New Nithin - TNJ

The document outlines the bill of quantities for the construction of Mr. Prabhu's residence in Peelamedu, Coimbatore, dated 24.03.2023. It details various construction tasks, materials, and associated costs, culminating in a total project amount of Rs. 25,50,000. The document includes specific descriptions of work such as excavation, concrete laying, brickwork, plastering, and electrical and plumbing installations.

Uploaded by

kelwin joseph
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views74 pages

New Nithin - TNJ

The document outlines the bill of quantities for the construction of Mr. Prabhu's residence in Peelamedu, Coimbatore, dated 24.03.2023. It details various construction tasks, materials, and associated costs, culminating in a total project amount of Rs. 25,50,000. The document includes specific descriptions of work such as excavation, concrete laying, brickwork, plastering, and electrical and plumbing installations.

Uploaded by

kelwin joseph
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 74

PROJECT NAME Mr.

Prabhu's Residence
PROJECT LOCATION Peelamedu, Coimbatore
DATE 24.03.2023
BILL OF QUANTITIES FOR THE PROPOSED RESIDENTIAL BUILDING, COIMBATORE
TOTAL
S.No DESCRIPTION OF WORK
AMOUNT
Excavate foundation in all kinds of soil including soft rock except hard rock requiring blasting part
1 return and spreading surplus earth within the site up to 1.5m depth . 18301
Cement concrete 1:5:10 (1cement, 5 sand, 10 hard blue granite stone metal 40mm and down gauge)
laid in layers not exceeding 1.5m each in depth well consolidated in foundation including necessary
2
shuttering, steps etc.all complete as directed. 44977
Gravel or Pallam sand filling for foundation sides and Basement including consolidation ramming
3 and leveling etc complete. Err:509

Cement concrete 1:4:8 (1 cement, 4 sand and hard granite stone metal 40mm and down gauge) laid
in layers not exceeding 15cms in depth well cosolidated in leveling course under floors including
4
necessary suttering of required profile all complete as directed. 111757

RCC M20 (Design Mix) Using hard blue granite metal 20mm and down gauge including centering,
5 curring etc., complete but excluding cost of reinforcement.
(a) Column Footing 41750

(b) Column
In Ground Floor 18788

( c) Plinth Beam 117137


(d) Basement Level Tie Beam 0

( e) Roof Beam
In Ground Floor 44297

(f) Roof Slab


In Ground Floor 207500

(g) Loft & Sunshade


In Ground Floor 19771

(h) Lintel Concrete


In Ground Floor 18819

(i) Sill level Concrete


In Ground Floor 0

Brick work with locally available best quality table moulded bricks of not less than 50 kg.sq.cm
6 crushing strength in cement mortar 1:6 mix (1cement, 6sand).
In Ground Floor including Basement 320998

Half brickwork with locally available best quality table moulded bricks of not less than
50kg/sq/cm crushing strength in Cm 1:4( 1 cement 4 sand) and reinforcement with two numbers of
6mm dia. M.S. rods at every fourth course embedded in cement mortar 1:4 (1cement, 4sand)for
partitinos
7
In Ground Floor Err:509
Ceiling plastering with CM 1:3 (1 cement 3 sand), 12mm minimum thick (sponge finish ) to ceiling
sides and soffit of beams and columns and other interior and exterior RCC surfaces not contiguous
8
masonry.
In Ground Floor 35432

Interior wall plastering with CM 1:5 (1cement, 5 sand), 12 mm minimum thick to all interior faces
of walls (sponge finish) including RCC sufaces not contiguous to masonry. Necessary intrenal
grooves of size 10mm x 10mm shall be carried out as shown /directed by engineer -in-charge.
9
In Ground Floor 77718

Exterior wall platering with CM 1:5 (1cement, 5 sand),( Sponge finish) 12mm minimum thick to all
external faces of brick walls including RCC surfaces not contiguous to masonry in all levels.
10
In Ground Floor 20649

Providing and 20mm thick granite slab of paradise shade / any other approved colour for counter
11 top and wash through including adge nosing, polishing etc., all complete as directed
Kitchen table 8795

Providing and laying 20mm thick machine cut and polished granite stone of approved shade in
teads and risers of steps and landing in CM 1:4 of minimum thickness 20mm jointed with white
cement slurry and pointing with matching pigments including rounding of nosing, rubbing,
forming grooves of required size in the plastering of side of steps and final polishing all complete as
directed Cost of granite : Rs. 150/sft
12
Entrance Steps 6765
Providing and laying first class vitrified tile of make Basic cost ( Rs 50/ Sft ) make Nitco / Johnson
of size 2'0" x 2'0" of approved colour in flooring over a bed of cement mortar 1:4 of minimum
thickness 20mm jointed with white cement slurry mixed with matching pigments all complete as
directed
13
In Ground Floor 65631

Providing and laying 12" X 15" or 12"x12" Ceramic tiles for floors in CM 1:4 with joints so as to
form a true even surface and joints finished neatly with white cement mixed matching pigments all
14
complete as directed. Cost of tiles : Rs. 40/sft
In Ground Floor Err:509

Providing and laying 12" X 15" from somany / Kajaria glazed tiles of approved colour wall
dadoing and floors in CM 1:3 with joints so as to form a true even surface and joints finished neatly
with white cement mixed matching pigments all complete as directed. ( Rate should include base
plastering with CM 1:5 of required thickeness) Cost of tiles : Rs. 40/sft
15
In Ground Floor Err:509

Providing and laying vitrified tile of make Basic cost ( Rs 50/ Sft ) make Nitco / Johnson of
approved colour of size 2'0" x 4" in CM 1:3 in skirting to form a true and even surface and joints
finished neatly with white cement mixed with matching pigments all complete as directed
16
In Ground Floor 6899

17 Providing shelves with cuddapah slab with regular intervals including labour & materials
Ground Floor Err:509
Grano flooring 40mm thick ( minimum) composed of one part of cement, one part of sand, 3 part of
wahed grade dry granite chiiping all to pass through 6mm mesh free from dust including finishing
surface smooth with power trowel including necessary shuttering or glass strips to form panel of
required size to be provided at no extra cost.
18
Terrace floor Err:509

19 Joineries
Supplying and fixing of wooden doors, windows and ventilators Including all mason labour charges and carpentry
charges

(a) Maindoor
In Ground Floor Err:509

(b) Other Doors (Flush)


In Ground Floor Err:509

( c) Toilet doors FRP


In Ground Floor Err:509

(d) Wooden Windows


In Ground Floor Err:509

20 Painting & Polishing Wooden joineries


Maindoor Polish GF Err:509

Other joineries Polish GF 3859

21 Painting
(a) Ceiling Area
Ground Floor 24402

(b) Inner Wall


Ground Floor 54348

( c) Exterior Wall
Ground Floor 12978

Electrical work and fittings including planning & laying of necessary roof and wall conduits (Concealed),
wiring, fixing of electrical switches including metal boxes with basic brands and providing with one light
22 fitting in each room.
Ground Floor 69291

Plumbing work includes, laying of Outer pipelines (exposed) with necessary chamber of standard sizes and
its top covers. Internal plumbing line (Concealed) with basic branded pipes. Also providing plumbing
23 fittings with basic brands(Basic model - White colour only) etc.,
Ground Floor Err:509

Other Works - LumpSum


1 Sump - brick work & 4.5" thickness of RC wall with deck slab & CI Manhole cover 96000

2 SepticTank with RR Masonry and deck cover slab Err:509

3 Elevation Work 25000

4 Gate fabrication and fixing and providing ramp with proper gradient & pillars Err:509

5 Over Head tank bed 5000


6 SS Handrails 19125

7 Coumpound Wall
Err:509

Total Amount - Rs.25,50,000/-


Say Rupees Twenty Five Lakh and Fifty Thousand Only
PROJECT NAME Mr. Prabhu's Residence
PROJECT LOCATION Peelamedu, Coimbatore
DATE 24.03.2023
BILL OF QUANTITIES FOR THE PROPOSED RESIDENTIAL BUILDING, COIMBATORE
TOTAL
S.No DESCRIPTION OF WORK QUANTITY UNIT RATE
AMOUNT
Excavate foundation in all kinds of soil including soft rock except hard rock
requiring blasting part return and spreading surplus earth within the site up
1
to 1.5m depth . 1408 cft 13.00 18301
Cement concrete 1:5:10 (1cement, 5 sand, 10 hard blue granite stone metal
40mm and down gauge) laid in layers not exceeding 1.5m each in depth well
consolidated in foundation including necessary shuttering, steps etc.all
complete as directed.
2 304 cft 148.00 44977
Gravel or Pallam sand filling for foundation sides and Basement including
3 consolidation ramming and leveling etc complete. Err:509 cft Err:509 Err:509

Cement concrete 1:4:8 (1 cement, 4 sand and hard granite stone metal 40mm
and down gauge) laid in layers not exceeding 15cms in depth well cosolidated
in leveling course under floors including necessary suttering of required
profile all complete as directed.
4 760 sft 147.00 111757

RCC M20 (Design Mix) Using hard blue granite metal 20mm and down gauge
including centering, curring etc., complete but excluding cost of reinforcement.
5
(a) Column Footing 250 cft 167.00 41750

(b) Column
In Ground Floor 113 cft 167.00 18788

( c) Plinth Beam 230 cft 510.40 117137


(d) Basement Level Tie Beam 0 rft 206.80 0

( e) Roof Beam
In Ground Floor 253 cft 175.00 44297

(f) Roof Slab


In Ground Floor 401 cft 517.00 207500

(g) Loft & Sunshade


In Ground Floor 86 sft 229.90 19771

(h) Lintel Concrete


In Ground Floor 91 rft 206.80 18819

(i) Sill level Concrete


In Ground Floor 0 rft 103.40 0

Brick work with locally available best quality table moulded bricks of not less
than 50 kg.sq.cm crushing strength in cement mortar 1:6 mix (1cement,
6
6sand).
In Ground Floor including Basement 1405 cft 228.55 320998

Half brickwork with locally available best quality table moulded bricks of not
less than 50kg/sq/cm crushing strength in Cm 1:4( 1 cement 4 sand) and
reinforcement with two numbers of 6mm dia. M.S. rods at every fourth course
embedded in cement mortar 1:4 (1cement, 4sand)for partitinos
7
In Ground Floor Err:509 sft 107.25 Err:509
Ceiling plastering with CM 1:3 (1 cement 3 sand), 12mm minimum thick
(sponge finish ) to ceiling sides and soffit of beams and columns and other
8
interior and exterior RCC surfaces not contiguous masonry.
In Ground Floor 976 sft 36.30 35432

Interior wall plastering with CM 1:5 (1cement, 5 sand), 12 mm minimum thick


to all interior faces of walls (sponge finish) including RCC sufaces not
contiguous to masonry. Necessary intrenal grooves of size 10mm x 10mm shall
be carried out as shown /directed by engineer -in-charge.
9
In Ground Floor 2174 sft 35.75 77718

Exterior wall platering with CM 1:5 (1cement, 5 sand),( Sponge finish) 12mm
minimum thick to all external faces of brick walls including RCC surfaces not
10
contiguous to masonry in all levels.
In Ground Floor 464 sft 44.55 20649

Providing and 20mm thick granite slab of paradise shade / any other approved
colour for counter top and wash through including adge nosing, polishing etc.,
11
all complete as directed
Kitchen table 30 sft 293.15 8795

Providing and laying 20mm thick machine cut and polished granite stone of
approved shade in teads and risers of steps and landing in CM 1:4 of
minimum thickness 20mm jointed with white cement slurry and pointing with
matching pigments including rounding of nosing, rubbing, forming grooves of
required size in the plastering of side of steps and final polishing all complete
as directed Cost of granite : Rs. 150/sft
12
Entrance Steps 30 sft 225.50 6765
Providing and laying first class vitrified tile of make Basic cost ( Rs 50/ Sft )
make Nitco / Johnson of size 2'0" x 2'0" of approved colour in flooring over a
bed of cement mortar 1:4 of minimum thickness 20mm jointed with white
cement slurry mixed with matching pigments all complete as directed
13
In Ground Floor 504 sft 130.35 65631

Providing and laying 12" X 15" or 12"x12" Ceramic tiles for floors in CM 1:4
with joints so as to form a true even surface and joints finished neatly with
white cement mixed matching pigments all complete as directed. Cost of tiles :
Rs. 40/sft
14
In Ground Floor Err:509 sft 107.25 Err:509

Providing and laying 12" X 15" from somany / Kajaria glazed tiles of
approved colour wall dadoing and floors in CM 1:3 with joints so as to form a
true even surface and joints finished neatly with white cement mixed matching
pigments all complete as directed. ( Rate should include base plastering with
CM 1:5 of required thickeness) Cost of tiles : Rs. 40/sft

15
In Ground Floor Err:509 sft 94.05 Err:509

Providing and laying vitrified tile of make Basic cost ( Rs 50/ Sft ) make Nitco /
Johnson of approved colour of size 2'0" x 4" in CM 1:3 in skirting to form a
true and even surface and joints finished neatly with white cement mixed with
matching pigments all complete as directed
16
In Ground Floor 111 rft 62.15 6899

17 Providing shelves with cuddapah slab with regular intervals including labour & materials
Ground Floor Err:509 sft Err:509 Err:509
Grano flooring 40mm thick ( minimum) composed of one part of cement, one
part of sand, 3 part of wahed grade dry granite chiiping all to pass through
6mm mesh free from dust including finishing surface smooth with power
trowel including necessary shuttering or glass strips to form panel of required
size to be provided at no extra cost.
18
Terrace floor Err:509 sft Err:509 Err:509

19 Joineries
Supplying and fixing of wooden doors, windows and ventilators Including all mason
labour charges and carpentry charges

(a) Maindoor
In Ground Floor Err:509 sft Err:509 Err:509

(b) Other Doors (Flush)


In Ground Floor Err:509 sft Err:509 Err:509

( c) Toilet doors FRP


In Ground Floor Err:509 sft Err:509 Err:509

(d) Wooden Windows


In Ground Floor Err:509 sft Err:509 Err:509

20 MS Handrails for Staircase with ornamental Works 21 rft 850.00 17850

21 Painting & Polishing Wooden joineries


Maindoor Polish GF Err:509 sft Err:509 Err:509

Other joineries Polish GF + Grill Painting 55 sft 150.00 8269

Cuddapah Slab Painting Work Err:509 sft Err:509 Err:509


21 Painting
(a) Ceiling Area - 2 coat Wall putty + 1 coat Primer + 2 Coat interior Emulsion
Ground Floor 976 sft 25.00 24402

(b) Inner Wall - 2 coat Wall putty + 1 coat Primer + 2 Coat interior Emulsion
Ground Floor 2174 sft 25.00 54348

( c) Exterior Wall - 1 Coat White wash + 1 coat Primer + 2 Coat exterior Emulsion
Ground Floor 464 sft 28.00 12978

Electrical work and fittings including planning & laying of necessary roof and wall
conduits (Concealed), wiring, fixing of electrical switches including metal boxes with
22 basic brands and providing with one light fitting in each room.
Ground Floor 69291

Plumbing work includes, laying of Outer pipelines (exposed) with necessary chamber
of standard sizes and its top covers. Internal plumbing line (Concealed) with basic
branded pipes. Also providing plumbing fittings with basic brands(Basic model -
23 White colour only) etc.,
Ground Floor Err:509

Other Works
1 Sump - brick work & 4.5" thickness of RC wall with deck slab & CI Manhole cover L.S 96000

2 SepticTank with RR Masonry and deck cover slab L.S Err:509

3 Elevation Work L.S 25000

4 Compund Wall @ 5'0" Height (basement upto Portico Level) with supply and fixing of 175 Rft 1250 Err:509
Gate fabrication and fixing and providing ramp with proper gradient & pillars
5 Soakpit For Kitchen, Bath amd septic Tank 3 nos 10000 30000

6 Outer Setback Area flooring, Washing Stone, Chambers L.S 30000


Total Amount Err:509

Total Amount - Rs.29,00,000/-


Say Rupees Twenty Nine Lakhs Only
PROJECT NAME - Mr.Prabhu's residence
PROJECT LOCATION - Meena Estate, Coimbatore
DATE - 01.09.2023

S.No Description of Work Area Unit Rate Amount


1 GF Utility + Staircase Area 105 Sft 2029325
2 Construction of First Floor 1305 Sft 2000 2610000
Front Side Drawing Class with Tile
3
Roofing 240 Sft 1100 264000
Soak pit ring erection for kitchen, bath &
4
S.T 1 nos 15000 15000
Demolition and conveyance of existing
5
structure L.S 35000
6 Elevation Charges L.S 30000

Total 4983325.2170833

Say Rs.32,75,000/-
Rupees Thirty One Lakhs Forty Four Thousand Only
S.No SPECIFICATION OF WORK
FOUNDATION - Pile Foundation (upto 20'0") with Pile Cap below Natural Ground
1 Level
2 BASEMENMT - Matching with existing basement Level
Basement Filling with earth and well gravel with Consolidation
3 SILL LEVEL 3'0" from Floor finish Level
4 LINTEL LEVEL - 7'0" from FFL
5 ROOF LEVEL - 10'0" From FFL
6 Concrete Grade M - 20 - For Framed Structure (stair area only)
First Floor Residence - Load Bearing Structure
7 Steel - Fe 550 Bars (Vizag/Indrola/iSteel)
8 Cement - ( JSW/Equivalent)
9 Brick Work - Flyash with IS Standard Specification
10 Drawing Class Room - AAC/ Light weight Block with 16" x 4" x 8" Size
Drawing Class Room - Roof will be with MS square tube frame and covered with Terracota
11 Roofing tile
12 Joineries
Main Door - Teak Wood with branded accessories*
Bedroom Doors - Readymade Flush Doors
Windows - UPVC with standard Size with MS square rod safety grill
Toilet Door -FRP Make
13 Plastering Work -
Ceiling Plastering in Cement Mortar Ratio 1:3 or 1:4
Wall Plastering in Cement Mortar Ratio 1:5
14 Roof Work
Grano Flooring with necessary gradient slope
15 Floor Finish
Vitrified Tiles of 4' x 2' of Cost Rs.50/Sft with branded Tiles*
Ceramic tiles for Toilet Floor with basic Cost of Rs.40.00/Sft (Branded*)
Glazed tiles for Kitchen & Toilet Walls with basic Cost of Rs.40.00/Sft (Branded*)
Black Granite for Kitchen Counter Top with basic cost of Rs.150/sft & 120/Sft for Staircase
16 Shelves using cuddapah Slabs for bedroom and Kitchen (necessary wide*)
17 Wall Finish
Inner - 2 Coat Wall Putty + 1 Coat primer + 2 Coat Emulsion Paint (Asian/Dulex/Nippon)
Outer - 1 Coat white wash + Primer + 2 Coat Exterior emulsion (Asian / Dulex/ Nippon)
18 Electrical Work
Concealed Roof and wall conduits with necessary switch points and light points incl. Light Fittings*
(Switches - GM/Legrand/Fybros Basic model White)
Wiring Work - Upto DB * (kundan/RR Kabe/Equivalent Brand)
17 Plumbing Work
Concealed Inner line and exposed outer line for Each toilet and Kitchen
Waste water line and solid waste line laying as per standard (Astral/Star/Ashirvad)
Supplying and Fixing of CP fitting and Sanitary Fittings (Parryware/Jaquar/Equivalent)
19 Handrails - SS 204 Grade
20 Compound Wall - Solid Block upto 5'0" height from portico Floor level
21 Gate with Contemporary Design using MS Rectangular Tube
22 Contemporary Style Façade Elevation*
23 Free Structural Consultation and details

Completion of Project - 6 Months From Commencement*

* Conditions Apply
PROJECT NAME - Mr.Prabhu's residence
PROJECT LOCATION - Meena Estate, Coimbatore
DATE - 02.09.2023

Rate/
S.No Description of Work
Area Unit Unit Amount
1 GF Utility + Staircase Area 2029325
Construction of First Floor and Outer
2
Staircase 1305 Sft 2100 2740500
Front Side Drawing Class with Tile Roofing
3
(Roof Area) 272 Sft 1100 299200
4 Soak pit ring erection for kitchen, bath & S.T
1 nos 15000 15000
Demolition and conveyance of existing
5
structure L.S 45000
6 Elevation Charges incl. 3D Design L.S 30000
7 Contigencies & any other Unforeseen Work
Total 5159025

Say Rs.34,95,000/-
Rupees Thirty Four Lakhs Eighty Two Thousand Only
S.No SPECIFICATION OF WORK
FOUNDATION - Pile Foundation (upto 20'0") with Pile Cap below Natural Ground Level
1
2 BASEMENMT - Matching with existing basement Level
Basement Filling with earth and well gravel with Consolidation
3 SILL LEVEL 3'0" from Floor finish Level
4 LINTEL LEVEL - 7'0" from FFL
5 ROOF LEVEL - 10'0" From FFL
6 Concrete Grade M - 20 - For Framed Structure (stair area only)
First Floor Residence - Load Bearing Structure
7 Steel - Fe 550 Bars (Vizag/Indrola/iSteel)
8 Cement - ( JSW/Equivalent)
9 Brick Work - Flyash with IS Standard Specification
10 Drawing Class Room - AAC/ Light weight Block with 16" x 4" x 8" Size
Drawing Class Room - Roof will be with MS square tube frame and covered with Terracota
11 Roofing tile
12 Joineries
Main Door - Teak Wood with branded accessories*
Bedroom Doors - Readymade Flush Doors
Windows - UPVC with standard Size (Openable) with MS square rod safety grill
Toilet Door -FRP Make
13 Plastering Work -
Ceiling Plastering in Cement Mortar Ratio 1:3 or 1:4
Wall Plastering in Cement Mortar Ratio 1:5
14 Roof Work
Grano Flooring with necessary gradient slope
15 Floor Finish
Vitrified Tiles of 4' x 2' of Cost Rs.50/Sft with branded Tiles*
Ceramic tiles for Toilet Floor with basic Cost of Rs.40.00/Sft (Branded*)
Glazed tiles for Kitchen & Toilet Walls with basic Cost of Rs.40.00/Sft (Branded*)
Black Granite for Kitchen Counter Top with basic cost of Rs.150/sft & 120/Sft for Staircase
Shelves using double side polished cuddapah Slabs for bedroom and Kitchen with edge nosing(necessary
16 wide*)
17 Wall Finish
Inner - 2 Coat Wall Putty + 1 Coat primer + 2 Coat Emulsion Paint (Asian/Dulex/Nippon)
Outer - 1 Coat white wash + Primer + 2 Coat Exterior emulsion (Asian / Dulex/ Nippon)
18 Electrical Work
Concealed Roof and wall conduits with necessary switch points and light points incl. Light Fittings*
(Switches - GM/Gold Medal/Fybros Basic model Great White)
Wiring Work - Upto DB * (kundan/RR Kabe/Equivalent Brand)
17 Plumbing Work
Concealed Inner line and exposed outer line for Each toilet and Kitchen
Waste water line and solid waste line laying as per standard (Supreme/Kauvery)
Supplying and Fixing of CP fitting and Sanitary Fittings (Parryware/Hindware/Equivalent)
19 Handrails for staircase & Balcony - SS 304 Grade
20 Outer Staircase - Finish with Tile Laying
21 Contemporary Style Façade Elevation*
22 Free Structural Consultation and details

Completion of Project - 7 Months From Commencement*

* Conditions Apply
S.
no Description of work Nos Length Breadth Depth Quantity Unit Rate Amount

A. GROUND FLOOR

1 Earth work excavation for Foundation


from natural GL incl. of excavated
earth all over foundation
Footing F1 10 5 ' 0 " 4 ' 0 " 5 ' 0 " 1000.00
1000.00 13.00 13000
Grade beam
All around Beam 1 120 ' 0 " 2 ' 0 " 1 ' 0 " 240.00
Cross walls 1 83.9 ' 0 " 2 ' 0 " 1 ' 0 " 167.80
407.80 cft 13.00 5301

2 Plain cement concrete in 1:5:10 mix


using 1.5" hard blue granite metal
including 2" sand filling ramming curing etc.,
Footing F1 10 5 ' 0 " 4 ' 0 " 0 ' 6 " 100.00
Plinth beam 1 204 ' 0 " 2 ' 0 " 0 ' 6 " 203.90
303.90 cft 148.00 44977
3 Reinforced cement concrete in
and 1:1.5:3 mix using 3/4" hard blue
granite metal including shuttering,
barbending,concreting and curing
etc complete.
a) Footing Concrete which including
barbending, erection & Concreting
incl. of material & labour charges
Footing F1 10 5 ' 0 " 4 ' 0 " 1 ' 3 " 250.00
250.00 cft 167.00 41750
b) Column
Column C1 10 1 ' 0 " 0 ' 9 " 15 ' 0 " 112.50
112.50 cft 167.00 18788
c) Plinth beam
PB1 1 204 ' 0 " 0 ' 9 " 1 ' 6 " 229.50
229.50 cft 167.00 38327
d) Basement level - Tie beam
All around Beam 0 204 ' 0 " 0.00
0.00 rft 206.80 0
e) Roof beam
Beam B1 (0'9"x1'6") 2 60 ' 0 " 0 ' 9 " 1 ' 6 " 135.00
Beam B2 (0'9"x1'6") 6 17 ' 6 " 0 ' 9 " 1 ' 6 " 118.13
253.13 cft 175.00 44297
f) Roof slab
Slab 1 Overall 1 17 ' 6 " 57 ' 6 " 0 ' 5 " 419.27
Staircase slab 1 3 ' 0 " 19 ' 0 " 0 ' 5 " 23.75
Deduction
Ground Floor Deduction 1 10 0 " 10 0 0 ' 5 " 41.67
Staircase Cutout 0 3 ' 0 " 10 ' 0 " 0 ' 5 " 0.00
401.35 cft 175.00 70237
g) Loft and Sunshades of 2" tk
W & KW 4 5 ' 6 " 2 ' 0 " - - 44.00
Loft - Kitchen & Dining 1 10 ' 0 " 2 ' 0 " - - 20.00
Kitchen Table 1 11 ' 0 " 2 ' 0 " - - 22.00
86.00 sft 175.00 15050
h) Lintel beam of 6" tk
Lintel Alround 9"wall 1 91 ' 0 " - - " - - 91.00
91.00 Rft 206.80 18819
i) Sill level concrete
Alround 0 221 ' 0 " - - " - - 0.00
0.00 Rft 103.40 0
4 9" Brick work in cement mortar 1:6
mix using Flyash table moulded
bricks including scaffolding,curing etc
Basement BrickWork
All Round 1 150 ' 0 " 0 ' 9 " 3 ' 0 " 337.50
Cross walls 1 63.5 ' 0 " 0 ' 6 " 3 ' 0 " 95.25
Super structure
All Round 1 150 ' 0 " 0 ' 9 " 9 ' 0 " 1012.50
Staircase Steps 19 3 ' 0 " 0 ' 6 " 0 ' 10 " 23.75
Deduction
Main door 1 3 ' 6 " 0 ' 9 " 7 ' 0 " 18.38
Window - W 2 4 ' 0 " 0 ' 9 " 4 ' 0 " 24.00
Narrow Window - NW 1 2 ' 6 " 0 ' 9 " 6 ' 0 " 11.25
Kitchen Window - KW 1 3 ' 6 " 0 ' 9 " 3 ' 0 " 7.88
Ventilator 1 2 ' 0 " 0 ' 9 " 2 ' 0 " 3.00
Net quantity 1404.50 cft 225.00 316013
5 6" Brick work in cement mortar 1:5
mix using well burnt table moulded
bricks including scaffolding,curing etc
complete.
Cross walls 1 63.5 ' 0 " - - 10 ' 0 " 635.00
Deduction
Toilet Door 1 2 ' 6 " - - 7 ' 0 " 17.50
Open 1 4 ' 0 " - - 7 ' 0 " 28.00
589.50 sft 220.00 129690
6 Refilling the basement with red gravel
and well consolidated with water
including all labour and material
charges complete.
Kitchen 1 16 ' 0 " 8 ' 0 " 5 ' 0 " 640.00
Living Room 1 16 ' 0 " 14 ' 6 " 3 ' 6 " 812.00
bed 1 16 ' 0 " 11 ' 6 " 5 ' 0 " 920.00
Toilet 1 1 4 ' 0 " 6 ' 0 " 5 ' 0 " 120.00
Portico 1 16 ' 3 " 15 ' 0 " 2 ' 6 " 609.38
Setback Passage 1 42 ' 0 " 2 ' 0 " 1 ' 6 " 126.00
Setback Passage 1 19 ' 6 " 2 ' 0 " 1 ' 6 " 58.50
3285.88 cft 20.00 65718
7 Ceiling Plastering in cement mortar
in 1:4 mix including scaffolding,curing
etc complete.
Kitchen 1 16 ' 0 " 8 ' 0 " - - 128.00
Living Room 1 16 ' 0 " 14 ' 6 " - - 232.00
Toilet 1 1 4 ' 0 " 6 ' 0 " - - 24.00
Foyer 0 6 ' 7.5 " 6 ' 0 " - - 0.00
Portico 1 15 ' 0 " 16 ' 3 " - - 243.75
Beam Soffits 1 96 ' 0 " 1 ' 0 " - - 96.00
Staircase slab 1 19 ' 4 " 4 ' 0 " - - 77.33
Soffits Door 1 17 ' 0 " 1 ' 0 " - - 17.00
Soffits Window 1 18 ' 0 " 1 ' 0 " - - 18.00
Loft(Dining) 1 16 ' 0 " 2 ' 0 " - - 32.00
Window Sunshade 4 5 ' 6 " 2 ' 0 " - - 44.00
Kitchen Table 2 16 ' 0 " 2 ' 0 " - - 64.00
976.08 sft 36.00 35139
8 Inner Wall plastering using gypsum
including scaffolding etc complete.

Basement Inner 1 278 ' 0 " - ' - " 5 ' 0 " 1390.00
Living Room 1 46.5 ' 0 " - ' - " 9 ' 6 " 441.75
Kitchen 1 32 ' 0 " - ' - " 9 ' 6 " 304.00
Toilet 1 1 23 ' 0 " - ' - " 9 ' 6 " 218.50
bed room 1 55 ' 6 " - ' - " 9 ' 6 " 527.25
Portico 1 62.5 ' 0 " - ' - " 9 ' 6 " 593.75
Stair area 1 16 ' 4 " - ' - " 9 ' 6 " 155.17
Soffits Door & open 1 1 ' 0 " - ' - " 7 ' 0 " 7.00
Soffits Window 1 68 ' 0 " 1 ' 0 " - - 68.00
loft -- Kitchen 1 10 ' 0 " 2 ' 0 " - - 20.00
Deduction
Main door 1 3 ' 6 " - - 7 ' 0 " 24.50
Toilet door 1 2 ' 6 " - - 7 ' 0 " 17.50
Stair area 1 10 ' 0 " - - 3 ' 0 " 30.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
Window 2 4 ' 0 " - - 4 ' 0 " 32.00
Kitchen Window 1 3 ' 6 " - - 3 ' 0 " 10.50
Narrow Window 1 2 ' 6 " - - 6 ' 0 " 15.00
Open 1 4 ' 0 " - - 7 ' 0 " 28.00
Net quantity 1390.00 sft 45.00 62550
2173.92
9 Outer Wall plastering in cement mortar
1:5 mix including scaffolding curing
etc complete.
Alround 1 150 ' 0 " 3 ' 6 " 525.00
Deduction
Window -W 2 4 ' 0 " ' " 4 ' 0 " 32.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
Narrow Window 1 2 ' 6 " - - 6 ' 0 " 15.00
Kitchen Window 1 3 ' 6 " - - 3 ' 0 " 10.50
463.50 sft 40.00 18540
10 Flooring concrete 1:4:8 Mix
including ramming consolidation
charges etc., complete
Living Room 1 14 ' 6 " 16 ' 0 " - 4" 232.00
Kitchen 1 16 ' 0 " 8 ' 0 " - 4" 128.00
bed 1 11 ' 6 " 11 ' 0 " - 4" 126.50
Toilet 1 1 4 ' 0 " 7 ' 6 " - 4" 30.00
Portico 1 15 ' 0 " 16 ' 3 " - 6" 243.75
Setback Passage 0 50 ' 0 " 1 ' 9 " - 4" 0.00
Setback Passage 0 12 ' 6 " 1 ' 9 " - 4" 0.00
760.25 cft 147.00 111757
11 Providing Granite slab for flooring
for Table tops & also for Staircase Steps
incl Full Nosing and all charges
Steps 0 3 ' 0 " 1 ' 6 " - - 0.00
Entrance Steps 2 5 ' 0 " 1 ' 6 " - - 15.00
Mid landing cross step 2 3 ' 0 " 3 ' 0 " - - 9.00
Door & Open Soffits 1 8 ' 0 " 0 ' 9 " - - 6.00
30.00 sft 225.50 6765
12 Black Pearl Granite Slab (cost 165/sft)
Kitchen table 1 12 ' 0 " 2 ' 0 " - - 24.00
Kitchen table Skirting 1 12 ' 0 " 0 ' 6 " - - 6.00
30.00 Sft 293.15 8795
13 Floor finishing with Vitrified Tiles (2'0"'x2'0")
over a cement mortar 1:6 mix including
laying and Finishing.@ 45.00/Sft
Living Room 1 14 ' 6 " 16 ' 0 " - - 232.00
Kitchen 1 16 ' 0 " 8 ' 0 " - - 128.00
bed 1 11 ' 0 " 11 ' 6 " - - 126.50
Soffits 1 17 ' 0 " 1 ' 0 " - - 17.00
503.50 sft 130.35 65631
14 Toilet Floor Tiles (basic cost Rs.40/-)
over a cement mortar 1:6 mix including
laying and Finishing.@ 40.00/Sft
Toilet Floor Tiles 1 4 ' 0 " 7 ' 6 " - - 30.00
30.00 sft 120.00 3600
15 Wall Tiles fixing work with cement paste
mortar using good quality tiles
of cost Rs.50.00/sft incl. all labour charges
Kitchen 1 20 ' 0 " - ' - " 4 ' 6 " 90.00
Toilet 1 1 23 ' 0 " - ' - " 7 ' 0 " 161.00
Deduction
T.door 1 2 ' 6 " ' " 7 ' 0 " 17.50
Ventilator 1 2 ' 0 " ' " 2 ' 0 " 4.00
229.50 sft 90.00 20655
16 Shelves with cuddapah slab including
material & labour charges
Kitchen 1 5 ' 0 " - ' - " 7 ' 0 " 35.00
35.00 sft 205.00 7175
17 Providing Skirting with vitrified tiles 4"
Including cutting fixing charges
Wall length 1 111 ' 0 " 111.00
111.00 rft 62.15 6899
18 Supplying and fixing of wooden doors,
windows and ventilators Including
all mason labour charges and
carpentry charges
a) Main Door (African Teak) 1 3 ' 6 " 7 ' 0 " 24.50 sft 1000.00 24500

b) Toilet Door-D2 (FRP) 1 2 ' 6 " 7 ' 0 " 17.50 sft 400.00 7000

c) UPVC Windows
Window - W 4 4 ' 0 " - - 4 ' 0 " 64.00
Kitchen Window - KW 1 3 ' 6 " - - 3 ' 0 " 10.50
Narrow Window - NW 1 2 ' 6 " - - 6 ' 0 " 15.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
93.50 sft 750.00 70125
d) M S grill work for UPVC Windows
window 4 4 0 " 4 0 " 64.00
10.50
15.00
4.00 kg 140.00

19 Painting & polishing for wooden joineries


incl all charges
Main Door Polish 24.50 55.125 sft 150.00 8269
Other joineries painting 93.50 210.375 sft 70.00 14726

20 Applying 1 coat primer + 2coat emulsion


on plastered gypsum wall

Ceiling plastering area 976.08 sft 25.00 24402


Inner plastering area 2173.92 sft 25.00 54348
Outer plastering area 463.50 sft 28.00 12978

21 SS Hand Rails with ornamental laser works 21 x 850 8925

22 Electrical works incl. light Fittings 5.00% 69291

23 Plumbing and Sanitary works 5.00% 69291

24 steel reinforcement for R.C.C items using ISI branded steel


including m.s wire with labour 400000.00% kg 80 360000

25 shuttering work for R.C.C column , beam, roof slab completed 3600.00% sft 38 136000

Total Amount A Rs 2029325


1999.335 /sft
B. FIRST FLOOR

1 Reinforced cement concrete in


and 1:1.5:3 mix using 3/4" hard blue
granite metal including shuttering,
barbending,concreting and curing
etc complete.

a) Column
C1 (incl.Parapet level) 4 1 ' 0 " 0 ' 9 " 9 ' 6 " 28.50
28.50 cft 180.00 5130
b) Roof beam
Beam B1 (0'9"x1'0") 4 17 ' 6 " 0 ' 9 " 1 ' 3 " 65.63
Beam B2 (0'9"x1'0") 2 30 ' 9 " 0 ' 9 " 1 ' 0 " 46.13
111.75 cft 200.00 22350
c) Roof slab
Rohtak dome 1 10 ' " 10 ' 5 " 0 ' 4 " 100.00 sq.ft 360.00 36000
bed room dome 1 12 ' " 12 ' 6 " 0 ' 5 " 144.00 sq.ft 360.00 51840
Slab 1 1 4 ' 9 " 17 ' 6 " 0 ' 5 " 34.64 cft 200 6928

Deduction
Spiral Staircase Cutout 0 4 ' 0 " 4 ' 0 " 0 ' 6 " 0.00
34.64 cft 414.00 14339
d) Loft and Sunshades of 2" tk
Window - W 2 5 ' 6 " 2 ' 0 " - - 22.00
22.00 sft 245.99 5412
e) Lintel beam of 6" tk
Lintel Alround 9"wall 1 89.5 ' 0 " - - " - - 89.50
Lintel Alround 4.5"wall 1 32 ' 0 " - - " - - 32.00
121.50 Rft 221.28 26886
f) Sill level concrete
Alround 0 122 ' 0 " - - " - - 0.00
0.00 Rft 110.64 0
2 9" Brick work in cement mortar 1:6
mix using Flyash table moulded
bricks including scaffolding,curing etc
Super structure
All Round 1 89 ' 0 " 0 ' 9 " 9 ' 6 " 634.13
Deduction
Window -W 2 4 ' 0 " 0 ' 9 " 4 ' 0 " 24.00
Ventilator 1 2 ' 0 " 0 ' 9 " 2 ' 0 " 3.00
Net quantity 607.13 cft 242.00 146924
3 4.5" Brick work in cement mortar 1:5
mix using flyash table moulded
bricks & hoop iron including
scaffolding,curing etc., complete.
Cross walls 1 12 ' 0 " 9 ' 6 " 114.00
Deduction
Bed Room Door 2 3 ' 0 " 7 ' 0 " 42.00
Toilet Door 1 2 ' 6 " 7 ' 0 " 17.50
Net quantity 54.50 cft 114.76 6254
4 Ceiling Plastering using gypsum
including scaffolding etc complete.

Bedroom(Incl. Toilet 1) 1 11 ' 6 " 16 ' 0 " - - 184.00


M.Bedroom 0 11 ' 0 " 16 ' 0 " - - 0.00
Toilet 2 1 12 ' 0 " 4 ' 6 " - - 54.00
FF Longue 0 11 ' 0 " 16 ' 0 " - - 0.00
Passage near M.Bedroom 0 3 ' 7.5 " 4 ' 6 " - - 0.00
Beam Soffits 1 96 ' 0 " 1 ' 6 " - - 144.00
Soffits Door 1 14 ' 0 " 1 ' 0 " - - 14.00
Soffits Window 2 24 ' 0 " 1 ' 0 " - - 48.00
Loft(Bedroom) 0 26 ' 0 " 2 ' 0 " - - 0.00
Window Sunshade 0 5 ' 6 " 2 ' 0 " - - 0.00
Deduction
Spiral Staircase Cutout 0 4 ' 0 " 4 ' 0 " - - 0.00
444.00 sft 48.00 21312
5 Inner Wall plastering using gypsum
including scaffolding etc complete.
Bedroom 1 89 ' 0 " - ' - " 9 ' 6 " 845.50
Toilet 1 1 33 ' 0 " - ' - " 9 ' 6 " 313.50
M.Bedroom 0 54 ' 0 " - ' - " 9 ' 6 " 0.00
Toilet 2 0 23 ' 0 " - ' - " 3 ' 0 " 0.00
FF Lounge 0 54 ' 0 " - ' - " 9 ' 6 " 0.00
Passage near M.Bedroom 0 16 ' 3 " - ' - " 9 ' 6 " 0.00
Soffits Door & open 10 1 ' 0 " - ' - " 7 ' 0 " 70.00
Soffits Window 1 88 ' 0 " 1 ' 0 " - - 88.00
loft -- Bedroom 1 26 ' 0 " 2 ' 0 " - - 52.00
Deduction
Bed Room Door 1 3 ' 0 " - - 7 ' 0 " 21.00
Toilet Door 1 2 ' 6 " - - 7 ' 0 " 17.50
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
Window 1 6 ' 0 " - - 8 ' 0 " 48.00
Open 1 3 ' 0 " - - 7 ' 0 " 21.00
Net quantity 1257.50 sft 48.00 60360
6 Outer Wall plastering in cement mortar
1:5 mix including scaffolding curing
etc complete.
Alround 1 123 ' 0 " 10 ' 0 " 1232.50
Deduction
Window 1 4 ' 0 " ' " 4 ' 0 " 16.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
1212.50 sft 48.00 58200
7 Floor finishing with Vitrified Tiles (4'0"'x2'0")
over a cement mortar 1:6 mix including
laying and Finishing.@ 50.00/Sft
Bedroom 0 11 ' 0 " 10 ' 0 " - - 0.00
M.Bedroom 1 11 ' 0 " 16 ' 0 " - - 176.00
FF Longue 0 11 ' 0 " 16 ' 0 " - - 0.00
Passage near M.bed 1 3 ' 7.5 " 4 ' 6 " - - 16.31
Soffits 1 14 ' 0 " 1 ' 0 " - - 14.00
Deduction
Toilet 1 1 4 ' 4.5 " 6 ' 4.5 " - - 27.89
Staircase area 1 3 ' 0 " 10 ' 0 " - - 30.00
148.42 sft 139.47 20701
8 Shelves with cuddapah slab including
material & labour charges
Bedroom& M.Bedroom 0 4 ' 0 " - ' - " 7 ' 0 " 0.00
0.00 sft 220.00 0
9 Providing Skirting with vitrified tiles 4"
Including cutting fixing charges
Wall length 1 131 ' 0 " 131.00
131.00 rft 66.50 8712
10 Supplying and fixing of wooden doors,
windows and ventilators Including
all mason labour charges and
carpentry charges
a) Bed Room Door 2 3 ' 0 " 7 ' 0 " 42.00 sft 850.00 35700
(African Sal wood frame with
skin door shutter)
b) Toilet Door-D2 (FRP) 1 2 ' 6 " 7 ' 0 " 17.50 sft 400.00 7000

c) UPVC Windows
Window -W1&SW 1 6 ' 6 " - - 6 ' 0 " 39.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
43.00 sft 750.00 32250
11 Ceramic Floor Tiles (basic cost Rs.40/-)
over a cement mortar 1:6 mix including
laying and Finishing.@ 40.00/Sft
Toilet Floor Tiles 1 4 ' 6 " 12 ' 0 " - - 54.00
Toilet Floor Tiles 0 7 ' 0 " 4 ' 6 " - - 0.00
54.00 sft 114.76 6197
12 Wall Tiles fixing work with cement paste
mortar using good quality tiles
of cost Rs.50.00/sft incl. all labour charges
Toilet Wall 1 33 ' 0 " - ' - " 7 ' 0 " 231.00
Toilet Wall 0 23 ' 0 " - ' - " 7 ' 0 " 0.00
Deduction
Ventilator 1 2 ' 0 " 2 ' 0 " 4.00
T.door 1 2 ' 6 " 7 ' 0 " 17.50
209.50 sft 105.00 21998
.
13 Painting & polishing for wooden joineries
incl all charges
Main door Polishing 0.00 0 sft 200.00 0
Other joineries and Grill painting 43.00 64.5 sft 75.00 4838

14 Applying 1 coat primer + 2coat emulsion


on gypsum plastered wall
including smoothening

Ceiling plastering area 444.00 sft 25.00 11100


Inner plastering area 1257.50 sft 25.00 31438
Outer plastering area 1212.50 sft 28.00 33950

15 Plumbing Works 7.50% 50686


16 Electrical works incl. light Fittings 7.50% 50686

Total Amount B Rs 777189

Area 1635.982 /sft


C. TERRACE FLOOR
1 4.5" Brick work in cement mortar 1:5
mix using flyash table moulded
bricks & hoop iron including
scaffolding,curing etc., complete.
Parapet walls 1 120 ' 0 " 3 ' 0 " 360.75
Headroom 1 4 ' 0 " 3 ' 0 " 12.00
Net quantity 372.75 sft 114.76 42776
2 Ceiling Plastering in cement mortar
in 1:4 mix including scaffolding,curing
etc complete.
Head Room 1 4 ' 0 " 4 ' 0 " - - 16.00
16.00 sft 38.84 621
3 Inner Wall plastering in cement mortar
1:5 mix including scaffolding curing
etc complete.
Parapet walls 1 117 ' 0 " - ' - " 3 ' 0 " 351.75
Head room 1 16 ' 0 " - ' - " 3 ' 0 " 48.00
Net quantity 399.75 sft 38.25 15291
3 Outer Wall plastering in cement mortar
1:5 mix including scaffolding curing
etc complete.
Alround 1 123 ' 0 " - ' - " 3 ' 0 " 369.75
Head room 1 16 ' 0 " - ' - " 3 ' 0 " 48.00
417.75 sft 47.67 19914
4 Supplying and fixing of Steel doors,
windows and ventilators Including
all mason labour charges and
carpentry charges
a) Terrace Door 1 4 ' 0 " 4 ' 0 " 16.00 sft
24.00 Kg 250.00 6000
5 Grano flooring with weathering
course in first floor roof level and top
finish with plastering
Terrace Flooring 1 11 ' 0 " 47 ' 7.5 " 523.88
Deduction
Spiral Cutout 1 4 ' 0 " 4 ' 0 " 16.00
507.88 sft 85.25 43296
6 Painting & polishing for joineries
incl all charges
Terrace door enamel paint 16.00 36 sft 70.00 2520

7 Applying 1 coat primer + 2coat emultion


over Wall putty finish on plastered
wall including smoothening
including all charges
Ceiling plastering area 16.00 sft 30.00 480
Inner plastering area 399.75 sft 25.00 9994
Outer plastering area 417.75 sft 28.00 11697

Total Amount C Rs 152589

D. Other Works
1 Sump -8000 ltrs Lumpsum 96000

2 SepticTank - RR Masonry Lumpsum 40000

1 Elevation Charges Lumpsum 20000

Total Amount =(A+B+C) Rs 2806515

Total Amount Rs.32,66,000/- Say Rupees Thirty Two Lakh and Sixty six Thousand only
1543500
1575
441000 sand
1984500 clay
273 cement
14800 1827
71800 822150 steel
2806650
centering,barbending,placing

0.666667

0.277778 266.8
57 963.1769 54901.08
15.83333
2112.167

0.75
0.333333 0.416667
0.25
0.0625
rohtak dome

brick size 9x
0.0625 cft

area of slab 60 cft


960 bricks
31680
labour 1200/sqft 144 sqft
17280
48960 340
400
11.32663
6.795979 240 6500
3.39799 1000 16250
1.132663 9786.21 0.034722 32.6207
11.32663
3914.065
total 21200.27
,barbending,placing 16675 108000

37875.27

50000
main dis
10.16667
60.95703 36.94365 23.27273
0.606061 0.387879

28000 5040
33040
4x 3
340/sq.ft
S.
NO DESCRIPTION UNIT RATE
1a. Excavate foundation in all kinds of soil including soft rock except hard
rock requiring blasting part return and spreading surplus earth within Cft 6.60
the site up to 1.5m depth .

1b. Excavate foundation in all kinds of soil including soft rock except hard
rock requiring blasting part return and spreading surplus earth within Cft 19.80
the site below 1.50m to 3.00m depth .
2 CEMENT CONCRETE
2b. Cement concrete 1:5:10 (1cement, 5 sand, 10 hard blue granite stone
metal 40mm and down gauge) laid in layers not exceeding 1.5m each in
depth well consolidated in foundation including necessary shuttering, Cft 152.35
steps etc.all complete as directed.

2a. Cement concrete 1:4:8 (1 cement, 4 sand and hard granite stone metal
40mm and down gauge) laid in layers not exceeding 15cms in depth
well cosolidated in leveling course under floors including necessary Cft 161.70
suttering of required profile all complete as directed.

3 Gravel or Pallam sand filling for foundation sides and Basement


Cft 54.45
including consolidation ramming and leveling etc complete.

4 R.C.C WORK
RCC M20 (Design Mix) Using hard blue granite metal 20mm and down
gauge including centering, curring etc., complete but excluding cost of With out
reinforcement. Steel

4a. In column footings including pedestals. Cft 244.75


4a1. Pile Foundation Rft 408.10
4a2. Pile cap Cft 248.60
4b. In column foundation and basement Cft 408.10
4b In column in superstructures at all levels
4b(1) In Ground floor Cft 408.10
4b(2) In First floor Cft 436.67
4b(3) In second floor Cft 465.23
4b(4) In third floor Cft 493.80
4c. In plinth beams Cft 371.80
4d. In sill slabs of required thickness
4d.1. In Ground floor Rft 63.25
4d.2. In First floor Rft 67.68
4d.3. In second floor Rft 72.10
4d.4. In third floor Rft 76.53
4e. In lintels, bands and bed block at all levels.
4e.1. In Ground floor Rft 146.85
4e.2. In First floor Rft 157.13
4e.3 In second floor Rft 167.41
4e.4 In third floor Rft 177.69
4f. Loft and Sunshade

4f.1 In Ground floor Sft 111.65


4f.2 In First floor Sft 119.4655
4f.3 In second floor Sft 127.281
4f.4 In third floor Sft 135.0965
4g. In sunshades of 63 mm thickness at all levels

4g.1. In Ground floor Sft 110.55


4g.2. In First floor Sft 118.29
4g.3. In second floor Sft 126.03
4g.4. In third floor Sft 133.77
4h. In Beams and brackets of required profile at all levels
4h.1. In Ground floor Cft 383.90
4h.2. In First floor Cft 410.77
4h.3. In second floor Cft 437.65
4h.4. In third floor Cft 464.52

4i In suspended Two Way roof slab (in beam and slab costruction)
4i(1) In Ground floor Cft 359.70
4i(2) In First floor Cft 384.88
4i(3) In second floor Cft 410.06
4i(4) In third floor Cft 435.24
4j In suspended One Way roof slab (in beam and slab costruction)
4j(1) In Ground floor Cft 347.60
4j(2) In First floor Cft 371.93
4j(3) In second floor Cft 396.26
4j.4 In third floor Cft 420.60
4k. In Sloping Roof Cft 456.50
4l. In staircase flight slab and mid landing
4l.1. In Ground floor Cft 371.80
4l.2. In First floor Cft 397.83
4l.3. In second floor Cft 423.85
4l.4. In third floor Cft 449.88
4m. Folded type / Concrete staircase steps
4m.1. In Ground floor Cft 550.00
4m.2. In First floor Cft 588.50
4m.3. In second floor Cft 627.00
4m.4. In third floor Cft 665.50
5 MASONRY WORK 10% Increased
5a. Brick work with locally avaiable best quality table moulded bricks of
not less than 50 kg.sq.cm crushing strength in cement mortar 1:6 Cft 228.55
(1cement, 6 sand) in foundation, plinth and Sump

5b. Brick work with locally available best quality table moulded bricks of
not less than 50 kg.sq.cm crushing strength in cement mortar 1:5 mix
(1cement, 6sand) in superstructure. Interlocking bricks 8"
5.1 In Ground floor Cft 228.55
5.2 In First floor Cft 228.55
5.3 In second floor Cft 260.55
5.4 In third floor Cft 276.55
6 Half brickwork with locally available best quality table moulded bricks
of not less than 50kg/sq/cm crushing strength in Cm 1:4( 1 cement 4
sand) and reinforcement with two numbers of 6mm dia. M.S. rods at
every fourth course embedded in cement mortar 1:4 (1cement,
4sand)for partitinos
6.1 In Ground floor Sft 107.25
6.2 In First floor Sft 114.76
6.3 In second floor Sft 122.26
6.4 In third floor Sft 129.77
PLASTERING
7a. Interior wall plastering with CM 1:5 (1cement, 5 sand), 12 mm
minimum thick to all interior faces of walls (sponge finish) including
RCC sufaces not contiguous to masonry. Necessary intrenal grooves of
size 10mm x 10mm shall be carried out as shown /directed by engineer
-in-charge.
7a.1 Ground Floor Sft 35.75
7a.2 First Floor Sft 38.25
7a.3 Second floor Sft 40.75
7a.4 Third Floor Sft 43.26
7b Exterior wall platering with CM 1:5 (1cement, 5 sand),( Sponge finish)
12mm minimum thick to all external faces of brick walls including RCC
surfaces not contiguous to masonry in all levels.

7b.1 Ground Floor Sft 44.55


7b.2 First Floor Sft 47.67
7b.3 Second floor Sft 50.79
7b.4 Third Floor Sft 53.91
8 Ceiling plastering with CM 1:3 (1 cement 3 sand), 12mm minimum
thick (sponge finish ) to ceiling sides and soffit of beams and columns
and other interior and exterior RCC surfaces not contiguous masonry.

8.1 Ground Floor Sft 36.30


8.2 First Floor Sft 38.84
8.3 Second floor Sft 41.38
8.4 Third Floor Sft 43.92
FLOORING
9 Grano flooring 40mm thick ( minimum) composed of one part of
cement, one part of sand, 3 part of wahed grade dry granite chiiping all
to pass through 6mm mesh free from dust including finishing surface
smooth with power trowel including necessary shuttering or glass strips
to form panel of required size to be provided at no extra cost.

9.1 In Ground floor Sft 49.50

10a Providing and laying first class vitrified tile of make Basic cost ( Rs 50/
Sft ) make Nitco / Johnson of size 2'0" x 2'0" of approved colour in
flooring over a bed of cement mortar 1:4 of minimum thickness 20mm
jointed with white cement slurry mixed with matching pigments all
complete as directed
10a.1 In Ground floor Sft 130.35
10a.2 In First floor Sft 139.47
10a.3 In second floor Sft 148.60
10a.4 In third floor Sft 157.72
10b Providing and laying 24" X 24" from somany / Kajaria glazed tiles of
approved colour flooring in CM 1:5 with joints so as to form a true
even surface and joints finished neatly with white cement mixed
matching pigments all complete as directed. Cost of tiles : Rs. 50/sft
10b.1 In Ground floor Sft 130.35
10b.2 In First floor Sft 139.47
10b.3 In second floor Sft 148.60
10b.4 In third floor Sft 157.72
11 Providing and laying vitrified tile of make Basic cost ( Rs 50/ Sft )
make Nitco / Johnson of approved colour of size 2'0" x 4" in CM 1:3 in
skirting to form a true and even surface and joints finished neatly with
white cement mixed with matching pigments all complete as directed
11.1 In Ground floor Rft 62.15
11.2 In First floor Rft 66.50
11.3 In second floor Rft 71.16
11.4 In third floor Rft 76.14

12 Providing and laying 12" X 15" Ceramic tiles for floors in CM 1:4
with joints so as to form a true even surface and joints finished neatly
with white cement mixed matching pigments all complete as directed.
Cost of tiles : Rs. 40/sft

12.1 In Ground floor 107.25


12.2 In First Floor 114.76
12.3 In Second floor 122.26
12.4 In Third floor 129.77

13 Providing and laying 12" X 15" from somany / Kajaria glazed tiles of
approved colour wall dadoing and floors in CM 1:3 with joints so as to
form a true even surface and joints finished neatly with white cement
mixed matching pigments all complete as directed. ( Rate should
include base plastering with CM 1:5 of required thickeness) Cost of
13.1 In Ground floor Sft 94.05
13.2 In First floor Sft 100.63
13.3 In second floor Sft 107.22
13.4 In third floor Sft 113.80
14 Providing and laying 20mm thick machine cut and polished granite
stone of approved shade in teads and risers of steps and landing in
CM 1:4 of minimum thickness 20mm jointed with white cement slurry
and pointing with matching pigments including rounding of nosing,
rubbing, forming grooves of required size in the plastering of side of
steps and final polishing all complete as directed Cost of granite : Rs.
150/sft
14.1 In Ground floor Sft 225.50
14.2 In First floor Sft 241.29
14.3 In second floor Sft 257.07
14.4 In third floor Sft 272.86

14.5 Providing and laying 20mm thick granite of paradise shade / any other
approved colour for flooring over ledges including edge nosing Sft 225.50
polishing etc., all complete as directed

14.6 Providing and 20mm thick granite slab of paradise shade / any other
approved colour for counter top and wash through including adge Sft 293.15
nosing, polishing etc., all complete as directed

15 Ellise pattern flooring using 6mm to 10mm of aggregate chips, cement


and sand and includes all labour charge Sft 49.50

TERRACE WORKS
16 Brick jelly cement concrete 1:4:8 using approved broken brick jelly 25
mm and down gauge laid in sunken floors. Cft 61.60

17 Providing and laying pressed tiles in C.M 1:3 over weathering course at
terrace includes all labour charges 88.00

18a Solid Block work 4" tk with locally available best quality table moulded
bricks of not less than 50 kg.sq.cm crushing strength in cement mortar
1:4 mix (1cement, 6sand) in superstructure.

18a.1 Ground Floor Sft 87.45


18a.2 First Floor Sft 93.57
18a.3 Second floor Sft 106.59
18a.4 Third Floor Sft 105.81
18b Solid Block work 6" tk with locally available best quality table moulded
bricks of not less than 50 kg.sq.cm crushing strength in cement mortar
1:4 mix (1cement, 6sand) in superstructure.

18b.1 Ground Floor Sft 93.50


18b.2 First Floor Sft 100.05
18b.3 Second floor Sft 106.59
18b.4 Third Floor Sft 113.13
18c Solid Block work 9" tk with locally available best quality table moulded
bricks of not less than 50 kg.sq.cm crushing strength in cement mortar
1:4 mix (1cement, 6sand) in superstructure.
18c.1 Ground Floor Sft 119.90
18c.2 First Floor Sft 128.29
18c.3 Second floor Sft 136.686
18c.4 Third Floor Sft 145.08
19 Supply, straighten, handle, cut bend, crank, fix and tie in position in all
RCC items of wrok including cost GI binding wire 18SWG double
strand complete.(On actual length including authorized lappages only at
theoretical weight for different sections payment will be made).
19.1 High yield strength deformed bars M.T 82500.00
20 Providing and injecting chemical emulsion using
Chlorpyrifos(dursban)mixed as a water emulsion in ratio 1:19 or
equivalent for antitermite treatment and creating a chemical barrier all
round the column pits , wall trenches, top durface of plinth filling,
junction of wall and floor,along the exterior perimeter of the building, Sft 11.00
expansion joints, surrounding of pipes and conduitsetc.all complete as
per IS 6313(part II)1981.(Plinth area of the building at ground floor
only shall be measured excluding yard /open arrears.)
10% Increased Old Rate

6.00

18.00

138.50

147.00

49.50

10% Increased

With Steel Old Rate

343.20 222.50 344.00


585.20 371.00 571.00
387.20 226.00 384.00
565.40 371.00 553.00

565.40 371.00 553.00


604.98 396.97 591.71
644.56 422.94 630.42
684.13 448.91 669.13
510.40 338.00 501.00
103.40 57.50 100.00
110.64 61.53 107.00
117.88 65.55 114.00
125.11 69.58 121.00

206.80 133.50 202.00


221.28 142.85 216.14
235.75 152.19 230.28
250.23 161.54 244.42

229.90 101.50 217.00


245.99 108.61 232.19
262.09 115.71 247.38
278.18 122.82 262.57

209.00 100.50 198.00


223.63 107.54 211.86
238.26 114.57 225.72
252.89 121.61 239.58

541.20 349.00 530.00


579.08 373.43 567.10
616.97 397.86 604.20
654.85 422.29 641.30

517.00 327.00 470.00


553.19 349.89 502.90
589.38 372.78 535.80
625.57 395.67 568.70
544.50 316.00 495.00

582.62 338.12 529.65


620.73 360.24 564.30
658.85 382.36 598.95
693.00 415.00 630.00

608.30 338.00 553.00


650.88 361.66 591.71
693.46 385.32 630.42
736.04 408.98 669.13

500.00
535.00
570.00
605.00
Old Rate

200.50

200.50
214.54
228.57
242.61

97.50
104.33
111.15
117.98
32.50
34.78
37.05
39.33

40.50
43.34
46.17
49.01

33.00
35.31
37.62
39.93

45.00

118.50
126.80
135.09
143.39
118.50
126.80
135.09
143.39

56.50
60.46
64.69
69.21

97.50
104.33
111.15
117.98

85.50
91.49
97.47
103.46
205.00
219.35
233.70
248.05

205.00

266.50

45.00

56.00

80.00

79.50
85.07
96.90
96.20

85.00
90.95
96.90
102.85

109.00
116.63
124.26
131.89

75000.00

10.00
R.G Associates
Civil Engineers & Structural Consultants 18.03.2024
60/6, Sri Ragavendra House, Thiruvalluvar Nagar,
Trichy Road, Ramanathapuram, Coimbatore - 641045
Ph: 9842530027, 9585530027.

DATA FOR CONSTRUCTION WORKS


Rate
with
Overhe
S.No Description Qty Rate Amount
ads &
Profit in
%
15
1 Earth work excavation In ordinary soil upto 5'0" depth for Open Well
Labour for excavation 100 cft Rs. 10.91 /cft 1090.91
1090.91
Rate/Cft = 10.91 13.00

1a Earth work excavation In ordinary soil below 5'0" depth for Open Well
Labour for excavation 100 cft Rs. 16.36 /cft 1636.36
1636.36
Rate/Cft = 16.36 19.00

1b Earth work excavation In ordinary soil upto 4'0" depth for Column Pits
Labour for excavation 100 cft Rs. 10.00 /cft 1000.00
1000.00
Rate/Cft = 10.00 11.50

1c Earth work excavation In rocky soil below 4'0" depth for Column Pits
Labour for excavation 100 cft Rs. 12.00 /cft 1200.00
1200.00
Rate/Cft = 12.00 14.00

2a Flooring concrete PCC 1:4:8 using 40mm metal - 100 cft


Cost of 40mm Metal 95 cft Rs. 60.00 /cft 5700.00
Cost of M sand 60 cft Rs. 65.00 /cft 3900.00
Cement 9.65 bags Rs. 300.00 /bag 2895.00
Labour charges 100 cft Rs. 30.00 /cft 3000.00
15495.00
Rate/Cft = 154.95 178.50
Rate/sft 4" thk= 15.00
2b Foundation base concrete PCC 1:5:10 using 40mm metal - 100 cft
Cost of 40mm Metal 95 cft Rs. 60.00 /cft 5700.00
Cost of M sand 60 cft Rs. 65.00 /cft 3900.00
Cement 7.33 bags Rs. 300.00 /bag 2199.00
Labour charges 100 cft Rs. 30.00 /cft 3000.00
14799.00
Rate/Cft = 147.99 170.50
Rate/sft 6" thk= 75.00
3a Filling the basement with quarry dust inluding consolidation - 100 cft
Quarry dust 130 cft Rs. 42.50 /cft 5525.00
Labour charges 100 cft Rs. 6.00 /cft 600.00
6125.00
Rate/Cft =Rs 61.25 70.50

3b Filling the basement with well gravel inluding consolidation - 100 cft
Well Gravel 130 cft Rs. 30.00 /cft 3900.00
Labour charges 100 cft Rs. 6.00 /cft 600.00
4500.00
Rate/Cft =Rs 45.00 52.00

4 RCC 1:1.5:3 using 20mm metal excluding centering & fabrication - 100 cft
Cost of 20mm metal 95 cft Rs. 60.00 /cft 5700.00
Cost of M sand 60 cft Rs. 65.00 /cft 3900.00
Cost of cement 20.00 bag Rs. 300.00 /bag 6000.00
15600.00
Rate/Cft =Rs 156.00 179.50

INCLUDING CENTERING
4a1 Pile Foundation - 100 rft
RCC M20 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 rft Rs. 200.00 /cft 20000.00
35600.00
Rate/Cft =Rs 356.00 409.50

4a2 Pile Cap


RCC M30 Grade 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 68.18 /cft 6818.00
22418.00
Rate/Cft =Rs 224.18 258.00

4a3 Column footing - 100 cft


RCC 1:1.5:3 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 65.00 /cft 6500.00
22100.00
Rate/Cft =Rs 221.00 254.50

4b Columns - 100 cft


RCC 1:1.5:3 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 200.00 /cft 20000.00
35600.00
Rate/Cft =Rs 356.00 409.50

4c Plinth beam - 100 cft


RCC 1:1.5:3 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 170.00 /cft 17000.00
32600.00
Rate/Cft =Rs 326.00 375.00

4d Sill beam 75mm thick - Rft


RCC 1:1.5:3 0.19 cft Rs. 156.00 /cft 29.64
Labour charges 1 rft Rs. 26.00 /rft 26.00
55.64
Rate/Rft =Rs 55.64 64.00

4e Lintel - 150mm thick - Rft


RCC 1:1.5:3 0.375 cft Rs. 156.00 /cft 58.50
Labour charges 1 Rft Rs. 70.00 /rft 70.00
128.50
Rate/Rft =Rs 128.50 148.00

4f Loft 50 mm thick average - 1 sft


RCC 1:1.5:3 0.160 cft Rs. 156.00 /cft 24.96
Labour charges 1 sft Rs. 70.00 /sft 70.00
94.96
Rate/Sft =Rs 94.96 109.50

4g Sunshade 63mm thick average - 1 sft


RCC 1:1.5:3 0.156 cft Rs. 156.00 /cft 24.34
Labour charges 1 sft Rs. 70.00 /sft 70.00
94.34
Rate/Sft =Rs 94.34 108.50

4h Roof beams - 100 cft


RCC 1:1.5:3 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 180.00 /cft 18000.00
33600.00
Rate/Cft =Rs 336.00 386.50

4i Two Way Roofslab - 100 Cft


RCC 1:1.5:3 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 160.00 /cft 16000.00
31600.00
Rate/Sft =Rs 316.00 363.50

4j One Way Roof slab -100 Cft


RCC 1:1.5:3 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 150.00 /cft 15000.00
30600.00
Rate/Sft =Rs 306.00 352.00

4k Sloped Roof slab -100 Cft


RCC 1:1.5:3 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 240.00 /cft 24000.00
39600.00
Rate/Sft =Rs 396.00 455.50

4l Staircase Flight slab - 100 Cft


RCC 1:1.5:3 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 cft Rs. 170.00 /cft 17000.00
32600.00
Rate/Sft = Rs 326 375.00

5 Brick work 9" thick in c.m.1:6 mix for super structure works - 100 cft
Bricks 1300 Nos Rs. 8.00 /Each 10400.00
M sand 34 cft Rs. 65.00 /cft 2210.00
Cement 5.00 bag Rs. 300.00 /bag 1500.00
14110.00
Labour charges 100 cft Rs. 44.00 /cft 4400.00
18510.00
Rate/Cft =Rs 185.10 213.00

6 Brick partition wall 115mm thick in c.m.1:4 including hoop iron - 100 sft
Bricks 550 Nos Rs. 8.00 /Each 4400.00
M sand 13 cft Rs. 65.00 /cft 845.00
Cement 2.00 bag Rs. 300.00 /bag 600.00
Hoop iron 6 kg Rs. 85.00 /kg 510.00
6355.00
Labour charges 100 Sft Rs. 26.00 /Sft 2600.00
8955.00
Rate/Sft =Rs 89.55 103.00

7a Inside wall Plastering in c.m.1:5 mix for an average thickness of 12mm - 100 sft
M sand 9.00 cft Rs. 65.00 /cft 585.00
Cement 2.00 bag Rs. 300.00 /bag 600.00
1185.00
Labour charges ( including Scaffoldin 100.00 sft Rs. 18.00 /sft 1800.00
Curing charges )
2985.00
Rate/Sft =Rs 29.85 34.50

7b Outside wall Plastering in c.m.1:5 mix for an average thickness of


12mm by externally - 100 sft
M sand 10.00 cft Rs. 65.00 /cft 650.00
Cement 2.00 bag Rs. 300.00 /bag 600.00
1250.00

Labour charges ( including Scaffoldin 100.00 sft Rs. 25.00 /sft 2500.00
Curing charges)
3750.00
Rate/Sft =Rs 37.50 43.50

8 Ceiling plastering in c.m.1:3 mix for an average thickness of 12mm - 100 sft
M sand 9.00 cft Rs. 35.00 /cft 315.00
Cement 2.00 bag Rs. 300.00 /bag 600.00
915.00

Labour charges ( including Scaffoldin 100.00 sft Rs. 20.00 /sft 2000.00
Curing charges)
2915.00
Rate/Sft =Rs 29.15 34.00

9 PCC 1:4:8 - in Using 40mm metal for flooring, 100mm thick - 100 sft
Cost of 40mm metal 30 cft Rs. 60.00 /cft 1800.00
Cost of M sand 19.5 cft Rs. 65.00 /cft 1267.50
Cement 2.75 bags Rs. 300.00 /bag 825.00
3892.50
Overheads & Profits 15% 3892.50 583.88
Labour charges 100 sft Rs. 15.00 /sft 1500.00
5976.38
Rate/Sft =Rs 59.76 69.00

10 Providing and fixing Vitrified tiles for flooring over c.m.1:4, 20mm thick - 1 Sft
Vitrified tile 1.10 Sft Rs. 50.00 /sft 55.00
Transportation, handling & wastage 10 % 5.50
White Cement 0.08 kg Rs. 25.00 / kg 2.00
Petty Materials 1.00 Sft Rs. 4.00 / sft 4.00
Cost of cement 0.04 bag Rs. 300.00 /bag 12.00
Cost of Sand 0.15 cft Rs. 35.00 /cft 5.25
83.75

Labour charges for cutting & Laying 1 sft Rs. 22.73 /sft 22.73
106.48
Rate/Sft =Rs 106.48 122.50
11 Providing and fixing Vitrified tiles skirting of 100mm in c.m.1:4, 20mm thick - 1 Rft
Vitrified tile 0.25 Sft Rs. 80.00 /sft 20.00
Transportation, handling & wastage 10 % 2.00
White Cement 0.08 kg Rs. 25.00 / kg 2.00
Petty Materials 1.00 Sft Rs. 4.00 / sft 4.00
Cost of cement 0.02 bag Rs. 300.00 /bag 6.00
Cost of Sand 0.06 cft Rs. 39.00 /cft 2.15
36.15

Labour charges for cutting & Laying 1 Rft Rs. 14.55 /rft 14.55
Rate/Rft =Rs 50.69 50.69 58.50

12 Providing and fixing ceramic tiles for flooring over c.m.1:4, 20mm thick - 1 Sft
Basic cost ( Rs 40/ Sft ) 1 Sft Rs. 50.00 /sft 50.00
Transportation, handling & wastage 7.5% 3.75
Cost of cement 0.02 bag Rs. 300.00 /bag 6.00
Cost of Sand 0.10 cft Rs. 65.00 /cft 6.50
66.25
Labour charges for cutting & Laying 1 sft Rs. 22.73 /sft 22.73
Rate/Sft =Rs 88.98 88.98 102.50

13 Providing and fixing glazed tiles for dadooing over cm.1:4, 20mm thick - 1 Sft
Vitrified Tiles Basic cost ( Rs 40/ Sft ) 1 Sft Rs. 40.00 /sft 40.00
Transportation, handling & wastage 7.5% 3.00
Cost of cement 0.02 bag Rs. 300.00 /bag 6.00
Cost of Sand 0.10 cft Rs. 65.00 /cft 6.50
55.50
Labour charges for cutting & Laying 1 sft Rs. 22.73 /sft 22.73
Rate/Sft =Rs 78.23 78.23 90.00

14 Providing and fixing Granite Slab for flooring over c.m.1:4, 20mm thick - 1 Sft
Basic cost (135/sft) 1 Sft Rs. 125.00 /sft 125.00
Transportation, handling & wastage 10% 12.50
Cost of cement 0.025 bag Rs. 300.00 /bag 7.50
Cost of Sand 0.11 cft Rs. 65.00 /cft 6.83
151.83
Labour charges for cutting & Laying 1 sft Rs. 35.00 /sft 35.00
186.83
Rate/Sft =Rs 186.83 215.00

15 Ellise pattern flooring - 100 sft


6mm to 10 mm metal 16.67 cft Rs. 42.50 /cft 708.48
M sand 9.75 cft Rs. 65.00 /cft 633.75
Cement 4.08 bag Rs. 300.00 /bag 1224.00
2566.23
Labour charges 100.00 sft Rs. 15.00 /sft 1500.00
4066.23
Rate/Sft =Rs 40.66 47.00

16 Weathering course using brick jelly lime concrete for an average


of 75mm thick - 100 sft
Brick bats 25.00 cft Rs. 25.00 /cft 625.00
Lime 9.76 cft Rs. 40.00 /cft 390.40
M sand 25.00 cft Rs. 65.00 /cft 1625.00
2640.40
Labour charges for laying 100.00 sft Rs. 27.50 /sft 2750.00
5390.40
Rate/Sft =Rs 53.90 62.00

17 Providing & Laying pressed tiles in C.M 1:3 Over laid weathering course - 1 Sft
Pressed tile 1.85 Nos Rs. 14.00 / No 25.90
M sand 0.15 cft Rs. 65.00 /cft 9.75
Cement 0.04 bag Rs. 300.00 /bag 12.00
47.65
Labour charges for laying & finishing 1.00 sft Rs. 22.73 /sft 22.73
70.38
Rate/Sft =Rs 70.38 81.00
18 Solid block Work
a Solid block Work wall 4" thick in c.m.1:4 - 100 sft
Solid Blocks 100 Nos Rs. 36.00 /Each 3600.00
M sand 11 cft Rs. 65.00 /cft 715.00
Cement 1.50 bag Rs. 300.00 /bag 450.00
4765.00

Labour charges 100 Sft Rs. 20.00 /Sft 2000.00


6765.00
Rate/Sft =Rs 67.65 78.00

b Solid block Work wall 6" thick in c.m.1:4 - 100 sft


Solid Blocks 100 Nos Rs. 46.00 /Each 4600.00
M sand 17 cft Rs. 65.00 /cft 1105.00
Cement 2.25 bag Rs. 300.00 /bag 675.00
6380.00

Labour charges 100 Sft Rs. 20.00 /Sft 2000.00


8380.00
Rate/Sft =Rs 83.80 96.50

c Solid block Work wall 9" thick in c.m.1:4 - 100 sft


Solid Blocks 100 Nos Rs. 46.00 /Each 4600.00
M sand 22 cft Rs. 65.00 /cft 1430.00
Cement 3.00 bag Rs. 300.00 /bag 900.00
6930.00

Labour charges 100 Sft Rs. 25.00 /Sft 2500.00


9430.00
Rate/Sft =Rs 94.30 108.50
MATERIAL RATE
Dhanam
CLIENT DATE
Gardens
PLACE Seerapalayam 18.03.2024
Sno Materials Rate Per
BUILDING MATERIALS
1 Cement Rs. 300.00 /bag JSW
2 Reinforcement steel Rs. 65.00 /kg vizag
3 Binding wire Rs. ### /MT
4 Bricks 9" x 4.5" x 3" Flyash Rs. 8.00 /Each Table Mould
5 River Sand Rs. 80.00 /cft Chettipalayam quarry
6 M Sand Rs. 65.00 /cft
7 Quarry Dust Rs. 42.50 /cft
8 Well Gravel Rs. 30.00 /cft
9 20 mm metal Rs. 60.00 /cft
10 40 mm metal Rs. 60.00 /cft
11 6 mm Chips Rs. 42.50 /cft
12 Size stone Rs. 18.00 /Nos
13 Bond stone Rs. 42.00 /Nos
14 Soling stone Rs. 25.00 /cft
FLOOR TILES
15 Vitrified tiles 4'0" x 4'0" Rs. 50.00 /sft
Vitrified tiles 2'9" x 2'9" Rs. 50.00 /sft
Vitrified tiles 4'0" x 2'0" Rs. 50.00 /sft
Vitrified Wood finish tiles 4'0" x 2'0" Rs. 50.00 /sft
WALL TILES
16 Digital Wall tiles 24" x12" Rs. 40.00 /sft
Digital Wall tiles 18" x12" Rs. 40.00 /sft
17 Glazed tiles 24" x12" Rs. 40.00 /sft
18 Pressed Tiles 9" x 9" Rs. 14.00 /Each
OTHER MISCELLANIOUS ITEMS
19 White Cement Rs. 25.00 /Each
20 Hoop iron bands Rs. 85.00 /kg
21 Brick bat Rs. 25.00 /cft
22 Lime Rs. 40.00 /cft
SOLID BLOCKS
23 4" Solid Block Coral x 16" x 8" Rs. 36.00 /Each
24 6" Solid Block Coral x 16" x 6" Rs. 46.00 /Each
25 8" Solid Block Coral x 12" x 8" Rs. 46.00 /Each
GRANITE SLABS
26 Ordinary Granite slab for staircase Rs. 125.00 /sft
27 Black pearl Granite slab/kitchen Rs. 165.00 /sft
28 Granite Tile 24"x 24" Rs. 65.00 /sft
29
ettipalayam quarry

Dust 2900.00/ unit

1210/50 kg bag Birla

57 45
115
35 35
150 210
900
1008
0.277778 0.208333
3240
184680 45360
230040

96.5
579 2084.4 105
118810.8 504 22680

371530.8
LABOUR RATE QUOTATION

S.
Description of work
No

1 Earth work excavation:


a. Earth work excavation In ordinary soil upto 6'0" depth for Open Well
b. Earth work excavation In ordinary soil below 6'0" depth for Open Well
c. Earth work excavation In ordinary soil upto 4'0" depth for Column Pits
d. Earth work excavation In ordinary soil below 4'0" depth for Column Pits
e. Earth work excavation In rocky soil below 4'0" depth for Column Pits

2 Plain cement concrete:


Plain cement concrete using 1-1/2" Metal for foundation work including foundation trench
a.
surface cleaning
Plain cement concrete using 1-1/2" Metal for foundation work including foundation trench
b.
surface cleaning up to 4" thick

c. Plain cement concrete using ellis pattern jelly for flooring work surface cleaning at 2" thick

3 Sand or earth filling with consolidation & surface leveling ( Consolidation for 2'0" )

4 Stone Work

a. R.R.Masonry for basement work ( Including surface cleaning and centering marking )

C.R.Masonry for basement work ( Including surface cleaning and centering marking )

b. Damp Proof course

5 Reinforced cement concrete works:


R.C.C for footing (including surface leveling marking, bar typering erection of column
a.
reinforcements, concrete levelling)
R.C.C for Pile Foundation with markings bar tyeing, plumbing with centering materials
a1
concrete 0'9" x 0'9" & above ( Including starter )
R.C.C for columns with markings bar tyeing, plumbing with centering materials concrete
b.
0'9" x 0'9" & above ( Including starter )
R.C.C for plinth beams with markings bar tyeing, plumbing with centering materials
c.
concrete 0'9" x 0'9" & above
R.C.C for Basement level beams with markings bar tyeing, plumbing with centering
d.
materials concrete 0'9" x 0'6"
R.C.C for roof beams with markings bar tyeing, plumbing with centering materials &
e.
concrete 0'9" x 0'9" & above
f. R.C.C for sill slabs with markings bar tyeing, plumbing with centering materials
R.C.C for lintel with markings bar tyeing, plumbing with centering materials & concreting
g.
upto 6" thick.
R.C.C for loft & sunshades (Including farms works bar tyeing leveling concreting placing,
h.
mixture machine and its transporting charges )
R.C.C for side wall,sump,lift well & septic tank (Including farms works ,bar tyeing double
i. Layers, leveling, concreting placing, mixture machine and its transporting charges ) upto 6"
thick ( Single Side Shuttering )
R.C.C for side wall,sump,lift well & septic tank (Including farms works bar tyeing double
j. Layers, leveling concreting, placing, mixture machine and its transporting charges ) upto 6"
thick ( Both Side Shuttering )

R.C.C for one way roof slab upto 4.5" thick (Including farms works bar tyeing leveling
k.
concreting placing, mixture machine and its transporting charges )

l. R.C.C for two way roof slab upto 5" thick ( Including farms works bar tyeing leveling
concreting placing, mixture machine and its transporting charges )

m. R.C.C for sloped roofslab upto 5" thick (Including farms works bar tyeing leveling concreting
placing,mixture machine and its transporting charges ) - A - TYPE

n. R.C.C for sloped roofslab upto 5" thick (Including farms works bar tyeing leveling concreting
placing,mixture machine and its transporting charges ) - 4 SIDE

R.C.C for Staircase Flight upto 5" thick (Including farms works bar tyeing leveling concreting
o.
placing,mixture machine and its transporting charges )

p. Conceiled lintels
q. Pre Cast Slabs

6 Brick Work
Brick work in CM 1:6 using table moulded bricks of approved make and of standard
a.
strength in super structure for 9" walls (Marking and brick soaking )
Brick work 4-1/2" thickness walls (Marking and brick soaking with hoop reinforcement at
b.
every 5th layer)
Brick on edge work in CM 1:6 using table moulded bricks of approved make and of
c.
standard strength in super structure for 9" walls (Marking and brick soaking )

Brick work for steps in CM 1:6 using table moulded bricks of approved make and of
d.
standard strength 3'0" wide (Marking and brick soaking ).

7 Solid Block Work


Solid Block Work CM using Machine moulded blocks of approved make and of standard
a.
strength 8" walls with both side Pointing

Solid Block Work CM using Machine moulded blocks of approved make and of standard
b.
strength 6" walls with both side Pointing

Solid Block Work CM using Machine moulded blocks of approved make and of standard
c.
strength 4" walls with both side Pointing
8 Plastering Work
Doors, windows, grill & gate with concrete fittings ( Including plumbing leveling and
a.
packing )
b. Ceiling plastering with cement mortar (Including scofolding and leveling and Hogging)
c. Inner wall plastering with cement mortar (Including scofolding and leveling)

d. Outer wall plastering with cement mortar (Including scofolding and leveling)

e. Sloped roof plastering with cement mortar (Including scofolding and leveling)

f. Column & Beam plastering with cement mortar (Including scofolding and leveling)

g. R.C.C Wall surface plastering with cement mortar (Including scofolding and leveling)

h. Inner wall & Floor plastering with cement slurry (Including scofolding and leveling)

8 Other works
Weathering course laying in surki with lime and brick bats 3" tk mixture including brick jelly
a.
breaking, pull fixing & lime concreting.
b. Flooring above the surki with cement mortar in cement morter
c. Flooring tiles laying above the surki and binding in cement morter
d. Elevation tiles laying and binding in cement morter
e. 3" Vertical brick work for sunshade edges with plastering in cement morter

g. Chickenmesh finishing with plastering (including tying of reinforcement and chickenmesh )

h. Rainwater cut of borders in cement morter


l. Curve border in cement morter
j. Plastering for Steps including tread, raiser and slope making
k. Chamber construction with bricks and plastering Up to 24"x24"
l. Outer scafolding work for existing building
m. Grooves Making in Elevation

9 Flooring
a. Vertified Tile Laying
Skirting

b. Granite Slab Laying


10 Electrical Work
Laying of conduits pipe lines in Roof and Walls, wire pulling, fixing of DB boxes,
fixing of electrical boxes as directed in drawing, fixing of switches and cover plate.
Fixing of Panel board and wiring. Fixing of meter box. Earthing Work etc.,

11 Plumbing Work

Erection of plumbing pipe lines as per GFC drawing or as directed by Engineer/Consultant,


laying and fixing of rain water lines, Drain & sewer lines (Incl. Earthwork excavation for
necessary depth & refilling etc) with necessary gradient as per site condition, with proper
& approved special clamps & joining materials and internal pipe lines with fixing of CP
fixtures & sanitary wares.

Mazdoor Rates : incl Tea charges


a Mason - Rs1100/day
b Male Coolie - Rs.800/day
c Female Coolie - Rs.650/day
d centering and barbending - Rs. 950/day
e Plumber - Rs. 850/day
f Electrician - Rs. 850/day
g Tiles Mason - Rs. 1400/day
h Ties Helper - Rs. 750/day
i Painter - Rs. 900/day

1 Lifting charges:

a) for all concrete and platering works

b) Brick work and block works

2 RMC -- DEDUCTIONS FROM THE QUOTED RATE FOR ROOF SLAB / ROOF BEAMS

Note :
The above rates are ground floor only, for each 10'0" height the rates will be increased by
1
15% each floor.

2 The curing of the building is incharge of the client.

Mazdoor work : Curing, Elevation, Decorative works, Skirting touchup work & Cleaning work
3
will be Billed Actual labour plus 10% Service charge.

4 Electricity, motor & water supply charges will be supplied by Client only.
Labour Shed & Place of storing materials to be provided by the client within 30 feet
5
otherwise lead charges to be claimed from client.
6 Payment to be given by the Client at various stages & Every Week end.
7 Whatever cost comes from Government Body it will be given by the client.
8 If there is any alteration & addition to the existing plan,that will be billed suitably.
For any additional works other than specified above rates will be given at the time of
9
execution
10 If there is joineries two sides jarms work no opening deduction in plastering area.
Date 05.03.23_
Rate for Data

Unit Rate

1 Cft 12.00
1 Cft 18.00
1 Cft 6.00
1 Cft 8.00
1 Cft 12.00

1 Cft 30.00

1 Sft 15.00

1 Sft 15.00

1 Cft 6.00

1 Cft 30.00

1 Cft 35.00

1Sft 21.00

1 Cft 65.00

1 Rft 200.00

1 Cft 200.00

1 Cft 170.00

1 Rft 50.00

1 Cft 180.00
1 Rft 26.00

1 Rft 70.00

1 Sft 70.00

1 Sft 75.00

1 Cft 125.00

1 sft 75.00

1 Sft 80.00

1 sft 120.00

1 sft 150.00

1 sft 85.00

1 Rft 50.00
1 Sft 58.00

cft

1 Cft 44.00 59

1 Sft 26.00

1 Rft 50.00

1 Rft 65.00

1 Sft 25.00

1 Sft 20.00

1 Sft 20.00
1 Sft 40.00

1 Sft 20.00
1 Sft 18.00

1 Sft 25.00

1 Sft 50.00

1 Sft 40.00

1 Sft 20.00

1 Sft 25.00

1 Sft 27.50

1 Sft 20.00
1 Sft 25.00
1 Sft 25.00
1 Rft 75.00

1 Sft 45.00

1 Rft 35.00
1 Rft 50.00
1 Sft 50.00
1 No 2000.00
1 Sft 10.00
1 Rft 20.00

1 Sft 25.00
1 Rft 16.00

1 Sft 35.00
1 Sft 30.00

1 Sft 30.00

15% each floor

15% each floor

Rs.9/- CFT
Data for wood work joineries
24.12.2021

Wood/Cft Frame Shutter Labour charges Rate Sft


Burma Teak 13570.00 15930.00 M.D 300
Mini Burma 6490.00 8850.00
African Teak 5310.00 7670.00 D 150 250
Kerala Teak 3127.00 6077.00
Paddak 4425.00 4897.00 W 250 300
Country Wood 1850.00 V 150
African oil Sal 1700.00 2700.00 PD 180
Rate including 18% GST

S.no Description of work Nos Piece Length Breadth Depth Qty Unit Rate Amount

1 Main door of size 5' 0" * 7' 0" made with Burma Teak I st class with carving work
a including all labour and material charges
WOOD
Vertical Frame 1 3 0 ' 5 " 0 ' 4 " 7 ' 0 " 2.92
Horizontal Frame 1 2 0 ' 5 " 0 ' 4 " 5 ' 6 " 1.53
Shutter Frame Vertical 1 2 0 ' 5 " 0 ' 2 " 7 ' 0 " 0.97
Shutter Frame Horzontal 1 2 0 ' 5 " 0 ' 2 " 3 ' 6 " 0.49
5.90 cft 13570.00 80100.694

b Shutter (palakai) 1 2 1 ' 3 " 0 ' 2 " 7 ' 0 " 2.92 cft 15930.00 46462.5

c Labour charges 1 1 5 ' 0 " - - 7 ' 0 " 35.00 sft 300.00 10500.00

d Glass 1 1 1 ' 2 " - - 7 ' 0 " 8.17 sft 450.00 3675.00

e Beeding wood 1 1 - - - - 18 ' 0 " 18 rft 25.00 450.00

f Grill 1 1 1 ' 6 " - - 7 ' 0 " 10.5 sft


18.375 kg 110.00 2021.25

g Tower bolt 1 2 - - - - - - 2 nos 250.00 500.00

h Brass hinges 1 4 - - - - - - 4 nos 150.00 600.00

i Handle 1 1 - - - - - - 1 nos 500.00 500.00

j Lock 1 1 - - - - - - 1 nos 2500.00 2500.00

k Fitting charges( mason ) 1 1 5 ' 0 " - - 7 ' 0 " 35 sft 25.00 875.00

l Cement concrete charges 1 1 - - - - - - 1 500.00 500.00

m Primer charges 1 1 5 ' 0 " - - 7 ' 0 " 78.75 sft 5.00 393.75

n Hold fast ( allu) 1 4 - - - - - - 4 nos 25.00 100.00

o Carving Works 1 1 3 ' 0 " - - 6 ' 0 " 18 sft 250.00 4500.00

Total Amount Rs 153678.19


Over head charges 10 % 15367.819
Total amount Rs 169046
Rate / Sft Rs 4829.89
2 Main door of size 5' 0" * 7' 0" made with African Teak I st class with carving work
including all labour and material charges
a WOOD
Vertical Frame 1 3 0 ' 5 " 0 ' 4 " 7 ' 0 " 2.92
Horizontal Frame 1 2 0 ' 5 " 0 ' 4 " 5 ' 6 " 1.53
Shutter Frame Vertical 1 2 0 ' 5 " 0 ' 2 " 7 ' 0 " 0.97
Shutter Frame Horzontal 1 2 0 ' 5 " 0 ' 2 " 3 ' 6 " 0.49
5.90 cft 3500.00 20659.722

b Shutter (palakai) 1 2 1 ' 3 " 0 ' 2 " 7 ' 0 " 2.92 cft 5500.00 16041.667

c Labour charges 1 1 5 ' 0 " - - 7 ' 0 " 35.00 sft 300.00 10500.00

d Glass 1 1 1 ' 2 " - - 7 ' 0 " 8.17 sft 500.00 4083.33

e Beeding wood 1 1 - - - - 18 ' 0 " 18 rft 25.00 450.00

f Grill 1 1 1 ' 6 " - - 7 ' 0 " 10.5 sft


18.375 kg 110.00 2021.25

g Tower bolt 1 2 - - - - - - 2 nos 250.00 500.00

h Brass hinges 1 4 - - - - - - 4 nos 150.00 600.00

i Handle 1 1 - - - - - - 1 nos 500.00 500.00

j Lock 1 1 - - - - - - 1 nos 2500.00 2500.00

k Fitting charges( mason ) 1 1 5 ' 0 " - - 7 ' 0 " 35 sft 25.00 875.00

l Cement concrete charges 1 1 - - - - - - 1 500.00 500.00

m Primer charges 1 1 5 ' 0 " - - 7 ' 0 " 78.75 sft 5.00 393.75

n Hold fast ( allu) 1 4 - - - - - - 4 nos 25.00 100.00

o Carving Works 1 1 3 ' 0 " - - 6 ' 0 " 18 sft 250.00 4500.00


Total Amount Rs 64224.722
Over head charges 10 % 6422.4722
Total amount Rs 70647.194
Rate / Sft Rs 2018.49

3 Outer door of size 3' 6" * 7' 0" made with African sal I st class wood panelled door
a Vertical Frame 1 2 0 ' 4 " 0 ' 3 " 7 ' 0 " 1.17
Horizontal Frame 1 2 0 ' 4 " 0 ' 3 " 3 ' 6 " 0.58
Shutter Frame Vertical 1 2 0 ' 5 " 0 ' 2 " 7 ' 0 " 0.97
Shutter Frame Horzontal 1 3 0 ' 5 " 0 ' 2 " 3 ' 6 " 0.73
3.45 cft 5310.00 18326.88

b Shutter ( Pad oak) 1 2 1 ' 3 " 0 ' 1.5 " 7 ' 0 " 2.19 cft 4897.00 10712.19

c carpenter charges 1 1 3 ' 6 " - - 7 ' 0 " 24.5 sft 150.00 3675.00

d Tower bolt 1 2 2 Nos 50 50.00

e Powder coat hinges 1 4 4 Nos 30 30.00

f Handle 1 1 1 Nos 80 80.00


g Lock 1 1 1 Nos 500 500.00

h Fixing charges( mason ) 1 1 3 ' 6 " - - 7 ' 0 " 24.5 sft 30.00 735.00

i Cement concrete charges 1 1 - - - - - - 1 300.00 300.00

j Hold fast ( allu) 1 4 - - - - - - 4 nos 25.00 100.00

k Primer charges 1 1 3 ' 6 " - - 7 ' 0 " 55.125 sft 10.00 551.25

Total amount Rs 35060.313


Over head charges 10 % 3506.0313
Total amount Rs 38566.344

Rate / Sft Rs 1574.14

4 Window of size 3' 6" * 4' 0" made with African teak wood Frame and Shutters in
Pad Oak wood
a Vertical Frame 1 2 0 ' 4 " 0 ' 3 " 4 ' 0 " 0.67 cft
Horizontal Frame 1 2 0 ' 4 " 0 ' 3 " 3 ' 6 " 0.58 cft
1.25 cft 5310.00 6637.50
Shutter Frame Vertical 1 4 0 ' 3 " 0 ' 2 " 4 ' 0 " 0.67 cft
Shutter Frame Horzontal 1 4 0 ' 3 " 0 ' 2 " 1 ' 9 " 0.29 cft
3.46 cft 7670.00 26525.42

b Glass 1 2 1 ' 2 " - - 3 ' 3 " 7.58 sft 60.00 455

c Grill 1 1 3 ' 6 " - - 4 ' 0 " 14.00 sft


24.50 kg 100.00 2450.00

d Hold fast 1 2 25.00 50.00

e Tower bolt (3") 1 4 15.00 60

f Handle (3") 1 2 15.00 30

g hinges (Imax) 1 2 200.00 400

h carpenter charges 1 1 3 ' 6 " - - 4 ' 0 " 14 sft 275.00 3850.00

i Fixing charges ( mason ) 1 1 3 ' 6 " - - 4 ' 0 " 14 sft 60.00 840.00

j Cement concrete charges 1 1 - - - - - - 1 200.00 200.00

k Primer charges 1 1 3 ' 6 " - - 7 ' 0 " 55.125 sft 10.00 551.25

l Beeding wood 1 1 13 ' 0 " - - - - 13 rft 40.00 520.00


35931.667
Over head charges 10 % 3593.1667
Total amount Rs 39524.833

Rate/Sft Rs 2823.20

5 Inner Flush door of size 3' 0" * 7' 0" made with African sal I st class wood and
skin door
a Vertical Frame 1 2 0 ' 4 " 0 ' 3 " 7 ' 0 " 1.17 cft
Horizontal Frame 1 1 0 ' 4 " 0 ' 3 " 3 ' 6 " 0.29 cft
1.46 cft 5310.00 7743.75

b Skin door shutters 1 1 3 ' 0 " - - 7 ' 0 " 21 sft 250.00 5250.00

c carpenter charges 1 1 3 ' 6 " - - 7 ' 0 " 24.5 sft 150.00 3675.00

d Tower bolt 1 2 2 Nos 50 100.00

e Powder coat hinges 1 4 4 Nos 50 200.00

f Handle 1 1 1 Nos 250 250.00

g Lock 1 1 1 Nos 1000 1000.00

h Fixing charges( mason ) 1 1 3 ' 6 " - - 7 ' 0 " 24.5 sft 18.37 450.07

i Cement concrete charges 1 1 - - - - - - 1 300.00 300.00

j Hold fast ( allu) 1 4 - - - - - - 4 nos 50.00 200.00

k Primer charges 1 1 3 ' 6 " - - 7 ' 0 " 55.125 sft 10.00 551.25

Total amount Rs 19720.065


Over head charges 10 % 1972.0065
Total amount Rs 21692.072

Rate / Sft Rs 1032.96


brick wise cost compavolume of bricks required for 1m3
flyash 8 0.001539 649.7726
red bricks 11 0.001539 649.7726
porotherm 75 0.016 62.5
interlockin 45 0.007872 127.0324
soild block 35 0.007872 127.0324
AAC blocks 150 0.0276 36.23188

141.26
bricks required for 1m3
5198.181
7147.498
4687.5
5716.457
4446.133
5434.783
4446.133