STP Work Program

The document outlines a work program for the development of two sewer treatment plants at Aga Khan Academy in Mombasa, scheduled from March 20, 2025, to May 14, 2025. It details tasks including earthworks, substructure, superstructure, finishes, and testing phases, with specific durations and start-finish dates for each task. The project is managed by QS. Josphat Othieno and includes inspection periods for quality assurance throughout the construction process.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views2 pages

STP Work Program

The document outlines a work program for the development of two sewer treatment plants at Aga Khan Academy in Mombasa, scheduled from March 20, 2025, to May 14, 2025. It details tasks including earthworks, substructure, superstructure, finishes, and testing phases, with specific durations and start-finish dates for each task. The project is managed by QS. Josphat Othieno and includes inspection periods for quality assurance throughout the construction process.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

WORK PROGRAM FOR STP AT AGA KHAN

ID Task Name Duration Start Finish Resource Names Mar '25 Apr '25 May '25 Jun '25
02 09 16 23 30 06 13 20 27 04 11 18 25 01 08
0 WORK SCHEDULE : PROPOSED DEVELOPMENT OF 2NO. 8.2 wks Thu 20/03/25 Wed 14/05/25
SEWER TREATMENT PLANT AT AGA KHAN
ACADEMY,MOMBASA
1 STP NO.1 8 wks Thu 20/03/25 Tue 13/05/25
2 EARTHWORKS 0.2 wks Thu 20/03/25 Thu 20/03/25
3 Site Clearance & Excavations - Oversite & Mass excavations 0.2 wks Thu 20/03/25 Thu 20/03/25
for STP pit
4 SUBSTRUCTURE 1.2 wks Fri 21/03/25 Thu 27/03/25
5 Blinding under Base slab foundation 0.2 wks Fri 21/03/25 Fri 21/03/25
6 Base slab - formworks, steel works & casting 1 wk Sat 22/03/25 Thu 27/03/25 3 Days Inspection 3 Days Inspection
7 SUPERSTRUCTURE 3.4 wks Mon 07/04/25 Tue 29/04/25 7 Days Concrete
Curing
8 R.C wall - Formworks,Steel works & Casting 1.2 wks Mon 07/04/25 Mon 14/04/25 3 Days Inspection 3 Days Inspection
9 Beams & Cover slab - Formworks,Steel works & Casting 1 wk Wed 16/04/25 Tue 22/04/25 3 Days Inspection 3 Days Inspection
10 Sump & Manhole - Formworks,Steel works & Casting 0.4 wks Wed 23/04/25 Thu 24/04/25
11 Waterproofing Testing; Filling the tank, Observing for leaks & 0.6 wks Fri 25/04/25 Tue 29/04/25 2 Days Inspection 2 Days Inspection
Draining the tank
12 FINISHES 2 wks Wed 30/04/25 Tue 13/05/25
13 Internal wall plaster Finishes, Surface Screed & SIKA waterproof 1 wk Wed 30/04/25 Tue 06/05/25
application
14 Waterproofing Testing; Filling the tank, Observing for leaks & 0.6 wks Wed 07/05/25 Fri 09/05/25 2 Days Inspection 2 Days Inspection
Draining the tank
15 Cat Ladder, PPR Water supply & Drainage pipes and Pressure Testing 0.4 wks Mon 12/05/25 Tue 13/05/25

16 STP NO.2 8 wks Fri 21/03/25 Wed 14/05/25


17 EARTHWORKS 0.4 wks Fri 21/03/25 Sat 22/03/25
18 Site Clearance & Excavations - Oversite & Mass excavations 0.4 wks Fri 21/03/25 Sat 22/03/25
for STP pit
19 SUBSTRUCTURE 1.2 wks Mon 24/03/25 Mon 31/03/25
20 Blinding under Base slab foundation 0.2 wks Mon 24/03/25 Mon 24/03/25
21 Base slab - formworks, steel works & casting 1 wk Tue 25/03/25 Mon 31/03/25 3 Days Inspection 3 Days Inspection
22 SUPERSTRUCTURE 3.4 wks Mon 07/04/25 Tue 29/04/25 7 Days Concrete
Curing
23 R.C wall - Formworks,Steel works & Casting 1.4 wks Mon 07/04/25 Tue 15/04/25 3 Days Inspection 3 Days Inspection
24 Beams & Cover slab - Formworks,Steel works & Casting 1 wk Wed 16/04/25 Tue 22/04/25 3 Days Inspection 3 Days Inspection
25 Sump & Manhole - Formworks,Steel works & Casting 0.4 wks Wed 23/04/25 Thu 24/04/25
26 Waterproofing Testing; Filling the tank, Observing for leaks & 0.6 wks Fri 25/04/25 Tue 29/04/25 2 Days Inspection 2 Days Inspection
Draining the tank

Task Project Summary Manual Task Start-only Deadline

Project: WORK SCHEDULE : PRO Split Inactive Task Duration-only Finish-only Progress
Date: Thu 20/03/25 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

PREPARED BY: QS. JOSPHAT OTHIENO Page 1


WORK PROGRAM FOR STP AT AGA KHAN
ID Task Name Duration Start Finish Resource Names Mar '25 Apr '25 May '25 Jun '25
02 09 16 23 30 06 13 20 27 04 11 18 25 01 08
27 FINISHES 2.2 wks Wed 30/04/25 Wed 14/05/25
28 Internal wall plaster Finishes, Surface Screed & SIKA waterproof 1 wk Wed 30/04/25 Tue 06/05/25
application
29 Waterproofing Testing; Filling the tank, Observing for leaks & 0.6 wks Wed 07/05/25 Fri 09/05/25 2 Days Inspection 2 Days Inspection
Draining the tank
30 Cat Ladder, PPR Water supply & Drainage pipes and Pressure Testing 0.4 wks Mon 12/05/25 Tue 13/05/25

31 Snag & Cleaning 0.2 wks Wed 14/05/25 Wed 14/05/25 Enginner's certification Enginner's certification

32 HANDOVER 0 wks Wed 14/05/25 Wed 14/05/25 14/05

Task Project Summary Manual Task Start-only Deadline

Project: WORK SCHEDULE : PRO Split Inactive Task Duration-only Finish-only Progress
Date: Thu 20/03/25 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

PREPARED BY: QS. JOSPHAT OTHIENO Page 2