22eh0015 Status

The document outlines the implementation status of the Batiano Boulevard Flood Mitigating Structure project as of May 15, 2023. The project experienced delays due to various factors, including weather and permit issues, resulting in a slippage of 7.51%. As of the report, the actual accomplishment stands at 90.74% against a planned accomplishment of 98.25%.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views1 page

22eh0015 Status

The document outlines the implementation status of the Batiano Boulevard Flood Mitigating Structure project as of May 15, 2023. The project experienced delays due to various factors, including weather and permit issues, resulting in a slippage of 7.51%. As of the report, the actual accomplishment stands at 90.74% against a planned accomplishment of 98.25%.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CY-2020 PROJECT IMPLEMENTATION STATUS

as of Monday,15 May 2023

1.0 Project Title


Construction/Maintenance of Flood Mitigation Structures and
Drainage Systems - Construction of Batiano Boulevard Flood
Mitigating Structure

2.0 Contract I 22EH0015-R1


3.0 Duration 304 C.D.
Date of Effectivity 3/29/2022
Date of Expiry 1/26/2023
Revised Duration CTE 1 364 C.D.
Revised Expiry CTE 1 3/27/2023
Revised Duration CTE2 424 C.D.
Revised Expiry CTE 2 5/26/2023
Details:
Approved Time Extension: No. 1
Approved 60 Calendar Days Time Extension
Shutdown Days due to S.O. 60 C.D.
Approved 60 Calendar Days Suspension due to non-issuance of
Association of Local Fishermen Permit
Approved Time Extension: No. 2
Approved 60 Calendar Days Time Extension
Shutdown Days due to S.O. 60 C.D.
Approved 60 Calendar Days Suspension due to inclement weather
brought by Tropical Disturbances that entered the Philippine area
of responsibility.

4.0 Physical Status


Planned Accomp. 98.25 %
Commitment %
Actual Accomp. 90.74 %
Reported (PCMA) 80.16 %
5.0 Slippage - 7.51 %
6.0 Allocation 100,000,000.00
Contract Amount Php 93,995,729.32
Revised Contract Amount Php 96,485,051.38
Mob./Advance Payment
Partial Payment
Interim Payment
Final Payment Php
10% Retention Php
Withheld
Released Php
7.0 Remarks:

8.0 Contractor: ROLCO CONSTRUCTION AND DEVELOPMENT


CORPORATION

9.0 Attested By: DANTE F. FETALVERO


Project Engineer