Republic of the Philippines
Province of Aklan
Ati-atihan Town of Kalibo
OFFICE OF THE MUNICIPAL PLANNING &
DEVELOPMENT COORDINATOR
October 24, 2024
ENGR. AMALIA L. FRANCISCO
Municipal Engineer/Building Official
Municipal Engineering’s Office
This Municipality
Dear Engr. Francisco,
Warmest greetings!
In preparation for the upcoming Barangay Development Plan Seminar/Workshop scheduled on
October 28-30, 2024, we are in the process of creating a video presentation to showcase the
various development projects in the municipality. To ensure the accuracy and completeness of
the presentation, we would like to request a detailed list of the following:
1. Implemented Projects: Projects that have been initiated or are ongoing.
2. Completed Projects: Projects that have been fully completed, including their timelines and key
achievements.
3. Ongoing Projects: Projects that are currently in progress and their expected completion dates.
Your cooperation in this matter is highly appreciated as it will greatly contribute to the success of
the event. Thank you for your attention and continued cooperation.
Sincerely,
ENGR. MARLO B. VILLANUEVA
Municipal Planning & Development Coordinator
Republic of the Philippines
Province of Aklan
Ati-atihan Town of Kalibo
PROJECT MONITORING COMMITTEE
October 21, 2024
ENGR. AMALIA L. FRANCISCO
Municipal Engineer/Building Official
Municipal Engineering’s Office
This Municipality
Dear Engr. Francisco,
Warmest greetings!
Furnishing you herewith is the copy of the Punch List for the Construct/Rehabilitation of
Drainage Canal System at Brgy. Briones, Kalibo, Aklan.
Thank you for your attention and continued cooperation.
Sincerely,
SBM PHILLIP Y. KIMPO, JR.
SBM/PMC-Chairperson
Republic of the Philippines
Province of Aklan
Ati-atihan Town of Kalibo
PROJECT MONITORING COMMITTEE
October 17, 2024
ENGR. AMALIA L. FRANCISCO
Municipal Engineer/Building Official
Municipal Engineering’s Office
This Municipality
Dear Engr. Francisco,
Warmest greetings!
Furnishing you herewith is the copy of the Accomplishment Report, Punch List, and the Final
Inspection Sign-off for the following projects:
1. Construction of Flood Control Project (Revetment wall)
2. Rehabilitation/Improvement of 3rd Floor New Building
3. Construction of Polyclinic/Satellite Health Center
4. Construction/Improvement of LGU Canteen
5. Construction/ Improvement of School Building (New Buswang)
6. Construction/Completion of Rural Health Center II
7. Improvement of Pastrana Park (Fountain)
8. Construction of Drainage (Tinigaw)
9. Construction of Drainage (Tigayon)
10. Construction of Retaining Wall
11. Concreting of Road (Gumamela Rd., Pook)
12. Concreting of Road (Acevedo Rd., Old Buswang)
13. Concreting of Road (Purok-1, Mobo)
14. Installation of 109 Units Solar Street Lights w/ Concrete Pedestral
15. Concreting of Road (Spanish Rd., New Buswang)
16. Concreting/Opening of Road (Mercedes, New Buswang)
17. Road Widening (Bayanihan Rd.,Pook)
Thank you for your attention and continued cooperation.
Sincerely,
SBM PHILLIP Y. KIMPO, JR.
SBM/PMC-Chairperson