Completed
Planning
Purchasing
Preparation
Painting Process
Cleaning
Thursday Friday
Task No. Task Description Date Start Date End Duration
10am 12pm 2pm 4pm 6pm 8pm 10am 12pm 2pm 4pm 6pm 8pm
1 Planning for Interior Painting 09/29/2022 09/30/2022 11 hrs / 30 mins
1.1 Conceptualizing design 09/29/2022 09/30/2022 10 hours
1.2 Choosing color 09/30/2022 09/30/2022 25 mins
1.3 Determining how much paint is needed 09/30/2022 09/30/2022 10 mins
1.4 Identifying needed tools and materials 09/30/2022 09/30/2022 15 mins
1.5 Setting realistic budget 09/30/2022 09/30/2022 40 mins
2 Purchasing Materials 09/30/2022 09/30/2022 3 hours
2.1 Canvassing 09/30/2022 09/30/2022 1 hour
2.2 Decide where to purchase 09/30/2022 09/30/2022 30 mins
2.3 Buying 09/30/2022 09/30/2022 1 hr / 30 mins
3 Preparations 09/30/2022 09/30/2022 2 hrs / 25 mins
3.1 Preping walls 10/01/2022 10/01/2022 2 hours
3.2 Placing covers for floor 10/01/2022 10/01/2022 10 mins
3.3 Mixing paints 10/01/2022 10/01/2022 10 mins
3.4 Picking right painting techniques 10/01/2022 10/01/2022 5 mins
4 Painting Process 10/01/2022 10/01/2022 1 day
4.1 First Wall Coating 10/01/2022 10/01/2022 2 hours
4.2 Paint Drying 10/01/2022 10/01/2022 6 hours
4.3 Second Wall Coating 10/02/2022 10/02/2022 2 hours
4.4 Paint Drying 10/02/2022 10/02/2022 6 hours
4.5 Final Coating 10/03/2022 10/03/2022 2 hours
4.4 Paint Drying 10/03/2022 10/03/2022 6 hours
5 Clean up (post-painting) 10/03/2022 10/03/2022 1 hr/ 10 mins
5.1 Clean/ wash materials used 10/01/2022 10/01/2022 20 mins
5.2 Gather floor covers 10/01/2022 10/01/2022 5 mins
5.3 Storing excess paints, ladder etc. in storage 10/01/2022 10/01/2022 20 mins
5.4 Wipe spills or splatters 10/01/2022 10/01/2022 25 mins
Project complete 10/03/2022 10/03/2022 ~end~
Completed
Planning
Purchasing
Preparation
Painting Process
Cleaning
Saturday Sunday
Task No. Task Description Start Time End Time Duration
10am 12pm 2pm 4pm 6pm 8pm 10am 12pm 2pm 4pm 6pm 8pm
1 Planning for Interior Painting 09/29/2022 09/30/2022 11 hrs / 30 mins
1.1 Conceptualizing design 09/29/2022 09/30/2022 10 hours
1.2 Choosing color 09/30/2022 09/30/2022 25 mins
1.3 Determining how much paint is needed 09/30/2022 09/30/2022 10 mins
1.4 Identifying needed tools and materials 09/30/2022 09/30/2022 15 mins
1.5 Setting realistic budget 09/30/2022 09/30/2022 40 mins
2 Purchasing Materials 09/30/2022 09/30/2022 3 hours
2.1 Canvassing 09/30/2022 09/30/2022 1 hour
2.2 Decide where to purchase 09/30/2022 09/30/2022 30 mins
2.3 Buying 09/30/2022 09/30/2022 1 hr / 30 mins
3 Preparations 09/30/2022 09/30/2022 2 hrs / 25 mins
3.1 Preping walls 10/01/2022 10/01/2022 2 hours
3.2 Placing covers for floor 10/01/2022 10/01/2022 10 mins
3.3 Mixing paints 10/01/2022 10/01/2022 10 mins
3.4 Picking right painting techniques 10/01/2022 10/01/2022 5 mins
4 Painting Process 10/01/2022 10/01/2022 1 day
4.1 First Wall Coating 10/01/2022 10/01/2022 2 hours
4.2 Paint Drying 10/01/2022 10/01/2022 6 hours
4.3 Second Wall Coating 10/02/2022 10/02/2022 2 hours
4.4 Paint Drying 10/02/2022 10/02/2022 6 hours
4.5 Final Coating 10/03/2022 10/03/2022 2 hours
4.6 Paint Drying 10/03/2022 10/03/2022 6 hours
5 Clean up (post-painting) 10/03/2022 10/03/2022 1 hr/ 10 mins
5.1 Clean/ wash materials used 10/01/2022 10/01/2022 20 mins
5.2 Gather floor covers 10/01/2022 10/01/2022 5 mins
5.3 Storing excess paints, ladder etc. in storage 10/01/2022 10/01/2022 20 mins
5.4 Wipe spills or splatters 10/01/2022 10/01/2022 25 mins
Project complete 10/03/2022 10/03/2022 ~end~
Completed
Planning
Purchasing
Preparation
Painting Process
Cleaning
Monday
Task No. Task Description Start End Duration
10am 12pm 2pm 4pm 6pm 8pm
1 Planning for Interior Painting 09/29/2022 09/30/2022 11 hrs / 30 mins
1.1 Conceptualizing design 09/29/2022 09/30/2022 10 hours
1.2 Choosing color 09/30/2022 09/30/2022 25 mins
1.3 Determining how much paint is needed 09/30/2022 09/30/2022 10 mins
1.4 Identifying needed tools and materials 09/30/2022 09/30/2022 15 mins
1.5 Setting realistic budget 09/30/2022 09/30/2022 40 mins
2 Purchasing Materials 09/30/2022 09/30/2022 3 hours
2.1 Canvassing 09/30/2022 09/30/2022 1 hour
2.2 Decide where to purchase 09/30/2022 09/30/2022 30 mins
2.3 Buying 09/30/2022 09/30/2022 1 hr / 30 mins
3 Preparations 09/30/2022 09/30/2022 2 hrs / 25 mins
3.1 Preping walls 10/01/2022 10/01/2022 2 hours
3.2 Placing covers for floor 10/01/2022 10/01/2022 10 mins
3.3 Mixing paints 10/01/2022 10/01/2022 10 mins
3.4 Picking right painting techniques 10/01/2022 10/01/2022 5 mins
4 Painting Process 10/01/2022 10/01/2022 1 day
4.1 First Wall Coating 10/01/2022 10/01/2022 2 hours
4.2 Paint Drying 10/01/2022 10/01/2022 6 hours
4.3 Second Wall Coating 10/02/2022 10/02/2022 2 hours
4.4 Paint Drying 10/02/2022 10/02/2022 6 hours
4.5 Final Coating 10/03/2022 10/03/2022 2 hours
4.6 Paint Drying 10/03/2022 10/03/2022 6 hours
5 Clean up (post-painting) 10/03/2022 10/03/2022 1 hr/ 10 mins
5.1 Clean/ wash materials used 10/03/2022 10/03/2022 20 mins
5.2 Gather floor covers 10/03/2022 10/03/2022 5 mins
5.3 Storing excess paints, ladder etc. in storage 10/03/2022 10/03/2022 20 mins
5.4 Wipe spills or splatters 10/03/2022 10/03/2022 25 mins
Project complete 10/03/2022 10/03/2022 ~end~
Completed
Pre-Cleaning
Main Cleaning
Disinfection
Organizing
Checking
October 1, 2022
Task No. Task Description Start End Duration
9am 10am 11am 12pm 1pm 2pm 3pm 4pm 5pm 6pm 7pm 8pm
1 Pre-cleaning 10/01/2022 10/01/2022 3 hours
1.1 Purge storage 10/01/2022 10/01/2022 1 hour
1.2 Removing loose debris and substances 10/01/2022 10/01/2022 1 hour
1.3 Inspection for any damages or deffects 10/01/2022 10/01/2022 30 mins
1.4 Segregating items (keep or ditch) 10/01/2022 10/01/2022 30 mins
2 Main Cleaning 10/01/2022 10/01/2022 3 hours
2.1 Thorough cleaning of tools that will be kept 10/01/2022 10/01/2022 1 hour
2.2 Coiling cords and wires 10/01/2022 10/01/2022 25 mins
2.3 Wiping storage area 10/01/2022 10/01/2022 20 mins
2.4 Cleaning racks with detergent 10/01/2022 10/01/2022 1 hour
2.5 Rinsing racks 10/01/2022 10/01/2022 10 mins
2.6 Throwing unecessary items 10/01/2022 10/01/2022 5 mins
3 Disinfection 10/01/2022 10/01/2022 30 mins
3.1 Disinfecting storage area 10/01/2022 10/01/2022 30 mins
4 Organizing 10/01/2022 10/01/2022 2 hrs / 35 mins
4.1 Buying shelves and storage tubs 10/01/2022 10/01/2022 1 hour
4.2 Sorting items 10/01/2022 10/01/2022 20 mins
4.3 Storing 10/01/2022 10/01/2022 35 mins
4.4 Labeling 10/01/2022 10/01/2022 40 mins
5 Checking 10/01/2022 10/01/2022 14 mins
5.1 Final checking 10/01/2022 10/01/2022 10 mins
5.2 Locking storage area for safety purposes 10/01/2022 10/01/2022 4 mins
Task complete 10/01/2022 10/01/2022 ~end~