 2.00
profit @ 15.0%
Unit Rate Item No. 5.1 (i) Page 24 of of WBSRDA Schedule of Rates January 2019
(b) Materials per sqm
Bitumen Emulsion (SS-1) @ 0.85 kg/sqm (avg.) kg 0.85 42.78 36.37
24
21
Providing and applying tack coat with Bitumen emulsion (RS-1 grade) conforming to
IS:8887 using emulsion distributor at the rate of 0.20 to 0.25 kg per sqm on the
prepared bituminous surface cleaned with Hydraulic broom including cost and
carriage of bitumen emulsion and all other incidental costs of work complete as per
Technical Specification Clause 503 of Specification for Rural Roads (1st Revision).
Construction wing will add cost and carriage of Bitumen Emulsion of approved grade
(quality) @ 0.225 kg/sqm to arrived at complete rate
Unit = Sqm
Taking output = 1 Sqm
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
Sqm 1.00 2.00 2.00
profit @ 15.0%
Unit Rate Item No. 5.2 (i) Page 24 of of WBSRDA Schedule of Rates January 2019
25
Unit = Sqm
Taking output = 1 Sqm
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
Sqm 1.00 42.00 42.00
profit @ 15.0%
Unit Rate New Item No. 5.9, Page 25 of WBSRDA Schedule of Rates January 2019
(b) Materials per sqm
Bitumen(VG-30 grade) kg 1.460 44.76 65.35
13.2 mm size @ 0.018 cum/sqm (Bazree) cum 0.018 1,365.21 24.57
11.2 mm size @ 0.009 cum/sqm (Bazree) cum 0.009 1,326.21 11.94
23
5.12 B (II)
Construction wing will add cost and carriage of Bitumen (VG-30) @ 0.68 Kg per sqm
and sand / grit (passing through 2.36mm sieve and retained on 180 micron sieve) @
0.006cum/sqm to arrive at complete rate
A. By Manual Means
Case - II : Type B
(II) Bitumen (Grade - VG-30)
Unit = sqm
Taking output = 1 sqm
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
Sqm 1.00 11.00 11.00
profit @ 15.0%
Unit Rate Item No. 5.12 B (II) Page 26 of WBSRDA Schedule of Rates 2019
(b) Materials per sqm
26
23
5.12 B (II)
Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
1701
Providing and fixing of typical PMGSY informatory sign board with Logo as per
MORD specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle
plate duly welded with MS flat 25mm x 5mm size on back on edges. The lower plate
will be welded with MS angle iron frame of 25mm x 25mm x 5mm. The angle iron
frame of the lower most plate and flat iron frame of middle plate will be welded to 2
nos. 75mm x 75mm of 12 SWG sheet tubes posts duly embedded in cement
concrete M-15 grade blocks of 450mm x 450mm x 600mm, 600mm below ground
level. The top most diamond plate will be welded to middle plate by 47mm x 47mm
of 12 SWG steel plate tube. All M.S. will be stove enameled on both sides. Lettering
and printing arrows, border etc. will be painted with ready mixed synthetic enamel
paint of superior quality in required shade and colour. All sections of framed posts
and steel tube will be painted with primer and two coats of epoxy paint as per
drawing Clause 1701 and Annexure 1700.1
Construction wing will add cost of 0.252 cum M-15 Cement Concrete
Unit = Each
Taking output = 1 No.
(a) Base rate including Labour, Tools & Plants, Machinery, overhead & contractor's
Each 1.00 9,321.00 9,321.00
profit @ 15.0%
Unit Rate Item No. 10.16, Page 39 of WBSRDA Schedule of Rates January 2019
(b) Materials
M15 Grade cement concrete (Ref. sub-analysis) cum 0.252 4,211.18 1,061.22
40 Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
1
10.18
Rumble Strip
Providing Rumble Strip covered with premixed bituminous carpet
20mm high at centre followed by Type B Seal Coat 250 mm wide
each and placed 1 m centre to centre at approved location to
control speed, marked with 30 cms. Wide white strips of Road
marking paint placed 60 cms. centre to centre along the alignment.
25
Unit = Sqm
Taking output = 1 Sqm
(a) Base rate including Labour, Tools & Plants, Machinery,
Sqm 1.00 42.00 42.00
overhead & contractor's profit @ 15.0%
Unit Rate New Item No. 5.9, Page 24 of WBSRDA Schedule of
Rates January 2019
(b) Materials per sqm
Bitumen(VG-30 grade) kg 1.460 44.76 65.35
13.2 mm size @ 0.018 cum/sqm (Bazree) cum 0.018 1,365.21 24.57
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
RATE ANALYSIS: ALLIED WORKS
District: coochbehar
Road Name: Construction of Triple Cell Box Culvert(4.0MX4.0M) At Ch.1845 M & CH.2280M at Jamaldah pwd road to Dangerb
Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing and
Clause 801 of Specifications for Road & Bridge Works
of MoRT&H (5th Revision).
Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing and
Clause 801 of Specifications for Road & Bridge Works
of MoRT&H (5th Revision).
cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing and
Clause 801 of Specifications for Road & Bridge Works
of MoRT&H (5th Revision).
WD Schedule 30.08.2018
Reference to SOR
as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
8.09
7
41 Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
The rate of each Board is inclusive of M.S square, M.S flats, M.S plates,
all labour, fabricating and welding charges, cost of paintings and primer,
cost of carriage & fixing and all other incidental charges in this regard
complete in all respect maintaining line and level as directed by the
Engineer-in-Charge including cost of protection, barricading and lighting
etc.
Sub Analysis M15 concrete
Base rate including Labour, Tools & Plants, Machinery, overhead &
cum 1.00 798.00 798.00
contractor's profit @ 15.0%
Cement kg 275.00 6.870 1,889.25
37.5 mm (Shingles 37.5mm) cum 0.480 1,208.21 579.94
22.4 mm (Bazree 22.4mm) cum 0.240 1,326.21 318.29
11.2 mm (Bazree 11.2mm) cum 0.080 1,326.21 106.10
Coarse Sand cum 0.480 809.00 388.32
Form work % 4.00 131.28
Item No. 11.4, II. (i) Page 42 of WBSRDA Schedule of Rates January
2019
Cost of 1 cum M15 (Nominal Mix 1:2.5:5) grade concrete = 4,211.18
41
Item 3 (ii)
(i) Logo Board at starting point (as per fig. 107 of Road signage
under PMGSY Published by the NRRDA on Dec. '06.)
Unit = Each
Taking output = 1 No.
(a) Base rate including Labour, Tools & Plants, Machinery, overhead &
Each 1.00 6,988.00 6,988.00
contractor's profit @ 15.0%
Unit Rate Item No. 3, Page 40 of WBSRDA Schedule of Rates January
2019
(b) Materials
M15 Grade cement concrete (Ref. sub-analysis) cum 0.122 4,211.18 513.76
Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
3
New Item 1
The rate of each Board is inclusive of M.S square, M.S flats, M.S plates,
cost of M-15 Cement Concrete, all labour and welding charges, cost of all
paintings and primer, Cost of Carriage & fixing and all other incidental
41
charges in this regard to complete in all respect maintaining line and level
as directed by the Engineer-in-Charge including cost of protection,
barricading, lighting etc.
The rate of each Board is inclusive of M.S square, M.S flats, M.S plates,
cost of M-15 Cement Concrete, all labour and welding charges, cost of all
paintings and primer, Cost of Carriage & fixing and all other incidental
charges in this regard to complete in all respect maintaining line and level
as directed by the Engineer-in-Charge including cost of protection,
barricading, lighting etc.
Construction wing will add cost of 0.54 cum M -15 cement concrete for
arriving at complete rate of each Board.
Unit = Each
Taking output = 1 No.
(a) Base rate including Labour, Tools & Plants, Machinery, overhead &
Each 1.00 10,346.00 10,346.00
contractor's profit @ 15.0%
Unit RateNew Item No. 1, Page 39 of WBSRDA Schedule of Rates
January 2019
(b) Materials
M15 Grade cement concrete (Ref. sub-analysis) cum 0.540 4,211.18 2,274.04
Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
4 The rate of each Board is inclusive of M.S square, M.S flats, M.S plates,
cost of M-15 Cement Concrete, all labour and welding charges, cost of all
paintings and primer, Cost of Carriage & fixing and all other incidental
charges in this regard to complete in all respect maintaining line and level
as directed by the Engineer-in-Charge including cost of protection,
barricading, lighting etc.
Construction wing will add cost of 0.54 cum M -15 cement concrete for
arriving at complete rate of each Board.
Unit = Each
Taking output = 1 No.
(a) Base rate including Labour, Tools & Plants, Machinery, overhead &
Each 1.00 11,138.00 11,138.00
contractor's profit @ 15.0%
Unit RateNew Item No. 4, Page 40 of WBSRDA Schedule of Rates
January 2019
(b) Materials
M15 Grade cement concrete (Ref. sub-analysis) cum 0.540 4,211.18 2,274.04
Unit = Each
5
39
Reference to SOR
Ref. as per SOR
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
Kilometre Stone
Reinforced cement concrete M15 grade kilometre stone/local stone of
standard design as per IRC:8 fixing in position including painting and
printing, etc as per drawing and Technical Specification Clause 1703 of
Specification for Rural Roads.
Construction wing will add cost of 0.269 cum M-15 Cement Concrete
and 1.88 Kg of Steel reinforcement
(ii) Ordinary Kilometer Stone (Precast)
Unit = Each
6
3
Reference to
Sl
SOR
1
9.3. E
36
1106
Reference to
Sl
SOR
3
Providing and Laying Reinforced Cement Concrete Pipe
NP3 with spigot socket as per design in Single Row :
Providing and laying reinforced cement concrete pipe NP3
with spigot socket for culverts on first class bedding of granular
material in single row including filling with cement mortar 1:2
but excluding excavation, protection works, backfilling and
masonry work in head walls and parapets including pumping
out water, lighting, barricading, protecting etc. complete as per
Clause 1101.6 of Specification for Rural Roads, MORD. A.
1200 mm Dia
5
Providing and Laying Reinforced Cement Concrete Pipe
NP3 with spigot socket as per Design in Double Row :
Providing and laying reinforced cement concrete pipe NP3
with spigot socket for culverts in double row including joining
pipes with cement mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and masonry works in
head walls and parapets including pumping out water, lighting,
barricading, protecting etc. complete as per Clause 1101.6 of
Specification for Rural Roads, MORD. A. 1200 mm Dia
pipes with spigot socket at site for arriving complete rate per
metre.
Unit = m
Taking output = 1 m
(a) Base rate including Labour, Tools & Plants, Machinery,
m 1.00 506.00 506.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 9.5 A, Page 36 of WBSRDA Schedule of
Rates January 2019
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
RATE ANALYSIS: Conduit
District: coochbehar
Package: Err:509
1106
9.5
Road Name:
Ref. as per SOR Construction of Triple Cell Box Culvert(4.0MX4.0M) At Ch.1845 M & CH.2280M at Jamaldah pwd road to Dangerb
Reference to
Sl
SOR
(b) Materials
Sand (Medium) cum 0.015 685.00 10.28
NP3 pipe (1200 mm dia) m 1.00 6,870.50 6,870.50
1106
pipes with spigot socket at site for arriving complete rate per
6
metre.
Unit = m
Taking output = 1 m
(a) Base rate including Labour, Tools & Plants, Machinery,
m 1.00 298.00 298.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 9.5 B, Page 37 of WBSRDA Schedule of
Rates January 2019
(b) Materials
Sand (Medium) cum 0.011 685.00 7.54
NP3 pipe (1000 mm dia) m 1.00 5,504.50 5,504.50
Reference to
Sl
SOR
9.1
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery,
cum 1.00 266.00 266.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 9.1, Page 34 of WBSRDA Schedule of
Rates January 2019
1109
Reference to
Sl
SOR
4
Laying concrete cradle bedding with M15 Grade Cement
Concrete on a firm foundation of uniform density throughout
the length of the culvert and shall conform to the specified
levels and grade including hire and operational charges for
machinery and tools & plants etc. complete as per Clause
1101.5 (i) of Specification for Rural Roads, MORD. The pipe
shall be laid in accordance with the requirements of IS:783 on
concrete bedding before the concrete has set.
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery,
cum 1.00 798.00 798.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 9.2 (i), Page 34 of WBSRDA Schedule of
Rates January 2019
(b) Materials
Cement kg 275.00 6.870 1,889.25
Coarse sand cum 0.480 809.00 388.32
37.5 mm (Shingles 37.5mm) cum 0.576 1,208.21 695.93
22.4 mm (Bazree 22.4mm) cum 0.288 1,326.21 381.95
11.2 mm (Bazree 11.2mm) cum 0.096 1,326.21 127.32
Add 4% for form work on material cost % 4.00 139.31
Reference to
Sl
SOR
Construction will add cost of i) 9.12 kg. of cement ii) 0.025 cum
1206
12.3
7
Reference to
Sl
SOR
7
11.2
Reference to
Sl
SOR
8
14.1
1301
Boulder Apron
Providing and laying boulder apron for bed protection with
stone boulders of minimum size and weight as per Table
1300.1, no fragment weighing less than 25 kg laid dry
complete as per
Construction wingdrawing
will addand technical
cost specifications
of 1.00 cum Clause
boulders (25 Kg
each minimum) and 0.20 cum stone spalls to arrive complete
rate.
Unit = cum
Taking output = 1 cum cum 1.00 388.00 388.00
(a) Base rate including Labour, Tools & Plants, Machinery,
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 14.1, Page 48 of WBSRDA Schedule of
Rates January 2019
(b) Materials cum 1.00 1437.92 1437.92
Stone / Boulder (25kg minimum each) cum 0.20 1208.21 241.64
Stone spalls (37.5 mm singles)
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery,
cum 1.00 798.00 798.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 11.4 I. (i), Page 41 of WBSRDA Schedule
of Rates January 2019
(b) Materials
Cement kg 250.00 6.870 1,717.50
Coarse sand cum 0.480 809.00 388.32
37.5 mm (Shingles 37.5mm) cum 0.576 1,208.21 695.93
22.4 mm (Bazree 22.4mm) cum 0.288 1,326.21 381.95
11.2 mm (Bazree 11.2mm) cum 0.096 1,326.21 127.32
Add 4% for form work on material cost % 4.00 132.44
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
Reference to
Sl
SOR
1
14.5
1302
Filter Material
Providing and laying filter materials undermeath pitching in
slopes complete as per drawing and technical specification.
Unit = cum
Taking output = 1 cum cum 1.00 730.00 730.00
(a) Base rate including Labour, T & P, Machinery, overhead &
contractor's profit @ 12.5%
Unit rate item No. 15.04 Page 317 of PW(R) 2018
(b) Materials
RBM cum 0.72 1123.21 808.71
Coarse sand cum 0.48 809.00 388.32
1302
Pitching on Slopes
Providing and laying pitching on slopes layed over prepared
filter media as per drawing and technical specification clause
1302 of specification of MORD
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
1
15.1
1903
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
4
502, 503 & 504
1904
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
6
Maintenance of Bituminous surface Road (Maintenance of
Non-Bituminous Base and Sub Base or WBM Road)
Patching of potholes by
draining water,cutting the pothole area to rectangular shape with
vertical edges,removing all loose materials,screening and
stacking the same for reuse with new materials as per
requirement,filling the pothole area with additional volume of
crushed stone materials/laterite/Jhama/broken shingles/coated
stones of Pakur variety etc. and screenings as applicable,and
compacting the same with static roller as per Water Bound
Macadam as per drawings and Technical Specification 1907 of
MoRD (1st Rivision),including cost of all materials and
machineries.
Unit = cum
Taking output = 1 cum
(a) Base rate including Labour, Tools & Plants, Machinery,
cum 1.00 509.00 509.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 15.3, (iii), Page 46 of WBSRDA Schedule of
Rates January 2019
(b) Materials
Grade-III Stone aggregates kg 2.34 1,577.21 3,690.67
Stone Screening Type-B cum 0.027 1,205.21 32.54
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
Unit = km
10
Taking output = 1 km
(a) Base rate including Labour, Tools & Plants, Machinery,
km 1.00 1,407.00 1,407.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 15.9, Page 52 of WBSRDA Schedule of Rates
January 2019
52
Unit = km
Taking output = 1 km
(a) Base rate including Labour, Tools & Plants, Machinery,
km 1.00 737.00 737.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 15.11, Page 52 of WBSRDA Schedule of
Rates January 2019
Sl
Description Unit Quantity Rate (Rs) Amount (Rs)
No.
12
15.12
(i) Cutting of branches of trees and shrubs from the road way or
with in R.O.W including disposal of wood and leaves to suitable
location as per technical specification Clause 1915 of
Specification for Rural Roads.
Unit = per tree
Taking output = 1 tree
(a) Base rate including Labour, Tools & Plants, Machinery, Each
1.00 106.00 106.00
overhead & contractor's profit @ 15.0% tree
Unit Rate Item No. 15.12, (i) Page 53 of WBSRDA Schedule of
Rates January 2019
1915
1914
53
(Extra quantity of earth for filling shall be obtained from road side
borrow pits.)
Unit = per tree
Taking output = 1 tree
(a) Base rate including Labour, Tools & Plants, Machinery,
sqm 1.00 12.00 12.00
overhead & contractor's profit @ 15.0%
Unit Rate Item No. 1, Page 53 of WBSRDA Schedule of Rates
January 2019