A gap analysis on the
implementation of a proactive
obsolescence management strategy
Vincent Janssen
Industrial Engineering and Management (BSc)
Obsolescence management scan: A gap analysis on the implementation
of a proactive obsolescence management strategy
Author
V. Janssen
S1598910
Student Industrial Engineering and Management (BSc)
University of Twente
DR. M.C. van der Heijden
DR. E. Topan
Thales
B. Jongebloed
1
2
Preface
Before you lies the bachelor thesis that I conducted at Thales and the RNLN, the Royal Netherlands Navy
conducted in the period: 1-11-2019 till 31-01-2020.
I look back on a period where I learned a lot. Working at a company provides a setting where other skills
are needed in comparison to working at the university, such as taking initiative, planning over a longer
period of time and working on a project individually.
My research is on the subject of obsolescence and in particular the logistical obsolescence. I would like to
thank both Thales and the RNLN for giving me the chance to conduct the research and I would like to thank
the employees of both companies for helping me with providing answers to my questions and for the
validation of my research. I would especially want to thank Berend Jongebloed, my supervisor, for helping
me with both providing me with answers as well as helping me with the structure of my thesis. From the
university I want to thank Matthieu van der Heijden, for providing me with feedback to enhance the quality
of this thesis and Engin Topan for being my second supervisor. From RNLN I want to thank Bart Pollmann
for the introduction into the company and providing me with feedback. Last I want to thank the members
of the Marconi project with their insights and answers.
Vincent Janssen
May 2020
3
Management summary
Motivation
This research is commissioned by the collaboration of Thales Hengelo and the RNLN, Royal Netherlands
Navy, where Thales produces radar systems for the Royal Netherlands Navy. The products Thales produces
can become obsolete, which means can be described either as when material or technology is not available
from existing stock and from an original manufacturer, which is referred to as logistical obsolescence.
Functional obsolescence is another form of obsolescence and can be described as the situation when the
product does not meet the required capability standard from the customer anymore.
There are multiple solutions for solving obsolescence, where the costs of some of these solutions can
become relative high. Therefore, Thales and the RNLN decided to implement a proactive OM,
obsolescence management, strategy to ensure that the costs of solving obsolescence will be minimized.
By recognizing obsolescence concerns and issues in an earlier stadium, an appropriate solution can be
identified and will be implemented to avoid costly solutions. Thales and the RNLN already implemented
parts of a proactive obsolescence management strategy, although it was at the start of the Marconi project
not clear how a complete proactive obsolescence management strategy should be implemented to
achieve maximum efficiency in handling obsolescence. Improvement of the Obsolescence policy is an on-
going process at Thales and at DMI. This research is one of the projects that contributes to the
improvement in the collaboration between Thales and DMI in general. Results of a recent and dedicated
project of Thales and DMI for a set of sensors are not fully included in this research. That specific project
will contribute to further improvement of an pro-active obsolescence policy within the scope of the
Marconi Network.
Methodology
This thesis analyses what the challenges are on implementing a complete proactive obsolescence
management strategy within the logistical obsolescence subject. To identify the challenges, the subjects
risk assessment, obsolescence monitoring and solutions need to be studied as they constitute the logistical
obsolescence subject. A gap analysis is used to identify the gaps between the desired and actual situation.
The first step is a literature review to assess what the most efficient proactive obsolescence management
strategy includes. The second step is to map the current situation, and the third step is to identify the gaps
between the actual and the desired situation.
Results
Risk assessment
The risk assessment which is currently performed at Thales results in 95% of the time in a medium risk
level. As this is not accurate enough, the risk assessment can be improved by integrating more attributes
in the calculation of the risk. Seuren (2018) constructed a model to calculate the risk level concerning more
accurately, but used too many attributes which Thales not all could integrate in the risk assessment. Krol
(2020) modified the model for RH Marine and reduced the amount of attributes. A similar modification
with a reduced amount of attributes is needed at Thales to have the model of Seuren (2018) implemented.
For a risk assessment the information of some of the suppliers of Thales is needed for completion of the
calculation. An example of such information is the plan of the coming period. If a supplier decided to stop
producing a required component and is the only manufacturer of the component, Thales needs to buy a
component similar to the original or a design change needs be implemented. By identifying the situations
as early as possible, sufficient time is left to investigate which solution suits the situation best.
4
Obsolescence monitoring
The process of obsolescence monitoring is executed similar to the literature, but gaps are identified in the
communication of the results from Thales to the RNLN. The first gap is due to miscommunication between
Thales and DMI. The list of obsolescence concerns and issues which Thales encounters is long. Thales
decided not to mention every detailed issue and concern to DMI, to make sure that DMI would only have
an overview on the important concerns and issues that directly effect DMI. As DMI only received these
messages, the misinterpretation that Thales has a reactive obsolescence strategy was formed. Thales does
have an obsolescence strategy in which issues in their own supply chain will be taken care of mainly on a
Form Fit Function basis, so DMI will not receive information on all matters. This causes a communication
problem.
The second gap is identified in the update Thales gives DMI. The issues and concerns are reported to DMI
but the mutual follow up plan on how to deal with the obsolescence is missing. As this information is
missing, DMI is unable to properly budget for the solutions of obsolescence. As DMI needs to budget for
an entire year for obsolescence, the information on the follow up plans is necessary.
Solutions
Multiple gaps are identified within the subject of the solutions to obsolescence. The first gap is identified
in the costs of the reactive and proactive solutions. The costs of the reactive solutions are estimated by
investigating the costs of these solutions in previous situations. When these solutions can exactly be
calculated and communicated to DMI, DMI is able to more accurately budget for obsolescence. The budget
needs to be accessible as solutions are not unlimited accessible, e.g. a last batch can be bought when a
supplier announces to stop producing a component, but this offer is not indefinitely useable.
As the costs of these proactive solutions can’t be determined on forehand, a plan on when to implement
a proactive solution on which components is missing. This is the second identified gap. The third gap
consists of a lack of information on which characteristics of a component are identified as possible
obsolescence concerns. This information is needed to continue the on-going implementation of proactive
solutions.
Furthermore, the RNLN needs to compose an obsolescence policy to adequately act on monitoring and on
solving obsolescence issues. The actions of the installation managers of DMI, who handle obsolescence for
the RNLN, are based on a general roadmap. By composing an obsolescence policy, fixed actions can be
identified and followed by the installation managers to decrease the decision time and ensure the
suggested solution to remain useable.
Obsolescence landscape
Subsequently to the analysis on the logistical obsolescence, the other subjects of the obsolescence
landscape are identified. Research on all topics should ensure the most efficient proactive obsolescence
management strategy.
Furthermore, there are gaps where Thales and the RNLN are already searching for a solution, so a follow
up project is not needed. These gaps are identified, explained and added to this thesis to ensure a
complete overview of the gaps.
5
Glossary of terms
Abbreviation Description
BOM(s) Bill Of Material(s)
COTS Commercial Off-The-Shelf
CZSK ‘Commando Zee StrijdKrachten’
DMI ‘Directie Materiele Instandhouding’
DMO ‘Defensie materieel organisatie’
EOL End Of Life (Component level)
IEC International Electrotechnical Commission
KPI Key Performance Indicator
LRU Line Replaceable Unit
LTB Last Time Buy
Marconi Maritime Remote Control Tower for Service Logistics Innovation
MTBF Mean Time Between Failures
OEM Original Equipment Manufacturer
OM Obsolescence Management
OMIS Obsolescence Management Information System
OMP Obsolescence Management Plan
ORB Obsolescence Review Board
PCN Product Change Notice
PDN Product Discontinuance Notice
RMB Risk Mitigation Buy
RNLN Royal Netherlands Navy
TRP Technological Refreshment Plan
YTEOL Years To End Of Life (Component level)
6
Table of content
Management summary 4
Glossary of terms 6
Table of content 7
1. Problem identification and problem approach 8
1.1. Introduction 8
1.2. Problem identification 11
1.3. Problem approach 13
1.4. Used methods 14
2. Theoretical framework 17
2.1. Risk assessment 17
2.2. Obsolescence monitoring 20
2.3. Solutions 21
3. Actual situation 25
3.1. Risk Assessment 25
3.2. Obsolescence monitoring 26
3.3. Solutions 27
4. Desired situation 31
4.1. Logistical obsolescence 31
4.2. Knowledge gap – Obsolescence landscape 33
5. Validation 39
5.1. Marconi project meeting 39
5.2. Expert panel meeting Thales 40
5.3 Priority list 42
6. Conclusion 44
6.1. Conclusion 44
6.2. Recommendations 45
6.3. Discussion 47
References 48
Appendix 1 50
Appendix 2 51
7
1. Problem identification and problem approach
This chapter provides an introduction into obsolescence, an introduction of both Thales and the RNLN and
the project of Marconi of which they are part of (1.1). After these introductions, the problem identification
(1.2) and the approach to solve the problem (1.3) will be discussed.
1.1. Introduction
1.1.1. Obsolescence
Within this chapter I will give a short explanation what obsolescence is. This topic will be the main topic in
my bachelor thesis.
Obsolescence means that a product does not meet the required capability standard, where the gap
between actual and desired capability typically grows over the life cycle of the product. This capability gap
consists of 2 parts. The first part is referred to as logistical obsolescence, as can be seen in figure 1 below
the dashed line. This type of obsolescence is described as when material or technology, which is needed
to manufacture or support a product or system, is not available from existing stock or the original
manufacturer of the material or technology (Bartels et al., 2012). This could occur when a supplier goes
bankrupt or when there is a lack of spare parts and/or maintenance personnel. Logistical obsolescence
could also occur when spare parts are infeasible to repair. A common situation on when a product
becomes obsolete is when a manufacturer does not find it economically viable anymore to produce a
product anymore.
In the case of functional obsolescence the product or the subsystem is still operating as intended and can
still be produced and supported, but the requirements by the customers have been increased (Bartels et
al., 2012) as can be seen in figure 1 above the dashed line. Besides materials also skills and software can
become obsolete. Functional and software obsolescence will be mentioned on later in this thesis as both
subjects are part of the transition to a complete OM, obsolescence management, strategy. However, the
scope of this research is on the domain of logistical obsolescence.
8
1.1.2. Thales
This chapter is meant to give a short introduction of the company where I will conduct most of my
research, Thales group Hengelo. Thales Netherlands is part of the worldwide Thales group, which is a
company that designs and produces electrical systems which are used in the fields of transportation,
defense, aerospace and security markets, where it also provides services for. The headquarter of this
multinational is established in Paris, France where the company was founded. Thales group has 64.000
employees who work in 56 countries. Thales Netherlands, consists of 4 sites where the site in Hengelo is
the biggest. Thales Hengelo is specialized in Radar and Combat Management technology for naval ships.
Innovation of this Radar Technology is done in close collaboration with the Dutch Defense organization.
1.1.3. DMI
DMI, ‘Directie Materiele Instandhouding’, represents the maintenance department of the navy. DMI is
responsible for the maintenance of all the systems on board, in the areas of platform, sensors,
communication and weapons. The support of DMI starts at the design and manufacturing of a vessel,
where on board experience is shared. The whole life cycle of a system or component is supported by DMI.
The 2000 employees of DMI work mostly in the Netherlands but if necessary also the mission areas are
supported by this department. There are 2 divisions at DMI, maintenance and logistics. Maintenance
(Maritieme instandhouding) receives the parts and services from logistics, where DMI logistics (Maritieme
Logistiek) receives these parts and services from their own worksite, Thales or other suppliers.
The MARCONI project, Maritime Remote Control Tower for Service Logistics Innovation, is a project which
is set up to integrate a control tower within the Service Logistics supply chain of the navy and it’s suppliers.
Companies which are included within the
MARCONI project can be found in figure 2,
and are the suppliers of services,
knowledge and products. The supply chain
acts as support for the CZSK, the
‘Commando Zee Strijdkrachten’, which is
the end user of the products. Within the
MARCONI project, there are 3 work
packages to make sure the control tower
can be integrated within the supply chain.
The first work package, service logistics
Figure 2, Included companies of the MARCONI project
decision support models, is the work
package which will be the area where my thesis will be of value too. This work package will deliver models
to support the primary processes and the supporting, service logistics processes. These processes contains
supply, resource and maintenance planning and an operating schedule which focus on supporting the use
of assets or products by CZSK. The other work packages are the control tower operating model (WP2) and
the information management (WP3). To conclude, the objective within the 3 year duration of the Marconi
project is to create a 5 to 10 year roadmap for proactive OM, obsolescence management.
9
The relevant area of this bachelor thesis is within the relationship between Thales and DMI, where a more
elaborate description of the relationship between the relevant companies can be found in figure 3. DMO,
‘Defensie materieel organisatie’, is involved in the purchase, conservation and the selling of materials and
defines the capability requirements for an Asset. Thales receives there parts from its own suppliers.
CZSK, DMI and DMO are departments of RNLN, the Royal Netherlands Navy. The triadic relationship
between DMI Maintenance, DMO and CZSK is called asset management (or Weapon System
Management), which refers to the fact that these departments represent the part of the supply chain
where the requirements are set.
De Vries (2019) made an overview on how the network looks like in terms of relation to each other (Figure
3). Within my research I will not focus on the relationships between Thales or DMI with their own suppliers,
as the scope would be too big to finish for me in time.
Figure 3 , Visualization of the network between Thales, DMI, DMO, CZSK and the supplier of
Thales and DMI (De Vries, 2019)
10
1.2. Problem identification
This section discusses the problem cause (1.2.1.), followed by the problem cluster (1.2.2.), the
identification of the core problem (1.2.3) and finally the overview of the current and the desired situation
(1.2.4).
After these research projects were finished, the question of which subjects could be identified within
obsolescence management arose. These subjects combined form the obsolescence landscape, which is
the overarching problem of this thesis. Following this obsolescence landscape, the direction for follow up
projects is desired, which should contribute to a complete overview and understanding of OM. Within this
research, the subject of logistical obsolescence will be researched in depth, the other subjects won’t, as
the scope would be too big elsewise. However, as this research is a starting point of the Marconi project,
the subjects will be identified, where some will be elaborated more on than others.
11
Figure 4 represents the problem cluster in which the core problem occurs and what the consequences are.
The problem cluster begins at the top left corner with the capability gap (1), which is described in
paragraph 1.1.1. This gap is present when somewhere in the supply chain logistical obsolescence occurs.
The proactive OM strategy is not optimal at the moment, as there are parts which should have a proactive
solution but either the relevant parts for a proactive solution are not identified, or the correct proactive
solution cannot be determined at this moment. This causes the situation that a reactive OM strategy
complies to these parts (2). By addressing the relevant parts with a reactive approach, the supply chain is
vulnerable when obsolescence occurs. Obsolescence is not always identified a long time in advance or
there could have been an error in the communication. This leaves with a short time to respond to the
obsolescence, what could result in a (costly) solution (5) and an increased lead time for the parts(6).
The proactive OM strategy which is implemented is incomplete. A part of the obsolescence issues which
should be treated proactively are now treated with reactive solutions. The Marconi network knows that
the strategy which is implemented is incomplete, however there is too little information present which
leads to the challenges of completing the OM strategy not being identified (3). These challenges are not
identified as the Marconi network does not know which subjects need research to complement the OM
strategy. These subjects are referred to as the obsolescence landscape (4).
The problem of the network having a limited inventory(7) is also a problem which needs to be solved but
this is beyond the scope of my research. Due to the problems stated at 5,6 and 7, a delay in maintenance
will occur (8) which leads to a decreased availability rate (11) and missions which get interrupted or
extended (9). The interrupted or extended missions will result in higher costs.
There is insufficient research about the obsolescence landscape and the challenges
there are to implementing an optimal OM strategy.
After the core problem was identified, I discussed with both my supervisor from Thales and my supervisor
from the university that I would identify one subject which would be researched in depth. This identified
subject is logistical obsolescence, as literature can be found on this subject and information about this
subject is present at both companies. This is important as the time which can be spend on this thesis will
be too short when a subject needs to be researched but information is limited or not available.
12
1.3. Problem approach
This chapter presents the approach on how the research goal stated in chapter 1.2 will be achieved. To
achieve the research goal, knowledge questions will be formulated. These knowledge questions will
provide a roadmap of coming to a solution for the research goal. The MPSM, Managerial Problem Solving
Method, which is invented by Heerkens (2012), is used as a guideline to come to the solution of the core
problem and thus achieving the research goal. The MPSM consists of the problem identification,
formulating the problem approach, the problem analysis, formulating the alternative solutions, the
decision, the implementation and the evaluation. This thesis is a fundamental research, which is a research
with the aim to gain an advancement of knowledge (Horváth, 2007), where this knowledge can be used as
input for an action research (Pradeep, 2018). As this is a fundamental research, the last three steps are
not directly applicable, but are replaced for this research by proposing solutions and follow up projects,
and validating them with experts.
Before the current situation of the network concerning obsolescence can be visualized, the methods to
identify which information is needed, and how this information should be visualized, need to be
researched. To identify which information is needed, the research question from the network will be
analysed. The network would like to obtain a clear overview on how to implement a complete proactive
obsolescence management strategy. To obtain this overview, the first step is to research what is needed
for an organization to implement a complete proactive OM strategy and which adaptions are needed to
do so. To obtain this information, the following knowledge question needs to be answered:
• What is needed to implement a complete OM strategy?
The second is step is to identify a method which would provide a roadmap on how the information should
be visualized. After a brief research on methods which provide a roadmap to visualize the current and the
desired situation, a gap analysis would be best applicable to this research, as it is an academic research
method, provides a roadmap on how to conduct a gap analysis and has multiple successful examples on
why the method proves to be the best choice. To use the gap analysis within this research, an answer must
be found on the knowledge question:
• What is a gap analysis and how can this be used?
The information which will be depicted in the first part of the gap analysis, the current and desired
situation, consists of a comparison between the literature found on the subjects within the logistical
obsolescence domain and the current status within the network. The logistical obsolescence domain
should be split up into separate subjects which will be researched separately. The following knowledge
questions should be answered to provide this overview of the current status:
• What is the optimal state of the subjects within the logistical obsolescence domain following the
literature?
• What is the current state of the subjects within the logistical obsolescence domain?
13
After the current situation is visualized, the desired situation needs to be identified. The bottlenecks in
completing the OM strategy need to be identified, which will lead to the situation where the gaps could
be identified. The step which is needed to identify the bottlenecks, is to compare the current situation
with the optimal situation found in the literature. Besides this comparisons should the employees be asked
which bottlenecks they identify to make to next step in implementing the complete proactive OM strategy.
To solve these bottlenecks, the challenges in solving need to be identified and if possible follow up projects
should be identified. This information will be the first part of the deliverables of this research, and is
obtained by answering the following knowledge questions:
• Which bottlenecks are there in completing the OM strategy?
• What are the possible challenges/follow up projects?
These challenges and follow up projects should also be identified for the other subjects of the
obsolescence landscape, as the relevant stakeholders, who need to make a decision on which follow up
projects should take place, are able to construct a list in which they can give their priority preference in
follow up projects. This priority should be identified after a validation on the research is conducted. This
information will be the second part of the deliverables, and is obtained by answering the next knowledge
questions:
• Which subjects are unidentified but are part of the obsolescence landscape?
• How do I prioritize the follow up projects?
The levels on which a business can be present regarding obsolescence management can be found in figure
1 (Romero Rojo, 2010). A proactive obsolescence strategy begins at level three where the essentials are
present such as obsolescence managers and the use of obsolescence monitoring tools. Thales is at this
point in time in the transition from level 3 to level 4, as obsolescence is assigned in the stadium before the
production has started. The missing activities of having a complete proactive OM strategy imbedded in
the company will be explained at the end of this thesis and how to come to a solution. Proactive solutions
used in a proactive OM strategy to mitigate the risk of obsolescence are design considerations, technology
transparency, partnering agreements with suppliers, a lifetime buy, obsolescence monitoring and a design
refreshment planning. These proactive solutions are elaborated on in chapter 2.3.
14
DMI is performing somewhere between level 1 and 2, which could be classified as a reactive obsolescence
management strategy. A reactive obsolescence management strategy is a strategy where there will only
be reacted to a case of obsolescence when the item is needed and has been declared obsolete. When this
obsolescence issue has been communicated, the relevant company (or companies) will react to the issue
with a resolution strategy to limit the consequences of the obsolete item. Examples of such a reactive
solution are reclamation (cannibalization), emulation, a design change or a life time buy. These examples
and the other reactive solutions are elaborated on in chapter 2.3.
To determine which parts are of more importance in relation to other parts or components, a ranking
should be made. A proactive mitigation method should be used for the parts with the highest ranking to
reduce the consequences of the obsolescence.
15
As the knowledge was limited, the questions which needed to be asked had several follow up questions,
or needed an extended explanation from the interviewee. Following from a research which was conducted
prior to this research, in the form of an essay, four criteria points were identified which determined what
sort of data gathering technique is best suitable for the situation. The criteria points are an in depth survey
versus a broad survey, the choice of interaction, the consideration of low costs, high quality or a high
response rate and the fourth criteria is the choice for open and closed questions. By comparing the
situation at the start of the research and the knowledge about data gathering, the choice for interviews
was substantiated.
Another mean of gaining the knowledge about the desired state is through a literature study. By identifying
the subjects which are not specified by the employees, the desired state can be extended by results which
are not researched yet in the business. The employee performance of the desired state consists of the
knowledge or skills which are not present yet to achieve the desired operational results. Whether this is
an issue will be identified in the interviews.
The current situation is identified in the same manner. Within the current situation it is important to gain
information from both businesses as there could also be a difference in the statement of employees from
both companies. By combining these two elements the current performance of the network can be
defined.
When the current state and the desired state are measured, the gap can be identified. A downfall of the
analysis could be when there is already a solution in mind before executing the analysis. By having the
solution in mind the outcomes will be biased and will more likely tend to a support of the solution instead
of the intended gap analysis. (Rose, Anastasia & Kiyoshi-Teo, Hiroko, (2017)) The improvement points
which will follow from the gap will be the starting points of the follow-up projects.
16
2. Theoretical framework
This chapter discusses what would be the best
practice of implementing a proactive obsolescence
management strategy within an organization,
following the found literature. This chapter
elaborates on the subjects which are identified as
the processes of which the strategy is composed of.
These subjects are the risk assessment (Chapter
2.1), the obsolescence monitoring (Chapter 2.2)
and the solutions to obsolescence (Chapter 2.3).
17
2.1.3. Step 3: Extract and filter the Bill of Materials
The actual risk assessment can start after the first two steps are completed. The BOM (Bill of Materials)
should be present for the obsolescence manager who will perform the risk assessment. The BOM will
contain systems or equipment which should first be divided in the components of which the system has
been made of. By breaking the system or equipment down to a component level the obsolescence
engineer will have a detailed view on the BOM which is needed for the next step.
The next step is identify the low risk components which need no further investigation to determine that
these are low risk components. By filtering these components out the obsolescence manager should
prevent the making of a complete risk assessment for components that obviously do not need some form
of monitoring or solution to obsolescence, and thus saving time and extra costs. Rojo et al. (2012) uses the
following criteria to filter out the low risk components:
• Mechanical components, for instance screws and bolts.
• Components with a standard design. A standard design represents a design where standard
connectors are integrated, an architecture with public known specifications and which is modular.
• The YTEOL, Years Till End Of Life, is eight or higher.
• Passive components. These components do not require energy to operate.
It is of importance to investigate whether these components have only one manufacturer or whether the
system will not work without these components. If a component is subject to one of these criteria the
component should be further investigated in the risk assessment.
The first part of determining the probability of becoming obsolete will be a comparison between the
consumption rate and the available stock. If there is a high level of stock and a low consumption rate the
comparison should be assessed as low. When the consumption rate and level of stock are on the same
level, for instance both low or both high, there is a medium level assessed to the comparison. When the
consumption rate is high and the stock level is low the obsolescence risk is assessed as high.
The second part could either be the YTEOL or the number of manufacturers who are present for the
selected component. This depends on the information which is present. A YTEOL of less than two years
yields a high risk obsolescence level, between two to five years a medium level and more than five years
has a low risk level of becoming obsolete. One manufacturer present for the selected component
represents a high level of obsolescence, two manufacturers a medium level and more than two
manufacturers represent a low risk level regarding obsolescence.
The impact of the obsolescence on the system consists of the potential loss of capability or availability of
the system. Rojo et al. (2012) constructed the following criteria to resemble the different levels of risk: a
high level of obsolescence risk is specified as safety critical, mission critical resembles the medium level
and all other criteria could be referred to as a low risk regarding obsolescence.
To determine the level of obsolescence risk, both parts of the risk analysis should be combined. First a
matrix should be conducted to determine the probability of a component becoming obsolete.
18
This matrix is made by combining the comparison between the consumption rate and the level of stock,
and the YTEOL or the available number of manufacturers. The highest level of risk of the YTEOL or the
impact should be on the axis if both numbers are present. This matrix is visualized in figure 7. After the
probability risk matrix is made the obsolescence risk matrix can be made by combining the probability risk
with the impact of the obsolescence. Figure 8 represents this matrix.
19
2.1.7. Step 7: Review
By reviewing the risk analysis the data will be updated. This is necessary as making decisions based on
outdated data would possibly lead to making the wrong decision. The recommended time period to have
the next risk analysis is a half year or one year. This depends on whether the manufacturing phase has
been completed. If this phase has been completed, the period of a year should be sufficient (Romero Rojo
et al., 2012).
Before obsolescence monitoring can be conducted it is necessary to determine the scope of the
monitoring. This scoping is done by defining the following points of interest:
• Who will perform the monitoring.
• The level on which the monitoring will be conducted. So component, LRU (Line Replacement Unit),
system level etc.
• How the monitoring will be conducted, which tools are being used, which processes will be used
etc.
• The communication of the monitoring, how will the results be presented, how many times per
year etc.
This chapter describes more in depth how the obsolescence monitoring is conducted, what the purpose
of the monitoring is and what will be done with the monitoring (2.2.1.). Besides the current executed
obsolescence monitoring, a method which calculates how well an organization is monitoring their parts is
explained (2.2.2.).
To ensure the notice of obsolescence to be on time to take proper measures, the obsolescence monitoring
should be conducted at a frequency which is appropriate for a company and corresponds to the outcomes
of the risk assessment.
These findings are described as triggers, which reach the organization. Product discontinuance notices
(PDN), End-of-life notices (EOL), Product change notices (PCN) and Lifetime Buy (LTB) notifications are
triggers which need to be followed up in time in order to analyze resolution alternatives. These triggers
should be evaluated and if necessary the change process should start. This process is explained in chapter
2.3.
20
Another form of monitoring is direct contact monitoring (IEC62402, 2019). Instead of triggers that reach a
company, the company has direct contact with the manufacturers. This contact could be contractually
agreed if applicable to ensure the update to be complete and in time. The data which should be in the
update are updated item support information, upcoming releases and related items, assessment of
manufacturer stability and planned item upgrades.
(𝐺 + 𝑌1)
𝑃𝐼 = 100 ∗
(𝐺 + 𝑌1 + 𝑅 + 𝑌2 + 𝐵)
Besides the result of the PI, the other attributes which need to be filled in within the equation are binary
numbers, ranking either zero or one. Ranking one means that the described situation is reached, zero
means that the current situation does not coincide with the described situation.
To indicate how well an organization scores on the health monitoring, the following scores of PI have been
determined by Bartels et al. (2012):
100 – 90 means that the organization performs optimal.
89 – 80 indicates that the organization is performing solid but there is room for improvement.
79 – 70 represents the situation that there is probably no solution on how to research the
unknown status parts yet.
69 – 55 indicates that the process of proactive obsolescence monitoring has just started and
measures should be taken to have a solid monitoring process present at the organization.
55 or less means that potentially catastrophically problems could occur.
2.3. Solutions
To react to an obsolescence issue, a resolution is used to mitigate the consequences of the issue. For an
obsolescence concern a proactive mitigation method can be used. There are two approaches to the issue
of obsolescence, a reactive and a proactive approach. The solution is chosen by analysing multiple factors,
where the proactive approach analyses both reactive and proactive solutions. The reactive approach only
considers reactive solutions. The factors which have influence on the decision are the probability of
obsolescence, the impact on the product/system and the costs, which have been described in chapter 2.1
about risk assessment. Within this chapter the resolution strategies (2.3.1) and mitigation methods which
are present (2.3.2.), are elaborated on.
21
2.3.1. Reactive resolution strategies
The reactive approach is the approach where a solution will only be provided after an obsolescence issue
has emerged. The solution following a reactive approach will be a strategy where the consequences of
the obsolescence issue are only mitigated. In paragraph 2.1.5 is explained that a reactive obsolescence
resolution strategy is used when the risk of obsolescence is low, as the resolution strategies which can be
used in this situation are less expensive in comparison to implementing a proactive mitigation method.
Explanation
To understand what the common resolutions and their particular considerations (IEC62402, 2019) are, a
short explanation is given below. The explanation on the resolution strategies is derived from the IEC62402
(2019) standard, which should be the standard in the terminology.
Existing stock: The conduct of an item search to find an alternate source for the same item from stock that
has been purchased from the manufacturer.
LTB (Last Time Buy): Following the description of the IEC, the current term of an LTB, or Last Time Buy, is
LNB, the Life of Need Buy. An LNB is the procurement of sub items sufficient to support the item
throughout its life cycle, or until the next planned upgrade.
Reclamation (Cannibalisation): This is the process of re-using items or components from other systems or
products which are unserviceable (Romero Rojo, 2010); each reclaimed item should be checked to see if
requalification is necessary (IEC62402, 2019).
Equivalent: These are items which are functionally, parametrically and technically interchangeable with
the obsolete item. This includes minor software security updates, which are backwards compatible. Minor
testing may be required to validate the use of an equivalent item.
Alternative: These are items that provide a limited parametric match, but which, after consultation with
the person or organization responsible for the design are an acceptable application specific alternative for
the obsolete item. This includes major software updates or changes (upgrades) that may result in use of
software provided by a different manufacturer, running on a different platform or operating environment,
and providing similar, but not identical functionality. Major testing may be required to validate the use of
an alternative item.
Authorised aftermarket: Items are produced through emulation, reverse-engineering, or design change,
that match the manufacturer’s specifications and satisfy customer/end user needs without violating the
manufacturer’s intellectual property rights, conducted by an organization. These items can also be
obtained from traders.
Emulation: This solution is a process that produces an equivalent item using either the original
specification or from characteristics gained from an in-depth examination of a working example of the
item to be replaced. In theory this solution could be applied by Thales.
Design change: A new design is done to resolve obsolescence by means of updating or upgrading the item,
as well as enabling the use of newer items. A design change should be considered when it is not possible,
practical, or cost effective to procure or emulate a substitute item. There are two levels of design change:
• Minor design change, for example: A subcomponent
• Major design change, for example: An LRU.
22
Costs and probability of reactive solutions
The base non-recurring costs of the resolution strategies used in a reactive obsolescence management
strategy can be found in figure 9, which are the result of research including broad expert opinions (Romero
Rojo, 2010). From this figure can be concluded that the costs for the major redesign are substantial higher
in comparison to the other types of reactive solutions. These costs are high as the new item needs to be
engineered, tested and implemented (Romero Rojo et al., 2011).
Figure 10 represents the distribution of using each obsolescence reactive solution per obsolescence
management level. These levels are explained in paragraph 1.3. Both figures 9 and 10 are a representation
of obsolescence resolutions in general in the defence sector (Romero Rojo et al., 2011). £14,580.90 of the
total average of £16,442 costs when operating on level 1 are generated by implementing a minor or major
redesign. Operating on level 5 generates an average of £5,065 of the total average of £7,620
To conclude, on average per obsolescence reactive resolution type, the costs for emulation and a minor
or major redesign are relatively high. By investing in a proactive OM strategy, where the desired situation
is to reach level 5, a decrease in average costs can be achieved as the probability to use a minor or major
redesign decreases per OM level.
Technology transparency: This method is a methodology which is based on the specification of interfaces
(IEC62402, 2019). This term is also referred to as hardware independent (North Atlantic Treaty
Organization (NATO), 2001), which means that the technology can still be used where it is possible that
every component can still be substituted (Seuren, 2018). A condition for this method is that the form, fit
and function is maintained (IEC62402, 2019), which represents the criteria on the design that is required
when the part is used as a replacement part (Bartels et al., 2012).
23
Design considerations: If obsolescence has been addressed at the design stage of the parts the costs in
the rest of the lifecycle concerning obsolescence will drop. For instance, regulations should be taken into
account. If future restrictions causes the part to become obsolete, the design of the part should be altered
to comply to the regulations (Schallmo, 2012). Another example could be the indication of a technology
which is highly likeable of becoming obsolete in the near future.
Partnering agreements with suppliers: If suppliers are contractually bound to keep producing the parts,
the risk of obsolescence has been mitigated. Only in case of a bankruptcy is obsolescence inevitable if
there are no other suppliers (Romero Rojo et al., 2009).
Design refreshment planning: By determining optimal points within the life cycle of a product for an
update of parts and/or replacement of obsolete items, the costs could be mitigated. These optimal points
are referred to as “just in time” moments, which are the moments immediately before the next production
(Zheng et al., 2015). By planning a design refreshment, long term mitigation methods can be implemented
as the planning ensures a time period without the loss of potential operating hours.
Risk Mitigation Buy (RMB): The procurement of items sufficient to support the product throughout its life
cycle, or until the next planned technology upgrade (JSP886) . Penalty and disposal costs, inventory and
procurement are the factors related to this proactive solution approach. (Venkatesan, 2014). This is also
referred to as a Life of Need Buy, or an LNB.
24
3. Actual situation
The obsolescence risk following the literature review is determined by the probability and the impact of
the obsolescence. The costs aspect, as is mentioned as one of the three criteria to assess when conducting
a risk assessment, is not integrated in this risk analysis. Thales integrated the costs aspect as a part of the
risk assessment.. When the component is already obsolete, a medium or a high supply risk level is
assessed. The matrix which resembles the probability of obsolescence, as is described in step 4 of the risk
assessment (chapter 2.1.4), could be extended in the assessment of Thales. The consumption rate versus
the level of stock is used in the impact of obsolescence. In this case, Thales, focuses on years till end of
stock.
3.1.2. DMI
Concerning the systems which Thales delivers at DMI, a risk assessment is not made by DMI. This is not
necessary, as Thales is the design authority who reports obsolescence concerns. Reporting by Thales is
done according to contracts, which leads to different ways of communication within multiple contracts
3.1.3. Bottlenecks
The risk assessment currently conducted by Thales results in a medium risk level in approximately 95% of
the time. The risk assessment is based on an expert opinion where only 6 attributes are used in the
determination of the level of risk. These attributes are the costs of solving obsolescence, YTEOL, number
of manufacturers, level of available stock, the criticality of the component for the functioning of the
product and the date, used to determine the impact. By integrating more attributes in the calculation of
the level of risk, the accuracy of the risk assessment could increase. Low and high levels of obsolescence
risk will be determined more frequently and reactive or proactive solutions can be implemented at an
earlier stage. As an example, figure 11 (Appendix 1) represents the attributes which Seuren (2018) used
to conduct a model on how to assess the risk of obsolescence.
25
3.2. Obsolescence monitoring
3.2.1. Thales
Thales is currently working with the described form of obsolescence monitoring. Approximately eighty
percent of the data which is needed for the monitoring is gathered from an external database and the
database from Thales in France, information provided by the own engineers and the present database at
Thales Hengelo. Between the external database and the database from Thales in France a big overlap could
occur. The remaining twenty percent of the data is requested from the suppliers of Thales.
Furthermore, customer-specific obsolescence reports are created and delivered according to agreed
contracts. The customer obsolescence report elaborates on detected obsolescence, its severity and the
impact, and already taken and planned corrective obsolescence actions. This means, e.g. that if a
component is no longer available, or its non-availability is imminent, and a Form, Fit and Function
replacement of the component is not available, it will be reported as obsolete.
On average fifteen triggers are reported at Thales per week, which affect around twenty products. Triggers
are notices that a component will be obsolete in a short period of time. On this part of proactive
obsolescence management, Thales is on the level of a solid performance. The results of this process are
stored in the OMIS (Obsolescence Monitoring Information System) and configuration management
systems. Decisions on the resolution are communicated with the customer in case of costs for DMI,
changes in the availability of spares or if there is an impact on maintenance.
The reviewing of the obsolescence monitoring was performed once a year in the beginning of the
implementation, but soon was discovered that this period was too long. In the actual situation Thales
reviews the obsolescence monitoring every 3 to 6 months. In the first initiation of this contract it was
decided that Thales would deliver a yearly report to DMI. After both companies experienced this time span
to be too long, the subject of obsolescence was added to the agenda of the telecom meeting, which takes
place once a month, where the obsolescence triggers are presented. After the resolution decision was
made, both companies agreed that DMI would specify the need of components and LRU’s, Line
Replacement Units, and Thales would investigate the available quantity and propose a resolution to the
issue. A big rapport is sent to DMI 1 times a year. In this report, the obsolescence issues and concerns are
stated, as well as the solutions.
3.2.2. DMI
DMI experiences the communication as rather late, which results in DMI to experience the time frame in
which to decide as too short. With the current amount of updates DMI is satisfied, however the
organization is not content with the information which is given. DMI recognizes that the triggers are
mentioned, but there were several times when the follow-up projects of actions are not elaborated on
enough, which leaves DMI uncertain about what is to happen next. To gain more insight in what is going
to happen, the decision moments within the life cycle of a component should be identified beforehand
and DMI should know when these moments are, in order for the organization to make sure there is enough
budget to make a decision. It is difficult for DMI to make a decision ad hoc when a trigger reaches them,
because the budget is predetermined at the beginning of the year. The money which is not spent
immediately will be withdrawn from the budget.
26
3.2.3. Bottlenecks
The bottlenecks which are identified are not within the execution of the monitoring itself, but within the
communication of the outcomes from Thales to DMI. Thales currently does not mention every
obsolescence issue which they encounter to DMI, as it would be a long list and could potentially cause a
disturbance on the side of DMI. Several issues will be take care of in Thales own supply chain and can be
handled with a Form Fit Function component replacement strategy. With this method of communicating
DMI thinks that Thales only has a reactive obsolescence strategy to all issues, although Thales explained
otherwise several times in more detail. Thales does have an incomplete proactive obsolescence strategy
and as problems follow which do not need a decision from DMI, DMI will not receive any information on
this matter. This causes a communication problem.
Another communication problem between Thales and DMI is identified in the update which Thales gives
to DMI. The mutual follow up plan has not mentioned or not elaborated on enough a couple of times, a
roadmap is missing, which leads to DMI being uncertain about what will happen next. Because this is
uncertain, DMI cannot budget for a possible decision which needs to be taken and when the decision point
is reached, DMI is unable to take a decision due to budget restrictions.
3.3. Solutions
3.3.1. Thales
As can be seen in figure 11, the current assessment of the resolution strategy at Thales is visualized when
a trigger concerning the end of life for a component arrives at Thales. This visualization is the simplified
representation of the actual resolution strategy. As a first step in solving an obsolescence issue, Thales will
investigate whether or not an equivalent or alternative item can be found. This type of resolution is
relatively cheap as can be seen in figure 11, and makes sure the system stays operational as no extra steps
are needed. This type of resolution is only relatively cheap if no requalification is needed. Requalification
is needed when an alternate component is not exactly the same as the original component and needs to
be requalified. This requalification assures that the design with the new component works as good as the
design with the original component. Requalification is mostly executed because of regulations made by
the government, to assure the safety of the machine or system (Bartels et al., 2012). The costs of a
requalification depends on the level of integration. A small or medium level increases the costs by a factor
of 1.36, a large level of integration increases the costs by a factor 2.46 and a very large level increases the
costs by a factor 3.58. A small level of integration relates to components that standalone and a very large
level are components that are fully integrated within the product (Romero Rojo, 2010).
After the option of choosing an alternative or equivalent item, the option of a life time buy is used, if
possible. This is determined after an impact analysis is made. This impact analysis consists of an estimation
of the expected new products and of the estimation of spare parts and repairs for the installed base and
the expected new products. After this analysis is conducted a decision has to be made whether or not it is
beneficial for Thales or the end user. If it is approved, an order will be made at the supplier. If it is not
approved, Thales will move on in the same decision tree as where a trigger is identified from the
obsolescence monitoring.
27
Figure 11, Flowchart of the decision for the resolution strategy LTB based on a trigger of EOL
notification
Following from the monitoring, as is explained in chapter 3.2, a trigger could be identified at Thales which
needs a solution, as can be seen in figure 12. The current level of stock is directly checked after the trigger
is identified. Same as with an EOL trigger, first the resolution strategies of an alternate or equivalent part
are considered. If no alternative or equivalent is available, Thales will investigate whether an authorised
aftermarket buy or an additional buy is available. In the case of an EOL trigger which cannot be solved by
the solutions presented in figure 11, this point in the flowchart is the starting point for finding the
alternative solution as depicted on the right side of figure 12.
If neither one of the previous mentioned resolution strategies is available, first the option of a minor
redesign will be considered. When there is no other choice, a major redesign is necessary to solve the
obsolescence issue. The solution will be discussed with DMI, who makes the final decision. The option of
an emulation is at this point considered by Thales after the option of a minor redesign, although is it not
present in the flowchart. This option is rarely used, following from an expert opinion less than in 1 percent
of the solutions. This is because Thales would be responsible to produce the part, which brings along extra
costs such as start-up costs, training of the employees etc. The reclamation resolution is not considered at
Thales, as this is a resolution strategy which should be executed by the end user. Only when the major
redesign would be the other solution, a reclamation is considered, as it would become a second-hand part
after a reclamation. When the major redesign would be too expensive, the reclamation solution will be
chosen. This solution, same as the emulation solution, is only used less than 1 percent.
28
Figure 12, Flowchart of the decision for a resolution strategy based on a trigger from the obsolescence monitoring
Thales is currently researching whether the mitigation strategies, as described in paragraph 2.3.2, would
be beneficial. Implementing one or several mitigation methods requires an investment. However, in the
current contract between Thales and DMI the distinction which company is responsible for these costs is
not specified. More information on the changing relationship between the companies can be found in
paragraph 4.2.4. The agreement with suppliers, on whether the supplier will remain to produce the
required component is something in which Thales is currently investing. By making new contracts with
subcontractors where this subject is integrated, as well as more clarity what the supplier wants to achieve
is the first mitigation option where Thales is focussing on. The need for more insight in the supply chain is
further elaborated on in paragraph 4.2.4.
3.3.2. DMI
In the current situation DMI only reacts to an obsolescence occurrence, which is communicated by Thales.
In the current situation the installation managers at DMI cannot follow an obsolescence policy because
there is none. Instead, these installation managers make individual agreements with the supplier, where
in consultation with the supplier a resolution strategy is chosen. This is done by following a general
roadmap. However, the installation managers need to make decisions depending on the situation and the
expert experience. By acting in this way, DMI is not capable of implementing a proactive obsolescence
management strategy in any way, as a more detailed guideline on how to handle obsolescence is missing,
especially before the obsolescence is identified.
3.3.3. Bottlenecks
The costs for the different resolution strategies have not always been exactly calculated because they
differ case by case, which could be a substantiated argument for the decision of a resolution strategy.
Paragraph 2.2.1. offers an overview on the average costs in the defence sector but such calculations of the
resolution strategies is missing at Thales right now. These costs are now estimated by investigating what
the costs were in the previously obsolescence issues and it is estimated by relying on an expert opinion.
As the costs cannot always be calculated precisely upfront, exact costs for different situations cannot
always be given.
29
Thales currently has developed an OMP, an Obsolescence Management Plan. Within this plan the
proactive solutions, which are explained in chapter 2.3, are integrated. However, in contrast to the
resolution strategies, a flow chart on the decision on which solution to use, and when, is missing right now.
This flowchart is missing because an overview on the costs of the mitigation methods is missing. Literature
exists about mitigation methods but at Thales there has not been research on which methods are proven
to mitigate the risk of obsolescence and are cost efficient. If these costs are identified, Thales and DMI
should investigate what costs each company is responsible for. This fact is unknown at the moment.
A detailed obsolescence policy is missing at DMI. There is no flowchart for what action to take if an
obsolescence issue or concern is presented at DMI. The actions of the installation managers are now based
on a general roadmap, the situation and the expert experience. As the obsolescence issues and concerns
are identified by the obsolescence monitoring, the time between the message with a proposal for the
solution and the decision time is short. DMI needs to budget for obsolescence and is unable to agree with
the proposal if there is insufficient budget for the proposal.
At the moment of the design of a component, obsolescence is an even more important factor which should
be thought of. At this moment in time, many characteristics of a component are taken into account for
identification of possible obsolescence concerns. When more characteristics are known, possibly a more
accurate future forecast and solution for specific situations can be identified on LRU, Line Replacement
Unit, level.
30
4. Desired situation
Within this chapter the bottlenecks, which are identified in the previous chapter, will be reviewed and the
possible solutions will be discussed. First the bottlenecks within the logistical obsolescence domain will be
discussed and which follow up projects should resolve the bottlenecks (4.1). Besides the logistical
obsolescence the knowledge gap will be elaborated on (4.2). In this paragraph the other subjects of the
obsolescence landscape are briefly explained and follow up projects are identified.
Calculations
The attributes which are used to determine the level of risk (Chapter 3.1) could be weighted more or less.
However, in the current risk calculation no weights are given to the various criteria. Additional to the new
implementation of the risk assessment, a research can to be conducted on acquiring the information
needed for the calculation of the risk. The calculation of the risk can be made by using the method
described in this chapter, but Seuren (2018) made a model in which another method is described to
calculate the risk of obsolescence. Within this method, Seuren (2018) describes that the subjects, which
altogether form the criteria, have weights assigned to them in order to distinguish the importance towards
obsolescence in relation to the other subjects.
Thales already considered to use this model but concluded that there are too many attributes which need
to be considered. Commissioned by RH Marine, Krol (2020) analysed the model and altered it to make it
applicable for RH Marine, where multiple attributes where taken out of the model. The model of Krol
evaluates 26 attributes, where the outcomes of the tool represents the reality in most cases, according to
experts. A similar study needs to be conducted at Thales to integrate the model. This leads to a follow up
project where a research will be conducted how the model of Seuren can be implemented within the risk
assessment of Thales and which attributes should be used.
The costs for the solutions for obsolescence (Chapter 2.3) are not always calculated at this moment at
Thales, so an overview of the costs is missing for both the reactive resolution strategies and the proactive
mitigation methods. Sometimes the prices of the solutions are delivered to DMI by price brackets. These
price brackets were presented to DMI as several solutions had to be implemented but the exact costs for
all separate solutions was not clear. The exact calculation would have been costly for DMI so price brackets
were presented to give an indication of the costs but to prevent making extra costs. As only rough costs
for all solutions can be identified, price cannot always be avoided.
The follow up project on a strategy for decisions on selecting the right resolution is already conducted at
Thales. Level 5 of the obsolescence management proactiveness strategy (paragraph 1.4.1.) describes that
obsolescence should be addressed at the design phase. The bottleneck on which characteristics are
possible obsolescence concerns (paragraph 3.3.3.) should be researched in a follow up project.
31
Flowchart proactive solutions
Because the costs of the proactive mitigation methods are not exactly known, an overview on which
proactive solution to implement is missing, due to two reasons. First the prices of the proactive solutions
need to be calculated, as is explained in the previous paragraph. Second, a method on how to assign the
appropriate proactive solution is not constructed. As no research has been conducted on implementing
proactive solutions within the network, a plan is missing, which ensures that a more cost efficient strategy
has been considered. After the costs of the proactive solutions are calculated, this plan should be
composed. A research needs to be conducted to compose this plan.
4.1.2. DMI
The bottleneck for DMI consists of not having an extensive obsolescence policy. At the moment, a roadmap
is present for the installation managers at DMI, as is mentioned in chapter 3.3. A subject of an
obsolescence policy, as identified by DMI, would be to add time brackets for making a decision. The time
brackets DMI wants to assign between the notification from Thales and the decision deadline depend on
the situation, where the urgency of obtaining a certain component is the key factor of determining these
time brackets.
By restricting the decision time, DMI would prevent that the solution, as will be proposed by Thales, will
become more expensive or the solution will become infeasible to execute. These time brackets should be
determined by a part of a research, which should be in collaboration with Thales. Within this research, the
subjects which should be covered in an obsolescence policy by DMI, must be determined and a flowchart
or detailed roadmap must be made.
4.1.3. Communication
The following bottlenecks are identified within the communication between the companies of the
network. As the relationship between the client and the company that manages obsolescence is changing,
the way of communicating is another subject which should be adapted to the changing situation.
At this moment, DMI is missing an overview on which obsolescence issues are solved. Thales proposed to
provide an overview in the meetings with DMI where the top five or top 10 obsolescence concerns or
issues are discussed. These concerns or issues could be suppliers who go suddenly bankrupt, skills
obsolescence, hardware obsolescence etc. These subjects are important to discuss with DMI during the
meetings to provide a complete overview. More on the relationship between a customer and the
organization that manages obsolescence can be found in paragraph 4.2.4.
32
4.2. Knowledge gap – Obsolescence landscape
As is described in chapter 1, about the obsolescence landscape, the other subjects besides the logistical
obsolescence should be identified. Within this chapter the subjects will be shortly introduced, as well as a
proposal on which further research is needed for the separate subjects.
Upgraded means that there is improved hardware or software with new functionality available.
Updated represents the situation where the existing software has been improved so errors or bugs are
eliminated.
As this world is rapidly changing, which has resulted in new warfare domains as the cyber and space threats
the RNLN (user) is facing, Thales and DMO should keep pace with the developments in technology in these
domains. However, not only the technology development in the new warfare domains is rapidly changing,
technology in all domains is improving and enhancing at a pace which cannot be supported by the current
obsolescence approach of the network. This is regarded as functional obsolescence by the network, on
which only a small amount of literature can be found. The found literature exclusively describes the
mitigation method of an technology refreshment plan, which is explained in Appendix 2.
To start the research on answering these questions, the case of the Spanish navy frigate F-100 and
Navantia, as is described by Sols, Romero & Cloutier (2011), should be investigated, as a similar solution
could be implemented at the RNLN and its suppliers. Another starting point of this research could be the
research of resilience. A definition of resilience has been described by Sols (2014): “Resilience is the ability
of systems to mitigate the severity and likelihood of failures or losses, as well as to be able to adapt to
changing needs and conditions, by responding appropriately.” (p. 26). More information can be found in
appendix 2.
33
4.2.2. Software obsolescence
A distinction in obsolescence could be made between hardware and software obsolescence. Software
obsolescence means that software is no longer supported. Making this distinction is a complex process, as
both hardware and software obsolescence could influence the other form of obsolescence. The different
types of software obsolescence are explained and a link to hardware/software, logistical and technological
obsolescence is made. After this link is made, the domains in which these types of software obsolescence
occur are discussed. To conclude, mitigation methods for software obsolescence are proposed in appendix
2.
The second area of software obsolescence is the skills obsolescence. In all areas of obsolescence, a skill
could become obsolete as knowledge is lost, which could also befall within a software obsolescence issue.
New programmers are likely to learn only the new coding language, as they will not be working with the
old one. However, as the older programmers retire, knowledge about the old coding language could be
lost. If an organization did not upgrade the software of all of their systems to the new coding language,
software obsolescence in the area of skills will most likely occur.
The third area consists of the problems at the development platform and tooling. The software which has
been developed within the organization itself could also become obsolete, where no solutions outside of
the organization can be found as it is made for the organization specific. Integration problems between
different departments could also be the cause of software obsolescence within this area.
The fourth and most common area of software obsolescence is the COTS software obsolescence, the
Customer Of The Shelf software obsolescence. This type of software obsolescence represents the inclusion
of software packages of (COTS) suppliers into the in-house developed software and the associated licenses
of this COTS software. The occurrence of this type of software obsolescence is due to the decision of the
supplier of the software to stop supporting the release of the software and/or continue with new software
products. The date of the decision is hard to predict for an organization which leads to a difficulty in
preventing the loss due to this type of software obsolescence. (Romero Rojo F. , et al., 2010)
The first area, media software, is directly related to logistical obsolescence. As this type is specified as parts
which are unavailable or inaccessible, the last part of this explanation is coherent to the explanation of
logistical software obsolescence as has been described by Bartels et al. (2012): “The ability to access the
software is limited or terminates”.
34
The second area, which is skills obsolescence, could be linked with hardware/software obsolescence. This
type of software obsolescence contains the issues which arise between software and hardware, as when
one type experience obsolescence the other type is directly affected. This is due to the fact that hardware
needs software to run and software should support the hardware for which it is coded. Following from
this issue the system could have a limited performance or could not perform at all (Bartels et al., 2012).
The third and fourth area of software obsolescence, the in-house software and COTS software
obsolescence, relate to technological software obsolescence, which consists of 2 parts. The first subject
includes the issues concerning purchasing such as being unable to purchase a legal copy of the required
software or when a supplier does not offer an extension of a software license. The second part represents
the situation when there is no option of technical support anymore or when updates for the software are
being discontinued. This second part can be linked with the explanation of both areas.
Domain
The types of software obsolescence, as were described in the previous chapter, describe the nature of the
software obsolescence and what the consequences of the obsolescence issue could be. The types of
obsolescence all occur somewhere in the range visualized in figure 17. The numbers one to four represent
the areas in which the types of software obsolescence could occur. For example, the Hardware/Software
obsolescence mechanism of the COTS software obsolescence is located at number 4, which represents the
relationship between software and hardware obsolescence. A complete research on how the types of
software obsolescence and the layers of a system, as depicted in figure 17, are connected is missing at the
moment.
35
Further research direction
As is stated by Rojo (2010), there is only a small amount of information on software obsolescence. To gain
an understanding of this subject within the network, the following three recommendations should be the
starting point for further research on this subject. The first recommendation is that a research should be
conducted on how the layers in figure 15 are connected. After this research has been conducted, the
current status of the software obsolescence at the four numbers, which make up the software domain, as
depicted in figure 13, should be researched.
The second recommendation on further research is to investigate what the costs of solving software
obsolescence are and what the costs of the mitigation methods are. Similar to logistical obsolescence,
these costs are not yet known within the network, whereas DMI would like a complete overview of the
possible costs for obsolescence. This is a part of the life cycle costs, which will be elaborated more on in
paragraph 4.2.3.
The third recommendation is to construct a flowchart for the mitigation methods for software
obsolescence. After the costs have been calculated, following the previous recommendation, the
mitigation methods could be ranked from least costly to most expensive which should be visualized in a
flowchart. Besides this flowchart, other possible mitigation methods should be searched for within the
literature on the subject of software obsolescence.
The second step will be for the OEMs to provide the RNLN with the lifetime buy costs of the relevant
products. The life cycle costs can be calculated according to the attributes proposed by Sandborn (2013),
as is depicted in figure 14. This cost estimation could also be made by using a commercial tool, such as
TruePlanning offered by Price or Seer by Galorath. However, it is difficult for the OEMs to calculate these
costs. For example, as is mentioned before in this thesis, the costs about the resolution strategies and
mitigation methods, for various types of obsolescence, are sometimes not exactly calculated but only
roughly estimated at Thales.
Even when these costs are calculated, it is hard to estimate the lifetime buy costs, as various factors could
have an influence on the life cycle costs. For example, the costs of a redesign of a component need to be
calculated, but also of the requalification of the component and the quantity of the components. Suppliers
who decide to stop producing a certain part of system, suppliers whom go bankrupt or a client who
changes its wishes concerning the requirements of a part or system, cannot be accounted for when
calculating the lifetime buy costs.
36
Figure 14, Lifetime Buy Cost, Sandborn 2013
The first step is to identify how the current state of obsolescence management is within both Thales
(product design authority applying Product Management) and DMI (Asset Owner and Asset maintainer
applying Asset Management). An important part of the current state is the information stream between
the companies but also within the companies themselves. Additionally to this part is the responsibility
which every person has in the obsolescence landscape. When these 2 parts are identified a conclusion can
be made whether this needs further research or whether this part is sufficient to support an environment
to implement the proactive OM strategy.
This information stream between the companies refers to the current state of the products and parts,
whether or not they are obsolete or if they have a potential of becoming obsolete. Next to the enhanced
insight, DMI would like to have more influence in the complete supply chain, and would like to be able to
make changes. The prices which will belong to the decision will depend on the deadline DMI sets for the
proposed change. When the change should be completed and/or implemented in a short period of time,
a higher price will be paid in contrast to when Thales, or a supplier of Thales, would have a larger time
span to complete or implement the required change proposed by DMI. Following from the theoretical
framework, the health monitoring could be an added value to provide an overview for DMI. A research
whether the result of the health monitoring outweighs the time which needs to be invested in the health
monitoring should conclude if the health monitoring is of added value.
37
At this moment there exists a gap between Thales and several suppliers on the subjects of forecasting and
planning. An example of this gap is when certain products can only be used for around five years, but the
contractor has not investigated which possible problems could occur and which possible solutions there
are to solve these problems. These contractors do not have a plan on what the organization of these
contractors wants to achieve in the coming ten years and how the organization will look like in ten years.
This is a problem when DMI wants to have an overview of the complete supply chain. Thales is currently
trying have these contractors to make roadmaps for the coming years by making new contracts in which
this topic is integrated.
38
5. Validation
Now that the bottlenecks and follow up projects are identified, it is important that this information is
validated with the expert opinions. The validation is needed for both the subjects within the obsolescence
landscape as for the bottlenecks and follow up projects of the logistical obsolescence subject. The subjects
of the obsolescence landscape are first validated by the experts of the Marconi project and secondly
validated by an expert panel consisting of employees of Thales. These employees of Thales will also
validate the findings within the logistical obsolescence domain.
Within the complete validation, the subjects will be ranked in order of importance on whether a follow up
project is needed. After these validations, 2 ranking methods are shortly introduced, where an excel sheet
is conducted in which these ranking methods can be filled in for the subjects within the obsolescence
landscape.
The first conclusion which can be drawn from this discussion is that the OEM’s of DMI first need to
investigate what the current status of OM is at the companies. This corresponds with chapter 4.2.3, where
the 5 levels of OM readiness are discussed. Besides the current status of the OM, the changing situation
of OM between the OEM and the client is brought up as a subject, where a more elaborate description of
this relationship is needed. This statement is directly related to chapter 4.2.4, where this bottleneck is
further explained. According to the present members of the Marconi project, these 2 subjects are
important to make the other subjects of the obsolescence landscape relevant.
Besides the representative of Boskalis, who states that logistical obsolescence is the most important
subject for Boskalis, the other companies identify the logistical, functional and software obsolescence as
equally important. Besides, the software obsolescence cannot be separated from the hardware
obsolescence, as is explained in chapter 4.2.2. Following from a short discussion at the meeting the
conclusion can be drawn that the software obsolescence is in fact essential as the other forms of
obsolescence are influenced by software obsolescence. A suggestion given in the meeting is to combine
the research of functional and software obsolescence, as they cannot be seen apart from one another and
little information is known about both subjects.
39
5.2. Expert panel meeting Thales
On the 29th of January a meeting took place where four experts were present for a panel meeting about
this research. Six experts were asked to attend and accepted the invitation, however due to circumstances
two experts were absent. The goal of this meeting was to discuss the findings within the logistical
obsolescence and to discuss the subjects of the obsolescence landscape. However, due to time limitations,
only the findings within the logistical obsolescence were discussed.
An important aspect which followed from a discussion during the meeting was the follow up from this
research and the previous researches in the subject of obsolescence. There is a plan to integrate the found
knowledge, to gain an insight of what is supported by the researches and to present the added value of
having the knowledge. However, at the moment this knowledge is unknown within the organisation.
The idea of reaching level five of the obsolescence readiness levels is not shared by the experts. The
opinion that is not the most cost efficient to be on level five is shared by three experts. One expert
expressed his concern that Thales first has to aim to have an organization where the reactive obsolescence
solutions are investigated thoroughly, that the costs for these solutions are clear and how the different
components relate to the obsolescence which occurs later in the life cycle. When this process is
streamlined, the other subjects should be investigated in his opinion. He did however agree that the
logistic obsolescence, especially the monitoring and solutions, and the relationship between asset
management, product management and obsolescence management subject which belong in the
obsolescence landscape.
The two present obsolescence engineers did not agree with the findings of this research. Their opinion is
that the requirements from DMI, the theory on obsolescence and the way of working at Thales are not
aligned and a plan on addressing all 3 opinions is missing. By comparing this statement to this research,
the conclusion of the current situation is the same, but the questionnaire missed clarity for the
obsolescence engineers. The other 2 experts agree with the proposed obsolescence landscape, and
defined the relationship between asset management, product management and obsolescence
management the most important subject, with the approach to calculate the capabilities of OEM’s as the
second most important subject.
40
Another suggestion, which was suggested by an obsolescence engineer, was to create an impact matrix,
similar to the probability matrix and obsolescence matrix (Chapter 2.1). The axes of this matrix would be
the criticality of the component and the date. The criticality is based on the experience of the obsolescence
engineer and the date resembles the date on when the (obsolete) stock will be running out. The amount
of days until the impact will determine the high, medium and low level of obsolescence risk. What the
exact amount of days should be for the different levels of risk should be discussed in an expert meeting.
The proactive mitigation method of an RMB could lead to multiple possible problems in the future
according to the experts. With an RMB the organization buys enough stock to support the component for
the complete life cycle of the component, or until the next upgrade, but there is no guarantee that the
component will still work after laying for years in a warehouse. Another problem that could occur is the
changings needs of the customer. When the customer decides that the product needs something else,
where the new plans do not contain the component. When the technology of the component is shared,
following the technology transparency method, this problem can be avoided. This solution is considered
at Thales, and the knowledge on how to make the calculation for the RMB is present. However, a validation
on the calculation can be improved, which could be a potential follow up project.
The information which DMI would like to receive from Thales is the subject where the experts encounter
multiple questions. As the life cycle costs are required by DMI, and the solutions to the obsolescence
concerns or issues can also be offered to DMI, the overview of the triggers will not be necessary anymore
according to the experts. When DMI would like more influence on in the supply chain, the life cycle costs
will become higher, but this factor cannot be considered in the calculation as it is unpredictable. The
questions whether DMI would like to receive the triggers and the calculation of the life cycle costs are
raised by the experts.
The upgrading of systems often requires extra costs for new trainings to train the employees to work with
the upgraded system, new handbooks are needed etc. By determining the optimal points of upgrading the
system, the costs can be reduced to the minimum following the design refreshment planning ideology
(paragraph 2.3.2). However, as these optimal points are not calculated at the moment, the total costs of
upgrading cannot be estimated accurately and therefore are often most likely to be higher than the most
efficient strategy on implementing upgrades.
To conclude, the experts at Thales would like to gain an insight where DMI identifies problems. Thales
identifies problems, as are explained in this research, but the problems that are identified by DMI are not
clear for the employees of Thales. Within this thesis, the problems of budgeting for DMI, the
communication problems etc. are identified but there are most probably more, smaller problems which
need to be identified. This question should be one of the first steps in the follow up project following the
experts. Besides the problems, the experts would like an overview on how much of the components and
systems DMI think they need in the upcoming years. This calculation should also be follow up project.
41
5.3 Priority list
As there is a disagreement about the priority in which order the follow up projects should be conducted,
two priority rules are programmed in excel. By filling in these priority rules, experts are able to state their
preference about the order of the follow up projects. The two priority rules which are programmed in
excel, are the hundred dollar test and the ranking method. These priority rules are not used at this
moment, as the meetings where the validation of the research were at the end stage of this research,
which resulted in a time constraint for every relevant stakeholder to fill in the excel file and to evaluate
these findings.
There are two situations where the 100-dollar test can be manipulated and the outcomes will not
represent the actual ranking. The first situation occurs when the test will be filled in a second run. When
the subject which a stakeholders identifies as a top priority scored low in the first run, the stakeholder will
be try to make the subject the top priority in the overall ranking by assigning too much units to the subject.
In this situation, the subject will be prioritized too much by the stakeholder too even it out in the overall
ranking. This will only happen when multiple stakeholders rank the subjects.
The second situation will also occur when a second run will be performed, as a stakeholder can assign
more units to a subject to rank it higher in the overall list, even when another subject is valued higher by
the stakeholder. The individual ranking of the stakeholder will not represent the actual ranking of the
stakeholder, but the overall ranking will be similar to the actual ranking of the stakeholder. As the 100-
dollar test is meant to provide an overview of the combined prioritization, the two situations should be
avoided. Therefore, the test should be run only once.
Ranking
The ranking principle is the most simple to represent the prioritization of stakeholders. By assigning a 1
to the most important subject and a n to the least important subject, a priority list can be composed. An
advantage in comparison to the 100-dollar test is that two or more subjects cannot be ranked equally
important. However, this can also be regarded as a disadvantage. Another disadvantage is caused by the
difference in importance, which cannot be visualized by the ranking principle. The ranking principle can
be manipulated comparable to the 100-dollar test. Therefore, the ranking principle should be run once
too (Aurum & Wohlin, 2005).
42
Figure 15, Explanation on chosen methods.
43
6. Conclusion
This chapter will provide a conclusion of the research, where the found bottlenecks and follow up projects
are summarized. The recommendations of this research are elaborated on, followed by a discussion.
6.1. Conclusion
This research is conducted to find a solution to the core problem and to identify follow-on research about
the obsolescence landscape and the challenges which there are to implementing an optimal OM strategy.
Thales and DMI are currently implementing a proactive OM strategy but the challenge is on how to make
this as efficient as possible.
Thales and DMI want to implement the most efficient proactive OM strategy to minimize the life cycle
costs. Besides high costs of solving obsolescence, the obsolescence could also lead to an interruption in
missions due to maintenance lateness, which is caused by a delay in solving an obsolescence issue. Since
the primary objective of DMI is to realise a 100% operationality the obsolescence must be solved before
maintenance lateness could occur. In the current situation Thales implemented the obsolescence
monitoring and the implementation of a proactive OM strategy is still under development. Within the
research the subject of logistical obsolescence is analysed where the following question is answered: What
are the challenges on implementing an efficient as possible obsolescence management strategy?
Through a gap analysis between the current and the desired situation, the points of improvement are
identified within the subjects of the risk assessment, the obsolescence monitoring and the solutions to
obsolescence. The analysis on the risk assessment results in an enhancement by implementing a model,
designed by Seuren (2018), where a modification is required to adjust the model to the situation at Thales.
Despite the obsolescence monitoring process operating according to the literature, the communication on
the outcomes is sometimes incomplete and the detailing of follow up plans are part of the ongoing
improvements in communication and decision making together with DMI.
Within the subject of the solutions to obsolescence, multiple gaps are identified. As calculations about the
exact costs of both the reactive and proactive solutions are missing, in some cases the estimated costs of
a solution are within a wide range. A more exact calculation or minimal margins aids in the decision on a
solution proposal, since DMI has to budget far in advance for obsolescence. The costs of the proactive
solutions are estimates. The existing plan on how to design for obsolescence can be integrated in a the
method to assign the most efficient proactive solution.
Currently DMI does not have an obsolescence policy for the situation where an obsolescence concern or
issues is reported by Thales. The installation managers of DMI handle these situation separately and
coming to a conclusion requires some time with the lack of an obsolescence policy. As the decision time
on a proposal for a solution from Thales requires more time, the proposed solution has a higher chance of
becoming unavailable and a more expensive solution is required to solve the obsolescence.
Besides analysing the logistical obsolescence, the subjects that need to be researched are identified and a
preliminary research is conducted. The subjects are the functional obsolescence, software obsolescence,
an approach to calculate the capabilities of OEM’s and the relationship between asset management,
product management and obsolescence management.
44
6.2. Recommendations
This paragraph summarizes the bottlenecks which are identified in chapter 3 and solutions for these
bottlenecks, discussed in chapter 4. The recommendations together form a construction to solve the main
problem. The order in which the recommendations should be researched should be determined by making
use of the excel tool.
Recommendation 1:
Start a research on the subjects of the approach on how to identify the capabilities of OEM’s and the
relationship between asset management, product management and obsolescence management. The
subjects complement one another on the subject of what the consequences are for the involved
companies when implementing a complete proactive OM strategy. The research on the capabilities of
OEM’s should start with the 5 levels of obsolescence readiness and a method on how to test on which
level the companies operate. A precondition for the research on these subjects is that the companies
within the network that contribute to the realisation of the end product, are present and informed about
this process.
Questions as who will be responsible for which costs, who will determine what solutions will be
implemented and what is the deadline on when the proactive solutions must be implemented, do not have
a clear answer at this moment. This research which aims on the organisational subject between DMI and
the suppliers such as Thales and sub suppliers should be researched as well.
The literature written by Romero Rojo et al. (2012) should be investigated to start this research.
Recommendation 2:
An obsolescence policy needs be developed at DMI to adequately react to the proposes on solutions from
Thales. At the moment the installation managers of DMI handle the obsolescence concerns and issues
coming in from Thales separately. By developing an obsolescence policy, the installation managers should
be able to react on a shorter term notice as the steps in the policy need to be checked in comparison to
the current situation where the situation needs to be investigated and researched. The exact sections
which should be included in the policy needs be investigated, but an elaborate roadmap on how to respond
to Thales when an obsolescence issue or concern comes in should be a part of it. Another section within
the obsolescence policy could be when the idea of having more influence in the supply chain is continued.
Recommendation 3:
Integrate the model of Seuren (2018) in the risk assessment and modify it so it complies to the system
Thales is working with, similar to the modification which Krol (2020) made for RH Marine. By enhancing
the risk assessment more components can be identified as low or high obsolescence risk and adequate
measures can be executed conform the risk level. The combination of the improved risk assessment and
the developed obsolescence policy will allow DMI to make faster decisions and prevent a solution from
becoming unavailable before the decision moment.
Recommendation 4:
A research on more exact calculations on reactive and proactive solutions can be conducted to minimize
the margins in the estimated costs. DMI needs to budget a vast time in advance on obsolescence, so a
calculation on the life cycle costs of a component is required. The calculations on the solutions are part of
these life cycle costs. A start on this research is to investigate how Romero Rojo (2010) calculated the
costs.
45
Recommendation 5:
The Marconi network has done no research on how obsolescence can be mitigated from the beginning of
a life cycle. Therefore, a research should be conducted which characteristics of products are vulnerable to
obsolescence and which products and components should be designed differently to mitigate
obsolescence.
Recommendation 6:
A plan on how to implement a method to assign the appropriate proactive solution has not been
composed, as the calculations on the prices are missing and the research of recommendation 5 has not
been conducted. When these 2 researches have been completed, a research on a plan how assign the
appropriate proactive solution should start.
Recommendation 7:
A research on software obsolescence should be conducted similar to this thesis. As only a limited amount
of research has been conducted on the subjects, the preliminary researches as described in appendix 3
should be the starting point to this new research. As opposed by the idea of the members of the Marconi
team, this research should be separated from the research on functional obsolescence. Software
obsolescence can be linked to other types of obsolescence, as is explained in paragraph 4.2.2., thus also
to functional obsolescence. This link is a part of the complete area of software obsolescence and should
be a part of the research, however the other parts of software obsolescence, such as the link with logistical
obsolescence, should also be a part of the research. To start the research, the following three
recommendations should be researched:
1. A research on how the layers in figure 13 are related and what the current status of software
obsolescence is at the four areas depicted in figure 13.
3. Construct a flowchart on the solutions for software obsolescence after the calculations on the costs are
finished.
Recommendation 8:
A research on functional obsolescence should be conducted. As only a limited amount of research has
been conducted on the subjects first of all the origin of the problem and the stakeholders related to the
subject should be clear. A start of this research should be to investigate the literature of Sols et al. (2011)
and Sols (2014) to answer the following four questions:
1. What is the impact on maintenance and service logistics (e.g. spare part supply) for DMI and Thales?
2. What are the consequences of more frequent upgrades for the RNLN in terms of less downtime and
better capabilities, etc.?
3. What are the pros and cons of more frequent and planned upgrades related to Obsolescence
Management?
4. What costs are implied when increasing the number of system upgrades?
46
6.3. Discussion
The recommendations are based on a gap analysis between the desired and actual situation. As the desired
situation is the literature review, the findings of the gap analysis cannot be tested in the actual situation
as the outcomes of the researches take time to be finished and the validation of these findings will be too
late to implement within this thesis.
The second discussion point is the opinion of the involved experts at Thales. These opinions do not
completely align with the proposed challenges as well as with the opinions of all the other experts on
obsolescence at Thales. In the expert panel meeting with the experts of Thales the transition to level 5 of
proactiveness is not a shared thought with all the experts yet. The supportability engineer stated that it is
important to first have the reactive OM strategy work as efficient as possible and only then the proactive
OM strategy can be implemented further. The product manager services, who has been discussing the
topic with RNLN multiple times, thinks that the transition to a proactive OM strategy is the first step which
needs to be taken and the literature supports this mindset.
To align the different points of views, a clear set of definitions is needed which is accepted by everyone
within the Marconi project. A start is made with a glossary with all relevant terms related to obsolescence,
which needs to be accepted by everyone and expended where possible. The next step is to convince all
stakeholders that the 5 levels of obsolescence management is a decent method to determine a roadmap
in obsolescence management between the different companies. To create the consistency between the
companies, an obsolescence policy following the guidelines of the IEC62402(2019) should be composed .
47
References
Amaral, L., & Faria, J. (2010). A Gap Analysis Methodology for the Team Software Process. 2010 Seventh
International Conference on the Quality of Information and Communications Technology, (pp. 424-429).
Porto.
Aurum, A., & Wohlin, C. (2005). Engineering and Managing Software Requirements. Heidelberg, Germany: Springer.
Retrieved from
https://dinus.ac.id/repository/docs/ajar/[Ayb%C3%BCke_Aurum_(Editor),_Claes_Wohlin_(Editor_)]_En(Bo
okFi.org).pdf
Bartels, B., Ermel, U., Pecht, M., & Sandborn, P. (2012). STRATEGIES TO THE PREDICTION,. Hoboken, New Jersey:
John Wiley & Sons, Inc.
Franklin, M. (2006). Performance Gap Analysis: Tips, Tools, and Intelligence for Trainers. American Society for
Training and Developtment.
Heerkens, J., & van Winden, A. (2012). Geen probleem, een aanpak voor alle bedrijfskundige vragen en mysteries.
Buren: Business School Nederland.
Horváth , I. (2007). Comparison of three methodological approaches of design research. International Conference
on engineering design, ICED'07 (pp. 1-11). Paris, France: Delft University of Technology .
Ministry of Defence. (n.d.). JSP 886 . The defence logistics support chain manual(Volume 7).
North Atlantic Treaty Organization (NATO). (2001). Strategies to Mitigate Obsolescence in Defense Systems Using
Commercial Components. The RTO Systems Concepts and Integration Panel (SCI) Symposium, (p. 270).
Budapest, Hungary.
Pradeep, M. (2018). Critical analysis on the fundamental and action research methods. Emerging areas of IT
applications in management, education and social sciences (pp. 226-232). Mangaluru, Karnataka, India:
Srinivas University.
Rode, K. (2014). Using Risk Mitigation Approaches to Define the Requirements for Software Escrow. Master thesis,
Rhodes University, Department of Computer Science. Retrieved from
https://research.ict.ru.ac.za/SNRG/Theses/Rode%202014%20Msc.pdf
Romero Rojo, F. (2010). Estimating the Cost of Obsolescence. PSS-Cost Project (p. 32). Cranfield University.
Romero Rojo, F., Roy, R., & Kelly, S. (2012). Obsolescence Risk Assessment Process Best Practice. 25th International
Congress on Condition Monitoring and Diagnostic Engineering. Journal of Physics.
Romero Rojo, F., Roy, R., Shebab, E., & Cheruvu, K. (2011). A study on obsolescence resolution profiles. Cranfield
University, Decision Engineering Centre, Manufacturing Department, Cranfield, UK.
Romero Rojo, F., Roy, R., Shebab, E., Cheruvu, K., Blackman, I., & Rumney, G. (2010). Key Challenges in Managing
Software Obsolescence for Industrial Product-Service Systems (IPS2). CIRP IPS2 Conference, (pp. 393-398).
Cranfield university.
48
Romero Rojo, F., Roy, R., Shehab, E., & Wardle, P. (2009). Obsolescence Challenges for Product-Service Systems in
Aerospace and Defence. 1st CIRP Industrial Product-Service Systems (IPS2). Cranfield University. Retrieved
from
https://dspace.lib.cranfield.ac.uk/bitstream/handle/1826/3845/Obsolescence_Challenges_for_Product-
Service_Systems_in_Aerospace_and_Defence_Industry-2009.pdf?sequence=3&isAllowed=y
Romero Rojo, F., Roy, R., Shehab, E., & Wardle, P. (2009). Obsolescence Challenges for Product-Service Systems in
Aerospace and Defence. 1st CIRP Industrial Product-Service Systems (IPS2) . Cranfield University.
Rose, A., & Kiyoshi-Teo, H. (2017). Fall Prevention practive gap analysis; Aiming for targeting improvement.
Medsurg nursing: official journal of the Academy of Medical- Surgical Nurses, 26.
Sandborn, P. (2013). Design for obsolescence risk management. Center for Advanced Life Cycle Engineering (p. 8).
University of Maryland: Elsevier B.V.
Schallmo, R. (2012). Clarifying Obsolescence: Definition, Types, Examples and Decision Tool. The 5th ISPIM
Innovation Symposium (p. 14). Seoul, Korea: ISPIM. Retrieved from
https://www.tandfonline.com/doi/full/10.1080/0740817X.2014.999898?casa_token=b5oImUneVqgAAAA
A%3Af74cBCRuJTa7iYcqM-KHhhKKttWBhxd7Hl0Y_f8C9h9fpgkig1CJHHfn2m7hONJTxskzGypwFoQ
Schallmo, R. (2012). Clarifying Obsolescence: Definition, Types, Examples and Decision Tool. The 5th ISPIM
Innovation Symposium (p. 14). Seoul, Korea: ISPIM.
Seuren, T. (2018). From reactive to proactive obsolescence management. Master thesis, Eindhoven university.
Retrieved from https://pure.tue.nl/ws/portalfiles/portal/101390794/Master_Thesis_Tim_Seuren.pdf
Seuren, T. (2018). From reactive to proactive obsolescence management. Master thesis, Eindhoven university.
Sols, A. (2014). Increasing Systems Resilience through the Implementation of a Proactive Technology Refreshment
Program. 2014 Conference on Systems Engineering Research (pp. 26-33). Kongsberg, Norway: Elsevier B.V.
Sols, A., Romero, J., & Cloutier, R. (2012). Performance-Based Logistics and Technology Refreshment Programs:
Bridging the Operational-Life Performance Capability Gap in the Spanish F-100 Frigates. Systems
Engineering, 422-432.
Venkatesan, M. (2014). Establishing link between product phase-out, spare parts and obsolescence management.
Hamburg, Germany: Technische Universitätt Hamburg-Harburg.
Zheng, L., Terpenny, J., & Sandborn, P. (2015). Design refresh planning models for managing obsolescence. IIE
Transactions, 1407-1423. Retrieved from
https://www.tandfonline.com/doi/full/10.1080/0740817X.2014.999898?casa_token=b5oImUneVqgAAAA
A%3Af74cBCRuJTa7iYcqM-KHhhKKttWBhxd7Hl0Y_f8C9h9fpgkig1CJHHfn2m7hONJTxskzGypwFoQ
Zheng, L., Terpenny, J., & Sandborn, P. (2015). Design refresh planning models for managing obsolescence. IIE
Transactions, 1407-1423.
49
Appendix 1
Figure 17, Overview of the considered attributes and their relationship towards their parent category, Seuren (2018)
50
Appendix 2
Functional obsolescence
The gap between the top line at a certain moment in time and the begin stage of that line in figure 1, which
has been described in chapter 1.1.1, is referred to as functional obsolescence and mainly consists of two
parts. These first part is obsolescence due to a new technology which causes the old technology to become
obsolete and the second part is new technology on an existing platform. These two parts could also be
described as respectively upgrades and updates. Next to updates and upgrades Thales also uses the term
upkeep.
Update: Maintaining the function inside the radar by means of using new technology, not implementing
new technology unless it is free to implement and perform maintenance to ensure the function and
technology keep running.
Upgrade: Maintaining the function by means of new technology, not implementing new technology unless
it is free to implement and performing maintenance to keep the function and technology running.
Upkeep: Maintaining the function inside the radar by means of using the original technology, performing
maintenance and to ensure that the function and technology keeps running.
51
Software obsolescence
In contrast to hardware resolution strategies, there are no standard reactive resolution strategies. This is
due to the fact that for solving the problem, the cooperation of the original supplier would be required.
Another possible solution involves the accessibility to a large amount of resources, which is sometimes
even inaccessible. Since an organization is depending on external factors which have a high probability of
being inaccessible, a standard reactive resolution strategy is missing.
Proactive solutions
In contrast to solving the problem of software obsolescence, mitigating methods could ensure a decrease
in costs of software obsolescence. A method for the calculation of the costs of software obsolescence is
not present at the moment, so the exact decrease in costs cannot be calculated. Various general mitigation
methods have been developed for software obsolescence, where some of these methods are explained in
the next paragraph. More strategies are developed but a research on which could be used best in which
situation is missing.
Open source software: by making use of the software offered in the open source environment, the
probability of software obsolescence will be mitigated as the support cannot stop in a short period of time.
However, as Thales and RNLN use software which is classified this option could be infeasible.
Technology roadmaps: When designing the software, the evolution of technology and the requirements
of the customer should be considered. Functional obsolescence, which is the term for this sort of
obsolescence, has been explained in paragraph 4.2.1.
Third party escrow: Within this mitigation method the source code will be handed over to a third party.
When the original software developer decides to stop the support, the third party can operate as the new
software support party. By making use of the model as proposed by Rode (2014), a suitable escrow
provider can be identified. This type of obsolescence mitigation could also be used for hardware.
Outsourcing development and/or maintenance of software: By outsourcing the development and/or the
maintenance of the software, the costs could be mitigated as skills are not necessary anymore within an
organization. A disadvantage of this mitigation method could be that an organization has no control over
the supplier anymore, which leads to an uncertainty about a possible software obsolescence issue.
Planned upgrades: By planning the upgrades of the software, the entire organization should have stored
the relevant data in a way, that it could be used within the upgraded software.
Contract for entire lifetime support: In order for an organization to prevent a supplier to discontinue the
support, the support for the entire lifetime of the software should be part of the contract with the supplier
(Romero et al. (2012)).