Module 2
Module 2
Transition to ISO
19650
Royal Institute of Chartered
Engineers
RICS
Table of Content
1. PART 1: INTRODUCTION TO ISO 19650..........................................................................................3
1. PART 1: INFORMATION REQUIREMENTS
1.1. Key learning points - Part 1
How the client requirements are developed
The purpose of key BIM information requirements (OIR, AIR, PIR, EIR) to be put into place at
the strategic definition stage of a project
1.2.1. Self-reflection
Do you think information requirements are a key aspect to information management? Why?
Information requirements can come from respective organisations or interested external parties.
The appointing party should be able to express these requirements to other relevant organisations
and individuals to either specify or inform their work.
Understanding the purpose,
intent, and nature of information requirements
is crucial for project success.
As identified by the UK BIM Framework guidance, the key enablers to collaborative and effective
information management are present when information requirements are:
Clearly defined
Value-driven
Prepared at the outset of the project
TOP TIP
1. Information requirements associated with the delivery
phase of an asset should be expressed in terms of the
project stages that the appointing party or lead
appointed party intends to use.
2. Information requirements associated with the
operational phase of an asset should be expressed in
terms of foreseeable life cycle trigger events such as
planned or reactive maintenance, fire equipment
inspection, component replacement, or change of asset
management provider.
1.3.2. The four facets of information requirements
(UK BIM Framework, Guidance Part D)
While the previous extract from ISO19650-1 concentrates on the importance of the information
purpose, we would like to dive deeper into the definition of the information requirements.
The purpose of information provides the reason why the information is required.
Key point
Always start with the reason (purpose) before the information itself is considered.
As per the Guidance Part D from the UK BIM Framework, information in accordance with the ISO
19650 series can be described across four main facets: purpose, content, form and format. Click on
the buttons below to find out more.
1.3.2.1. Purpose
The need that the information will fulfil. For example, to convey fire performance of a wall.
1.3.2.2. Content
Content is split into:
1.3.2.3. Form
How information is presented.
For example, a schedule or a drawing, etc.
1.3.2.4. Format
How information is encoded. For example, PDF or IFC(-SPF), etc.
Each set of requirements has its own purpose and before going into explaining
each set we would like to describe their relationship between them.
However, on a project t per project level we normally have asset and project
delivery requirements combined, meaning that all information requirements
should be considered. According to ISO 19650-1 the relationship between
information requirements could be represented in the following diagram:
Figure 4 Hierarchy of information requirements
OIR explain the information needed to answer or inform high-level strategic objectives within the
appointing party.
These requirements can arise for a variety of reasons such as:
1. strategic business operation
2. strategic asset management
3. portfolio planning
4. regulatory duties
5. policy-making
Organisations often comprise multiple departments (Finance, Human Resources and Estates, etc.)
which may need to use information generated through the BIM process. For example:
Key point
All these diverse requirements need to be collated and articulated in one place – the OIR.
Once the strategic level information requirements are defined, they can be used to provide input to
the AIR and PIR.
Example
ISO 19650-3 Annex A.2 provides examples of activities requiring asset
information and examples of organisational information requirements
1. strategic
2. tactical
3. operational
The following are examples of OIR, which can also be grouped according to
whether they are strategic, tactical, or operational. Information to support:
1.4.5. EXPLORE
Have a look at the Centre for Digital Built Britain -
International BIM Toolkit Documents for the templates and
guidance for OIR
Repeat clients may develop a generic set of PIR that can be adopted,
with or without amendment, on all of their projects.
Additionally, PIR does not need to be a stand-alone document and could
be incorporated into other information requirements.
1.5.1. EXPLORE
Have a look at the Centre for Digital Built Britain International BIM Toolkit
Documents for the templates and guidance for PIR:
When developing the asset information requirements, the appointing party should identify the
foreseeable trigger events for which information shall be managed. There are a number of trigger
events that should be considered, for example:
inspection of an asset
maintenance work on an asset, whether planned or reactive
minor works on an asset, such as minor repairs, component replacements or minor upgrades
initiating a project to deliver a new asset
major works on an existing asset such as major repairs, refurbishments, or major upgrades
creation of a new asset
In addition to the above, the appointing party shall consider how the information is going to be
linked to the asset management enterprise systems.
It is crucial to identify how the information gathered throughout the project delivery phase will link
to document management, CAFM, enterprise resource planning systems, etc.
Each system may have a requirement, which should be translated into the AIR to avoid ambiguity.
1.6.3. Example:
The AIR should capture the requirements to specify the Asset Information Model.
ISO19650-3 Annex A.4 provides great examples of information that can be required within an AIM:
The following are examples of information that can be required within an AIM to support managerial
OIR:
The following are examples of information that can be required within an AIM to support technical
OIR:
The following are examples of information that can be required within an AIM to support legal OIR:
details of ownership and maintenance demarcation where assets interface across a system
or network of assets
work instructions together with diagrams and reporting requirements, legal obligations such
as health and safety file information, and safety/environmental considerations
asset related contractual information
task risk assessments and control measures
The following are examples of information that can be required within an AIM to support
commercial OIR:
The following are examples of information that can be required within an AIM to support financial
OIR:
whole life costs of asset deployment including cost of historical and planned maintenance
tasks
operating costs
downtime impact
current asset replacement value
original purchase/leasing costs
1.6.4. EXPLORE
Have a look at the Centre for Digital Built Britain International BIM Toolkit Documents for the
templates and guidance for AIR:
International BIM Toolkit Documents for the templates and guidance for AIR
https://www.cdbb.cam.ac.uk/AboutDBB/Promoting-digital-construction-Internationally/
international-bim-toolkit
1.7. Exchange information requirements (EIR)
Exchange information requirements (EIR) should specify those detailed pieces of information needed
to answer PIR and AIR.
Since the EIR topic is quite broad, we will explain the contents of the EIR in the next module when
we go through the invitation to tender stage.
Guidance part D from the UK BIM Framework provides a fantastic diagram outlining the hierarchy
of the information requirements:
Figure 5 Hierarchy of the information requirements
As mentioned before, it all starts at the organisational level, where the appointing party should
outline their strategic programme objectives that are captured in the OIR.
The OIR will guide the requirements needed to answer project delivery requirements, which are
covered in the PIR and operational requirements which are covered in the AIR. Both AIR and PIR are
still considered to be relatively high-level requirements, which will be detailed in the EIR.
We’ll explore how the project information requirements (PIR) and delivery milestones are
determined, how to establish the project’s information standard as well as production methods and
procedures, the project’s reference information and shared resources, common data environment
and project’s information protocol.
While ISO 1950-2 concentrates on the delivery phase of the assets, we know from the previous
lesson that information requirements pertain to both delivery and operational phases, thus asset
information requirements would be considered at this stage as well.
TOP TIP
While we will explain information management functions in
1.9.1.1. EXPLORE
Follow the link to access the detailed information management assignment matrix in excel published
by the UK BIM Framework.
https://www.ukbimframework.org/resources/
OK, let's begin by reviewing the first information management activity which is to appoint individuals
to undertake the information management function and establish their responsibilities.
Both of these activities would be performed by the appointing party or appointing party’s
representative.
Figure 7- Project’s information requirements (1.2) project’s information delivery milestones (1.3)
Figure 6 Example of key decision points and information delivery milestones in relation to the RIBA Plan of work stages
2013
Key
Reference to numbers 2 to 7 reflect the information
Key
management activities set out in ISO 19560-2 clauses 5.2
to 5.7, which are as follows:
2 Invitation to tender
3 Tender response
4 Appointment
5 Mobilization
Key point
The key takeaway from the diagram is that information exchanges should be planned in advance of
the key decision points to allow for review and approval processes.
When developing the project’s information standard the appointing party shall consider:
1.9.3.1. The exchange of information within the appointing party’s
organisation, between the appointing party and external stakeholders,
operators and maintainer and between appointed parties and lead
appointed parties.
Information container
Exchange format
type
1.9.3.2.
Animations (as required) .mp4
Documents .pdf
.pdf and .dwg (as
Drawings
required)
Visualisations .jpg
Native 3D models
(Autodesk Revit) .rvt
In the UK the appointing party may want to utilise Uniclass 2015 classification
system, while in the US the appointing party might want to utilise Omniclass.
Level of Information
Method of assignment
Need
Information provided should comply
with the requirements included in the
project’s information production
Documentation
methods and procedures and be
appropriate to the RIBA Stage for which
the document is issued.
1.9.3.4. Last but not least, The appointing party shall also consider the
use of information during the operational phase of the asset.
For example, the appointing party may want to utilise laser scanning processes.
If they have a preferred method for capturing the existing asset, they may specify it under project’s
information production methods and procedures.
For example, the appointing party may prescribe the method of how the lead appointed party
(architect) shall number the rooms in the new facility.
For example, the appointing party may utilise the security triage process defined in the ISO1965-5 to
identify the security requirement for the project. In most of the cases, the implementation of the
CDE with rigid access permissions will satisfy the security of information distribution.
This is where the appointing party shall consider linked enterprise systems and identify how the
information will be delivered at the key information exchanges as well as at the handover.
For example, the appointing party may identify that they want project information to be transferred
to their internal SharePoint system at the project handover.
The appointing party shall consider the inclusion of existing asset information:
from within the appointing party’s organization
from adjacent asset owners (utility companies, etc.)
under license from external providers (mapping and imagery, etc.)
within public libraries and other sources of historical records
For example, an appointing party may have an existing facility asset register maintained by their
CAFM system, which would be issued to the delivery team as part of the existing asset information.
The existing asset register would be updated by the delivery team and submitted back to the
appointing party at the end of the project.
2. Share resources
The appointing party shall consider the inclusion of shared resources, for example:
process output templates (BIM execution plan, master information delivery plan, etc.)
information container templates (2D/3D geometrical models, documents, etc.)
style libraries (lines, text, hatch, etc.)
object libraries (2D symbols, 3D objects, etc.)
For example, an appointing party such as the Ministry of Justice may have developed a library of 3D
objects for prison design that they want the delivery team to utilise on the project .
3. Library objects defined within national and regional standards
For example, an appointing party may include Health and Safety Risk symbols as the common object
library to be used by the delivery team.
Figure 9 - project’s information standard; project’s information production methods and procedures;
shared resources
Figure 7 The diagram above identifies where we are in the information management process according to ISO19650-2
As we feel the CDE is a crucial component of any project, we will explain the role of Common Data
Environment in Part 3 of this module in greater detail.
1.10. Summary
In summary, developing information requirements is a
rather complex activity, which encapsulates both
the delivery and operational phase requirements.
When drafting information requirements, we need to take into
consideration the need of information from multiple appointing
party’s organisation departments, external stakeholders as well as
delivery teams information requirements.
Key point
Understanding the nature of these interactions is critical to the success of the information
management process.
This section of the module will explain the various ‘function’ that has collective responsibility and
authority for the ISO 19650 information management process.
TOP TIP
Don’t confuse information management functions with job or professional titles. These relate to
design, construction, or operation responsibilities, etc, however the term function relates
to information management responsibilities. Often these two types of responsibility will be carried
out by the same team(s) or individual(s).
The information management function encompasses the collective responsibility and authority for
ISO 19650 Guidance Part A (edition 3): The information management function and resources, UK BIM Framework
management function’.
This function is owned by the appointing party who is ultimately accountable for implementing the
process. Also, an individual within their organisation should be nominated to carry out the function
on their behalf.
This function is owned by the appointing party who is ultimately accountable for implementing the
process. Also, an individual within their organisation should be nominated to carry out the function
on their behalf.
The assignment of the information management function will require the appointing party to
The key elements and benefits of using a Common Data Environment (CDE)
Agreed source of information for any given project or asset, for collecting, managing, and
disseminating each information container through a managed process.
ISO 19650-1 Clause 3.3.15
More simply put, a CDE is a central repository for project and asset
information, acting as a single source of the truth. It is used to collect,
manage, collaborate, and share project information with the project team.
Personnel and other occupants or users of the asset and its services
The asset itself
Asset information
The benefits the asset exists to deliver
Understanding the security framework is a fundamental aspect of establishing who can access what
information and what they can do with it. It is therefore at the heart of how common data
environments are configured and managed. Typically, this aspect is enabled by the CDE solution, but
effective CDE process workflows are required to manage access.
It is this combination of technical solution and process workflow that both principally define the CDE
(according to ISO 19650), and aid project success.
3.1.5.3. EXPLORE
The UK BIM Framework ISO 19650 Guidance Part C: Facilitating the CDE (workflow and technical
solutions) documentation gives a robust explanation about practical components of CDE use;
For detailed further information about information containers with respect to the above, it is
Note – this guidance information is specific to the UK BIM Framework implementation of Status,
Metadata, Classification, and Revisions. Whilst this may not be always be accurate or applicable in all
international frameworks, it is a clear demonstration and application of ISO 19650 principles (with
respect to CDEs) within a UK context and provides one region’s example of good practice.
We’ll start with the client and then move to the delivery team.
Often this is used to facilitate information exchange between different delivery teams on the
project, or for set project information exchanges.
Typically, project CDEs are set up to facilitate information containers in the state of Shared,
Published or Archive
In some instances, CDE’s may be established allowing information containers with the status Work In
Progress information to be used on the client provided CDE, however, this is not best practice nor
envisaged by ISO 19650-2.
Because this will enable all invitations to tender information to be provided through a secure,
organised, and effective environment – driving many of the benefits and reasons noted above.
The appointing party may elect to appoint a third party to provide and manage the common data
environment. ISO 19650-2 says;
The appointing party can also appoint a third party to host, manage or support the project’s CDE. In
this case, it is recommended that this is done as a separate appointment before procurement of any
other appointed party starts. Or the appointing party can also, at a later date, appoint an appointed
party to take over the hosting, management or support of the project’s CDE.
Extracted from ISO 19650-2 clause 5.1.7
Revision, state, and classification are all information container metadata. These give categorisation
and context to the information container that can be used to derive structure in the CDE.
These metadata attributes are mandatorily required for information containers, in order for the CDE
to be compliant with ISO 19650.
A basic overview of States and Revisions will be laid out below, however, it is strongly recommended
that the section Explore above is reviewed and noted content additionally reviewed to get a fuller
picture of these topics.
The project’s common data environment – Each information container to have the following
attributes assigned:
Status (suitability)
Revision
Classification (in accordance with the framework defined in ISO 12006-2)
3.3.1.1. Revision
ISO 19650-1 recommends that the information container revision system should follow an agreed
standard. The application of this system tracks the progression of information container revisions.
This is an important consideration for downstream parties who are dependent on the accuracy and
reliability of the information.
Example
As an example of best practice, the ISO 09650-2 national annex for the UK depicts the following
3.3.1.2. States
According to ISO 19650-1 (clause 12.1);
The current revision of live information containers within the CDE should be in one of the following
three states:
Work in progress
Shared
Published
Current information containers can exist across all three states, depending on their
development.
There should also be an archive state providing a journal of all information container transactions
and an audit trail of their development.
See the below figure taken from ISO 19650-1 (Figure 10) for context of these states:
Figure 9Information Containers transition between states by the workflow process.
3.3.1.3. Classification
ISO 19650-2 clause 5.1.7 requires that information containers be assigned classification metadata in
accordance with ISO 12006-2.
It is important to classify information containers to agreed and established type standards in order
to understand the contents of the information container, rather than the form of the information
container (as this is typically dealt with by other metadata in the CDE solution).
Uniclass 2015 is compliant with ISO 12006-2 and is the preferred classification system in the UK. It
is referenced in the ISO 19650-2 National Annex.
Uniclass 2015 contains multiple classification tables which can be used to classify different types of
information containers.
The appointing party should define the classification method in the project’s information standard
as the national annex only acts to make a recommendation.
This would indicate which of the Uniclass 2015 tables are used for classifying information containers.
If the appointing party does not have a preference, then the lead appointed party would define
requirements.
3.4. Scenario 2
A new landmark museum is planned for the centre of the capital city.
During procurement, a prospective lead appointed party communicates to the appointing party that
their organisation’s policies require that information they produce be stored within their own
enterprise systems until it has been reviewed and found suitable for sharing externally. This policy
stems from a condition within their organisation’s indemnity insurance.
Simultaneously, project specific security requirements create two material considerations for the
management of project information:
1. An overarching requirement that all project information be protected, and unless approved
by the appointing party be made available only to members of the immediate project team
2. A heightened requirement for the museum’s security room which is considered a sensitive
area. Only parties with legitimate need should have access to information about this
location.
The solution
A common data environment may consist of multiple technical solutions since it is the workflows
between these that is most important. The nominated individuals for the appointing party and lead
appointing party agree that information in the work in progress state should be controlled within the
lead appointed party’s technical solution. The shared and published states will remain under the
control of the appointing party. A work in progress to shared state workflow is established which
incorporates both the check, review and approve processes needed by the lead appointed party’s
policy and the transition between the two technical solutions.
To resolve the overarching security consideration, the appointing party restricts common data
environment access to individuals within the project team. This restriction applies across both
technical solutions. A workflow is established by which parties can seek appointing party approval to
share information with external parties.
To resolve the heightened security consideration, the appointing party identifies a volume
encompassing the security room which is considered sensitive. Only individuals directly involved in
the design and construction of the security room will be permitted access to information within this
volume. Information containers holding information relating to the security room volume will be
appended with metadata identifying this condition. Using this metadata, the appointing party will
configure the technical solution so that only known and permitted individuals can view these
sensitive information containers.
3.5. Summary
Using a project CDE on construction projects is explicitly included in ISO 19650-2, being the
responsibility of the Appointing Party to implement. However, there are a number of
reasons why implementing a CDE is beneficial, not just because it’s a requirement of ISO
19650.
A CDE is made up of a CDE technical solution and CDE process workflow, both elements
must be present.
Early establishment of a CDE is recommended, ideally before Tender stage, before
procurement of any other appointed party starts.
There are important principals for management of Information Containers within a CDE that
must be considered, Revision, Status, and Classification.