Rajat Biomass-1-2-1

The RAJAT BIO MASS project focuses on manufacturing biomass briquettes and pellets, operating as a proprietorship. The project includes detailed financial planning, implementation schedules, and machinery requirements, with a total project cost outlined. It also specifies the workforce structure and working capital needs for the initial month of operations.

Uploaded by

royalrajat207
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views5 pages

Rajat Biomass-1-2-1

The RAJAT BIO MASS project focuses on manufacturing biomass briquettes and pellets, operating as a proprietorship. The project includes detailed financial planning, implementation schedules, and machinery requirements, with a total project cost outlined. It also specifies the workforce structure and working capital needs for the initial month of operations.

Uploaded by

royalrajat207
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

HIGHLIGHTS OF THE PROJECT

1. Name of the project : RAJAT BIO MASS

2. Address of unit

3. Constitution : Proprietorship

4. Nature of Activity Manufacturing of biomass briquettes and pellets

5. Proprietor

6. Cost of Project

7. Means of Finance
Sheet2

Means of finance:

This project shall be financed in following manner:


₹In Lacs
A. Capital contribution
B. Bank Term loan
Total

Project cost details:

₹ In lacs
A. Land and Development

B. building

C. plat & machinery

D. Electricfication and installation

E. tractor & implement

Total

Implementation schedule:

this project will be implemented in following schedule

Sr. No. Activity Period


1. Acquisition and development of land Own

2. Civil work and building construction 5 months

3. Procurement of machinery and equipment 1-2 months

4. Arrangements for power supply 1 month

5. Water supply Arrangements 2 weeks

6. Erection and installation of machinery 1 month

7. Inltlal procurement and commissioning 1 month

Page 2
Sheet2
8. Trial Runns 2 weeks

9. Commercial Production 1 week

machinery:

1. Briquetting press

2. Chaff Cutter

3. Weight scale

4. packing machine

Page 3
Sheet3
Employees and worker

worker type no.ofworker salary per month type


1.non skilled 3 12000 worker
2. Employee 1 20000 manager
3. CEO 1 50000 CEO

Working capital
In 1 month:

1 ton price
1. RawRaw materials 2000-2500

Page 4
Sheet3

gg

Page 5