Issued by
Issued by
Issued By
Executive Engineer
Jabalpur Development Authority
7A, Civic Center, Marhatal,
Jabalpur – 482002
Mob.: 9826492114
Email: ceojda@gmail.com
                                         Page |1
                 JABALPUR DEVELOPMENT AUTHORITY
                    7A, Civic Center, Marhatal, Jabalpur (M.P.) Pin – 482002
NOTICEINVITINGTENDER
(Rs.)
Note:-
   1. The Firms should have registration with Employees Provident Fund, ESIC,
      GST, and PAN. Copy of registration is to be submitted along with
      tender document.
   2. Amendments to NIT if any, would be published on portal (https://www.mptenders.gov.in.)
      only, and not in newspaper.
   3. Any type of exemption in Tender form fees/EMD will notable allowed and tender
      without tender form fees / EMD shall be rejected prima facie.
                                                                   Executive Engineer
                                                            Jabalpur Development Authority
                                                                       Jabalpur
                                                                                                    Page |2
           JABALPUR DEVELOPMENT AUTHORITY
               7A, Civic Center, Marhatal, Jabalpur (M.P.) Pin – 482002
RFP Document
JABALPUR Development Authority Invites Request for Proposal (RFP) from eligible Consultant
for Providing Consultancy Selection PROJECT MANAGEMENT CONSULTANCY
FOR INFRASTRUCTURAL DEVELOPMENT WORKS FOR                             Scheme     No    64
and 65 &TDS-02 (PHASE-II) OF JDA, AT JABALPUR.
Costofproject: -
Tentative cost of projects for monitoring is Rs. 350 Crore. The Final Payment
to the consultant will be calculated as per the percentage rate of the final
project cost quoted in the bid . The final project cost will be the payment
made to the contractors including escalation but excluding G.S.T.
                                                                                 Page |3
                             Key Dates:-
                       TENDERTIMESCHEDULE
                                                                 Page |4
                                      DATASHEET
                                                                                     Page |5
10   Performance Security   Performance security: - The Bidder shall have
                            to produce a performance security in the form
                            of bank guarantee/ FDR by any nationalized/
                            scheduled bank in India. The above performance
                            security can be liquidated by the authority i.e.
                            JABALPUR      Development    Authority  JABALPUR
                            stating that the amount claim is due by way
                            of loss or damage cost to or suffered the
                            authority by reason of any breach by said
                            Bidder of any of the terms or conditions
                            contained in the agreement or by reason of
                            the Bidder failure to perform their duty.
                            The       decision   of  Chief   Executive   Officer
                            JABALPUR Development Authority JABALPUR
                            shall be final and binding in this regards.
                            I. The performance security in the form of
                                 bank guarantee/ FDR by any nationalized/
                                 scheduled bank in India shall be equivalent
                                 to 5% of the total fees to be paid to the
                                 Bidder by the Authority at the time of
                                 Agreements.
                            II. 5% Security Deposit will be deducted from
                                 each running bill of the consultant.
                            III. The Performance security will be refunded
                                 after successful completion of project.
                            IV. The security deposit will be refunded after
                                 successful completion of project.
                                                                              Page |6
  EXPLANATORYNOTEOFTHEPROJECT
1) PROJECT      MANAGEMENT       CONSULTANCY       FOR   CONSTRUCTION OF TAR
   R O A D S , SEWER LINE SYSTEM, WATER PIPE LINE, STORM WATER
   UTILITY     DUCT,    ELECTRIFICATION     WORK,     BOUNDARY     WALL,    BOX
   CULVERT & OTHER INFRASTRUCTURAL DEVELOPMENT WORKS, FOR
   SCHEME NO 64, SCHEME NO 65 AND TDS 2 (II PHASE) OF JDA, AT
   JABALPUR. WITH AREA APPROX. 336.4 HECT. AND TENTATIVE PROJECT
   COSTWILL BE RS. 350CRORE.
   DISCLAIMER
   1. The information contained in this Expression of Request For Proposal (RFP)
    are     subsequently               provided        to        Applicants        (Firms),           whether            verbally          or     in
    documentary or any other form by or on behalf of JABALPUR Development
    Authority     (here          in     after    referred          to     as     JDA/          The     JDA)         or     any        of        their
    employees, is provided to Applicants on the terms and conditions set out in
    this    RFP        and        such         other    terms            and     conditions           subject        to        which            such
    information is provided.
  4. This RFP may not be appropriate for all persons, and it is not possible for
    the JDA and its                    employees to consider the                          objectives, technical expertise and
    particular needs of each party who reads or uses this RFP. The assumptions,
    assessments, statements and                         information contained                    in this RFP, may not be
    complete,         accurate,          adequate           or     correct.        Each         Applicant        should,             therefore,
    conduct     its     own           investigations        and         analysis      and       should        check        the       accuracy,
    adequacy,          correctness,             reliability        and          completeness             of      the           assumptions,
    assessments            and        information       contained           in     this        RFP     and      obtain         independent
    advice from appropriate sources.
 5- Information provided in this RFP to the Applicants maybe on a wide range of
    matters,      some           of      which         may        depend           upon         interpretation            of        law.        The
    information       given       is     not     intended          to     be     an       exhaustive          account          of     statutory
    requirements           and        should      not        be         regarded       as       a      complete            or authoritative
    statement of law. The JDA accept s no responsibility for the accuracy or otherwise for any
    interpretation or opinion on the law expressed herein.
                                                                                                                                                  Page |7
    6- The JDA and its employees/ advisor smoke no representation or warranty and shall
    have no liability to any person including any Applicant under any law, statute,
    rules or regulations or tort, principles of restitution or unjust enrichment or otherwise
    for any loss, damages, cost or expense which may arise from or be incurred or
    suffered on account of anything contained in this RFP or otherwise, including the
    accuracy, adequacy, correctness, reliability or completeness of the RFP and any
    assessment, assumption, statement or information contained therein or deemed to
    form part of this RFP or arising in any way in this Selection Process.
7    The   JDA    also   accepts      no   liability   of   any    nature   whether    resulting    from
     negligence    or    otherwise     however         caused     arising   from    reliance   of   any
     Applicant upon the statements contained in this RFP.
8- The      JDA    may in     its    absolute    discretion,      but   without    being   under    any
     obligation   to     do    so,     update,         amender      supplement      the    information,
     assessment or assumption contained in this RFP.
9- The issue of this RFP does not imply that the JDA is bound to select
     an Applicant or to appoint the Selected Applicant, as the case may be,
     for the Consultancy Work and the JDA reserves the right to reject all or
     any of the Proposals without assigning any reasons whatsoever.
                                                                                                      Page |8
          Part–1
Pre-QualificationinGeneral
                             Page |9
1. INFORMATION TO APPLICANTS
                                                                                   Page |10
3. PREPARATION OF PROPOSAL
     Preparation and submission shall be in two envelopes as below.
   DOCUMENTSINPROOFOFELIGIBILITY
  The bidder’s eligibility proposal must       include the following information       but
  not limited to the formats attached          in envelope A (technical) (To           be
  Submitted online only)
     Bid Security
     ▪  The bid shall be accompanied by bid security of Rs. 3,50,000/- online only
        as per website link.
     ▪   Any bid not accompanied by the Bid Security will be rejected.
         In the event of his bid being accepted subject to provisions of the sub
         clause, the said amount if so, requested by the bidder be appropriated
         towards the amount of Performance Security payable by him under the
         conditions of contract.
     ▪  If, after submitting the bid, the bidder withdraws his offer or modifies the
        same or if after acceptance of his bid, fails or neglects to furnish the
        performance security, without prejudice to any rights and powers of the
                                                                                        Page |11
     JDA here under or law, JDA shall be entitled to forfeit the full amount
     of Bid Security deposited by the bidder and may refrain the bidder to
     take part in any bid of the JDA in future for a period of 3 years.
▪    In the event of bid being not accepted, the amount of Bid Security
     deposited by the bidder shall unless it is prior thereto to forfeit
     under provision of sub clause above, be refunded to him on
     passing of receipt thereto without any interest.
TECHNICALPROPOSAL
Under the technical proposal the CV’s of the key personnel’ sare required which
must be true and correct. The CV must indicate the work in hand and the duration
till which the person will be required to be engaged in that assignment.
The Key personnel whose CV’s will be evaluated is as per Data
Sheet.
   The bidder(s) must submit genuine CVs of the persons who are
actually working with the consultant. The Consultants should refrain from
using hired CVs or the CVs without consent. In case any such incidence,
if comes to the notice of JDA, the same shall be viewed seriously and
may involve termination of contract.
The technical proposal must include the following information but not limited
to the formats attached.
i. The composition of the proposed Team and Task Assignment to individual
     personnel.
ii. Curriculum Vitae (CV) recently signed by the proposed key
     professional staff and also by an authorized official of the Bidder.
     Each page of the CV must be signed. The key information shall be as
     per the format. Un signed and photo copies or scanned copy of CVs shall
     be rejected.
iii. Proposed work program and methodology for the execution of the
                                                                             Page |12
         services illustrated with bar charts of activities, equipment and
         procedure, any change proposed in the methodology of services
         indicated in the Scope of Work, and procedure for quality assurance.
    iv. Estimates of the total time effort (person x months) to be provided for
         the services, supported by bar diagrams showing the time proposed
         (person x months) for each Key Professional Staff.
    v. The technical proposal must not include any financial information.
    vi. JDA will carry out the evaluation by applying point system. Each
         responsive proposal will be attributed technical score.
    vii. The minimum essential requirement in respect of qualification in technical proposal
         has been indicated in the Data Sheet, if the consultant does not fit
         in the criteria, evaluation of his financial proposal will not be done.
▪ FINANCIALPROPOSAL
    The financial proposal shall take into account all type of the tax
    liabilities including cost of insurance specified in the Data Sheet, but
    excluding Goods & Service Tax (GST) will be reimbursed by JDA, at
    the prevailing rate.
    The payments shall be made in Indian Rupees only, by the JABALPUR Development
    Authority on presentation of bills after due verification
                                                                                         Page |13
4. AMENDMENTS TO DOCUMENTS
    Definitions
     In the document, the following words and expressions shall have the
 meaning hereby assigned to them except where the context otherwise requires:
                                                                                 Page |14
 5. ELIGIBILITY CRITERIA
     Bidder should be a well-established consultant/ consultancy firm/company
 having at least 10 years’ experience in the field of project management
 consultancy work (PMC) for infrastructure Development (road, Drinking water,
 sewerage, Drainage and electrification etc)projects in India for a Government/
 Semi Government/Autonomous dept.
 (Self-Attested certificate of experience along with certificate of establishment
 must be enclosed)
  The bidder should have experience of providing project management
consultancy/SQC/Authority Engineer for execution of successfully completed road,
Drinking water, sewerage, Drainage and electrification etc PROJECTS in India
for any State Govt., Central Govt. Corporation, Development authorities and
other Govt./Semi Govt. Organization, in the same name and capacity in last
10years as below:
     (a) The Bidder has completed single work costing equal to 50% of the
        cost of the work put to the tender (including all or individual projects);
                                                          OR
     (b) The Bidder has completed two works costing equal to 30% of the
       cost of the work put to the tender (including all or individual projects);
                                                          OR
     (c) The Bidder has completed three works costing equal to 20% of the
        cost of the work put to the tender (including all or individual projects);
(Certificate from principal employer must be enclosed with the application form).
   Bidder should have an annual average turnover of at least 1000 lakh in last three
   financial years.
   ▪ Bidders should have Employees Provident Fund, GST, and PAN Registration.
   ▪ The bidder would be required to have valid registration at the time of
        signing of the Contract.
   ▪ No Joint Venture is allowed for this project.
Note:-
       1- The experience shoulders on date of publication of this NIT.
       2- Certificate issued by Principal Employer or his authorized person
           not below the rank, of Executive Engineer should be submitted.
       3- The bidders are requested to enclose only requisite and relevant
           data which has been asked for. Attachment of irrelevant data
           shall attract to disqualify the bid.
       4- Enhancement factor as per clause3.2will be applicable.
           a) The statement of turnover shall be supported by a certificate
              from a Chartered Accountant.
         b) The financial year means year starting from 1st April to 31 st March of next year.
         c) If the certificates issued by employer are for inclusive values, then a
            certificate From CA for its bifurcate on in to base value and taxes separately, should
            submitted.
        ▪ The Bidder should not have been blacklisted/ debarred/ in
            negative     list  by     any     of the    government     department/semi-
            government department or local self-government during last 5
            years. Provide self-declaration on stamp paper duly notarized.
                                                                                         Page |15
     ENHANCEMENT FACTOR: Following enhancement factors will be used for the
     cost of works executed and the financial figures bring to a common base
     for the value of works completed in India.
                              Year           Multi plying Factor
                              2024-25        1.10
                              2023-24        1.21
                              2022-23        1.33
                              2021-22        1.46
                              2020-21        1.60
       6. Evaluation Criteria
     a) The evaluation of Technical Proposal will be taken up if the bidder
         meets the minimum Eligibility Criteria as mentioned in this document.
     b) The bid will be examined by a Committee Constituted by JABALPUR
        Development Authority JABALPUR. The bid shall be evaluated based on
        the following parameters.
         The bidder will be awarded marks for each of the parameter on the following criteria.
S.No.      Description                                                                         Marks
a.         Relevant Experience of the Bidder related to the assignment                         40
b.         Methodology Adopted for executed and proposed project.                              20
c.         Evaluation & Marking for Key Personnel’s for PMC                                      40
TOTAL                                                                                            100
   a. Sub criteria for relevant Experience of the Bidder related to the assignment
                                                                                               Page |16
                C- Adequacy of the proposed work plan and methodology                               in
                    response to the TOR.
S.No.      Description                                                                                    Marks
1.         Project management methodology adopted for the project executed in the past                    10
2.         Project management methodology to be adopted for the proposed project                          10
           TOTALMARKS (b)                                                                                 20
                Evaluation & Marking for Key Personnel’s for PMC areas under.
                                                                                         Number     Marks Of
                   Staff                                                                                          Total
S.NO.                            Description                                              of post   each person   Marks
                   Position
1.                 Team     lead Essential qualification B.E./ B.Techin civil engineering  1
                                                                                                    4             4
                   cum Reside with15years’Experience. 5marks
                   Engineer
                                 Post-graduation in Construction Management. 1
                                                                                                    1             1
                                  marks
                                  Experience as Team Leader for
                                  INFRASTRUCTURE DEVELOPMENT work.
                                  Minimum10years–2mark                                              4             4
                                  Add 0.5 marks extra for each additional 1
                                  year experience subject to maximum 2 marks
TOTALC1=                                                                                                          9
                                  Essential  Qualification B.E./ B.Tech in civil           2
                                                                                                    1.5           3
                                  Engineering with 7 years’ Experience. 2 mark
                  Assistant
2.                Resident        Experience    as ARE ( Assistant       Resident
                  Engineer        Engineer or above post) in INFRASTRUCTURE                         1             2
                                  DEVELOPMENT work Minimum 5years–1 mark
TOTALC2= 5
                                                                                                    Page |17
Note:
           1. Proof of Educational Qualification & experience to be submitted for key personnel.
           2. The technical proposal should score at least 70marks to be considered
                responsive for financial evaluation.
           3.    The weight age given to technical proposal is 70%.
           4.    The weight age given to financial proposal is 30%.
           5.    C.V. Personnel’s were presented at the time of selection for PMC
                 consultancy services should not be change at least 6 month from the
                 date of work order ,until unless the department did not find him
                 appropriate for the work
LITIGATIONHI STORY
   The Bidder should provide accurate       information on any litigation or arbitration resulting
   from contracts completed or under        its execution over the last five (5) yearsa consistent
   histories of litigations against the     bidder or any member of the Consortium may
   result in failure of the bid at the     desertion of JDA, JABALPUR.
                                                                                           Page |18
  9- SCOPE OF SERVICES FOR PROJECT MANAGEMENT CONSULTANCY (PMC)
The scope of PMC shall include but not necessarily be limited to the following:
1.    To assist JDA in contract administration and management of the project
       including supervision & quality check (SQC).
2.    Act as “Engineer In-charge” along with the JDA for the purpose of works contract.
3.    Interpretation of the technical specification & contract documents.
4.    Along with JDA scrutinize the contractor’s detailed work programme for execution
       of work, traffic diversion plan, material sources, manpower/machinery deployment
       plans proposed by the contractor for caring out the works & suggest
       modification if any.
5.    Initiate advance actions for handing over of site&/or issue of drawings, & /or
       advice to the JDA.
6.    Along with JDA scrutinize the detailed drawings for the work be for execution.
7.    To issue on behalf of JDA (with their permission), notes, damage claims of
       interest, penalty etc. whenever applicable to the contractor for contract
       administration.
8.    At various stages of work and during execution of work full check will
       be exercised by PMC consultants & to ensure correctness as per
       approved drawings &specification.
9.
           a.   At various stages of work, consultant will take samples and
                conduct tests as per provision of IRC, MORTH, IS code, MP
                PWD SOR etc. Consultant will be responsible for Quality
                Assurance. Consultant shall supervise non destructive tests if
                suggested by JDA to be performed by contractor. Report all the
                results and recommendations to JDA if required.
           b.   Frequency of the testing needed to be conducted in NABL/GOVT.
                approved laboratory PMC has to be there with competent
                representative.
           c.   The test conducted out of city for approval of material or
                material testing then the PMC has to be there with competent
                representative.
29.   Before the issuance of the completion certificate, a mandatory walk down of
      the complete facility on micro level checking with contractors authorized
      representative and JDA officials.
30. Any items which are going to execute according to approved make list, it
      must be approved by the Executive Engineer of JDA.
31. With mutual concern, any work outside the plot boundary of the project shall
      be carried out on the sanctioned rate.
32. All expenses regarding fee for obtaining Green Building certification, shall be
      borne by JDA. On written permission from Executive Engineer PMC has to
      travel in this regards to the same, JDA shall borne all expense including
      travelling, lodging and boarding etc. on actual basis.
33. Test reports, Safety audit reports during the construction phase shall be
      submitted monthly along the bill to JDA.
34. The consultant       has to liaison or coordination to obtain all necessary NOC & approval
      required for the execution of project. Necessary Fees payable to Govt. Deptt,
      Municipal Corporation etc. for required NOC and approval shall be paid by
      JDA.
35. The PMC consultant will be responsible for quality and workmanship and also
      for incorrectness of measurements and bills proposed, submitted for payment.
36. The Executive Engineer or their representative shall monitor the progress and
      as and when required. The PMC shall have to attend the meeting organized
      by the Executive Engineer as and when required and shall have to prepared
      agenda note & minutes of meeting for approvals of Executive Engineer.
37. The Executive Engineer may instruct PMC for the works assigned to PMC.
38. Services of PMC will started from commencement date of work Order of contractor.
39. The consultant shall be wholly responsible for the successful completion of the
      project in all respects consistent with safety and structural stability from the
      inception up to the handing over for occupation to the employer.
40. Any other services connected with the works usually and normally rendered by
      the Consultant, but not referred to herein above.
41. The PMC shall have to supervise as per ground conditions with reference to
      the existing contour levels given by the architect required for the site conditions.
42. Woking design and drawings submitted by the contractor or DPR consultant
      must be reviewed by the structural engineer of the PMC and submitted to the
      office of the JDA for issuance with signature of structural engineer. PMC has
      the sole responsibility to verify the designs &drawings.
43. PMC should be established a site office, equipped with a computer, printer,
      internet and a computer operator to maintain documents and fulfill other
      requirements.
44. The Consultant shall in project interest shall supervise the work day and night
      if required a duty chart should be made to supervise the work on weekly off
      days.
Project Facility:
 1)   The Consultant shall rent or purchase an office space of a minimum of 600
      square feet, which approved by the SE/EE of JDA. Failure to establish the
      office space shall attract a penalty of Rs. 10,000 per month.
                                                                                    Page |21
2)    The Consultant shall engage below mentioned vehicle which for supervision of
      work and any other work relating  to the project:
          01 No Innova Penalty               30,000/-
           01 No Bolero     Penalty          25,000/-
          01 Swift Dezire   Penalty          20,000/-
Recording of Measurements: -
1.   All record and running measurements of the works shall have to be entered
     by the bill engineer of the PMC in Measurement Books will be issued &
     certified by the Executive Engineer, JDA.
2.   All measurement of all items of works will be recorded in the Measurement Book as per
     provisions and rules.
3.   All measurement of hidden items of works will be recorded by the Billing cum
     Material Engineer in the Measurement Book as per provision and rules.
4.   Following percent checks on measurement shall be done by the team members
     of the PMC :
     By Team Leader/RE                          50%
     By ARE                                     100%
5. At least 25% of the measurement shall be check by Assistant Engineer & 50% By Sub
   Engineer and 5% Executive Engineer of JDA.
6. However overall responsibility of correctness of all the measurements shall be of the PMC.
     In the interest of work if any intermittent bill is required, shall be decided by
     Executive Engineer JDA on request by PMC.
      Any type of measurement and financial irregularities in work and payment to the
     contractor if found during agreement period or after agreement period, the PMC
     will be solely responsible for such irregularities.
     JDA have all rights to review, re-measure, and verify the                work at any time.
     The PMC will have to corporate in this process.
     In case of any discrepancy the decision of the Superintending Engineer/Executive
     Engineer of JDA will be final and binding to all concerned.
   10- PAYMENT TO CONSULTANT
       The JDA shall pay the consultant for services as per agreement.
  11- TIMEPERIOD FOR SERVICES
      Time period shall be as per data sheet.
  12- MINIMUMM ANPOWERD EPLOYMENT FOR PROJECT MANAGEMENT
      Category-wise minimum manpower to be deployed for Supervision Period
      are given in relevant clause.
 12.1 Implementation Schedule:
        The implementation schedule(indicative only)for the work shall be as follows:
            Activity description              Estimated time in Months
             Post Tender Activity              30Months(excluding rainy season)+3     month
                                                             post completion
 15 B.DURINGDLPPERIOD,THECONSULTANTWILLDEPLOYFOLLOWINGSTAFFFOR DLP.
Team Leader/ Resident Engineer who shall visit once in six month.
2-Assistant Resident Engineer who shall visit once in three months.
                                                                                             Page |23
  16     Terms Of Reference
2.9.   The consultants shall not have any objection to JDA in maintaining any
       engineering staff atits cost at the site of works to carryout works and
       duties allotted to them by the JDA in respect of works.
2.10.
    a. The consultants shall certify that the work measured, are fully consistent
       with the type, quality and specifications prescribed in the agreement with
       the contractors.
    b. Inthematterof     approvingsuchmeasurements,theconsultantsshallconfirmtotherulesand
       instructions issued to guarantee the correctness, scrutinized, checked or
       issued by them, as to quality control of the work concerned.
    c. If any mistake or mismatching with BOQ/Items has been observed then
       immediately contact the design consultant and get it rectified and then only
       proceed to execute the work.
2.11.
    a. The     consultants   would   be     responsible   for    checking   the   materials,
       workmanship and soundness of the structures keeping in view Quality
       Assurance checks and safety standards.
    b. Consultants shall submit monthly progress recommendations in regard to the
       extra items with supporting site records and also supervise field’s tests on
       materials, structures etc., and in accordance with predetermined schedules.
    c. The consultants shall also maintain adequate records of the work done,
       including recommendations of extension applications, extra items, variation
       statements, Quality and Quantity checks for all items etc.
    d. The consultants should also hold periodic review meeting with JDA and
       contractors and co-ordinate follow up actions.
    e. The consultant should maintain staff attendance register at site and shall
       be made available for inspection when requested by JDA.
    f. The consultant shall exercise complete day to day supervision during
       construction period of the assigned work, ensuring quality control in
       accordance     with   tender   stipulations,  specifications,  drawing   and   site
       conditions.
    g. The quality control will be exercised at all stages of construction, viz.
       approval of materials thereof in proper proportion including prescribing
       norms for test periodically and acceptability criteria and workmanship at all
       stages of execution of individual items of work.
                                                                                  Page |25
     h. The Consultant shall perform all the requisite tests on ingredients of
          materials periodically.
     i. The consultants shall ensure proper establishment of field laboratories by
          contractor to conduct laboratory test on materials for construction.
     j. Essential gauges, instruments etc. should be arranged to be calibrated
          periodically. The consultant shall maintain necessary site records & obtain
          data in support of the same.
     k. The consultant shall ensure all requisite tests on materials of constructions
          as well as partially or completely erected structures etc. are carried out
          by contractor and maintain adequate records thereof.
2.12. The consultant shall suggest to JDA modifications, if any, due to site
          conditions and advising regarding cost variation, on account of extra items
          and excesses on the contract.
2.13. The consultant shall advise the JDA with regard to extra claim / dispute,
          if any, till the cases are settled. The consultant will also be required to
          brief the legal adviser / legal consultant of the JDA on cases pertaining
          to the work.
2.14. The consultant has to coordinate with the concern architect & other
          relevant design agency for obtaining decision in time.
2.15. The consultant hasto witness thethird partyteststo beconductedin cityof
          worksite or any other city in the country.
2.16. During bill checking and bill payment procedure of JDA, if any
          objection/clarification raised by the JDA office/pre audit section the
          consultant has clarified all the objection.
2.17. If any mish appending/ accident/incident etc. Happened on work project, the
          consultant have to take necessary action and make F.I.R. if needed.
          Consultants have to submit action report to the JDA.
2.18. Theconsultantwillsubmitcopiesofallcorrespondencemadewithcontractor& other
          department immediately and in compile form spiral binding file monthly.
2.19.
    a. JDA may conduct independent quality monitoring and checking or by JDA
          Engineers at random, of works carried or/and recommended for payment
          by the consultant.
    b. If such checks disclosed that works certified or/and recommended for
          payment by the consultant do not meet the specified requirement. JDA
          will not pay the consultant fee of the affected portion which shall be
          calculated @2.5% of the value of such work.
 1.1. Before the issuance of the completion certificate, a mandatory walk
        down of the complete facility on micro level checking with contractors
        authorized representative and JDA officials.
 1.2. Any items which are going to execute according to approved make
        list, it must be approved by the Executive Engineer of JDA.
 1.3. Any type of measurement and financial irregularities in work and
        payment to the contractor if found during agreement period or after
        agreement period, the PMC will be solely responsible for such
        irregularities.
 1.4. If, any reduction in the scope of work, then payment shall be made accordingly.
 1.5. JDA will have full right tore-measure the work at anytime.
                                                                                      Page |26
 3.0       TIMEPERIOD FOR SERVICES
            Time period for PMC will be 30, Months (excluding rainy season) + 3 months post completion
            The consultant will indemnify JDA for any direct loss or damage, which occur due to deficiency in
            services. Penalty may be imposed on the consultants for poor performance/deficiency in services
            as expected from the consultant as per below.
S.NO.      ACTIVITIES                           PENALTY
                                                                                                    Page |27
                                                    APPENDIX–A
1. FACILITIESANDSERVICESOFOTHERSTOBEPROVIDEDBYJDA
1.2. ACCESSTOLAND
       JDA    warrant      that    the     Consultants       shall   have,     free    of    charge      unimpeded
access to all and of the Government’s/ JDA in respect of which accessis required for the
performance of the services. JDA will be responsible for any damage to such land
or   any     property     there on resulting         from    such      access        and    will   indemnify      the
Consultants     and      each     of     the    Personnel      in    respect    of    liability    for   any     such
damage     unless       such    damage         is   caused    by     the   default     or   negligence      of    the
Consultants or any Sub Consultant or the Personnel of either of them.
                                                                                                                 Page |28
                                           APPENDIX–B
 REPORTINGREQUIREMENTS
   1. REPORTS
1.1. ASBUILTDRAWINGS
                              GENERALCONDITIONSOFCONTRACTDEFINITI
                              ONSANDINTERPRETATION
 1.DEFINITIONS
 The following words and expressions shall have the meanings assigned to them
 except where the context otherwise requires:
 I    The      ‘PROJECT         MANAGEMENT          CONSULTANCY          FOR
 INFRASTRUCTURAL DEVELOPMENT WORKS FOR Scheme No 64 and
 65 &TDS-02 (PHASE-II) OF JDA, AT JABALPUR.
iv. The“Chief Engineer” shall mean the officer of JDA who is designatedas such for the time
    being in whose jurisdiction the work lies.
vi. The “Executive Engineer” shall mean the officer of JDA who is designatedassuch for the
    time being in whose jurisdiction the work lies and also called project
    Engineer of JDA.
vii. A “Day” shall mean a day of 24 hours from midnight to mid night irrespective
     of number of hours worked in that day.
viii. A “Week” shall mean 7 consecutive days without regard to the number of
      hours worked in any day in that week.
    Month and Year and all dates shall be as per the Gregorian calendar. The time referred to shall be
                 Indian Standard Time.
ix. The “Site” shall mean the lands and/ or other places, on under, in or
    through which the work is to be executed under the contract including any
    other lands or places which may be allotted by the Department or used
    for the purpose of contract work.
                                                                                          Page |29
 x.   “Urgent    Works” shall mean any measures, which in the opinion of
      Engineer   becomes necessary during the progress of the work to obviate
      any risk   or accident or failure or which becomes necessary for security of
      the work   or the persons working thereon.
xii. The “Engineer” means The Team Leader of PMC or any authorized person.
2. INTERPRETATION
2.1. The headings in the Agreement shall not be used in its interpretation.
      2.2. The singular includes the plural; the masculine includes the feminine, advice-
           versa where the context requires.
OBLIGATIONSOFJDA
3. INFORMATION
4. DECISIONS
5. ASSISTANCE
           JDA shall provide support to the consultant if sought in the following matter
      5.1. The provision of documents necessary for entry ,residence, work and exit;
      5.2. Providing unobstructed access where verities required for the Services;
      5.3. Providing access to other organizations for collection of
           information, which is to be obtained by the Consultant?
6. SERVICESOFOTHERS
         The JDA shall at his cost arrange for the provision of services from
         others as described in Appendix – A and the Consultant shall co-operate
         with the suppliers of such services but shall not be responsible for them
         or their performance.
                                                                                            Page |30
7. PERSONNEL
     The Consultant shall employ and depute qualified personnel for the work
     as per the name and qualification given in the Technical Proposal.
8. REPRESENTATIVES
      The Consultant shall depute a senior officer capable of taking decisions
      and represent the consultant with the JDA. Such person so deputed shall
      not be changed without the consent of the JDA.
9. CHANGESIN PERSONNEL
   9.1. RELATIONBETWEENTHEPARTIES
      Nothing contained herein shall be construed as establishing a relation of
      master and servant or of agent and principal as between JDA and the
      Consultants. The Consultants, subject to this contract, have complete
      charge of Personnel performing the services and shall be fully responsible
      for the Services performed by them or on their behalf here under.
   9.2. REMOVALAND/ORREPLACEMENTOFPERSONNEL
      9.2.1. Except as JDA may otherwise agree in writing at the request of
           the consultant on reasonable ground to its satisfaction, no change
           shall be made in the key Personnel. However, it becomes necessary
           to replace any of the Personnel; the Consultants shall forthwith
           provide as a replacement a person of equivalent or better
           qualifications.
      9.2.2. If JDA
           (i) finds that any of the Personnel has committed serious misconduct
           or has been charged with having committed a criminal action; or
           (ii) has reasonable cause to be dissatisfied with the Performance of
           any of the Personnel, then the Consultants shall at the JDA’s written
           notice     specifying the grounds    thereof, forthwith provide as are
           placement a person with qualifications and experience acceptable to
           the JDA.
     9.2.3 if due to unforeseen reason the consultant agency required to
           change the deployed person it may be allowed with the one-time
           penalty as below:
          Team Leader                       25000/-
          Assistant Resident engineer       15000/-
          Field Engineer                    10,000/-
          Computer operator                 5000/-
10. INDEMNITY
   10.1.        The Consultant agrees to indemnify and hold harmless JDA from and against
       any and all claims, actions proceedings, lawsuits, demands, losses,
       liabilities, damages, fines or expenses (including interest, penalties,
       attorneys’ fees and other costs of defense or investigation.
         a. Related to or arising out of, whether directly or indirectly;
         b. The breach by the Consultant of any obligations;
         c. The alleged negligent, reckless or otherwise wrongful act or
         omission  of  the    Consultant  including professional   negligence or
         misconduct of any nature whatsoever in relation to Services rendered
         to the JDA;
                                                                                     Page |31
   10.2.       As soon as reasonably practicable after the receipt by JDA of a
       notice of the commencement of any action by a third party, JDA will
       notify the Consultant of the commencement thereof; provided, however,
       that the omission so to notify shall not relieve the Consultant from any
       liability which it may have to the JDA or the third party. The
       obligations to indemnify and hold harmless, or to contribute, with respect
       to losses, claims, actions, damages and liabilities relating to the
       Indemnified Matter shall survive till all claims for indemnification and/or
       contribution asserted shall survive and until their final resolution thereof.
   10.3.    The fore going provision sare in addition to any rights which the JDA may have
       at common law, in equity or otherwise.
11. AGREEMENTEFFECTIVE
       This Contract shall come into force and effect on the         date (the “Effective
Date”) notice to proceed with the work to the contactor of           the work issued by
JDA and instructing the Consultants to begin carrying out           the Services. This
notice shall confirm that the effectiveness conditions, if          any, listed in the
Contract have been met.
12. COMMENCEMENTANDCOMPLETION
   12.1. The service shall be commenced from the date when the Consultant actually
         commence the work as may be notified to the JDA; and shall be
         provided till completion of project or on such date as may be
         extended by the JDA in writing.
  12.2. The services of consultants shall be available till the completion
        schedule date of the project or till the completion of Defect liability
        period or in case of claims/ court cases, if the services of the
        consultant are required then the fees will be decided on mutual
        consent, however in any case the same shall not be more than
        proportionate fees payable under this contract.
  12.3. The consultant will maintain the record of work till Completion of the
        defect liability period and or till the claims and court matters pertaining
        to the work are settled, whichever is later.
  12.4. The consultant will also submit the certificate regarding Satisfactory
        complete of the work before the final bill is paid from in charge
        officer of the JDA.
13. VARIATIONS
      The Agreement can be varied on application by either party by written
agreement of the parties.
14. FURTHERPROPOSALS
        JDA shall have the right to request in writing for changes, additions,
modifications or deletions in any part of the scope of work and to request in writing
additional work in connection and the consultant shall comply with such request.
The preparation and submission of such proposals shall be an Additional
Service & will be paid separately with mutual consent of both the parties.
                                                                                      Page |32
15. EXTENSIONOFTIME
        In case of delay in completion of the work for the reason not
attributable to the Consultant, the JDA may consider grant of extension of
services of the Consultant on its sole discretion, The Consultant shall be paid
fees as specified below.
    15.1.      After 24months from the date of commencement 10% extra of
               approved rates will be given for the balance works till completion of
               works + Goods & Service Tax.
    15.2.      PMC will be responsible for all the works till DLP.
    15.3.      Fee is inclusive of all taxes but exclusive of Goods & Service Tax.
    15.4.      Goods & Service Tax will be paid separately as per rules and regulation.
     15.5.    TheChallanofGoods&ServiceTaxshallbesubmittedforlastpaymentspriorto
              current bill.
16. SUSPENSIONANDPAYMENTSDURINGSUSPENSIONPERIODOFPMCWORK
     16.1.1. JDA may, by written notice of 15 days of suspension to the
             Consultants, suspend all payments to the Consultants hereunder if the
             Consultants fail to perform any of their obligations under this
             contract, including the carrying out of the services provided that such
             notice of suspension shall specify the nature of the failure.
    16.1.2. If suspension gets continued for six months then beyond six months the
            agreement will get automatically null and void and neither of the
            party is required to give any notice for termination of work after six
            months of suspension. However if the work get revoke after six month& if
            services   from   consultant  are   required,  then   the    services for
            consultancy on mutual consent may be again resume by consultant
            on the revised fee mutually agreed upon by both the parties.
      The Consultants may, by not less than thirty (30) days written notice to
JDA, terminate this contract.
       18.1.1. If JDA fails to pay any money due to the Consultants pursuant to
               this Contract and not subject to any dispute within ninety (90) days
               after receiving written notice from the Consultants that such payment
               is overdue; If JDA is in material breach of its obligations pursuant to
               this contract and has not remedied the same within forty-five (45)
               days or longer period, the Consultants has to establish such breach
               of contract by JDA in writing following the receipt by the JDA of
               the Consultant’s notice specifying such breach;
       18.1.2. If, as result of Force Majeure, the Consultant sareunable to performa material
               portion of the Service for a period of not less than six (6)months.
       18.1.3. If JDA fail stocomply with any final decisionreachedasa result of arbitration
               pursuant to relevant Clause of agreement.
 19.      Expiration of Contract
      This Contract shall expire when services have been completed and all
payments have been made at the end of such time after the Effective Date
as shall be specified in the Contract.
21. MODIFICATION
                                                                                            Page |34
22. CESSATIONOFRIGHTSANDOBLIGATIONS
26. PAYMENTTOTHECONSULTANT
      The bidder shall submit a percentage rate inclusive of all overhead
      expenses. Fee is inclusive of all taxes but exclusive of Goods & Service
      Tax. Goods & Service Tax will be paid separately as per rules and
      regulation of State. The Challan of Goods & Service Tax shall be
      submitted for last payments prior to current bill.
      The payments to the consultant shall be made in stages as mentioned in the RFP document.
    26.2.      PAYMENTFOREXTRADEPLOYMENTOFMANPOWER
       In case SE/EE (JDA) require any additional manpower for other works of
       Authority or in the same project (in addition to the manpower mentioned
       in the PMC) i.e. technical, managerial, or technician, the consultant has
       to deploy the needed the resources on this project as per the needs.
       The payment for the extra manpower shall be paid to the consultant as
       follows:
                                                                             Page |35
        26.2.1. Team Leader/ Resident Engineer (BE /B.Tech. Civil, with 15 years’
                experience ) =Rs.60,000permonth+GST
        26.2.2. AssistanceResidentEngineer(BE/B.Tech.Civil,with7years’experience) =
                Rs.40,000 per month+GST
        26.2.3. Filed Engineer (BE or B.Tech./Diploma in CivilEngineering,          with 3/5
                years’ experience= Rs. 30,000 per month + GST
        26.2.4. Billing Engineer/Material Engineer (BE or B.Tech./Diploma in Civil
                Engineering, with 3/5 years’ experience) = Rs. 30,000 per month +
                GST
        26.2.5. Computer Operator (10+2pass,having experience of office assistant for 2years
                with computer typing experience) = Rs. 15,000 + GST
        Note:
28. ASSIGNMENTANDSUB-CONTRACTS
   28.1. The Consultant shall not without the written consent of the JDA assign
         the benefits from the Agreement other than money.
   28.3. The Consultant shall not without the written consent of the JDA initiate
         or terminate any sub-contract for performance of all or part of the
         Services.
29. COPYRIGHT
       Documents prepared by the Consultants to be the Property of the JDA.
       All plans, drawing, specifications, designs, report and other documents
       prepared by the Consultants in performing the Services shall become and
       remain the properly of the JDAs, and the consultants shall not later
       than15 days upon termination or expiration of this Contract, deliver all
       such documents to the JDA, together with detailed inventory thereof. The
       Consultants may retain a copy of such documents. JDA is free to use
       the above documents for other project of the JDAs.
                                                                                            Page |36
30. CONFLICTOFINTEREST/CORRUPTIONAND FRAUD
    1. CONSULTANTSNOTTOBENEFITFROMCOMMISSIONS,DISCOUNTS, ETC.
       The   remuneration     of   the   Consultants    hereof     shall constitute the
Consultants’ sole remuneration in connection with this Contract or the Services
and thereof, the Consultants shall not accept for their own benefit any trade
commission, discounter similar payment in connection with activities pursuant to this
Contract or to the Services or in the discharge of their obligations here under,
and the Consultants shall use their best efforts to ensure that any Sub-consultants
as well as the Personnel and agents of either of them, similarly shall not
receive any such additional remuneration.
   2. CONSULTANTSANDAFFILIATESNOTTOENGAGEINCERTAIN ACTIVITIES
       The Consultants agree that, during the term of this Contract and after
its termination, the Consultants and any entity affiliated with the Consultants, as
well as any Sub-consultant and any entity affiliated with such Sub-consultant,
shall be disqualified from providing goods, works or services (other than the
Services and any continuation thereof) for any project resulting from or closely
related to the Services.
    3. PROHIBITIONOFCONFLICTINGACTIVITIES
       The Consultants shall not engage, and shall cause their Personnel as
well as their Sub- consultants and their Personnel not to engage, either directly
or indirectly, in any of the following activities:
31. CONFIDENTIALITY
    32. INSURANCETOBETAKENOUTBYTHECONSULTANTS
        The Consultants (i) shall take out and maintain, and shall cause any
Sub-consultants to take out and maintain, at their (or the Sub-consultants’, as
the case may be) own cost but on terms and conditions approved by the
Employer, insurance against the risks, and for the coverage, as shall be
specified in the Contract, and (ii) at the Employer’s request, shall provide
evidence to the Employer showing that such insurance has been taken out and
maintained and that the current premiums therefore have been paid.
                                                                                   Page |37
   33. ACCOUNTING,INSPECTIONANDAUDITING
       The Consultants (i) shall keep accurate and systematic accounts and
records   in   respect    of    the Services, hereunder, in accordance with internationally
accepted accounting principles and in such form and detail as will clearly identify all
relevant time charges and cost, and the bases thereof (including such bases as
may be specifically referred in the Contract); (ii) shall permit the Employer or its
designated representative periodically, and up to ne year from the expiration or termination
of this Contract, to inspect the same and make copies thereof as well as to
have them audited by auditors appointed by the Employer.
34. CONSULTANTSACTIONSREQUIRINGEMPLOYER’SPRIORAPPROVAL
      The following shall obtain the Employer’s approval in writing before taking
any of the following actions:
35. REPORTINGOBLIGATIONS
        The Consultants shall submit to the Employer the reports and documents
specified in contract, in the form, in the numbers and within the time set forth
in the contract. It should be submitted in the form of PDF & excel as well.
   36. DOCUMENTSPREPAREDBYTHECONSULTANTSTOBETHEPROPERTYOFTHE
       EMPLOYER
                                                                                        Page |38
   37. CONSULTANTS’PERSONNELANDSUB-CONSULTANTS37.1.GENERAL
        The Consultants shall employ and provide such qualified and experienced
Personnel and Sub-consultants as are required to carry out the Services as
specified in Tender Document.
DESCRIPTIONOFPERSONNEL
      (i)    That such adjustments shall not alter the originally estimated of
             engagement of any individual by more than 10% or one week,
             whichever is larger, and
      (ii)   That the aggregate of such adjustments shall not cause payments
             under this Contract to exceed the ceilings set forth of this Contract.
             Any other such adjustments shall not be made without the
             Employer’s written approval.
APPROVALOFPERSONNEL
                                                                               Page |39
   38. OBLIGATIONSOFTHEEMPLOYER
38.1ASSISTANCEANDEXEMPTIONS
      Unless otherwise specified in the Contract,           the   Employer   shall   use    its
best efforts to ensure that the JDA shall:
   b) Assist for the Personnel and, if   appropriate, their eligible dependent stobe provided
      promptly with all necessary        entry documents required for their stay in
      India.
       If, after the date of this Contract, there is any change in the Applicable
Law with respect to taxes and duties which increase or decreases the cost or
reimbursable expenses incurred by the Consultants in performing the Services,
then the remuneration and reimbursable expenses otherwise payable to the
Consultants under this Contract shall be increased or decreased accordingly by
agreement between the Parties hereto, and corresponding adjustments shall be
made to the ceiling amounts specified in Contract.
                                                                                           Page |40
   40. SERVICES, FACILITIES AND PROPERTY OF THE EMPLOYER
       The Employer shall make available to the Consultants and the Personnel,
for the purposes of the services and free of any charge, the services, facilities
and property described in contract at the times and in the manner specified in
contract, provided that if such services, facilities and property shall not be
made available to the Consultants as and when so specified, the Parties shall
agree on (i) any time extension that it may be appropriate to grant to the
Consultants for the performance of the Services,(ii) the manner in which the
Consultants shall procure any such services, facilities and property from other
sources, and (iii)the additional payments, if any, to be made to the Consultants
as a result thereof pursuant to Contract hereinafter.
41. COUNTERPARTPERSONNEL
   42. FAIRNESSANDGOODFAITH
        42.1 GOODFAITH
        The Parties under take to act in good faith with respect to each other’s rights under this
Contract and to adopt all reasonable measures to ensure the realization of the
objectives of this Contract.
    43. OPERATIONOFTHECONTRACT
        The Parties recognize that it is impractical in this Contract to provide for
every contingency which may arise during the life of the Contract, and the
Parties hereby agree that it is their intention that this Contract shall operate fairly
as between them, and without detriment to the interest of either of them, and that,
if during the term of this Contract either Party believes that this Contract is
operating unfairly, the Parties will use their best efforts to agree on such
action as may be necessary to remove the cause or causes of such unfairness,
but no failure to agree on any action pursuant to this Clause shall give rise
to dispute subject to arbitration in accordance with contract.
   44. CONFLICTOFINTEREST/CORRUPTIONANDFRAUD
       Not with standing any penalties that may be enforced against the
Consultant under the law of the country of the project, or of other jurisdictions,
JDA will be entitled to terminate the Agreement) and the Consultant shall be
                                                                                             Page |41
deemed to have breached the contract, if it is shown that the Consultant is
guilty of:
    i. offering, giving, receiving or soliciting anything of value with a view to
       influencing the behavior or action of anyone, whether a public official or
       otherwise, directly or indirectly in the selection process or in the conduct
       of the Agreement; or
DEBARRINGTHECONSULTANT
In case the Consultant fails to perform to the satisfaction of JDA or fails to
deliver the results as envisaged in the assignment or delay the grant of
approval, sanction, permission, instruction for execution of the work to any
agency or contractor which results in delay in completion of the project or fails
to inform and bring to notice of the JDA any incidence, action, deed or cause
which may delay the completion of the project within 15 days of occurrence of
such event or fails to supervise the quality of work of CONSTRUCTION OF
INFRASTRUCTURAL DEVELOPMENT WORKS FOR Scheme No. 64 & 65 and
TDS-02 ( Phase-II) OF JDA, AT JABALPUR.
    45. .the JDA not withstanding any other action including forfeiture of
        performance security, may debar the consultant to take part in any work
        of the JDA in future for a period not exceeding 3 years.
    46. NOTICES
        Any notice, request or consent required or permitted to be given or
made pursuant to this Contract shall be in writing & by e-mail. Any such
notice, request or consent shall be deemed to have been given or made when
delivered in person to an authorized representative of the Party to whom the
communication is addressed, or when sent by registered mail, or facsimile to
such Party at the address specified in the Contract.
  Notice will be deemed to be effective as specified in the Contract.
        A Party may change its address for notice here under by giving the other Party
notice of such change pursuant to the provisions listed in the Contract.
    47. LOCATION
   48. AUTHORIZEDREPRESENTATIVES
       Any action required or permitted to be taken, and any document required
or permitted to be executed, under this Contract by the Employer or the
Consultants may be taken or executed by the officials specified in the Contract.
                                                                                  Page |42
   49. TAXESANDDUTIES
       The Consultants and Personnel shall pay such taxes,               duties, fees and
other impositions as may be levied under the Applicable                  Law. GST paid
separately
50. SETTLEMENTOFDISPUTES
50.1. AMICABLEDISPUTERESOLUTION
       Any dispute between the Parties as to matter sari sing pursuant to this Contract
which cannot be settled amicably within thirty (30) days after receipt by one
Party of the other Party's request for such amicable settlement may be
submitted by either Party for settlement to the Superintending Engineer/Executive
Engineer, JABALPUR Development Authority, JABALPUR.
                                                                                         Page |43
              ii.    Force Majeure shall not include (a) any event, which is
                     caused by the negligence or intentional action of a Party or
                     such Party’s sub consultants or agents or employees, nor
                     (b) any event which a diligent Party could reasonably, have
                     been expected of this Contractor and [B] avoid or over come
                     in the carrying out of its obligations hereunder.
              iii.   Force Majeure shall not include insufficiency of funds or
                     failure to make any payments required hereunder.
       NOBREACHOF CONTRACT
       The failure of a Party to fulfill any of its obligations hereunder shall not
be considered to be a breach of, or default under, this contract in so far as
such inability arises from an event of Force Majeure, provided that the Party
affected by such an event has take all reasonable precautions, due care and
reasonable alternative measures, all with the objective of carrying out the terms
and conditions of this contract.
       MEASURETOBETAKEN
       EXTENSIONOFTIME
       Any period within which a Party shall, pursuant to this contract, complete any
actions of task, shall be extended for aperiod equal to the time during which such Party
was unable to perform such action as a result of Force Majeure.
        PAYMENTS
        During the period of their inability to perform the services as a result of
an event of Force Majeure, the Consultants shall be entitled to be reimbursed
for providing the services during such period as per the input provided by
them. The requirement of team of consultants during such period shall be
decided by JDA in accordance to the approved rate quoted by consultant for
individual technical personnel. The JDA shall intimate in writing to consultant for
such requirements however in case of non- requirement of consultant’s
personnel, minimum 30% of monthly fee shall be paid to consultant against
other heads and expenses of establishment. The additional costs reasonably and
necessarily incurred by consultants during such period for the purpose of the
Services and in reactivating the Services after the end of such period shall also
be paid additionally.
                                                                                Page |44
   54. LIABILITYOFCONSULTANT
The    JDA’s   Endeavour is  to           select PROJECT
                                                    a     reputed    consultant
MANAGEMENT CONSULTANCY FOR INFRASTRUCTURAL DEVELOPMENT
WORKS FOR Scheme No 64 and 65 &TDS-02 (PHASE-II) OF JDA,
AT JABALPUR.
    55. THIRDPARTYTEST
        Third party test (if any) shall be conducted separately and the cost of
all such required tests and appointment of third party shall be exclusive of
consultant’s fee and shall be borne by JDA/Contractor.
    56. REPRESENTATIONS,WARRANTIES AND DIS CLAIMER
ii. It has full power and authority to execute, deliver and perform its obligations under
        iii.   It has taken all necessary corporate and other                     action under
               Applicable Laws and its constitutional documents to                authorize the
               execution, delivery and performance ofthis Contract;
iv. It has the financial standing and capacity to under take the Project;
                                                                                            Page |45
       viii.   No representation or warranty by the Consultant contained herein
               or in any other document furnished by it to the JDA contains or will
               contain any untrue statement of material factor omits or will omit to
               state a material fact necessary to make such representation or
               warranty not misleading; and
57. MISCELLANEOUS
      ADDITIONSANDALTERATIONS
        i.  The JDA shall have the right to request in writing for changes,
            additions, modifications or deletions in any part of the scope of
            work and to request in writing additional work in connection and
            the consultant shall comply with such request.
            ii.    The consultant shall not make any deviations, alterations,
                   additions, to or omissions from the work shown / described
                   and awarded to the contractor except through and with
                   proper approval of the JDA.
      ASSIGNMENTANDCHARGES
            i.  The Contract shall not be assigned by the Consultant save
                and except with prior consent in writing of the JDA, which
                consent the JDA shall be entitled to decline without
                assigning any reason whatsoever.
                                                                                Page |46
   60. SERVICEABILITY
   ii.   Neither the failure by either Party to in sis ton any  occasion upon the
         performance of the terms, conditions and provisions of the Contract or
         any obligation here under nor time or other indulgence granted by a
         Party to the other Party shall be treated or deemed as waiver of such
         breach or acceptance or any variation or the relinquishment of any such
         right hereunder.
                                                                                Executive Engineer
                                                                    Jabalpur Development Authority
                                                                        7A, Civic Center, Marhatal,
                                                                                 Jabalpur – 482002
                                                                                            Page |48
PROJECT   MANAGEMENT  CONSULTANCY   FOR   INFRASTRUCTURAL
DEVELOPMENT WORKS FOR Scheme No 64 and 65 &TDS-02 (PHASE-II)
OF JDA, AT JABALPUR.
FINANCIAL PROPOSAL
Page |49