CHAPARMUKHFOB BRIDGE-130
column foundation for c/c 3 Staircase (1500*1500*
ITEM
SL NO DESCRIPTION BAR SHAPE C/C DISTANCE DIA OF BARS CUTTING LENGTH
WITH LAP
BOTTOM
165
LONG 165
1 1400 100 12 1.682
BARS(Raft
slab)
BOTTOM
TRANS
165
165
2 100 12 1.682
BARS( Raft 1400
slab)
150
4036
3 pedestal 20 4.406
300
350
4 pedestal strup 240 250 8 1.316
275
275
5 Tie beam 3350
20 3.82
250
Tiea beam 300
6 150 10 1.22
strup
TOTAL WT (KG)
TOTAL WT (MT)
HAPARMUKHFOB BRIDGE-130
n for c/c 3 Staircase (1500*1500*4100) PF -1
NO OF PIC1 RAFT TOTAL RAFT
TOTAL LENGTH UNIT WT(KG/MTR UNIT WT(KG) REMARKS
SLAB SLAB
30 1 50.46 0.888 44.81
30 1 89.712 0.888 79.66
12 2 105.744 2.469 261.08
34 2 89.488 0.395 35.35
8 1 30.56 2.469 75.45
23 1 28.06 0.617 17.31
(KG) 513.67
(MT) 0.514
CHAPAR MUKH FOB BRIDGE-130
MAIN FOUNDATION(14.100*6.000*0.950) M PF -01
ITEM
TOTALCUTTING NO OF PIC1 TOTAL RAFT
SL NO DESCRIPTION BAR SHAPE C/C DISTANCE DIA OF BARS LAP LENGTH CUTTING LENGTH TOTAL LENGTH UNIT WT(KG/MTR UNIT WT(KG) REMARKS
+LAP LENGTH RAFT SLAB SLAB
WITH LAP
BOTTOM LONG
174
174
1 100 12 0.672 14.3 14.972 60 2 1796.64 0.888 1595.416
BARS(Raft slab) 14000
BOTTOM TRANS
2 100 16 6.232 6.252 141 2 1763.064 1.58 2785.641
BARS( Raft slab) 190
190
5900
TOP LONG 14000
3 100 12 0.672 14.3 14.972 60 2 1796.64 0.888 1595.416
BARS(Raft slab)
174
174
5900
TOP TRANS
4 100 16 6.232 6.252 141 2 1763.064 1.58 2785.641
190
190
BARS(Raft slab)
1000
5 Chair (Raft slab) 160
200 1000 16 1.656 68 2 225.216 1.58 355.841
610
610
6 Main beam 14000
25 1.4 15.12 16.52 32 2 1057.28 3.858 4078.99
850
Shear strup(mainn
7 200 10 2.68 288 2 1543.68 0.617 952.45
430
beam)
610
610
Crass Beam 5900
25 7.02 96 2 1347.84 3.858 5199.97
850
Shear strup(Crass
200 10 2.68 384 2 2058.24 0.617 1269.93408
430
beam)
Tie beam 20 1.12 14.52 15.64 16 2 500.48 2.469 1235.68512
300
300
14000
300
strup(tie beam) 200 10 1.22 142 2 346.48 0.617 213.778
250
8 Tie beam 20 6.42 48 2 616.32 2.469 1521.694
300
300
5900
300
9 strup(tie beam) 200 10 1.22 186 2 453.84 0.617 280.019
250
150
250
150
10 Pedestal 175 25 4.382 192 2 1682.688 3.858 6491.81
4032
300
150
700
700
11 Pedestalstrups 150 10 2.92 336 2 1962.24 0.617 1210.702
100 100
12 Additional Links 700 150 8 0.852 672 2 1145.088 0.395 452.31
700
363
13 Pedestalstrups 150 8 2.246 672 2 3018.624 0.395 1192.356
TOTAL WT (KG) 33217.65
TOTAL WT (MT) 33.218
chaparmukh FOB BRIDGE-130
Combind Foundation for c/c 3.00 Staircase (6000*3000*4100) pf no 1
ITEM
NO OF PIC1 TOTAL RAFT
SL NO DESCRIPTION BAR SHAPE C/C DISTANCE DIA OF BARS CUTTING LENGTH TOTAL LENGTH UNIT WT(KG/MTR UNIT WT(KG) REMARKS
RAFT SLAB SLAB
WITH LAP
BOTTOM LONG
215
215
1 100 12 6.282 30 4 753.84 0.888 669.41
BARS(Raft slab) 5900
BOTTOM TRANS
2 100 12 3.252 60 4 780.48 0.888 693.066
BARS( Raft slab) 200
200
2900
TOP LONG 5900
3 100 12 6.282 30 4 753.84 0.888 669.41
BARS(Raft slab)
215
215
2900
TOP TRANS
4 100 12 3.252 60 4 780.48 0.888 693.066
200
200
BARS(Raft slab)
1000
5 Chair (Raft slab) 214
200 1000 16 1.732 18 4 124.704 1.58 197.032
495
495
6 Main beam 5900
16 6.826 8 4 218.432 1.58 345.123
Shear 750
7 strup(mainn 200 10 2.2 62 4 545.6 0.617 336.635
290
beam)
8 Tie beam 58 20 4.12 8 4 131.84 2.469 325.513
300
300
3600
300
9 strup(tie beam) 150 10 1.22 24 4 117.12 0.617 72.263
250
150
10 Pedestal 25 4.386 25 4 438.6 3.858 1692.119
4036
300
600
308
11 Pedestalstrups 150 8 2.152 56 4 482.048 0.395 190.409
450
217
12 Pedestalstrups 150 8 1.47 28 4 164.64 0.395 65.033
TOTAL WT (KG) 5949.079
TOTAL WT (MT) 5.949
CHAPAR MUKH FOB BRIDGE-130
MAIN FOUNDATION COLUMN TIE BEAM & PEDESTAL (1
ITEM
DIA OF LAP CUTTING
SL NO DESCRIPTION BAR SHAPE C/C DISTANCE
BARS LENGTH LENGTH
WITH LAP
150
1 Pedestal 175 25 4.382
4032
300
3332
A 25 3.582
300
2332
25 2.582
B 300
150
25 1.4 1.8
3100
BB
150
2100
25 1.4 0.8
AA
700
700
2 Pedestalstrups 150 10 2.92
100 100
3 Additional Links 700 150 8 0.852
700
363
4 Pedestalstrups 150 8 2.246
5 Tie beam 20 1.12 13.32
300
300
12800
300
6 strup(tie beam) 200 10 1.22
250
300
300
7 Tie beam 3700 20 4.22
300
250
8 strup(tie beam) 200 10 1.22
TOTAL WT (KG)
TOTAL WT (MT)
PAR MUKH FOB BRIDGE-130
UMN TIE BEAM & PEDESTAL (14.100*6.000*0.950) M PF -01
TOTALCUTTING NO OF PIC1 TOTAL RAFT TOTAL UNIT
UNIT WT(KG) REMARKS
+LAP LENGTH RAFT SLAB SLAB LENGTH WT(KG/MTR
60 1 262.92 3.858 1014.35
72 257.904 3.858 994.99
3.858
60 154.92 597.68
3.2 3.858
60 192 740.74
2.2 3.858
72 158.4 611.11
336 1 981.12 0.617 605.351
672 1 572.544 0.395 226.155
672 1 1509.312 0.395 596.178
14.44 16 1 231.04 2.469 570.43776
142 1 173.24 0.617 106.889
48 1 202.56 2.469 500.121
117 1 142.74 0.617 88.071
KG) 6652.07
MT) 6.65