0% found this document useful (0 votes)
6 views5 pages

Construction Material Works

The document outlines a detailed list of construction materials and works, including unit prices and total costs for various tasks such as brick work, plastering, and installation of fixtures. It includes multiple annexes with specific quantities and pricing for each item. Additionally, it notes the inclusion of percentages for electricity work and unforeseen costs in the gross amount calculation.

Uploaded by

Abdullah Fazal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views5 pages

Construction Material Works

The document outlines a detailed list of construction materials and works, including unit prices and total costs for various tasks such as brick work, plastering, and installation of fixtures. It includes multiple annexes with specific quantities and pricing for each item. Additionally, it notes the inclusion of percentages for electricity work and unforeseen costs in the gross amount calculation.

Uploaded by

Abdullah Fazal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Annex ‘A’

CONSTRUCTION MATERIAL / WORKS

Unit Price Total


S.No Description Unit SI Qty in Price
PKR In PKR
1 Brick work in walls 4.5" thick 1:4 CM Cum 4-2 12.47
Providing and laying RCC concrete
2 Cum 3-10 0.64
1:2:4 in lintel beams complete
supply and fixing of reinforcement
3 Kg 9-56 20.84
bars
222.3
4 Plaster of walls in 1:4 CM Sqm 13-4 8
Three coats of plastic emulsion paint over 15-53
preparation of Surface by using putty to 2(15-
5 222.3
form smooth base for Sqm 54)
8
Distemper as spd (internal walls). 15-101
Supply and fix, Solid Flush door, Teak
6 veneered, 32 mm thick including mongery,
Sqm 7-44 11.06
without chowkats.
Lacquer polish to wood work
7 Sqm 15-74 22.12
(complete rate).
Supply and Fixing of Chowkats in wall
8 Meter 7-80 26.52
complete
69.38
Cleaning and chemical polishing of terrazzo
9 floor / dado/Marble floors. Sqm 12-33 61889
3
Providing and laying Standard quality tiles
of any make not exceeding 1600 Sq cm,
10
including setting, jointing and Bonding, Sqm 12-35 60.18
complete all as specified.
Supply and Fix Water Closet (WC) of
11 standard quality, European pattern complete
Each 17-1 2
(coupled) all as specified.
Supply and Fix Wash Hand Basin (WHB)
of standard quality, including pedestal,
12
waste pipe, bolts / bracket and coupling
Each 17-34 2
etc., complete all as specified.
Supply and fix , Mirror, (any shape and
pattern, circular, rectangular, oval etc.) upto
13 2700 sqcm, 5 mm thick, with plastic frame
of any colour edges ground, complete all as Each 17-41 2
specified.
Supply and fix, Soap / sponge tray any
14 shape, pattern and size with plugs, screws
Each 17-52 2
etc. complete all as specified.
Supply and fix, Toilet paper holder, any
15 shape, pattern, size with plugs, screws etc.,
Each 17-50 2
complete all as specified.
Supply and fix, Towel rail, CP, single rod,
16 any pattern, shape and size with plugs,
Each 17-56 2
screws etc. complete all as specified.
Supply and fix, Corner Shelf in any size,
17
shape with plugs and screw complete all Each 17-51 2

1
as specified.
Supply and fixing of brush holder
18 Each 17-53 2
complete
Stop cock brass, CP, screw down, high
19 pressure, fancy type, 15mm dia, supply and
fixing. Each 18-331 2
Supply and fix, 100 mm dia floor trap,
20 including reducer etc. complete all as
Each 17-63 2
specified.
Supply and fix, Casted Grating CP,
21 Each 17-65 2
150 mm x 150 mm.
CP Mixer, 15mm dia, fancy head, any
pattern and shape, screw down, high
22 pressure, lettered Hot and cold with long
screw channels and fly nuts complete, Each 18-328 2
supply and fixing.
Supply and fix, u-PVC, Soil and waste pipe
23 75 mm dia, complete, with plain end and
Meter 20-50 15
solvent cement joint, all as specified.
Supply and fix, u-PVC, Soil and waste pipe
24 110 mm dia, complete, with plain end and
Meter 20-51 15
solvent cement joint, all as specified.
Supply and fix, uPVC Elbow/bend, 90° 75
25 mm dia, complete with Z joint and rubber
Each 20-70 4
ring, all as specified.
Supply and fix, uPVC Elbow/bend,
26 90° 110 mm dia, complete with Z joint and
Each 20-71 4
rubber ring, all as specified.
Supply and fix, Socket 75mm dia complete
27
with solvent cement joint, as specified. Each 20-90 3
Supply and fix, Socket 110mm dia complete
28 Each
with solvent cement joint, as specified. 20-91 3
28-
29 Supply and Fixing of Toilet Shower Each 2
283
Supply and Fixing of Wall Shower 28-
30 Each 1
Delux quality 309
PPR pipe, with all fittings i.e. socket,
bend, tee, elbow, where required, 25 mm
31
dia, Class PN-20 (excluding excavation), Meter 18-894 20
supply and fixing.
PPR pipe, with all fittings i.e. socket,
bend, tee, elbow, where required, 32 mm
32
dia, Class PN-20 (excluding excavation), Meter 18-895 20
supply and fixing.
Elbow 25mm dia 90° for PPR pipe, supply
33 and fixing. Each 18-974 10
Elbow 32mm dia 90° for PPR pipe, supply
34 and fixing. Each 18-975 10
PPR Coupler / Socket, 25 mm dia, supply
35 and fixing. Each 18-909 5
PPR Coupler / Socket, 32 mm dia, supply
36 and fixing. Each 18-910 5
Electric Water Cooler, SP, 220/240V,
18-
37 cooling capacity 60 Lit/hr, complete, supply Each
532 2
and fixing.
Water filter, 3 stage, consisting of 18-
38 Each 2
polypropylene fiber cartridge 5 micron, 543

2
granular activated carbon cartridge 1
micron, and size of cartridge 10" with ultra
violet lamp, water flow rate 3 GPM
complete, supply and fixing.
Total Amount of Civil Works

Add 20% for Electricity Work

Add 10% for Unfor-seen

Gross Amount

3
Annex ‘B’

CONSTRUCTION MATERIAL / WORKS

Unit
Total Price
S.No Description Unit SI Qty Price in
In PKR
PKR
1 Dismentaling of Brick Work Cum - 2.01
Brick work in walls 4.5" thick 1:4
2 Cum 4-2 16.06
CM
Providing and laying RCC concrete
3 Cum 3-10 0.12
1:2:4 in lintel beams complete
supply and fixing of reinforcement
4 Kg 9-56 29.60
bars
5 Plaster of walls in 1:4 CM Sqm 13-4 294.43
Three coats of plastic emulsion
paint over preparation of Surface 15-53
6 by using putty to form smooth 2(15-54) 294.43
Sqm
base for distemper as spd 15-101
(internal walls).
Supply and fix, Solid Flush door,
Teak veneered, 32 mm thick
7 7-44 9.56
including mongery, without Sqm
chowkats.
Supply and Fixing of Chowkats in
8 Meter 7-80 22.41
wall complete
Lacquer p o l i s h t o w o o d
9 Sqm 15-74 19.13
w o r k (complete rate).
Providing wooden partitions
10 Sqm 7-125 25.86
complete in all respects
Providing Wooden Cabinets
11 Sqm 7-135 16.40
Complete in all respects
Cleaning and chemical polishing
12 of terrazzo floor / dado/Marble Sqm 12-33 227.7290303
floors.

Total Amount of Civil Works

Add 20% for Electricity Work

Add 10% for Unfor-seen

Gross Amount

4
Annex ‘C’

CONSTRUCTION MATERIAL / WORKS

Unit
Total Price
S.No Description Unit SI Qty Price in
In PKR
PKR
Brick work in walls 4.5" thick 1:4
1 Cum 4-2 19.36
CM
Providing and laying RCC concrete
2 Cum 3-10 0.22
1:2:4 in lintel beams complete
supply and fixing of reinforcement
3 Kg 9-56 33.22
bars
4 Plaster of walls in 1:4 CM Sqm 13-4 342.57
Three coats of plastic emulsion
paint over preparation of Surface 15-53
5 by using putty to form smooth 2(15-54)
Sqm 342.57
base for distemper as spd 15-101
(internal walls).
Supply and fix, Solid Flush door,
Teak veneered, 32 mm thick
6
including mongery, without Sqm 7-44 4.88
chowkats.
Lacquer p o l i s h t o w o o d
7 Sqm 15-74 20.82
w o r k (complete rate).
Supply and Fixing of Chowkats in
8 Meter 7-80 21.95
wall complete
Cleaning and chemical polishing
9 of terrazzo floor / dado/Marble
Sqm 12-33 237.0240928
floors.

Total Amount of Civil Works

Add 20% for Electricity Work

Add 10% for Unfor-seen

Gross Amount