BoQ - Hafir Construction - Final
BoQ - Hafir Construction - Final
SUDAN OFFICE
                     Tender Reference:XXXXXXXXX
 Construction of Roofed Water Catchment and Associated Structures in East
                                 Dafur
NOTE: It is a MANDATORY requirement for bidders to complete and return both this excel BOQs and their
                          respective duly signed pdf for Authentication
Failure to complete all sections of the BOQ may result to automatic disqualification of your bid.
2    The Bills of Quantities (BoQs) for the Works comprise the following:
     Preamble to Bill of Quantities
     List of principal Quantities
     Grand Summary
     * Bill of Quantity (BoQ) Nr.1 - Construction of Roofed Water Catchment and Associated
3    Structures
     The           in East
          Contractor’s  unitDafur
                             rates in these bills are to cover supplying of materials, taking delivery, transporting, loading
     and off loading inspection, storage, stacking, landing, preparation, installation including provision of all labor,
     requirement false work, temporary support, surface preparation and testing of the works. The rates shall include
     all applicable taxes and duty. The cost of testing of the materials to be used in the works unless otherwise
     provided is to be included in the rates of the respective Bill items.
4 Measurement for payment shall be for the complete installation and having passed all necessary tests.
5    Work shall not be executed on a Day Work Basis unless ordered in writing by the Consultant on approval by the
     Employer. The rates entered in the Day works Bill of Quantities (BoQs) shall apply to any quantity of Day Work
     instructed by the Consultant. Nominal quantities have been indicated against each item to permit the extended
     total to be carried forward to the Grand Summary.
6 “Rates and prices shall be inserted in the rate and total columns of the Bill of Quantities (BoQs) in US$
7    Bills of Quantities (BoQs) are to be read in conjunction with the Instructions to Bidders, the Conditions of Contract
     Data, the Specifications and the Drawings. The quantities stated against each item in the Bills of Quantities
     (BoQs), with the exception of those items specifically marked ‘SUM’, are the estimated quantities of the Work to
     be executed by the Contractor in fulfillment of his/her obligations under the Contract.
8    The Contractor is required to check the number of the pages and should any be found to be missing or in
     duplicate he must inform the Engineer at once and have the same rectified.
9    No liability whatever will be admitted or claim allowed in respect of errors in the Contractor’s tender due to
     mistakes in the Bills of Quantities (BoQs) which should have been rectified in the manner described above.
10   The contractor shall not alter or otherwise qualify the text of these Bills of Quantities (BoQs). Any alteration or
     qualification made without authority will be ignored and the text of the Bills of Quantities (BoQs) as printed will be
     adhered to.
11   Each item in the Bills of Quantities (BoQs) is to be priced. If any items are left un-priced it will be assumed that
     the value of the work described there under is elsewhere allowed for. The prices and rates to be inserted in the
     Bills of Quantities (BoQs) are to be fully inclusive of all costs and expenses which may be required for the
     construction of the work described, together with general risks, liabilities and obligations set forth or implied in
     these documents.
12   In no case will any claim for expenses incurred by the Contractor in preparation of this Tender be allowed.
13     The Contractor is solely responsible for the accurate ordering of materials in accordance with the Specifications,
       Drawings and Engineer’s Instructions and no claim for any loss or expense will be entertained for orders for
       materials based on the Bills of Quantities (BoQs).
14     The quantities given in the Bills of Quantities (BoQs) are estimated and no claim by the Contractor for the final
       quantities being larger or smaller than the quantities given in the Bills of Quantities (BoQs) will be permitted
       except in accordance with Clause 38 of the Conditions of Contract.
15     The dimensions given in the Drawings are generally in millimeters unless otherwise indicated. Levels are given in
       meters.
16     The term ‘provide’ or ‘supply’ used for any item shall be deemed to include transport to site, handling, storage
       and fixing complete, and the Bidder’s rate shall include for this.
17      The following abbreviations might have been used in the Bills of Quantities (BoQ) and shall be interpreted as:
        kg                                                           kilogram
        t                                                            tonne
        m                                                            meter
        m2                                                           square meter
        m3                                                           cubic meter
        mm                                                           millimeter
        Nr.                                                          Number
        USD                                                          United States Dollar
        uPVC                                                         un-plasticized poly vinyl chloride
        HDPE                                                         high density polyethylene
        GMS                                                          galvanized mild steel
        LS                                                           Lump Sum
        PS                                                           Provisional Sum
        General Items
     18 Unless otherwise provided there are no separate measurement items for Contractual requirements. The
        Contractor is deemed to have included his costs for the Contractual requirement
                        ALIGHT (Formerly American Refugee Committee): SUDAN Office
                                        BILL 1: ROOFED CATCHMENT
                                        (hafir) (Dwg Nos. AG_RC/1/4-4/4)
                 Construction of Roofed Water Catchment and Associated Structures in East Dafur
                                                   Bidder Legal Name: [insert here]
Item                                                                                          Unit/P in
 No. Description of work                                                        Unit   Qty      USD
      NB. This is a full contract BOQ where bidder has to factor in costs for purchasing material,equipment,transport to
      site, construction/fixing them,labor and Government taxes where applicable.Decsription has to be read together
      with drawings and specifications which are provided together with this BOQ
      A list of typical general items are given below. However, the                    Note
      Bidder is requested to price only those items that may affect this
      Contract.
      The Bidder is advised to visit the site of the proposed work, as it is           Note
      his responsibility to ascertain the conditions governing access to
      the site, and external working space, storage area etc.
      The Bidder is advised to visit the site of the proposed work, as it is           Note
      his responsibility to ascertain the conditions governing access to
      the site, and external working space, storage area etc.
      If no price has been stated against any item hereunder, the                      Note
      Contractor shall not be entitled to claim any money for such items
      even though he is obliged to execute the work or provide services
      described therein. Preliminary items priced by the Tenderer are
      deemed to include the cost of unpriced items.
      The Bidder is advised to refer to the General Notes, Pricing                     Note
      Preambles, Drawings, Specifications, Conditions of Contract,
      Particular Conditions of Contract and other relevant documents
      prior to pricing of the following items.
      The bidder is required to visit the site of the proposed work, as it is          Note
      his responsibility to ascertain the conditions governing access to the
      site, the external working space, storage area and any other
      information he may find necessary before he can tender for the
      work.
      Cost and expenses in connection with any other preliminary item                  Note
      which is not listed below, but is necessary for the due completion
      of works, is deemed to be included in the tender rates.
      Mechanical plant and equipment which emits excessive noise,                      Note
      smoke, fumes, obnoxious gases etc., will not be allowed to be used
      in the Site, without the prior approval of the Engineer.
      The contractor shall be responsible for any loss or damage to the                Note
      works, existing structures, adjoining structures and unfixed
      materials.
      The contractor shall try to locate the new units in a way to avoid               Note
      cutting trees. If it is really needed to cut down any number of trees,
      allow for planting same number of trees – Contractor has to take
      care about watering and maintenance of plants for about 3 months
      or until completion of the contract. (Fill schedule of late)
      EARTH WORKS (PROVISIONAL)
      Excavation of Hafir, 50m long and 10m wide at the top, with flanks
1.1   sloping 60° (58%) to the vertical, the bottom should be at 5m
      below ground level (bgl) at the inlet and 5.50m (bgl) at the
      outflow, consequently will result to the mean slope of 5% and
      arrangement of soil to form two steep dykes on both long sides.      m3   1,383
1.2   Excavation of exiting Hafir, 50m long and 25m wide by 1m average
      depth 5-10m far from the above mentioned Hafir, cut and arrage
      45% angle at each side of the hafir.                                 m3   1,363
      Excavation of Hafir inlet and the trench for the pipeline to
1.3   evacuate the overflow until the nearest watercourse, inlet
      structure 12.50 x 3.80 x 1.0m, trench 294m x 1.2m and
      arrangement of soil locally.                                            m3    400
      Excavation of trenches for foundations of the walls locate at the
1.4   origin and at the end of Hafir, 3x1.5x11m and arrangement of soil
      to form two steeply dykes in both long sides of the Hafir.              m3     99
      Excavation of trenches for foundations of steel structure of Hafir,
1.5   1.0 x 1.0 x 51m and arrangement of soil to form two steep dykes
      on both long sides of the Hafir.                                        m3    102
      Supply materials and build the walls at the extremities of the hafir,
1.9   0.50 m thick, externally shaped like the tunnel, and founded at
      3.5m bgl, masonry made, as per the attached drawings. The wall at
      the end of the hafir will have an access door to the hafir measuring
      0.90 x 2.0m.                                                            m3     32
      Supply and install the access door to the hafir, 0.90 x 2m, made
`1.10 with 1mm steel plate electrically welded on a frame of 50 x 50mm
      "L" sections, with 2No hinges firmly fixed to the wall and hooks for
      pad lock.                                                              No   1
1.11 Construct the hafir inlet and washout as illustrated in the attached
     drawings                                                             Item    1
     Supply and install the pipeline draining muddy water collected in
1.12 the hafir inlet structure toward the washout pipeline. The pipeline
     to made with Ø 110 mm U-PVC SN4-SDR 41 pipe.                            M    12
      SUB-TOTAL PAGE 2 CARRIED TO
      COLLECTION
1.13 Supply and install the washout pipeline. The pipeline to be made
     with Ø 400 mm U-PVC SN2-SDR 51 pipe.                                    M      150
     Supply and install 0.70 x 5.60m ladder, made with 2No. Ø40 x
     2.0mm x 5.60m pipes and 25No. Ø24 x 2mm pipes both
     made with AISI 304 stainless steel, electrically welded with
1.17 electrodes with C< 5%. The ladder should be firmly fixed at the top
     to the wall with SS steel dowels. At the base and in three points
     sparsely distributed along the length the ladder will be supported
     by a soft footers made with smoothed stainless steel plate and
     binded with polypropylene sheet, 1cm thick as per the attached
     drawings                                                            Item            1
      SUB-TOTAL PAGE 3 CARRIED TO
      COLLECTION
      COLLECTION
      COLLECTION FROM PAGE 1
      COLLECTION FROM PAGE 2
      COLLECTION FROM PAGE 3
East Dafur
                 Total in
                   USD
aterial,equipment,transport to
ption has to be read together
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
                  ALIGHT (Formerly American Refugee Committee): SUDAN Office
                                  BILL 2: ROOFED CATCHMENT
                                  (hafir) (Dwg Nos. AG_RC/1/4-4/4)
           Construction of Roofed Water Catchment and Associated Structures in East Dafur
                                                   Bidder Legal Name: [insert here]
Item                                                                                          Unit/P in   Total in
 No. Description of work                                                        Unit   Qty      USD         USD
      NB. This is a full contract BOQ where bidder has to factor in costs for purchasing
      material,equipment,transport to site, construction/fixing them,labor and Government taxes where
      applicable.Decsription has to be read together with drawings and specifications which are provided
      together with this BOQ
BILL 2 WATER DISTRIBUTION INFRUSTRUCRE
      A list of typical general items are given below. However, the                    Note
      Bidder is requested to price only those items that may affect this
      Contract.
      The Bidder is advised to visit the site of the proposed work, as it is           Note
      his responsibility to ascertain the conditions governing access to
      the site, and external working space, storage area etc.
      The Bidder is advised to visit the site of the proposed work, as it is           Note
      his responsibility to ascertain the conditions governing access to
      the site, and external working space, storage area etc.
      If no price has been stated against any item hereunder, the                      Note
      Contractor shall not be entitled to claim any money for such items
      even though he is obliged to execute the work or provide services
      described therein. Preliminary items priced by the Tenderer are
      deemed to include the cost of unpriced items.
      The Bidder is advised to refer to the General Notes, Pricing                     Note
      Preambles, Drawings, Specifications, Conditions of Contract,
      Particular Conditions of Contract and other relevant documents
      prior to pricing of the following items.
      The bidder is required to visit the site of the proposed work, as it is          Note
      his responsibility to ascertain the conditions governing access to the
      site, the external working space, storage area and any other
      information he may find necessary before he can tender for the
      work.
      Cost and expenses in connection with any other preliminary item                  Note
      which is not listed below, but is necessary for the due completion
      of works, is deemed to be included in the tender rates.
      Mechanical plant and equipment which emits excessive noise,                      Note
      smoke, fumes, obnoxious gases etc., will not be allowed to be used
      in the Site, without the prior approval of the Engineer.
      The contractor shall be responsible for any loss or damage to the                Note
      works, existing structures, adjoining structures and unfixed
      materials.
      The contractor shall try to locate the new units in a way to avoid               Note
      cutting trees. If it is really needed to cut down any number of trees,
      allow for planting same number of trees – Contractor has to take
      care about watering and maintenance of plants for about 3 months
      or until completion of the contract. (Fill schedule of late)
       NB. This is a full contract BOQ where bidder has to factor in costs for purchasing material,equipment,transport to s
       construction/fixing them,labor and Government taxes where applicable.Decsription has to be read together with dr
       specifications which are provided together with this BOQ
       The Bidder is advised to refer to the General Notes, Pricing Preambles,                 Note
       Drawings, Specifications, Conditions of Contract, Particular Conditions of
       Contract and other relevant documents prior to pricing of the following items.
       The bidder is required to visit the site of the proposed work, as it is his             Note
       responsibility to ascertain the conditions governing access to the site, the
       external working space, storage area and any other information he may find
       necessary before he can tender for the work.
       Cost and expenses in connection with any other preliminary item which is not            Note
       listed below, but is necessary for the due completion of works, is deemed to
       be included in the tender rates.
       Mechanical plant and equipment which emits excessive noise, smoke, fumes,               Note
       obnoxious gases etc., will not be allowed to be used in the Site, without the
       prior approval of the Engineer.
       The contractor shall be responsible for any loss or damage to the works,                Note
       existing structures, adjoining structures and unfixed materials.
        The contractor shall try to locate the new units in a way to avoid cutting trees.         Note
        If it is really needed to cut down any number of trees, allow for planting same
        number of trees – Contractor has to take care about watering and
        maintenance of plants for about 3 months or until completion of the contract.
        (Fill schedule of late)
     1 Foundation works
  1.1 Site clearance and preparation of Guard Room                                           LS     1.0
  1.2 Footing Excavation: Excavate 4 (1.2x1.2x1)m holes for footings, level and             CUM    5.76
       compact well ( before receiving foundation blinding)/cut and trim all
       projected faces
  1.3   Footing Blinding: Lay 100mm thick lean 4 (1.2X1.2x0.05)m concrete                   CUM     0.3
        1:4:8 /3bags of cem/0.4cum of river sand /0.8cum of Graded stone 40mm
        nominal size AS PER SPECSabove the excavated footing and foundation
        trenchs, cure the blinding
  1.3   Footing concrete : provide and cast 4 (1.2x1.2x0.4)m R.C.C footing over the         CUM    2.30
        blinding mix 1:2:4 /6bags of cem/1cum of concrete ___Reinforeced with
        double layered 6Y14 Bars spacing 200mm C/C deformed steel in both
        directions/use vibrator in accordance with specifications
  1.4   Columns: Cast in place 4 (0.4x0.2x4.2)m R.C.C Columns Mix 1:2:4/6bags of CUM                1.3
        cem/1cum of concrete____Reinforced with 6Y14mm +R8@150mm c/c
        (DOUBLE LINKED)
  1.5   Slab Beam: provide and cast (0.3x0.3x14.8m) R.C.C beam MIX 1:2:4/6bags              CUM     1.3
        of cem/1cum of concrete___Reinforeced with 6Y12 linked with Y8mm
        stirupps @1590mm c/c
  1.4   Excavation : excavate foundation of Room depth 600mm@400mm width                    CUM     5.1
        plus the excavation of pipe trenches
  1.5   Foundation Blinding: Lay 50mm thick lean concrete 1:4:8 /3bags of                   CUM    1.06
        cem/0.4cum of river sand /0.8cum of gravel above excavated foundation
        trenchs
  1.6   Stone Wall: construct (0.4x0.6x21.2)m rubble masonry stone sealed with CUM                 5.09
        cement mortar mix 1:4 above the blinding
  1.7   Plinth Beam: cast in place (0.4x0.2x21.2)m R.C.C plinth beam Mix 1:2:4 cum                  0.8
        /6bags of cem/1cum of concrete __Reinforced with 4Y12 +R8@200MM C/C
  1.6   Backfilling with Good Hardcore and Crashed Stone: supply and fill                   cum    1.50
        (imported or Excavated selected material over the ground floor compact AS
        PER Specification
  1.7   Hardcore: supply and fill 300mm (imported or Excavated selected material  CUM               5.8
        over the ground floor compact AS PER Specification
  1.8   Flooring Concrete Slab: lay 100mm thick plain concrete over the crashed   CUM               1.9
        stones mix 1:4:8 6bags of Oman ordinary portland cem/1cum of concrete for
        the rooms and verandaha
Sub total A
   2    WALLING
  2.1 Walling: construct 200mm thick concrete hollow blocks sealed with cement              SQM    45.4
        mortar mix 1:4 (Less door)
  2.2 Plastering: apply 20mm thick plastering to both faces of the wall                     SQM    90.9
  2.3 White washing: apply No2 coats of white washing to both faces of the wall             SQM    90.9
  2.4 Emulsion Paint: apply No2 coats of emulsion paint to the external face of the         SQM    90.9
        wall (color and type to be approved by the Engineer)
Sub total of Walling =
   3    DOOR & WINDOWS
  3.1 DOOR 1:Purpose-made steel casement two leaf door made of 15mm thick             PCS       1.0
        steel plate welded to the frame, 38x38x3mm thick steel angles for door main
        frame, 20x20x1.5mm RHS welded to steel plate by 200mm long fillet welds
        at 200mm, hedges and 8mm diameter steel bars embedded in the wall with
        mortar and welded onto the door frame for anchoring the door complete with
        all the necessary ironmongery overall size 900 x 2100mm high
  3.3   Windows 1:Purpose-made steel casement window made of 15mm thick steel         PCS       2.0
        plate welded to the frame, 38x38x3mm thick steel angles for window main
        frame, 20x20x1.5mm RHS welded to steel plate by 200mm long fillet welds
        at 200mm, hedges and 8mm diameter steel bars embedded in the wall with
        mortar and welded onto the window frame for anchoring the window
        complete with all the necessary ironmongery overall size 100x 100mm high
  3.5  Step :Construct Concrete step at verandaha fo easy access                      CUM       1.6
       (2000mmx800mmx600mm
  3.6 Ladder: supply and install iron ladder to the tank                               lm       1.0
Sub-Total of TOTAL DOOR & Windows=
   4   ROOFINGS
  4.1 RCC Slab : provide and cast (3.5*3.5*0.1) R.C.C Slab mix 1:2:4 /6bags of        SQM       1.2
       cem/1cum of concrete ___Reinforeced with double layered 10mm Bars
       spacing 200mm C/C deformed steel in both directions/use vibrator in
       accordance with
  4.2   Water Tank: Provide and install at the top of the 10 cubic meter PE Plastic             1.0
        tank put the top slab of the room                                             Lumps
  4.3  Portable Pump: Provide and Install 3 Inch Petrol pump, maximum                  Pcs      1.0
       delivery horizontal 200m and maximum head 20m
Sub-Total of Roofing=
       BILL 3 (ROOM WITH TANK)
       TOTAL CARRIED TO SUMMARY
        GRAND TOTAL of all work cost in SDG                                           sum
                                                                 Name of Signatory: [insert here]
                                                                      Designation: [insert here]
                                                                         Signature: [sign here]
                                                                     Date Signed: [insert here]
SUDAN Office
               Unit/P in         Total in
                 USD               USD
material,equipment,transport to site,
on has to be read together with drawings and
-
-
-
-
-
-
-
            -
                -
                -
                -
            -
            -
            -
            -
 rt here]
 rt here]
n here]
 rt here]
          Alight (Formerly American refugee Committee)
                                                                           Total
       Bill Nr. 4 Sand Filtee & Chamber                        Price in   Amount
                                                                USD       in USD
       A: Slow Sand Filter
       EARTHWORKS
       Excavations: Rates for excavation to
       include for disposal
       Clear site of works of grass, shrubs, bush
       and small trees, grub up roots, fill with
2.1    selected soil and burn debris                m2   11               0
       Excavations to reduced levels not exceeding
2.2    0.2 m deep and cart away                    m3    2                0
       Excavate underground to a depth not
       exceeding 1500mm deep from stripped
2.3    level                                        m3   14               0
       xtra over excavations for excavating in rock
2.4    at any depth                                 m3   2                0
       Filling                                                            0
2.5    Return fill and ram - make up level          m3   4                0
       CONCRETE WORK                                                      0
2.6    150mm thick Mass Concrete base 1:2:4         m3   1.5              0
       COLLECTION
       A: SLOW SAND FILTER                                      0
       B: FILTERED WATER COLLECTION
       CHAMBER                                                  0
       C: WATER TANK                                            0
Page 26 of 1