QUANTITY SURVEY OF CONCRETE
Materials
                                                                                                  Aggregate (Cft)
S.No.                Item              Quantity Unit       Ratio
                                                                       Cement   Sand
                                                                        (Bag)   (Cft)    10mm     20mm         40mm
Upto
Plinth M-10 Concrete                       1  Cum.        1:03:06        4.44   16.32      4.90     8.16             19.58
       M-15 Concrete                       1  Cum.        1:02:04        6.34   15.54      4.66     7.77             18.65
       M-20 Concrete                       1  Cum.        1;1.5:3        8.06   14.83      4.45     7.42             17.80
       M-25 Concrete                       1  Cum.        1:01:02       11.09   13.60      4.08     6.80             16.32
   1 PCC Below Footing                  12.74 Cum.        1:03:06       56.50   207.88    62.37   103.94            249.46
   2 Footing Concrete                     21  Cum.        1:01:02      232.85   285.55   228.44      342.66
   3 Pedestal Column Concrete            2.24 Cum.        1:01:02       24.84   30.46     24.37    36.55
   5 Ground Beam Concrete                9.81 Cum.        1:01:02      108.77   133.39   106.72   160.07
   7 DPC                                30.98 Sqm.        1:02:04        9.81   24.07     19.25    28.88
   8 Plinth Beam Concrete              0.5175 Cum.        1:01:02        5.74    7.04      5.63     8.44
   9 Floor PCC                          12.50 Cum.        1:02:04       79.19   194.24    58.27    97.12            233.09
  10 Column Concrete for Sub Structure   2.16 Cum.        1:01:02       23.95   29.37     23.50       35.25
                 TOTAL MATERIAL FOR BELOW PLINTH                       571.58   972.30   546.63      843.07         554.89
                                                     Ground Floor
 11     Column Concrete for Super Structure  7.20 Cum.    1:01:02       79.83   97.90     78.32   117.49
 14     DPC                                 13.22 Sqm.    1:02:04        4.19   10.27      8.22    12.33
 15     Sill Band Concrete                   1.32 Cum.    1:01:02       14.66   17.98     14.38    21.57
 16     Lintel Beam Concrete                 3.00 Cum.    1:01:02       33.31   40.85     32.68    49.02
 17     Chajja Concrete                      1.05 Cum.    1:01:02       11.68   14.32     11.45    17.18
 18     Slab Beam Concrete                  11.45 Cum.    1:01:02      126.90   155.63   124.50   186.75
 19     Slab Concrete                       14.59 Cum.    1:01:02      161.76   198.38   158.70   238.05
 20     Staircase Concrete                   1.98 Cum.    1:01:02       22.00   26.98     21.58    32.38
                    TOTAL MATERIAL FOR GROUND FLOOR                    454.33   562.30   449.84   674.76
                                                         First Floor
38   Column Concrete for Super Structure  7.20   Cum. 1:01:02    79.83   97.90      78.32    117.49
41   DPC                                 13.22   Sqm. 1:02:04     4.19   10.27       8.22     12.33
42   Sill Band Concrete                   1.32   Cum. 1:01:02    14.66   17.98      14.38     21.57
43   Lintel Beam Concrete                 3.00   Cum. 1:01:02    33.31   40.85      32.68     49.02
44   Chajja Concrete                      1.05   Cum. 1:01:02    11.68   14.32      11.45     17.18
45   Slab Beam Concrete                  11.45   Cum. 1:01:02   126.90   155.63    124.50    186.75
46   Slab Concrete                       14.59   Cum. 1:01:02   161.76   198.38    158.70    238.05
47   Staircase Concrete                   1.98   Cum. 1:01:02    22.00   26.98      21.58     32.38
                   TOTAL MATERIAL FOR FIRST FLOOR               454.33   562.30    449.84    674.76
                                               PARAPET & STAIR TOWER
65   Column Concrete for Parapet          1.40   Cum. 1:01:02    15.52    19.04     15.23     22.84
66   Column Concrete for Stair Tower      0.84   Cum. 1:01:02     9.31    11.42      9.14     13.71
67   B/W for Stair Tower                         Cum.   1:06      0.00    0.00       0.00      0.00
68   Sill Band Concrete                  0.206   Cum. 1:01:02     2.28    2.80       2.24      3.36
69   Beam Concrete                       0.735   Cum. 1:01:02     8.15    9.99       8.00     11.99
70   Slab Concrete                        1.08   Cum. 1:01:02    11.93    14.63     11.70     17.55
           TOTAL MATERIAL FOR PARAPET FOR STAIR TOWER            47.20    57.88     46.30     69.46
          TOATAL QUANTITY OF MATERIALS                         1527.43   2154.78   1492.62   2262.05   554.89