Name Duration Start Finish Predeces…
1 3 UNIT CONSTRUCTION PROJECT 115 d… 5/12/14 8:00… 10/17/14 5:00…
2 PREBUILD FOR ALL 3 UNITS 17 days 5/12/14 8:00… 6/3/14 5:00 PM
3 Deposit to builder- 5% 1 day 5/12/14 8:00 AM 5/12/14 5:00 PM
4 Site Investigation 2 days 5/12/14 8:00 AM 5/13/14 5:00 PM
5 Site Work / Preparation 3 days 5/14/14 8:00 AM 5/16/14 5:00 PM 4
6 Site cut / Excavation 3 days 5/19/14 8:00 AM 5/21/14 5:00 PM 5
7 Under Ground Services (water, gas and electricity, service meters) 5 days 5/22/14 8:00 AM 5/28/14 5:00 PM 6
8 Plumbing and Electrical rough in 3 days 5/29/14 8:00 AM 6/2/14 5:00 PM 7
9 Inspection (Building Surveyor) 1 day 6/3/14 8:00 AM 6/3/14 5:00 PM 8
10 BASE 15 days 6/4/14 8:00 AM 6/24/14 5:00…
11 unit 1 3 days 6/4/14 8:00 AM 6/6/14 5:00 PM
12 Pre-slab(Form Work, Plastic, Wafflepod,Reinforcement etc). 3 days 6/4/14 8:00 AM 6/6/14 5:00 PM 9
13 unit 2 3 days 6/9/14 8:00 AM 6/11/14 5:00…
14 Pre-slab(Form Work, Plastic, Wafflepod,Reinforcement etc). 3 days 6/9/14 8:00 AM 6/11/14 5:00 PM 12
15 unit 3 3 days 6/12/14 8:00… 6/16/14 5:00…
16 Pre-slab(Form Work, Plastic, Wafflepod,Reinforcement etc). 3 days 6/12/14 8:00 AM 6/16/14 5:00 PM 14
17 Pre pour inspection all 3 units (Building Surveyor) 1 day 6/17/14 8:00 AM 6/17/14 5:00 PM 16
18 Concrete Pour- all 3 units 3 days 6/18/14 8:00 AM 6/20/14 5:00 PM 17
19 Post pour Inspection (Building Surveyor) 1 day 6/23/14 8:00 AM 6/23/14 5:00 PM 18
20 Progress payment due to the builder- 15% 1 day 6/24/14 8:00 AM 6/24/14 5:00 PM 19
21 FRAMING 17 days 6/24/14 8:00… 7/16/14 5:00…
22 unit 1 9 days 6/24/14 8:00… 7/4/14 5:00 PM
23 Construct & Erect Frame 3 days 6/24/14 8:00 AM 6/26/14 5:00 PM 19
24 Erect Roof Trusses 3 days 6/27/14 8:00 AM 7/1/14 5:00 PM 23
25 Fascia, Eaves, Gutter and Downpipe 3 days 7/2/14 8:00 AM 7/4/14 5:00 PM 24
26 unit 2 9 days 6/27/14 8:00… 7/9/14 5:00 PM
27 Construct & Erect Frame 3 days 6/27/14 8:00 AM 7/1/14 5:00 PM 23
28 Erect Roof Trusses 3 days 7/2/14 8:00 AM 7/4/14 5:00 PM 24
29 Fascia, Eaves, Gutter and Downpipe 3 days 7/7/14 8:00 AM 7/9/14 5:00 PM 25
30 unit 3 9 days 7/2/14 8:00 AM 7/14/14 5:00…
31 Construct & Erect Frame 3 days 7/2/14 8:00 AM 7/4/14 5:00 PM 27
32 Erect Roof Trusses 3 days 7/7/14 8:00 AM 7/9/14 5:00 PM 28
33 Fascia, Eaves, Gutter and Downpipe 3 days 7/10/14 8:00 AM 7/14/14 5:00 PM 29
34 Frame Inspection (Building Surveyor) 1 day 7/15/14 8:00 AM 7/15/14 5:00 PM 33
35 Progress claim due to builder- 20% 1 day 7/16/14 8:00 AM 7/16/14 5:00 PM 34
3 UNIT CONSTRUCTION SCHULE - page1
Half 2, 2014
Resource Names
M J J A S O N
builder 5/13
builder;surveyor builder;surveyor
builder builder
excavator excavator
plumber plumber
electrician;plumber electrician;plumber
building surveyor;builder building surveyor;builder
concreter concreter
concreter concreter
concreter concreter
building surveyor;builder 6/18
concreter concreter
builder;building surveyor 6/24
builder 6/25
carpenter carpenter
carpenter carpenter
carpenter carpenter
carpenter carpenter
carpenter carpenter
carpenter carpenter
carpenter carpenter
carpenter carpenter
carpenter carpenter
builder;building surveyor 7/16
builder 7/17
3 UNIT CONSTRUCTION SCHULE - pa…
Name Duration Start Finish Predeces…
36 LOCK UP 23 da… 7/16/14 8:00… 8/15/14 5:00…
37 unit 1 16 days 7/16/14 8:00… 8/6/14 5:00 PM
38 Roofing (Colourbond) 3 days 7/16/14 8:00 AM 7/18/14 5:00 PM 34
39 Windows/ Exterior Doors/Garage Doors/Exterior Locks 3 days 7/21/14 8:00 AM 7/23/14 5:00 PM 38
40 Waterproof building skin 3 days 7/24/14 8:00 AM 7/28/14 5:00 PM 39
41 Brickwork 3 days 7/29/14 8:00 AM 7/31/14 5:00 PM 40
42 Plumbing Rough in 3 days 8/1/14 8:00 AM 8/5/14 5:00 PM 41
43 Electrical Rough in 3 days 8/1/14 8:00 AM 8/5/14 5:00 PM 41
44 Lock up & pre plaster 1 day 8/6/14 8:00 AM 8/6/14 5:00 PM 43
45 unit 2 16 days 7/21/14 8:00… 8/11/14 5:00…
46 Roofing (Colourbond) 3 days 7/21/14 8:00 AM 7/23/14 5:00 PM 38
47 Windows/ Exterior Doors/Garage Doors/Exterior Locks 3 days 7/24/14 8:00 AM 7/28/14 5:00 PM 39
48 Waterproof building skin 3 days 7/29/14 8:00 AM 7/31/14 5:00 PM 40
49 Brickwork 3 days 8/1/14 8:00 AM 8/5/14 5:00 PM 41
50 Plumbing Rough in 3 days 8/6/14 8:00 AM 8/8/14 5:00 PM 42
51 Electrical Rough in 3 days 8/6/14 8:00 AM 8/8/14 5:00 PM 43
52 Lock up & pre plaster 1 day 8/11/14 8:00 AM 8/11/14 5:00 PM 51
53 unit 3 17 da… 7/24/14 8:00… 8/15/14 5:00…
54 Roofing (Colourbond) 3 days 7/24/14 8:00 AM 7/28/14 5:00 PM 46
55 Windows/ Exterior Doors/Garage Doors/Exterior Locks 3 days 7/29/14 8:00 AM 7/31/14 5:00 PM 47
56 Waterproof building skin 3 days 8/1/14 8:00 AM 8/5/14 5:00 PM 48
57 Brickwork 3 days 8/6/14 8:00 AM 8/8/14 5:00 PM 49
58 Plumbing Rough in 3 days 8/11/14 8:00 AM 8/13/14 5:00 PM 50
59 Electrical Rough in 3 days 8/11/14 8:00 AM 8/13/14 5:00 PM 51
60 Lock up & pre plaster 1 day 8/14/14 8:00 AM 8/14/14 5:00 PM 59
61 Progress payment due to builder- 25% 1 day? 8/15/14 8:00 AM 8/15/14 5:00 PM 60
62 FIXINGS 47 days 8/14/14 8:00… 10/17/14 5:00…
63 Unit 1 36 days 8/14/14 8:00… 10/2/14 5:00…
64 Heating & Cooling Services 3 days 8/14/14 8:00 AM 8/18/14 5:00 PM 59
65 Insulation / Plaster 5 days 8/19/14 8:00 AM 8/25/14 5:00 PM 64
66 Water Proofing 3 days 8/26/14 8:00 AM 8/28/14 5:00 PM 65
67 Joinery (Kitchen/Wardrobes/Internal doors) 3 days 8/29/14 8:00 AM 9/2/14 5:00 PM 66
68 Tiling 3 days 9/3/14 8:00 AM 9/5/14 5:00 PM 67
69 Fix (Interior doors and window jambs,architraves,moldings,ski… 3 days 9/8/14 8:00 AM 9/10/14 5:00 PM 68
70 Painting 5 days 9/11/14 8:00 AM 9/17/14 5:00 PM 69
3 UNIT CONSTRUCTION SCHULE - page3
Half 2, 2014
Resource Names
M J J A S O N
roofer roofer
window/door manufact… window/door manufacturer
waterproofer waterproofer
bricklayer bricklayer
plumber plumber
electrician electrician
plasterer plasterer
roofer roofer
window/door manufact… window/door manufacturer
waterproofer waterproofer
bricklayer bricklayer
plumber plumber
electrician electrician
plasterer plasterer
roofer roofer
window/door manufact… window/door manufacturer
waterproofer waterproofer
bricklayer bricklayer
plumber plumber
electrician electrician
plasterer plasterer
builder 8/16
electrician electrician
plasterer plasterer
waterproofer waterproofer
carpenter carpenter
tiler tiler
carpenter carpenter
painter painter
3 UNIT CONSTRUCTION SCHULE - pa…
Name Duration Start Finish Predeces…
71 Flooring (carpet/wood) 3 days 9/18/14 8:00 AM 9/22/14 5:00 PM 70
72 Fit Off Plumbing (toilets/sinks/showers/bathtubs/faucets) 5 days 9/23/14 8:00 AM 9/29/14 5:00 PM 71
73 Fit Off Electrical (outlets/switches/lights) 3 days 9/23/14 8:00 AM 9/25/14 5:00 PM 71
74 Final Fit off (bench tops, locks,shower screens, mirrors, flyscre… 5 days 9/26/14 8:00 AM 10/2/14 5:00 PM 73
75 Unit 2 38 days 8/19/14 8:00… 10/9/14 5:00…
76 Heating & Cooling Services 3 days 8/19/14 8:00 AM 8/21/14 5:00 PM 64
77 Insulation / Plaster 5 days 8/26/14 8:00 AM 9/1/14 5:00 PM 65
78 Water Proofing 3 days 8/29/14 8:00 AM 9/2/14 5:00 PM 66
79 Joinery (Kitchen/Wardrobes/Internal doors) 3 days 9/3/14 8:00 AM 9/5/14 5:00 PM 67
80 Tiling 3 days 9/8/14 8:00 AM 9/10/14 5:00 PM 68
81 Fix (Interior doors and window jambs,architraves,moldings,ski… 3 days 9/11/14 8:00 AM 9/15/14 5:00 PM 69
82 Painting 5 days 9/18/14 8:00 AM 9/24/14 5:00 PM 70
83 Flooring (carpet/wood) 3 days 9/23/14 8:00 AM 9/25/14 5:00 PM 71
84 Fit Off Plumbing (toilets/sinks/showers/bathtubs/faucets) 5 days 9/30/14 8:00 AM 10/6/14 5:00 PM 72
85 Fit Off Electrical (outlets/switches/lights) 3 days 9/26/14 8:00 AM 9/30/14 5:00 PM 73
86 Final Fit off (bench tops, locks,shower screens, mirrors, flyscre… 5 days 10/3/14 8:00 AM 10/9/14 5:00 PM 74
87 Unit 3 41 days 8/22/14 8:00… 10/17/14 5:00…
88 Heating & Cooling Services 3 days 8/22/14 8:00 AM 8/26/14 5:00 PM 76
89 Insulation / Plaster 5 days 9/2/14 8:00 AM 9/8/14 5:00 PM 77
90 Water Proofing 3 days 9/3/14 8:00 AM 9/5/14 5:00 PM 78
91 Joinery (Kitchen/Wardrobes/Internal doors) 3 days 9/8/14 8:00 AM 9/10/14 5:00 PM 79
92 Tiling 3 days 9/11/14 8:00 AM 9/15/14 5:00 PM 80
93 Fix (Interior doors and window jambs,architraves,moldings,ski… 3 days 9/16/14 8:00 AM 9/18/14 5:00 PM 81
94 Painting 5 days 9/25/14 8:00 AM 10/1/14 5:00 PM 82
95 Flooring (carpet/wood) 3 days 9/26/14 8:00 AM 9/30/14 5:00 PM 83
96 Fit Off Plumbing (toilets/sinks/showers/bathtubs/faucets) 5 days 10/7/14 8:00 AM 10/13/14 5:00… 84
97 Fit Off Electrical (outlets/switches/lights) 3 days 10/1/14 8:00 AM 10/3/14 5:00 PM 85
98 Final Fit off (bench tops, locks,shower screens, mirrors, flyscre… 5 days 10/10/14 8:00… 10/16/14 5:00… 86
99 Progress payment due to builder - 25% 1 day 10/17/14 8:00… 10/17/14 5:00… 98
100 HANDOVER- ALL 3 UNITS 6 days 10/17/14 8:00… 10/24/14 5:00…
101 Clean 3 days 10/17/14 8:00… 10/21/14 5:00… 98
102 Final Inspection (By Building Surveyor) 1 day 10/22/14 8:00… 10/22/14 5:00… 101
103 Handover to client (homeowner) 1 day 10/23/14 8:00… 10/23/14 5:00… 102
104 Final progress payment to builder- 10% 1 day 10/24/14 8:00… 10/24/14 5:00… 103
3 UNIT CONSTRUCTION SCHULE - page5
Half 2, 2014
Resource Names
M J J A S O N
floorer floorer
plumber plumber
electrician electrician
carpenter carpenter
electrician electrician
plasterer plasterer
waterproofer waterproofer
carpenter carpenter
tiler tiler
carpenter carpenter
painter painter
floorer floorer
plumber plumber
electrician electrician
carpenter carpenter
electrician electrician
plasterer plasterer
waterproofer waterproofer
carpenter carpenter
tiler tiler
carpenter carpenter
painter painter
floorer floorer
plumber plumber
electrician electrician
carpenter carpenter
builder 10/18
cleaner;day labourer cleaner;day labourer
building surveyor;builder 10/23
builder builder
builder 10/25
3 UNIT CONSTRUCTION SCHULE - pa…