0% found this document useful (0 votes)
56 views34 pages

Module-2 Cofferdam - 4

A cofferdam is a temporary structure used to create a dry work environment in water bodies for construction projects like dams and bridges. Various types of cofferdams exist, including earthfill, rockfill, and cellular, each with specific design features and construction methods tailored to the conditions of the site. Key considerations in cofferdam design include water tightness, stability against environmental forces, and prevention of leakage and piping.

Uploaded by

Ankit Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views34 pages

Module-2 Cofferdam - 4

A cofferdam is a temporary structure used to create a dry work environment in water bodies for construction projects like dams and bridges. Various types of cofferdams exist, including earthfill, rockfill, and cellular, each with specific design features and construction methods tailored to the conditions of the site. Key considerations in cofferdam design include water tightness, stability against environmental forces, and prevention of leakage and piping.

Uploaded by

Ankit Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 34

Advance construction & Equipment

Coffer Dam
Coffer dam
• Introduction
• Use of coffer dam
• Selection of type of coffer dam
• Types of cofferdam
• Design feature of cofferdam
• Leakage prevention in cofferdam
• Economic height of cofferdam
• Piping in single wall cofferdam
What is cofferdam ?
• A cofferdam is a temporary structure which is built in a river, lake etc.
to remove water from an area and make it possible to carry on the
construction work under reasonably dry conditions.
• It is required for project such as dams, docks and construction of
bridge piers and abutment.
Requirement of cofferdam
• It should be watertight.
• It should be generally constructed at site of work.
• The Design and layout of coffer dam must be economical in
construction , maintenance and pumping is minimum.
• Stable against bursting, overturning and sliding under the floods and
waves.
• Material used for construction are earth, timber, steel and concrete.
• It should be so planned as to facilitate any dismantling and reuse of
material.
Necessity of cofferdam

• Construction of a structure in river bed , sea shore, or inside lake.


• When deep excavation are carried out in a course grained soil.
• Excavation is carried out below ground water table.
• Chances of collapse of side trenches during deep excavation.
• Public/government property is situated close to the excavation.
• Chances of seepage of water in trenches form surrounding area.
Use of cofferdams

• To facilitate pile driving operation.


• To place grillage and raft foundation.
• To construction foundation of piers and abutment of bridge, dam,
locks.
• Enclose a space for the removal of sunken vessels.
• Provide a working platform for the foundation of building when water
is met with.
• To provide space for carrying out the foundation work without
disturbing or damaging the adjoining structure such as building,
sewer, pipelines.
Selection of type of cofferdams
• The area to be protected by a coffer dam
• The depth of water to dealt / execution.
• The possibility of overturning by floods tides etc.
• Nature of bed on which the coffer dam is to rest
• Velocity of flowing water
• Possibility of scouring due to reduction of waterway
• Availability of material on site.
• Transportation facility.
Types of cofferdam
• Earthfill cofferdam
• Rockfill cofferdam
• Rockfilled crib cofferdam
• Single walled cofferdam
• Double walled cofferdam
• Cellular cofferdam
• Concrete cofferdam
• Suspended cofferdam
Earthfill dam Cellular cofferdam

Rockfill Crib cofferdam Rockfill dam


Single walled cofferdam Concrete cofferdam

Double walled cofferdam Movable cofferdam


Earth-fill cofferdam

• It is constructed in places where the depth of


water is less about 1.2 to 1.5 m and velocity of
flow is low.
• Top of embankment should be 1 m above the
water level.
• Side slop vary from 1:1.5 to 1:2
• It is built up from a mixture of clay and sand or
clay and gravel.
• If clay is not easily obtain at site the banks may
constructed with central clay wall slopes of sand
on either side.
• To prevent the embankment from scouring water
side be pitched with rubble bounders.
Rockfill cofferdam

• Rocks have more stability in steeper slopes than earth


fill dam.
• They can constructed for 3 m. water depth with stone
or rubble for embankment.
• An impervious layer of earth is laid on the outer face
of the cofferdam which makes it impervious.
• For better construction the core walls or steel sheet
pile extending up to impervious layer may be
provided.
• The core wall may be of clay or concrete.
• A constructed rockfill cofferdam can withstand the
overtopping of water without any serious damage.
Rockfilled crib cofferdam

• A rock filled crib cofferdam consists of timber


cribs made from logs of wood.
• A crib is a framework of wooden horizontal
and cross beams laid in alternate courses.
• The cribs are open at the bottom and are filled
with rock or gravel or earth.
• It gives stability to the crib against overturning
or sliding.
Idea conditions favorable for this type of cofferdams

• The current of water is swift.


• The stream is having hard and uneven strata at bottom.
• Working space is limited.
• Depth of water is more.
• There is danger of overturning of structure.
• Timber is cheap as compare to sheet pile.
Construction procedure
• Dimension of crib is decided on depth of water and current of flow.
• Crib is built on land up to such height that when it is placed in water
some of its portion will projected above the water level.
• Crib is taken on site and it is floated and placed in position
• Pocket of crib are filled with rock which give stability and sheet pile
are driven on the outside face to give water tightness.
• The pumping is started and work of foundation is carried out.
• While dismasting the coffer dam the filling is removed and cribs are
dislocated.
Single walled cofferdam
• It is used in places where the area to be enclosed is
very small and the depth of water is more, say 4.5 to
6 m.
• Timber pile known as guide piles are first driven
deep into the firm ground below the river bed.
• A single row of sheet piles is provided on the whole
length of the cofferdam.
• The centre to centre spacing of the piles may vary
between 1.8 to 4 m. which is Depending upon the
velocity of the current of the water in the river.
• horizontal runners called wales are then bolted to
the guide piles at suitable distance apart.
• The sheet piles are then driven into the river bed
along the wales and are secured to the wales by
bolts.
• The sheet pile are supported and strengthen from
inside by wales and strut.
• Sand bag are stacked inside which increase stability
of cofferdam.
Double walled cofferdam

• It is used when area to be enclosed


is large to give stability to the
structure of the cofferdam.
• There are two type of the double
wall cofferdam
• Ohio river type cofferdam
• Timber or steel sheeting cofferdam
Ohio-River Type Cofferdam

• This type of cofferdam was frequently used


on the river ohio in USA hence it derives it
name as ohio river type cofferdam.
• It is cheap and can be built rapidly.
• It is suitable for hard bed where there is
problem of erosion.
• It can be also used on soft ground if
properly protected against erosion.
• It is not suitable for deep water and flow
of water with swift current.
Construction
• A dam is constructed by prefabricating a continues row of timber
frames having vertical post of 100 x 100 mm size and wales size is
200 x 150 mm or 200 x 200 mm.
• Cross bracing of size 50 x 50 mm is provide inner side and 20 mm and
25 mm dia. steel tie roads are provided outer side.
• The framework is assemble on barrage.
• The framework is lowered into a river.
• After placing some section sheet pile are fixed in to wales.
• When purpose of cofferdam is over it is removed by reverse process.
Timber or steel sheeting cofferdam
• It useful when depth of water is about 6
to 10m.
• For small and ordinary cofferdam
timber sheet pile are used.
• For large or it is not possible to drive
guide pile due to more depth steel
sheet pile are used.
• Various part of cofferdam are;
• Vertical guide pile and sheet pile
• Horizontal wales and caps
• Tie road on outer side
• Struts in side
Construction
• Guide pile are driven at interval of 2 to 3 m.
• Wales are fixed between two guide pile.
• The sheet pile are then driven along the inside edge of wales.
• The soft material from bottom of cofferdam is dredged out.
• Space between sheet piles is filled with puddle which have mixture of sand
or clay with gravel.
• A berm of clay may be provided on the outside of the cofferdam for
leakage .
• The width of wall should be equal to the depth of water upto 3 m.
• For greater depth
H>3 m width = 3+1/3(H-3)
Concrete cofferdam
• They are small concrete dam.
• Pre-cast R.C.C pile and sheets are used for framework which are
provided with suitable edge.
• They are driven in a similar manner to steel sheet pile.
• It costly but when it is to be incorporated as part of permanent
structure it become economical.
• It useful to avoid vibration from the process of pile driving.
Suspended cofferdam
• A cofferdam is design in such a way
that a single unit used several time.
• The cofferdam as such is lifted floated
and placed in another position as
soon its purpose is served.
• Such cofferdam are also known as
movable cofferdam.
• It consist of a hollow steel cylinder
which can be used to prepare a
temporary enclosed space for
construction work.
Cellular cofferdam
• The cellular cofferdam is made of
steel sheet pile.
• It is mostly used for de-watering
large area in place where the depth
of water may be 18 to 21 m.
• There is two type of cellular
cofferdam;
1. Circular type of cellular cofferdam
2. Diaphragm type of cellular cofferdam
Circular Type Of Cellular Cofferdam
• It consists of a set of large diameter main
circular cells interconnected by arcs of
smaller cells.
• Each cell may be filled independently to
other cells without any danger of
distortion of cells.
• Each cell is self supporting unit.
• Steel required in running length is less then
the steel required in diaphragm cell.
Diaphragm Type Cellular Cofferdam
• In Diaphragm cellular cofferdam,
series of arcs are connected to
straight cross walls.
• Distance between wall is
generally equal hence diameter of
radius is same due to this tension
in arcs and cross wall remain
equal.
• Cells are driven at desire depth
then they are filled with earth,
sand or gravel.
Design Feature Of Cofferdam
• Factors for design of a cofferdam
• Hydrostatic head of water
• Dimension of the area to be covered by the cofferdam
• Velocity of flow to be excluded
• Subsoil condition
• Fluctuation of outside water level
• Possibility of erosion
• Floating logs
Design Feature Of Cofferdam
• Force acting on cofferdam
• Self weight of cofferdam
• Water pressure
• Earth pressure from outside of soil
• Uplift pressure
• Scouring action
• Ice pressure
Leakage in cofferdam
• The water enters the cofferdam in two ways;
• By leakage of sheet pile
• By flow from base
Leakage Prevention In Cofferdam
• cement grouting.
• Dump material in out and inside
• bitumen or cement mortar.
• For serious damage tarpaulin is use which is canvas coated with tar.
• Sufficient grease applied at interlocks of sheet piles.
• In single walled cofferdam placing a V-shaped wooden trough outside
each joint and filling it with puddle.
• In case of double-walled cofferdams leakage is generally because of
insufficient compaction of the filling material. In this case, measures
to control seepage through filling material should be adopted.
Economic Height Of Cofferdam
• The maximum height of cofferdam for which it total cost is minimum
is known as most economical height of cofferdam.
• The height of cofferdam can determined based on the height of
average normal flood during every year.
• The cost of damage caused by the flood higher then estimated height
is estimated.
• Cofferdam are constructed to excluded normal flood water and
provisional damaged caused by higher flood.
• It is advisable to increase the height of dam when cost of damage
caused by higher flood is high.
Piping In Single Wall Cofferdam
• Piping or boiling in the base result from heavy upward seepage of ground
water into the cofferdam.
• It is checked in cases where the sheet pile are not driven in to impermeable
strata.
• Piping begins when the hydraulic gradient become critical gradient.
• The soil at exit is removed by the percolating water.
• When the soil near the exit has been removed, more concentration of flow
lines in the remaining soil mass results increase of exit gradient.
• The process of backward erosion towards the upstream and pipe is formed.
• large amount of water from outside rushes through the channel and the
cofferdam fails.
Piping prevention
• Reducing the exit gradient by increasing the length of seepage path.
• The length of seepage path may be increased by driving sheet piles to
a sufficient depth.
• Reducing the head of water causing seepage.
• This can be done by pumping from well point or below the level of
the bottom of the sheet pile.
• Piping is occur in loose fine sand which have permeable.
• In silty or sandy clay piping is not occur due to low permeability.
• In gravel also piping is not occur due to high permeability as hydraulic
head is reduced.

You might also like