Procedure & Timeline
Applicant Registration
Applicant downloads
felling permission SMS for successful
registration
Applicant Login
DFO uploads
felling permission
Apply Online by filling
after enquiry
up Form I(B)
SMS for completing
application
Applicant download the Pay Application fees
Inquiry Report & Apply Online through
for felling Permission by GRIPS(Rs-1000/-)
uploading Certificate of
Completion of
Plantation & Approved
building/construction
plan or approval letter NO Is Payment
Successful??
NO
YES
DFO uploads
1)Inquiry Report Application
Is Inquiry
2)Clearance YES
Report submitted to
3)Approved concerned DFO
positive?
Plantation Plan
30 days
Inquiry Officer DFO Allocate Are documents NO
YES
submits the Inquiry Officer submission
Inquiry Report for Verification satisfactory?
Resubmission
30 days
90 days
Timeline:
1. Inquiry by the Inquiry Officer: 30 days(after receipt of applicant)
2. Issuance of Certificate of Clearance :30 days(after receipt of inquiry)
3. Issuance of Tree Felling permission:90 days (after receipt of application)