Edureka Support Book
Edureka Support Book
Hand Book
Based on A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth
Edition
Note: The handbook ‘PMP® Exam Prep Workshop’ that Edureka offers the learners is NOT the replacement of PMBOK ® Guide. We have created the
handbook to simplify and make the guide learner friendly. The handbook is aligned to PIMBOK ® Guide, but NOT the replacement of PMBOK® Guide.
1|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Table of Content
Contents
1. PMP® Examination - At a Glance.............................................................................................................. 30
2|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
2.6. Competencies of Project Manager ................................................................................................... 41
2.7.1. Program.......................................................................................................................................... 42
3|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
3.2. Project Management Process Group ................................................................................................ 55
4|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.3.1.4. Enterprise Environmental Factor ................................................................................................... 72
4.3.2. Direct and Manage Project Work – Tools and Techniques ................................................................. 72
5|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.4.3.1 Lessons Learned Register ............................................................................................................... 78
4.5.2. Monitor & Control Project Work – Tools and Techniques .................................................................. 81
6|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.5.2.4. Data Analysis ............................................................................................................................... 85
7|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5.2.1.2 Project Management Plan ............................................................................................................. 95
8|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5.4.1.3. Enterprise Environmental Factors ................................................................................................ 102
9|Page
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.1.1. Plan Schedule Management – Inputs ............................................................................................. 112
10 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.3.2.2. Dependency determination & integration ................................................................................... 119
11 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.6.1.5. Organizational process assets ..................................................................................................... 128
12 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.7.2.4. Resource Optimization Techniques .............................................................................................. 115
13 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
7.2.2.6. Data Analysis ............................................................................................................................. 124
14 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
7.4.1.6. Organizational Process Assets ..................................................................................................... 130
15 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
8.2.1.2. Project Documents...................................................................................................................... 141
16 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
9.1. Plan Resource Management .......................................................................................................... 142
17 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
9.4.1.2. Project Staff Assignments ........................................................................................................... 151
18 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
9.5.3.5 Organizational Process Assets Updates ........................................................................................ 156
19 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
10.1.2.4. Communication Methods .......................................................................................................... 161
20 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
10.3.3. Control Communications – Outputs .............................................................................................. 167
21 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.2.1.13. Organizational process assets ................................................................................................. 177
11.3.3. Perform Qualitative Risk Analysis – Tools and Techniques ............................................................. 180
22 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.4.3. Perform Quantitative Risk Analysis – Tools and Techniques ........................................................... 183
23 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.6.3.5. Reserve analysis ....................................................................................................................... 187
24 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
12.1.3.6. Change requests ....................................................................................................................... 195
25 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
12.3.1.2. Procurement documents ........................................................................................................... 199
26 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
13.1.2. Identify Stakeholders – Tools and Techniques ............................................................................... 206
27 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
13.3.2.5. Meetings .................................................................................................................................. 216
28 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
29 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
1. PMP® Examination - At a Glance
This Chapter discusses on how a participant of PMP® Exam Prep Program would approach the PMP®
examination and what are the key information they need to know.
→ Understand the best practices of Project Management as per PMBOK® Guide - 6th Edition
→ Get familiar with the multiple choice questions in line with the PMP® Certification process
30 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Project management experience mentioned in both the categories must be from unique and non-
overlapping projects
→ Within the specified 4,500/7,500 hours, experience in all 5 performance domain is required
(experience need not be in all 5 performance domains on a single project)
→ Candidates can satisfy Project Management Education requirement by successfully completing the
training sessions through PMIs Global Registered Education Provider.
Re-examination Computer-
USD 275.00 USD 375.00
based
31 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ We recommend candidates to become a member of PMI® first, and then apply for PMP® Certification
because as a PMI® member receive Exclusive Members Discount on PMP® exam fee.
→ All candidates will be given one year to take the examination. This one-year eligibility
period begins when a candidate’s application is approved.
→ Candidates will have three opportunities to take and pass the PMP® examination within their one
year eligibility period. If candidates do not succeed in 3 attempt, candidates will have to wait one year
from their unsuccessful attempt before being permitted to take the exam again.
→ Please log on to Membership section at www.PMI®.org and get a complete list of valuable benefits
that help to promote your professional and career development.
4) Offer a standardized and objective mechanism for attaining and recording professional
development activities
→ The CCR program supports the ongoing professional development of PMI® certified PMP®s and the
maintenance of PMP® Certification.
→ PMP®s must attain minimum of sixty (60) Professional Development Units (PDUs) during each CCR cycle
of 3 years.
→ Up to 18 excess PDUs earned during the final year of the current CCR cycle can be transferred to next
CCR cycle.
→ PMP®s who fail to satisfy the continuing certification requirements prior to the completion of their
cycle have 12 months from the cycle expiration to do SO. During this time their PMP® certification
will remain suspended.
32 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ On completion of suspension period of 12 months, PMI® will revoke the certification of a PMP® not
satisfying the CCR program requirements.
→ To renew the PMP® certification, candidates will be charged renewal fee once during the CCR cycle.
Payment will be required with submission of the application for Certificate renewal after PMP® has
earned the required PDUs. Amount of renewal fee:
→ 25 Pretest questions (also known as dummy questions) will be randomly placed throughout the
examination to gather statistical information on the performance of these questions in order to
determine whether they may be used on future examinations. These 25 pretest questions are
included in the 200-question but will not be included in the pass/fail determination. Candidates will
be scored on 175 questions.
→ To pass the PMP® examination, candidates must correctly answer a minimum of 106 of the 175
scored questions.
→ Upon completion of the test, the examination contractor will immediately provide candidates with a
printed copy of results indicating pass or fail status.
33 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Distribution of
Domain Questions
13%
Initiation
24%
Planning
30%
Execution
8%
Closing
35 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
36 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
2. Project Management Foundation – Framework, Lifecycle &
Organization
This chapter lays the foundation upon which entire set of knowledge areas are built. In this chapter
you are going to learn about the Project, Project Management Framework, what are the factors that
can have an impact on a project and also how the role and powers of project manager changes in
different organizational structures?
Topics covered in this chapter are highly important with respect to PMP® examination as questions
coming from these areas will gauge your understanding of project organization, relationship between
various endeavors of an organization (project, program & portfolio) and key project roles
(stakeholders, sponsor and project manager).
A project can thus be defined in terms of its specific characteristics. Temporary means that every
project has a definite beginning and a definite end. Unique means that the product or service is
different in some distinguishing way from all other products or services. For many organizations,
projects are a means to respond to those requests that cannot be addressed within the organizations
normal operational limits. Product or service characteristics are progressively elaborated.
How Temporary?
→ The need for the project no longer exists or the fund is exhausted
How Unique?
− End result or product or service is different in some way from the other product, service or result.
For example: Within a Housing complex, each type of flat has different designs, facilities and features
to differentiate their end characteristics -mosaic with teak wood finish or marble with teak wood
finish or red-oxide flooring with forest wood finish.
37 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
− Projects drive change in organizations. From a business perspective, a project is aimed at moving an
organization from one state to another state in order to achieve a specific objective.
− PMI® defines business value as net quantifiable benefit derived from business endeavor.
Progressive Elaboration
→ Progressive elaboration is a characteristic of projects that combines the concepts of temporary and
unique. Because the product of each project is unique, the characteristics that distinguish the
product or service must be progressively elaborated. Progressively means “proceeding in steps;
continuing steadily by increments.”
Project become existent for solving an existing problem or a need came from market or social need
or technological change or business need or cultural change or organizational need or environmental
change, or a customer request or a Legal requirement, etc. All the companies, institutions or
establishments perform certain work which generally involve either projects or operations. Both
Projects and Operations own the following commonalities:
→ Performed by People
38 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Projects and Operations vary primarily as projects are temporary and unique while operations are
repetitive and ongoing. The characteristics of the Projects and Operations are given below:
Project Operations
39 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
2.3. What is Project Management?
Project management is accomplished through the use of PM processes such as: initiating, planning,
executing, controlling, and closing (IPECC). The project team manages the work of the projects, which
typically involves:
→ Identified requirements
It is important to note that many of the processes within project management are iterative in nature.
This is in part due to the existence of arid the necessity for progressive elaboration in a project
throughout the project life cycle; i.e., the more you know about your project, the better you are able
to manage it. The term project management is sometimes used to describe an organizational
approach to the management of ongoing operations. This approach, more properly catted
management by projects, treats many aspects of ongoing operations as projects to apply project
management techniques to them.
The key challenge in the project management is to successfully manage the project while striking the
right balance among the various project elements. These elements are also known as “Constraints”.
Some of the key constraints are Scope, Time, Cost, Quality, Risk and Resources etc. These constraints
work in tandem with each other.
40 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
2.5. Project Stakeholders
Project stakeholders are individuals and organizations that are actively involved in the project, or
whose interests may be positively or negatively affected as a result of project execution or project
completion, they may also exert influence over the project and its results.
The project management team must identify the stakeholders, determine their requirements, and
then manage and influence those requirements to ensure a successful project. Stakeholder
identification is often difficult to achieve.
For example: Escalation in cost of input materials may threaten Construction worker’s future and
continuous employment. Some of the key stakeholders common in almost every project are identified
below:
→ Sponsor
→ Project manager
→ Customer
→ Sellers/Contractors
→ Government agencies
The naming or grouping of stakeholders primarily helps identifying which individuals and
organizations consider themselves as stakeholders. Stakeholder roles and responsibilities may
overlap, for example a customer playing a role of a sponsor and customer.
Project manager is responsible for overall success of the project within the constraints of scope, time,
cost, quality, risk, resources and other key constraints. Project stakeholders have a significant impact
on these constraints hence it becomes crucial for project manager to manage the stakeholders
effectively for successful delivery. In past few years, industry has witnessed unprecedented dynamics
as organization respond to increasing completion within complex project environment.
With such a changing working climate project managers find themselves confronted by issues that
have traditionally not been a part of their responsibilities. To deal with those issues, they must acquire
certain specific skills which will result in effective management of the projects.
41 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
2.6.1. Interpersonal skills
People Management, relationship creation and retention are of today’s order of the day with
internal customer, external customers, external agencies, governmental agencies, society, and
stakeholders. interpersonal skills are of paramount important in order to be successful In today’s
competitive, mechanical, fast-phased, demanding environment, coupled with a diverse workforce,
call for significant amounts of people management skills, e.g.:
Certain types of endeavors are closely related to projects. There is often a hierarchy of strategic plan,
program, project, and subproject, in which a program consisting of several associated projects will
contribute to the achievement of a strategic plan.
2.7.1. Program
A program is a group of projects managed in a coordinated way to obtain benefits not available
from managing them individually. Many programs also include elements of ongoing operations.
For Example:
→ The “Integrated Guided Missile Project” includes a group of projects to design and develop
the missiles, as well as the ongoing manufacturing and support of that missiles in operation.
→ Many Software and related firms have program managers who are responsible for both
individual product releases (projects) and the coordination of multiple releases over time
(an ongoing operation)
→ Programs may also involve a sense of repetitive or cyclical undertakings: for example:
→ Testing or Quality audit are classical cases, where the product or components or piece of
software code should meet the predetermined standards or test/quality criteria.
42 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Many voluntary organizations have a “resource mobilization programs,” an ongoing effort to
obtain requisite support that often involves a series of discrete projects, such as a
membership drive or an auction or sponsorship or conferences or programs.
Portfolio management refers to the selection and support or projects or program investments.
These investments in projects and programs are guided by the organization’s strategic plan arid
available resources. Organizations manage their portfolios based on specific goals. With Portfolio
Management, organizations can maximize the value of the portfolio by careful examination of
various projects or programs for inclusion in portfolio arid timely exclusion of projects not meeting
the portfolio’s strategic business objectives.
2.7.3. Sub-projects
Components of a project that are often contracted out is known as subproject. Projects are
frequently divided into more manageable components or subprojects. Subprojects are often
contracted to an external enterprise or to another functional unit in the performing organization.
Subprojects are based on the project process, such as a single phase. Subprojects according to
human resource skill requirements, such as the installation of plumbing or electrical fixtures on a
construction project or testing of software by a skilled employee, etc.
A project management office (PMO) is an organizational unit to centralize and coordinate the
management of projects under its domain. A PMO can also be referred to as a ‘program
management office,” “project office.” or “program office.”
A PMO oversees the management of projects, programs, or a combination of both. The projects
supported or administered by the PMO may or may not be related other than by being managed
together. Some PMOs, however, do coordinate arid manage related projects. In many
organizations, those projects are indeed grouped or are related in some manner based on the
way the PMO will coordinate and manage those projects. The PMO focuses on the coordinated
planning, prioritization and execution of projects and sub-projects that are tied to the parent
organization’s or client’s overall business objectives.
43 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
2.8. Purpose of Project Management
The purpose of project management is to plan, manage and control activities so that the project is
successfully completed fulfilling the objective of customer and the performing organization. The need
for project management was never so important considering some of the key following factors:
Worldwide markets face incense competition from transnational, multi-national and developing
economies whose aim is to globalize all the countries’ economies across the world. Such intense
whore
competition demands ready to market, what to build, where to build, how to build to
various
products and services for global markets and communicate with customers and other
stakeholders. It is also challenging for all the global corporations Lo manage their specialists and
support human resources, and also manage the challenges of marketing products and services and
meeting the distribution needs.
With the availability of abundant human knowledge, specific knowledge is called for solving
specific/relevant problems associated with the development, production and distribution of
goods and services by ever increasing number of academic disciplines. This expands the horizon
of different types of projects that people can think of and put thru. For Example, “Construction of
a Technology Park requires multi-skilled human resources with knowledge in the areas of civil,
mechanical, electrical, water management, environmental engineering, and Information
Technology.
With the explosion of population and globalization of world economy, all the products/service
providers are out in the market to fulfill ever-growing demand throughout the world for a broad
range of scientific, electronics, personal, industrial inputs, raw materials, semi-finished,
sophisticated, customized goods and services. Consumerism is the keyword which has taken the
world by storm. Meeting such rapidly changing demands require design flexibility, coordination
of group efforts, and change control into all manufacturing and well entrenched distribution chain
for supply of goods and services with superior quality attributes and delivery on time, all the time.
There is also a demand for existing mass produced products which, needs a presence of PM
processes and a qualified project head. To give an example, moving factories overseas to reduce
manufacturing and shipping costs and to gain a physical presence in
44 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
an expanding market. Information Technology plays a major role in unifying the manufacturer
with their customer sitting elsewhere in the world and also satisfies their need without customer
or manufacturer meeting face to face with each other.
In the current trend, skill & knowledge and ability needed are not generally found to be available
in a single person and thus it is necessary to have a team, which possesses such spectrum of
skills/knowledge/ability to meet the customer needs or resolving a complex problem. To
successfully complete the large complex multinational projects, it is essential that the team with
varied skills and disciplines work together, within organization structure, distant locations or
contract entities, or combination of all.
The factors that affect a project's success include Type of Organization, processes, knowledge,
leadership style, culture, PM Information System and effective communication etc. Each of these
factors should be examined thoroughly as they will have a significant impact on the project
outcome. While several of these topics are covered in detail in the later part of this handbook, this
section explains how maturity of the organization with respect to following elements can impact
the project significantly:
The structure of any organization represents the hierarchy of people and its functions. It sets the
level of authority, roles and responsibilities and the reporting structure within the project. Based on
the nature of the business, organizations tend to adopt one of the three types of structures for
effective control on the day to day operational and project management related work.
Organizational structure define what level of authority and control project manager can exercise
on their team and how much decision-making power they will have with respect to the project.
45 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Following are the three types of organization structures that can be observed in
organizations:
Functional organizations are made up of units or division based on the types of businesses
and their associated responsibility. This type of organizational structure has clear reporting
hierarchy and communication channels. Skills of the team members are specific to the staff
in a function/department and projects/project team are specific to the function/department.
Communication between departments takes place through functional managers down to the
project team and Project manager may be known as a project coordinator or team leader.
46 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Organizations that derive revenue from performing projects for others fall under this type. In
Projectized Organizations, project manager works full time on the project with his team and
has complete or close to complete power over the project team. Project Manager may have
full time administrative staff to help expedite the project and entire team reports directly to
project manager
47 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Weak matrix structures map closely to a functional structure. Project teammay come from
different departments, but the project manager reports directly to a specific functional
manager. Project manager has very limited authority in the project and he is not more
than a project coordinator.
48 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
A balanced matrix structure has many of the same attributes as a weak matrix, but the
project manager has more time and control over the project and shares power with the
functional manager. Team members generally face time- accountability issues in this type
of organization as they have dual reporting to Functional Manager as well as Project
manager.
49 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Strong matrix organization, has several attributes similar to the Projectized organization.
Project manager gains more control over resources and their time when it comes to
project work and he has little more authority than functional managers when it comes to
the project. The project team may also have more time available for the project even
though they may come from different departments
50 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Below table illustrates the comparison of various elements in different types of Matrix
structure:
51 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
2.9.2.4. Composite Organization
Composite organizational structure is an ad-hoc structure that is created to manage a high-
priority project for its duration. This type of project team organization consist of highly skilled
resources from various functions/departments and they report directly to project managers
for the project duration.
The project management system is the set of tools, techniques, methodologies, resources, and
procedures used to manage a project. PMS ensures consistency in application and continuity on
the various projects being performed. To facilitate the project management activities, most of the
organizations develop PMS that can include automated tools, such as a scheduling software tool,
configuration management system, information collection and distribution system, or web
interfaces to other online automated systems.
52 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
A project life cycle is the series of phases that a project passes through from its start to its completion.
Following are a few life cycles :
→ Predictive or waterfall life cycle : The scope, time and cost are determined at the early phases of the life cycle.
Changes are managed carefully.
→ Iterative Life Cycle : Project Scope is generally determined early in the project but the time and cost estimates
are routinely modified as the project team’s understanding increases.
→ Incremental life cycle : The deliverables are produced through a series of iterations that add functionalities within
a pre-defined time frame.
→ Adaptive or Agile life cycle : The detailed scope is defined before the start of an iteration.
53 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
54 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
3. Processes, Process Groups and Knowledge Areas
This chapter provides an overview of the ten PMBOK® Guide – Sixth Edition Project Management
Knowledge Areas and the associated 49 processes and how they are aligned to 5 process groups.
Topics covered in this chapter provides an overview of the structure on which all the later chapters
are based.
3.1. Process
“A set of interrelated actions and activities performed to create a pre-specified product, service, or
result. Each process is characterized by its inputs, the tools and techniques that can be applied, and the
resulting outputs.”
The project life cycle is managed by a series of project management activities known as project
management processes. Every project management process produces one or more outputs from one
or more inputs by using appropriate project management tools & techniques. The output can be a
deliverable or an outcome.
Project team identifies the processes that needs to be followed to meet/comply with project
requirements while balancing the triple constraints of a Project. Information or data is received from
various sources in Inputs, analyzed using specified Tools & Techniques and Output is churned out.
Output of one process can be an Input to other process(es). PMBOK® Guide – 6th Edition has listed 49
processes spread across different knowledge areas and process groups. All processes interact with
each other throughout the project via their Inputs and Outputs. To manage a project successfully,
project team must manage and guide these interactions.
▪ Initiating Process Group. Those processes performed to define a new project or a new phase of
an existing project by obtaining authorization to start the project or phase.
▪ Planning Process Group. Those processes required to establish the scope of the project, refine
the objectives, and define the course of action required to attain the objectives that the project
was undertaken to achieve.
55 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
▪ Executing Process Group. Those processes performed to complete theGuide
work defined in the project
management plan to satisfy the project requirements.
▪ Monitoring & Controlling Process Group. Those processes required to track, review and regulate
the progress and performance of the project; identify any areas in which changes to the plan are
required; and initiate the corresponding changes.
▪ Closing Process Group. Those processes performed to formally close project, phase or contract.
PMBOK® Guide - Sixth Edition provides a best-practice approach to handle project management
challenges across domains at all levels. The integrative approach of five process groups yields positive
results for if the project manager or team understand how the five different process groups overlap
throughout all phases of the project.
56 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Project Integration Management. Includes the processes and activities to identify, define, combine,
unify and co-ordinate the various processes and project management activities within the Project
Management Process Groups.
▪ Project Scope Management. Includes the processes required to ensure the project includes all the
work required, and only the work required, to complete the project successfully.
▪ Project Schedule Management. Includes the processes required to manage the timely completion of
the project.
▪ Project Cost Management. Includes the processes involved in planning, estimating, budgeting,
financing, funding, managing, and controlling costs so that the project can be completed within
approved budget.
▪ Project Quality Management. Includes the processes for incorporating organization’s quality policy
regarding planning, managing and controlling project and product quality requirements, in order to
meet the stakeholder’s expectation.
▪ Project Resource Management. Includes the processes to identify, acquire and manage resources
needed for the successful completion of the project.
▪ Project Communication Management. Includes the processes required to ensure timely and
appropriate planning, collection, creation, distribution, storage, retrieval, management, control, and
ultimate disposition of project information.
▪ Project Risk Management. Includes the processes of conducting risk management planning,
identification, analysis, response planning, response implementation, and monitoring risks on a
project.
▪ Project Procurement Management. Includes the processes necessary to purchase or acquire products,
services, or results needed from outside the project team.
▪ Project Stakeholder Management. Includes the processes required to identify the people, groups or
organizations that could impact or be impacted by the project, to analyze stakeholder expectations
expectation and their impact on the project and develop appropriate management strategies for
57 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
effectively engaging them in project decisions and execution.
Following table shows mapping of 49 processes to process groups and knowledge areas:
4. Project 4.1 Develop 4.2 Develop 4.3 Direct and 4.5 Monitor & Control 4.7 Close Project
Project Project Manage Project Project Work or Phase
Integration
Charter Management Work
Management 4.6 Perform
Plan
4.4 Manage Project Integrated
Knowledge Change Control
Management
58 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
9.6 Control Resources
9. Project 9.1 Plan Resource 9.3 Acquire
Resource Management Resources
13. Project 13.1 Identify 13.2 Plan 13.3 Manage 13.4 Monitor
Stakeholder Stakeholder Stakeholder Stakeholder
Stakeholder
s Engagement Engagement Engagement
Management
59 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
60 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4. Project Integration Management
Project Integration Management includes the processes and activities to identify, define, combine,
unify, and coordinate the various processes and project management activities within the Project
Management Process Groups.
Project Integration Management consist of high level process which are performed to ensure
all the elements of the project are properly coordinated. It involves controlling changes to
the overall project and making tread offs to ensure stakeholder’s objectives are being met. Project
Integration Management is comprised of following processes:
Knowledge Monitoring
Area Initiating Planning Executing and Closing
Controlling
4 Project 4.1 Develop 4.2 Develop 4.3 Direct and 4.5 Monitor and 4.7 Close Project
Integration Project Project Manage Control or Phase
Charter Management Project Work Project Work
Management Plan
4.4 Manage 4.6 Perform
Project Integrated
Knowledge Change
Control
Develop Project Charter is the first process of developing a document that formally authorizes the existence
of a project and provides the project manager with the authority to apply the organizational resources o project
activities. Developing the Project charter is primarily concerned with documenting the business needs,
project justification, current understanding of the customer’s requirements, and the new product,
service, or result that is intended to satisfy those requirements.
A project can be linked to the ongoing work of the organization by preparing the project charter. In
some organizations, a project is not formally chartered and initiated until completion of a needs
assessment, feasibility study, preliminary plan, or some other equivalent form of analysis that was
separately initiated.
An illustration of Inputs, Tools & techniques and Outputs of this process is given below:
61 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Business Case. The approved business case describes the necessary information from
business stand point to determine whether the expected outcome of the project justify
the required investment. This is the most commonly used document for developing
project charter. The business case is created as a result of one or more of the followings:
62 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
such Legal need.
− A social need: Example: Rotary Club engaged ¡n authorizing projects to alleviate
social needs Like “HIV/AIDS awareness campaign”, “Blood Bank Camps”,
‘Education for underprivileged children” in the rural and semi-urban areas.
▪ Benefits Management Plan. This is the document that describes how and when the
benefits of the project will be delivered and describes the mechanism that should be in
place to measure the benefits.
4.1.1.2. Agreements
If the project is being done for an external customer, a contract from the customer is treated
as an Input.
→ Organizational Culture and Structure: Culture is a “shared value’ among the entire
workforce and the structure indicates as to how the whole company’s functional
framework is in place with appropriate communication channels and approval levels.
Complex structure will itself be a constraint for the organization to pull through successful
project completion. Whereas projectized organization having fiat organization structure”
will more amenable to the project Success.
→ Governmental or industry standards: Regulatory agency regulations, product standards,
quality standards, and workmanship standards etc. are some example of governmental or
industry standard which has an impact on project planning and execution. ISO 9001:2000
or BIS 150(X), CMMIor Six Sigma are considered the Quality standards and governmental
regulations like FEMA or product standards like ISI or Agmark are the key factors to be
considered while developing project charter.
→ Organizations’ human capital: Technical, managerial and administrative skills, functional
63 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
discipline, and knowledge, such as product design, serviceGuide
framework development,
secretarial, Legal, logistics, inventory management, supply chain management, quality
management, business process knowledge etc.
→ Market Condition and Global Competition: The intensity of the project increases or
decreases based on the fact that as to which market the company competes with and
what is the intensity of the competition in that market segment. To give a simple
example, if the company is engaged in high intensity zone where it is expected to meet
consistently the customers (coming from different segments with product variants, per
se a challenge to meet with. Therefore, in such organizations the project teams’ success
of product development is a paramount importance foe company’s survival. On the
contrary, if the company’s existence in a market is, by and large less intensive and thus
the project teams’ will have a different intensity to work with.
64 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Other departments/units within the organization
→ Consultants
→ Stakeholders including customers or sponsors
→ Professional and technical associations
→ Industry groups.
▪ Brainstorming. This technique is used to identify a list of ideas in a short period of time.
It is conducted in a group environment and led by facilitator. Brainstorming can be used
to gather data & solution from stakeholders & SME when developing Project Charter.
▪ Focus Group. Through this technique the perceived project risks, success criteria and
other topics are learned in a more conversational way than one-to-one interview.
▪ Conflict Management.
▪ Facilitation. Facilitation techniques is one of the most commonly used Tools &
Techniques used to help teams and individuals to brainstorm, resolve conflicts, solve
problems and manage the meetings. In Develop Project Charter process facilitation
techniques are used to collaborate the efforts of stakeholders to translate the
requirements of the customers to high-level objectives.
65 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Meeting Management. Meeting management includes preparing agenda, ensuring that
representative of each key stakeholder is invited and preparing and sending the MOM.
4.1.2.4. Meetings
For this process the meetings are held with key stakeholders to identify the project
objective, success criteria, key deliverables, high level requirements and summary
milestones.
→ Project Title
→ Project Description
→ Overall Project Risks
→ Objectives
→ Project Scope Overview
→ Major Deliverables
→ Key Milestones
→ Business Case
→ Financial Benefits
→ Top Management’s Approval
→ Project Manager’s Acceptance
This document contains the high-level Assumptions and Constraint identified in the business case
before the project is initiated. This document will be used to record all the assumptions and constraints
throughout the project life cycle.
66 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.2. Develop Project Management Plan:
The process of defining how a project is planned should be executed, monitored and controlled and
closed is called as The Develop Project Management Plan. It includes the actions necessary to define,
integrate, and coordinate all subsidiary plans. The project management plan content may vary
depending upon the application area and complexity of the project. This process results in a project
management plan that may be updated and revised through the Integrated Change Control process.
Described in section 4.1.3.1. Project Charter provides the reference to start the detailed
project planning processes.
The primary objective of Develop Project Management Plan process is to combine and unify
output from other planning processes. All the subsidiary plans and baselines that are created
in all relevant knowledge areas are unified and combined in this process.
The enterprise environmental factors that can influence the Develop Project Management
Plan process include:
67 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Project management information system
Organizational process assets provide a list of policies, procedures, and guidelines, controls
procedures, Historical information and lessons learned knowledge bases that is used as a key
input in developing the Project Management plan.
Expertise is needed to develop project management plan can provided by any group or
individual with specialized knowledge or training and can be made available from several
sources including:
Data gathering techniques used in this process includes but not limited to:
▪ Brainstorming.
▪ Focus Groups
▪ Interviews
▪ Checklists. Many organizations have standardized checklists available prepared by
themselves or use checklists from the industry. It may help the project manager to develop a
plan or to verify if all the requirements are included in the project plan.
▪ Conflict Management
▪ Facilitation
▪ Meeting Management.
4.2.2.4. Meetings
68 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.2.3. Develop Project Management Plan – Output
It can be composed of one or more subsidiary plans and other components and it can be
either summary level or detailed. Each of the subsidiary plans and components is
detailed to the extent required by the specific project. These subsidiary plans include:
→ Resource Calendar
→ Cost Baseline
→ Milestone List
→ Schedule Baseline
→ Quality Baseline
→ Risk Register
In order to accomplish the work defined r the project scope statement, the project manager and the
project team need to execute the project management plan performing multiple actions defined in
this process. Some of these actions are:
The project manager manages the various technical and organizational interfaces that exist within the
project and directs the performance of the planned project activities along with the project
management team. The project application area generally affects the Direct and Manage Project Work
process directly. The project work planned and scheduled in the project management plan to
accomplish Deliverables are outputs from the processes. Work performance information about the
completion status of the deliverables, and what has been accomplished, is collected as part of project
execution and is fed into the performance reporting process.
Although the products, services, or results of the project are frequently in the form of tangible
deliverables such as buildings, roads, etc. and intangible deliverables, such as training, can also be
provided. Direct and Manage Project Work also requires Implementation of:
→ Approved corrective actions that will bring anticipated project performance into compliance with the
project management plan.
→ Approved preventive actions to reduce the probability of potential negative consequences.
→ Approved defect repair requests to correct product defects found by the quality process.
70 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
It can be composed of one or more subsidiary plans and other components and it can be
either summary level or detailed. Each of the subsidiary plans and components is
detailed to the extent required by the specific project.
The project documents that can be input to this process may include but not limited to:
▪ Change Log
▪ Lesson Learned Register
▪ Requirement Traceability Matrix
▪ Risk Register
▪ Other documents
71 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.3.1.3. Approved Change Request
In order to expand or contract project scope, authorized changes are documented Change
Requests that can also modify policies, project management plans, procedures, costs or
budgets, or revise schedules. Approved change requests are scheduled for implementation
by the project team.
Organizational process assets provide a list of policies, procedures, and guidelines, controls
procedures, Historical information and lessons learned knowledge bases that is used as a key
input in developing the Project Management plan.
Expertise is needed to Direct and Manage Project work can provide by any group or individual
with specialized knowledge or training and can be made available from several sources
including:
72 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Standardized set of automated toots available within the organization are integrated into a
system that is catted as the Project Management Information System (PMI®S). The PMI®S is
used by the project management team to support generation of a project plan, facilitate
feedback as the document is refined, control changes to the project plan, and release the
approved document.
4.3.2.3. Meetings
While directing and managing project work, project manager, project team and stakeholders
may need to conduct meetings to discuss and address pertinent topics of the project.
Meetings are tending to be one of three types:
→ Information Exchange
→ Brainstorming, option evolution or design or
→ Decision making
Any verifiable product, service or result (or part of it) which is identified in the project management
planning documentation is considered as deliverable which must be produced and provided to
complete the project.
Work performance data is the lowest level of detail coming from raw observations and measurements
of activities while carrying out the project work. Raw data is gathered throughout the execution phase
and passed to the controlling processes of each process area for detailed analysis. Work Performance
Data includes work completed, KPIs, start/finish dates of activities, number of defects, actual duration
and cost etc.
Through out the lifecycle of the project the project manager will face problems, gaps, inconsistencies
or conflicts, where some action is to be taken. This document records all such issues which can be
tracked.
73 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
74 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.3.3.3. Change Requests
While the project work is being performed requests for direct or indirect charges to expand or
reduce project scope, to modify policies or procedures, to modify project cost or budget, or to
revise the project schedule are often identified and documented as requested changes.
Requests for a change can be, externally or internally initiated, and can be optional or
legacy/contractually mandated.
Elements of the project management plan that may be updated include, but are not limited
to:
Project documents that may be updated include, but are not limited to:
→ Requirements documentation,
→ Project logs (issues, assumptions, etc.),
→ Risk register, and
→ Stakeholder register.
75 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.4. Manage Project Knowledge
Manage Project Knowledge is the process of using existing knowledge and creating new knowledge to achieve
the project’s objective and contribute to organizational learning. The benefit of this process is to leverage the
organizational knowledge to produce improved outcome. This process is performed throughout the life cycle
of the project.
Factors Skills
▪ Organizational Process
Assets
4.4.1.3 Deliverables
Deliverables are tangible components completed to meet the project’s objectives.
▪ Active Listening
▪ Facilitation
▪ Leadership
77 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Networking
▪ Political awareness
To monitor project processes associated with initiating, planning, executing, and closing, the Monitor
and Control Project Work process is performed. Corrective or preventive actions are taken to control
the project performance. One of the aspect of project management performed throughout the project
is monitoring that includes collecting, measuring, and disseminating performance information, and
assessing measurements & trends to influence process improvements. Continuous monitoring
identifies any areas that can require special attention and gives the project management team insight
into the health of the project.
78 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
It can be composed of one or more subsidiary plans and other components and it can be
either summary level or detailed. Each of the subsidiary plans and components is
detailed to the extent required by the specific project. These subsidiary plans include:
→ Resource Calendar
→ Cost Baseline
→ Milestone List
→ Schedule Baseline
→ Quality Baseline
→ Risk Register
79 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.5.1.2. Project Document
The project documents that can be considered as inputs to this process includes but not limited to:
▪ Schedule Forecast
The schedule forecast provides variance against the planned finish dates and forecasted finish
dates for various tasks and overall project. Forecast is calculated from progress against the
schedule baseline and computed time estimate to complete (ETC) which is generally
expressed in terms of schedule variance (SV) and schedule performance index (SPI).
▪ Cost Forecast
The cost forecasts provide variances against the planned versus actual expenditures and
forecasted final costs. Cost forecast is calculated derived from progress against the cost
baseline and computed estimates to complete (ETC) which is generally expressed in terms of
cost variance (CV) and cost performance index (CPI). An estimate at completion (EAC) can be
compared to the budget at completion (BAC) to see if the project is still within tolerance ranges
or if a change request is required.
▪ Risk Register
▪ Issue Log
▪ Milestone List
As a part of the project management plan execution, the work performance data is analyzed
in context and integrated based on the relationship across areas. Work performance data gets
transformed into Work Performance Information and provides a basis for decisions making
associated with project.
The Monitor and Control Project Work process is influenced by enterprise environmental
factors that include:
80 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.5.1.5. Organizational Process Assets
The organizational process assets that can influence the Monitor and Control Project Work
process include:
Expert judgment is used by the project management team to interpret the information
provided by the monitor and control processes.
→ Regression analysis
→ Grouping methods
→ Causal analysis,
→ Root cause analysis
→ Forecasting methods (e.g., time series, scenario building, simulation, etc.)
→ Failure mode and effect analysis (FMEA)
→ Fault tree analysis (FTA)
→ Reserve analysis
→ Trend analysis
→ Earned value management
→ Variance analysis.
81 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.5.2.3. Project Management Information System
4.5.2.4. Meetings
Meetings may be face-to-face, virtual, formal, or informal. They may include project team
members, stakeholders, and others involved in or affected by the project.
As a result of variance analysis, change requests may be issued to expand, adjust, or reduce
project scope, product scope, or quality requirements and schedule or cost baselines. It may
include Corrective or Preventive actions or actions for defect repair.
Work performance reports are status reports, information notes, recommendations, and
updates to help project team and stakeholders to take decisions, actions, or awareness.
Source of work performance reports is the work performance information that is compiled in
the project documents.
Changes identified during the Monitor and Control Project Work process may affect the
overall project management plan. These changes, after being processed through the
appropriate change control process can lead to project management plan updates.
Schedule and cost forecasts, Work performance reports and Issue log are some of the
project documents that may be updated.
82 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.6. Perform Integrated Change Control
Perform Integrated change control is the process of reviewing all changes, approving changes and
managing changes to deliverables, project documents and project management plan; and
communicating the decision. The project management plan, the project scope statement and other
deliverables must be maintained carefully & continuously either by rejecting or approving changes so
approved changes can be incorporated into a revised baseline. Integrated Change Control process is
performed from project inception through completion. Since projects seldom run exactly according
to the project management plan, change control becomes necessary.
Project Management Plan components includes but are not limited to:
▪ Change Management Plan. The change management plan provides the direction for
managing the change control process and documents the roles and responsibilities of
the change control board
▪ Configuration Management Plan. This plan describes the configurable items and
identifies the items that will be recorded so that the product of the project remains
consistent and operable.
▪ Scope Baseline. It provides the project and the product definition.
▪ Schedule Baseline. It is used to assess the impact of the change in the project schedule.
▪ Cost Baseline. It is used to assess the impact of the change in project cost.
▪ Basis of Estimate. This indicates how the duration, costs and resource estimations were
derived and can be used to determine the impact of the change on time, budget and
resources.
▪ Requirement Traceability Matrix. This helps to determine the impact of the change on the
project scope.
▪ Risk Report. It is used to determine the overall risks impact on the project due the change.
It provides documentation about project performance against the project management plan.
Results from performance areas like control schedule, control cost, control quality, scope
verification, and procurement audits and their related forecasts assists the project team
management In determining future human resource requirements, recognition and rewards
and updates to HR Management plan.
Requests for direct or indirect charges to expand or reduce project scope, to modify policies or
procedures, to modify project cost or budget, or to revise the project schedule are often
identified and documented as requested changes. Requests for a change can be, externally or
internally initiated, and can be optional or legacy/contractually mandated.
Project management information system is one of the key enterprise environmental factor can
influence the Perform Integrated Change Control process. PMI®S may include the scheduling
software tool, a configuration management system, an information collection and
distribution system, or web interfaces to other online automated systems.
The organizational process assets that can influence the Perform Integrated Change Control
process include:
Stakeholders may be asked to provide their expertise and may be asked to sit on the change
control board (CCB). Such judgment and expertise are applied to any technical and
management details during this process and may be provided by various sources
4.5.2.2. Meetings
Meetings are usually referred to as change control meetings. When needed for the project, a
change control board (CCB) is responsible for meeting and reviewing the change requests and
approving, rejecting, or other disposition of those changes.
Manual or automated tools to manage the change requests and resulting decisions with
respect to change and/or configuration management. Types of tools that can be used is based
on the requirements of the project stakeholders considering the enterprise environment
and/or constraints.
Data analysis techniques that can be used for this process includes but not limited to:
▪ Alternative Analysis. This technique is used to assess the requested change and decide
which are accepted, rejected or needs to be modified before finally accepted.
4.5.2.5. Cost Benefit Analysis. This analysis helps to determine if the requested change is
worth its associated costs.
▪ Voting. Voting can take the form of unanimity, majority and plurality to decide whether to
accept, reject or defer the change request.
▪ Autocratic Decision Making. In this technique one individual take the responsibility for making
the decision for the entire team.
▪ Multi-criteria Decision Analysis. This technique uses a decision matrix to provide a systematic
analytical approach to evaluate the requested changes according to pre-defined criteria.
85 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
A change request that has been processed through the integrated change control process and
approved by change control board. Approved change requests are implemented through the
Direct and Manage Project Work process.
Any formally controlled project document may be changed as a result of this process. The most
common document which is updated through this process is change log.
▪ Change Log.
A comprehensive list of changes made during the project. This typically includes dates of the
change and impacts in terms of time, cost, and risk. Rejected change requests are also
documented in Change Log.
Key outcome of Integrated Change Control Process is updates to any subsidiary plans and
baselines subject to decision by change control board. Changes to baselines
should only show the changes from the current time forward. Past performance may not be
changed.
Project documents that may be updated as a result of the Perform Integrated Change Control
process include all documents specified as being subject to the project’s formal change
control process.
The project closure portion of the project management plan is performed through the Close Project or
Phase process. This process closes out the portion of the project scope and associated activities
applicable to a given phase in multi-phase projects. This process includes finalizing all activities
completed across all Project Management Process Groups to formally close the project or a project
phase, and transfer the completed or cancelled project as appropriate. The Close Project process also
establishes the procedures to coordinate activities needed to verify and document the project
deliverables, to coordinate and interact to formalize acceptance of those deliverables by the customer
86 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
or sponsor, and to investigate and document the reasons for actions taken if a project is terminated
before completion.
The project charter documents the project success criteria, approval requirements and who will sign
off on the project.
All components of the project management plan are input to this process.
Project documents that may be input to this process includes but not limited to:
▪ Assumption Log
▪ Issue Log
▪ Basis of estimate
▪ Change log
▪ Milestone list
▪ Others
Approved product specifications, delivery receipts, and work performance documents. Partial
or interim deliverables may also be included for phased or cancelled projects.
87 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
4.7.1.5. Organizational process assets
The organizational process assets that can influence the Close Project or Phase process are
Project or phase closure guidelines or requirements and Historical information and lessons
learned knowledge base.
Experts Judgment ensure the project or phase closure is performed to the appropriate
standards. Expertise is available from many sources like other project managers within the
organization and Project management office (PMO).
▪ Document Analysis
▪ Regression Analysis.
▪ Trend Analysis
▪ Variance Analysis
4.7.2.3. Meetings
Meetings may include project team members and other stakeholders, involved in or
affected by the project.
Formal statement that the terms of the contract have been met and hand over of the final
product, service or result that the project was authorized to produce.
Development of the index and Location of project documentation are included in the
Closure. The documents that are updated are, but not limited to:
→ Project Files: Project files are documentation resulting from the project’s activities like
project management plan, scope, cost, schedule and quality baselines, project calendars,
risk register, planned risk response actions, and risk impact.
→ Project Closure Documents: These documents consist of formal documentation indicating
88 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guideproject deliverables to
completion of the project and the transfer of the completed
others, such as Operations group. If the project was terminated prior to completion, the
formal documentation indicates why the project was terminated, and formalizes the
procedures for the transfer of the finished and unfinished deliverables of the cancelled
project to others.
→ Historical Information: Lessons learned are transferred to the lessons learned knowledge
base for use by future projects or phases. This can include information on issues and risks
as well as techniques that worked well that can be applied to future projects.
89 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
90 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5. Project Scope Management
Project Scope Management includes the processes required to ensure that the project includes all the work
required, and only the work required, to complete the project successfully. Managing the project scope is
primarily concerned with defining and controlling what is and is not included in the project. The PMBOK
®
Guide – 6th Edition.
Knowledge Monitoring
Area Initiating Planning Executing and Closing
Controlling
▪ Plan Scope Management. The process of creating a scope management plan that documents how the
project and product scope will be defined, validated and controlled.
▪ Collect Requirements. The process of determining, documenting and managing stakeholder needs and
requirements to meet project objective.
▪ Define Scope. The process of developing a detailed description of the project and product.
▪ Create WBS. The process of subdividing the project deliverables and the project work into smaller more
manageable components.
▪ Validate Scope. The process of formalizing acceptance of completed project deliverables.
▪ Control Scope. The process of monitoring the status of project and product scope and managing changes
to scope baseline.
Project’s overall success depends on proper definition and effective management of the project scope. Projects
required a careful balance of tools, data sources, methodologies, processes and procedures, and other factors
to ensure that the effort spent on scoping activities is adequate as per size, complexity, and importance of the
project. The project scope management plan describes:
It can be composed of one or more subsidiary plans and other components and it can be
either summary level or detailed. Each of the subsidiary plans and components is
detailed to the extent required by the specific project. These subsidiary plans include:
→ Resource Calendar
→ Cost Baseline
→ Milestone List
→ Schedule Baseline
→ Quality Baseline
→ Risk Register
92 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5.1.1.2. Project Charter
The project charter provides the project context needed to plan the scope management
processes. It provides the high-level project description and product characteristics from the
project statement of work.
The enterprise environmental factors that can influence the Plan Scope
Management process include:
→ Organization’s culture
→ Infrastructure
→ Personnel administration
→ Marketplace conditions
Historical information, lessons learned knowledge base and Policies & procedures are the
key elements of organizational process assets that may influence the Plan scope
management process.
Experts Judgment refers to input received from knowledgeable and experienced parties.
Expertise is available from many sources like other project managers within the organization
and Project management office (PMO). Expertise should be considered from individuals or
groups with specialized knowledge and trainings in the following topics:
The data analysis technique that can be used for this process includes but not limited to alternative
analysis, various ways of collecting requirements, elaborating product scope etc.
5.1.2.3. Meetings
Meetings may include project team members and other stakeholders, involved in or
affected by the project.
93 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5.1.3. Plan Scope Management – Outputs
5.1.3.1. Scope Management Plan
Scope Management Plan is a part of the project management plan. It provides guidance on
how project scope will be defined, documented, verified, managed and controlled. The
components of a project scope management plan include:
→ Product metrics that will be used and the rationale for using them
94 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Collect Requirements
The scope management plan provides clarity as to how project teams will determine which type of
requirements need to be collected for the project.
95 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Stakeholder Management Plan
▪ Stakeholder Register
The stakeholder register provides an exhaustive list of the key stakeholders who will provide
the requirements and it also captures their main expectations.
▪ Assumption Log
▪ Lessons Learned Register
5.2.1.5. Agreements
▪ Business Analysis
▪ Requirements elicitation
▪ Requirement Analysis
▪ Diagraming techniques
▪ Conflict Management
Data gathering techniques that can be used for this process includes but not limited to:
▪ Brainstorming
▪ Interviews
▪ Focus Groups
96 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide and subject matter
An elicitation technique that brings together prequalified stakeholders
experts to learn about their expectations and attitudes about a proposed product, service, or
result.
▪ Voting
▪ Autocratic Decision Making
▪ Multi-Criteria Decision Analysis
Data representation techniques that can be used for this process include but not limited to:
▪ Affinity Diagram. Affinity diagram allows large number of ideas to be classified into groups for
review and analysis.
▪ Mind Mapping. Mind mapping consolidates the ideas collected through individual interviews and
brainstorming into a single map to achieve commonality.
A visual depiction of the product scope showing a business system (process, equipment,
computer system, etc.), and how people and other systems (actors) interact with it.
5.2.2.8. Prototypes
A method of obtaining early feedback on requirements by providing a working model of the expected
product before actually building it.
A description of how individual requirements meet the business need for the project.
Requirements can be grouped into classifications for further refinement. These includes:
▪ Business Requirements.
▪ Stakeholder Requirements
▪ Solution Requirements
▪ Project Requirements
▪ Quality Requirements
A grid that links product requirements from their origin to the deliverables that satisfy them.
The implementation of a requirements traceability matrix helps ensure that each requirement
adds business value by linking it to the business and project objectives.
Define Scope process provides a detailed project scope statement which is critical to project success. In
this process, the project scope is defined with greater details and with more specific Information
about the project. Stakeholder needs & expectations are detailed in this document. The assumptions
and constraints are analyzed and detailed in this process.
98 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Define Scope
The Project Charter provides a high level project descriptions, product charecteristics and
approval requirements.
The component Scope management plan of the project management plan describes how the
project scope will be defined, validated and controlled. Other components of the project
management plan may also be used in this process.
Following is a list of project documents that can be used in this process as input.
▪ Assumption Log
▪ Requirements Documentation
▪ Risk Register
The Enterprise environmental factors that can influence the Define Scope process may
include:
▪ Organization Culture
▪ Infrastructure
▪ Market place condition
One of the data analysis technique used for this process is alternatives analysis to be used to evaluate
ways to meet requirements and objectives in the charter.
The multi-criteria decision analysis is used but not limited to in this process to apply a systematic
analytical approach to define the project and product scope.
An example of interpersonal and team skill is facilitation, which is used in workshops and working
sessions with key stakeholders who have a variety of expectation or expertise.
The project scope statement is a detailed description of project work and deliverables along
with project boundaries. It provides a common understanding of the project scope among all
stakeholders and describes the project’s objectives in detail. It helps in further detailed
planning, guides during execution, and creating scope baseline. The detailed project scope
statement Includes:
▪ Product Scope Description. Progressively elaborates the characteristics of the product,
100 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
service or result.
▪ Deliverables. Any unique and verifiable product, result or capability to perform a service
required to be complete the project, phase or process.
▪ Project Exclusions. Identifies, what is excluded from the project. Explicitly documents the
“Out-of-Scope” items to manage the stakeholders expectations.
▪ Acceptance Criteria. A set of conditions that needs to be met before the deliverable is
accepted.
▪ Stakeholder register
▪ Requirements documentation
▪ Requirements traceability matrix
The Work Breakdown Structure (WBS) is a deliverable oriented hierarchical decomposition of the
work to be performed by the project team to create the deliverables. The WBS subdivides the project
work into smaller, more manageable pieces of work. Each tower level of the WBS represents further
detailed breakup of the project work. The lowest level nodes are called work packages, which can be
scheduled, estimated, monitored, and controlled by an individual or a team.
Create WBS
The project management plan components include but not limited to Scope management plan.
▪ Scope Management Plan
101 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
The scope management plan specifies how to create the WBS from the detailed project
scope statement and how the WBS will be maintained and approved.
Examples of project documents that can be considered as inputs to this process are:
Breaking down project deliverables into smatter, more manageable components is called
decomposition. Breakdown should be done until the cost and schedule for the work can be
reliably estimated. The Level of detail for work packages will depend on the size and
complexity of the project.
102 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Scope Baseline is a component of the project management plan which provides the final list of all
deliverables detailed in WBS and WBS dictionary. Any changes to scope beyond this point can be done
through formal change control process only. Scope baseline includes:
▪ Project Scope Statement
▪ WBS
▪ Work Package
▪ Planning Package
▪ WBS Dictionary
The Project documents that may be updated as a result of this process are:
▪ Assumption Logs
▪ Requirements Documents
103 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Sample WBS Dictionary Format
Validate Scope is the process of verification of completed project scope and deliverables by
stakeholders. This includes performing review and getting formal acceptance of the deliverable from
stakeholder.
Validate Scope is different from Quality Control process as scope validation is concerned with
acceptance of the deliverables and work as per project scope while Quality Control process focuses
on meeting the quality requirements specified for the deliverables. Usually quality control is
performed before scope verification, but sometimes these two processes can be performed parallelly.
104 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Validate Scope
The components of the project management plan used in this process includes but not limited to:
The project documents that can be considered as input to this process includes but are not limited
to:
Verified deliverables are project deliverables that are completed and checked for correctness
through the Control Quality process.
105 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5.5.1.4 Work Performance Data
Work performance data is the lowest level of detail coming from raw observations and
measurements of activities while carrying out the project work. Raw data is gathered
throughout the execution phase and passed to the controlling processes of each process area
for detailed analysis. Work Performance Data includes work completed, KPIs, start/finish
dates of activities, number of defects, actual duration and cost etc.
Work performance data is analyzed in context and integrated based on the relationship across
areas and gets transformed into Work Performance Information which provides a basis for
decisions making associated with project.
106 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5.5.3.4. Project document updates
Project documents that may be updated as a result of the Validate Scope process include any
documents that define the product or report status on product completion.
Control Scope process controls the factors which induce changes in project scope. It also controls the
impact of those changes on project scope. Control Scope is associated with Integrated Change Control
process. This process makes sure that all requested changes and recommended corrective actions are
processed through the Integrated Change Control process. This process also manages the actual
changes when they occur in coordination with other control processes. It controls scope creeps, which
is one of the biggest reasons of project failure.
Control Scope
The following information from the project management plan is used to control scope:
107 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5.6.1.2. Project Documents.
A grid that links product requirements from their origin to the deliverables that satisfy them.
The implementation of a requirements traceability matrix helps ensure that each requirement
adds business value by linking it to the business and project objectives.
Work performance data is the lowest level of detail coming from raw observations and
measurements of activities while carrying out the project work. Raw data is gathered
throughout the execution phase and passed to the controlling processes of each process area
for detailed analysis. Work Performance Data includes work completed, KPIs, start/finish
dates of activities, number of defects, actual duration and cost etc.
The organizational process assets that can influence the Control Scope process are:
Data analysis techniques that can be used in this process includes but are not limited to:
▪ Variance Analysis
Valiance analysis provides project performance measurements to assess the variation of
actual values against the planned values. It helps in determining the quantifiable impact
of change.
▪ Trend Analysis
Trend analysis examines project’s performance over time to determine if the performance is
improving or deteriorating.
108 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
5.6.3. Control Scope – Outputs
5.6.3.1. Work performance information
Work performance data is analyzed in context and integrated based on the relationship across
areas and gets transformed into Work Performance Information which provides a basis for
decisions making associated with project.
▪ Requirements Documentation
109 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
110 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6. Project Schedule Management
Project Schedule Management includes the processes required to ensure timely completion of the
project. The following are the list of processes under this knowledge area.
Knowledge Monitoring
Area Initiating Planning Executing and Closing
Controlling
▪ Plan Schedule Management. The process of establishing the policies, procedures and documentation
of planning, developing, managing, executing, and controlling the project schedule.
▪ Define Activities. The process of identifying & documenting the specific actions to be performed to
produce the project’s deliverables.
▪ Sequence Activities. The process of identifying and documenting the relationship amongst the project
activities.
▪ Estimate Activity Duration. The process of estimating the number of work period needed to complete
the individual activity with estimated resource.
▪ Develop Schedule. The process of analyzing activity sequences, durations, resource requirements, and
schedule constraints to create the project schedule model for project execution, monitoring and
controlling.
▪ Control Schedule. The process of monitoring the status of the project to update the project schedule
and manage changes to the schedule baseline.
111 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.1 Plan Schedule Management
Plan Schedule management is the process of establishing the policies, procedures and documentation for
developing, managing, executing and controlling the project schedule. This process provides a guidance and
direction on how the project schedule will be managed throughout the life cycle of the project.
→ Resource Calendar
→ Cost Baseline
→ Milestone List
→ Quality Baseline
→ Risk Register
6.1.1.2. Project Charter
Project Charter provides inputs in developing schedule with regards to key milestones that
will have significant impact on the management of project schedule.
112 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.1.1.4. Organizational Process Assets
Organizational Process Assets provides details of scheduling tools that can be used,
historical information and processes that will be used to develop and manage project
schedule.
The Data Analysis technique used in this process includes but not limited to alternative analysis.
Alternative analysis can include which scheduling method to be used, how to combine various
methods, to what level the schedule should be detailed out, the duration of rolling wave planning etc.
6.1.2.3. Meetings
Project team may hold planning meetings to develop the schedule management plan.
Participants at these meetings may include project manager, project sponsor, selected team
members, selected stakeholders and anyone who can contribute and responsible in planning
and execution.
113 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.1.3. Plan Schedule Management – Outputs
6.1.3.1. Schedule Management Plan
Schedule Management Plan sets the guidelines and defines the necessary steps to be taken to
develop, monitor and control the project schedule. Schedule management plan can establish the
following:
▪ Project Schedule Model. The scheduling methodology and the scheduling tools to be
used in developing project schedule.
▪ Level of accuracy. The acceptable range used to determine realistic activity duration
estimates.
▪ Units of Measures. Each unit of measurements such as staff hours, staff days, or weeks
are defined for each of the resources.
▪ Control Thresholds. This parameter determines the agreed upon variance allowed
between planned and actual data before any corrective or preventive action is taken.
Define Activities process identifies and documents the activities that needs to be performed by
decomposing the work packages (i.e. lowest level of WBS). These activities provide a basis for
estimating, scheduling, executing, and monitoring & controlling the project work.
Define Activities
114 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.2.1 Define Activities – Inputs
6.2.1.3. Project Management Plan.
The components of the project management plan which can be considered as input to this process
includes but not limited to:
With this planning technique, schedule activities can exist at various levels of detail in the
project’s Life cycle. In early stage of planning, when information is less defined, activities
might be listed at the milestone level.
→ Activity identifier
→ Activity codes
→ Activity description
→ Predecessor activities
→ Successor activities
→ Logical re1ationships
→ Leads and lags
→ Resource requirements
→ Imposed dates
→ Constraints
→ Assumptions
→ Person responsible for executing the work
116 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.2.3.4 Change Request
Once the project is baselined, the progressive elaboration and rolling wave planning may reveal
work that was not identified and defined and a part of the baseline. This may result a change
request.
Any change to the project management plan shall have to go through the change control process.
Components that may get changed as a result of this process:
▪ Schedule Baseline
▪ Cost Baseline
This is the process of identifying and documenting the logical relationships among schedule activities. This
logical relationship represents inter-activity dependencies.
Logically sequencing of activities can be represented by precedence relationships like Finish to start,
start to finish, start to start and finish to finish. Leads and lags are introduced for preparing a realistic
and achievable project schedule. Project management software provides the facilities of defining and
managing dependencies, led and lag while preparing the project schedule.
Sequence Activities
117 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.3.1 Sequence Activities – Inputs
The Project documents that is used as input to this process includes but not limited to:
▪ Activity List
▪ Activity attributes
Activity attributes for the activities may include:
→ Activity identifier
→ Activity codes
→ Activity description
→ Predecessor activities
→ Successor activities
→ Logical re1ationships
→ Leads and lags
→ Resource requirements
→ Imposed dates
→ Constraints
→ Assumptions
▪ Milestone List
Milestone list contains all milestones along with the information that the particular milestone
is mandatory as contractual requirement or optional as per project requirements or historical
information. The milestone list is a part of the project management plan and used for
scheduling purpose.
118 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.3.1.5. Organizational Process Assets
Organization process assets containing activity planning related policies, procedures and
guidelines are considered in developing the activity definitions. Lessons learned knowledge
base with historical information regarding activities, lists of previous similar projects may be
used when sequencing project activities.
→ Finish to Start: The start of the successor activity depends upon completion of the
predecessor activity.
→ Finish to Finish: The completion of the successor activity depends upon the
completion of the predecessor activity.
→ Start to Start: The start of the successor activity depends upon the start of the
predecessor activity.
→ Start to Finish: The completion of the successor activity depends upon the start of
the predecessor activity.
In PDM, finish to start is the most commonly used type of precedence relationship. Start to
finish relationship is rarely used.
119 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
foundation before erecting the structure. Mandatory dependencies are also
referred as hard logic.
→ Discretionary dependencies: Discretionary dependencies are usually defined based on
knowledge of best practices and standard procedures for the specific application area.
These relationships are called soft Logic, preferred logic or preferential logic. These
relationships are decided by project management team based on previous experience
on a similar successful project.
→ External dependencies: External dependencies involve a relationship between project
activities and non-project activities or external entitles. For example, the testing activity
in a project may dependent on delivery of specific hardware from an external source.
Historical data of similar previous projects provides inputs for defining this dependency.
→ Activity attributes
→ Activity List
→ Project logs (issues, assumptions, etc.), and
→ Milestone List
120 | P a g
e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Estimate activity duration is the process of estimating the number of work periods needed to
complete individual activities with estimated resource. The Estimating Activity Duration process uses
information like scope of work, required resource types, number of resources, resource calendars and
resource availabilities for determining work periods needed for each activity. These estimates are
progressively elaborated. Factors that may impact this process and should be taken into consideration
are:
▪ Law of diminishing Returns
▪ Number of resources
▪ Advances in technology
▪ Motivation of staff
The components of the project management plan that may be considered as input to this process are:
▪ Activity List
A comprehensive list including all activities that are required to be performed for each work
121 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide and a description of
package in the project. This activity list includes the activity identifier
work for each schedule activity with sufficient detail to ensure that project team understands
what work is required to be completed. The activity list is used in schedule network diagram
as part of project management plan.
▪ Activity attributes
Activity attributes provide primary data for identifying and estimating the resources required
for each activity in the activity list. Activity attributes for the activities may include:
→ Activity identifier
→ Activity codes
→ Activity description
→ Predecessor activities
→ Successor activities
→ Logical re1ationships
→ Leads and lags
→ Resource requirements
→ Imposed dates
→ Constraints
→ Assumptions
→ Person responsible for executing the work
▪ Resource calendars
Availability of people, equipment, and material, their location and available quantities are
considered during the process of activity resource estimation.
▪ Risk Register
Risk events may impact resource selection and availability. Updates to the risk register are
included with project documents updates.
123 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
An activity duration estimate can be determined by using an average of the three estimated
durations, i.e. optimistic, pessimistic and most likely. That average will often provide a more
accurate duration estimate than the single point (most likely) estimate.
Bottom estimation technique for project duration or cost is considered the most accurate as the
estimation is done at the lowest level of the WBS and then it is aggregated to achieve the project
duration. When activity duration cannot be estimated with a relative degree of confidence, it is
further decomposed for more details.
The data analysis techniques that can be used for this purpose may be :
▪ Alternative Analysis
▪ Reserve Analysis. Reserve analysis is used to determine how much amount is needed for
contingency and management reserve. Contingency Reserves are amount included in the
schedule baseline, which are allocated for identified risks. It is also known as reserve for “Known-
unknown” . This could be a percentage of the project duration or a fixed number of days.
Management Reserves on the other hand are the specified amount of money held with
management and is associated for un-identified risks or “unknown-unknown” . Management
Reserve is not included in schedule baseline.
124 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.4.3.8. Meetings
The project team may hold meetings to estimate activity duration. When using agile approach, it is
necessary to conduct sprint or iteration planning meetings to discuss the product backlog,
prioritization and decide upon the items on which the team will start working on the next iteration.
Basis of estimates provides a clear understanding on the basis the estimation was carried out. This
could be very high level or granular, but it must be documented.
→ Activity attributes,
→ Project logs (issues, assumptions, etc.), and
Develop Schedule is the process of determining planned start and finish dates for project activities.
Schedule development is an iterative process which requires review & refinement based on duration
and resource estimates. An approved project schedule becomes baseline against which project
progress is monitored.
Develop Schedule process continues throughout the project as re-planning may be needed due to
change requests, or risk situation or upon identification of new risks.
125 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Develop Schedule
The components of the project management plan used as input to this process are :
▪ Scope Baseline
Project documents that can be considered as inputs for this process includes but not limited to:
▪ Activity List
A comprehensive list including all activities that are required to be performed for each work
package in the project are used as a key input in this process as for each activity in the list,
schedule date will be identified in this process.
▪ Activity attributes
Activity attributes provide additional data for developing the schedule for each activity in
the activity list. Activity attributes for the activities may include:
→ Activity identifier
126 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Activity codes
→ Activity description
→ Predecessor activities
→ Successor activities
→ Logical re1ationships
→ Leads and lags
→ Resource requirements
→ Imposed dates
→ Constraints
→ Assumptions
→ Person responsible for executing the work
▪ Resource requirements
Resource requirement and their availability are used as an input as they may have a significant
impact on overall schedule.
▪ Resource calendars
Resource calendar is used along with project calendar. The resource calendar provides
Information on working days or shifts with working and non-working time or the resources.
▪ Duration estimates
Activity duration estimates provide the likely number of work periods that will be required to
complete a schedule activity.
▪ Risk Register
Risk events may impact project schedule. Due to certain risks, the team may decide to carry out
certain activities at a different date or time. Updates to the risk register are included with
project documents updates.
127 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.6.1.3. Agreements
Project has suppliers and con tractors, who may have input to be considered in the project schedule.
This process calculates the early start, early finish, late start and late finish dates in the project
schedule. This analysis also provides scheduled start and finish dates for the uncompleted
project activities.
→ Forward pass analysis to calculate early start and early finish dates
128 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Backward pass analysts to calculate late start and late finish dates
→ Analysis of float to identify critical path
Calculated early start and finish dates, and late start and finish dates may or may not be the
same on any network path since total float, may be positive, negative, or zero.
▪ Resource Leveling
▪ Resource Smoothing
6.6.2.5. Data Analysis
▪ What-If Scenario Analysis. In this technique various scenarios are evaluated in order to predict
their effect positive or negative on the project schedule.
▪ Simulation. Simulation is a technique where project risks and other sources of uncertainties are
evaluated to assess its impact on the project schedule. Monte-Carlo Analysis is one of the most
used simulation technique.
110 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
The leads or Lags are adjusted during schedule network analysisGuide
to develop a viable project
schedule.
A lead allows an earlier start of the successor activity. This helps in fast tracking in finish-to-
start relationship wherein successor activity starts before the completion of predecessor
activity.
A lag creates a delay in the successor activity. In finish-to-start relationship, the successor
does not start immediately at completion of predecessor activity. Lag is the delay period in
starting the successor activity after completion of predecessor activity.
Agile Release planning provide a high-level summary time line of release schedule based on the
product roadmap and product vision. This also helps the product owner to determine how much can
be produced and how long it will take to release a marketable product. For Agile based project
release planning and iteration planning are mode of determining the feature wise project schedule.
111 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.6.3.1. Schedule baseline
A schedule baseline is a specific version of the project schedule which is accepted and
approved by the project management team as the schedule that can be changed only following
through change control process. Baseline start and baseline finish dates are compared with
actual dates to determine if the project is on schedule or there is any variance.
1) Project schedule network diagrams: These diagrams show the schedule activity dates,
project network logic and the critical path. The activity-on-node diagram
or a time scaled schedule network diagram is used for representing network diagram.
2) Bar Charts: These charts contain bars representing activities, show activity start and end
dates, as well as expected durations. At broader level, more comprehensive summary
activity, also called as hammock activity, is used between milestones or across multiple
interdependent work packages.
3) Milestone Charts: These charts contain bar representing the scheduled start or
completion of major deliverables and key external interfaces.
Modification to project scope or project schedule may result in change requests in scope baseline or
components of project management plan. Changes are processed through integrated change control
and corrective actions can be undertaken to reduce negative schedule variance.
112 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
Since this process can be followed multiple times in the project, anGuide
update to project schedule
baseline and schedule management plan may get updated if needed.
Control Schedule process is a part of the Monitor & Control process group. This process helps
determining the current status of the project schedule, influencing the factors, by taking corrective or
preventive actions, that causes deviations from project schedule and also determining that the project
schedule has changed. The actual project progress is updated and changes to the schedule baseline
are managed in this process to ensure timely completion of the project activities and project.
Control Schedule
o Project schedule network diagrams: These diagrams show the schedule activity
dates, project network logic and the critical path. The activity-on- node diagram
or a time scaled schedule network diagram is used for representing network
diagram.
o Bar Charts: These charts contain bars representing activities, show activity start
and end dates, as well as expected durations. At broader level, more
comprehensive summary activity, also called as hammock activity, is used
between milestones or across multiple interdependent work packages.
o Milestone Charts: These charts contain bar representing the scheduled start or
completion of major deliverables and key external interfaces.
▪ Project Calendars: A project calendar may be required for some activities to calculate the
schedule forecast.
▪ Schedule Data: Supporting data for the project schedule that includes alternative schedule, best-
case or worst-case scenario, resource histograms showing resource requirements at time periods
etc. may get updated in this process.
▪ Earned Value Analysis: The performance measurement SV (Schedule Variance) & SPI (Schedule
Performance Index) are used as a part of EVM analysis.
▪ Iteration burndown chart: For agile projects this tool is used to track the work remaining to be
completed in the iteration backlog. It is used to calculate the variance with respect to ideal
burndown.
Earned value management is the key technique used in performance review. Schedule
performance measurements such as schedule variance (SV) and schedule performance
index (SPI), are used to assess the magnitude of variation to the original schedule baseline.
The total float and early finish variances are also essential planning components to
evaluate project time performance. Important aspects of schedule control include
determining the cause and degree of variance relative to the schedule baseline, estimating
the implications of those variances for future work to completion, and deciding whether
corrective or preventive action is required.
▪ Trend Analysis
▪ Variance Analysis
▪ What-if scenario Analysis
115 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
where shared or critical resources are available at certain times or in limited quantities.
Resource usage is optimized using resource leveling that is performed after identlft1ng the
critical path and it may force changes in critical path due to constraints on availability of
critical resources.
A lead allows an earlier start of the successor activity. This helps in fast tracking in finish-to-
start relationship wherein successor activity starts before the completion of predecessor
activity.
A lag creates a delay in the successor activity. In finish-to-start relationship, the successor
does not start immediately at completion of predecessor activity. Lag is the delay period in
starting the successor activity after completion of predecessor activity.
116 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
6.7.3.2. Schedule Forecast
Schedule forecasts are predictions of conditions and events in the project’s future based on the work
performance information comparing it with the schedule baseline. The EVM parameters such as SV and
SPI can be used to indicate the project’s past performance and expected future performance.
→ Project Schedule
→ Schedule Data
→ Risk registers
117 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
118 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
7. Project Cost Management
Project Cost Management includes the processes involved in planning, estimating, budgeting, financing,
funding, managing, and controlling costs so that the project can be completed within the approved budget.
Knowledge Monitoring
Area Initiating Planning Executing and Closing
Controlling
▪ Plan Cost Management. The process of determining how the project costs will be estimated,
budgeted, managed, monitored and controlled.
▪ Estimate Cost. The process of estimating the cost of the resources needed to complete the work.
▪ Determine Budget. The process of aggregating the estimated costs of authorities and work packages
to establish an authorized cost baseline for the project
▪ Control Cost. The process of monitoring the status of the project vis-à-vis the actual spend and
applying corrective and preventive actions to reduce the negative cost variance.
Plan Cost Management is the process of defining how the project cost will be estimated, budgeted, managed,
monitored and controlled. The key benefit of this process, that it provides guideline and direction on how the
project cost will be managed throughout the lifecycle of the project.
119 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
The project charter provides the information on high level pre-approved project budget. It also
provides the project approval requirement which may influence the management of project costs.
▪ Schedule Management Plan. The schedule management plan provides processes and
controls that will impact the estimation and management of project cost.
▪ Risk Management Plan. The Risk management plan provides processes and controls
that may impact the estimation and management of project cost.
7.1.2.3. Meetings
While developing the cost management plan, project manager, project team and stakeholders may
need to conduct meetings to discuss cost management plan.
Cost estimates are refined and adjusted during the project lifecycle to reflect additional details
available. Wherever required, guidelines are generated for when such refinements are made and for
what degree of accuracy is expected. Resource’s for which costs are estimated Include infrastructure,
tabor, materials, equipment etc. and special categories like inflation, contingency etc. If the
performing organization does not have formally trained project cost estimators, then the project team
will need to supply both the resources and the expertise to perform project cost estimating activities.
Estimate Cost
The cost management plan defines how project costs will be managed and controlled. It
includes the method used and the level of accuracy required to estimate activity cost.
▪ Quality Management Plan
The Quality management plan describes the activities and resources necessary for the
project to meet the quality objective of the project.
▪ Scope Baseline
Scope baseline is comprised of project scope statement, WBS and WBS dictionary. The
constraints like project budget, delivery dates, availability of human and material resources,
122 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guidestatement. Relationship
assumptions limiting factors etc. are derived from the Project scope
and dependencies between all project components as described in WBS is used for building
effective and accurate cost estimates. WBS dictionary provides clarity among deliverables to
facilitate accurate estimation.
The project documents used as input to this process includes but not limited to:
▪ Project Schedule
Project Schedule includes activity resource and duration estimations, provides the most
important inputs for cost estimation - quality, quantity and availability of human and material
resources. All costs including charges, interest rates, agreements, cost variations, overhead
costs are derived out of the Project Schedule.
▪ Risk Register
All risks are considered in developing alternative cost estimates. Risks, either threats or
opportunities are studied and expected variations are planned for.
▪ Lessons Learned Register
▪ Resource Requirements
An activity cost estimate can be determined by using an average of the three estimated cost,
i.e. optimistic, pessimistic and most likely. That average will often provide a more accurate
cost estimate than the single point (most likely) estimate.
▪ Alternative Analysis.
▪ Reserve Analysis
All identified risks and their impact is considered while estimating the cost. Some additional
cost is added to project cost estimates, which is known as contingency reserve, cost reserve
or buffer. The contingency reserve can be a percentage of the estimated cost, a fixed cost, or
124 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide and team gets more
developed by quantitative risk analysis. As estimation process proceeds
detailed information, the contingency reserve can be used completely or partially, or can later
be reducedor eliminated.
▪ Cost of Quality
Cost of Quality refers to the investment needed for conformance vs the cost of non-conformance. In
other words, the cost to fix bug vs investment to ensure reduced bugs. Cost of Quality could be
important factor for project cost and should be considered while estimation.
The project documents which gets updated as a result of this process includes but not limited to:
▪ Risk Register
▪ Assumption Log
▪ Lessons Learned Register
125 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
7.3. Determine Budget
Determine budget involves aggregating the estimated cost of individual activities or work packages to
establish a total cost baseline for measuring project performance. The project scope statement may
provide the summary budget. However, activity or work package cost estimates are prepared prior to the
detailed budget requests and work authorization.
Determine Budget
The components of the project management plan which could be used as input to this process
includes but not limited to:
The resource management plan provides information on rates, estimation of travel costs, and
other costs that are necessary to consider for project costing.
▪ Scope Baseline
Scope baseline is comprised of project scope statement, WBS and WBS dictionary. The
constraints like project budget, delivery dates, availability of human and material resources,
126 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guidestatement. Relationship
assumptions limiting factors etc. are derived from the Project scope
and dependencies between all project components as described in WBS is used for building
effective and accurate cost estimates. WBS dictionary provides clarity among deliverables to
facilitate accurate estimation.
The project documents that can be input to this process includes but not limited to:
▪ Cost Estimates
An activity cost estimate is a quantitative assessment of the likely costs of the resources
required to complete activities. This type of estimate can be presented in summary form or in
detail. Costs are estimated for all resources, human and material and may consider inflation,
contingency reserves etc.
▪ Basis of Estimate
Details validating the derivation of the cost estimates are provided. Supporting details for
justification of cost estimate can include description of activity’s scope of work,
documentation of how it was estimated, what tools were used and what assumptions &
constraints have been considered.
▪ Project Schedule
Project Schedule includes activity resource and duration estimations, provides the inputs for
determining budget - quality, quantity and availability of human and material resources. All
costs including charges, interest rates, agreements, cost variations, overhead costs are
derived out of the Project Schedule.
▪ Risk Register
Risk events may impact project budget. All risks are considered in developing alternative cost
estimates and the cost of response should be aggregated to make a part of the project budget.
The business documents that can be considered as input includes but not limited to:
▪ Business Case.
▪ Benefits management plan
127 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
7.3.1.4. Agreements
Agreements with external vendors regarding what product, service or results have been
purchased – and their costs are used in developing the budget.
▪ Reserve Analysis
Reserve or management contingency allowance are used to deal with uncertainty or “known
unknowns”. The reserve is added to project budget but not distributed to project team as
budget.
Financing refers to acquiring funding for the project. It is common for long term infrastructure,
industrial and public service projects to seek external sources of funds. If the project is funded
externally then the funding entity may have terms and conditions which needs to be taken into
consideration.
Control cost is the process of monitoring the status of the project to update the project cost and managing
changes to the cost baseline. The cost baseline is maintained throughout the project.
129 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Control Cost
The components of the project management plan which can be included as input are :
130 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
7.4.2.2. Data Analysis
Examples of data analysis techniques used during control cost process includes but not limited to :
▪ Variance Analysis
Variance analysis refers to analyzing the variance parameters of EVM such as cost variance (CV=PV-
AC), Schedule Variance (SV=PV-EV) and variance at completion (VAC=BAC-EAC).
An important aspect of project cost control is to determine the cause and degree of the variance
relative to the cost baseline and deciding if a corrective or preventive action is required. Further
analysis can be performed to determine the cause and degree of the schedule variance and deciding
if a corrective or preventive action is required.
Earned value analysis combines scope, schedule, and resource measurements to assess
project performance and progress. It compares the cumulative value of scope, time and cost
baseline to form the performance baseline to assess and measure project performance and
progress. The earned value technique involves developing these key values to each activity,
work package or control account:
131 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Forecasting
The earned value technique parameters of BAC (Budget At Completion), actual cost (AC)
to date, and the cumulative CPI (Cost Performance Index) efficiency indicator are used to
calculate ETC (Estimate to complete) and EAC (Estimate at completion) for a schedule
activity, work package, control account, or other W8S component.
▪ Trend Analysis
Trend analysis is performed on the project with data collected over time to determine if the
project performance is improving or deteriorating.
▪ Reserve Analysis
The purpose of reserve analysis is to monitor the status of the contingency and the management
reserves for the project to determine if these reserves are still needed or additional reserves need
to be requested. As the project progresses, these reserves may have been used to cover the risk
responses.
132 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
occur, the unused contingency reserves may be removed from the project budget to free up
resources for other projects or operations.
133 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
134 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
8. Project Quality Management
Project Quality Management includes the processes and activities of the performing organization that
determine quality policies, objectives, and responsibilities so that the project will satisfy the needs for
which it was undertaken.
Knowledge Monitoring
Area Initiating Planning Executing & Closing
Controlling
▪ Plan Quality Management. The process of identifying quality requirements and standards for the
project and its deliverables and document how the project will meet the quality requirements and
standards.
▪ Manage Quality. The process of translating the quality management plan into executable quality
activities that incorporates the organization’s quality policies into the project.
▪ Control Quality. The process of monitoring and recording the result of quality management activities
to assess performance and ensure the deliverables are correct, complete and meet customer’s
expectation.
It is one of the key processes that identifies quality standards that are relevant to the project and steps to satisfy
them. It is performed in parallel to other planning processes and is a key determinant in the formulation of
other subsidiary planning processes. There are several quality planning techniques that are used in different
application areas, some of which are discussed here.
135 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
136 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Plan Quality Management
The charter provides high level project description, product characteristics, approval requirements,
measurable project objectives and success criteria. All of these influences the quality management of
the project.
The components of the project management plan that can be considered as input to this process
includes but not limited to:
▪ Requirements Management Plan. Provides information to identify, analyze and manage the
project requirements which will be needed for quality management plan and quality metrics for
reference.
▪ Risk Management Plan. The information in Risk management plan and quality management plan
work together to successfully deliver the product and project success.
▪ Stakeholder Engagement Plan.
▪ Scope Baseline
137 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
8.1.1.3. Project Documents
The project documents that can be considered as input to this process includes but not limited to:
▪ Stakeholder Register
It provides a list of stakeholders having a particular interest in, or having an impact on,
quality.
▪ Risk Register
It contains information on threats and opportunities that may impact quality
requirements.
▪ Requirements Documentation
Requirements documentation captures the requirements that the project must meet
pertaining to stakeholder expectations. The components of the requirements documentation
include, project (including product) and quality requirements. The requirements are used by
the project team to help plan how quality control will be implemented on the project.
▪ Requirements Traceability Matrix
▪ Assumption Log
Expertise should be considered from individuals or groups having specialized knowledge and trainings
on the following topics:
▪ Quality Assurance
▪ Quality Control
▪ Quality Measurements
138 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Quality Improvements
▪ Quality Systems
The Data gathering techniques that can be used includes but not limited to:
▪ Benchmarking.
Benchmarks involving actual or planned project practices within or outside the organization in the
same application area or outside are used for quality planning and performance measurement
▪ Brainstorming
▪ Interviews
The Data Analysis techniques used in this process includes but not limited to:
The data representation techniques that can be used in this process includes but not limited to :
▪ Flowcharts.
▪ Logical Data Model
▪ Matrix Diagram
▪ Mind Mapping
During the planning phase the project manager and project team determine how to test the product,
deliverable, or service to meet stakeholder’s need and expectation, as well as how to meet the goal of
performance and reliability. Some of the example of industry standard tests are alpha test, beta test,
field test etc.
139 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
8.1.2.6. Meetings
Project teams that may include project manager, project sponsor, respective project team
members, stakeholders or anyone with responsibility for Project Quality Management
activities, may hold planning meetings to develop the quality management plan.
The quality management plan is brought in early in the project life cycle where initial
decisions, designs and tests are verified by an independent peer group that may reduce
project costs and schedule overruns. This plan is built based on Individual project
requirements.
The components of the project management plan which may be updated as a result of this process
includes but not limited to:
140 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Manage Quality
The components of the project management plan that may be used as input:
The project documents that may be considered as input to this process includes but not limited to:
▪ Quality Metrics
A metric describes what project or product is and how the quality control process measures
it. The quality metrics provide the attributes that should be measured and the allowable
variations.
▪ Quality Control Measurements.
Quality control measurements are the outputs of quality control activities that are fed back
to the QA process for re-evaluating and analyzing the quality standards and processes of the
organization.
▪ Risk Reports
▪ Lessons Learned Register
141 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
The Organizational process assets that can influence this processGuide
are:
▪ Organization’s quality management system
▪ Quality Templates
▪ Results from previous audits
▪ Lessons learned repository with information from similar projects.
Data gathering techniques that can be used for this process includes but not limited to is checklist. A
checklist is a structured tool, used to verify that a set of required steps has been performed or
checked, if a requirement has been satisfied.
The data analysis techniques used in this process includes but not limited to:
▪ Alternative Analysis . This technique is used to evaluate which quality options are approaches are
appropriate to use.
▪ Document Analysis. This is primarily used to evaluate and identify the processes which are faulty
using various reports such as quality reports, test reports, variance analysis reports, performance
reports.
▪ Process Analysis. The process analysis identifies opportunity for process improvement.
The process Improvement plan enables process analysis for continuous Improvement in
technical and organizational areas. Process analysis Includes root cause analysis to
identify the cause, effect and provide solution to a problem.
▪ Root Cause Analysis. Root cause analysis is aa analytical technique to determine the underlying
reasons or causes that are responsible for variance, causes or risks.
The decision-making technique that may be used in this process is multi-criteria decision analysis.
8.2.2.4. Data Representation
Data representation technique that may be used in this process includes but not limited to:
▪ Affinity Diagram. Affinity diagrams can organize potential causes of defects into groups showing
areas that should be focused on the most.
142 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
▪ Cause and Effect Diagram. which are also known as fishboneGuide
diagrams or as Ishikawa diagrams.
▪ Flowcharts. which are also referred to as process maps.
▪ Histograms. are a special form of bar chart and are used to describe the central tendency,
dispersion, and shape of a statistical distribution.
▪ Matrix Diagrams.
▪ Scatter Diagram plot ordered pairs (X, Y) and are sometimes called correlation charts
because they seek to explain a change in the dependent variable, Y, in relationship to a
change observed in the corresponding independent variable, X.
143 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
The quality reports can be graphical, numerical or quantitative. The information presented in the
report may include all quality issues escalated by team; recommendations, and product
improvement; corrective action recommendations and summary of findings of control quality
process.
These documents can be created as per the industry needs and the organization template and will be
an input to the control quality process.
144 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
8.2.3.4. Project Management Plan Updates
Any update to the Quality Management Plan requires an update to the project management
plan. Existing processes may be updated, process Improvements may be implemented.
Requested changes (additions, modifications, deletions) to the project management plan and
its subsidiary plans are processed through the Integrated Change Control process.
Control Quality
145 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
8.3.1. Quality Control – Inputs
The component of the project management plan that can be included as input are:
▪ Quality Management Plan. This document defines how Quality Control will be performed within
the project.
The project documents used as input to this process includes but not limited to:
▪ Lessons Learned Register
▪ Quality Metrics
▪ Test & Evaluation Documents
8.3.1.5. Deliverables
A deliverable is any unique and verifiable product, result, or capability that results in a
validated deliverable required by the project.
146 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
standard work guidelines, issue and defect reporting procedures Guide
and communication policies
can be used as in input in this process.
▪ Checklists
▪ Check sheets which are also known as tally sheets
▪ Statistical Sampling
Statistical sampling involves selecting few samples for inspection at random. Sample
frequency and sizes should be determined during the Plan Quality Management process
so the cost of quality will include the number of tests, expected scrap, etc.
▪ Questionnaire & Surveys
▪ Performance Review
▪ Root Cause Analysis
8.3.2.3. Inspection
An inspection is the examination of a work product to determine if it conforms to documented
standards. The results of an inspection can include measurements and may be conducted at
any level.
Testing is an organized and constructed investigation conducted to provide information about the
quality of the product or service. The purpose of testing is to ensure that the deliverables produced
meet the project requirements. Testing is carried out throughout the life cycle of the project. Early
testing can find out defects which can be fixed to reduce the cost of defects or non-conformance.
147 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
8.3.2.6. Meetings
148 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
project are initiated in accordance with Integrated Change Control Process.
149 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
140 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
9. Project Resource Management
Project Resource Management includes the processes to identify, acquire and manage the resources
needed for the successful completion of the project. These processes help ensure that the right resources
will be available to project manager and project team at right time and place.
Knowledge Monitoring
Area Initiating Planning Executing and Closing
Controlling
▪ Plan Resource Management. The process of defining how to estimate, acquire, manage and utilize
physical and team resource.
▪ Estimate Activity Resource. The process of estimating team resources and the type and quantities of
material, equipment and supplies necessary to perform project work.
▪ Acquire Resources. The process of obtaining team members, materials, equipment, supplies and other
necessary resources required to complete the project work.
▪ Develop Team. The process of improving competencies, team member interaction, and over all team
environment to improve the project performance.
▪ Manage Team. The process of tracking team member performance, providing feedback, resolving
issues and managing team changes to optimize project performance.
▪ Control Resources. The process of ensuring that the physical resources assigned and allocated to the
project are available as planed; as well as monitoring the plan vs actual use of the resources, and
performing corrective action as necessary.
141 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
9.1. Plan Resource Management
Plan Resource management is the process of defining how to estimate, acquire, manage and use team
and physical resources.
Human Resource Planning process helps organization in developing staffing management plan,
determines project roles, responsibilities, and reporting relationships. Staffing management plan
specifies how and when team members will be acquired, determining If a training need exists and if
It does, what training is required to fill the gap, recognition and rewards plan and safety issue. Project
roles are designated for persons or groups from inside or outside the performing organization.
▪ Enterprise Environmental
Factors
The project charter provides high level project description and requirements. It also has information
such as key stakeholder, summary milestone, pre-approved resource, that may influence the resource
management plan
The components of the project management plan that could be part of the input to this process are:
▪ Quality Management Plan. The quality management plan provides the information about the
desired level of quality which will be factor for defining the level of resources that will be
required.
142 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
▪ Scope Baseline. The scope baseline defines the deliverables,Guide
which help to determine the type
and quantity of resource needed for the project.
The data representation technique that can be used in this process are:
▪ Historical Charts
▪ Organization breakdown structure
143 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Resource breakdown structure
▪ Assignment Matrix
▪ RACI chart
9.1.2.4. Meetings
While developing the HR management plan, project manager, project team and stakeholders may
need to conduct meetings to discuss HR management plan.
The team charter is a document that establishes the team values, agreements and operating
guidelines for the team.
The project documents that can be updated as a result of this process are:
▪ Assumption Logs
▪ Risk Register
Estimate Activity Resource is the process of estimating team resources and type and quantity of materials,
equipment and supplies necessary to perform project work.
145 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
The components of the project management plan which can be considered as input to this process
are:
▪ Resource Management Plan
▪ Scope Baseline
The project documents which can be considered as input to this process are:
▪ Activity Attributes
▪ Activity List
▪ Assumption Log
▪ Cost Estimates
▪ Resource Calendars
▪ Risk Register
The Enterprise environmental factors that may influence this process are:
▪ Resource Location
▪ Resource Availability
▪ Team Resource Skills
▪ Organizational culture
The Organizational Process Assets that may be included as an input to this process are:
▪ Policies and Procedures regarding staffing
▪ Policies and procedures regarding supplies and equipment
▪ Historical information
Expertise should be considered from individuals or group having specialized knowledge and training
146 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
in team and physical resource planning and estimating.
Team and physical resources are estimated at thee activity level and then aggregated to develop
estimates for work packages, control accounts and summary at project level.
This technique is used with estimation information from previous similar project completed in the
past.
Using historical data and other variables, the estimates are developed using parametric estimation
technique.
The data analysis techniques that are used in this process is primarily alternative analysis. It assists in
providing best solution to perform project activities.
The PMI®S may include the resource management software which can help manage the resources of
the project.
9.2.3.7. Meetings
Project manager may have held meetings with functional managers to estimate the resources needed
, their skill level, LoE (Level of effort) , and other details.
Acquire Resource
9.2.6.2. Negotiation
Negotiations may happen on many projects. To ensure that the project receives appropriately
competent staff in the required time frame, and that project team members will be able to
work on the project until their responsibilities are completed, the project management team
may need to negotiate with Functional managers. The project management team may also
need to negotiate with other project teams within the performing organization to
appropriately assign scarce or specialized resources.
9.2.6.3. Acquisition
Sometimes, required services can be acquired from outside sources if the performing
organization lacks the in-house staff needed to complete the project. This can involve hiring
individual consultants or subcontracting work to another organization.
149 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
It documents the time periods each project team member will work on the project. Creating a
reliable final schedule depends on having a good understanding of each person’s schedule
conflicts, including vacation time and commitments to other projects.
Develop Team
150 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Leadership
→ Team building
→ Motivation
→ Communication
→ Influencing
→ Decision making
→ Political and cultural awareness
→ Negotiation
→ Trust building
→ Conflict management
→ Coaching
151 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
9.4.2.2. Training
It includes all formal or Informal activities designed to enhance the competencies of the project
team members. Examples of training methods Include classroom, online, computer based, on
the job training from another project team member, mentoring and coaching.
153 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Manage Team
156 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
performance appraisals of any project team member with whom Guide
they interact in a significant
way. In order to create historical database of the organization, all knowledge learned during
the project should be documented. Lessons learned in the area of HR Management can
include a Project organization chart, position descriptions, and staffing management plans
that can be saved as templates, Ground rules, conflict management techniques, and
recognition events that was particularly useful, a procedure for virtual teams, co-Location,
negotiation, training, and team building that proved to be successful.
Control resource is the process of ensuring that the physical resources assigned and allocated to the project
are available as planned, as well as monitoring the plan vs actual utilization of resources and taking corrective
actions as necessary.
Control Resource
158 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
10. Project Communications Management
Project Communications Management includes the processes that are required to ensure timely and
appropriate planning, collection, creation, distribution, storage, retrieval, management, control,
monitoring, and the ultimate disposition of project information.
▪ Plan Communication Management. The process of developing an appropriate approach and plan for
project communication activities based on the information needs of each stakeholder or group,
available organizational assets and the needs of the project.
▪ Manage Communcation. The process of ensuring timely and appropriate collection , creation,
distribution, storage, retreaval, management, monitoring and ultimate disposition of project
information.
▪ Monitor Communication. The process of ensuring the information needs of the project and its
stakeholders are met.
10.1. Plan communication Management
Plan Communications Management process determines the information and communication needs of the
stakeholders, for example who needs what information, when they will need it, how it will be given to them,
and by whom. A project manager spends most of his time communicating with the various stakeholders and
providing necessary information to the project team to successfully complete their work.
159 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Plan Communication
Management
160 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
10.1.2.5. Meetings
While developing the Communication Management Plan, project manager, project team and
stakeholders may need to conduct meetings to discuss most appropriate way of
communicating the project information to stakeholders.
162 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Manage Communication
163 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Organizational culture and structure, Government or industry standards & regulations and
Project management information system are some of the specific enterprise environmental
factors that can influence the Manage Communications process.
→ Stakeholder notifications
→ Project reports
→ Project presentations
→ Project records
→ Feedback from stakeholders
→ Lessons learned documentation
165 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Monitor Communication
166 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
10.3.2.3. Meetings
Project manager, project team and stakeholders may need to conduct meetings to discuss
most appropriate way of to update and communicate the project information to stakeholders.
167 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
across areas. Work performance data gets transformed into Work Performance Information
and provides a basis for decisions making associated with project.
→ Forecasts
→ Performance reports
→ Issue log
168 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
169 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11. Project Risk Management
Project Risk Management includes the processes of conducting risk management planning, response
implementation, identification, analysis, response planning, and monitoring risk on a project.
Knowledge Monitoring
Area Initiating Planning Executing and Closing
Controlling
▪ Plan Risk Management. The process of defining how to conduct risk management activities for a project.
▪ Identify Risks. The process of identifying individual project risks as well as source of overall project risks and
documenting their characteristics
▪ Perform Qualitative Risk Analysis. The process of prioritizing individual project risks for further analysis or action
by assessing their probability of occurrence and impact as well as other characteristics.
▪ Perform Quantitative Risk Analysis. The process of numerically analyzing the combined effect of identified
individual project risks and other sources of uncertainty on overall project objectives.
▪ Plan Risk Response. The process of developing actions, selecting strategies, and agreeing on actions to address
overall project risk exposure as well as treat individual project risk.
▪ Implement Risk Response. The process of implementing the agreed upon risk response plan.
▪ Monitor Risks. The process of monitoring the agreed upon risk response plans, tracking identified risks, identifying
and analyzing new risks, and evaluating the risk process effectiveness throughout the project.
170 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Plan Risk Management is the process of defining how to conduct risk management activities for a project.
Risk Management Planning is important to ensure that the level, type and visibility of risk management are
commensurate with both the risk and importance of the project to the organization. Planning is also important
to provide sufficient resources and time for risk management activities and to establish an agreed upon basis
of evaluating risks.
171 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Enterprise Environmental
Factors
11.1.2.3. Meetings
Project manager, project team and stakeholders may need to conduct meetings to develop
the Risk management Plan.
→ Methodology: Defines the approaches, tools, and data sources that may be used to
perform risk management on the project.
→ Roles and Responsibilities: Defines the Lead, support, members of the risk management
team for each type of activity in the risk management plan, assigns people to these
roles, and clarifies their responsibilities.
→ Budgeting: Assigns resources and estimates costs needed for risk management for
173 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
inclusion in the project cost baseline.
→ Timing: Defines schedule and frequency of the risk management process that will be
performed throughout the project tile cycle, and establish risk management activities
in the project schedule.
→ Risk Categories: Provides a structure that ensure a comprehensive process of
systematically Identifying risk to a consistent level of detail and contributes to the
effectiveness and quality of Risk Identification. A risk breakdown structure (RBS) is one
approach to providing such a structure.
→ Definitions of Risk Probability and impact: The quality and credibility of the Qualitative
Risk Analysis process requires that different levels of the risk probabilities and impact
be defined. General definitions of probability levels and impact Levels are tailored to
the individual projects during the Risk Management planning process for use in the
Qualitative Risk Analysis process.
→ Probability and Impact Matrix: Risks are prioritized according to their potential
implications on meeting the project’s objectives. The typical approach in prioritizing risk
is to use a lookup table or a Probability and Impact Matrix. The specific combination of
probability and impact leads to a risk being rated as of high, moderate or low
Importance.
→ Revised Stakeholders’ tolerances: Stakeholders tolerances may be revised in the Plan
Risk Management process, as they apply to the specific project.
→ Reporting Formats: Describes the content and format of the risk register as well as any
other required risk related reports. Defines how the outcomes of the risk management
processes will be documented, analyzed, and communicated.
→ Tracking: Documents whether and the risk management processes will be audited.
174 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.2. Identify Risk
Identify Risk process determines which risk may affect the project and documents their
characteristics. Participants in risk identification activities can include project manager, project team
members, risk management team (if assigned), subject matter experts from outside the project team,
customers, end users, other project managers, stakeholders and risk management expects. The Risk
Identification process usually leads to the Qualitative Risk Analysts process.
Identify Risks
175 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.2.1.4. Quality management plan
The quality management plan provides a baseline of quality measures and metrics for use in
identifying risks.
176 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Academic studies
→ Published checklists
→ Benchmarking
→ Industry studies
→ Risk attitudes.
177 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
178 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Probability and impact are assessed for each identified risk. Risks can be assessed in interviews
or meetings and the level of probability for each risk and its impact on each objective is
evaluated.
Explanatory details, including assumptions justifying the levels assigned, is also recorded. Risk
probabilities and impacts are rated according to the definitions given in the risk management
plan.
The organization should determine which combinations of probability and impact results in a
classification of high, moderate or low risk.
180 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.3.3.3. Risk data quality assessment
A qualitative risk analysis requires accurate and unbiased data if it is to be credible. Analysis of
the quality of risk data is a technique to evaluate the degree to which the data about risks is
useful for risk management. It involves examining the degree to which the risk is understood
and the accuracy, quality, reliability and integrity of the data about the risk.
181 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
and assigns a numerical rating to those risks. It also presents a quantitative approach towards
making a decisions in the presence of uncertainty.
The components of the project management plan which can be considered as input to this process
are:
▪ Risk Management Plan
▪ Scope Baseline
▪ Schedule Baseline
▪ Cost Baseline
The project Documents which can be considered as input to this process are:
▪ Assumption Log
▪ Basis of Estimate
▪ Cost Estimate
▪ Cost Forecast
▪ Schedule forecasts
▪ Duration estimates
182 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Risk Register
→ Interviewing: Interviewing techniques are used to quantify the probability and impact of
risks on project objectives. Documenting the rationale of the risk ranges is an important
component of the risk interview, because it can provide information on reliability and
credibility of the analysis.
→ Probability Distribution: Continuous probability distribution represents the uncertainty
in values, such as durations of schedule activities and costs of project components.
→ Sensitivity Analysis: Sensitivity analysis helps to determine the risks that have the most
potential impact on the project. It examines the extent to which the uncertainty of each
project element affects the objective being examined when all other uncertain
elements are held at their baseline values.
→ Expected Monetary Value Analysis: Expected Monetary Value (EMV) analysis is a
statistical concept that calculates the average outcome when the future includes
scenarios that may or may not happen (i.e., analysis under uncertainty). A common use
of this type of analysis is in decision tree analysis.
→ Decision Tree Analysis: Decision Tree Analysis is usually structured using a decision tree
diagram that describes a situation under consideration, and the implications of each of
the available choices and possible scenarios.
→ Modeling and simulation: A project simulation uses a model that translates the
uncertainties specified at a detailed level of the project into their potential impact on
project objectives. Simulations are typically performed using the Monte Carlo
183 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
technique.
184 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
180 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.5.1. Plan Risk Responses – Inputs
11.5.1.1. Risk management plan
Important components of the risk management plan include roles and responsibilities, risk
analysis definitions, risk thresholds for low, moderate, and high risks, and the time and budget
required to conduct Project Risk Management.
11.5.1.2. Risk register
The risk register is first developed in the Risk Identification process, and is updated during the
Qualitative and Qualitative Risk Analysis processes. The Plan Risk Response process may have
to refer back to Identified risks, root causes of risks, lists of potential responses, risk owners,
symptoms, and warning signs in developing risk responses.
→ Avoid: Risk avoidance involves changing the project management plan to eliminate the
threat posed by an adverse risk, to isolate the project objective from the risk’s impact, or
to relax the objective that is in jeopardy. Risks that arise early in the project can be
avoided by clarifying requirements, obtaining information, improving communication, or
acquiring expertise.
→ Transfer: Risk transference requires shifting the negative impact of a threat, along with
ownership of the response, to a third party. Transferring the risk simply gives another
party responsibility for its management. It does not eliminate it.
→ Mitigate: Risk mitigation implies a reduction in the probability and/or impact of an adverse
risk event to an acceptable threshold. Taking early action to reduce the probability and/or
impact of a risk occurring on the project is often more effective than trying to repair the
damage after the risk has occurred. Where it is not possible to reduce probability, a
mitigation response might address the risk impact by targeting linkages that determine
the severity.
→ Accept: Risk acceptance involves the decision to acknowledge the risk and not take any
actions unless the risk occurs. This strategy is adopted where it is not possible or cost-
effective to address a specific risk in any other way.
181 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.5.2.2. Strategies for positive risks or opportunities
There are four strategies typically deal with opportunities or risks that may have positive
impacts on project objectives if they occur. These strategies are:
→ Exploit: The exploit strategy may be selected for risks with positive impacts where the
organization wishes to ensure that the opportunity is realized. This strategy seeks to
eliminate the uncertainty associated with a particular upside risk by ensuring the
opportunity definitely happens.
→ Share: Sharing a positive risk involves allocating ownership to a third party who is best
able to capture the opportunity for the benefits of the project.
→ Enhance: This strategy modifies the “size of an opportunity by increasing probability
and/or positive impacts, and by identifying and maximizing key drivers of these post-
impact risks. Strategy for Both Threats and Opportunities.
→ Accept: Acceptance involves the decision to acknowledge the opportunity and not take
any actions unless the opportunity arises.
→ Schedule management plan: Changes in resource loading and leveling, and schedule
strategy.
182 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Cost management plan: Changes in cost accounting, tracking, and reports and updates
to the budget strategy and how contingency reserves are consumed.
→ Quality management plan: Changes in behavior related to requirements, quality
assurance, or quality control and updates to the requirements documentation.
→ Procurement management plan: Alterations in the make-or-buy decision or contract
type(s) driven by the risk responses.
→ Human resource management plan: Changes in project organizational structure and
resource applications, staff allocation, as well as updates to the resource loading.
→ Scope baseline: Modified or omitted work generated by the risk responses.
→ Schedule baseline: Changes in schedule baseline to reflect changes in Scope baseline.
→ Cost baseline: Changes in schedule baseline to reflect changes in Scope baseline.
Implement Risk response it the process of implementing agreed upon risk response plans. The key benefit of
this process is that it ensures that agreed upon risk responses are executed as planned in order to address
overall project risk exposure, minimize individual project threats and maximize individual project
opportunities.
183 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
The project documents that can be a part of the input to this process are:
▪ Risk Register
▪ Risk Reports
▪ Lessons Learned Register
The Organizational process assets that can influence this process is Lessons Learned Repository
containing information on similar completed projects.
The PMI®S may contain, schedule, resource and cost management software which can and may
include the risk response plan and associated actions are integrated.
Monitor Risks
185 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
186 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
11.6.3.4. Technical performance measurement
Technical performance measurement compares technical accomplishments during project
execution to the project management plan’s schedule of technical achievements.
11.6.3.6. Meetings
Project risk management can be an agenda item at periodic status meetings.
If the approved change requests have an effect on the risk management processes, the corresponding
component documents of the project management plan are revised and re-issued to reflect the
approved change requests.
The key document to be updated as an outcome of Control Risk process is Risk Register. It may get
updated with outcomes of risk reassessments, risk audits, and periodic risk reviews. It may also contain
result of project’s risk and risk response.
The risk management processes produce information that may be used for future projects, and
should be captured in the organizational process assets.
187 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
188 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
12. Project Procurement Management
Project Procurement Management includes the processes necessary to purchase or acquire products,
services, or results needed from outside the project team. Project Procurement Management includes
management and control processes required to develop and administer agreements such as
contracts, purchase orders, MOA & SLA.
Knowledge Monitoring
Area Initiating Planning Executing and Closing
Controlling
189 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Plan Procurement
Management
190 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Marketplace conditions
→ Products, services, and results that are available in the marketplace
→ Suppliers, including past performance or reputation
→ Terms and conditions
→ Unique local requirements.
→ Fixed Price or Lump Sum Contracts: The buyer and seller agree on a well- defined
deliverable for a set price. In this kind of contract, the biggest risk is borne by the seller.
1) Firm Fixed Price Contracts (FFP)
2) Fixed Price Incentive Fee Contracts (FPIF)
191 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
3) Fixed Price Incentive Fee Contracts (FPIF)
→ Cost-reimbursable contracts: All the costs the seller takes on during the project are
charged back to the buyer, thus the seller is reimbursed. Three of the more common
types of cost-reimbursable contracts are:
1) Cost Plus Fixed Fee (CPFF)
2) Cost Plus Incentive Fee (CPIF)
3) Cost Plus Award Fee (CPAF)
→ Time and Material contracts (T&M): This type of contract is a mix of fixed price and cost
reimbursable contract. The full amount of the material costs is not known at the time
the contract is awarded. This resembles a cost reimbursable contract as the costs will
continue to grow during the contract’s life.
12.1.2.4. Meetings
192 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Project manager, project team and stakeholders may need to conduct meetings with potential
bidders for exchange of additional information.
193 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
buyer. A procurement SOW describes the product service or result to be supplied by the seller.
Information included in a procurement SOW can include specifications, quantity desired,
quality levels, performance data, period of performance, work location and other
requirements.
→ Understanding of need
→ Overall life-cycle cost
→ Technical capability
→ Management approach
→ Technical approach
→ Financial capability
→ Production capacity and interest
→ Business size and type
→ References
→ Intellectual property rights
→ Proprietary rights
194 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Conduct Procurements
195 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
12.2.1.2. Procurement documents
Procurement documents provide an audit trail for contracts and other agreements.
196 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop
during this initial buyer and seller interaction to produce the bestGuide
bid.
12.2.2.5. Advertising
Existing lists of potential sellers can be expanded by placing advertisements in general
circulation publications such as selected newspapers or in trade publications. Some
government jurisdictions require public advertising of certain types of procurement items,
and most government jurisdictions require public advertising or online posting of pending
government contracts.
12.2.3.2. Agreements
An agreement is a legal relationship subject to remedy in the courts that is awarded to each
selected seller. It can be in the form of a complex document or a simple purchase order.
Regardless of the document’s complexity, an agreement is a mutually binding legal agreement
that obligates the seller to provide the specified products, services or results and obligates
the buyer to pay the seller.
→ Cost baseline
→ Scope baseline
→ Schedule baseline
→ Communications management plan
→ Procurement management plan
12.2.3.6. Project document updates
Project documents that may be updated include:
→ Requirements documentation
198 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Requirements traceability documentation
→ Risk register
→ Stakeholder register
Control Procurements
12.3.1.3. Agreements
Agreements are understandings between parties, including understanding of the duties of
199 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
each party.
201 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Correspondence
→ Payment schedules and requests
→ Seller performance evaluation documentation
202 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
203 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
13. Project Stakeholders Management
Project Stakeholder Management includes the processes required to identify the people, groups, or
organizations that could impact or be impacted by the project, to analyze stakeholder expectations and
their impact on the project, and to develop appropriate management strategies for effectively engaging
stakeholders in project decisions and execution.
▪ Identify Stakeholder. The process of identifying project stakeholders regularly and analyzing and
documenting relevant information regarding their interest, influence, involvement etc.
▪ Plan Stakeholder Engagement. The process of developing approaches to involve stakeholders based
on their needs, expectation, interest, involvement and potential impact on the project.
▪ Manage Stakeholder Engagement. The process of communicating and working with stakeholders to
meet their needs and expectations, address issues and foster appropriate involvement.
▪ Monitor Stakeholder Engagement. The process of monitoring the project stakeholder relationship
and tailoring strategies for engaging stakeholders.
Identify Stakeholders is the process of identifying the people, groups, or organizations that could
impact or be impacted by a decision, activity, or outcome of the project, analyzing and
documenting relevant information regarding their interests, involvement, interdependencies,
influence, and potential impact on project success.
204 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Identify Stakeholder
Inputs Tools and Techniques Outputs
▪ Agreements
▪ Enterprise Environmental
Factors
In the first iteration of Identify Stakeholder process, the following are the source of information.
▪ Business Case
▪ Benefits Management Plan.
13.1.1.3. Project Management Plan
The project management plan is not available when initiating identify stakeholder, however once it is
developed its components are used as input .
205 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
13.1.1.4. Project Documents
Initially documents may not be available to be used for this process, however the Stakeholder
identification happens through out life cycle of the project. So following documents may be used.
▪ Change Log
▪ Issue Log
▪ Requirement Documentation.
13.1.1.5. Agreements
13.1.1.6. Enterprise environmental factors
Organizational culture and structure, global, regional or local trends, and practices, or industry
standards are the environmental factors that can influence the identify stakeholders process.
Data gathering techniques that can be used for this process includes but not limited to:
▪ Stakeholder analysis
Stakeholder analysis is systematic gathering and analyzing of information to determine whose
interests should be taken into account in a project. Project manager uses stakeholder analysis
to assess interests, positions, alliances, and importance given to the project by such
stakeholders.
206 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
→ Assess how key stakeholders are likely to react or respond in various situations
There are multiple classification models used for stakeholders analysis, such as:
▪ Document analysis
▪ Power/ Interest grid, power/influence grid, Impact/Influence grid. Each of these techniques
group the stakeholders according to their level of authority, level of interest and ability to
influence the outcome of the project.
13.1.2.5. Meetings
Project team can meet to develop an understanding of major project stakeholders, and to
exchange and analyze information about roles, interests, knowledge, and the overall position
of each stakeholder in the project.
− Identification information
− Assessment information (Major requirements, main expectations, potential
influence in the project)
− Stakeholder classification (Internal/external, supporter/neutral/resistor, etc.)
The stakeholder register should be consulted and updated on a regular basis, as stakeholders may
change throughout the life cycle of the project.
207 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
13.1.3.2. Change Requests
During the first iteration of this process there will be no changes. However as the project progresses,
new stakeholders will be introduced, existing stakeholders may be exiting and the interest, influence
and involvements of the stakeholders may change. All these changes should be processed through
Integrated change request process and recorded.
The project documents that may be updated as a result of this process includes but not limited to:
▪ Assumption Log
▪ Issue Log
▪ Risk Register
During the first iteration of the process there will not be any updates on the project management
plan or its components. However as the project progresses the following components of the project
management plan may get updated.
208 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
The project charter contains the information on the project purpose, objectives and success criteria,
that can be taken into consideration when planning how to engage stakeholders.
▪ Resource Management Plan. The resource management plan may contain the
information regarding roles and responsibilities of the team and other stakeholders
listed in the stakeholder register.
▪ Communication Management Plan. Communication strategies and their
implementation plan are both input to this process.
▪ Risk Management Plan. The risk register plan may contain the risk threshold or risk
attitude that could be vital information to be used in this process.
The project documents that could be input to this process includes but not limited to:
209 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
13.2.1.4. Agreements
When planning for engagement of contractors and suppliers, who are also stakeholders of the
project, coordination is involved with procurement or contracting group in the organization to ensure
the suppliers/contractors are effectively managed.
Data gathering techniques that can be used for this process includes but not limited to benchmarking,
where the stakeholder analysis results are compared with other organization or other projects that
are considered to be world class.
210 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
211 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
The decision making techniques that can be used in this process is prioritizing/ ranking.
The data representation technique that may be used in this process includes but not limited to:
▪ Mind Mapping
▪ Stakeholder Engagement Assessment Matrix. The said matrix supports the comparison between
the current engagement level of the key stakeholders vs the desired level of engagement
required for a successful project delivery. The engagement level can be classified as the following
aspects:
o Unaware - Unaware of the project and potential impact.
o Resistant – Aware of the project and impact, but resistant to any change.
o Neutral – Aware of the project but neither supportive or un-supportive.
o Supporting – Aware of the project and potential impact and supportive towards the
project and its outcome.
o Leading - Aware of the project and the potential impact and is actively engaged to
ensure the success of the project.
13.2.2.7. Meetings
Manage Stakeholder Engagement is the process of communicating and working with stakeholders to meet
their needs and expectations, address issues and foster appropriate stakeholder involvement in the project
and through out the project. It allows the project manager to have increased support and minimum
resistance from the stakeholders.
212 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Manage Stakeholder
Engagement
Inputs Tools and Techniques Outputs
The components of the project management plan which can be considered as an input to this process
includes but not limited to:
▪ Stakeholder Engagement Plan. The stakeholder management plan provides guidance on how
the various stakeholders can be best involved in the project. The stakeholder management
plan provides the understanding of stakeholder’s goals, objectives and level of
communication required during the project.
The project documents that can be considered as input to this process includes but not limited to:
▪ Change Log. A change log is used to document changes that occur during a project. These
changes—and their impact on the project in terms of time, cost, and risk—are communicated
to the appropriate stakeholders.
▪ Issue Log
213 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Lesson Learned Register
▪ Stakeholder Register
The enterprise environmental factors that can influence this process are:
▪ Organization culture
▪ Stakeholder Risk Threshold
▪ Geographic distribution of facilities and resource
▪ Conflict Management
▪ Cultural Awareness
▪ Negotiation
▪ Observation & Conversation
▪ Political awareness
Ground rules are defined in team charter is a set of expected behavior for project team members as
well as other stakeholders.
214 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
215 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
13.3.2.5. Meetings
Meetings are used to discuss and address any issues or concerns regarding stakeholder engagement.
The types of meetings may be listed as:
▪ Decision meetings
▪ Issue Resolution
▪ Lessons Learned and retrospectives
▪ Project kick off,
▪ Sprint planning
▪ Status update
Monitor Stakeholder
Engagement
Inputs Tools and Techniques Outputs
216 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
▪ Issue Log
▪ Lessons Learned Register
▪ Project Communication
▪ Risk Register
▪ Stakeholder Register
The data analysis techniques used in this process may include but not limited to:
▪ Alternative Analysis
▪ Root Cause analysis
▪ Stakeholder Analysis
The data representation techniques used in this process includes but not limited to Stakeholder
engagement matrix.
The two most effective communication skills used in this process are:
▪ Feedback
▪ Presentation. Presentations provide clear information to stakeholders.
13.4.2.6. Meetings
Project team can meet to develop an understanding of major project stakeholders, and to
exchange and analyze information about roles, interests, knowledge, and the overall position
of each stakeholder in the project.
218 | P a g e
PMP® Exam Preparation PMP® Exam Prep Study
Workshop Guide
Project team may need to update Stakeholder register as stakeholder’s information may change due
to addition of new stakeholders or when existing stakeholders no longer involved in the project. It may
also require updates to issue log as new issues may be identified and current issues may get resolved
during the process.
219 | P a g e