0% found this document useful (0 votes)
9 views4 pages

Summary of Cost (Boq)

The document is a detailed Bill of Materials summarizing costs for various construction works including plan preparation, site clearing, concrete works, painting, architectural works, and plumbing/electrical works. It outlines material costs, manpower, equipment, and includes subtotals, contingencies, overhead, and profit margins leading to a total estimated cost. The final total estimated cost for all works is 41,689.96.

Uploaded by

Jesus Abad Jr.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views4 pages

Summary of Cost (Boq)

The document is a detailed Bill of Materials summarizing costs for various construction works including plan preparation, site clearing, concrete works, painting, architectural works, and plumbing/electrical works. It outlines material costs, manpower, equipment, and includes subtotals, contingencies, overhead, and profit margins leading to a total estimated cost. The final total estimated cost for all works is 41,689.96.

Uploaded by

Jesus Abad Jr.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

BILL OF MATERIALS (Summary of Cost)

PLAN PREP. 1 lumpsum


Materials:
Blueprinting 3 sheets 30.00 90.00
Architectural (3D only) 1 lot 6,000.00 6,000.00
Architectural Sign & Sealed 4 sheets 5,000.00 20,000.00
Miscellaneous 1 lot 500.00 500.00
Sub-total 26,590.00
per lumpsum
SITE CLEARING & CLEANING: 1 lumpsum
Materials:
Empty Sacks 100 pcs. 12.00 1,200.00
Walis 2 lot 200.00 400.00
Miscellaneous 1 lot 5,000.00 5,000.00
Sub-total 6,600.00
per lumpsum
CONCRETE WORKS: (W/ REBARS & FORM WORKS)
FOOTINGS: 6.10 cu.m.
Materials:
Portland Cement 10.00 bags 240.00 2,400.00
Mixing Sand 2.00 cu.m. 500.00 1,000.00
Gravel 3/4" 2.00 cu.m. 1,000.00 2,000.00
20mm dia. DSB - pcs. 350.00 -
#16 G.I. Wire 3.00 kg. 80.00 240.00
Miscellaneous 1 lot 500.00 500.00
Sub-total 6,140.00

Manpower:
1 Site Supervisor 4 days 592.31 2,369.23
1 Working Leadman 4 days 447.80 1,791.20
1 Steelman 4 days 412.80 1,651.20
2 Laborers 4 days 397.80 3,182.40
Sub-total 8,994.03

Equipments:
1 One-Bagger Concrete Mixer 2 day 1,800.00 3,600.00
1 Concrete Vibrator 2 day 1,200.00 2,400.00
Sub-total 6,000.00

Total Amount 21,134.03


Contingency (5%) 1,056.70
DIRECT COST 22,190.73

Overhead (5%) 1,109.54


Profit (15%) 3,328.61

TOTAL ESTIMATED COST 26,628.88


Tax 2% 532.58
27,161.46
4,451.24
per cu.m.
PAINTING WORKS:
EXTERIOR: 280.00 sq.m.
Materials:
Concrete Neutralizer 6.00 gals. 450.00 2,700.00
Latex Primer 10.00 gals. 600.00 6,000.00
Semi-Gloss Latex 10.00 gals. 615.00 6,150.00
Masonry Putty 3.00 gals. 550.00 1,650.00
Miscellaneous 1 lot 1,000.00 1,000.00
Sub-total 17,500.00

Manpower:
1 Project Manager 4 days 1,153.85 4,615.40
1 Site Supervisor 4 days 592.31 2,369.23
1 Working Leadman 4 days 472.80 1,891.20
1 Painters 4 days 447.80 1,791.20
2 Laborers 4 days 397.80 3,182.40
Sub-total 13,849.43

Total Amount 31,349.43


Contingency (5%) 1,567.47
DIRECT COST 32,916.90

Overhead (5%) 1,645.85


Profit (15%) 4,937.54

TOTAL ESTIMATED COST 39,500.28


Tax 2% 790.01
40,290.29
143.89
per sq.m.
ARCHITECTURAL WORKS:
INTERIOR CEILING: 64.84 sq.m.
Materials:
6" x 12' Prepainted Wood Accent PVC Ceiling Panel 20.00 pcs. 400.00 8,000.00
0.5mm THK Fascia Cover - pcs. 1,080.00 -
0.5mm THK Corner Cap 2.00 pcs. 540.00 1,080.00
5/32 x 1/2 Blind Rivets 2.00 boxes 1,000.00 2,000.00
1'' x 1'' x 8' Wall Angle 10.00 pcs. 40.00 400.00
Delivery Charge 1.00 lot 6,000.00 6,000.00
Miscellaneous 1 lot 1,000.00 1,000.00
Sub-total 18,480.00

Manpower:
1 Project Manager 3 days 1,153.85 3,461.55
1 Site Supervisor 3 days 592.31 1,776.92
1 Working Leadman 3 days 472.80 1,418.40
1 Carpenter 3 days 447.80 1,343.40
2 Laborers 3 days 397.80 2,386.80
Sub-total 10,387.07

Total Amount 28,867.07


Contingency (5%) 1,443.35
DIRECT COST 30,310.43

Overhead (5%) 1,515.52


Profit (15%) 4,546.56

TOTAL ESTIMATED COST 36,372.51


Tax 2% 727.45
37,099.96
572.18
per sq.m.
WINDOWS and DOORS: - lumpsum
Materials:
W1 1.60x1.30 Sliding- 3 Panels 1.00 set 11,100.00 11,100.00
D1 0.40x0.50 Awning- 1 Panel 1.00 set 2,333.00 2,333.00
Delivery Charge 1.00 lot 6,000.00 6,000.00
Miscellaneous 1.00 lot 5,000.00 5,000.00
Sub-total 24,433.00

Manpower:
1 Project Manager 1 days 1,153.85 1,153.85
1 Site Supervisor 1 days 592.31 592.31
Labor 1,746.16

Total Amount 26,179.16


Contingency (5%) 1,308.96
DIRECT COST 27,488.12

Overhead (5%) 1,374.41


Profit (15%) 4,123.22

TOTAL ESTIMATED COST 32,985.74


Tax 2% 659.71
33,645.45
per lumpsum
TILE WORKS: #REF! sq.m.
600x600mm Ceramic Glazed Tiles #REF! pcs. 220.00 #REF!
300x300mm Ceramic Unglazed Tiles #REF! pcs. 150.00 #REF!
600x600mm Granite Countertop Tiles #REF! pcs. 350.00 #REF!
Decorative Stone Wall Cladding #REF! sq.m. 750.00 #REF!
Tile Adhessive #REF! bags 250.00 #REF!
Tile Grout #REF! packs 75.00 #REF!
Cement #REF! bags 250.00 #REF!
Diamond Cutting Disk 5.00 pcs. 150.00 750.00
Mixing Sand #REF! cu.m. 500.00 #REF!
Miscellaneous 1 lot 5,000.00 5,000.00
Sub-total #REF!

1 Project Manager 2 days 1,153.85 2,307.70


1 Site Supervisor 2 days 592.31 1,184.62
1 Working Leadman 2 days 472.80 945.60
2 Tile Setter 2 days 447.80 1,791.20
2 Laborers 2 days 397.80 1,591.20
Labor 7,820.32

Equipment:
1 Electric Grinder 7 days 150.00 1,050.00
Labor 1,050.00

Total Amount #REF!


Contingency (5%) #REF!
DIRECT COST #REF!

Overhead (5%) #REF!


Profit (15%) #REF!

TOTAL ESTIMATED COST #REF!


Tax 2% #REF!
#REF!
#REF!
per sq.m.
FURNITURES:
Dining Chairs 12 pcs 1,100.00 13,200.00
Round Tables 5 pcs 1,800.00 9,000.00
Dining Table 5 pcs 3,200.00 16,000.00
High Chair 1 pcs 1,100.00 1,100.00
Counter Top 1 pcs 5,500.00 5,500.00
Dorations 6,000.00 6,000.00
Cabinetry 15,000.00 15,000.00
Steel Table 1 pcs 3,000.00 3,000.00
Signage 12,000.00 12,000.00
Subtotal 80,800.00

1 Working Leadman 2 days 650.00 1,300.00


3 Laborers 2 days 550.00 3,300.00

85,400.00

Appliances:
Chest Fridge 1 pc 23,000.00
Rerigerator 1 pc 19,000.00
Stove 1 pc 17,000.00
Griller 1 pc 12,000.00
Storage Rack 2 pcs 5,000.00
Computer 1 pc 25,000.00
Range Good 12,000.00
118000
Subtotal 203,400.00
SANITARY/PLUMBING AND ELECTRICAL WORKS:
PIPES & FITTINGS: 1 lumpsum
Materials:
1/2" dia. Blue Pipe 5 pcs. 350.00 1,750.00
1/2" dia. Blue Tee 2 pc. 65.00 130.00
1/2" dia. Blue Elbow 6 pcs. 65.00 390.00
1/2" dia. Blue Elbow threaded 6 pcs. 65.00 390.00
1/2" x 18" Stainless Flexible Hose 0 pcs. 115.00 -
1/2" dia. Female Adapter 0 pc. 200.00 -
1/2" dia. Check Valve 0 sets 600.00 -
1/2" dia. Gate Valve 1 sets 350.00 350.00
4" dia. PVC Pipes 8 pcs. 470.00 3,760.00
4" dia. PVC Elbow 90 deg. 1 pcs. 65.00 65.00
3" dia. PVC Elbow 90 deg. 1 pcs. 55.00 55.00
3" dia. PVC Cleanout 2 pcs. 115.00 230.00
3" dia. PVC P-Trap 2 pcs. 125.00 250.00
3" dia. PVC Pipes 4 pcs. 110.00 440.00
4" x 4" Stainless floor drain 2 pcs. 250.00 500.00
3" dia. PVC Tee 0 pcs. 130.00 -
Solvent Cement 5 can 450.00 2,250.00
Water Meter w/ accessories 1 lot 2,500.00 2,500.00
Miscellaneous 1 lot 1,000.00 1,000.00
Sub-total 14,060.00

Ceiling Mouted Lights 20 pcs. 220


Pendant Light 4 pcs. 600
Switch 10 pcs. 150
Sacket 8 pcs. 250
Electrical Wire 1 Roll 900
Wire Cover 1 Roll 500

PLUMBING FIXTURES: 1 lumpsum


Materials:
Water Closet 1 pcs. 12,631.00 12,631.00
Mariwasa Ceramic Lavatory Sink 0 sets 2,200.00 -
700x400mm Stainless Sink 2 sets 2,200.00 4,400.00
Shower Head w/ Valve 0 set 1,800.00 -
Lavatory faucet 2 set 1,500.00 3,000.00
Miscellaneous 1 lot 1,000.00 1,000.00
Sub-total 21,031.00
Manpower:
1 Site Supervisor 3 days 592.31 1,776.92
0 Working Leadman 3 days 447.80 -
1 Plumber 3 days 547.80 1,643.40
1 Laborers 3 days 397.80 1,193.40
Sub-total 4,613.72

Total Amount 39,704.72


Contingency (5%) 1,985.24
DIRECT COST 41,689.96

Overhead (5%) 2,084.50


Profit (10%) 4,169.00

TOTAL ESTIMATED COST 47,943.45


Tax 2% 958.87
48,902.32
per lumpsum

TOTAL ESTIMATED COST:


Php. 461,569.17

You might also like