DURGA PROCESSORS PVT. LTD.
MONTH
HOSE BOX MONTHLY CHECK LIST
DOOR BOX
SR.No. CHEKING DATE HB NO BUILDING FLOOR LOCATION HOSE PIPE BRANCH KEY REMARKS
GLASS CONDITION
1 1 A GF SIDE OF LIFT NO- 03.
2 2 A GF DP MAIN GATE NO. 01 ENTARY.
3 3 A GF BETWEEN STENTER NO- 2&3.
4 4 A GF BETWEEN STENTER NO- 1 &7 NO.
5 5 A GF EXIT SIDE OF DYIENG KHATA. STENTER NO- 1 &7 FRONT
6 6 A 1F NEAR PADDING-01 STAIRCASE
7 7 A 1F BACK SIDE OF ROTARY NO- 04.
8 8 A 1F BATCHING M/C NO.1 MARKETING OFFICE SIDE.
9 9 A 2F NEAR LIFT NO- 03.
10 10 A 1F BACK SIDE OF LOOP M/C.
11 12 A 2F MID-SIDE OF GREY KHATA.
12 13 A 2F GREY KHATA NEAR WATER TANK.
13 14 A 2F RO SIDE GREY KHATA.
14 47 A 2F GREY KHATA ON STAIRCASE.
15 59 A 2F GREY KHATA NEAR TOILET.
16 58 A 3F GREY KHATA NEAR STAIRCASE.
17 15 B GF NEAR LIFT NO- 04.
NEAR LIFT
18 16 B GF MEZZ
NO- 04.
19 17 B 1F NEAR LIFT NO- 04.
20 18 B 1F MEZZ CHARKHA KHATA NEAR LIFT NO- 04.
21 19 B 2F NEAR LIFT NO- 04 STAIRCASE
22 20 B 3F GREY KHATA.
23 11 C GF STAIRCASE LABOUR CANTEEN .
24 29 C GF NEAR LIFT- 07.
DOOR BOX
SR.No. CHEKING DATE HB NO BUILDING FLOOR LOCATION HOSE PIPE BRANCH KEY REMARKS
GLASS CONDITION
25 24 C 1F NEAR ST- 06.
26 26 C 1F BETWEEN ST- 05 & 06 .
27 25 C 1F NEAR LIFT NO-07.
28 23 C 1F NEAR HOSPITAL STAIRCASE.
29 43 C 1F MEZZ CHARKHA KHATA NEAR STAIRCASE.
30 27 C 2F NEAR STAIRCASE.
31 22 C 2F GREY KHATA NEAR LIFT- 07.
32 30 D GF NEAR RECEPTION OFFICE.
33 31 D GF NEAR RELAX DRAYER MACHINE.
34 32 D GF NEAR MASTER OFFICE.
35 33 D GF NEAR LIFT NO- 09.
36 34 D GF NEAR LIFT NO- 10.
37 35 D GF UTILITY SIDE.
38 36 D GF MEZZ NEAR LIFT NO- 10.
39 63 D GF MEZZ FOLDING
40 37 D 1F NEAR LIFT.10 STAIR CASE SIDE.
41 66 D 1F BOILER SIDE EMERGENCY STAIR CASE.
42 28 D 1F NEAR STENTER NO- 08 OFFICE.
43 41 D 1F NEAR LIFT NO- 09.
44 42 D 1F NEAR WASHING MACHINE NO- 03.
45 39 D 1F NEAR CALENDER NO- 06.
46 40 D 1F NEAR STENTER NO- 11.
47 38 D 1F BACK SIDE OF LIFT NO- 08.
48 61 D 1F MEZZ 10 LIFT SIDE
49 49 D 2F NEAR LIFT NO- 09.
50 46 D 2F HR OFFICE SIDE.
51 48 D 2F NEAR BATCHING STENTER.
DOOR BOX
SR.No. CHEKING DATE HB NO BUILDING FLOOR LOCATION HOSE PIPE BRANCH KEY REMARKS
GLASS CONDITION
52 50 D 2F MAINTENANCE SIDE.
53 44 D 2F NEAR LIFT NO- 10.
54 45 D 2F NEAR LOOP MACHINE- 03.
55 51 D 2F MEZZ LIFT NO.10 STAIR CASE BOILER SIDE.
56 62 D 2F MEZZ STAIR CASE SIDE U3 - OFFICE.
57 65 D 2F MEZZ STAIR CASE BOILER
58 54 D 3F NEAR PRINTING MACHINE NO- 06.
59 53 D 3F BACK SIDE OF LIFT NO. 08.
60 55 D 3F BACKSIDE PRINTING NO- 06.
61 56 D 3F LIFT NO- 09.
62 57 D 3F SAMPAL KHATA NEAR.
63 52 D 3F NEAR LIFT NO. 08.
64 64 D 3F MEZZ STAIR CASE BOILER
65 68 E 1F STAIRCASE.
66 69 E 3F STAIRCASE.
67 21 BOILER BOILER BOILER NEAR E BUILDING.
68 67 BOILER BOILER BOILER NEAR EMERGENCY STAIR CASE.
69 60 BOILER BOILER BOILER NEAR ELECTRIC PANEL.
CHECKED BY:- VERIFIED BY:-
SIGN:- SIGN:-