Storm Water Pollution Prevention
Storm Water Pollution Prevention
Pamphlet
No. 1110-1-16                                                                               28 February 1997
1. Purpose. This pamphlet provides guidance for the preparation and development of plans for the prevention
of storm water pollution at construction projects. Section 402 of the Federal Water Pollution Control Act (the
Clean Water Act) requires that such plans be made.
2. Applicability. This pamphlet applies to HQUSACE elements and USACE commands having civil works and
military construction responsibilities.
3. Discussion. In 1972, the CWA was amended to provide that the discharge of pollutants to waters of the United
States from any point source is prohibited unless the discharge is in compliance with a National Pollutant
Discharge Elimination System (NPDES) permit. In 1987, amendments to the CWA were added as Section 402(p)
which established a fi-amework for regulating municipal and industrial discharges of storm water under the
NPDES. Regulations that established NPDES application requirements for these discharges were promulgated
by the U.S. Environmental Protection Agency (EPA). In 1992, additional regulations broadened the classification
for industrial discharges to include discharges associated with construction activities. EPA defined construction
activities tQ include clearing, grading, or excavation that results in the disturbance of at least 5 acres of total land
area. EPA regulations require that such activities disturbing 5 acres or more be regulated as an industrial activity
and be covered by an NPDES permit. Constmction activity on sites of less than 5 acres require an NPDES permit
if the construction is part of a larger common plan of development or sale. Future revisions to the regulations are
expected to require NPDES permits for construction activities at lest acres. Already some states are requiring an
NPDES permit for construction sites less than 5 acres and for sites in environmentally sensitive areas.
4. Intent. The intent of this pamphlet is to provide the planner with guidance through the NPDES permitting
process. It is not intended to be used as a directional or operations document.
                                              w~
                                              OTIS WIL I
                                                          1
                                              Colonel, Corps
                                              Chief of Staff
                                                                    S
                                                                     *
                                                                            ●
                                                                  of Engineers
                                     DEPARTMENT OF THE ARMY                                                      EP 1110-1-16
                                     U.S. Army Corps of Engineers
CECW-EP                              Washington, DC 20314-1000
Pamphlet
No. 1110-1-16                                                                                                28 February 1997
Table of Contents
SECTION PAGE
                                                                i
SECTION                                                                                                                                                                                     PAGE
      2.7   Special Requirements — Discharges to
              Municipal Separate Storm Sewer Systems . . . . . . . . . . . . . . . . . . . . . . . 2-13
            2.7.1 Compliance With Municipal Storm
                     Water Management Programs . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-13
            2.7.2 Availability of Plans . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-14
      2.8   Special Requirements-Releases                      of Reportable Quantities                                                     . . . . . . . . . . . . 2-14
3.0   SITE DESCRIPTION            . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
      3.1   DataCollection/DataAnalysis..                  .   .    .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   ...         ..      .   .   .   .   .   3-1
            3.1.1 Topography . . . . . . . .           .   .   .    .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   ...         ..      .   .   .   .   .   3-1
            3.1.2 Drainage Patterns . . . .            .   .   .    .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   ...         ..      .   .   .   .   .   3-2
            3.1.3 Soils . . . . . . . . . . . . . .    .   .   .    .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   ...         ..      .   .   .   .   .   3-2
            3.1.4 Ground Cover . . . . . . .           .   .   .    .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   ...         ..      .   .   .   .   .   3-3
            3.1.5 Adjacent Areas . . . . . .           .   .   .    .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   ...         ..      .   .   .   .   .   3-3
            3.1.6 State/LocalRequirements                      .    .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   ...         ..      .   .   .   .   .   3-4
      3.2   Site Plan Development . . . . . . . . . . . .                       ..      .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   3-4
            3.2.1 Controlled Grading . . . . . . . . .                          ..      .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   3-5
            3.2.2 Critical Areas . . . . . . . . . . . . .                      ..      .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   3-5
            3.2.3 Cluster Development . . . . . . . .                           ..      .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   3-5
            3.2.4 Minimization of lmpetviousness.                                .      .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   3-6
            3.2.5 Utilization of Natural Drainage .                             ..      .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   .   3-6
      3.3   Storm Water Runoff Calculations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-6
            3.3.1 Calculation Method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-10
      3.4   Erosion and Sediment Control Plan . . . . . . . . . . . . . .                                                       ........                        .   .   .   .   .   .   .   3-10
            3.4.1 Technical Assistance . . . . . . . . . . . . . . . . . . . .                                                  ........                        .   .   .   .   .   .   .   3-15
            3.4.2 Limits of Disturbance . . . . . . . . . . . . . . . . . . . .                                                 ........                        .   .   .   .   .   .   .   3-16
            3.4.3 Drainage Map . . . . . . . . . . . . . . . . . . . . . . . . .                                                ........                        .   .   .   .   .   .   .   3-16
            3.4.4 Erosion and Sediment Control Best Management                                                                  Practices                       .   .   .   .   .   .   .   3-16
                   3.4.4.1 Vegetative Controls, . . . . . . . . . . . . .                                                       ........                        .   .   .   .   .   .   .   3-17
                   3.4.4.2 Structural Controls, . . . . . . . . . . . . . .                                                     ........                        .   .   .   .   .   .   .   3-18
                   3.4.4.3 Management Measures . . . . . . . . . . .                                                            ........                        .   .   .   .   .   .   .   3-19
4.0   SOURCE IDENTIFICATION.......,..                                   . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
      4.1   The Erosion Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
            4.1.1 Types of Erosion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
            4.1.2 Factors influencing Erosion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2
      4.2   Sedimentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4
            4.2.1 Sediment Pollution and Damage . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4
            4.2.2 Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-6
                                                               ii
SECTION                                                                                                                                                                               PAGE
1.0 INTRODUCTION
1.1 Pu~ose
This pamphlet provides guidance for the preparation and development of Storm Water
Pollution Prevention Plans for construction projects. The requirement for such plans is
regulated by Section 402 of the Federal Water Pollution Control Act (henceforth referred to as
the Clean Water Act or the CWA).
1.2 Applicability
The pamphlet applies to HQUSACE elements and USACE commands having civil works and
military construction responsibilities.
In 1972, the CWA was amended to provide that the discharge of pollutants to waters of the
United States from any point source is effectively prohibited unless the discharge is in
compliance with a National Pollutant Discharge Elimination System (NPDES) permit.
Amendments to the CWA in 1987 added Section 402(p) to the Act, which established a
framework for regulating municipal and industrial discharges of storm water under the NPDES.
Regulations that established NPDES application requirements for regulated municipal and
industrial storm water discharges were promulgated by the U.S. Environmental Protection
Agency (EPA) and published in the Federal Register on 16 November 1990. Additional
regulations promulgated by the EPA and published in the Federal Register on 9 September
1992 broadened the classification for industrial dischargers to include discharges associated
                                               1-1
EP 1110-1-16
28 Feb 97
with construction activities. EPA further defined construction activities to include any clearing,
grading, or excavation which results in the disturbance of at least 2 hectares (5 acres) of total
land area. The EPA regulations require that construction actwities disturbing an area of
2 hectares or more be regulated as an industrial activity and covered by an NPDES permit.
Construction activity on sites of less than 2 hectares requires a permit if the construction is
part of a larger common pIan of development or sale. Future revisions to the regulations are
expected to require NPDES permits for construction activities at substantial y less than
2 hectares. Presently, some states are requiring an NPDES permit for construction sites less
than 2 hectares and for construction sites located in environmentally sensitive areas.
According to the Federal regulations, permit coverage for storm water discharges associated
with construction activity can be obtained through individua/ permits or genera/ permits.
/ndividua/ permitting involves the submittal of specific data on a single construction project to
the appropriate permitting agency who will issue a site-specific NPDES permit for the project.
NPDES coverage under a genera/ permit involves the submittal of a notice of intent (NOI) by
the regulated construction project to comply with a genera/ permit, to be developed by the
EPA or a delegated State with general permitting authority.
The final Federal regulations (40 CFR 122.26[a][6]) require that storm water associated with
industrial activity from point sources which discharge through a nonmunicipal storm sewer
system be regulated either under a single NPDES permit issued to the system operator (the
principal permittee) with each discharger to the system listed as a copermittee to the operator,
or that each discharging entity to the nonmunicipal system obtain separate permit coverage.
The sole permitting of the nonmunicipal system is not an available option according to the
Federal regulations since the control of discharges into a private system is often beyond the
control of the system operator. The selection of one of the two available options is at the
discretion of the regulating authority.
                                               1-2
                                                                                       EP 1110-1-16
                                                                                          28 Feb 97
In terms of implementing the final regulations, the states are divided into three basic
categories: delegated NPDES states with general permitting authority; delegated NPDES
states without general permitting authority; and states without NPDES delegated authority.
Most states have moved toward implementation of the permitting process. However, not all
state programs are in place at this time. Appendix A contains a list of contacts for each state,
and readers are encouraged to contact the applicable regulatory representatives for up-to-date
information early in the permitting process.
The first step in the NPDES permitting process is the development of a Storm Water Pollution
Prevention Plan (SWPPP). The SWPPP has two major objectives: (1) to identify the source of
pollutants that affect the quality of the industrial storm water discharge; and (2) to describe
practices which shall be implemented to reduce the pollutants in the industrial storm water
discharge. The SWPPP is a requirement of the storm water discharge permit and is
considered by EPA to be a very important requirement of the NPDES permit. EPA requires
the development of a SWPPP for each construction activity covered by a general permit.
SWPPP’S shall be prepared in accordance with good engineering practices emphasizing storm
water Best Management Practices (BMP’s) and complying with Best Available Technology
Economically Achievable (BAT) and Best Conventional Pollutant Control Technology (BCT).
The SWPPP shall identify potential sources of pollution which may reasonably be expected to
affect storm water discharges associated with the construction activity. In addition, the
SWPPP shall describe and ensure the implementation of practices which are to be used to
reduce pollutants in storm water discharges associated with the construction activity and to
assure compliance with the terms and conditions of this permit. Facilities must implement the
provisions of the SWPPP required under this part as a condition of this permit.
                                                1-3
EP 1110-1-16
28 Fsb 97
compliance with EPA and other Federal and state regulations. The storm water control
measures and practices described herein should be used only when they meet or exceed all
applicable EPA or other Federal and state regulations concerning the control of hazardous or
toxic materials, erosion, sedimentation, storm water management, pollutants, and worker
safety. Any pollution prevention measures used on a construction site, but not identified
herein, should be included in the SWPPP.
Construction activities that are covered by the EPA baseline general permit (Issued
3 September 1992) must have a completed SWPPP prior to mobilization. It must
include the following:
        1.     Certifications required under Part IV.E of the general permit, prior to the
               submittal of a notice of intent (NOI) to be covered under the permit and updated
               as appropriate;
       3.      For construction activities that have begun after October 1, 1992, the SWPPP
               shall provide for compliance with the terms and schedule of the general permit
               beginning with the initiation of construction activities.
Other facilities that have filed an individual application must comply with the conditions of their
individual permit, when issued. In most states, the SWPPP is not submitted to the permitting
authority, but it must be retained onsite at the facility generating the discharge in accordance
with Pad V of the general permit. The SWPPP must be made available upon request to the
Program Director; to a state or local agency approving erosion and sediment control plans,
                                                 1-4
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
grading plans, or storm water management plans; or, in the case of discharge through a
municipal separate storm sewer system with an NPDES permit, to the municipal operator of
the system. The SWPPP must be available for review by the permit authority and the public.
The permit authority may notify the construction activity representatives if the SWPPP for the
construction activity does not meet the minimal requirements. Table 1-1 gives a brief
description of each state’s status, concerning SWPPP’S, as of October 1993.
1.6 Statement of Policy for the Storm Water Pollution Prevention Plan
The U.S. Army Corps of Engineers (COE) intends to develop and implement the SWPPP (with
the expressed cooperation of any tenants, contractors, or subcontractors (contractors)) for the
purpose of minimizing the potential for the release of sediments and toxic or hazardous
substances directly, or indirectly, to the storm drainage system. To achieve this objective, the
responsibilities of both the COE and any contractors for the facilities they individually operate
include:
           9
               Implementing the policies and procedures presented in the SWPPP.
           ●
               Conducting periodic reviews of policies and procedures to evaluate the
               effectiveness of the current SWPPP.
           ●
               Updating the SWPPP and related materials whenever there is a significant
               physical change in a construction activity or a significant change in the
               operational procedures of a construction activity that could result in the
               discharge of pollutants to the storm water drainage system, or an increased risk
               of such discharge.
                                                1-5
    L
     Table 1 -1
     Compa ‘ison of State Ger eral Permits for Industrial Storm Water Dischargers
                                                                             —
                                                  1                                 I
                           Permits
                    No. of
    E   state
    .,:,:.:,:,:.:.:.:.:.:,:,
       ...f...l......~:::
                     ....::::,:\.:
                            f.l..
    .,.,.,.,.,.,.,.,.,.,.,.,.,.:,..,.,,,,,,:,
       ...............,.,,,.,,,:,,,
                      ................
     ;~~~
     ........... .......
     ;w~
     f-g
     AL             15               mid tolate
                                     1997
AK** 1 \10/1/97”
     AZ**           1            I 10/1/97”
     AR             1            I9130197
w
&    cA             1            I1/15/97
co 5 I6/30196
CT 1 I10JU97*
DE 1 I8/6/98
FL** 1 I10/1/97”
GA 1 5/31/98
HI 1 I10/29/97
ID** 1 10/1/97”
IL 1 10/1/97”
     IN             permit           none
                    by rule
                                 1
                                                                                        (,
rable 1-1 (Continued)
                  Permits                                               SWPPPS                                            Monitoring
                                                                           Specialrqts                                                  Rep.
        No. of      Expiration          Completion       Implementation    SARA Title    Require    Submit   Monitoring     Submit      discharge
State   Permits     date         Fees   deadline         deadline          III W.P.C.    PE cert.   SWPPP    required       results     allowed
KS &afi
m draft
MO many varies Y varies varies varies varies varies varies varies varies
                                                                                                                                      (Sheet 2 of 4)
Table 1-1 (Continued)
                  Permits                                                SWPPPS                                                Monitoring
NC      12            8/3 1/93     Y      12 months after 12 months after      Y(12)          N          N*(13)   Y(14)         Y           Y(13)
                                          coverage        coverage
RI 2 Y 4/1/93” 10I1I93* Y“ Y* N* Y Y“ Y*
VA      emergency
        permits
                                                                                                                                          (Sheet 3 of 4)
Table 1-1 (Concluded)
                                                                             Sw
                                                                                                                                  Rep.
                                                               Implementation                   Submit   Monitoring   Submit      discharge
                                                               deadline                         SWPPP    required     results     allowed
                                                                                  Y*       Y*
                     I   6/7197      Y      w/in 180 &ys
                                            of coverage
                                                               w/in 365 days of
                                                               coverage
                                                                                                N*       IY
                                                                                                                      Y           Y(13)
WI      Idraft       I              II
WYl
        I                8/3 1/97
                                    IN      w/in 180 days
                                            of coverage
                                                               w/in 365 days of
                                                               coverage         +      1
                                                                                                          N           N           N
Note:
I                                                                                                                               (Sheet 4 of 4,
                                                                                    EP 1110-1-16
                                                                                      28 Feb 97
2.1 Organization
The U.S. Army Corps of Engineers (COE) has developed a comprehensive approach to
address the permitting of storm water discharges associated with construction activity. Due to
the location and complexity of COE construction-related activities, the many contractors and
subcontractors, and the number of projects related to COE operations and maintenance, the
COE has elected to assume a role as a principal permittee with contractors who conduct
construction activities at COE sites included as copermittees on the permit. Individual
construction project operators (COE, tenants, and contractors) are responsible for the
implementation of SWPPP provisions and the monitoring and reporting requirements of the
general permit.
Many of the facilities under COE jurisdiction are comprised of numerous leaseholds
and tenants which are part of a “iarger common pian of deveiopment,” (i.e., miiitary
instaiiations). For this reason, COE wiii aiso require construction projects associated
with these types of facilities which disturb iess than 2 hectares (5 acres) to be inciuded
under permit coverage and thus subject to provisions of the SWPPP. COE wiii
assembie a working iist of proposed construction projects at each faciiity, and the iist
wiii be updated semiannually and incorporated into the SWPPP. COE wiii annuaiiy
submit NOi’s to cover construction activities at these types of installations.
This pamphlet is organized to function as a user’s guide to meet SWPPP requirements. The
step-by-step guidelines and checklists in the following sections are designed to assist in the
organization of the required information. Using this information, the pianner wiil deveiop and
implement the SWPPP following the six basic phases listed below. Each phase is important
and should be completed before advancing to the next one.
                                               2-1
EP 1110-1-16
28 Feb 97
Developing an SWPPP is basically a six-phase process. The first three phases are primarily
the responsibility of the COE and any leasehold tenants planning construction activities. The
final three phases are the joint responsibility of the COE and leasehold tenants and the
construction site operators as co-permitters on a project-by-project basis. Because most
aspects of the SWPPP take a significant amount of planning, its development must be closely
connected to the development of the overall site plan for construction. Postconstruction storm
water management controls must be considered in the planning stage.
The first phase in preparing an SWPPP for a construction project is to define the
characteristics of the site and of the type of construction which will be occurring there. This
phase is divided into three tasks: (1) Data collection, (2) Data Analysis, and (3) Site Plan
Development. Section 3.0 describes these tasks in detail. The COE must address both
project design considerations and the implementation of the SWPPP during construction and
postconstruction phases of projects. Contractors will be primarily concerned with the
implementation of the SWPPP during the construction and postconstruction phases of
projects. The intent of this pamphlet is to place the various construction activities into
perspective in terms of the intent of EPA with respect to storm water control of construction
activities.
The reader should note the sections addressing special conditions, such as construction
activities located on sites containing Title Ill, Section 313, water priority chemicals listed in the
Superfund Amendments and Reauthorization Act of 1986 (SARA), and/or other priority
pollutants. It is anticipated that most of the construction activities of the COE and leasehold
                                                 2-2
                                                                                       EP 1110-1-16
                                                                                         28 Feb 97
tenants will not involve these special conditions, but some sites will—hence the inclusion of
these sections. Appendix H lists the Section 313 water priority chemicals as published in the
Federal Register on September 9, 1992. Since this list is subject to change, the designer
should review 40 CFR 122 and 40 CFR 372 for the current list of priority pollutants.
In order to ensure that the plan is completely developed and adequately implemented, the
regulations require that authorized representative(s) of the operator(s) sign and certify the
plan. Section 2.4 details this requirement. Once the planning, design, and certification are
completed, construction may commence. Section 6.0 details the requirements of
implementation, documentation, and termination.
The term planning could include the project as a whole as well as planning for the SWPPP.
Design considerations for the project as a whole will affect the development of the SWPPP.
Three tasks should be completed before developing the SWPPP document. These tasks are:
(1) designating the person(s) responsible for developing and implementing the SWPPP,
(2) reviewing existing pollution prevention plans for procedures which overlap the
requirements and purpose of the SWPPP, such as state and local erosion and sedimentation
regulations, and (3) reviewing and addressing specific permit regulations included in individual
state NPDES Storm Water Permit requirements.
Designating a specific individual or team that will develop and implement the pollution
prevention plan serves several purposes. Naming the individual or team members makes it
clear that part of the job of the identified person(s) is to prevent storm water pollution.
Identifying a specific individual(s) also provides a point of contact for those outside of the
jobsite who may need to discuss aspects of the SWPPP.
Where setting up a pollution prevention team is appropriate, it is important to identify the key
people onsite who know the construction activity and its operations well, and to provide
                                                2-3
EP 1110-1-16
28 Feb 97
adequate structure and direction for the construction activity’s entire storm water management
program. Specific activities of the pollution prevention team and the type and number of
members vary for different sizes and types of projects.
Effective organization of the pollution prevention team is important in order for the team to
accomplish the task of developing and implementing a comprehensive SWPPP. There are
two important features in organizing a team of this nature: (1) selecting dedicated individuals
to serve on the team and (2) establishing good channels of communication.
The formation and operation of any team involves decision-making and planning within a
group environment. The team structure allows for people with different ideas and areas of
expertise to share knowledge and collectively determine what works best for a particular        ~
construction activity. To broaden the base of involvement in the construction activity’s storm
water pollution prevention program, team members should represent all phases of the
construction activity’s operations.
       ●
               29 CFR 1910 (Subparts G, H, 1,J, and K) Hazardous Materials, Environmental
               Controls, and Personnel Protection.
       ●
               29 CFR 1910.1200 OSHA Hazard Communication Standard.
       ●
               40 CFR 112 Oil Pollution Prevention (SPCC Plans).
       ●
               40 CFR 122 NPDES Regulations (Storm Water Discharges).
                                                   2-4
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
       ●
                40 CFR 280-281 Underground Storage Tanks.
       ●
                40 CFR 372 Toxic Chemical Release Reporting: Community Right-to-Know.
       ●
                40 CFR 761 Toxic Substances.
       ●
                49 CFR 171-173, 175, and 177 Department of Transportation Regulations.
It is the responsibility of the pollution prevention team to understand the NPDES Storm Water
Permit requirements of the state where the construction activities are to take place and to
determine which requirements of the SWPPP overlap with other plans or requirements and to
so note them.
To ensure compliance with the NPDES permit regulations, it is necessary to establish a list of
personnel who will be responsible for overseeing and coordinating and, when necessary,
amending the policies, practices, and procedures of the SWPPP. These persons should be
knowledgeable in construction operations and capable of understanding the technical aspects
of the SWPPP. Trained personnel responsible for the execution of the SWPPP requirements
should be available at the jobsite. Depending upon the size of the construction project and
complexity of the SWPPP, it may be necessary to establish a team or committee of trained
personnel to implement the SWPPP.
The personnel chosen should be identified by name and title. Exhibit D-1, in Appendix D, is
provided to list names, titles, and phone numbers of the committee members. The storm
water pollution prevention team concept is flexible and should be molded to conform to the
resources and specific conditions of the construction activity. Specific activities of the storm
water pollution prevention team and type and number of members vary for different projects.
                                               2-5
EP 1110-1-16
28 Feb 97
For facilities leasing space to tenant operations, the SWPPP committee should include at least
one representative from each tenant operation. The SWPPP committee will be responsible for
overseeing the activities as outlined below and shall meet at least annually to address the
implementation of these activities:
In order to ensure that the SWPPP is completely developed and adequately implemented,
state-issued NPDES permits typically require that authorized representative(s) of the
operator(s) sign and certify the plan. In signing the plan, the authorized representative
certifies that the information is true and assumes liability for the plan.
Official signatures provide a basis for an enforcement action to be taken against the person
signing the document. The permittee should be aware that Section 309 of the CWA provides
for significant penalties where information is false or the permittee violates, either knowingly or
negligently, the permit requirements. Specific signatory requirements for the SWPPP will be
listed in the state-issued permits.
                                                 2-6
                                                                                       EP 1110-1-16
                                                                                          28 Feb 97
On the Federal level, the SWPPP certification must be signed in accordance with the
provisions of Part V1l. G of the baseline general permit. All reports, certifications, or other
information required by the permit or requested by the permit authority shall be signed by a
person described below:
The person who signs the document may also be a “duly authorized representative.”          A
person is a duly authorized representative only if:
                                                2-7
EP 1110-1-16
28 Feb 97
The SWPPP must clearly identify the contractor(s) and/or subcontractor(s) who will be
responsible for implementing the plan, and each must sign a copy of the certification located
in Appendix F. A certification page must also be signed by a duly authorized representative of
the COE and retained in the SWPPP document.
The NOI is essentially an application and contains important information about the site,
including site location, owner information, operator (general contractor) information, receiving
water(s), existing NPDES permit number, if any, an indication of existing quantitative data, and
a brief description of the project. EPA has developed a one-page form to be used by
industrial facilities and construction activities when they submit NOI’S. A copy of the Federal
NOI form is located in Appendix B.
There are different deadlines for submitting NOI’S depending on the permitting authority
responsible for issuing the NPDES permit. Time required to submit NOI’S can vary from
2 days prior to construction for Federal regulated permits to over 120 days prior to
construction for some states. The reader is referred to Appendix A for a list of state contacts
to determine who and where the NOI is to be submitted. NOI’S for the EPA general permit
must be submitted directly to EPA’s central processing center at the following address:
                                                2-8
                                                                                      EP 1110-1-16
                                                                                        28 Feb 97
Each party or each of the parties who have day-to-day responsibilities for site operations and
each party or each of the parties who have control over the designs and specifications
necessary to ensure compliance with SWPPP requirements and permit conditions must be
identified in the NOI. It is anticipated that there will be projects where more than one entity
(e.g., the owner, developer, or general contractor) will need to submit an NOI so that both of
the requirements for an operator are met. In this case, those persons will become co-
permitters.
Regardless of whether or not the SWPPP is submitted to the permitting authority or other
public agency, the SWPPP and supporting materials must be kept at the site of the
construction activity at all times throughout the project. In maintaining plans onsite, the
SWPPP committee should keep all records and supporting documents compiled together in an
orderly fashion. The state-issued permit may require that all records be maintained for a
certain period of time after the project is completed. The Federal regulations require
                                               2-9
EP 1110-1-16
28 Feb 97
permitters to keep the SWPPP and all reports and data for at least 3 years after the project is
complete. This provision ensures that all records are available in case a legal situation arises
for which documentation is necessary.
Despite the fact that plans and associated records are not necessarily required to be
submitted to the Director, these documents are considered to be “reports” according to
Section 308(b) of the CWA and, therefore, are available to the public. State-issued permits
may require the submittal of copies of the SWPPP to the permitting authority, municipal
operator, or state or local agency upon request. However, permitters may claim certain
portions of their SWPPP as confidential according to the regulations at 40 CFR Part 2.
Basically, these regulations state that records which contain trade secret information may be
claimed as confidential.
SWPPP elements will be modified as required (site inspections, additional BMPs, etc.) under
the general permit by the appropriate COE SWPPP coordinator. Elements specific to tenant
construction projects can be modified by the tenant project coordinator or duly authorized
representative, as required under the general permit. Copies of any changes made by the
tenant construction project coordinator must be immediately provided to the local COE
SWPPP coordinator. The SWPPP will also be amended at any time it inadequately addresses
conditions of the general permit or any amendments to the permit. The record of revision
forms are located in Appendix G and are labeled Table G-1 and Exhibit G-1.
                                              2-1o
                                                                                        EP 1110-1-16
                                                                                          28 Feb 97
Control measures as listed below must be practiced in areas where Section 313 water priority
chemicals are stored, handled, processed, or transferred: (A, list of Section 313 water priority
chemicals is located in Appendix H.)
           ●
               Provide containment, drainage control, and/or diversionary structures.
           ●
               Minimize discharges from liquid storage areas (install liquid materials in
               compatible storage containers and/or provide secondary containment or
               equivalent measures designed to hold the largest volume of the largest storage
               tank plus precipitation).
           ●
               Minimize discharges from material storage areas.
           ●
               Minimize discharges from loading/unloading areas (use drip pans and/or
               implement a strong spill contingency and integrity testing plan).
           ●
               Minimize discharges from handling/processing/transferring areas (use covers,
               guards, overhangs, door skirts and/or conduct visual inspections or leak tests
               for overhead piping).
           ●
               Minimize discharges from all the above-listed areas (use manually activated
               valves with drainage controls in all areas, and/or equip the plant with a drainage
               system to return spilled material to the storage facility).
           ●
               Introduce facility security programs to prevent spills (use fencing, lighting, traffic
               control, and/or secure equipment and buildings).
                                                2-11
EP 1110-1-16
28 Feb 97
The SWPPP must include methods, controls, and procedures which will be incorporated to
minimize, limit, and/or prevent leaks or spills of Section 313 water priority chemicals, as
defined in the CWA, from occurringon the constructionsite. To prevent spills from occurring,
these facilities are required to designate a person responsiblefor spill prevention, response,
and reporting procedures. Any contaminated soil, material, or debris resulting from a spill of a
priority chemical shall be removed promptly and disposed of in accordance with Federal,
state, and local requirements and as described in the SWPPP. All areas of the construction
activity must be inspected at appropriate intewals for the following as specified in the plan:
       w
               Leaks or conditions that would lead to discharges of Section 313 water priority
               chemicals.
       ●
               Conditions that could lead to direct contact of storm water with raw materials,
               intermediate materials, waste materials or products thereof.
       ●
               Piping, pumps, storage tanks and bins, pressure vessels, process and material
               handling equipment, and material bulk storage areas for leaks, wind blowing
               loose material, corrosion, support or foundation failure, or other deterioration or
               noncontainment problems.
2.6.3 Training
Employees and contractorpersonnel must be trained in the following areas, at least once per
yeac
       ●
               Preventative measures, including spill prevention and response, construction
               activity inspections, and preventative maintenance.
       9
               Pollution control laws and regulations.
       ●
               The construction activity’s SWPPP.
       ●
               Features and operations of the construction activity that are designed to
               minimize discharges of Section 313 water priority chemicals, particularity spill
               prevention procedures.
                                               2-12
                                                                                         EP 1110-1-16
                                                                                            28 Feb 97
Certain states require that SWPPP plans be reviewed and certified by a Registered
Professional Engineer and recertifiedevery 3 years or anytime the plan is significantly
changed.
2.6.5 MonitoringRequirements
SARA Title Ill Section 313 facilities must monitor semiannually storm water discharges that
come into contact with equipment, tanks, containers, or other vessels or areas used for
storage of Section 313 water priority chemicals, or located at a truck or rail car loading or
unloading area. Note that the permit provides an alternative to whole effluent toxicity (WET)
testing. In lieu of monitoring for acute WET, the facility may monitor for pollutants that the
facility “reasonably” believes are present onsite. Such determinations are to be based on
reasonable best efforts to identify significant quantities of materials or chemicals present
onsite. The pollutants are identified in Tables II and Ill of Appendix D of 40 CFR 122.
Further, the permit provides that if the discharger certifies that industrial activities in a given
drainage area are not exposed to storm water, monitoring is not required.
Additional requirements for storm water discharges associated with industrial activity
discharging to municipal separate storm sewer systems serving a population of 100,000 or
more include:
Activities must comply with applicable requirements in municipal storm water management
programs developed under NPDES permits issued for the discharge of the municipal separate
                                                 2-13
EP 1110-1-16
28 Feb 97
storm sewer system that receives the construction activity’s discharge, provided the discharger
has been notified of such conditions, in addition to complying with the permit requirements.
Permitters which discharge storm water associated with industrial activity through a municipal
separate storm sewer system serving a population of 100,000 or more must make plans
available to the municipal operator of the system upon request.
Due to the fact that construction activities may handle certain hazardous substances over the
course of the project, spills of these substances in amounts that equal or exceed Reportable
Quantity (RQ) levels are a possibility. EPA has issued regulations which define what
reportable quantity levels are for oil and hazardous substances. These regulations are found
at 40 CFR Part 110, 40 CFR Part 117, or 40 CFR Part 302. For oil, if an oily sheen is
detectable in the storm water runoff, the reportable quantity level has been exceeded. For
hazardous substances, the final RQ levels depend on the chemical. For example, for dieidrin,
a pesticide, the level is 1 kilogram (kg). If there is a spill or other release of 1 kg or more, the
RQ threshold has been exceeded. Spill events such as these can be avoided if the SWPPP
addresses this possibility. Section 4 discusses spill prevention and control.
                                               2-14
                                                                                    EP 1110-1-16
                                                                                       28 Feb 97
An inventory of the existing site conditions which will be used in the development of the
SWPPP will be required. The information obtained should be both plotted on a map and
verbally explained in this portion of the plan. After all data are considered, an assessment of
the site potentials and limitations should be made. The site planner or designer should be
able to determine those areas which have critical pollutant generation potential. The following
are some of the most important considerations in site analysis.
3.1.1 Topography
A small-scale topographic map of the site should be prepared to show the existing contour
elevations at intervals of from 0.3 to 1.5 meters (1 to 5 feet) depending upon the slope of the
terrain. Existing topographic maps (e.g., U.S. Geological Survey (USGS) or local government
topos) can be a good starting point; however, the information should be verified by a field
investigation. The primary topographic considerations are slope steepness and slope length.
Because of the effect of accumulated runoff, erosion potential is greater on long, steep slopes.
When the percent slope has been determined, areas of similar steepness should be outlined.
Slope gradients can generally be grouped into three general ranges of soil erodability:
                      *                   Erosion Hazard
                      o-7%            Low erosion hazard
                      7-15%           Moderate erosion hazard
                      >15°A           High erosion hazard
Within these slope gradient ranges, the erosion hazard becomes greater as the slope length
increases. Therefore, in determining potential critical areas, the site planner should be aware
                                              3-1
EP 1110-1-16
28 Feb 97
of excessively long slopes. As a general rule, the erosion hazard will become critical if the
slope exceeds the following criteria:
All existing drainage swales and patterns on the site should be located and clearly marked on
the topographic map. Perennial or intermittent streams, as well as wetland areas, should also
be shown on the map. The existing drainage patterns, which consist of overland flow, swales
and depressions, and natural watercourses, should be identified in order to plan around critical
areas where water will concentrate. Where possible, natural drainageways should be used to
convey runoff over and off the site to avoid the expense and problems of constructing an
artificial drainage system. Man-made ditches and waterways can become part of the erosion
problem if they are not properly designed and constructed. Care should also be taken to be
sure that the increased runoff from the site will not erode or flood the existing natural drainage
system. Possible sites for storm water detention should be located at this time.
3.1.3 Soils
Major soil type(s) on the site should be shown on the topographic map. Soils information can
be obtained from a soil survey if one has been published for the county in which the project is
proposed. If a soil survey is not available, a request can be made to a district Soil
Conservation Service (SCS) office, a county extension service, or a state or Federal
Department of Agriculture. Commercial soils evaluations may also be available. Soils
information should be plotted directly onto the map or an overlay of the same scale for ease
of interpretation. Such soils properties as natural drainage, depth to bedrock, depth to
                                                   3-2
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
seasonal high water table, permeability, shrink-swell potential, texture, and erodibility should
exert a strong influence on land development decisions.
The existing vegetation such as tree clusters, grassy areas, and unique vegetation should be
shown on the map. In addition, existing denuded or exposed soil areas should be indicated.
Ground cover is the most important factor in terms of preventing erosion. Any existing
vegetation which can be saved will help prevent erosion. Trees and other vegetation protect
the soil, as well as beautify the site after construction. If the existing vegetation cannot be
saved, the planner should consider staging construction and using temporary seeding or
temporary mulching. Staging of construction involves stabilizing one part of the site before
disturbing another. In this way, the entire site is not disturbed at one time. Temporary
seeding and mulching involve seeding or mulching areas which would otherwise lie exposed
for long periods of time. Thus, the time of exposure is shortened and the erosion hazard is
reduced.
Areas adjacent to the site should be delineated on the topographic map. Features such as
streams, roads, houses or other buildings, and wooded or wetland areas should be shown.
Streams which will receive runoff from the site should be surveyed to determine their carrying
capacity. The analysis of adjacent properties should focus on areas downslope from the
construction activity. Of major concern are watercourses which will receive direct runoff from
the site. The potential for sediment pollution of these watercourses should be considered, as
well as the potential for downstream channel erosion due to increased volume, velocity, and
peak flow rate of storm water runoff from the site. The potential for sediment deposition on
adjacent properties due to sheet and rill erosion should also be analyzed so that appropriate
sediment-trapping measures can be planned and installed prior to any land-disturbing activity.
Drainage from large areas upstream from proposed active construction sites should be
                                                3-3
EP 1110-1-16
26 Feb 97
Federal, state, and local agencies that undertake land-disturbing activities are generally
regulated by the same authorities that regulate private land-disturbing activities. Readers are
encouraged to contact local jurisdictional agencies such as the County Engineer regarding
permits, fees, and plan submission, as well as any other requirements. Facilities which are
already operating under approved state or local sediment and erosion plans, grading plans, or
storm water management plans are required to submit copies of the NOI to the agency
approving such plans in accordance with Part 11.Aof the general permit (or sooner where
required by state or local rules), in addition to submitting the NOI to EPA or the NPDES-
delegated authority in accordance with paragraph 11.Cof the general permit.
The permits issued by NPDES-delegated states will specify deadlines for plan development
and implementation.   The sequence of events, assumably, will be that the SWPPP’S will be
completed and implemented at the time the project breaks ground and revised, if necessary,
as construction proceeds. The SWPPP should be in place before project initiation because
construction operations pose environmental risks as soon as activity begins. The initial
clearing and grubbing operation may contribute a significant amount of pollutants to storm
water runoff. The reader is urged to read the applicable permit carefully to determine what
dates and deadlines apply to the project,
The planning for pollution prevention measures should be done concurrently with the
development of the construction plans. The best SWPPP’S are developed at the same time
as the design of the site plan. However, if the site design has already been completed, it is
not necessary to start the process all over again. Much of the information needed for the
                                               3-4
                                                                                    EP 1110-1-16
                                                                                       28 Feb 97
SWPPP should already be included in the design documents. An SWPPP can be prepared
for most construction projects by using information from the existing design, and modifying the
design to accommodate the controls.
After analyzing the data and determining the site limitations, the planner can develop a site
plan. When designing the site plan, the planner should keep in mind that increases in runoff
may require structural runoff control measures or channel improvements. Both items are
expensive, and even more so when the site plan has to be redesigned to accommodate the
runoff control measures. Therefore, the planner should minimize the increase in runoff or
include runoff control measures in the initial design. The following are some issues to
consider when developing the site plan.
The development of an area should be tailored to the existing site conditions. This tailoring
will avoid unnecessary land disturbance, thereby minimizing the erosion hazards and costs.
Excessive cutting and filling should be avoided, if possible. Slopes should be at a maximum
of 2:1 or less, depending on soil type to provide for final stabilization.
Land disturbance in critically erodible areas may necessitate the installation of more costly
control measures. See criteria for critical areas in Section 3.1.1.
                                                 3-5
EP 1110-1-16
28 Feb 97
area, and provides more open natural space. The cluster concept not only lessens the
erodible area, but it generally reduces runoff and generally reduces development costs.
Keep paved areas such as parking lots and roads to a minimum. This pavement minimization
goes hand-in-hand with cluster development in eliminating the need for duplicating parking
areas and access roads. The more land that is kept in vegetative cover, the more water will
infiltrate, thus reducing runoff and erosion.
If the natural drainage system of a site has been determined that it can properly handle runoff
generated during and after construction activities without resulting in bank and bed erosion,
the natural system should be preserved instead of being replaced with storm sewers or
concrete channels.
The problems associated with storm water runoff in rapidly urbanizing watersheds have
become well known. These problems relate both to the quantity and quality of storm water
runoff. Major problems include increased flooding magnitude and frequency, accelerated
stream channel erosion, and water quality degradation. The basic underlying cause of these
problems is not difficult to understand. The hydrologic systems which have reached a natural
equilibrium over centuries simply cannot adjust to the sudden impact of urban development.
Flooding occurs because the increased volume and peak rate of runoff exceed the natural
carrying capacity of the streams. Stream channel erosion accelerates due to suddenly
increased flow velocities and flooding frequency. The water quality itself is degraded by
sedimentation and numerous other pollutants associated with urbanization that become
available to be washed off the land surface and into water resources.
                                                  3-6
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
Studies have shown that most natural stream channels are formed with a bankfull capacity to
pass runoff from a storm with a 1.5- to 2-year recurrence interval. As upstream development
occurs, the volume and velocity of flow from these relatively frequent storms increase.
Consequently, even smaller storms with less than 1-year recurrence intewals begin to cause
streams to flow full or flood. According to one study, stream channels are subject to a three-
to five-fold increase in the frequency of bankfull flows in a typical urbanizing watershed. This
increase in the flooding frequency places a stress on the channel to adjust its shape and
alignment to accommodate the increased flow. Unfortunately, this adjustment takes place in a
very short time in geologic terms, and the transition is usually not a smooth one. Meandering
stream channels, which were once parabolic in shape and covered with vegetation, typically
become straight, wide rectangular channels with barren vertical banks. This process of
channel erosion often causes significant property damage, and the resulting sediment is
transported downstream, further contributing to channel degradation.
One strategy for dealing with this problem is to increase the carrying capacity and stability of
affected streams through channel modifications. This strategy may be employed most
effectively on man-made channels or small, intermittent streams. Significant modifications to
natural, continuous flowing streams, however, can be the subject of intense local controversy.
Wherever modifications to natural flowing streams are being considered, extreme care must
be taken to weigh the benefits of such modifications against the cost and the concerns of the
local citizens. Where channel modifications are necessary, an attempt should be made to
incorporate conservation practices that will minimize adverse impacts to fish, wildlife, and the
aesthetic quality of the stream. In general, erosion and sedimentation controls, and the
overall SWPPP, are focused on preserving existing streamflow quantity and quality, whenever
possible.
The following storm water runoff requirements were developed to provide guidance for
designers and planners in the absence of state regulatory guidance or local storm water
management programs. These criteria are considered “rule of thumb” minimums:
                                               3-7
EP 1110-1-16
28 Feb 97
       9
               Concentrated storm water runoff leaving a development site must be
               discharged directly into an adequate natural or man-made receiving channel,
               pipe, or storm sewer system.
       ●
               An adequate channel is defined as “a watercourse that will convey a chosen
               frequency storm event without overtopping its banks or causing erosive damage
               to the bed, banks, and overbank sections of the watercourse.”
       .       For natural channels, the 2-year frequency storm is used to verify that storm
               water will not overtop the channel banks nor cause erosion of the channel bed
               or banks.
       ●
               For man-made channels, the 10-year frequency storm is used to verify that
               storm water will not overtop the channel banks and the 2-year storm is used to
               demonstrate that storm water will not cause erosion of the channel bed or
               banks.
       ●
               For pipes and storm sewer systems, the 10-year frequency storm is used to
               verify that storm water will be contained within the pipe or storm sewer.
       ●
               Improve the channels to a condition where the 10-year frequency storm will not
               overtop the channel banks and the 2-year frequency storm will not cause
               erosion to the channel bed or banks. The applicant must provide evidence of
               permission to make the improvements.
       .       Improve the pipe or storm sewer system to a condition where the 10-year
               frequency storm is contained within the appurtenances. The applicant must
               provide evidence of permission to make the improvements.
       8       Develop a site design such that when runoff discharges directly to a natural
               channel, the postconstruction peak flow for the 2-year storm will be no greater
                                              3-8
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
       ●
               Provide a combination of channel improvements, storm water detention, or
               other measures satisfactory to the plan-approving authority to prevent
               downstream erosion.
If the applicant chooses an option that includes storm water detention, the applicant must
obtain approval from the locality for a plan for maintenance of the detention facility. The plan
must establish the maintenance requirements for the facility and identify the person or entity
responsible for performing the maintenance.
Each receiving channel must be tested for adequacy.      A channel is considered adequate if
any of the following conditions can be met:
       ●
               The bankfull capacity of the natura/ receiving channel is sufficient to pass the
               postdevelopment peak flow from the 2-year frequency storm and the channel
               velocity (2-year frequency storm) does not exceed the permissible (non-
               erodible) velocity of the channel lining.
9 The storm sewer conduits (pipes) must pass the 10-year frequency storm.
       ●
               The contributing drainage area of the development site is less than 1 percent of
               the total drainage area to the point of consideration in the channel.
       .       There is no increase in the peak runoff rate for the 2-year frequency storm (for
               natural receiving channels) or the 10-year frequency storm (for man-made
               channels) at the point of discharge after development.
If the receiving channel is found to be inadequate,   the applicant should incorporate measures
to either improve the receiving channel to an adequate condition, or detain runoff on the site
so that the postdevelopment peak runoff rate for the 2-year storm will not exceed the
                                               3-9
EP 1110-1-16
28 Feb 97
predevelopment peak rate. The plan-approving authority may also approve a combination of
channel improvements and detention or other measures deemed satisfactory to protect the
channel
           .       If a storm water detention option is chosen, the applicant must submit a plan for
                   the continued maintenance requirements of the structure and designate
                   someone, who has consented to be responsible, to carry out the maintenance.
                   The local government may choose to accept the maintenance responsibility for
                   detention structures. However, where the local government does not accept
                   responsibility, the responsibility must be borne by the COE, other Federal
                   agency, landowner, a homeowners’ association, or other legal entity.
Selection of the appropriate method of calculating runoff should be based upon the size of the
drainage area and the output information required. Table 3-1 lists the acceptable calculation
methods for different drainage areas and output requirements. The plan-approving authority
may require or accept other calculation methods deemed more appropriate for local
conditions.
Simply stated, an erosion and sediment (E&S) control plan is a document that describes the
measures to be taken to control the potential for erosion and sedimentation on a construction
project.
                                                  3-1o
                                                                                                        EP 1110-1-16
                                                                                                           28 Feb 97
 Table 3-1
 Runoff Calculation Methods: Selection Criteria
 Calculation Methods*
 1. Rational Method
 2. Peak Discharge Method
 3. Tabular Method (TR-55)
 4.   Unit Hydrography Method
 Peak discharge and total runoff volume      Up to 809 hectares (2,0CQ acres)         2,3,4
                                             Up to 52 sq km (20 square miles)         3,4
 * There are numerous publications that describe the four methods listed in Table 3-1. A comprehensive discussion of
 each of these methods is beyond the scope of this pamphle~ readers are encouraged to consult other sources. One such
 source is McCuen, Richard H., Hydrologic Analysis ursd Design, Prentice-Hall, Inc., Englewood Cliffs, NJ, 1989.
The E&S control plan should be an independent entity from the construction drawings of a
project. While it is a good idea to include E&S control standards and specifications in contract
documents, the E&S control plan itself should contain measures to ensure that the controls
are installed, inspected, and maintained properly.
The plan narrative should explain the E&S control decisions made for a particular project and
the justification for those decisions. The narrative is especially important to the plan-approving
authority because it contains concise information concerning existing site conditions,
construction schedules, and other pertinent items which are not apparent in a typical site plan.
Since a plan reviewer cannot always visit the site or discuss the project at length with the site
planner, it is essential that the necessary information be provided for the plan review.
The narrative is also important to the construction superintendent and inspector who are
responsible for seeing that the plan is implemented properly. The narrative provides them
                                                         3-11
EP 1110-1-16
28 Feb 97
with a single report that describes where and when the various erosion and sediment control
practices should be installed.
An E&S control plan must contain sufficient information to satisfy the plan-approving authority
that the problems of erosion and sedimentation have been adequately addressed for a
proposed project. The length and complexity of the plan should be commensurate with the
size of the project, the severity of site conditions, and the potential for offsite damage.
Obviously, a plan for constructing a small structure on smaller area does not need to be as
complex as a plan for a large multistructure project involving many acres. Also, plans for
projects undertaken on flat terrain will generally be less complicated than plans for projects
constructed on steep slopes where erosion potential is greater. The greatest level of planning
and detail should be evident on plans for projects which are directly adjacent to flowing
streams, dense population centers, or high value properties where damage may be
particularly costly or detrimental to the environment. As a guide to E&S plan content, the site
planners should use the checklists located on the following pages.
                                                3-12
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
                                         CHECKLIST
                   FOR EROSION AND SEDIMENT             CONTROL     PLANS
NARRATIVE
     Proiect description - Briefly describe the nature and purpose of the land-disturbing
     activity and the area (hectares or acres) to be disturbed.
     Existirm site conditions - Describe the existing topography, vegetation, ground cover,
     and drainage.
     Adiacent areas - Describe neighboring areas such as streams, lakes, residential areas,
     and roads which might be affected by the land disturbance.
     Offsite areas - Describe any offsite land-disturbing activities that will occur (including
     borrow sites, waste or surplus areas, etc.). Will any other areas be disturbed?
     Soils - Describe the soils on the site giving such information as soil name, mapping
     unit, erodibility, permeability, depth, texture, and soil structure.
     Critical areas - Describe areas on the site which have potentially serious erosion
     problems (e.g., steep slopes, channels, and wet weather/underground springs).
     Erosion and sediment control measures - Describe methods which will be used to
     control erosion and sedimentation on the site.
     Storm water runoff considerations - Will the development site cause an increase in
     peak runoff rates? Will the increase in runoff cause flooding or channel degradation
     downstream? Describe the strategy to control storm water runoff.
                                             3-13
EP 1110-1-16
28 Feb 97
                                           CHECKLIST
                     FOR EROSION AND SEDIMENT             CONTROL      PLANS
                                            (continued)
SITE PLAN
       Vicinity map - Provide a small map locating the site in relation to the surrounding area.
       Include any landmarks which might assist in locating the site.
Limits of clearinq and ~radinq - Show areas which are to be cleared and graded.
      Final contours - Indicate changes to the existing contours, including final drainage
      patterns.
Existinq veqeta~ - Show the existing tree lines, grassed areas, or unique vegetation.
      Existina drainaqe ~atterns - Indicate the dividing lines and the direction of flow for the
      different drainage areas. Include the size (area in hectares or acres) of each drainage
      area.
Critical erosion areas - Show areas with potentially serious erosion problems.
      Site development - Show all improvements such as buildings, parking lots, access
      roads, and utility construction.
      Location of practices - Show the locations of erosion and sediment controls and storm
      water management practices used on the site.
      Offsite areas - Identify any offsite land-disturbing activities (e.g., borrow sites and
      waste areas). Show location of erosion controls. (Is there sufficient information to
      assure adequate protection and stabilization?)
      Detail drawinas - Note that any structural practices used that are not referenced to an
      erosion and sedimentation handbook or local handbooks should be explained and
      illustrated with detail drawings.
                                               3-14
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
Erosion and sediment control planning should be an integral part of the site planning process,
not an afterthought. The potential for soil erosion should be a significant consideration when
deciding upon the layout of buildings, parking lots, roads, and other facilities. Costly erosion
and sediment control measures can be minimized if the site design can be adapted to existing
site conditions and if good conservation principles are used. Note that sedimentation ponds,
often used for erosion and sedimentation control during construction, can be adapted to site
amenities, if properly preplanned. The owner or lessee of the land being developed has the
responsibility for plan preparation and submission. The owner or lessee may designate
someone (e.g., an engineer, architect, or contractor) to prepare the plan, but the owner or
lessee retains the ultimate responsibility.
There are a number of possible sources of erosion and sediment control planning assistance
within most states.
       1.      Soil and Water Conservation Districts: These districts usually have elected
               representatives (directors) from different localities throughout the state. One of
               the primary functions of these districts is to provide assistance to landowners
               for soil conservation planning and implementation. Requests for assistance in
               preparing an erosion and sediment control plan for a construction site can be
               made through the local district.
                                              3-15
EP 1110-1-16
28 Feb 97
               addition will have soil samples analyzed upon request to determine fertilization
               and liming needs for establishing vegetation on a particular site.
After the layout of the site has been determined, a plan to control erosion and sedimentation
from the disturbed areas must be formulated. Decision concerning which areas must be
disturbed in order to accommodate the proposed construction must be made. Special
attention is directed to critical areas that may be disturbed.
The site should be divided into drainage areas. Potential runoff flow paths over the developed
site should be determined. Considerations concerning how erosion and sedimentation can be
controlled in each small drainage area should be made before considering the entire site. The
guiding principle is that it is easier to control erosion than to contend with sediment after it has
been carried downstream.
Erosion and sediment control practices can be divided into three broad categories: vegetative
controls, structural controls, and management measures. Each of these categories have
temporary and permanent control measures to be considered. Vegetative and structural
practices should be selected and designed in accordance with Federal, state, and/or local
specifications if they exist. In lieu of any local standards and specifications, the best
                                                3-16
                                                                                         EP 1110-1-16
                                                                                            28 Feb 97
         (1) Virginia Department of Conservation and Recreation Division of Soil and Water
             Conservation’s Virginia Erosion and Sediment Contro/ Handbook, 1992 Third
             Edition.
         (3) United States Department of Agriculture, Soil Conservation Service’s Guidelines for
             the Control of Erosion and Sediment in Urbanizing Areas Within Mississippi, 1975.
         (4) United States Environmental Protection Agency’s Summary Guidance For Storm
             Water Management For Construction Activities - Developing Po//ution Prevention
             P/ans and Best Management Practices, 1992.
In the event of overlap or conflicting specifications (i.e., riprap gradations or filter fabric design
specs), the appropriate geographic district should be contacted to resolve any discrepancy.
The following are summary overviews of the erosion and sediment control practices
recommended for use. Management measures are construction management techniques
which, if properly utilized, can minimize the need for physical controls and possibly reduce
costs.
Planners should keep in mind that the first line of defense is to prevent erosion. Erosion
prevention is accomplished by protecting the soil surface from raindrop impact and overland
flow of runoff. The best way to protect the soil surface is to preserve the existing ground
cover. Where land disturbance is necessary, temporary seeding or mulching should be used
on areas which will be exposed for long periods of time. Erosion and sediment control plans
must contain provisions for permanent stabilization of denuded areas. Selection of permanent
vegetation should include the following considerations:
                                                 3-17
EP 1110-1-16
28 Feb 97
               ●
                         Applicability to site conditions.
               ●
                         Establishment requirements.
               9         Maintenance requirements.
               ●
                         Aesthetics.
The vegetative BMP’s in Appendix C are numbered according to the following categories of
use:
The local agricultural extension service should be consulted concerning suitable vegetation
and vegetative treatments.
Structural control practices are generally more costly than vegetative controls. However, they
are usually necessary since not all disturbed areas can be protected with vegetation.
Structural controls are often used as a second or third line of defense to capture sediment
before it leaves the site. It is very important that structural practices be selected, designed,
and constructed according to BMP’s of which many are listed in Appendix C. Improper use or
inadequate installation can result in failure of the control and subsequent release of any
trapped sediment.
The structural BMP’s in Appendix C are numbered according to the following categories of
use:
                                                   3-18
                                                                                        EP 1110-1-16
                                                                                           28 Feb 97
       .      Include erosion and sediment control as an agenda item for the pre-
              construction meeting.
       ●
              Sequence construction so that no area remains exposed for unnecessarily long
              periods of time.
       9
              On large projects, stage the construction, if possible, so that one area can be
              stabilized before another is disturbed, whenever possible.
                                                 3-19
EP 1110-1-16
28 Feb 97
       ●
               Consider the time of year.
               Physically mark off limits of disturbance on the site with tape, signs, or other
               methods, so that workers can see areas to be protected.
               Develop and carry out a regular maintenance schedule for erosion and
               sediment control practices.
                                              3-20
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
The principal source of pollutant export associated with construction activities is erosion. Soil
erosion is the process by which the land’s surface is worn away by the action of wind, water,
ice, and gravity. Natural, or geologic erosion, has been occurring at a relatively slow rate
since the earth was formed and is a tremendous factor in creating the earth as we know it
today. Except for some cases of shoreline and stream channel erosion, natural erosion
occurs at a very slow and uniform rate and is a vital factor in maintaining environmental
balance.
        ●
               Raindrop erosion is the first effect of a rainstorm on the soil. Raindrop impact
               dislodges soil particles and splashes them into the air. These detached
               particles are then vulnerable to the next type of erosion.
        ●
               Sheet erosion is the erosion caused by the shallow flow of water as it runs off
               the land. These very shallow moving sheets of water are seldom the detaching
               agent, but the flow transports soil particles which are detached by raindrop
               impact and splash. The shallow surface flow rarely moves as a uniform sheet
               for more than a meter (3 feet) on land surfaces before concentrating in the
               surface irregularities.
                                                4-1
EP 1110-1-16
28 Feb 97
         .       Rill erosion is the erosion which develops as the shallow surface flow begins to
                 concentrate in the low spots of the irregular contours of the surface. As the
                 flow changes from the shallow sheet flow in these low areas, the velocity and
                 turbulence of flow increase. The energy of this concentrated flow is able to
                 both detach and transport soil materials. This action begins to cut small
                 channels of its own. Rills are small but well-defined channels which are
                 normally less than 100 mm (4 inches) deep. The rills are easily obliterated by
                 harrowing or other surface treatment.
        ●
                 Gully erosion occurs as the flow in rills comes together in larger and larger
                 channels. The major difference between gully and rili erosion is in magnitude.
                 Gullies are too large to be repaired with conventional tillage equipment and
                 usually require heavy equipment and special techniques for stabilization.
        .        Channel erosion occurs as the volume and velocity of flow causes movement of
                 the streambed and bank materials.
The erosion potential of any area is determined by four principal factors: the characteristics of
the soil, vegetative cover, topography, and climate. Although each of these factors is
discussed separately herein, they are interrelated in determining erosion potential.
So// characteristics   which influence the potential for erosion by rainfall and runoff are those
properties which affect the infiltration capacity of a soil and those which affect the resistance
of the soil to detachment and being carried away by falling or flowing water. The following
four factors are important in determining soil erodibility:
Soils containing high percentages of fine sands and silt are normally the most erodible. As
the clay and organic matter content of these soils increases, the erodibility decreases. Clays
                                                  4-2
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
act as a binder to soil particles, thus reducing erodibility. However, while clays have a
tendency to resist erosion, once eroded, they are easily transported by water. Soils high in
organic matter have a more stable structure which improves their permeability. Such soils
resist raindrop detachment and infiltrate more rainwater. Clean, well-drained and well-graded
gravel and gravel-sand mixtures are usually the least erodible soils. Soils with high infiltration
rates and permeabilities either prevent or delay and reduce the amount of runoff.
Vegetative cover has an extremely important role in controlling erosion as it provides the
By limiting and staging the removal of existing vegetation and by decreasing the area and
duration of exposure, soil erosion and sedimentation can be significantly reduced. Special
consideration should be given to the maintenance of existing vegetative cover on areas of
high erosion potential such as moderately to highly erodible soils, steep slopes, drainageways,
and the banks of streams.
Topography.    The size, shape, and slope characteristics of a watershed influence the amount
and rate of runoff. As both slope length and gradient increase, the rate of runoff increases
and the potential for erosion is magnified. Slope orientation can also be a factor in
determining erosion potential. For example, a slope that faces south and contains droughty
soils may have such poor growing conditions that vegetative cover will be difficult to re-
establish.
                                                4-3
EP 1110-1-16
28 F@ 97
C/irnate.   The frequency, intensity, and duration of rainfall are fundamental factors in
determining the amounts of runoff produced in a given area. As both the volume and velocity
of runoff increase, the capacity of runoff to detach and transport soil particles also increases.
Where storms are frequent, intense, or of long duration, erosion risks are increased.
Seasonal changes in temperature, as well as variations in rainfall, help to define the high
erosion risk period of the year. When precipitation falls as dry snow, no erosion will take
place. However, when the temperature rises, melting snow adds to runoff, and erosion
hazards are high. Because the ground may still be partially frozen, its absorptive capacity is
reduced. Frozen soils are relatively erosion-resistant.    However, soils with high moisture
content are subject to uplift by freezing action and are usually very easily eroded upon
thawing.
4.2 Sedimentation
Normally, runoff builds up rapidly to a peak and then diminishes. Excessive quantities of
sediment are derived by erosion, principally during the higher flows. During lower flows, as
the velocity of runoff decreases, the transported materials are deposited to be picked up by
later peak flows. In this way, sediments are carried downslope, or downstream, intermittently
and progressively from their source or point of origin.
Sediment pollution is soil out of place. It is a product accentuated by the activities of man
which leads to severe soil loss. When these large quantities of soil enter our waters, then
sediment pollution occurs.
Over four billion tons of sediment are estimated to reach the ponds, rivers, and lakes of our
country each year, and approximately one billion tons of this sediment are carried all the way
to the ocean. Approximately 10 percent of this amount is contributed by erosion from land
undergoing highway construction or land development. Although these latter quantities may
                                                 4-4
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
appear to be small compared to the total, they could represent more than one-half of the
sediment load carried by many streams draining small subwatersheds which are undergoing
development.
Excessive quantities of sediment cause costly damage to waters and to private and public
lands. Obstruction of stream channels and navigable rivers by masses of deposited sediment
reduces their hydraulic capacity which, in turn, causes an increase in subsequent flood crests
and a consequent increase in the frequency of damaging storm events.
Sediment may fill drainage channels, especially along highways and railroads, and plug
culverts and storm drainage systems, thus necessitating frequent and costly maintenance.
Municipal and industrial water supply reservoirs lose storage capacity, the usefulness of
recreational impoundments is impaired or destroyed, navigable channels must be continually
dredged, and the cost of filtering muddy water preparatory to domestic or industrial use may
become excessive. The added expense of water purification in the United States, because of
sedimentation, amounts to hundreds of millions of dollars each year.
In an aquatic environment, the general effect of fine-graded sediments such as clays, silts,
and fine sands is to reduce drastically both the kinds and the amounts of organisms present.
Sediments alter the existing aquatic environment by screening out sunlight and by changing
the rate and the amount of heat radiation. Particles of silt settling on stream and lake bottoms
form a blanket which creates a hostile environment for the organisms living there and literally
smothers many of them and their eggs.
Coarser-grained materials also blanket bottom areas to suppress aquatic life found in these
areas. Where currents are sufficiently strong to move the bedload, the abrasive action of
these materials in motion accelerates channel scour and has an even more severely
deleterious effect upon aquatic life. The aesthetic attraction of many streams, lakes, and
reservoirs used for swimming, boating, fishing, and other water-related recreational activities
                                               4-5
EP 1110-1-16
28 Feb 97
has been seriously impaired or destroyed by bank cutting and channel scour, accelerated by a
4.2.2 Costs
Many state and local jurisdictional agencies require that land-disturbing activities have an
approved E&S control plan prior to commencement of work. The owner is responsible for the
development of E&S control plans. Once a plan is approved, generally a contractor will be
responsible for implementing, installing, and maintaining the E&S control plan. However, the
owner is ultimately responsible and in many instances must certify that the plan will be carried
out. Once the project has moved through the bid process, the cost of implementation
becomes the primary concern. Proper implementation of the E&S plan can save the
developer and the contractor money in excavation costs. If denuded areas are stabilized
initially, little or no additional work will be required later. This can speed up completion dates,
and overall savings will be realized. This strategy requires that planning take on a more
important role in the management of a project. Good management throughout the life of a
project will lead to increased savings.
On the other hand, failure to implement an E&S plan or failure to maintain controls during
construction of a project can mean additional costs to the developer and the contractor.
These additional costs exist at three levels. The primary level is the cost of work being
stopped for noncompliance with an approved plan; the secondary level is the cost of repairing
damage to adjacent properties; the tertiary level would be the costs associated with missed
deadlines, litigation with damaged parties, and extra charges by the contractor for additional
work. The perception by the public that the developer and the contractor were negligent in
performing their responsibilities may also pose a negative cost, if not immediately, sometime
in the future.
                                                4-6
                                                                                    EP 1110-1-16
                                                                                       28 Feb 97
The general permit requires the listing of potential nonsediment pollutants likely to be present
in storm water in significant quantities. The sections below discuss potential pollutants which
are commonly associated with construction activities.
4.3.1 Nutrients
Nitrogen, phosphorus, and potassium are the major plant nutrients used for the fertilizing of
new landscape at construction sites. Heavy use of fertilizers can result in the discharge of
nutrients to water bodies resulting in excessive algal growth and eutrophication, and in some
states a violation of water quality standards.
Galvanized metal, painted surfaces, and pressure-treated lumber comprise many of the
surfaces exposed to storm water as a result of construction activity. These coatings and
treatments contain metals which enter storm water as the surfaces corrode, flake, dissolve,
decay, or leach. Acid rain can accelerate these processes.
4.3.3 Pesticides
Herbicides, insecticides, and rodenticides are commonly used at construction sites. The
unnecessary or improper application of these pesticides may result in direct contamination,
indirect pollution through drift, or the transport of soil surfaces into water.
Petroleum products, pesticides, and other synthetic organic compounds (glues, sealants,
solvents, etc.) are used widely at construction sites and may be improperly stored and
                                                  4-7
EP 1110-1-16
28 Feb 97
disposed.   Deliberate dumping of these materials, which can migrate into surface or ground-
water resources, is a direct violation of the CWA. On parking lot or highway construction
projects, the application of diesel fuel to the contact surfaces of the “hot mix asphalt”
application and transport vehicles is a common practice that should be discontinued
immediately.
Miscellaneous wastes include wash from concrete mixers; solid wastes resulting from the
clearing and grubbing of vegetation; wood and paper materials derived from packaging of
building products; food containers such as paper, aluminum, and steel beverage cans; and
sanitary wastes. In addition to erosion and sediment controls, the SWPPP must address the
other potential pollutant sources that may exist on a construction site. These controls include
proper disposal of construction site waste; compliance with applicable state or local waste
disposal, sanitary sewer, or septic system regulations; control of offsite vehicle tracking; and
control of allowable nonstorm water discharges which are discussed in Section 6.5.
The following discharges are generally allowed if they do not commingle with contaminated
material or other discharges associated with industrial activity:
       ●
               Uncontaminated groundwater resulting from dewatering activities.
       ●
               Naturally occurring flows such as springs, wetlands, and riparian habitats.
                                                4-8
                                                                                       EP 1110-1-16
                                                                                          28 Feb 97
       ●
               Irrigation water discharged during seeding, planting, and maintenance, provided
               fertilizers and pesticides are applied correctly.
       9
               Pavement wash waters for dust control and general housekeeping practices
               providing that spills or leaks of toxic or hazardous materials have not occurred
               and where detergents are not used.
It must be emphasized that the flows described above are uncontaminated flows. For
example, if the discharge from potable water line flushing were to collect significant amounts
of sediment or contaminants while flowing over soil or pavement, it would be considered
contaminated and, therefore, could not be discharged directly to the storm drain system.
The construction activity should list any pollutants that have a reasonable potential to be
present in the storm water discharge in significant quantities. The definition of significant
quantities varies from item to item. In general, a significant quantity is taken to be any
quantity that is not consumed within a normal day’s operations or would result in spills beyond
the immediate cleanup capabilities of the individual charged with the use of the materials. A
significant quantity also relates to a “reportable” quantity for those substances that are
regulated under SARA Title Ill Section 313, or any of the programs mentioned in Section 2.6.
Table E-1 in Appendix E has been provided to inventory materials found onsite.
Some of the primary contaminants associated with construction activities are as follows:
        ●
          CCA treated lumber          s Gasoline                     ● Propane
        9 AZCA treated lumber         ● Hydrogen peroxide            ● Solvents
        ●
          Boiler treatment            9 Maintenance                  ● Sulfuric acid
          chemicals                     and motor                    ● Timber
        ●
          Creosote                      lubricants                   “ Mold
        w Tribucide                     and coolants                   inhibitor
        . Diesel fuel                 ●
                                        Paints, thinners,            ● Water
        ●
          Fire retardant                and sealants                   repellant
        9 White wood                  ●
                                        Pentachlorophenol            s Refrigerant
        ●
          Fuel oil                      treated lumber               ● Concrete
        9 Detergents                  ●
                                        Metal studs                  ● Tar
                                                4-9
EP 1110-1-16
28 I%b 97
Because construction activities may handle certain hazardous substances over the course of
the project, spills of these substances in amounts that equal or exceed Reportable Quantity
(RQ) levels are a possibility. EPA has issued regulations that define the reportable quantities
for oil and hazardous substances. These regulations are found at 40 CFR Part 110, 40 CFR
Part 117, and 40 CFR Part 302. If a release occurs, a contingency plan should be put into
effect. The single most important action required in the contingency plan should be to
minimize environmental impacts or health threats. If there is a RQ release during the
construction period, the following actions must be taken:
        s
               Notify the National Response Center immediately at (800) 424-8802; in
               Washington, DC, call (202) 426-2675.
        .      Within 14 days, submit a written description of the release to the EPA Regional
               office providing the date and circumstances of the release and the steps to be
               taken to prevent another release.
If a spill occurs and the above actions are taken, the single most important action is to
document all calls, correspondence, and any other communications relative to the spill.
Record names, titles, phone numbers, dates, times, and any other information that may be
used to prove that the actions were taken.
The construction activity must list all historical spills or leaks of toxic or hazardous pollutants
to the storm water system that have occurred in the last 3 years. This .Iist must include: toxic
chemicals listed in 40 CFR Part 372 that have been discharged to storm water as reported on
EPA Form R, and oil or hazardous substances in excess of reportable quantities, 40 CFR
                                                4-1o
                                                                                    EP 1110-1-16
                                                                                       28 Feb 97
Part 110, 117, or 302. Table E-2, in Appendix E may be used to record the lists described
previously.
The SWPPP should designate a person who is accountable for spill response at the
construction site. The designated person will be responsible for emergency procedure action
and documentation.    The responsible person should be thoroughly trained and familiar with all
aspects of the response plan as well as the operations and daily activities of the construction
activity. In addition this person must have the authority to commit the resources needed to
accomplish the spill plan response.
Contingency plans are required by law for proper response to a hazardous waste, chemical, or
oil spill. The plans are designated Exhibit E-1, -2, and -3, in Appendix E. These plans are
provided as a guideline only and should be customized by the construction activity. These
plans and lists of contacts should be posted in obvious locations to facilitate a quick response
to any spill.
The key to a successful SWPPP is that no matter what quantities of materials are dispensed
and stored, proper and safe management can reduce the risk of spills and leaks substantially.
The following sections highlight the most common activities with a reasonable potential for
spill or releases of hazardous materials to ground or surface water resources.
Underground fuel storage has been addressed in other EPA programs. The use of double
containment tanks, monitoring wells, and other controls has been established and all facilities
should be in compliance. (The construction activity management should assure itself that all
regulated underground storage tanks meet requirements.) Not all tanks fall under existing
programs. The objective is to assure that tank mntents do not leak into the storm sewer
system or into the groundwater.
                                              4-11
EP 1110-1=16
28 Feb 97
Aboveground storage tanks are not regulated in the same way that underground tanks are
regulated. Areas containing fuel, lubricants, chemicals, waste oil, waste solvent, and other
such tanks or storage barrels should be covered (preferably under roof) wherever possible.
Storm water flows should be directed around the storage locations. Protective dikes around
the sites which can provide containment are also in order, particularly if the potential spill
volume exceeds the sump volume or what can be contained using absorbent “pillows” or other
material and containment booms.
The construction activity should identify areas in which a leak or a spill of significant materials
could result in contact with storm water runoff and enter the storm water drainage system.
These areas will coincide with areas of material handling, transfer, and storage. After areas of
concern are identified, specific material handling procedures, storage requirements, and
cleanup equipment and procedures should be established. Table E-4, in Appendix E, will be
used to record the spill control and countermeasures established by the construction activity.
Additional documentation relating to spill prevention countermeasures and control must be
added to the SWPPP document.
Aboveground tanks are primarily used for the bulk storage of chemicals, diesel, gasoline,
coolants, and lubricants. These tanks may be serviced by any combination of below ground
or aboveground piping systems. Bulk shipments are generally received from tank trucks. The
products are off-loaded adjacent to the storage tanks and are dispensed to equipment as
needed. Hazardous wastes generated from construction activity operations primarily consist
of contaminated sediments from the fueling or maintenance areas.
Waste oils are stored in both aboveground and underground tanks. Generally, the tanks are
less than 1,900 liters (500 gallons) in capacity. All outdoor, aboveground tanks should be
contained by dikes having adequate volume to hold a spill and, depending upon the region, an
appropriate precipitation event. Underground storage tanks (UST’S) must conform to their own
set of regulations. The SWPPP should contain appropriate references to UST management.
                                               4-12
                                                                                       EP 1110-1-16
                                                                                          28 Feb 97
Fuel is usually delivered to construction activities by tank truck. The bulk storage area should
be contained by dikes and loading/unloading areas should be served by oil/water separators.
Dispensing to vehicles and equipment is usually accomplished through standard fuel
dispensers. Most spills are relatively minor. Spills are usually cleaned up by construction
activity personnel and/or private contractors under the supervision of the local fire department.
In the event a spill does reach the storm sewer system, a licensed cleanup contractor should
be immediately dispatched to clean out the storm lines and recover spilled fuel.
Most construction activity vehicles and equipment are maintained by construction activity
personnel and are frequently repaired and serviced on the jobsite. Substantial volumes of
petroleum oils, including engine oil, transmission fluid, brake fluid, and other lubricants, are
used in vehicle maintenance operations. As a result, there is a potential for illicit discharges
or storm water discharge contamination by oils, solvent, lubricants, fuel, and coolants.
Equipment maintenance typically takes place in one of two locations: (1) the construction
activity maintenance area or garage; or (2) wherever the equipment breaks down. The
potential for storm water contamination where the equipment is serviced must be considered.
                                               4-13
EP 1110-1-16
28 Feb 97
The following fluids have the potential to enter the storm water system from spillage: diesel
fuel, gasoline, engine oil, hydraulic fluid, transmission fluid, lubricants, refrigerants, and
solvents. All spillage other than potable water should be prevented from entering the storm
water system. Engine oil and hydraulic fluids are used in relatively small quantities but may
enter the storm drain system during precipitation events. If the garage area has unsealed
cracks, spillage may result in groundwater contamination.      Maintenance activities which occur
inside garages may result in storm water contamination through floor drains connected to the
storm sewer system. Hydrocation spillage should be minimized and cleaned up when it
occurs. Residual cleanup waters should be passed through an oil/water separator into a
sanitary sewer system if available or transported to a permitted treatment facility.
The spent wash water from vehicle and equipment cleaning may be contaminated with
surface dirt, rust, flash metal, or paint from the surface of the equipment and fluids (fuel,
hydraulic fluid, oil, lubricants, etc.). Most construction activity vehicles and equipment are
maintained by construction activity personnel and are frequently repaired and serviced on the
jobsite. As a result, there is a potential for illicit discharges or storm water discharge
contamination by oils, solvents, lubricants, fuel, and coolants.
EPA regulations prohibit the discharge of wash water from car and truck cleaning facilities
without a permit. The potential for storm water runoff contamination and the presence of illicit
discharges from these facilities must be considered. The discharge should be treated for the
removal of oil, grease, solvents, soaps, and solids prior to discharge to receiving waters.
Although some vehicle-cleaning activities are not currently covered separately by the EPA
storm water regulations, these activities must be addressed under the SWPPP wherever storm
water may come into contact with the results of activities that are covered.
                                                4-14
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
Many of our nation’s older and more-established cities are coping with problems related to a
deteriorated infrastructure stressed beyond capacity. Chronic flooding occurs in some areas
where storm sewer trunk lines were not designed to convey the extent of development that
has occurred. As a result of this flooding, deteriorated sanitary sewers are overloaded by
infiltration and inflow (1& l). This I & I laden sewage often overflows during high intensity or
long duration storms washing pollutants into surface waters.     Several older cities combined
sanitary and storm sewers into a single combined sewer system, These also overflow during
larger storm events as combined sewer overflows. These discharges containing raw sewage
threaten the health of all who come into contact with them. In addition to being a threat to
public health, CSO’S jeopardize the beneficial use of surface waters. High bacterial counts
result in beach closings and shellfish contamination.   Low dissolved oxygen levels affect the
health of fish and other aquatic life. Toxic pollutants tend to settle out and increase the level
of contamination in the sediments. Floating debris, containing materials commonly associated
with sewage, is offensive and greatly reduces the enjoyment of streams, rivers, and coastal
zones.
Federal and state regulatory agencies are currently struggling to develop the proper program
for monitoring and controlling CSO’S. They are struggling because each system varies from
one community to the next, and each CSO solution is inherently complex and potentially
expensive. Programs are in place to attempt to control I & I problems with sanitary sewer
systems. The required level of control for the CSO discharges is not clearly specified in
current NPDES discharge permits, nor are CSO control requirements defined in most state
water quality standards. Construction designers and managers should be aware of the state
and local trends concerning CSO’S. Impacts concerning problems could conceivably result in
sanitary sewer user fees, moratoriums on expansion, or even requiring onsite sewage
disposal.
                                               4-15
EP 1110-1-16
28 Feb 97
Onsite sewage disposal systems (OSDS) include conventional septic systems, large-scale
conventional systems, alternative and innovative designs, and private sewage treatment
facilities. The term applies to any residential or industrial sewage that is not treated or
planned for treatment in a centralized public sewer system.
If storm water runoff from the proposed construction site has been sampled and analyzed for
the presence of any pollutant (e.g., total suspended solids), then the results of the analyses
must be included in the SWPPP. In most cases, existing runoff water quality data are not
available for a specific site, particularly an undeveloped site. However, if the construction is
on or adjacent to an existing industrial facility, that facility may have collected runoff water
quality data to satisfy another permit. If there are no existing data on the quality of runoff from
the site, then it is not necessary to collect samples for the general permit. Runoff water
quality data may sometimes be available from your state or local government. You may also
be able to obtain runoff water quality information from the USGS or state or local watershed
protection agencies. The sampling event(s) information should be recorded in Table E-3, in
Appendix E, and a one-page summary included from the sampling data report package.
Previous sampling data will be useful in determining the source of pollutants and in initiating
controls.
                                                4-16
                                                                                       EP 1110-1-16
                                                                                          28 Feb 97
This section of the SWPPP describes storm water management measures to control and
abate water quality impairment associated with the activities described in the preceding
sections.
Land conversion associated with development has resulted in the loss of vegetation and
sensitive wetlands, alteration of natural drainage patterns, and the creation of expanded areas
of imperviousness. This loss of infiltration capacity has correlated with increases in the
velocity, volume, and frequency of storm water runoff. Mitigation of this process is inherently
complex in that sources are somewhat diverse, changes in water quality tend to be gradual
and cumulative, and the site-specific physical and safety constraints associated with the
configuration of the different facilities tend to limit the number of viable measures for
implementation at each site. However, since pollutants have a limited number of pathways by
which they reach water resources, the practices that constitute management measures for the
various source categories tend to be somewhat similar for each construction activity.
The design and implementation of effective source control measures is achieved from a
management systems approach as opposed to an approach that focuses on individual
practices. That is, the pollutant control achievable from any given management system is
viewed as the sum of the parts, taking into account the range of effectiveness associated with
each single practice, the costs of each practice, and the resulting overall cost and
effectiveness of the system. Some individual practices may not be effective alone but, in
combination with others, may provide a key function in a highly effective system. This is
analogous to the use of ‘treatment trains” or a series of treatment steps.
                                                5-1
EP 1110-1-16
28 Feb 97
generate pollutants from a number of discrete activities, or unit areas, the guidance includes
management measures for each activity, or area.
It is generally not possible to prescribe a highly specific management measure that will be
uniformly applicable over an expanded region. For example, when designing erosion and
sediment control systems, one considers soil types, antecedent moisture conditions, land use,
precipitation patterns, and slopes to determine the proper set of practices. The multitude of
combinations of site-specific factors that arise within a state, region, and even within a
watershed, makes it difficult to develop a list of specific management measures to be used.
Congress has defined management measures as “economically achievable measures for the
control of the addition of pollutants from existing and new categories and classes of nonpoint
sources of pollution which reflect the greatest degree of pollutant reduction achievable through
the application of the best available nonpoint pollution control practices, technologies,
processes, siting criteria, operation methods, or other alternatives.” Congress has not defined
the term “economically achievable,” nor has it explained the term in legislative history. This
distinction relates to the extensive flexibility inherent in implementing pollution prevention
management measures. The ability of a particular management measure to deal with
nonpoint source pollution from a particular site is subject to a variety of factors (e.g.,
geography, geology, soils, hydrology, and production methods) too complex to address in a
single set of simple, mechanical prescriptions at the state or regional level, so this guidance
provides considerable flexibility for local selection. These considerations make it difficult to
predict the costs and economic impacts of measures that will ultimately be developed, applied,
and implemented on a localized basis. Many of the proposed management measures are
regarded as low-cost, yet highly effective. Examples include source control measures such as
spill prevention or pesticide management. Others are more expensive, yet widely practiced
(e.g., construction management measures such as erosion and sediment control practices,
storm water management measures such as constructed wetlands or pond systems). This
guidance provides a set of management practices for each source category. The number and
type of systems identified per source category are based upon the range and diversity of
                                                5-2
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
For each management measure, a list of management practices that can be used in designing
an equivalent or better system is provided. The list of practices reflects the best available set
of practices, or components of best available systems, but is not all-inclusive of those
practices that could be used to develop systems that are equivalent to or better than specified
management measures.
The pollutant reduction estimates that can be achieved using the specified management
practices are also described in this guidance, quantitatively wherever possible. These
reductions serve as the benchmarks for equivalent or better management measures. All
estimates provided are based upon the best available data currently available, but are
somewhat empirical. Further monitoring will provide data to support the effectiveness of this
portion of the SWPPP.
The controls to be implemented at each construction activity will reflect the identified potential
sources of pollutants at each construction site. This list of sources will be different for each
construction activity. It is recommended that the SWPPP personnel or committee be
responsible for implementing the appropriate control measures for the construction activity.
Each construction activity will find some solutions more appropriate or feasible than others.
Nonpoint source pollutants are transported to surface water by a variety of means, including
runoff and ground water infiltration. Ground water and surface water are both considered part
of the same hydrologic cycle when designing management measures. Ground water
contributions of pollutant loadings on surface waters are often very significant. The transport
                                                5-3
EP 1110-1-16
28 Feb 97
of nonpoint source pollutants to surface waters through ground water discharge is governed
by physical and chemical properties of the water, pollutant, soil, and aquifer.
The combination of source control and delivery reduction measures and the application of
those measures as components of management systems are dependent upon site-specific
conditions. Technical factors that may affect the suitability of management measures include,
but are not limited to, land use, climate, size of drainage area, soil permeability, slopes, depth
to water table, space requirements, the type and condition of the receiving waters, depth to
bedrock, and the pollutants to be addressed.
Source control is the first opportunity in any nonpoint source control effort. Source control
methods vary for different types of nonpoint source problems. Examples of source control
include:
       (2)     Preventing nonintroduced pollutants (such as loose dirt and sediments) from
               leaving the site during land-disturbing activities.
                                               5-4
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
facilities, and any structural source controls already in place, such as drip pads, sumps, and
tank containment.   Each contractor should be directly responsible for inspection, testing,
adjustment, andrepair of their contractor-owned facilities andequipment,     subject to the
supervision and review bythe SWPPP committee.          Contractor-owned facilities, equipment,
and maintenance records will be reviewed by construction activity SWPPP personnel on a
regular scheduled basis.
       ●
               Periodic inspections of identified equipment and systems.
                                                5-5
EP 1110-1-16
28 Feb 97
Inspection and maintenance guidelines for construction equipment should follow the
manufacturer’s specifications. The equipment itself should be serviced in designated areas as
indicated above. Special attention must be given to those portions of the equipment that
come into contact with any suspected pollutant. These portions include, among others: trams
or conveyor mechanisms, pipes for liquid conveyance (including vacuum hoses for liquid
extraction), tanks and associated valves, fittings, nozzles, and tank seams. Particular
attention should be given to remedying leaks and replacement of deteriorated rubber or plastic
hoses, pipes, washers, and gaskets.
Good housekeeping refers to the cleaning and maintenance practices conducted at the
construction activity. Good housekeeping is an important component of the pollution
prevention plan. Periodic training of employees in housekeeping techniques for those areas
of the construction activity where pollutant sources are found reduces the significant material
contamination of storm water. Housekeeping practices include:
       .       Safe and orderly storage of construction debris, chemicals, and other significant
               materials.
Maintenance areas should be kept clean. Chemicals, grease, oil, solvent, and fuel spills
should be collected by use of absorbents and booms where necessary. Disposal of these
                                              5-6
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
Cleaning protocols should be site-specific. The protocols should fit the nature of construction
activity (and tenant organizations). The protocols should be developed to meet the site-
specific requirements of the construction activity. The protocols should cover:
. Frequency of inspection.
       ●
               Records of inspection and filing requirements.
Pollution prevention often involves delivery reduction (intercepting pollutants prior to delivery to
the receiving waters) in addition to appropriate source control measures. Management
measures include delivery reduction practices to achieve the greatest degree of pollutant
reduction economically achievable, as required by NPDES regulations.
Delivery reduction practices intercept pollutants leaving the source by capturing the runoff or
infiltrate, followed either by treating and releasing the effluent or by permanently keeping the
effluent from reaching a surface or ground water resource. By their nature, delivery reduction
practices often bring with them side effects that must be accounted for. For example,
management practices that intercept pollutants leaving the source may reduce runoff, but also
increase infiltration to ground water. These devices, although highly successful at controlling
                                                5-7
EP 1110-1-16
28 Feb 97
suspended solids, may not, because of their infiltration properties, be suitable for use in areas
with high ground water tables and nitrate or petroleum residue problems. The performance of
delivery reduction practices is to a large extent dependent on suitable designs, operational
conditions, and proper maintenance. For example, filter strips may be effective for controlling
particulate and soluble pollutants where sedimentation is not excessive, but may be
overwhelmed by high sediment input. In many cases, filter strips are used as pretreatment or
supplemental treatment for other practices within a management system.
The evolution of the need to manage or control storm water runoff has directly paralleled the
evolution of Iand development and its impact on the environment.      In the past, control of storm
water was attempted by maximizing conveyance with rapid downstream disposal of surface
water. The cumulative effects of this practice have created frequent downstream flooding and
depletion of underground water supplies. Until the early 1970’s little or no consideration was
given to the downstream impacts of such activity. Current practices dictate the attenuation of
design peak flows to predevelopment rates. While this approach has proven reasonably
effective in curtailing flooding problems, it does not mitigate the adverse impacts of pollutant
export. The first flush of pollutants refers to the higher concentrations of storm water
pollutants that characteristically occur during the early part of a storm with concentrations
decaying as the runoff continues. Concentration peaks and decay functions vary from site to
site and from region to region, depending on contributing Iand use, the pollutants of interest,
and the characteristics of the drainage basin. Studies have indicated that for a variety of land
uses the first 1.25 cm (0.5 in.) of each runoff contains 80 to 95 percent of the total annual
loading of most storm water pollutants. The best available procedures for storm water
management include both structural and nonstructural components and involve a combination
of detention, infiltration, and filtering devices. Treatment systems, rather than individual
practices, will tend to achieve the greatest pollutant reduction goal. Treatment systems should
include source control, storm water management, and riparian protection to achieve the
highest level of effectiveness.
                                                5-8
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
Storm water treatment systems are site-specific and their effectiveness is highly variable and
dependent on many factors. Practices or combinations of practices that are considered to be
“best available” in some or in many situations, nevertheless, may not be the most effective or
economically achievable for a particular site, and may even be entirely ineffective for the site.
A system of practices should be tailored to a particular site to avoid selection of unsuitable
practices, maintenance problems, or failure to achieve desired pollutant reduction.
Storm water management controls are constructed to prevent or control pollution of storm
water after the construction is completed. The general permit requires that the pollution
prevention plan include a description of the measures that will be installed to control pollutants
in storm water after construction is complete. For sites in which the development results in
runoff flows that are higher than preconstruction levels, the SWPPP must include a technical
explanation of why a particular storm water management measure was selected.
Selection of the most appropriate BMP depends upon a number of factors associated with site
conditions. EPA expects that most sites can employ measures to remove 80 percent of the
total suspended solids from postconstruction runoff. When selecting BMP’s for a development
project, consider the impacts of these measures on other environmental media (e.g., land, air,
and ground water).
In addition to pollutant removal, the SWPPP must address velocity dissipation at discharge
locations. Development usually means an increase in speed with which the site will drain
because of the addition of paved areas, storm sewers, curbs, gutters, etc. The general permit
requires that the velocity dissipation devices be placed along the length of any outfall where
the discharge from the developed area may erode the channel. See Section 3.3 for further
information on runoff calculations.
                                               5-9
EP 1110-1-16
28 Feb 97
Retrofit projects must take into account a number of site-specific factors. Nature of pollutants,
loading rates, classification of receiving waters, location and condition of existing storm drains,
existing and proposed land uses, location of existing utilities, soil characteristics, and
floodplain location are but a few. A brief discussion of these practices follows:
Pond Systems
The ponds described in the following paragraphs range from completely dry structures to
permanently wet structures with various combinations included. In addition, wetland
components are discussed for their ability to enhance pollutant removal, create habitat
diversity, and provide visual interest.
Wet Extended Detention Pond - A permanent pool system containing a forebay near the inlet
to trap sediments and a deeper pool near the riser. This pond system provides an optimal
combination of downstream channel protection and pollutant removal. Extended detention wet
ponds are generally the most cost-effective urban/coastal practices available for pollutant
removal and storm water control.
Wet Pond - A pond system with all of its storage utilized as a permanent pool. This system
traps sediments and may provide pollutant removal through biological uptake from aquatic
wetland plant species. In addition, a wet pond can be an attractive aesthetic feature.
Extended Detention (ED) Micro-Pool - A dry ED system containing one or two small
permanent pools for pollutant removal. One micro-pool located near the inlet acts as a
sediment forebay. The micro-pool system has a much lower maintenance burden than
conventional dry ED pond systems and is a particularly useful design for fingerprinting a pond
into a sensitive woodland or wetland area.
                                               5-1o
                                                                                       EP 1110-1-16
                                                                                          28 Feb 97
Extended Detention Shallow Marsh - A system utilizing emergent aquatic wetland plant
species as its principal pollutant removal mechanism. The ED shallow marsh typically
consists of a O- to 1-meter- (O-3 feet) deep irregularly shaped permanent pool, creating
diverse wetland habitats in a relatively small space, while providing moderate levels of soluble
pollutant removal.
Shallow Marsh - A system with much of its storage devoted to a shallow marsh, this pond
design can consume a great deal of land area. However, with proper grading, design, and
propagation techniques, this system can result in the creation of an extensive, high quality
emergent wetland habitat. The shallow marsh can achieve high removal rates of soluble and
particulate pollutants through the biological uptake mechanism of emergent aquatic plants.
In-Filter Drv Pond - An innovative dry pond system for sites having permeable soils that
promote infiltration. Design includes storm water detention, pretreatment via plunge pools and
grassed swales, and a series of infiltration trenches and basins.
Dry Extended Detention Pond - A pond system typically comprised of two stages: The upper
stage is graded to remain dry except for infrequent storms; whereas the lower stage is
designed for regular inundation. Runoff pretreatment is difficult to achieve with this pond
system, and it is equally difficult to prevent clogging of the ED control device.
Wet Ponds and Wet Extended Detention Ponds are extremely effective water quality practices.
When properly sized and maintained, Wet Ponds and Wet Extended Detention Ponds can
achieve high removal rates for sediment, biochemical oxygen demand (BOD), nutrients, and
trace metals. Biological processes within the pond also remove the soluble nutrients (nitrate
and ortho-phosphorus) that contribute to nutrient enrichment (eutrophication).      Soluble nutrient
removal is achieved through a process known as biological uptake where algae and other
aquatic plants convert the soluble nutrients into biomass which eventually settles into pond
sediments and is later consumed by bacteria. Some of the nutrients are recycled to the water
column, but most nutrients remain in the consolidated sediments.
                                               5-11
EP 1110-1-16
28 Feb 97
Wet Extended Detention Ponds are most cost effective in larger, more intensely developed
sites. Pond practices normally require a significant contributing watershed area (greater than
4 hectares or 10 acres) to ensure proper operation. Positive impacts associated with wet
pond systems can include: creation of local wildlife habitat, increased property values,
recreation, and landscape amenities.
Extended Detention Ponds are effective in controlling postdevelopment peak storm water
discharge rates to a desired predevelopment level for the design storm(s) specified. If storm
water is detained for 24 hours or more, as much as 90-percent removal of particulate         or
suspended solid pollutants is possible. It should be noted, however, that extended detention
ponds have the disadvantage of elevating water temperatures, thus potentially contributing to
thermal pollution. Their use may be inappropriate in some locations, such as, adjacent to
trout streams. In addition, care should be taken not to reduce base flows below those
necessary to sustain the resident aquatic habitat.
Infiltration Systems
The infiltration systems described below range in design from stone-filled trenches and basins
to permeable asphalt pavement. All utilize differing methods for removing soluble and fine
particulate pollutants found in storm water runoff. To prevent infiltration systems from
becoming clogged with fine sediment, it is essential to pretreat the incoming runoff. Methods
of pretreatment range from filter cloth to vegetated filter strips. With pretreatment, infiltration
systems can be an effective component of a water quality management measure.
It is important to recognize that infiltration systems create a risk of transferring pollutants from
surface water to ground water. Therefore, infiltration systems should not be used near wells,
in wellhead protection areas, in areas with high ground water, or in karstic terrain or in settings
in which drinking water supplies may become contaminated. Furthermore, concentrations of
toxic materials leached into the substrate could result in a hazardous waste designation for
the area subject to regulations under CERCLA.
                                                5-12
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
Infiltration Trench #1 - An infiltration trench works by diverting storm water into a shallow (1 to
2.5 meter or 3 to 8 feet) excavated trench which has been backfilled with stone to form an
underground reservoir. Runoff is then either exfiltrated into the substrate or collected in
underdrain pipes and conveyed to an outfall. Infiltration trenches are an adaptable practice
that adequately removes both soluble and particulate pollutants. They are primarily an onsite
control and are seldom practical or economical for drainage areas larger than 2 to
4 hectares (5 to 10 acres). Infiltration trenches are one of the few practices that adequately
provide pollutant removal on small sites of infill development. They preserve the natural
ground water recharge capabilities of a site and can often fit into margins, perimeters, and
other unused areas of the site. A disadvantage is that infiltration trenches require careful
construction, pretreatment, and regular maintenance to prevent premature clogging.
Infiltration trenches can be used effectively in sandy or sandy loam soil areas but are much
less effective for clayey or silty soils.
Infiltration Trench #2 - Similar to the trench system described above, this design accepts
sheet flow from the lower end of a parking lot or paved surface. Runoff is diverted off the
paved parking lot through slotted curbs. The slotted curbs function as a level spreader for
storm water. A grass filter strip separates the trench from the paved surface for capture of
sediments. This trench includes a perforated PVC-type pipe for passage of large design
storm events. At the end of the trench is a grassed berm to ensure that runoff does not
escape.
Infiltration Basin - Infiltration basins are an effective means for removal of soluble and fine
particulate pollutants. Unlike other infiltration systems, basins are easily adaptable to provide
full control for peak storm events. Basins can also serve large drainage areas (up to
20 hectares or 50 acres). Basins are a feasible option where soils are permeable. Basins are
advantageous in that they can preserve the natural water table of a site, serve larger
developed areas, be used as a construction sediment basin during construction and converted
later to a long-term BMP, and are reasonably cost-effective in comparison to other practices.
                                               5-13
EP 1110-1-16
28 Feb 97
One disadvantage is the need for frequent maintenance. In addition, infiltration basins have
sometimes failed because they were installed in unsuitable locations or soils.
Drv Well - A small infiltration system designed to accept storm water from a roof-drain
downspout.     Rather than dispersing its storm water across a paved surface or grassed area,
the downspout pipe connects directly into the dry well which filters rooftop runoff into soils.
This system should not be used near foundations where expansive soils are found, as
foundations may be damaged.
From a pollutant removal standpoint, Infiltration Trenches, Basins, and Porous Pavement have
a moderate to high removal capability for both particulate and soluble pollutants, depending
upon how much of the annual runoff volume is effectively exfiltrated through the soil layer. It
should be noted that infiltration practices should not be entirely relied upon to achieve high
levels of particulate pollutant removal (particularly sediments), because these particles can
rapidly clog the device. For these systems to be effective, particulate pollutants must be
removed before they enter the structure by means of a filter strip, sediment trap, or other
pretreatment devices, and these devices must be regularly maintained.
                                               5-14
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
Filter Strips
The filter systems described below rely on various forms of erosion-resistant vegetation to
amplify particulate pollutant removal, improve terrestrial habitat, and enhance the appearance
of a site. In addition, filter systems can improve both the performance and amenity value of
pond and infiltration practices via storm water pretreatment.
Grass Filter Stri~ - These are similar to a grassed swale, but they can only accept overland
flow. Filter strips are effective when used to protect surface infiltration trenches from clogging
by sediment. They are effective in removal of sediment, organic material, and trace metals.
They should be used as a component in an integrated storm water management system.
Filter strips are inexpensive to establish if presewed prior to site development.   As with all
filter systems, long-term maintenance (mowing, inspection for short circuiting, etc.), should be
included in overall costs.
Riparian Buffer Strip - Riparian buffer strips improve water quality by removing nutrients,
sediment and suspended solids, and pesticides and other toxins from surface runoff as well as
from subsurface and ground water flows. The pollutant removal mechanism associated with
riparian vegetation combines the physical process of filtering and the biological processes of
nutrient uptake and denitrification.
Grassed Swale - This is a grassed, low gradient conveyance channel that provides some
water quality improvements for storm water via natural filtration, settling, and nutrient uptake of
the grass cover. Often used as an alternative to curb-and-gutter drainage conveyance,
grassed swales affect peak discharges by lengthening the time of concentration. They can
also be fitted with low check dams to increase removal efficiency via temporary pending.
Sand Filters - Sand filters are a water quality control filtration system used to remove large
particulate     from runoff and protect filter media from excessive sediment loading at storm
                                                 5-15
EP 1110-1-16
28 Feb 97
water quality control basins. Sand filters can be used independently or with a dry pond basin
element.
Peat/Sand Filters - This is a man-made soil filter system utilizing the natural absoptive
features of peat. The system features a grass cover crop and alternating sublayers of peat,
sand, and a perforated pipe underdrain system. Systems are presently used for municipal
waste effluent treatment and are being adapted for use in storm water management.
Filter strips have a low-to-moderate capability of removing pollutants in urban runoff and
exhibit higher removal rates for particulate     rather than soluble pollutants. Pollutant removal
techniques include filtering through vegetation and soil, settling and deposition, and uptake by
vegetation.     Riparian buffer strips appear to have a higher pollutant removal capability than
grass filter strips. However, length, slope, and soil permeability are critical factors that
influence the effectiveness of any strip. Another practical design problem is prevention of
storm water from concentrating and thereby “short-circuiting” the strip.
Oil/Water Separators
There are several types of oil-water separators. The basic separators that could be utilized at
a construction activity are listed as follows:
                                                 5-16
                                                                                    EP 1110-1-16
                                                                                       28 Feb 97
API Separator - The API separator consists of a rectangular vault with a series of baffles.
Some systems have sophisticated equipment for skimming and removal of oil and other
materials.
CPI Separator - The CPI separator consists of a vault that contains a series of closely aligned
parallel plates made of fiberglass. The plates are positioned at an angle to the direction of
inflow from O to 60 degrees.
Oil/water separators may be used within a storm drainage system or as a pretreatment for
discharge into the sanitary system or hold tank for removal. An SC separator is effective for
retaining small fuel or oil spills. The API and CPI separators are effective in removing diluted
oil droplets from storm water. Maintenance must be performed regularly. Oil/water separators
must be cleaned frequently to keep accumulated oil from escaping during larger storm events.
                                              5-17
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
6.1 Mobilization/impiementation
The first step of mobilization should be the implementation of controis. The controis shouid be
constructed or appiied in accordance with state or iocai standard specifications.   If there are
no state or iocal specifications for control measures then the controis should be constructed in
accordance with Appendix C. in any event the controls must be constructed in accordance
with good engineering practices and in compliance with NPDES regulations. Appendix C iists
typical design standards for structural control measures. The controis should be constructed
and the stabilization measures applied in the order indicated by the sequence of major
activities.
To ensure that controls are adequately implemented, it is important that the work crews
installing the measures are experienced and/or adequately trained. Improperly installed
controls can have little or no effect and may actually increase pollutant export. It is also
important that ali other workers on the construction site be made aware of the controls so that
they do not inadvertently disturb or remove them.
inspection and maintenance of the control measures are as important to poiiution prevention
as proper planning and design. inspection should be performed at the frequency specified in
the SWPPP and/or the issued permit. Each state has different inspection         and reporting
requirements,     the reader is encouraged to contact the permit authority for the states in
question.     The inspector should note any damage or deficiencies in the control measures in
an inspection report. An example of an inspection report can be found in Appendix D, as
Exhibit D-2. The operator should correct damages or deficiencies as soon as practicable after
the inspection, and any changes that may be required to correct deficiencies in the SWPPP
shouid be made as soon as practicable after the inspection. In addition to the inspection and
                                                6-1
EP 1110-1-16
28 Feb 97
maintenance reports, the operator should keep records of the construction activity on the site.
In particular, the operator should keep a record of dates when each activity starts and is
completed. Exhibits D-2 through D-4, in Appendix D may be used to record this information.
The Inspection and Maintenance Report Forms are organized into three basic management
measures: (1) Structural Controls, (2) Vegetative Controls, and (3) Management Measures.
The particular practices associated with these measures are located in Appendix C, and are
categorized in Section 3.4.4. The general permit requires inspection every 7 days or within
24 hours of a storm event of 12.5 mm (0.5 inch) or more. All disturbed areas of the site,
areas for material storage, locations where vehicles enter or exit the site, and all of the
erosion and sediment controls that were identified as part of the plan must be inspected.
Controls must be in good operating condition until the area they protect has been completely
stabilized and the construction activity is complete. The construction project manager will
designate an inspector for monitoring BMP’s (these inspections can be performed as part of a
regular construction inspection program). As the principal permittee, COE will also regularly
inspect each construction site to determine compliance with provisions of the SWPPP.
Construction sites which do not comply with provisions of the SWPPP will be shut down by
COE until compliance is achieved.
Designated personnel for each contractor/tenant construction project should be listed in the
Pollution Prevention Committee Members form, Exhibit D-1, in Appendix D.
6.4 Training
Personnel performing site inspections (COE and tenant projects) are required to be
experienced in construction practices and erosion and sediment control practices. Many
states and organizations offer general training programs in sediment and erosion control.
Training as a whole should address:
                                               6-2
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
       ●
               The location and type of control measures.
       ●
               The construction requirements for the control measures.
       ●
               Spill response.
       ●
               Inspection and maintenance record-keeping requirements.
       ●
               Pollution control laws and regulations.
       ●
               Good housekeeping and material management practices.
       ●
               Particular construction activity features and operations designed to minimize
               storm water pollution.
COE will review SWPPP requirements with each tenant or contractor before approving
construction activities.
A large part of the success of an SWPPP is the capability and interest of the employees
responsible for implementing and maintaining the program. Personnel must understand the
importance of the program and the goals of the SWPPP. Personnel must be trained in the
techniques of response, removal, and documentation.      The permit authority representatives
will be inspecting the general permit participants, and it is important that they are received by
trained, knowledgeable personnei who have access to the SWPPP, environmental files, and
other documentation.     The SWPPP documentation must be current and complete when
inspected.
Annual training workshops and meetings should be established, at which time employee
participation and input should be encouraged. Training schedules should be recorded (see
Table E-5, Appendix E). New techniques of storm water management controls as well as
changes in permit compliance or limits should be explained to the employees.
                                               6-3
EP 1110-1-16
28 Feb 97
6.5.1 Certification
The general permit requires nonstorm water discharges to be eliminated prior to the
implementation of the SWPPP.      Existing industrial facilities must certify that there are no
nonstorm water discharges present in the storm water drainage system.         All facilities must
The certification page for nonstorm water certification is shown in Appendix F. A certification
page should be signed and retained as part of the SWPPP documentation.           All forms filled out
while surveying and evaluating outfalls should also be inserted into the nonstorm water
discharge section of the SWPPP. A record of methods used, dates, and time conducted
If certification is not feasible because of the inability to eliminate the nonstorm water discharge
because of the need for significant structural changes, the construction activity must notify the
permit authority. This notification should include a summary of why the extension in
eliminating nonstorm water discharges is required and a schedule indicating when nonstorm
water discharges will be eliminated. The schedule is subject to modification by the permit
authority.
The inspection for nonstorm water discharges should take place concurrently with the
inspection of the drainage system (Section 6.5.3).
                                               6-4
                                                                                        EP 1110-1-16
                                                                                           28 Feb 97
There may be several drainage systems serving the construction activity depending on
topography. The inspection for each drainage system should begin at the farthest discharge
point from the center of construction activity operations. The farthest discharge point may be
at the property boundary, or it may be at the point where the “waters of the United States”
cross the construction activity property and intersect with a drainage system.
       ●
               Flow            If flow is present, and precipitation has not occurred within the
                               past 3 days, there maybe a problem requiring further
                               investigation unless the source is positively known and is
                               nonpolluting.
       ●
               Odor            The presence of any odor from the drainage system may indicate
                               an unnatural occurrence.
       ●
               Clarity         If water is present, standing or flowing, and it is not clear,
                               pollution should be suspected.
       ●
               Floatable       If there is floating debris, garbage, sewage, or an oily sheen, the
                               source of the material should be identified.
       ●
               Stains, etc.    If stains are present on lined channelslpipes, or other than the
                               normal vegetation or soil color, this may be an indicator requiring
                               further investigation.
       ●
               Vegetation      If vegetation in the discharge channel is more luxurious or,
                               conversely, appears stressed in comparison to adjacent
                               vegetation, this is likely an indicator of excess nutrients or other
                               problems and requires further investigation.
In addition, inspection should note siltation or scour problems below outfalls, or at system
confluences, for referral to construction activity maintenance officials.
                                                 6-5
EP 1110-1-16
28 Feb 97
Chemical inspection of outfalls may make use of dry weather monitoring kits if dry weather
flow is observed from the discharge points(s) or stagnant pools are observed at the discharge
point(s). The results of the tests using these kits can assist in identifying possible problem
sources upstream in the system,
From the discharge point(s), the inspection should proceed upstream. Similar inspections
should be made of each intervening discharge point, if the storm drain is not continuous to its
final outfall. If the storm drain is continuous, inspections should be made at each manhole
upstream to the inlets of the storm water drainage system. (Inspectors     shall not enter
manholes   unless OSHA-approved       confined space entry procedures       are followed.)    The
inspectors should make note of any of the items listed above. Particular attention should be
given to connections in the storm water drain lines or any inlet lines not shown on the plans.
Patched pavements may be indicators of postdesign connections.
Attention should be given to determine the discharge destination of floor drains. These
drains must be connected to the sanitary sewer system.
The flow paths to each of the inlets must be inspected, as well as the inlets themselves.
Particular attention should be given to the presence of grease, oil, fuel, chemical, or solvent
residues along these flow paths, as well as any other staining that could indicate a pollutant
that could be washed down the storm drain. Inlet sumps should be inspected. Debris
collected in inlet sumps should be removed regularly and before any substantial buildup
occurs.
The physical condition and cleanliness of the components of the drainage system must be
inspected as well. The inspector should make sure that the drainage areas are clean and free
of debris. The physical integrity of all conveyances and discharge points should be inspected
for corrosion, seam and joint connections, erosion, silting, leaks, and condition of dikes,
berms, and other structures of the storm water controls.
                                               6-6
                                                                                      EP 1110-1-16
                                                                                         28 Feb 97
Tabie D-6, Appendix D, wiii be used to record drainage system maintenance and inspection
observations.
inspection of paved areas is not a difficuit task, because aii surfaces can be easiiy seen. With
respect to storm water poiiution, if the paved areas are free of visibie poiiutants, storm water
contamination is less iikeiy.
inspections wiii focus on maintenance activities that assure that paved surfaces are clean of
chemicais, grease, oii, soivents, and fuels, and that other potentiai pollutants are kept off the
paved areas, or that they are kept covered and out of storm water fiow paths.
Paved areas wiii aiso be inspected for cracks. Where there is a significant potentiai for a spiii,
such as drip pads or fueiing stations, cracks may aliow pollutants to seep into the soii where
ground water contamination couid occur. Maintenance activities couid inciude proper grouting
of aii pavement joints.
Herbicides and petroieum products are sometimes applied to pavement cracks and at joints to
controi vegetation growth. The use of herbicides or other chemicals shouid be reviewed, as
these materials may combine with storm water runoff or infiltrate into the underlying soii. If
herbicides must be used, those with iow toxicity and persistence shouid be considered. The
frequency of application should be reduced to the minimum required. Grouting of joints and
cracks may offer an alternative to herbicide application.
                                                6-7
EP 1110-1-16
28 Feb 97
As soon as practicable after construction activities have been completed in a disturbed area,
permanent stabilization should be started to prevent further erosion of soil from that area. All
disturbed areas of a site, except those portions which are covered by pavement or a structure,
should be finally stabilized once all construction activities are completed. Final stabilization
requirements may vary from permit to permit. Final stabilization is defined by the EPA
General Permit as meaning that all soil-disturbing activities at the site have been completed,
and that a uniform perennial vegetative cover with a density of 70 percent of the cover for the
unpaved areas has been established or equivalent stabilization measures, such as the use of
riprap, gabions, or geotextiles, have been employed.
Operators of a construction site must continue to comply with permit conditions until: (1) they
no longer meet the definition of an operator of a construction site; or (2) the construction
activity is complete, all disturbed soils have been finally stabilized, and temporary erosion and
sediment controls have been or will be removed. A permittee should submit a Notice of
Termination (NOT) to inform EPA that they are no longer an operator of a construction activity.
The NOT is a one-page form (see Appendix F) which should be completed and submitted to
the permitting authority when a site has been finally stabilized or when an operator of a
construction activity changes. The NOT is typically the final task required to comply with the
requirements of an NPDES storm water permit for a construction activity. The NOT
communicates to the permitting authority that the construction activity has ceased and the
area is stabilized.
Note that when there is a change in operators of a construction activity, then the new operator
must submit an NOI to be covered by the permit at least 2 days before the change in
operator.
                                                6-8
                                                                                     EP 1110-1-16
                                                                                        28 Feb 97
Where the NOT’s are submitted depends on the permitting authority. Some state agencies do
not require submittal of NOT’S. Federally regulated NPDES permits require NOTS to be
submitted to the following address:
Following the termination of construction activities, the permitters must keep a copy of the
SWPPP and records of all the data used to complete the NOI for a period of at Ieast 3 years
following final stabilization.   The record retention period may be extended by the permitting
authority’s request.
6-9