0% found this document useful (0 votes)
17 views34 pages

Summary - BFD

The document provides a comprehensive overview of various capital investment appraisal techniques, including NPV, IRR, MIRR, and payback period, along with examples and practice problems. It emphasizes the importance of using realistic assumptions for reinvestment rates in MIRR to avoid the misleading nature of IRR. Key takeaways highlight the strengths and weaknesses of each method, guiding decision-making in project evaluation.

Uploaded by

MUHAMMAD BASIR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views34 pages

Summary - BFD

The document provides a comprehensive overview of various capital investment appraisal techniques, including NPV, IRR, MIRR, and payback period, along with examples and practice problems. It emphasizes the importance of using realistic assumptions for reinvestment rates in MIRR to avoid the misleading nature of IRR. Key takeaways highlight the strengths and weaknesses of each method, guiding decision-making in project evaluation.

Uploaded by

MUHAMMAD BASIR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 34

Example:

Project cost: $1,000

Cash flows (3 years): $400, $500, $600

Discount rate (WACC): 10%

Answer:

IRR

NPV=

IRR

Modified IRR

Formula

Example Project Details


Initial Investment (Year 0): $10,000
Cash Inflows:

Year 1: $4,000
Year 2: $5,000
Year 3: $6,000
Finance Rate (Borrowing Cost): 8%
Reinvestment Rate (Earnings on Cash Inflows): 6%

Practice Problem (Test Yourself!)


Project X:
Initial Cost: $8,000
Cash Inflows: Year 1: $3,000, Year 2: $4,000, Year 3: $5,000
Finance Rate: 7%, Reinvestment Rate: 5%
Calculate MIRR.

4. Payback Period
What it is: Time to recover the initial investment.
Example:
Project cost: $1,000
Cash flows: $300, $400, $500, $600
Calculation:

Example:
PV of inflows = $1,227.65 (from NPV example)
Initial cost = $1,000

Practice Problem:
Budget: $1,500
Projects:
Project
P
Q
R
S
What’s the best combination?
*(Answer: P + S = $1,400 → NPV $560; or P + Q + R = $1,500
→ NPV $535. Choose P + S for higher NPV.)*

Answer:

P
S
Q
R
Budget: $1,500
Combination 1

Combination 2

Combination 2 is best combination.


APV=

Example: APV Calculation


Project:
Initial Investment: $1,000
FCF (Year 1-3): $400, $500, $600
Unlevered Cost of Equity (r₀): 12%
Debt: $500 at 6% interest
Tax Rate: 30%

APV=

Capital Investment Appraisal Techniques – Simplified


Guide
We’ll break down each method with examples and progress
to ICAP-level problems.

1. Net Present Value (NPV)


What it is: Calculates the present value of future cash
flows minus the initial investment.
Formula:
NPV=∑(CFt(1+r)t)−Initial InvestmentNPV=∑((1+r)tCFt)​

−Initial Investment
Decision Rule:
NPV > 0 → Accept project (adds value)
NPV < 0 → Reject project
Example:
Project cost: $1,000
Cash flows (3 years): $400, $500, $600
Discount rate (WACC): 10%
Calculation:
NPV=400(1.10)1+500(1.10)2+600(1.10)3−1000NPV=(1.10)14
00+(1.10)2500+(1.10)3600
​ ​ ​

−1000=363.64+413.22+450.79−1000= ∗∗+227.65 ∗∗=363.64


+413.22+450.79−1000=∗∗+227.65∗∗
Verdict: ✅ Accept (NPV > 0)

2. Internal Rate of Return (IRR)


What it is: The discount rate where NPV = 0 (break-even
return).
Decision Rule:
IRR > WACC → Accept
IRR < WACC → Reject
Example: Same project as above.
Solve for IRR where:
0=400(1+IRR)1+500(1+IRR)2+600(1+IRR)3−10000=(1+IRR
)1400+(1+IRR)2500+(1+IRR)3600−1000
​ ​ ​

Trial & Error (or Excel): IRR ≈ 23.4%


Verdict: ✅ Accept (23.4% > 10%)

3. Modified IRR (MIRR)


Why use it? Fixes IRR’s unrealistic reinvestment assumption.
Formula:
MIRR=(Terminal Value of Cash InflowsPV of Outflows)1/
n−1MIRR=(PV of OutflowsTerminal Value of Cash Inflows ​

)1/n−1
Example:
Reinvestment rate = 10%, Finance rate = 8%
Terminal Value = 400(1.10)² + 500(1.10)¹ + 600
= 1,634
PV Outflows = 1,000
MIRR=(16341000)1/3−1≈∗∗17.8 MIRR=(10001634 ​

)1/3−1≈∗∗17.8

4. Payback Period
What it is: Time to recover the initial investment.
Example:
Project cost: $1,000
Cash flows: $300, $400, $500, $600
Calculation:
Year 1: $300 (Remaining: $700)
Year 2: $400 (Remaining: $300)
Year 3: $500 → Only need $300 → 2.6 years
Decision Rule:
If company’s max payback = 3 years, accept.

5. Profitability Index (PI)


What it is: Measures value per dollar invested.
Formula:
PI=PV of Cash InflowsInitial InvestmentPI=Initial Investment
PV of Cash Inflows ​

Example:
PV of inflows = $1,227.65 (from NPV example)
Initial cost = $1,000
PI=1227.651000=∗∗1.23∗∗PI=10001227.65=∗∗1.23∗∗

Verdict: ✅ Accept (PI > 1)

6. Scenario & Sensitivity Analysis


What it is: Tests how changes in assumptions affect NPV.
Example:
Base Case NPV = $227.65
What if sales drop 20%?

New cash flows: $320, $400, $480


New NPV = $49.42 (still positive, but riskier).

7. Capital Rationing
What it is: Choosing projects under a limited budget.
Rule: Rank by PI (highest to lowest) and select within budget.
Example:
Project
A
B
C
Budget = $800 → Pick A + B (Total NPV = $320).

8. Advanced Techniques (APV, EIRR)


Adjusted Present Value (APV)
Formula:
APV=NPVUnlevered+PV(Tax Shield)APV=NPVUnlevered ​

+PV(Tax Shield)
Use: For projects with changing debt levels.
Equivalent IRR (EIRR)
Used in: Public sector projects (adjusts for social
costs/benefits).

ICAP-Level Practice Problems


1. NPV + IRR Conflict:

Project X: NPV = $100, IRR = 12%


Project Y: NPV = $80, IRR = 15%
WACC = 10%. Which to choose?
Answer: Project X (higher NPV).
2. MIRR Calculation:

Cash flows: -$1,000, $400, $600, $800


Reinvestment rate = 12%, Finance rate = 8%
Answer: MIRR ≈ 18.2%
3. Capital Rationing:

Budget = $1M. Projects:

A (Cost: $600K, PI=1.5)


B (Cost: $400K, PI=1.8)
C (Cost: $500K, PI=1.2)
Optimal Choice: B + A (Total PI = 3.3).

Key Takeaways
NPV = Best for absolute value.
IRR = Easy %, but can mislead.
MIRR = More realistic than IRR.
Payback = Simple but ignores time value.
Ready for mock questions? Or dive deeper into any
technique? 😊
show how to calculate IRR using two assumed rates
How to Calculate IRR Using Two Assumed Rates
(Trial & Error Method)
Since IRR is the discount rate that makes NPV = 0, we
estimate it by:
1. Assume two discount rates (one giving +NPV,
another giving -NPV).
2. Use linear interpolation to find the exact IRR.

Step-by-Step Example
Project:
Initial Investment = $1,000
Cash Flows (3 years) = $400, $500, $600
Step 1: Assume Two Rates
Rate 1 (r₁) = 20% → Try a rate that gives NPV > 0
Rate 2 (r₂) = 25% → Try a higher rate for NPV < 0
Step 2: Calculate NPV for Both Rates
At 20% (r₁):
NPV=400(1.20)1+500(1.20)2+600(1.20)3−1000NPV=(1.20)14
00+(1.20)2500+(1.20)3600−1000
​ ​ ​

Plugging in the numbers:


IRR=20%+(27.77×(25%−20%)27.77−(−52.80))IRR=20%
+(27.77−(−52.80)27.77×(25%−20%))=20%

+(27.77×5%80.57)=20%+(80.5727.77×5%) ​

eXPLAIN THIS IRR’s unrealistic reinvestment assumption


IRR’s Unrealistic Reinvestment Assumption –
Explained Simply
The Core Problem
The Internal Rate of Return (IRR) implicitly assumes that all
future cash flows generated by a project are reinvested at the
IRR itself. This is often unrealistic because:
1. IRR can be very high (e.g., 30%), but in reality, you
may not find other projects with such high returns to
reinvest in.
2. Market conditions change – actual reinvestment
rates (like WACC or bank interest) are usually lower.

Why This is Misleading?


Example: Two Projects with Same IRR but Different Reality

Project A:
Investment: $1,000
Cash Flows: $500 in Year 1, $500 in Year 2
IRR = 15%
IRR’s Hidden Assumption:
The $500 received in Year 1 is reinvested at 15% for
Year 2.
But if your actual reinvestment rate is just 5% (e.g., in
a bank), the true return is lower!
Real-World Calculation (5% Reinvestment):
Year 1: $500 → Reinvested at 5% → $525 in Year 2
Year 2: Another $500
Total Future Value = $525 + $500 = $1,025
Actual Annualized Return ≈ 12.2% (not 15%)
→ IRR overstates returns if reinvestment rates are lower.

How MIRR Fixes This


The Modified IRR (MIRR) lets you explicitly set:
1. Finance Rate (cost of borrowing, e.g., WACC).
2. Reinvestment Rate (realistic return on cash flows,
e.g., 5-10%).
Formula:

MIRR=(Terminal Value of InflowsPV of Outflows)1/


n−1MIRR=(PV of OutflowsTerminal Value of Inflows )1/n−1

Same Project A with MIRR (Reinvest at 5%):


1. Terminal Value = $500(1.05)¹ + $500 = $1,025
2. PV Outflows = $1,000
3. MIRR = (1025/1000)^(1/2) - 1 ≈ 12.2% (matches
reality!)

Key Takeaways
1. IRR’s Flaw: Assumes cash flows are reinvested at
IRR, which is often too optimistic.
2. MIRR’s Solution: Uses realistic reinvestment
rates for accurate returns.
3. ICAP Exam Tip: If a question asks
about reinvestment risk, IRR’s assumption is a critical
weakness!

Practice Question
Project B:
Investment: $2,000
Cash Flows: $1,000 Year 1, $1,200 Year 2
IRR = 18%
Q: If you can only reinvest at 6%, what’s the true annualized
return (MIRR)?
*(Answer: Terminal Value = $1,000(1.06) + $1,200 = $2,260
→ MIRR ≈ 6.3%)*
Need more clarification? 😊
explain MIRR fORMULA IN DETAIL AND GIVE AN DETAILED
EXAMPLE
Modified Internal Rate of Return (MIRR) – Detailed
Explanation with Example
The MIRR fixes IRR’s unrealistic reinvestment assumption
by explicitly defining two key rates:
1. Finance Rate (Cost of Capital): The rate at which
cash outflows (investments) are discounted.
2. Reinvestment Rate: The rate at which cash inflows
(profits) are reinvested.

MIRR Formula Breakdown


MIRR=(Future Value of Cash Inflows (Compounded at Reinv
estment Rate)Present Value of Cash Outflows (Discounted at F
inance Rate))1n−1MIRR=(Present Value of Cash Outflows (D
iscounted at Finance Rate)Future Value of Cash Inflows (Com
pounded at Reinvestment Rate))n1−1
​ ​

Where:
Future Value of Inflows (FVI) = Sum of all cash inflows
compounded at the reinvestment rate.
Present Value of Outflows (PVO) = Initial investment
(if no further outflows) or discounted at the finance
rate.
n = Project life in years.
Step-by-Step Example
Project Details
Initial Investment (Year 0): $10,000
Cash Inflows:

Year 1: $4,000
Year 2: $5,000
Year 3: $6,000
Finance Rate (Borrowing Cost): 8%
Reinvestment Rate (Earnings on Cash Inflows): 6%

Step 1: Calculate Future Value of Cash Inflows (FVI)

We compound each cash inflow to Year 3 (project end) at


the reinvestment rate (6%):
Year 1 Cash Flow ($4,000):

Compounded for 2 years (Year 1 → Year 3)


Year 2 Cash Flow ($5,000):

Compounded for 1 year (Year 2 → Year 3)


Year 3 Cash Flow ($6,000):

Already at Year 3 → No compounding needed


Total FVI = $4,494.40 + $5,300 + $6,000 = $15,794.40

Step 2: Calculate Present Value of Cash Outflows


(PVO)
Since the only outflow is the initial investment ($10,000 at
Year 0), PVO = $10,000.
(If there were later outflows, we’d discount them at
the finance rate (8%).)

Step 3: Apply MIRR Formula


MIRR=(FVIPVO)1n−1=(15,794.4010,000)13−1MIRR=(PVO
FVI)n1−1=(10,00015,794.40)31−1
​ ​ ​ ​

Interpretation:
The project’s true annualized return, considering a 6%
reinvestment rate, is 16.5% (vs. IRR’s unrealistic
assumption).

Comparison with IRR

Metric

IRR

MIRR

Conclusion: MIRR gives a more conservative and


realistic return estimate.

Why MIRR Matters in ICAP Exams?


1. More accurate than IRR for capital budgeting.
2. Reflects real-world reinvestment conditions (e.g., if
profits are kept in a bank at 6%).
3. Avoids misleading high returns from IRR’s flawed
assumption.

Practice Problem (Test Yourself!)


Project X:
Initial Cost: $8,000
Cash Inflows: Year 1: $3,000, Year 2: $4,000, Year 3:
$5,000
Finance Rate: 7%, Reinvestment Rate: 5%
Calculate MIRR.
*(Answer: FVI = $3,000(1.05)² + $4,000(1.05)¹ + $5,000 =
$12,957.50 → MIRR ≈ 17.4%)*
Need further clarification? 😊
Year 1: $300 (Remaining: $700) Year 2: $400 (Remaining:
$300) Year 3: $500 → Only need $300 → 2.6 years (How did
you calculate 2.6 Years please explain)
Calculating the Exact Payback Period (2.6 Years) –
Step-by-Step Explanation
When the payback period doesn’t land exactly on a full year,
we calculate the fractional year needed to recover the
remaining investment. Here’s how it works:

Given:
Initial Investment: $1,000
Cash Flows:

Year 1: $300 *(Remaining: $1,000 - $300 = $700)*


Year 2: $400 *(Remaining: $700 - $400 = $300)*
Year 3: $500 (But we only need $300 to fully recover
the investment)

Step-by-Step Calculation:
1. After Year 2, the remaining amount to recover
= $300.
2. Year 3’s cash flow = $500 (but we only
need $300 to hit payback).
3. Fraction of Year 3 needed to recover the final $300:
Fraction=Remaining AmountYear 3 Cash Flow=300500=0.6
yearsFraction=Year 3 Cash FlowRemaining Amount =500300
​ ​

=0.6 years
4. Total Payback Period = Full years + Fractional year

=2 years+0.6 years=2.6 years=2 years+0.6 years=2.6 years

Visual Timeline:
text
Copy
Download
Year 0: Invest $1,000
Year 1: +$300 → Remaining: $700
Year 2: +$400 → Remaining: $300
Year 3: Need $300 out of $500 → Takes 0.6 of the year.
Payback = 2.6 years.

Why This Matters for ICAP Exams:


1. Accuracy: Projects rarely pay back exactly at year-
end.
2. Exam Tricks: Questions often test whether you can
calculate fractional years.
3. Decision-Making: A shorter payback (e.g., 2.6 vs.
3.1 years) is preferred.

Practice Problem:
Project Y:
Initial Cost: $5,000
Cash Flows: Year 1: $2,000, Year 2: $1,500, Year 3:
$2,500
Calculate Payback Period.
Solution:
1. Year 1: $2,000 → Remaining: $3,000
2. Year 2: $1,500 → Remaining: $1,500
3. Year 3: Need $1,500 out of $2,500 → Fraction = 0.6
Payback = 2.6 years. (Same logic!)
Need another example? 😊
Scenario & Sensitivity Analysis. Please elaborate more with
short examples
Scenario & Sensitivity Analysis – Simplified with
Examples
1. Sensitivity Analysis ("What-If" for One Variable)
What it does: Tests how changes in a single input (e.g., sales
price, cost) affect NPV/IRR.
Example:
Project: Sell 1,000 units at $10/unit, variable
cost $6/unit, WACC = 10%.
Base Case NPV: $2,000.
Test Sensitivity to Price Changes:

Price/Unit

$9

$11

Key Insight: A 10% price drop cuts NPV by 40% → High


sensitivity!

2. Scenario Analysis ("What-If" for Multiple Variables)


What it does: Examines combinations of
changes (Best/Worst/Likely cases).
Example:
Project: Initial cost = $100K, 3-year cash flows.
Scenarios:

Scenario

Best Case
Base Case
Worst Case
Decision Rule: If Worst-Case NPV > 0, low risk.

Why This Matters?


1. Sensitivity: Identifies critical variables (e.g., price is
more impactful than cost).
2. Scenario Planning: Prepares for real-world
uncertainty (e.g., recession vs. boom).
ICAP Exam Tip: Expect questions like:
"If raw material costs rise by 15%, how much does NPV fall?"
(Calculate new cash flows and re-discount!)
Need a practice problem? 😊
Capital Rationing EXPLAIN WITH EXAMPLES
Capital Rationing Explained with Examples
Capital rationing occurs when a company has limited funds to
invest and must choose between competing projects
to maximize returns within the budget.

Types of Capital Rationing


1. Hard Rationing: External limits (e.g., no access to
loans).
2. Soft Rationing: Internal limits (e.g., management
sets a budget cap).

How to Allocate Funds?


Rank projects by Profitability Index (PI) or NPV per dollar
invested and select the best combination within the budget.
Formula:
Profitability Index (PI)=PV of Future Cash FlowsInitial Invest
mentProfitability Index (PI)=Initial InvestmentPV of Future C
ash Flows ​

Rule: Accept projects with PI > 1.0 (NPV > 0).

Example 1: Single-Period Rationing


Budget: $1,000
Projects:
Project
A
B
C
D
Step 1: Rank by PI (highest to lowest): A & B (tied) → C & D
(tied).
Step 2: Select within $1,000:
Option 1: A ($500) + B ($300) + D ($200)
= $1,000 → Total NPV = $370
Option 2: A ($500) + C ($400) + D ($200) = $1,100 (❌
Over budget)
Option 3: B ($300) + C ($400) + D ($200)
= $900 → Total NPV = $270 (Less optimal)
Best Choice: A + B + D (NPV = $370).

Example 2: Multi-Period Rationing


Budget: Year 0: $800, Year 1: $500
Projects:

Project

X
Y
Z
Constraints:
Year 0: X + Y + Z ≤ $800
Year 1: X + Y + Z ≤ $500
Optimal Combination:
X ($500) + Y ($300) → Year 0: $800, Year 1: $300
→ Total NPV = $400
Cannot add Z (exceeds Year 1 budget).
Key Takeaways
1. PI Ranking: Ensures highest returns per dollar
spent.
2. Budget Constraints: Multi-period rationing requires
checking limits for each year.
3. ICAP Focus: Exam questions often test optimal
project selection under rationing.
Practice Problem:
Budget: $1,500
Projects:
Project
P
Q
R
S
What’s the best combination?
*(Answer: P + S = $1,400 → NPV $560; or P + Q + R = $1,500
→ NPV $535. Choose P + S for higher NPV.)*
Need further clarification? 😊
Explain APV & EIRR in detail
Adjusted Present Value (APV) and Equivalent IRR
(EIRR) – Detailed Explanation with Examples

1. Adjusted Present Value (APV)


What it is: A valuation method that separates the value of a
project into:
1. Base Value (Unlevered NPV) – As if fully financed by
equity.
2. Value of Financing Effects (Tax shields, subsidies,
etc.).
Formula:
APV=NPVUnlevered+PV(Financing Benefits)APV=NPVUnlever
ed+PV(Financing Benefits)

Components of APV
1. Unlevered NPV:

Discount Free Cash Flows (FCF) at the unlevered cost


of equity (r₀).
Ignores debt (pure equity assumption).
2. Financing Benefits:

Tax Shield (PV of Interest Tax Savings):


Tax Shield=Debt×Tax Rate×Cost of DebtTax Shield=Debt×
Tax Rate×Cost of Debt
Subsidies/Grants: Present value of any government
incentives.

Example: APV Calculation


Project:
Initial Investment: $1,000
FCF (Year 1-3): $400, $500, $600
Unlevered Cost of Equity (r₀): 12%
Debt: $500 at 6% interest
Tax Rate: 30%
Step 1: Calculate Unlevered NPV
NPVUnlevered=4001.12+5001.122+6001.123−1000= ∗∗$227
.65∗∗NPVUnlevered=1.12400+1.122500+1.123600
​ ​ ​ ​

−1000=∗∗$227.65∗∗
Step 2: Calculate Tax Shield
Annual Interest = $500 × 6% = $30
Annual Tax Savings = $30 × 30% = $9
PV of Tax Shield (assuming perpetuity):
PV(Tax Shield)=90.06=∗∗$150∗∗PV(Tax Shield)=0.069 ​

=∗∗$150∗∗
Step 3: Compute APV
APV=227.65+150=∗∗$377.65∗∗APV=227.65+150=∗∗$377
.65∗∗
Conclusion: Debt financing adds $150 in value due to tax
savings.

2. Equivalent IRR (EIRR)


What it is: A modified IRR used in public sector
projects where:
Cash flows include social benefits/costs (not just
financial).
Discount rate adjusts for public opportunity cost.
Key Differences from IRR
Feature

Purpose

Cash Flows

Discount Rate

Example: EIRR Calculation


Public Highway Project:
Initial Cost: $10M
Annual Benefits (Social + Financial):

Year 1: $2M (reduced traffic)


Year 2: $3M (toll revenue)
Year 3: $4M (economic growth)
Social Discount Rate (SDR): 5%
Step 1: Find EIRR (where NPV = 0)
0=−10+2(1+EIRR)
+3(1+EIRR)2+4(1+EIRR)30=−10+(1+EIRR)2+(1+EIRR)23
​ ​

+(1+EIRR)34 ​

Solve numerically (or Excel):


EIRR ≈ 10.5%
Step 2: Compare to SDR (5%)
Since EIRR (10.5%) > SDR (5%), the project is socially
viable.

When to Use APV vs. EIRR?

Metric

APV
EIRR

ICAP Exam Tips


1. APV: Expect questions on tax shield
calculations and WACC vs. unlevered cost of equity.
2. EIRR: Focus on social vs. financial cash
flows and SDR.
Practice Problem:
A project has:
Unlevered NPV = $200
Debt = $1,000, Interest = 7%, Tax Rate = 25%
Calculate APV.
*(Answer: Tax Shield = $1,000 × 7% × 25% =
$17.5/year → PV at 7% = $17.5/0.07 = $250 → APV =
$200 + $250 = $450)*
Need further clarification? 😊
too complex. again teach PV & EIRR but in easy and
understanding way
**
too complex. again teach APV & EIRR but in easy and
understanding way
APV & EIRR Made Super Simple
1. APV (Adjusted Present Value) – Like a Discounted Burger
Meal
What it is: A way to value a project by separating its core
value (burger) from financing perks (free fries).
How it works:
1. Burger Value (Unlevered NPV):

Calculate project’s cash flows without debt (like a


burger’s base price).
Discount at equity cost (no debt).
2. Free Fries (Tax Shield):

Debt gives tax savings (like a coupon).


Calculate savings: Debt × Interest Rate × Tax Rate.
Example:
Project cost: $100
Cash flows (no debt): $120 → Burger Value = $20
profit
Debt: $50 at 5%, Tax: 20%

Yearly tax save: $50 × 5% × 20% = $0.50


Free Fries Value: $0.50 / 5% = $10 (forever savings)
APV = Burger ($20) + Fries ($10) = $30

2. EIRR (Equivalent IRR) – Social Project’s True Return


What it is: IRR for government projects where benefits aren’t
just cash (e.g., schools, roads).
How it works:
1. Include social benefits (e.g., reduced pollution,
jobs).
2. Use Social Discount Rate (SDR) (like a charity’s low
return expectation).
Example:
Build a park for $1,000.
Benefits:

Year 1: $300 (visitors)


Year 2: $500 (tourism boost)
Year 3: $400 (healthier community)
EIRR = The "break-even" rate making total benefits =
$1,000.

Turns out to be 8% (vs. SDR of 4% → Good project!).

Key Differences

Use

Focus

Math
APV Tip: Debt makes projects cheaper (like a discount).
EIRR Tip: If EIRR > SDR, the project helps society.

Real-Life Analogy
APV = Ordering a meal with a coupon (burger + free
fries).
EIRR = Donating to a food bank (less cash return, but
big social impact).
Need an even simpler breakdown? 😊
6/28/2025 12/3/2025 158

NPV= PV of Future Cash Flow- Initial Investment


NPV= 227.6483847

IRR using Interpolation Method


Npv @ LR 20% Npv @ HR 25%

27.78 -52.8

IRR using interpolation method

21.72%

MIRR (Terminal Value of cashinflow/PV of Outflow)^1/n - 1

(FV of Cash Inflow Compounded @ Revinvestment Rate/PV of cash outflow discounted @ Finance Rate) ^ 1/n -1

n= Project Life in Years


Answer
16%
16%

Answer:
Years Cash Inflow Remaining Cost
1000
1 300 700
2 400 300
3 500 -200 0.6
4 600

So, recovery period is 2.6 years.

Answer:
Profitabilty Index= PV of cash inflows/ Initial Investment
1.22765
If PI > 0 than accept the Project

Cost NPV PI
$600 $240 1.4
$500 $175 1.35
$400 $120 1.3
$800 $320 1.4

First we are
going to rank
these projects
in sequence of
Highest to
lowest PI

Cost NPV PI
$600 $240 1.4
$800 $320 1.4
$500 $175 1.35
$400 $120 1.3

PQR
1500 535
PS
1400 560

Unlevered NPV + PV (Financing Benefits)

Answer :
Unlevered NPV

Formula= FCF discounted @ cost of equity Less Initial Inv


182.8079446
PV (Financing Benefits)

Tax Benefits= 9
PV of tax benefits= 150
332.807944606414
Cost NPV PI
500 200 1.4
300 120 1.4
200 60 1.3
Key
Calculation Result
Assumption

Reinvests
Solves for
~22% at 22% (unre
NPV=0
alistic)

Reinvests
Uses explicit
16.50% at 6% (realis
rates
tic)
Change
New NPV
vs. Base
▼ $800
$1,200
(40% ↓)
▲ $800
$2,800
(40% ↑)
Sales Volume Price/Unit NPV

20% 10% $150K


0% 0% $100K
-15% -5% $60K
Initial Cost NPV PI
$500 $200 1.4
$300 $120 1.4
$400 $100 1.25
$200 $50 1.25

Cost
Cost (Year 0) NPV
(Year 1)
$500 $200 $250
$300 $100 $150
$400 $300 $200
Cost NPV PI
$600 $240 1.4
$500 $175 1.35
$400 $120 1.3
$800 $320 1.4
IRR EIRR
Public
Private projects
projects

Includes
Financial only social
impacts

Social
Discount
WACC/ROI
Rate
(SDR)

Key
Best For Advantag
e

Separate
Leveraged s project
buyouts, M&A risk &
financing
Captures
Government non-
infrastructure financial
benefits
APV EIRR
Governm
Companies with
ent/social
debt
projects

Tax savings Non-cash


from loans benefits

IRR +
NPV + Tax
Social
Shield
Benefits
ate) ^ 1/n -1

You might also like