New Nithin - TNJ
New Nithin - TNJ
Prabhu's Residence
PROJECT LOCATION Peelamedu, Coimbatore
DATE 24.03.2023
BILL OF QUANTITIES FOR THE PROPOSED RESIDENTIAL BUILDING, COIMBATORE
TOTAL
S.No DESCRIPTION OF WORK
AMOUNT
Excavate foundation in all kinds of soil including soft rock except hard rock requiring blasting part
1 return and spreading surplus earth within the site up to 1.5m depth . 18301
Cement concrete 1:5:10 (1cement, 5 sand, 10 hard blue granite stone metal 40mm and down gauge)
laid in layers not exceeding 1.5m each in depth well consolidated in foundation including necessary
2
shuttering, steps etc.all complete as directed. 44977
Gravel or Pallam sand filling for foundation sides and Basement including consolidation ramming
3 and leveling etc complete. Err:509
Cement concrete 1:4:8 (1 cement, 4 sand and hard granite stone metal 40mm and down gauge) laid
in layers not exceeding 15cms in depth well cosolidated in leveling course under floors including
4
necessary suttering of required profile all complete as directed. 111757
RCC M20 (Design Mix) Using hard blue granite metal 20mm and down gauge including centering,
5 curring etc., complete but excluding cost of reinforcement.
(a) Column Footing 41750
(b) Column
In Ground Floor 18788
( e) Roof Beam
In Ground Floor 44297
Brick work with locally available best quality table moulded bricks of not less than 50 kg.sq.cm
6 crushing strength in cement mortar 1:6 mix (1cement, 6sand).
In Ground Floor including Basement 320998
Half brickwork with locally available best quality table moulded bricks of not less than
50kg/sq/cm crushing strength in Cm 1:4( 1 cement 4 sand) and reinforcement with two numbers of
6mm dia. M.S. rods at every fourth course embedded in cement mortar 1:4 (1cement, 4sand)for
partitinos
7
In Ground Floor Err:509
Ceiling plastering with CM 1:3 (1 cement 3 sand), 12mm minimum thick (sponge finish ) to ceiling
sides and soffit of beams and columns and other interior and exterior RCC surfaces not contiguous
8
masonry.
In Ground Floor 35432
Interior wall plastering with CM 1:5 (1cement, 5 sand), 12 mm minimum thick to all interior faces
of walls (sponge finish) including RCC sufaces not contiguous to masonry. Necessary intrenal
grooves of size 10mm x 10mm shall be carried out as shown /directed by engineer -in-charge.
9
In Ground Floor 77718
Exterior wall platering with CM 1:5 (1cement, 5 sand),( Sponge finish) 12mm minimum thick to all
external faces of brick walls including RCC surfaces not contiguous to masonry in all levels.
10
In Ground Floor 20649
Providing and 20mm thick granite slab of paradise shade / any other approved colour for counter
11 top and wash through including adge nosing, polishing etc., all complete as directed
Kitchen table 8795
Providing and laying 20mm thick machine cut and polished granite stone of approved shade in
teads and risers of steps and landing in CM 1:4 of minimum thickness 20mm jointed with white
cement slurry and pointing with matching pigments including rounding of nosing, rubbing,
forming grooves of required size in the plastering of side of steps and final polishing all complete as
directed Cost of granite : Rs. 150/sft
12
Entrance Steps 6765
Providing and laying first class vitrified tile of make Basic cost ( Rs 50/ Sft ) make Nitco / Johnson
of size 2'0" x 2'0" of approved colour in flooring over a bed of cement mortar 1:4 of minimum
thickness 20mm jointed with white cement slurry mixed with matching pigments all complete as
directed
13
In Ground Floor 65631
Providing and laying 12" X 15" or 12"x12" Ceramic tiles for floors in CM 1:4 with joints so as to
form a true even surface and joints finished neatly with white cement mixed matching pigments all
14
complete as directed. Cost of tiles : Rs. 40/sft
In Ground Floor Err:509
Providing and laying 12" X 15" from somany / Kajaria glazed tiles of approved colour wall
dadoing and floors in CM 1:3 with joints so as to form a true even surface and joints finished neatly
with white cement mixed matching pigments all complete as directed. ( Rate should include base
plastering with CM 1:5 of required thickeness) Cost of tiles : Rs. 40/sft
15
In Ground Floor Err:509
Providing and laying vitrified tile of make Basic cost ( Rs 50/ Sft ) make Nitco / Johnson of
approved colour of size 2'0" x 4" in CM 1:3 in skirting to form a true and even surface and joints
finished neatly with white cement mixed with matching pigments all complete as directed
16
In Ground Floor 6899
17 Providing shelves with cuddapah slab with regular intervals including labour & materials
Ground Floor Err:509
Grano flooring 40mm thick ( minimum) composed of one part of cement, one part of sand, 3 part of
wahed grade dry granite chiiping all to pass through 6mm mesh free from dust including finishing
surface smooth with power trowel including necessary shuttering or glass strips to form panel of
required size to be provided at no extra cost.
18
Terrace floor Err:509
19 Joineries
Supplying and fixing of wooden doors, windows and ventilators Including all mason labour charges and carpentry
charges
(a) Maindoor
In Ground Floor Err:509
21 Painting
(a) Ceiling Area
Ground Floor 24402
( c) Exterior Wall
Ground Floor 12978
Electrical work and fittings including planning & laying of necessary roof and wall conduits (Concealed),
wiring, fixing of electrical switches including metal boxes with basic brands and providing with one light
22 fitting in each room.
Ground Floor 69291
Plumbing work includes, laying of Outer pipelines (exposed) with necessary chamber of standard sizes and
its top covers. Internal plumbing line (Concealed) with basic branded pipes. Also providing plumbing
23 fittings with basic brands(Basic model - White colour only) etc.,
Ground Floor Err:509
4 Gate fabrication and fixing and providing ramp with proper gradient & pillars Err:509
7 Coumpound Wall
Err:509
Cement concrete 1:4:8 (1 cement, 4 sand and hard granite stone metal 40mm
and down gauge) laid in layers not exceeding 15cms in depth well cosolidated
in leveling course under floors including necessary suttering of required
profile all complete as directed.
4 760 sft 147.00 111757
RCC M20 (Design Mix) Using hard blue granite metal 20mm and down gauge
including centering, curring etc., complete but excluding cost of reinforcement.
5
(a) Column Footing 250 cft 167.00 41750
(b) Column
In Ground Floor 113 cft 167.00 18788
( e) Roof Beam
In Ground Floor 253 cft 175.00 44297
Brick work with locally available best quality table moulded bricks of not less
than 50 kg.sq.cm crushing strength in cement mortar 1:6 mix (1cement,
6
6sand).
In Ground Floor including Basement 1405 cft 228.55 320998
Half brickwork with locally available best quality table moulded bricks of not
less than 50kg/sq/cm crushing strength in Cm 1:4( 1 cement 4 sand) and
reinforcement with two numbers of 6mm dia. M.S. rods at every fourth course
embedded in cement mortar 1:4 (1cement, 4sand)for partitinos
7
In Ground Floor Err:509 sft 107.25 Err:509
Ceiling plastering with CM 1:3 (1 cement 3 sand), 12mm minimum thick
(sponge finish ) to ceiling sides and soffit of beams and columns and other
8
interior and exterior RCC surfaces not contiguous masonry.
In Ground Floor 976 sft 36.30 35432
Exterior wall platering with CM 1:5 (1cement, 5 sand),( Sponge finish) 12mm
minimum thick to all external faces of brick walls including RCC surfaces not
10
contiguous to masonry in all levels.
In Ground Floor 464 sft 44.55 20649
Providing and 20mm thick granite slab of paradise shade / any other approved
colour for counter top and wash through including adge nosing, polishing etc.,
11
all complete as directed
Kitchen table 30 sft 293.15 8795
Providing and laying 20mm thick machine cut and polished granite stone of
approved shade in teads and risers of steps and landing in CM 1:4 of
minimum thickness 20mm jointed with white cement slurry and pointing with
matching pigments including rounding of nosing, rubbing, forming grooves of
required size in the plastering of side of steps and final polishing all complete
as directed Cost of granite : Rs. 150/sft
12
Entrance Steps 30 sft 225.50 6765
Providing and laying first class vitrified tile of make Basic cost ( Rs 50/ Sft )
make Nitco / Johnson of size 2'0" x 2'0" of approved colour in flooring over a
bed of cement mortar 1:4 of minimum thickness 20mm jointed with white
cement slurry mixed with matching pigments all complete as directed
13
In Ground Floor 504 sft 130.35 65631
Providing and laying 12" X 15" or 12"x12" Ceramic tiles for floors in CM 1:4
with joints so as to form a true even surface and joints finished neatly with
white cement mixed matching pigments all complete as directed. Cost of tiles :
Rs. 40/sft
14
In Ground Floor Err:509 sft 107.25 Err:509
Providing and laying 12" X 15" from somany / Kajaria glazed tiles of
approved colour wall dadoing and floors in CM 1:3 with joints so as to form a
true even surface and joints finished neatly with white cement mixed matching
pigments all complete as directed. ( Rate should include base plastering with
CM 1:5 of required thickeness) Cost of tiles : Rs. 40/sft
15
In Ground Floor Err:509 sft 94.05 Err:509
Providing and laying vitrified tile of make Basic cost ( Rs 50/ Sft ) make Nitco /
Johnson of approved colour of size 2'0" x 4" in CM 1:3 in skirting to form a
true and even surface and joints finished neatly with white cement mixed with
matching pigments all complete as directed
16
In Ground Floor 111 rft 62.15 6899
17 Providing shelves with cuddapah slab with regular intervals including labour & materials
Ground Floor Err:509 sft Err:509 Err:509
Grano flooring 40mm thick ( minimum) composed of one part of cement, one
part of sand, 3 part of wahed grade dry granite chiiping all to pass through
6mm mesh free from dust including finishing surface smooth with power
trowel including necessary shuttering or glass strips to form panel of required
size to be provided at no extra cost.
18
Terrace floor Err:509 sft Err:509 Err:509
19 Joineries
Supplying and fixing of wooden doors, windows and ventilators Including all mason
labour charges and carpentry charges
(a) Maindoor
In Ground Floor Err:509 sft Err:509 Err:509
(b) Inner Wall - 2 coat Wall putty + 1 coat Primer + 2 Coat interior Emulsion
Ground Floor 2174 sft 25.00 54348
( c) Exterior Wall - 1 Coat White wash + 1 coat Primer + 2 Coat exterior Emulsion
Ground Floor 464 sft 28.00 12978
Electrical work and fittings including planning & laying of necessary roof and wall
conduits (Concealed), wiring, fixing of electrical switches including metal boxes with
22 basic brands and providing with one light fitting in each room.
Ground Floor 69291
Plumbing work includes, laying of Outer pipelines (exposed) with necessary chamber
of standard sizes and its top covers. Internal plumbing line (Concealed) with basic
branded pipes. Also providing plumbing fittings with basic brands(Basic model -
23 White colour only) etc.,
Ground Floor Err:509
Other Works
1 Sump - brick work & 4.5" thickness of RC wall with deck slab & CI Manhole cover L.S 96000
4 Compund Wall @ 5'0" Height (basement upto Portico Level) with supply and fixing of 175 Rft 1250 Err:509
Gate fabrication and fixing and providing ramp with proper gradient & pillars
5 Soakpit For Kitchen, Bath amd septic Tank 3 nos 10000 30000
Total 4983325.2170833
Say Rs.32,75,000/-
Rupees Thirty One Lakhs Forty Four Thousand Only
S.No SPECIFICATION OF WORK
FOUNDATION - Pile Foundation (upto 20'0") with Pile Cap below Natural Ground
1 Level
2 BASEMENMT - Matching with existing basement Level
Basement Filling with earth and well gravel with Consolidation
3 SILL LEVEL 3'0" from Floor finish Level
4 LINTEL LEVEL - 7'0" from FFL
5 ROOF LEVEL - 10'0" From FFL
6 Concrete Grade M - 20 - For Framed Structure (stair area only)
First Floor Residence - Load Bearing Structure
7 Steel - Fe 550 Bars (Vizag/Indrola/iSteel)
8 Cement - ( JSW/Equivalent)
9 Brick Work - Flyash with IS Standard Specification
10 Drawing Class Room - AAC/ Light weight Block with 16" x 4" x 8" Size
Drawing Class Room - Roof will be with MS square tube frame and covered with Terracota
11 Roofing tile
12 Joineries
Main Door - Teak Wood with branded accessories*
Bedroom Doors - Readymade Flush Doors
Windows - UPVC with standard Size with MS square rod safety grill
Toilet Door -FRP Make
13 Plastering Work -
Ceiling Plastering in Cement Mortar Ratio 1:3 or 1:4
Wall Plastering in Cement Mortar Ratio 1:5
14 Roof Work
Grano Flooring with necessary gradient slope
15 Floor Finish
Vitrified Tiles of 4' x 2' of Cost Rs.50/Sft with branded Tiles*
Ceramic tiles for Toilet Floor with basic Cost of Rs.40.00/Sft (Branded*)
Glazed tiles for Kitchen & Toilet Walls with basic Cost of Rs.40.00/Sft (Branded*)
Black Granite for Kitchen Counter Top with basic cost of Rs.150/sft & 120/Sft for Staircase
16 Shelves using cuddapah Slabs for bedroom and Kitchen (necessary wide*)
17 Wall Finish
Inner - 2 Coat Wall Putty + 1 Coat primer + 2 Coat Emulsion Paint (Asian/Dulex/Nippon)
Outer - 1 Coat white wash + Primer + 2 Coat Exterior emulsion (Asian / Dulex/ Nippon)
18 Electrical Work
Concealed Roof and wall conduits with necessary switch points and light points incl. Light Fittings*
(Switches - GM/Legrand/Fybros Basic model White)
Wiring Work - Upto DB * (kundan/RR Kabe/Equivalent Brand)
17 Plumbing Work
Concealed Inner line and exposed outer line for Each toilet and Kitchen
Waste water line and solid waste line laying as per standard (Astral/Star/Ashirvad)
Supplying and Fixing of CP fitting and Sanitary Fittings (Parryware/Jaquar/Equivalent)
19 Handrails - SS 204 Grade
20 Compound Wall - Solid Block upto 5'0" height from portico Floor level
21 Gate with Contemporary Design using MS Rectangular Tube
22 Contemporary Style Façade Elevation*
23 Free Structural Consultation and details
* Conditions Apply
PROJECT NAME - Mr.Prabhu's residence
PROJECT LOCATION - Meena Estate, Coimbatore
DATE - 02.09.2023
Rate/
S.No Description of Work
Area Unit Unit Amount
1 GF Utility + Staircase Area 2029325
Construction of First Floor and Outer
2
Staircase 1305 Sft 2100 2740500
Front Side Drawing Class with Tile Roofing
3
(Roof Area) 272 Sft 1100 299200
4 Soak pit ring erection for kitchen, bath & S.T
1 nos 15000 15000
Demolition and conveyance of existing
5
structure L.S 45000
6 Elevation Charges incl. 3D Design L.S 30000
7 Contigencies & any other Unforeseen Work
Total 5159025
Say Rs.34,95,000/-
Rupees Thirty Four Lakhs Eighty Two Thousand Only
S.No SPECIFICATION OF WORK
FOUNDATION - Pile Foundation (upto 20'0") with Pile Cap below Natural Ground Level
1
2 BASEMENMT - Matching with existing basement Level
Basement Filling with earth and well gravel with Consolidation
3 SILL LEVEL 3'0" from Floor finish Level
4 LINTEL LEVEL - 7'0" from FFL
5 ROOF LEVEL - 10'0" From FFL
6 Concrete Grade M - 20 - For Framed Structure (stair area only)
First Floor Residence - Load Bearing Structure
7 Steel - Fe 550 Bars (Vizag/Indrola/iSteel)
8 Cement - ( JSW/Equivalent)
9 Brick Work - Flyash with IS Standard Specification
10 Drawing Class Room - AAC/ Light weight Block with 16" x 4" x 8" Size
Drawing Class Room - Roof will be with MS square tube frame and covered with Terracota
11 Roofing tile
12 Joineries
Main Door - Teak Wood with branded accessories*
Bedroom Doors - Readymade Flush Doors
Windows - UPVC with standard Size (Openable) with MS square rod safety grill
Toilet Door -FRP Make
13 Plastering Work -
Ceiling Plastering in Cement Mortar Ratio 1:3 or 1:4
Wall Plastering in Cement Mortar Ratio 1:5
14 Roof Work
Grano Flooring with necessary gradient slope
15 Floor Finish
Vitrified Tiles of 4' x 2' of Cost Rs.50/Sft with branded Tiles*
Ceramic tiles for Toilet Floor with basic Cost of Rs.40.00/Sft (Branded*)
Glazed tiles for Kitchen & Toilet Walls with basic Cost of Rs.40.00/Sft (Branded*)
Black Granite for Kitchen Counter Top with basic cost of Rs.150/sft & 120/Sft for Staircase
Shelves using double side polished cuddapah Slabs for bedroom and Kitchen with edge nosing(necessary
16 wide*)
17 Wall Finish
Inner - 2 Coat Wall Putty + 1 Coat primer + 2 Coat Emulsion Paint (Asian/Dulex/Nippon)
Outer - 1 Coat white wash + Primer + 2 Coat Exterior emulsion (Asian / Dulex/ Nippon)
18 Electrical Work
Concealed Roof and wall conduits with necessary switch points and light points incl. Light Fittings*
(Switches - GM/Gold Medal/Fybros Basic model Great White)
Wiring Work - Upto DB * (kundan/RR Kabe/Equivalent Brand)
17 Plumbing Work
Concealed Inner line and exposed outer line for Each toilet and Kitchen
Waste water line and solid waste line laying as per standard (Supreme/Kauvery)
Supplying and Fixing of CP fitting and Sanitary Fittings (Parryware/Hindware/Equivalent)
19 Handrails for staircase & Balcony - SS 304 Grade
20 Outer Staircase - Finish with Tile Laying
21 Contemporary Style Façade Elevation*
22 Free Structural Consultation and details
* Conditions Apply
S.
no Description of work Nos Length Breadth Depth Quantity Unit Rate Amount
A. GROUND FLOOR
Basement Inner 1 278 ' 0 " - ' - " 5 ' 0 " 1390.00
Living Room 1 46.5 ' 0 " - ' - " 9 ' 6 " 441.75
Kitchen 1 32 ' 0 " - ' - " 9 ' 6 " 304.00
Toilet 1 1 23 ' 0 " - ' - " 9 ' 6 " 218.50
bed room 1 55 ' 6 " - ' - " 9 ' 6 " 527.25
Portico 1 62.5 ' 0 " - ' - " 9 ' 6 " 593.75
Stair area 1 16 ' 4 " - ' - " 9 ' 6 " 155.17
Soffits Door & open 1 1 ' 0 " - ' - " 7 ' 0 " 7.00
Soffits Window 1 68 ' 0 " 1 ' 0 " - - 68.00
loft -- Kitchen 1 10 ' 0 " 2 ' 0 " - - 20.00
Deduction
Main door 1 3 ' 6 " - - 7 ' 0 " 24.50
Toilet door 1 2 ' 6 " - - 7 ' 0 " 17.50
Stair area 1 10 ' 0 " - - 3 ' 0 " 30.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
Window 2 4 ' 0 " - - 4 ' 0 " 32.00
Kitchen Window 1 3 ' 6 " - - 3 ' 0 " 10.50
Narrow Window 1 2 ' 6 " - - 6 ' 0 " 15.00
Open 1 4 ' 0 " - - 7 ' 0 " 28.00
Net quantity 1390.00 sft 45.00 62550
2173.92
9 Outer Wall plastering in cement mortar
1:5 mix including scaffolding curing
etc complete.
Alround 1 150 ' 0 " 3 ' 6 " 525.00
Deduction
Window -W 2 4 ' 0 " ' " 4 ' 0 " 32.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
Narrow Window 1 2 ' 6 " - - 6 ' 0 " 15.00
Kitchen Window 1 3 ' 6 " - - 3 ' 0 " 10.50
463.50 sft 40.00 18540
10 Flooring concrete 1:4:8 Mix
including ramming consolidation
charges etc., complete
Living Room 1 14 ' 6 " 16 ' 0 " - 4" 232.00
Kitchen 1 16 ' 0 " 8 ' 0 " - 4" 128.00
bed 1 11 ' 6 " 11 ' 0 " - 4" 126.50
Toilet 1 1 4 ' 0 " 7 ' 6 " - 4" 30.00
Portico 1 15 ' 0 " 16 ' 3 " - 6" 243.75
Setback Passage 0 50 ' 0 " 1 ' 9 " - 4" 0.00
Setback Passage 0 12 ' 6 " 1 ' 9 " - 4" 0.00
760.25 cft 147.00 111757
11 Providing Granite slab for flooring
for Table tops & also for Staircase Steps
incl Full Nosing and all charges
Steps 0 3 ' 0 " 1 ' 6 " - - 0.00
Entrance Steps 2 5 ' 0 " 1 ' 6 " - - 15.00
Mid landing cross step 2 3 ' 0 " 3 ' 0 " - - 9.00
Door & Open Soffits 1 8 ' 0 " 0 ' 9 " - - 6.00
30.00 sft 225.50 6765
12 Black Pearl Granite Slab (cost 165/sft)
Kitchen table 1 12 ' 0 " 2 ' 0 " - - 24.00
Kitchen table Skirting 1 12 ' 0 " 0 ' 6 " - - 6.00
30.00 Sft 293.15 8795
13 Floor finishing with Vitrified Tiles (2'0"'x2'0")
over a cement mortar 1:6 mix including
laying and Finishing.@ 45.00/Sft
Living Room 1 14 ' 6 " 16 ' 0 " - - 232.00
Kitchen 1 16 ' 0 " 8 ' 0 " - - 128.00
bed 1 11 ' 0 " 11 ' 6 " - - 126.50
Soffits 1 17 ' 0 " 1 ' 0 " - - 17.00
503.50 sft 130.35 65631
14 Toilet Floor Tiles (basic cost Rs.40/-)
over a cement mortar 1:6 mix including
laying and Finishing.@ 40.00/Sft
Toilet Floor Tiles 1 4 ' 0 " 7 ' 6 " - - 30.00
30.00 sft 120.00 3600
15 Wall Tiles fixing work with cement paste
mortar using good quality tiles
of cost Rs.50.00/sft incl. all labour charges
Kitchen 1 20 ' 0 " - ' - " 4 ' 6 " 90.00
Toilet 1 1 23 ' 0 " - ' - " 7 ' 0 " 161.00
Deduction
T.door 1 2 ' 6 " ' " 7 ' 0 " 17.50
Ventilator 1 2 ' 0 " ' " 2 ' 0 " 4.00
229.50 sft 90.00 20655
16 Shelves with cuddapah slab including
material & labour charges
Kitchen 1 5 ' 0 " - ' - " 7 ' 0 " 35.00
35.00 sft 205.00 7175
17 Providing Skirting with vitrified tiles 4"
Including cutting fixing charges
Wall length 1 111 ' 0 " 111.00
111.00 rft 62.15 6899
18 Supplying and fixing of wooden doors,
windows and ventilators Including
all mason labour charges and
carpentry charges
a) Main Door (African Teak) 1 3 ' 6 " 7 ' 0 " 24.50 sft 1000.00 24500
b) Toilet Door-D2 (FRP) 1 2 ' 6 " 7 ' 0 " 17.50 sft 400.00 7000
c) UPVC Windows
Window - W 4 4 ' 0 " - - 4 ' 0 " 64.00
Kitchen Window - KW 1 3 ' 6 " - - 3 ' 0 " 10.50
Narrow Window - NW 1 2 ' 6 " - - 6 ' 0 " 15.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
93.50 sft 750.00 70125
d) M S grill work for UPVC Windows
window 4 4 0 " 4 0 " 64.00
10.50
15.00
4.00 kg 140.00
25 shuttering work for R.C.C column , beam, roof slab completed 3600.00% sft 38 136000
a) Column
C1 (incl.Parapet level) 4 1 ' 0 " 0 ' 9 " 9 ' 6 " 28.50
28.50 cft 180.00 5130
b) Roof beam
Beam B1 (0'9"x1'0") 4 17 ' 6 " 0 ' 9 " 1 ' 3 " 65.63
Beam B2 (0'9"x1'0") 2 30 ' 9 " 0 ' 9 " 1 ' 0 " 46.13
111.75 cft 200.00 22350
c) Roof slab
Rohtak dome 1 10 ' " 10 ' 5 " 0 ' 4 " 100.00 sq.ft 360.00 36000
bed room dome 1 12 ' " 12 ' 6 " 0 ' 5 " 144.00 sq.ft 360.00 51840
Slab 1 1 4 ' 9 " 17 ' 6 " 0 ' 5 " 34.64 cft 200 6928
Deduction
Spiral Staircase Cutout 0 4 ' 0 " 4 ' 0 " 0 ' 6 " 0.00
34.64 cft 414.00 14339
d) Loft and Sunshades of 2" tk
Window - W 2 5 ' 6 " 2 ' 0 " - - 22.00
22.00 sft 245.99 5412
e) Lintel beam of 6" tk
Lintel Alround 9"wall 1 89.5 ' 0 " - - " - - 89.50
Lintel Alround 4.5"wall 1 32 ' 0 " - - " - - 32.00
121.50 Rft 221.28 26886
f) Sill level concrete
Alround 0 122 ' 0 " - - " - - 0.00
0.00 Rft 110.64 0
2 9" Brick work in cement mortar 1:6
mix using Flyash table moulded
bricks including scaffolding,curing etc
Super structure
All Round 1 89 ' 0 " 0 ' 9 " 9 ' 6 " 634.13
Deduction
Window -W 2 4 ' 0 " 0 ' 9 " 4 ' 0 " 24.00
Ventilator 1 2 ' 0 " 0 ' 9 " 2 ' 0 " 3.00
Net quantity 607.13 cft 242.00 146924
3 4.5" Brick work in cement mortar 1:5
mix using flyash table moulded
bricks & hoop iron including
scaffolding,curing etc., complete.
Cross walls 1 12 ' 0 " 9 ' 6 " 114.00
Deduction
Bed Room Door 2 3 ' 0 " 7 ' 0 " 42.00
Toilet Door 1 2 ' 6 " 7 ' 0 " 17.50
Net quantity 54.50 cft 114.76 6254
4 Ceiling Plastering using gypsum
including scaffolding etc complete.
c) UPVC Windows
Window -W1&SW 1 6 ' 6 " - - 6 ' 0 " 39.00
Ventilator 1 2 ' 0 " - - 2 ' 0 " 4.00
43.00 sft 750.00 32250
11 Ceramic Floor Tiles (basic cost Rs.40/-)
over a cement mortar 1:6 mix including
laying and Finishing.@ 40.00/Sft
Toilet Floor Tiles 1 4 ' 6 " 12 ' 0 " - - 54.00
Toilet Floor Tiles 0 7 ' 0 " 4 ' 6 " - - 0.00
54.00 sft 114.76 6197
12 Wall Tiles fixing work with cement paste
mortar using good quality tiles
of cost Rs.50.00/sft incl. all labour charges
Toilet Wall 1 33 ' 0 " - ' - " 7 ' 0 " 231.00
Toilet Wall 0 23 ' 0 " - ' - " 7 ' 0 " 0.00
Deduction
Ventilator 1 2 ' 0 " 2 ' 0 " 4.00
T.door 1 2 ' 6 " 7 ' 0 " 17.50
209.50 sft 105.00 21998
.
13 Painting & polishing for wooden joineries
incl all charges
Main door Polishing 0.00 0 sft 200.00 0
Other joineries and Grill painting 43.00 64.5 sft 75.00 4838
D. Other Works
1 Sump -8000 ltrs Lumpsum 96000
Total Amount Rs.32,66,000/- Say Rupees Thirty Two Lakh and Sixty six Thousand only
1543500
1575
441000 sand
1984500 clay
273 cement
14800 1827
71800 822150 steel
2806650
centering,barbending,placing
0.666667
0.277778 266.8
57 963.1769 54901.08
15.83333
2112.167
0.75
0.333333 0.416667
0.25
0.0625
rohtak dome
brick size 9x
0.0625 cft
37875.27
50000
main dis
10.16667
60.95703 36.94365 23.27273
0.606061 0.387879
28000 5040
33040
4x 3
340/sq.ft
S.
NO DESCRIPTION UNIT RATE
1a. Excavate foundation in all kinds of soil including soft rock except hard
rock requiring blasting part return and spreading surplus earth within Cft 6.60
the site up to 1.5m depth .
1b. Excavate foundation in all kinds of soil including soft rock except hard
rock requiring blasting part return and spreading surplus earth within Cft 19.80
the site below 1.50m to 3.00m depth .
2 CEMENT CONCRETE
2b. Cement concrete 1:5:10 (1cement, 5 sand, 10 hard blue granite stone
metal 40mm and down gauge) laid in layers not exceeding 1.5m each in
depth well consolidated in foundation including necessary shuttering, Cft 152.35
steps etc.all complete as directed.
2a. Cement concrete 1:4:8 (1 cement, 4 sand and hard granite stone metal
40mm and down gauge) laid in layers not exceeding 15cms in depth
well cosolidated in leveling course under floors including necessary Cft 161.70
suttering of required profile all complete as directed.
4 R.C.C WORK
RCC M20 (Design Mix) Using hard blue granite metal 20mm and down
gauge including centering, curring etc., complete but excluding cost of With out
reinforcement. Steel
4i In suspended Two Way roof slab (in beam and slab costruction)
4i(1) In Ground floor Cft 359.70
4i(2) In First floor Cft 384.88
4i(3) In second floor Cft 410.06
4i(4) In third floor Cft 435.24
4j In suspended One Way roof slab (in beam and slab costruction)
4j(1) In Ground floor Cft 347.60
4j(2) In First floor Cft 371.93
4j(3) In second floor Cft 396.26
4j.4 In third floor Cft 420.60
4k. In Sloping Roof Cft 456.50
4l. In staircase flight slab and mid landing
4l.1. In Ground floor Cft 371.80
4l.2. In First floor Cft 397.83
4l.3. In second floor Cft 423.85
4l.4. In third floor Cft 449.88
4m. Folded type / Concrete staircase steps
4m.1. In Ground floor Cft 550.00
4m.2. In First floor Cft 588.50
4m.3. In second floor Cft 627.00
4m.4. In third floor Cft 665.50
5 MASONRY WORK 10% Increased
5a. Brick work with locally avaiable best quality table moulded bricks of
not less than 50 kg.sq.cm crushing strength in cement mortar 1:6 Cft 228.55
(1cement, 6 sand) in foundation, plinth and Sump
5b. Brick work with locally available best quality table moulded bricks of
not less than 50 kg.sq.cm crushing strength in cement mortar 1:5 mix
(1cement, 6sand) in superstructure. Interlocking bricks 8"
5.1 In Ground floor Cft 228.55
5.2 In First floor Cft 228.55
5.3 In second floor Cft 260.55
5.4 In third floor Cft 276.55
6 Half brickwork with locally available best quality table moulded bricks
of not less than 50kg/sq/cm crushing strength in Cm 1:4( 1 cement 4
sand) and reinforcement with two numbers of 6mm dia. M.S. rods at
every fourth course embedded in cement mortar 1:4 (1cement,
4sand)for partitinos
6.1 In Ground floor Sft 107.25
6.2 In First floor Sft 114.76
6.3 In second floor Sft 122.26
6.4 In third floor Sft 129.77
PLASTERING
7a. Interior wall plastering with CM 1:5 (1cement, 5 sand), 12 mm
minimum thick to all interior faces of walls (sponge finish) including
RCC sufaces not contiguous to masonry. Necessary intrenal grooves of
size 10mm x 10mm shall be carried out as shown /directed by engineer
-in-charge.
7a.1 Ground Floor Sft 35.75
7a.2 First Floor Sft 38.25
7a.3 Second floor Sft 40.75
7a.4 Third Floor Sft 43.26
7b Exterior wall platering with CM 1:5 (1cement, 5 sand),( Sponge finish)
12mm minimum thick to all external faces of brick walls including RCC
surfaces not contiguous to masonry in all levels.
10a Providing and laying first class vitrified tile of make Basic cost ( Rs 50/
Sft ) make Nitco / Johnson of size 2'0" x 2'0" of approved colour in
flooring over a bed of cement mortar 1:4 of minimum thickness 20mm
jointed with white cement slurry mixed with matching pigments all
complete as directed
10a.1 In Ground floor Sft 130.35
10a.2 In First floor Sft 139.47
10a.3 In second floor Sft 148.60
10a.4 In third floor Sft 157.72
10b Providing and laying 24" X 24" from somany / Kajaria glazed tiles of
approved colour flooring in CM 1:5 with joints so as to form a true
even surface and joints finished neatly with white cement mixed
matching pigments all complete as directed. Cost of tiles : Rs. 50/sft
10b.1 In Ground floor Sft 130.35
10b.2 In First floor Sft 139.47
10b.3 In second floor Sft 148.60
10b.4 In third floor Sft 157.72
11 Providing and laying vitrified tile of make Basic cost ( Rs 50/ Sft )
make Nitco / Johnson of approved colour of size 2'0" x 4" in CM 1:3 in
skirting to form a true and even surface and joints finished neatly with
white cement mixed with matching pigments all complete as directed
11.1 In Ground floor Rft 62.15
11.2 In First floor Rft 66.50
11.3 In second floor Rft 71.16
11.4 In third floor Rft 76.14
12 Providing and laying 12" X 15" Ceramic tiles for floors in CM 1:4
with joints so as to form a true even surface and joints finished neatly
with white cement mixed matching pigments all complete as directed.
Cost of tiles : Rs. 40/sft
13 Providing and laying 12" X 15" from somany / Kajaria glazed tiles of
approved colour wall dadoing and floors in CM 1:3 with joints so as to
form a true even surface and joints finished neatly with white cement
mixed matching pigments all complete as directed. ( Rate should
include base plastering with CM 1:5 of required thickeness) Cost of
13.1 In Ground floor Sft 94.05
13.2 In First floor Sft 100.63
13.3 In second floor Sft 107.22
13.4 In third floor Sft 113.80
14 Providing and laying 20mm thick machine cut and polished granite
stone of approved shade in teads and risers of steps and landing in
CM 1:4 of minimum thickness 20mm jointed with white cement slurry
and pointing with matching pigments including rounding of nosing,
rubbing, forming grooves of required size in the plastering of side of
steps and final polishing all complete as directed Cost of granite : Rs.
150/sft
14.1 In Ground floor Sft 225.50
14.2 In First floor Sft 241.29
14.3 In second floor Sft 257.07
14.4 In third floor Sft 272.86
14.5 Providing and laying 20mm thick granite of paradise shade / any other
approved colour for flooring over ledges including edge nosing Sft 225.50
polishing etc., all complete as directed
14.6 Providing and 20mm thick granite slab of paradise shade / any other
approved colour for counter top and wash through including adge Sft 293.15
nosing, polishing etc., all complete as directed
TERRACE WORKS
16 Brick jelly cement concrete 1:4:8 using approved broken brick jelly 25
mm and down gauge laid in sunken floors. Cft 61.60
17 Providing and laying pressed tiles in C.M 1:3 over weathering course at
terrace includes all labour charges 88.00
18a Solid Block work 4" tk with locally available best quality table moulded
bricks of not less than 50 kg.sq.cm crushing strength in cement mortar
1:4 mix (1cement, 6sand) in superstructure.
6.00
18.00
138.50
147.00
49.50
10% Increased
500.00
535.00
570.00
605.00
Old Rate
200.50
200.50
214.54
228.57
242.61
97.50
104.33
111.15
117.98
32.50
34.78
37.05
39.33
40.50
43.34
46.17
49.01
33.00
35.31
37.62
39.93
45.00
118.50
126.80
135.09
143.39
118.50
126.80
135.09
143.39
56.50
60.46
64.69
69.21
97.50
104.33
111.15
117.98
85.50
91.49
97.47
103.46
205.00
219.35
233.70
248.05
205.00
266.50
45.00
56.00
80.00
79.50
85.07
96.90
96.20
85.00
90.95
96.90
102.85
109.00
116.63
124.26
131.89
75000.00
10.00
R.G Associates
Civil Engineers & Structural Consultants 18.03.2024
60/6, Sri Ragavendra House, Thiruvalluvar Nagar,
Trichy Road, Ramanathapuram, Coimbatore - 641045
Ph: 9842530027, 9585530027.
1a Earth work excavation In ordinary soil below 5'0" depth for Open Well
Labour for excavation 100 cft Rs. 16.36 /cft 1636.36
1636.36
Rate/Cft = 16.36 19.00
1b Earth work excavation In ordinary soil upto 4'0" depth for Column Pits
Labour for excavation 100 cft Rs. 10.00 /cft 1000.00
1000.00
Rate/Cft = 10.00 11.50
1c Earth work excavation In rocky soil below 4'0" depth for Column Pits
Labour for excavation 100 cft Rs. 12.00 /cft 1200.00
1200.00
Rate/Cft = 12.00 14.00
3b Filling the basement with well gravel inluding consolidation - 100 cft
Well Gravel 130 cft Rs. 30.00 /cft 3900.00
Labour charges 100 cft Rs. 6.00 /cft 600.00
4500.00
Rate/Cft =Rs 45.00 52.00
4 RCC 1:1.5:3 using 20mm metal excluding centering & fabrication - 100 cft
Cost of 20mm metal 95 cft Rs. 60.00 /cft 5700.00
Cost of M sand 60 cft Rs. 65.00 /cft 3900.00
Cost of cement 20.00 bag Rs. 300.00 /bag 6000.00
15600.00
Rate/Cft =Rs 156.00 179.50
INCLUDING CENTERING
4a1 Pile Foundation - 100 rft
RCC M20 100 cft Rs. 156.00 /cft 15600.00
Labour charges 100 rft Rs. 200.00 /cft 20000.00
35600.00
Rate/Cft =Rs 356.00 409.50
5 Brick work 9" thick in c.m.1:6 mix for super structure works - 100 cft
Bricks 1300 Nos Rs. 8.00 /Each 10400.00
M sand 34 cft Rs. 65.00 /cft 2210.00
Cement 5.00 bag Rs. 300.00 /bag 1500.00
14110.00
Labour charges 100 cft Rs. 44.00 /cft 4400.00
18510.00
Rate/Cft =Rs 185.10 213.00
6 Brick partition wall 115mm thick in c.m.1:4 including hoop iron - 100 sft
Bricks 550 Nos Rs. 8.00 /Each 4400.00
M sand 13 cft Rs. 65.00 /cft 845.00
Cement 2.00 bag Rs. 300.00 /bag 600.00
Hoop iron 6 kg Rs. 85.00 /kg 510.00
6355.00
Labour charges 100 Sft Rs. 26.00 /Sft 2600.00
8955.00
Rate/Sft =Rs 89.55 103.00
7a Inside wall Plastering in c.m.1:5 mix for an average thickness of 12mm - 100 sft
M sand 9.00 cft Rs. 65.00 /cft 585.00
Cement 2.00 bag Rs. 300.00 /bag 600.00
1185.00
Labour charges ( including Scaffoldin 100.00 sft Rs. 18.00 /sft 1800.00
Curing charges )
2985.00
Rate/Sft =Rs 29.85 34.50
Labour charges ( including Scaffoldin 100.00 sft Rs. 25.00 /sft 2500.00
Curing charges)
3750.00
Rate/Sft =Rs 37.50 43.50
8 Ceiling plastering in c.m.1:3 mix for an average thickness of 12mm - 100 sft
M sand 9.00 cft Rs. 35.00 /cft 315.00
Cement 2.00 bag Rs. 300.00 /bag 600.00
915.00
Labour charges ( including Scaffoldin 100.00 sft Rs. 20.00 /sft 2000.00
Curing charges)
2915.00
Rate/Sft =Rs 29.15 34.00
9 PCC 1:4:8 - in Using 40mm metal for flooring, 100mm thick - 100 sft
Cost of 40mm metal 30 cft Rs. 60.00 /cft 1800.00
Cost of M sand 19.5 cft Rs. 65.00 /cft 1267.50
Cement 2.75 bags Rs. 300.00 /bag 825.00
3892.50
Overheads & Profits 15% 3892.50 583.88
Labour charges 100 sft Rs. 15.00 /sft 1500.00
5976.38
Rate/Sft =Rs 59.76 69.00
10 Providing and fixing Vitrified tiles for flooring over c.m.1:4, 20mm thick - 1 Sft
Vitrified tile 1.10 Sft Rs. 50.00 /sft 55.00
Transportation, handling & wastage 10 % 5.50
White Cement 0.08 kg Rs. 25.00 / kg 2.00
Petty Materials 1.00 Sft Rs. 4.00 / sft 4.00
Cost of cement 0.04 bag Rs. 300.00 /bag 12.00
Cost of Sand 0.15 cft Rs. 35.00 /cft 5.25
83.75
Labour charges for cutting & Laying 1 sft Rs. 22.73 /sft 22.73
106.48
Rate/Sft =Rs 106.48 122.50
11 Providing and fixing Vitrified tiles skirting of 100mm in c.m.1:4, 20mm thick - 1 Rft
Vitrified tile 0.25 Sft Rs. 80.00 /sft 20.00
Transportation, handling & wastage 10 % 2.00
White Cement 0.08 kg Rs. 25.00 / kg 2.00
Petty Materials 1.00 Sft Rs. 4.00 / sft 4.00
Cost of cement 0.02 bag Rs. 300.00 /bag 6.00
Cost of Sand 0.06 cft Rs. 39.00 /cft 2.15
36.15
Labour charges for cutting & Laying 1 Rft Rs. 14.55 /rft 14.55
Rate/Rft =Rs 50.69 50.69 58.50
12 Providing and fixing ceramic tiles for flooring over c.m.1:4, 20mm thick - 1 Sft
Basic cost ( Rs 40/ Sft ) 1 Sft Rs. 50.00 /sft 50.00
Transportation, handling & wastage 7.5% 3.75
Cost of cement 0.02 bag Rs. 300.00 /bag 6.00
Cost of Sand 0.10 cft Rs. 65.00 /cft 6.50
66.25
Labour charges for cutting & Laying 1 sft Rs. 22.73 /sft 22.73
Rate/Sft =Rs 88.98 88.98 102.50
13 Providing and fixing glazed tiles for dadooing over cm.1:4, 20mm thick - 1 Sft
Vitrified Tiles Basic cost ( Rs 40/ Sft ) 1 Sft Rs. 40.00 /sft 40.00
Transportation, handling & wastage 7.5% 3.00
Cost of cement 0.02 bag Rs. 300.00 /bag 6.00
Cost of Sand 0.10 cft Rs. 65.00 /cft 6.50
55.50
Labour charges for cutting & Laying 1 sft Rs. 22.73 /sft 22.73
Rate/Sft =Rs 78.23 78.23 90.00
14 Providing and fixing Granite Slab for flooring over c.m.1:4, 20mm thick - 1 Sft
Basic cost (135/sft) 1 Sft Rs. 125.00 /sft 125.00
Transportation, handling & wastage 10% 12.50
Cost of cement 0.025 bag Rs. 300.00 /bag 7.50
Cost of Sand 0.11 cft Rs. 65.00 /cft 6.83
151.83
Labour charges for cutting & Laying 1 sft Rs. 35.00 /sft 35.00
186.83
Rate/Sft =Rs 186.83 215.00
17 Providing & Laying pressed tiles in C.M 1:3 Over laid weathering course - 1 Sft
Pressed tile 1.85 Nos Rs. 14.00 / No 25.90
M sand 0.15 cft Rs. 65.00 /cft 9.75
Cement 0.04 bag Rs. 300.00 /bag 12.00
47.65
Labour charges for laying & finishing 1.00 sft Rs. 22.73 /sft 22.73
70.38
Rate/Sft =Rs 70.38 81.00
18 Solid block Work
a Solid block Work wall 4" thick in c.m.1:4 - 100 sft
Solid Blocks 100 Nos Rs. 36.00 /Each 3600.00
M sand 11 cft Rs. 65.00 /cft 715.00
Cement 1.50 bag Rs. 300.00 /bag 450.00
4765.00
57 45
115
35 35
150 210
900
1008
0.277778 0.208333
3240
184680 45360
230040
96.5
579 2084.4 105
118810.8 504 22680
371530.8
LABOUR RATE QUOTATION
S.
Description of work
No
c. Plain cement concrete using ellis pattern jelly for flooring work surface cleaning at 2" thick
3 Sand or earth filling with consolidation & surface leveling ( Consolidation for 2'0" )
4 Stone Work
a. R.R.Masonry for basement work ( Including surface cleaning and centering marking )
C.R.Masonry for basement work ( Including surface cleaning and centering marking )
R.C.C for one way roof slab upto 4.5" thick (Including farms works bar tyeing leveling
k.
concreting placing, mixture machine and its transporting charges )
l. R.C.C for two way roof slab upto 5" thick ( Including farms works bar tyeing leveling
concreting placing, mixture machine and its transporting charges )
m. R.C.C for sloped roofslab upto 5" thick (Including farms works bar tyeing leveling concreting
placing,mixture machine and its transporting charges ) - A - TYPE
n. R.C.C for sloped roofslab upto 5" thick (Including farms works bar tyeing leveling concreting
placing,mixture machine and its transporting charges ) - 4 SIDE
R.C.C for Staircase Flight upto 5" thick (Including farms works bar tyeing leveling concreting
o.
placing,mixture machine and its transporting charges )
p. Conceiled lintels
q. Pre Cast Slabs
6 Brick Work
Brick work in CM 1:6 using table moulded bricks of approved make and of standard
a.
strength in super structure for 9" walls (Marking and brick soaking )
Brick work 4-1/2" thickness walls (Marking and brick soaking with hoop reinforcement at
b.
every 5th layer)
Brick on edge work in CM 1:6 using table moulded bricks of approved make and of
c.
standard strength in super structure for 9" walls (Marking and brick soaking )
Brick work for steps in CM 1:6 using table moulded bricks of approved make and of
d.
standard strength 3'0" wide (Marking and brick soaking ).
Solid Block Work CM using Machine moulded blocks of approved make and of standard
b.
strength 6" walls with both side Pointing
Solid Block Work CM using Machine moulded blocks of approved make and of standard
c.
strength 4" walls with both side Pointing
8 Plastering Work
Doors, windows, grill & gate with concrete fittings ( Including plumbing leveling and
a.
packing )
b. Ceiling plastering with cement mortar (Including scofolding and leveling and Hogging)
c. Inner wall plastering with cement mortar (Including scofolding and leveling)
d. Outer wall plastering with cement mortar (Including scofolding and leveling)
e. Sloped roof plastering with cement mortar (Including scofolding and leveling)
f. Column & Beam plastering with cement mortar (Including scofolding and leveling)
g. R.C.C Wall surface plastering with cement mortar (Including scofolding and leveling)
h. Inner wall & Floor plastering with cement slurry (Including scofolding and leveling)
8 Other works
Weathering course laying in surki with lime and brick bats 3" tk mixture including brick jelly
a.
breaking, pull fixing & lime concreting.
b. Flooring above the surki with cement mortar in cement morter
c. Flooring tiles laying above the surki and binding in cement morter
d. Elevation tiles laying and binding in cement morter
e. 3" Vertical brick work for sunshade edges with plastering in cement morter
9 Flooring
a. Vertified Tile Laying
Skirting
11 Plumbing Work
1 Lifting charges:
2 RMC -- DEDUCTIONS FROM THE QUOTED RATE FOR ROOF SLAB / ROOF BEAMS
Note :
The above rates are ground floor only, for each 10'0" height the rates will be increased by
1
15% each floor.
Mazdoor work : Curing, Elevation, Decorative works, Skirting touchup work & Cleaning work
3
will be Billed Actual labour plus 10% Service charge.
4 Electricity, motor & water supply charges will be supplied by Client only.
Labour Shed & Place of storing materials to be provided by the client within 30 feet
5
otherwise lead charges to be claimed from client.
6 Payment to be given by the Client at various stages & Every Week end.
7 Whatever cost comes from Government Body it will be given by the client.
8 If there is any alteration & addition to the existing plan,that will be billed suitably.
For any additional works other than specified above rates will be given at the time of
9
execution
10 If there is joineries two sides jarms work no opening deduction in plastering area.
Date 05.03.23_
Rate for Data
Unit Rate
1 Cft 12.00
1 Cft 18.00
1 Cft 6.00
1 Cft 8.00
1 Cft 12.00
1 Cft 30.00
1 Sft 15.00
1 Sft 15.00
1 Cft 6.00
1 Cft 30.00
1 Cft 35.00
1Sft 21.00
1 Cft 65.00
1 Rft 200.00
1 Cft 200.00
1 Cft 170.00
1 Rft 50.00
1 Cft 180.00
1 Rft 26.00
1 Rft 70.00
1 Sft 70.00
1 Sft 75.00
1 Cft 125.00
1 sft 75.00
1 Sft 80.00
1 sft 120.00
1 sft 150.00
1 sft 85.00
1 Rft 50.00
1 Sft 58.00
cft
1 Cft 44.00 59
1 Sft 26.00
1 Rft 50.00
1 Rft 65.00
1 Sft 25.00
1 Sft 20.00
1 Sft 20.00
1 Sft 40.00
1 Sft 20.00
1 Sft 18.00
1 Sft 25.00
1 Sft 50.00
1 Sft 40.00
1 Sft 20.00
1 Sft 25.00
1 Sft 27.50
1 Sft 20.00
1 Sft 25.00
1 Sft 25.00
1 Rft 75.00
1 Sft 45.00
1 Rft 35.00
1 Rft 50.00
1 Sft 50.00
1 No 2000.00
1 Sft 10.00
1 Rft 20.00
1 Sft 25.00
1 Rft 16.00
1 Sft 35.00
1 Sft 30.00
1 Sft 30.00
Rs.9/- CFT
Data for wood work joineries
24.12.2021
S.no Description of work Nos Piece Length Breadth Depth Qty Unit Rate Amount
1 Main door of size 5' 0" * 7' 0" made with Burma Teak I st class with carving work
a including all labour and material charges
WOOD
Vertical Frame 1 3 0 ' 5 " 0 ' 4 " 7 ' 0 " 2.92
Horizontal Frame 1 2 0 ' 5 " 0 ' 4 " 5 ' 6 " 1.53
Shutter Frame Vertical 1 2 0 ' 5 " 0 ' 2 " 7 ' 0 " 0.97
Shutter Frame Horzontal 1 2 0 ' 5 " 0 ' 2 " 3 ' 6 " 0.49
5.90 cft 13570.00 80100.694
b Shutter (palakai) 1 2 1 ' 3 " 0 ' 2 " 7 ' 0 " 2.92 cft 15930.00 46462.5
c Labour charges 1 1 5 ' 0 " - - 7 ' 0 " 35.00 sft 300.00 10500.00
k Fitting charges( mason ) 1 1 5 ' 0 " - - 7 ' 0 " 35 sft 25.00 875.00
m Primer charges 1 1 5 ' 0 " - - 7 ' 0 " 78.75 sft 5.00 393.75
b Shutter (palakai) 1 2 1 ' 3 " 0 ' 2 " 7 ' 0 " 2.92 cft 5500.00 16041.667
c Labour charges 1 1 5 ' 0 " - - 7 ' 0 " 35.00 sft 300.00 10500.00
k Fitting charges( mason ) 1 1 5 ' 0 " - - 7 ' 0 " 35 sft 25.00 875.00
m Primer charges 1 1 5 ' 0 " - - 7 ' 0 " 78.75 sft 5.00 393.75
3 Outer door of size 3' 6" * 7' 0" made with African sal I st class wood panelled door
a Vertical Frame 1 2 0 ' 4 " 0 ' 3 " 7 ' 0 " 1.17
Horizontal Frame 1 2 0 ' 4 " 0 ' 3 " 3 ' 6 " 0.58
Shutter Frame Vertical 1 2 0 ' 5 " 0 ' 2 " 7 ' 0 " 0.97
Shutter Frame Horzontal 1 3 0 ' 5 " 0 ' 2 " 3 ' 6 " 0.73
3.45 cft 5310.00 18326.88
b Shutter ( Pad oak) 1 2 1 ' 3 " 0 ' 1.5 " 7 ' 0 " 2.19 cft 4897.00 10712.19
c carpenter charges 1 1 3 ' 6 " - - 7 ' 0 " 24.5 sft 150.00 3675.00
h Fixing charges( mason ) 1 1 3 ' 6 " - - 7 ' 0 " 24.5 sft 30.00 735.00
k Primer charges 1 1 3 ' 6 " - - 7 ' 0 " 55.125 sft 10.00 551.25
4 Window of size 3' 6" * 4' 0" made with African teak wood Frame and Shutters in
Pad Oak wood
a Vertical Frame 1 2 0 ' 4 " 0 ' 3 " 4 ' 0 " 0.67 cft
Horizontal Frame 1 2 0 ' 4 " 0 ' 3 " 3 ' 6 " 0.58 cft
1.25 cft 5310.00 6637.50
Shutter Frame Vertical 1 4 0 ' 3 " 0 ' 2 " 4 ' 0 " 0.67 cft
Shutter Frame Horzontal 1 4 0 ' 3 " 0 ' 2 " 1 ' 9 " 0.29 cft
3.46 cft 7670.00 26525.42
i Fixing charges ( mason ) 1 1 3 ' 6 " - - 4 ' 0 " 14 sft 60.00 840.00
k Primer charges 1 1 3 ' 6 " - - 7 ' 0 " 55.125 sft 10.00 551.25
Rate/Sft Rs 2823.20
5 Inner Flush door of size 3' 0" * 7' 0" made with African sal I st class wood and
skin door
a Vertical Frame 1 2 0 ' 4 " 0 ' 3 " 7 ' 0 " 1.17 cft
Horizontal Frame 1 1 0 ' 4 " 0 ' 3 " 3 ' 6 " 0.29 cft
1.46 cft 5310.00 7743.75
b Skin door shutters 1 1 3 ' 0 " - - 7 ' 0 " 21 sft 250.00 5250.00
c carpenter charges 1 1 3 ' 6 " - - 7 ' 0 " 24.5 sft 150.00 3675.00
h Fixing charges( mason ) 1 1 3 ' 6 " - - 7 ' 0 " 24.5 sft 18.37 450.07
k Primer charges 1 1 3 ' 6 " - - 7 ' 0 " 55.125 sft 10.00 551.25
141.26
bricks required for 1m3
5198.181
7147.498
4687.5
5716.457
4446.133
5434.783
4446.133