Generator Fansing

This report proposes the installation of a back-up power generator at the Fansing facility to mitigate risks associated with electrical power failures, which could lead to employee injuries and damage to equipment. The generator, available at a cost of approximately AED 4060, can be installed in January and will require minimal training for personnel. The project aims to enhance safety and prevent costly damages during power outages, with a total estimated installation cost of AED 3,690.

Uploaded by

mohamed elsaka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views4 pages

Generator Fansing

This report proposes the installation of a back-up power generator at the Fansing facility to mitigate risks associated with electrical power failures, which could lead to employee injuries and damage to equipment. The generator, available at a cost of approximately AED 4060, can be installed in January and will require minimal training for personnel. The project aims to enhance safety and prevent costly damages during power outages, with a total estimated installation cost of AED 3,690.

Uploaded by

mohamed elsaka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Title : Installation of a Power Generator

Abstract

The purpose of this report is to propose a back-up generating plant at the new Fansing facility.

The problems that might result from an electrical power failure at the plant involve both
personnel and facilities. Employee injuries could result from moving about with no lighting in the
plant, being trapped inside closed tanks, and being struck by items falling from cranes that are
operated by vacuum lifts or battery magnets. The plant itself would be in danger of damage from
surface-drainage water, fire, and the freezing of pipes and heaters.

A surplus generator is available from our Field Force Division and could be installed for
approximately AED4060, including labor and material. It can be installed in the powerhouse’s
air-compressor room during the month of January, and its operation will require minimum
training of personnel.

The generator can meet all the plant’s emergency requirements and do so very economically.

Introduction

Purpose

This report proposes the installation of an on-site electrical generating plant at the new
manufacturing facility in Fansing.

Problem

At present, a power failure would result in the following unsafe conditions for the employees: (1)
plant lighting would be lost, and employees could not move safely within the plant; (2)
employees working inside closed tanks could not get out until the tank could be rotated by an
electric motor; (3) employees could be injured by item falling from the three overhead cranes
that hold their loads by vacuum lifts or battery magnets and must set them down within 10
minutes after power failure.

A power failure would also cause damage to the plant: (1) the sump pump for surface-drainage
water would not operate in the main office building and the basement of the grit-blast area,
causing extensive damage to equipment; (2) the fire alarm systems and the main fire pump
would not function, and a fire could not be contained; (3) during winter, loss of the main heating
boilers would cause water lines and fire loop feedlines to freeze, break, flood areas of the plant,
and ruin equipment.
SCOPE

In Section I, this report describes the installation of the generator. This is followed by sections
on lighting and equipment changes, the schedule for the project, personnel training, and cost. At
the end of the report, conclusions are presented.
SECTION I : INSTALLATION OF THE GENERATOR

A back-up generator is readily available for this project. One was purchased by the Field Force
Division in 1970 for use as a standby unit at building sites. Because it was used only while other
units were being repaired, the generator has operated for just 565 hours. Similar units have
operated in excess of 15,000 hours, so the generator is almost new. It was built by
Westinghouse and has a General Motors diesel engine.

The generator can be located in the air-compressor room at the powerhouse. This location will
allow easy hookup to the main utility substation. The floor of the powerhouse is sufficient to hold
the weight of the generator and to retain bolts needed to anchor the unit. The start-up fuel tank,
located near the generator, will be used to operate the diesel engine.

Siding along the powerhouse’s east wall must be removed to allow entrance of the generator; a
louvered panel will replace the siding and allow cooling air to circulate around the generator.
Installation of the generator will require drilling holes in the floor to mount the anchor bolts. A
rack must be built to hold the batteries for starting the diesel engine. An electric load-transfer
panel will be assembled and wired into the existing substation, and a fuel line will be connected
to the 2000 gallon fuel tank. Hooking the generator to the substation requires installation of
three 460 volt cables between the powerhouse and the transformer. This can be accomplished
by maintenance personnel.

SECTION II: LIGHTING AND EQUIPMENT CHANGES

In order to stay within the capacity of the generator and still provide the power needed to
maintain necessary lighting and motor power, some electrical wiring changes must be made in
the plant. Lighting circuits now operated by mechanical switches will have to be changed to
electricity. This change means that if the electric power fails, the lighting will not turn on after
auxiliary power is established, thus removing electrical loads during power failure. However, the
night lights, which will turn on automatically with the start of auxiliary power; will allow
employees to leave the plant safely.

The rotoblast power supply will have to be changed to a manual-start mode. This conversion
requires the addition of one relay to the panel board and allows personnel operating the cranes
to lower suspended loads safely to the floor.

Sump pumps used for the removal of drainage water from the office building and basement of
the gritblast will automatically return to operation when auxiliary power is supplied. No changes
will be required in the existing circuits to these pumps.

The fire alarm will function as soon as power is transferred to the generator. If a fire should start,
the alarm would be sounded immediately. At that time, all electrical power would be turned off,
including the night-light circuitry. This is necessary because the fire pump’s motor taxes the
generator so much that very little electricity is available.
SECTION III: SCHEDULE FOR THE PROJECT

Phase One

Phase one will be completed during the normal work week, using plant personnel. This phase
will include wiring the rotoblast, changing the lighting, installing anchor bolts, installing the fuel
line, building and installing battery racks, and wiring the generator to the substation.

Phase Two

Phase two will involve Saturday work because two shifts of four workers each will be required,
and these workers cannot be spared from duty during weekdays. Work will consist of removing
the siding on the powerhouse wall, moving the generator into the powerhouse, installing it on its
anchor bolts, and replacing the siding with a louvered panel.

Phase Three

Phase three will be accomplished on a Sunday when power can be turned off in the plant. Work
will consist of hooking cables into the outside substation, hooking the fuel line to the engine, and
connecting the power and battery cables to the generator. The power will be off for only half an
hour, and no special precautions should be necessary because no operating personnel will be
in the plant.

This project can begin 4 weeks before the start of plant shutdown, which is scheduled to begin
July 7. Phase one can start June 21. Phase two can be done Saturday, June 22, and phase
three can be completed Sunday, June 30.

SECTION IV: PERSONNEL TRAINING

No personnel training will be needed for starting the diesel generator. The control panel installed
in the powerhouse will automatically start the engine in the event of a power failure and transfer
the plant’s reduced electrical load to the generator.

Operation of the fire pump from auxiliary power requires the manual operation of a start switch.
All members of the plant fire team are familiar with this operation.

SUPERVISION

All shop supervisors will be instructed about the limitations of the auxiliary power. These
supervisors will tell their personnel which equipment should be operated to assure the safe
shutdown. The supervisors have enough experience in their areas to know what needs to be
done. All instructions to supervisors will be covered by an interoffice memorandum when the
auxiliary generator is operational.

MAINTENANCE

Routine maintenance on the engine and generator, using plant maintenance personnel who are
familiar with this type of equipment, will be scheduled. The generator will be tested once per
month to insure its availability for an emergency.
SECTION V: COST

The generator, which cost $14,657 in 1963, is now worth approximately $4330 and is available
at no cost.

Following are estimated costs for installing the generator, which include labor to build and install
the necessary equipment, and costs for material.

Labor rates for plant personnel are based on the latest figures for this plant. Straight-time labor
is $7.00 per hour, time and a half is $9.25 per hour, and double time is $11.50 per hour:

Material —————– AED 2,450.00


Labor ——————– AED1,240.00
—————————– AED 3,690.00
Contingency (10%)——— 370.00
TOTAL COST FOR PROJECT – AED 3,690.00

CONCLUSION

1. Our new manufacturing facility in Fansingrepresents an investment of $7 million and


employs 300 people. Any interruption of electric power would create a total blackout and
completely halt the equipment. This would result in very unsafe conditions for employees
trying to move within the plant. Damage to equipment and spoilage of materials would
also result if the power failure were prolonged.
2. Considering the safety of the employees, $4060 for back-up generator is an extremely
reasonable investment. In addition, the facilities and equipment that might be damaged
during a power failure would cost more than installation of the generator.