Points To Ensure:
1. Check for any physical breakage / damage
2. Cubicals bolted in position.
3. Position of busbars and spacing checked and found within acceptable limit.
4. All the insulators are in good condition.
5. Inter-changing of all size of Motor, Power and ACB Feeders checked.
6. Operation of shutter mechanism checked and satisfied.
7. Panel wiring checked and found as per scheme.
o Motor Feeders.
o Motor feeder interlock with Control Room Panels
o Incomer interlocks scheme.
8. All circuits tested and CT / PT. Ratio checked as per the ITP. And CT's have been put
in service.
9. All protection relays tested and tripping through relays checked.
10. BUSBAR IR checked.
11. Auxiliary power supply made available.
o DC Supply for protection & interlocks.
o Auxiliary supply for Space Heaters.
o Control Power supply.
12. Check all the Main & Control fuses of recommended ratings.
13. Check Feeder