Edited Final Gc2003
Edited Final Gc2003
ARBAMINCH UNIVERSITY
ENGINEERING DEPARTMENT
JUNE, 2011
ARBAMINCH
CANAL NETWORKING AND DRAINAG SYSTEM
DESIGN
ON RIBB IRRGATION PROJECT
SUBMITTED BY:
ABIY ALEMU
BETELHEM W/RUFEAL
ESHETU TSEGA
FIREZER GETACHEW
GETAHUN ALAMNEH
MATEWOS WOMA
MOHAMED EBRAHEM
TARIKU DEGEFA
IN
ARBAMINCH UNIVERSITY
AND
SUBMITTED BY:
ABIY ALEMU
BETELHEM W/RUFEAL
ESHETU TSEGA
FIREZER GETACHEW
GETAHUN ALAMNEH
MATEWOS WOMA
MOHAMED EBRAHEM
TARIKU DEGEFA
IN
ARBAMINCH UNIVERSITY
JUNE 2011
ARBAMINCH
Acknowledgement
About all, we would like to express our deepest heartfelt thank to Eternal God whose hand
support us in all our study and careers in AMU.
We would like to express our sincere gratitude and indebtedness to our advisors Ato
Taddesse Shimelis (M.Sc) and Ato Habte Gebeyehu (B.Sc) who support and cooperated us
by providing the necessary data what we need, and for their intelligent guidance to solve
varieties of difficulties in the process of our work.
We would like also like to express our thanks to librarian for their generous cooperation in
providing us the necessary books, sample project when required.
Finally, we thanks our families, friends communities of AMU and all others who have
helped us in our activities through moral, financial and material in our four year study in
AMU.
ABSTRACT
The report on canal networking and drainage design system project consists of genuine
work on the design of the irrigation scheme for 1000ha of land of which will be effectual
through diversion of Ribb River.
The report consists of background information of the project area, such as soil, crop water
demand assessment for the selected crops, design of canal and canal structures, irrigation
water application design, design of drainage system, environmental impact assessment,
economic analysis of the project, conclusion and recommendation and annexes have been
provided.
The project consists of eight chapters and each chapter has its own content to deal with.
Chapter One-deals about the introduction, General situation of the area, Project area,
Location, Topography, Climate, and Soil type of the area, and Scope of the project.
Chapter Two – Irrigation water demand assessment, calculation method of ETO, crop
selection, cropping pattern, land allocation of the selected area, calculation of K C,
calculation of ETC, irrigation requirement, effective rainfall, NIWR, GIR, irrigation schedule,
depth of irrigation and irrigation interval.
Chapter Three – irrigation canal system, canal alignment, design of canal structure(such as
culvert, canal drop, stilling basin, canal outlet, division box, and aqueduct.
Chapter Four – about water application system, surface irrigation system, furrow
irrigation system, designs of siphon tube and irrigation system management.
Chapter Five - deals about system design of drainage under this it deals , selection of
drainage system, surface and sub surface drainage system design .
Chapter Six - deals about economic analysis and estimation the project benefit.
Chapter - Seven - deals about EIA, potential impact and mitigation measures, negative
impact, positive impact and mitigation measure.
GW-ground water
Rad-radiation
CHAPTER ONE
INTRODUCTION
1.1 General
Ethiopia is one of the developing countries and around 85% of the total population
depends on agriculture most of the agricultural practice is rain fed crop production.
However, due to the back ward method farming, unreliable rainfall, including population
and drought. The nation faced series food shortage. These food shortages were followed by
sever famines that resulted in the loss of the lives of millions of citizens.
Hence, it is obvious that the agricultural system has to be improved and irrigation practice
should be spread extensively to bring about sustainable food self-sufficiency and to earn
foreign exchange.
Fortunately, Ethiopia is luck of in that it has got ample source of surface and subsurface
water which it is known as” The water tower of east Africa.”
Moreover, the irrigation potential is estimated to be about 4025 million hectare of which
only 5.8% is irrigated. (Source; study carried out by international water management
institute-IWMI. In this project it is aimed to irrigate 1000ha i.e. small scale irrigation
project.
Lake Tana Basin is one of the major agricultural areas of the country. However, this
potential area is under threat. The ever-increasing devastation of the natural vegetation, the
Water Resources And Irrigation Engineering Final Year Project 2011 Page 1
Canal Network Design on Ribb Irrigation Project
gentle slopes, and traditional land management practices, poorly adapted to land
conservation under the prevailing conditions, have resulted in dramatic soil erosion in the
area.
The basin population is expected to triple over the next fifty years. This will place enormous
additional pressure on the land base in the highlands, where it is already fully utilized.
Indeed, it is clear that the land as a whole cannot possibly absorb the expected population,
and alternate means of livelihood must be created.
Lake Tana's shore is characterized by flat low-lying land with poor drainage conditions. In
these low-lying lands, the rivers have inadequate flood-carrying capacity due to mild slope
and shallow cross-sections caused by sediment deposition in the riverbed. Surface inflows
overtopping the riverbanks, direct rainfall on the area, poor drained soil and Lake Tana
backwater effect also contribute to flooding in the area. This has even hampered the
development of rain fed crops during the main season.
The introduction of irrigation will make farmers feel more secure about their basic food
supply and enable them to diversify their crops based on local market demand and export
opportunities.
The land and water resources in the area are suitable for irrigation development.
Experience from small-scale irrigation schemes has demonstrated that a range of crops
could be grown profitably during the dry season, without affecting the production of staple
food crops during the rainy season.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 2
Canal Network Design on Ribb Irrigation Project
Tertiary unit
1.2.2 Climate
The climate of the Ribb Basin is marked by bimodal rainy season the first round extend
from March to June, with monthly rainfall varying from 74.6 mm in March to 148.9 mm in
April; the second round extends from August to November with monthly rainfall varying
from 74.1mm in August to 124.9mm in October . The dry season is from December to
February. Dependable rainfall varies from less than 51.1 mm during the dry season to 74.1–
148.9 mm/month during the period of rainy season. The average minimum and maximum
temperature variations throughout the year are extending from 16.49 ºC to 29.85 ºC
respectively. Humidity varies between 44% in Feb and 66% in May. Wind speed is low, it
varies from 0.8m/s in Dec to 1.17m/s in June the average Sunshine duration varies from
4.7-9.1hours during July and January
Water Resources And Irrigation Engineering Final Year Project 2011 Page 3
Canal Network Design on Ribb Irrigation Project
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Water Resources And Irrigation Engineering Final Year Project 2011 Page 4
Canal Network Design on Ribb Irrigation Project
improve the living standard of the area. This ensures food self-sufficiency and reduces
poverty.
The area being very near to the three big towns Gonder, Addiss Zemen and Bahir Dar, the
agricultural product has good marketing facilities.
To utilize existing resources in a better way and reduce the wastage of materials and
human dependency on rainfall
Finally to improve the socio economic life of the community, by increasing per
capital incomes too.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 5
Canal Network Design on Ribb Irrigation Project
CHAPTER TWO
2.1 General
Water is one of the most important agricultural inputs which plays vital role in the process
of plant growth. Crops need water, starting from the time of sowing until they got matured.
However, the rate of use of water is affected by various factors such as
Type of soil
Type of crop
Length of growing season
Meteorological variables like sun shine, temperature humidity, rainfall and wind
speed.
Irrigation water is a major source of water supply that ensures the required, Irrigation
water requirement is the total quantity of water required to be supplied by irrigation to
meet crop needs for consumptive use and additional needs like leaching and unavoidable
losses. The total quantity of water sizing of a reservoir
There is no vital requirement other than water for crops. It has a number of functions in the
process of growth.
The function of water with respect to growth of plant and its yield are:
1. Solvent for gaseous, minerals and other soluble food.
2. Conduct and translocation of solutions in cell and tissues.
3. as an active reagent in photosynthesis and hydrolysis.
The factors that affect the water requirement of plants are: type of soil, type of plant,
metrological variables like sunshine, temperature, humidity, rainfall and wind etc.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 6
Canal Network Design on Ribb Irrigation Project
restricting conditions including soil water and fertility and achieving full production
potential under the given growing environment.
The water requirement of crops may be contributed from different sources such as
irrigation requirement, effective rainfall, soil moisture storage and ground water
contributions.
CWR=IR+ER+S+GW
Where, CWR=crop water requirement
IR=irrigation requirement
ER=effective rainfall
S=carry over soil moisture in the root zone
GW=ground water contribution
Water Resources And Irrigation Engineering Final Year Project 2011 Page 7
Canal Network Design on Ribb Irrigation Project
So, Blaney-criddle and Thornthwaite methods use temperature data only so that the other
climatic conditions are ignored. Hardgrave’s and Modified penman methods are over
estimated.
The FAO penman method was found to frequently overestimate ET o while the other FAO
recommended equations, namely the radiation, the Blaney-Criddle the evaporation
methods, showed variable adherence to the grass reference cop evapotranspiration. As
result, the FAO penman-Monteith method is recommended. As the sole method for
determining reference evapotranspiration, the method has been selected because it closely
approximates grass ETo at the location evaluated. However, procedures have been
developed for estimating climatic data based on given metrological data.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 8
Canal Network Design on Ribb Irrigation Project
Adaptability to climate
Water Resources And Irrigation Engineering Final Year Project 2011 Page 9
Canal Network Design on Ribb Irrigation Project
Socio-economic aspect
Marketing value of crop (priority should be given to those with higher market
value).
Based on the above criteria Potato, Maze, Tomato, Barely, & Pepper crop was
selected to grow in the project area
Water Resources And Irrigation Engineering Final Year Project 2011 Page 10
Canal Network Design on Ribb Irrigation Project
The following points are considered on the generation of the objective function
of the optimization problem.
Project yields of each crop taken from local information and yield response to
water, FAO 1986.
Price of the products taken from local market of the project area.
Input costs for seeds, fertilizers and chemical protection such as herbicides are
taken from feasibility report of the project area.
Labor required adopted from local information;
Labor costs are 20 birr/day for the project area, obtained from local information.
Irrigation system operation and maintenance costs are difficult to estimate.
However, the estimation has been taken from previously done projects (i.e. 100
Birr/ha).
Overhead cost is usually taken as a certain percentage of the total cost. For this
project 10% of the total cost is adopted.
table 2. 2 Optimization Techniques
Types of Yield Price Selling Input Labor Labor Tillage Total Over Profit
crops Qui/ha per Birr/ha cost red’s cost O&M cost cost head Birr/ha
Qui Birr/ha man- Birr/ha Costs Birr/ha Birr/ha cost
day/ha Birr
Potato 210 400 84000 1500 100 2000 100 250 3850 385 79765
Maize 75 500 37500 4000 90 1800 100 400 6300 630 30570
Tomato 400 500 20000 2000 100 2000 100 300 4400 440 15160
Barely 85 500 42500 900 45 900 100 450 2350 235 39915
Pepper 225 600 13500 2000 100 2000 100 280 4380 438 8682
Season one crops are potato, maize Tomato, barely and pepper. For the second season
these crops use too. By considering the most staple food for the local people, profitability of
the crops and water requirements of the crops, take 100% of total area which is irrigated
by surface irrigation method.
Let X1 = amount of hectares of land for potato
X2 = amount of hectares of land for maize
Water Resources And Irrigation Engineering Final Year Project 2011 Page 11
Canal Network Design on Ribb Irrigation Project
Constraint functions
Water Resources And Irrigation Engineering Final Year Project 2011 Page 12
Canal Network Design on Ribb Irrigation Project
Water Resources And Irrigation Engineering Final Year Project 2011 Page 13
Canal Network Design on Ribb Irrigation Project
standard value for Kc between location and climates. Different crops have different crop
coefficients. The changing characteristics of crop cover the growing season also affect the
crop coefficient, Kc. The following are factors affecting crop coefficient.
Crop type
Climate
Soil evaporation
Crop growth stage
Water Resources And Irrigation Engineering Final Year Project 2011 Page 14
Canal Network Design on Ribb Irrigation Project
Since we use similar crop for season 2 we have the same Kc value
But the values for Kc(initial), Kc (mid) and Kc (end) in the above table represents those for
sub humid climate with an average day time minimum relative humidity (RH min) of about
44%.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 15
Canal Network Design on Ribb Irrigation Project
Water Resources And Irrigation Engineering Final Year Project 2011 Page 16
Canal Network Design on Ribb Irrigation Project
Water Resources And Irrigation Engineering Final Year Project 2011 Page 17
Canal Network Design on Ribb Irrigation Project
On the other hand, if the plant is receiving some of its water from other sources such as
rainfall, stored water in the soil, or underground seepage, the irrigation requirement may
be considerably less than the water requirement.
This is the ratio of water directly available to crop and that received at the field inlet.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 18
Canal Network Design on Ribb Irrigation Project
This is the ratio between water received at the field in let and that received at the inlet of
the blocks of the fields
This is the ratio between water received at the inlet to the block of fields and that released
at the project headwork
Project Efficiency:
It indicates the overall efficiency of the system from the head work to the finall use by
plants for consumptive use.
EP= Ea*Eb*Ec
The values of Ea,Eb&Ec are recommended for different conditions as shown below
Water Resources And Irrigation Engineering Final Year Project 2011 Page 19
Canal Network Design on Ribb Irrigation Project
Ea = 0.7 & Eb=0.8 for unlined and Eb=0.9 for lined Ec=0.8
Water Resources And Irrigation Engineering Final Year Project 2011 Page 20
Canal Network Design on Ribb Irrigation Project
Season one=
Season two=
Season one=
Season two =
Scheduling is affected also by soil characteristics because different soils have different
water holding capacities. The soil moisture is not allowed to be depleted up to the wilting
Water Resources And Irrigation Engineering Final Year Project 2011 Page 21
Canal Network Design on Ribb Irrigation Project
point, as it would result inconsiderable fall in crop yield. In other words, the total available
water (i.e. water held in the soil b/n field capacity and permanent wilting point) is not
readily available for plant use but only a certain fraction of it.
RAM= (FC-PWP)*P=290mm/m*60=174mm/meter
P – depletion factor, %
FC-PWP – the total available water, mm/m (taken from cropwatt8 version)
Irrigation should be supplied as soon as the moisture falls up to optimum level known as
MAD or moment allowable deficit (hence, fixing irrigation frequency) and its quantity
should be just sufficient to bring the soil moisture up to field capacity (hence, fixing
irrigation depth).
Depth of irrigation applied (d) is equal to the readily available soil water times the root
depth (D). An application efficiency (Ea.) is always added to account for uneven application
over the field.
d= D * (FC - PWP) * P
Water Resources And Irrigation Engineering Final Year Project 2011 Page 22
Canal Network Design on Ribb Irrigation Project
Water Resources And Irrigation Engineering Final Year Project 2011 Page 23
Canal Network Design on Ribb Irrigation Project
The peak net scheme irrigation requirement has been found to be 0.39l/s/ha from crop
watt. The total irrigable land of area was fixed as 1000ha during the feasibility study of the
project. The design discharge in the main canal is calculated as follows.
As Ea has already have been considered in the calculation of net irrigation requirement in
the cropwat8 computer package, only the values of Ec and Eb are taken for design
discharge calculation. The crop watt computer package considers Ea of 70% in computing
net irrigation requirement. Thus,
`Ep=Eb*Ec
For lined………………….0.9*0.8=0.72
For unlined………………0.8*0.8=0.64
Since the main canal is unlined, its design discharge is calculated as follows.
Since the irrigation water is not applied for 24hr, it needs to multiply the design discharge
by the working time factor, adopting 16hours of irrigation, the design discharge becomes,
Design discharge
Water Resources And Irrigation Engineering Final Year Project 2011 Page 24
Canal Network Design on Ribb Irrigation Project
The minimum irrigation interval is 20 day. The irrigable land is divided in to 5 blocks.
Each block covers 200ha of land.
dnet for the crop which have minimum irrigation interval is 104.4mm.
From this volume the time of irrigation for each block is calculated as follows.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 25
Canal Network Design on Ribb Irrigation Project
Each block irrigate for 4 day and one day for operation and maintenance for the system.
The irrigation return to the first 200ha block is after 20day; so water stress is not formed in
the soil.
CHAPTER THREE
3.1 General
Irrigation scheme which utilize weir, a barrage or a storage reservoir necessitates the construction
of network of canals. The entire system of canals (main and branches) distributed over the field are
to be designed properly for certain realistic value of maximum discharge, that must pass through
them so as to provide sufficient irrigation water to the command area; the success of the flow
irrigation depends on the perfect design of the network of canals
The design of canals is carried out in considerations of Kennedy’s and Lacey’s theory which are
based on the characteristics of sediment load i.e. (silt) in canal water.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 26
Canal Network Design on Ribb Irrigation Project
The design consideration of irrigation canals naturally varies according to the type of soil, again the
velocity of flow in the canal should be critical (i.e., none silting and scouring).
The alignment should not pass through the valuable lands, religious places, villages, etc. to
avoid unnecessary compensation and unwanted conflict.
The alignment should be short as far as possible, but to make it short the alignment should
not be taken through the area where irrigation is not yet all possible.
The alignment should be straight as far as possible.
The alignment should cross the natural stream, drainage, etc approximately at the right
angles. At the crossing point, the width of the drainage should be minimum and the banks
should be well defined.
The alignment should not involve heavy cutting or banking.
The alignment along the ridge line or water shade line is very good as the water shed canal
can irrigate the area on both the side. Moreover, cross drainage work may be avoided.
The alignment should be such that the maximum area may be irrigated with minimum
length of the canal.
The alignment should not pass through the water logged area because the canal may be
collapsed due to the heavy moisture in the area.
The alignment should not pass through the sandy soil as the percolation in the loss soil will
be more and the duty of the soil will be less.
The average slope of a main canal is flatter than the average slope of a branch canals.
Having the above considerations the proper canal alignments have been made for the given
topographical map.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 27
Canal Network Design on Ribb Irrigation Project
The main canal starts from the weir site and divided in to five secondary canals and then each
secondary canal divide in to five tertiary canals depending on topography of the irrigable area. All
field canals are supplied by branched canals; which are generally governed by the orientation and
direction of field, and the method of irrigation.
Divide the command area in to suitable size for layout and management
Convey water in efficient way to each tertiary canal perpendicularly
To cover all suitable command area even in hills
Minimum length of canals
Minimum number of falls, cross drainage structures.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 28
Canal Network Design on Ribb Irrigation Project
By using the above considerations, the tertiary canal layout is best to be across contour. It has the
advantage of irrigating both sides of the canal. Thus, the number of tertiary canals decreases per
unit area of land. And by using contour field canals, the minimum slope and enough length of
furrow is assigned. The tertiary canals have fall in each stripe of cultivatable area. However, the
design of fall is small and economical than fall exist in secondary and main canal.
The alignment of tertiary canals as discussed in the above paragraphs is aligned across contour, to
irrigate both sides. To minimize the number of canal density in the cultivated area, the length of
tertiary canals is the maximum length.
The length of furrow and topography of land govern the space between tertiary canals. According to
FAO, the maximum allowable length of furrow for loam and loam soil is 300m.
3.3.1 General
To take away water from the canal headwork such as weir, barrage, storage reservoir or storage
dam to the field; a well-designed distribution consisting of a network of canals is required.
Based on the water requirements of crops on the area to be irrigated, the entire system of main
canal, secondary canal, tertiary canal and field distributaries should be designed properly. The
canals are designed for a certain realistic value of peak discharge that must pass through them, to
provide sufficient irrigation water to the command area. Therefore, the design of canal is based on
the irrigation water requirement and irrigable area. Depending upon the soil type in Ribb irrigation
project unlined canal was recommended.
Design parameters
Duty: - Duty is the capacity of water to irrigate the land. It is the ratio of the area of the land to be
irrigated to the quantity of water required. The field water supply of the project estimated by using
“cropWat8 ”. The duty of canal is 0.39l/s/ha.
Time factor:-Time factor is the ratio of the number of days the canal actually runs during a
watering period to the total number of days of the watering. Take 16hr working time out of the 24
hr. of the day and the rest 8hr. used for to drain the irrigable land and other purposes.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 29
Canal Network Design on Ribb Irrigation Project
Slope: - Slope is fixed by the design discharge and silt factor or velocity. A steeper slope with
maximum permissible velocity will be more economical, but the FSL will be lower. Additionally the
design slop is flatter than the natural available slope. Fall is provided to adjust the slope, but the
number of falls must be of minimum.
The slope to be given to the sides depends on the angle of the internal friction for a particular
soil .in other word the slope adopted should also be remembered that the side slopes adopted in
cutting and filling are not the same.
Cutting Embankment
Compact clay 1 : 1 1 .5 : 1
soil
Water Resources And Irrigation Engineering Final Year Project 2011 Page 30
Canal Network Design on Ribb Irrigation Project
Longitudinal slope
Canal bed slope depends up on the slope of the natural ground for economy in the earth work, and
for structural safety it depends on the permissible velocity.
Roughness Coefficient
The roughness of the canal bed affects the velocity of the flow. The roughness is caused due to the
ripple s formed on the bed of the canal. So the roughness coefficient was introduced by the R.G
Kennedy to calculate the mean velocity flow.
Design discharge
Water Resources And Irrigation Engineering Final Year Project 2011 Page 31
Canal Network Design on Ribb Irrigation Project
Discharge capacity of canal is fixed by considering the irrigation area, duty, application or working
time, and efficiency of conveyance and application. The design capacity of main canal is to irrigate
200ha at time, by assuming rotational water application by dividing the total irrigable area in to five
roots (blocks).
Qd=0.12*0.183m3/s=0.205m3/s
Permissible velocity
Permissible velocity is the one which can be resisted by the canal boundary surfaces. This velocity
is taken depending on the soil type. The velocity of design canal should be self-cleaning; in other
word, it should not deposit silt on canal, and should not also scour the bed and sides of the canal.
The maximum value of mean velocity must be safe against erosion. Based on soil type that is found
in the irrigable area.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 32
Canal Network Design on Ribb Irrigation Project
[Arora 2003]
The maximum value of mean velocity must be safe against erosion. Based on soil type that is found
in the irrigable area i.e. loam clay or loam soil the permissible velocity lies from 0.38m/s to
1.37m/s.
B=1.011D
0.5125=2.511 D=0.45m
B=1.011*0.45=0.46m
Water Resources And Irrigation Engineering Final Year Project 2011 Page 33
Canal Network Design on Ribb Irrigation Project
S=0.000635=
Take approximately S
Water Resources And Irrigation Engineering Final Year Project 2011 Page 34
Canal Network Design on Ribb Irrigation Project
Water Resources And Irrigation Engineering Final Year Project 2011 Page 35
Canal Network Design on Ribb Irrigation Project
B=0.575D
0.108=2.075
D=0.23m
B=0.575D =0.575*0.23=0.13m
S=0.00162=
Water Resources And Irrigation Engineering Final Year Project 2011 Page 36
Canal Network Design on Ribb Irrigation Project
Take approximately S
Water Resources And Irrigation Engineering Final Year Project 2011 Page 37
Canal Network Design on Ribb Irrigation Project
The main access road may be laid parallel to the primary canal starting from the diversion weir site
up to the end of the irrigation command area; this access road will have sub base and gravel
surfacing
These access roads are close to each plots of area which are parallel to all secondary and tertiary
canals.
Generally
Inspection road is used for the purpose of inspection, repair and maintenance of canal; in addition,
it is also used for community transport facility. The Inspection road is provided at 0.5m higher than
the FSL of canal. It has been constructed by compacting and filling the excavated soil of the canal.
3.5.1 Culverts
Culverts are the structures constructed at the crossing of roads, drainages & irrigation canals.
Making the water flow freely .It consists of a barrel which can be circular or rectangular on entrance
and exit flow in culverts can be either free flow (open channel) or pipe flow (pressure flow).
Whenever road has to cross on existing drain or canal or some times when a drain has to cross an
existing road small bridge, culvert is constructed at the point of crossing .
Water Resources And Irrigation Engineering Final Year Project 2011 Page 38
Canal Network Design on Ribb Irrigation Project
The difference in elevation between the u/s culvert, the inlet and d/s out let is equal to the friction
head loss through the pipe.
hf = L*S2
Where L= 6m culvert length which is equal to main access road, width, adopted standard width of
gravel road for all main national standard (RR30)
Design Procedure
Depth d2=0.45
, A=b2*d2=0.46*0.45=0.207m2
V2=0.20/0.207=0.97m/s
V22 0.97 2
Velocity head in the culvert,hv2= 0.048m
2 g 19.62
Wetted perimeter, P2=b2+2d2=0.46+2(0.45) =1.36m
A 0.45 * 0.46
Hydraulic mean radius, R= 0.152m
P2 1.36
Longitudinal bed slop,s
For uniform slope is the same as energy slope
n * V2 2 0.014 * 0.97 2
Bed slope in culvert, S 2 ( 2/3
) ( ) 0.0023
R 0.152 2 / 3
Water Resources And Irrigation Engineering Final Year Project 2011 Page 39
Canal Network Design on Ribb Irrigation Project
The difference in elevation between the u/s culvert, the inlet and d/s out let is equal to the friction
head loss through the pipe.
hf = L*S2
Where L= 6m culvert length which is equal to main access road, width, adopted standard width of
gravel road for all main national standard
hf = 6*0.0023m=0.0138
V22 _ V12
Drop of water surface at the inlet of the culvert h1 1.5( )
2g
0.97 2 0.4 2
h1 1.5( ) 0.059
2 * 9.81
c) Elevation
Water Resources And Irrigation Engineering Final Year Project 2011 Page 40
Canal Network Design on Ribb Irrigation Project
HT = 0.5∆hv+hf+0.7∆h +hf=
e) Check water surface elevation difference between u/s & d/s canals,
HT =1793.15-1793.09 =0.06m ok
Canal drop is a structure Constructed on a channel to lower down the water level and the bed level
of the channel. Because of the drop of the water at the fall, the potential energy of the water is
converted in to the kinetic energy, which may damage the D/S portion of the canal by scouring
action.
The canal fall is therefore designed to dissipate the surplus energy. [Arora, 2002]
For this project, a rectangular weir with raised crest from the category of vertical drop has been
adopted.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 41
Canal Network Design on Ribb Irrigation Project
H 1/ 6
Q 1.835L( H ) 3 / 2 * ( )
B
H 1/ 6
0.205 1.835 * 0.46( H ) 3 / 2 * ( ) → H = 0.36m
0.2
Height of crest above D/S bed, d= crest level - D/S bed level = 1792.79-1791.7=1.09m
Bottom width, m
Where G = 2.24m
2) Cistern
Water Resources And Irrigation Engineering Final Year Project 2011 Page 42
Canal Network Design on Ribb Irrigation Project
1/ 2 1/ 2
The length of cistern, LC 5 * ( H H L ) 5 * (0.364 1.0) 5.84m
Hs= 1792.79-1791.7=1.09m
L= 8*1.09=8.72m
D1 0.45
Depth of U/S cut off = 0 .6 0.6 0.75
3 3
D2 0.45
Depth of D/S cut off = 0 .6 0.6 0.825
2 2
Ld=2(d2+L2)+HL=2(0.45+0.825)+1=3.05m
Water Resources And Irrigation Engineering Final Year Project 2011 Page 43
Canal Network Design on Ribb Irrigation Project
Hr 3.45
Thickness of the floor 2.79
G 1 1.24
Hr 0.375
Thickness of the floor, 0.302m
G 1 1.24
Water Resources And Irrigation Engineering Final Year Project 2011 Page 44
Canal Network Design on Ribb Irrigation Project
It provided just downstream of weir structure to remove sediments and flushed back to the natural
drainage through the settling sluice (gated structure).
The size of a basin depends on discharge and velocity. Flow velocity in the basin should is 0.38m.
The deposited sediment in the basin will be disposed off natural drainage.
V = 1/n*R2/3S1/2
For simplicity of construction in Ribb Irrigation Project rectangular silting basin is selected
S – Longitudinal slope of the basin (1/1500 from wood’s table based on discharge and
topography)
0.4m/s=1/0.016* (1.011d2/1.011d+2d)2/3*(1/1500)1/2
Water Resources And Irrigation Engineering Final Year Project 2011 Page 45
Canal Network Design on Ribb Irrigation Project
d = 0.51m take d =1m because it should be greater than the depth of the main canal to accumulate
the flow discharge.
· Semi modular out lets or flexible out lets is selected for the project because of its
discharge depend only on the water surface level .
Water Resources And Irrigation Engineering Final Year Project 2011 Page 46
Canal Network Design on Ribb Irrigation Project
Data input:
Qd= 0.041m3/s
Assume h = 0.5m
= 0.62*a*(2*9.81*0.5)1/2 =0.041
The design of out let have the same procedure as that of tertiary canal calculated
Sample calculation
Water Resources And Irrigation Engineering Final Year Project 2011 Page 47
Canal Network Design on Ribb Irrigation Project
3
Q C * L * H 2
Assuming that
-equal coefficient of discharge and sill height for the divide canal
Water Resources And Irrigation Engineering Final Year Project 2011 Page 48
Canal Network Design on Ribb Irrigation Project
H = 0.40m
Q 0.205
L1 = 3 = 3
= 0.45m
1.79 * 0.40
2
CH 2
L2 Q1 Q1
= => L2 = L1
L Q2 Q2
0.205
= 0.45 * = 0.45m
0.205
B b 2 * mD
B= 1.81m
Q = 0.205m3/s
B = 0.46m
M = 1.5:1
D = 0.45m
Water Resources And Irrigation Engineering Final Year Project 2011 Page 49
Canal Network Design on Ribb Irrigation Project
H = 0.30m
Q 0.205
L1 = 3 = 3 = 0.45m
C*H 2
1.79 * 0.40 2
L2 Q1 Q
L1 1
L1 Q Q2 = 0.45m.
= 2 => L2 =
B b 2 * mD
All other division boxes at the inlet of tertiary canals are designed in the same way and size.
There are 25 total number of division boxes on secondary canals.
Note: In our case, to regulate the discharge, manually operating gates called vertical gate
made up of steel are installed at openings of L1 and L2 designed for division box
The primary canal cross the river along its path at chain age of 0+900 and its design is shown below
and the design data are taken from previous work.
Water Resources And Irrigation Engineering Final Year Project 2011 Page 50
Since the bed level of the canal is below the river bed level and the full supply level of the canal is
sufficiently below the bed level of the drainage bed level, hence the cross drainage work to be
constructed at the crossing will be a super passage. The design of super passage is to be done as
follow.
V=Q/A=0.205/0.5125=0.5m/s these show that the velocity is low which does not create further
erosion so that it can be earthen canal but to be economical we have to provide splay on the canal.
Providing a splay of 2:1 contraction on the upstream side, the length of contraction transition
= (0.46-0.3)/2*2=0.16m
Providing a splay of 3:1 on the downstream expansion the length of expansion transition
=(0.46-0.3)/2*3=0.225m
Length of flumed rectangular section of canal will be equal to the width of the drainage through as
worked out in the next step.
The length of drainage waterway should be determined by lacey’s equation, but the discharge of the
drain is not known and its width from the contour map to be 1.5m, providing piers having
thickness 0.5m on both side of the canal. Thus the length of rectangular portion of canal will be
2.5m.
Since the drainage has also been slightly flumed and kept lesser than its previous width, so let us
design its contraction and expansion length.
=1.5-1/2*2=0.5m
=1.5-1/2*3=0.75m
figure 3. 6 Indicative plan of super passage crossing
a)Contraction transition
Bn.Bf .Lf
Bx = where Bf=1m
Lf .Bn X ( Bn Bf )
Bn=1.5m
Lf=0.5m
0.75
Bx=width at any distance from the flumed section=
0.75 0.5 x
For various value of x between 0 to 0.5m, values of b are worked as shown below
X 0 0.1 0.2 0.3 0.4 0.5
A) Expansion transition
Bn.Bf .Lf
Bx = where Bf=1m Bn=1.5m and Lf=0.75m
Lf .Bn X ( Bn Bf )
1.125
Bx=width at any distance from the flumed section=
1.125 0.5 x
For various value of x between 0 to 0.5m, values of b are worked as shown below
figure 3. 7 Aqueduct
Use C-30MPa & =9.81KN/m3
to control cracks
T (wall) = 200mm
Provide vertical bar at 200mm c/c placed on water inner face of wall
1st trial
T (wall) = 200mm
KN/m2
Net moment developed at the center of the slab (l=2.5m and h=0.75m)
Check thickness of slab for flexure
Then effective depth of slab assuming bars and 40mm clear cover
Therefore provide 2 bars in two layers placed at the bottom of the wall.
CHAPTER FOUR
4.1 General
The term surface irrigation refers to water application methods in which the soil surface conveys
and distributes water over the irrigated field, and into the soil within usable range of the roots of
the growing plant. It is the oldest and still the most widely used method of water application to
agricultural land. The scientific approach of irrigation in recent years is water control, to make the
best use of both water, labor, and avoid the hazards of water logging and salinity. Most commonly,
surface irrigation methods applied in the forms of:
* Wild flooding
* Basin irrigation
* Border irrigation
* Furrow irrigation
However, where high value cash crops are to be grown there may be economic justification for
considering other types of irrigation especially where conditions are not ideal (or costly
amendments are required) for surface irrigation.
Some of the limiting conditions to determine the choice of surface irrigation systems are:
-type of crop
-level of technology
-previous experiences with irrigation
In case of Ribb irrigation project most of the crops selected are row crops, which can be irrigated by
furrow systems. The other conditions are also, almost favorable for furrow irrigation method to be
employed. Therefore, furrow irrigation system, is selected for this particular project.
As the area wetted some percentage of the cropped area of the field, puddling and
crusting of the soil, is minimum, and men and machines can work in the field sooner
after the end of water application.
Loss of water due to deep percolation and evaporation (due to the lesser open water
surface) is restricted.
Furrows do not put hindrance in use of field machinery or other farming methods.
In this method plants in there early tender age are not damaged by flow of water.
By laying the furrows along the contours, across the slope of land, soil erosion
minimization is possible.
Furrow making is a simple and cheap method and working expenses are minimal.
Land between the rows of plants is utilized to construct furrows; therefore, useful
irrigable land is not wasted.
Maximum allowable flow velocity (Vmax):-non-erosive flow velocity, to estimate the non-
erosive flow rate, Qmax.
Manning’s roughness coefficient (n):-It is the measure of the resistance effects, which flow
might encounter, as it moves down the furrow. Generally, for furrow irrigation system
design, n is taken as 0.04.
Channel bed slope (So):-It is the average slope in the direction of irrigation (furrow slope).
Unit inlet flow rate (Qo):- this is the discharge diverted into a furrow.
Cut-off time (Tco):- It is the time at which the supply is turned- off, measured from the onset
of irrigation. The most important effect of cut-off is reflected on the amount of losses, deep
percolation and surface runoff, and hence adequacy and efficiency of irrigation.
Maize 75 x 30
Potato 80 x 30
Tomato 150 x 20
Pepper 60 x 40
Onion 60 x 40
(Michael, 1994)
table 4. 2 Furrow infiltration and inflow rate
Soil texture Infiltration rate Furrow inflow
-------------------------------------------meters------------------------------------------
In the case of Rib irrigation area the most of the soils are silt loam soils.
Based on the slope and soil type, furrow length is considered equal to 300m.
P = 0.265 + 0.227
Ta =
Cut of time (Tco):Tco reflects an irrigation management decision made by the former and
designer. It should be an adequate length of time to infiltrate a satisfactory depth of water over the
length of the furrow without causing excessive deep percolation.
Tco = Ta+Tn-Tr, min
Where Tr is recession time is assumed zero for open–ended gradient furrow (i.e. for
furrows whose slope is not equal to zero) without loss of accuracy.
Therefore Tco = Ta + Tn
The average infiltration opportunity time
Toavg = Tco -
Where =
Ed = * 100 (>50%)
If the value of distribution efficiency is less than the standard specification value, cut-back condition
is necessary to minimize the deep percolation of the water .In this condition some formulas are
modified.
Cut back stream Q2: means flow after the water reaches the lower end of furrow; the
stream is reduced or cut back. Cut back stream size is equal to half initial stream flow
Q2 = = = 0.6l/s
P2 = 0.265* + 0.277
Tn =
Time of cut back Tcb, is the time of advance at full flow, Tcb = Ta
Tavg= ; Where =
Ig = [Q1(Ta) + Q2(Tn)]
Ed =
table 4. 4 Intake and advance coefficients for furrow intake family equation
Soil type Intake family
Coarse sandy 2
Fine sandy 2
table 4. 5 Kostiakov-Lewis intake family number
Intake family A B C F g*10-4
Design parameter
Sample calculation for potato
Intake families IF: 0.60(silt loam soil)
Ta =
P1 = 0.265( +0.227
= 0.265 +0.227
= 0.452m
Net infiltration time, Tn
Tn
= 649.2min
Cut off time, Tco
Tco = Ta + Tn = 102.0+649.2 = 751.2min
The average infiltration opportunity time
Tavg= Tco- ;
gx / Q2 s 0.5 = =1.02
dg = = = 225.36mm
The distribution pattern efficiency is less than 50%, therefore we use cut back condition.
Cut back stream, Q2
Q2 = = = 0.6l/s
Reduced inflow perimeter
P2 = 0.265 + 0.227
Tn =
Tn = =1040.12min
Tavg = =79.48min
davg = 106.06+7.543=113.603mm
Gross application depth
=186.62mm
Surface run off dro = dg -davg= 186.62-113.603 =73.015mm
Deep percolation depthddp= davg –dn= 113.603- 104.4 =9.203mm
Furrows are aligned along the contour, slightly decreasing in elevation; and supplied from a head
ditch (tertiary canal). A tail ditch at the end of the run collects water for re-use or disposal at the
lower levels. The old practice of breaching canal banks to release water from the head tertiary canal
should be avoided in a modern irrigation system. The canal banks are scarred and likely to leak
after the breach has been closed, and there is no control or measure of the flow on to the field.
Instead, plastic or aluminum siphon tubes are used, which are light, simple to use, give a control
flow, and preserve the canal bank.
4.5 Design of siphon tubes
Siphons of plastic tubing are used in field irrigation to transfer water from the tertiary canal to the
head of a furrow at a known rate. The siphon is particularly useful in irrigation work as a simple
and robust device for discharging at known rate from a farm channel onto a field. The design of
siphon tubes is a simple task, provided that, the maximum discharge required by a furrow is
known.
Flow through a siphon is a function of the difference in water level between its ends, i.e. hydraulic
gradient line (slope). Assuming that the minimum head difference between its ends is equal to the
furrow slope, the maximum size of the siphon tube can be determined.
2 1
A
Q = *R3 *S 2
n
3
Where: Q = maximum stream size of furrow, =1.20 l s = .0012 m s
D 2
A = cross sectional area of the siphon tube, =
4
D 2
A D
R = hydraulic radius of the siphon tube, = = 4 =
P 4
D
n = roughness coefficient of the siphon tube; it is equal to 0.008 for the smoothest plastic
pipe
D = 0.05491m = 54.91 mm 80 mm
Comparing this with the standard products of plastic tubes, an appropriate 80mm diameter of
siphon tubes will be selected.
CHAPTER FIVE
5.1 General
Drainage is the term applied to systems for dealing with excess water that describe all the
processes where by surplus water is removed from the land. It includes both internal drainage of
soil and the collection and dispersal of surface runoff.
By its nature, irrigation creates periodically saturation condition of upper layers of soil formation
over a long period where intensive irrigation is practiced; even deep soil layers tend to become
saturated and consequently underground water table rises in absence of adequate drainage
facilities. The knowledge of drainage engineering is very essential to solve this problem.
Water logged land is of little use; however, it can be utilized after providing proper drainage
arrangement. Usually in undulating country, the surface slopes are sufficient to carry off this
surplus water into the ditches and stream without any engineering construction. Low lying flat
areas are usually invariably near or below the flood level of the river. In order to prevent the area
from flooding the river must be trained; it is usually done by constructing of embankments. Like
this, we must construct drainage canal in order to prevent the irrigation canal from silting.
When all this space is filled with water, the soil is termed as saturated. A soil can only remain in a
saturated condition, if it is below water table and cannot drain truly. It may be temporarily
saturated during and immediately after irrigation or heavy rainfall. Saturation capacity is maximum
amount of water or moisture that a soil can hold at saturation, it depends on the volume of its pore
space.
In order for plant to grow, apart from availability of water, air also is needed, and hence soil should
be permanently saturated with water. A good soil, therefore, has internal drainage characteristic,
which means water must be able to move fairly and easily through the soil, that excess water can
remove when required.
So far irrigated lands are concerned the following benefits may be achieved from adequate drainage
scheme.
Those are:
-Collection systems
-conveying systems
-Outlet system
Water from the individual field is collected and is then removed through a system to the outlet.
Generally, surface drainage is required for-
1. The removal of storm rainfall where the subsurface drainage is not economically feasible
However, here in our case we have recommended to use the surface drainage system because of the
fact that our project is small scale and low cost of installation.
Firstly, alignment should follow a natural drainage line that is the lowest contouring in the valley.
To reduce the cost of drainage scheme the drain should have minimum length. It can be achieved by
taking alignment straight rather than zigzag.
Secondly, alignment of drain should not pass through ponds or marshes. The reason is that such
drain may act as feeder line to the marsh and the pond will go on expanding. The solution to the
situation is to align the drain clear off the pond.
Thirdly, so far as possible drains should not cross irrigation canals. The reason is that some
expensive structures will have to be constructed at the crossing point. It increases the cost of
drainage scheme.
5.5 Design of surface drainage
When we design surface drainage for a given irrigable command area, the following parameters are
to be considered.
Capacity of drainage
Longitudinal slope of the drain is given by the general slope of natural ground; of course slope
should be fixed in correlation to the permissible velocity. An efficient drain is one, which is so
designed as not to produce velocity, which may induce either silting or scouring. Economy and
efficiency should be the main considerations in designing drainage systems. Generally, the bed
slope is determined from Top map of the irrigable area.
From the top map of Ribb irrigation project, the following result is found.
The drainage coefficient is the amount of water that must be removed from soil surface in order to
have sustainable agriculture. It depends, on depth of irrigations, method of irrigation, leaching
requirement and soil characteristics. There are different methods for estimating drainage
coefficient. Those are:
#2 Hudson (1983)’s method; In this method the following two conditions are considered
If MAR <1000 mm, DC = 10 mm/day
#3 Muzumdor methods; In this method, the following table is provided for estimation of drainage
coefficient from MAR.
From the above three methods the value of the drainage coefficient (Dc) for the maximum one is
taken for design of the drainage canal. DC = 12mm/day
= 0.758m
= 0.068m2
= 0.090m
S = 1/300 = 0.0033
V= 1.213m/s
The top of canal banks has to be maintained higher than the level to allow for waves and possible
fluctuation in supply. The vertical distance between the top of drainage canal banks and the full
supply level of drainage canal, known as free board. For this case, take a free board of 0.1m.
B = 0.109m
D = 0.18m
Where = 33.69o
For m =1.5m
B= 0.18m
= 1.26m
= 0.189m2
= 0.15m
Available data
Where = 33.69o
For m =1.5m
B= 0.333m
= 2.316m
= 0.637m2
= 0.275m
S = 1/1000 = 0.001
-Side slope, m = 1.5
-Manning roughness coefficient, n= 0.025
V= 0.540m/s
For m =1.5m
B= 0.424m
= 2.948m
= 1.032m2
= 0.35m
ECONOMIC ANALYSIS
6.1 General
Economic analysis is helpful to know the schemes cost to the farmers (beneficiaries) and how it will
be interpreted in terms of the farm products. It is also helpful for selecting alternative design and
construction materials.
A project is economically feasible if the benefit, which results from the project, exceeds the total
cost spent to implement the project.
2.1 Drops
Concrete m3 0.2006 2728 547.24
Reinforced bar
Reasonably assuming the annual operation and maintenance cost of the project to be 10% of the
annual cost (A),
The Operation and Maintenance cost (Mn) = 0.1* A=54508.37Birr/year
Using the modified benefit cost ratio method
Where:
Bn- net capital saving
Mn- net Operation and Maintenance cost
Cn- capital cost of replacing the present facility with the future facility.
B/C - benefit cost ratio
The result of the above equation of benefit cost ratio is
B/C=13.36>1.0
Hence the project is feasible!
CHAPTER SEVEN
7.1 General
The environment is composed of various systems comprising of physical, biological and socio-
economic sub systems, which are subjected to construction of development works, like water
resource development projects. These changes may shape the environment for the better or worse
condition. It necessitates that they should be analyzed in the design of the project. Environmental
impact assessment is therefore a systematic structured, identification, prediction and evaluation of
the environmental consequences of proposed actions.
The impact of the proposed action will be identified by using the existing environment as a control.
A change in the environment is the difference in the environment between the control, the existing
environment and the new environment, the altered condition caused by a project. How good or
adverse the condition, is depend on what happened to the environment after the change has taken
places.
EIA is a set of activities under taken to ensure that a development project not only brings out the
intended economic development but also mitigates the likely negative environmental impacts of
implementing such projects.
CHAPTER EIGHT
8.1 Conclusion
Based on the study and the results obtained from the Ribb irrigation project in the area no more
drought. The climatic condition indicates in the area there is binomial rainfall; the annual rainfall is
about 1024.9mm. Even though this rainfall is fairly enough for crop growth; but from the
background of the project area and living standard of the people irrigation project is required, to
harvest more than one in a year.
As we see from different background of field history, it can be concluded that the majority of the
soil and its topography is suitable for the production of crops such as potato, maize, tomato, barely,
pepper and other edible fruits.
The result of cropwatt shows extra water is required for additional production.
For safe design we have to use dependable ERF because it is the smallest of all other ERF
calculation method which enables us to design our canal for the worst condition.
From topographical nature of command area, suitable canal alignment was done and
trapezoidal unlined canal section is selected based on soil criteria. The design of the cross section
of the canal fixed by using Kennedy theory. And also different components of canal structures such
as culverts, drops, diversion box.
For supplying faire amount of water to the command area, surface irrigation method i.e. furrow
irrigation is designed appropriate.
To improve existing drainage condition, internal drainage system, which remove the excess
irrigation or rainwater, is designed.
During the design of drainage system surface drainage system is preferable than the subsurface
drainage system because the subsurface drainage system is very cost than the surface drainage
system.
The cost of the project is approximately estimated by considering the dimension of the
structure and the materials used for construction of the structure. The approximant cost of the
project was estimated to be 3097087.335Birr.
Some environmental effects of the scheme, which have direct impact on the environment, have
discussed, and valuable remedial measures are provided for each effect, which have negative
impact on environment.
8.2 Recommendation
The farmers should organize for efficient use of water.
Since most of the canals are unlined, frequent maintenance or silt removal is needed that makes
the canals serve durably.
The maintenance condition, embankment condition and general performance of the main canal
should have maintained periodically.
It should have been very much nice, had the university sought some means for final year project
group to have a visit to their respective project site.
Since no information is given about irrigation water quality and it is just assumed that the
available water is good for irrigation apart from erosion during rainy season due to steeping slope
of land of command area. These results rapid silting up of canals which nesses sits soil conservation
activities.
Most of the beneficiaries have no enough knowledge of irrigation. Thus education and training
should be given to the farmers for adopting practice of conservative use of water on scientific line.
REFERENCES
ARORA,K.R, (2002). Irrigation, Water Power And Water Resources Engineering, Standard
Publishers, NAIA Saraf,Delhi.
FAO,(1996). Guide Lines for computing crop water requirement, Irrigation And Drainage
Project Paper 56, FAO,Roma.
Garge, S.K, (2003). Irrigation Engineering And Hydraulic Structures, 12th edition, Khanna
Publisher, New Delhi.
Michael A.M ,(1997). Irrigation Theory and Practice, (publisher)
Novac, (1996). P.Hydraulic Structures
Sahasrabudhe, J.K, Irrigation Engineering and Hydraulic Structures,1994
CropWAT 8 software version.