1 and 2

The document outlines a detailed schedule for an interior painting project, including planning, purchasing materials, preparation, the painting process, and post-painting cleanup. Each task is broken down with specific start and end dates, durations, and subtasks. The project is set to be completed by October 3, 2022.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views4 pages

1 and 2

The document outlines a detailed schedule for an interior painting project, including planning, purchasing materials, preparation, the painting process, and post-painting cleanup. Each task is broken down with specific start and end dates, durations, and subtasks. The project is set to be completed by October 3, 2022.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Completed

Planning
Purchasing
Preparation
Painting Process
Cleaning
Thursday Friday
Task No. Task Description Date Start Date End Duration
10am 12pm 2pm 4pm 6pm 8pm 10am 12pm 2pm 4pm 6pm 8pm
1 Planning for Interior Painting 09/29/2022 09/30/2022 11 hrs / 30 mins
1.1 Conceptualizing design 09/29/2022 09/30/2022 10 hours
1.2 Choosing color 09/30/2022 09/30/2022 25 mins
1.3 Determining how much paint is needed 09/30/2022 09/30/2022 10 mins
1.4 Identifying needed tools and materials 09/30/2022 09/30/2022 15 mins
1.5 Setting realistic budget 09/30/2022 09/30/2022 40 mins
2 Purchasing Materials 09/30/2022 09/30/2022 3 hours
2.1 Canvassing 09/30/2022 09/30/2022 1 hour
2.2 Decide where to purchase 09/30/2022 09/30/2022 30 mins
2.3 Buying 09/30/2022 09/30/2022 1 hr / 30 mins
3 Preparations 09/30/2022 09/30/2022 2 hrs / 25 mins
3.1 Preping walls 10/01/2022 10/01/2022 2 hours
3.2 Placing covers for floor 10/01/2022 10/01/2022 10 mins
3.3 Mixing paints 10/01/2022 10/01/2022 10 mins
3.4 Picking right painting techniques 10/01/2022 10/01/2022 5 mins
4 Painting Process 10/01/2022 10/01/2022 1 day
4.1 First Wall Coating 10/01/2022 10/01/2022 2 hours
4.2 Paint Drying 10/01/2022 10/01/2022 6 hours
4.3 Second Wall Coating 10/02/2022 10/02/2022 2 hours
4.4 Paint Drying 10/02/2022 10/02/2022 6 hours
4.5 Final Coating 10/03/2022 10/03/2022 2 hours
4.4 Paint Drying 10/03/2022 10/03/2022 6 hours
5 Clean up (post-painting) 10/03/2022 10/03/2022 1 hr/ 10 mins
5.1 Clean/ wash materials used 10/01/2022 10/01/2022 20 mins
5.2 Gather floor covers 10/01/2022 10/01/2022 5 mins
5.3 Storing excess paints, ladder etc. in storage 10/01/2022 10/01/2022 20 mins
5.4 Wipe spills or splatters 10/01/2022 10/01/2022 25 mins
Project complete 10/03/2022 10/03/2022 ~end~
Completed
Planning
Purchasing
Preparation
Painting Process
Cleaning
Saturday Sunday
Task No. Task Description Start Time End Time Duration
10am 12pm 2pm 4pm 6pm 8pm 10am 12pm 2pm 4pm 6pm 8pm
1 Planning for Interior Painting 09/29/2022 09/30/2022 11 hrs / 30 mins
1.1 Conceptualizing design 09/29/2022 09/30/2022 10 hours
1.2 Choosing color 09/30/2022 09/30/2022 25 mins
1.3 Determining how much paint is needed 09/30/2022 09/30/2022 10 mins
1.4 Identifying needed tools and materials 09/30/2022 09/30/2022 15 mins
1.5 Setting realistic budget 09/30/2022 09/30/2022 40 mins
2 Purchasing Materials 09/30/2022 09/30/2022 3 hours
2.1 Canvassing 09/30/2022 09/30/2022 1 hour
2.2 Decide where to purchase 09/30/2022 09/30/2022 30 mins
2.3 Buying 09/30/2022 09/30/2022 1 hr / 30 mins
3 Preparations 09/30/2022 09/30/2022 2 hrs / 25 mins
3.1 Preping walls 10/01/2022 10/01/2022 2 hours
3.2 Placing covers for floor 10/01/2022 10/01/2022 10 mins
3.3 Mixing paints 10/01/2022 10/01/2022 10 mins
3.4 Picking right painting techniques 10/01/2022 10/01/2022 5 mins
4 Painting Process 10/01/2022 10/01/2022 1 day
4.1 First Wall Coating 10/01/2022 10/01/2022 2 hours
4.2 Paint Drying 10/01/2022 10/01/2022 6 hours
4.3 Second Wall Coating 10/02/2022 10/02/2022 2 hours
4.4 Paint Drying 10/02/2022 10/02/2022 6 hours
4.5 Final Coating 10/03/2022 10/03/2022 2 hours
4.6 Paint Drying 10/03/2022 10/03/2022 6 hours
5 Clean up (post-painting) 10/03/2022 10/03/2022 1 hr/ 10 mins
5.1 Clean/ wash materials used 10/01/2022 10/01/2022 20 mins
5.2 Gather floor covers 10/01/2022 10/01/2022 5 mins
5.3 Storing excess paints, ladder etc. in storage 10/01/2022 10/01/2022 20 mins
5.4 Wipe spills or splatters 10/01/2022 10/01/2022 25 mins
Project complete 10/03/2022 10/03/2022 ~end~
Completed
Planning
Purchasing
Preparation
Painting Process
Cleaning
Monday
Task No. Task Description Start End Duration
10am 12pm 2pm 4pm 6pm 8pm
1 Planning for Interior Painting 09/29/2022 09/30/2022 11 hrs / 30 mins
1.1 Conceptualizing design 09/29/2022 09/30/2022 10 hours
1.2 Choosing color 09/30/2022 09/30/2022 25 mins
1.3 Determining how much paint is needed 09/30/2022 09/30/2022 10 mins
1.4 Identifying needed tools and materials 09/30/2022 09/30/2022 15 mins
1.5 Setting realistic budget 09/30/2022 09/30/2022 40 mins
2 Purchasing Materials 09/30/2022 09/30/2022 3 hours
2.1 Canvassing 09/30/2022 09/30/2022 1 hour
2.2 Decide where to purchase 09/30/2022 09/30/2022 30 mins
2.3 Buying 09/30/2022 09/30/2022 1 hr / 30 mins
3 Preparations 09/30/2022 09/30/2022 2 hrs / 25 mins
3.1 Preping walls 10/01/2022 10/01/2022 2 hours
3.2 Placing covers for floor 10/01/2022 10/01/2022 10 mins
3.3 Mixing paints 10/01/2022 10/01/2022 10 mins
3.4 Picking right painting techniques 10/01/2022 10/01/2022 5 mins
4 Painting Process 10/01/2022 10/01/2022 1 day
4.1 First Wall Coating 10/01/2022 10/01/2022 2 hours
4.2 Paint Drying 10/01/2022 10/01/2022 6 hours
4.3 Second Wall Coating 10/02/2022 10/02/2022 2 hours
4.4 Paint Drying 10/02/2022 10/02/2022 6 hours
4.5 Final Coating 10/03/2022 10/03/2022 2 hours
4.6 Paint Drying 10/03/2022 10/03/2022 6 hours
5 Clean up (post-painting) 10/03/2022 10/03/2022 1 hr/ 10 mins
5.1 Clean/ wash materials used 10/03/2022 10/03/2022 20 mins
5.2 Gather floor covers 10/03/2022 10/03/2022 5 mins
5.3 Storing excess paints, ladder etc. in storage 10/03/2022 10/03/2022 20 mins
5.4 Wipe spills or splatters 10/03/2022 10/03/2022 25 mins
Project complete 10/03/2022 10/03/2022 ~end~
Completed
Pre-Cleaning
Main Cleaning
Disinfection
Organizing
Checking

October 1, 2022
Task No. Task Description Start End Duration
9am 10am 11am 12pm 1pm 2pm 3pm 4pm 5pm 6pm 7pm 8pm
1 Pre-cleaning 10/01/2022 10/01/2022 3 hours
1.1 Purge storage 10/01/2022 10/01/2022 1 hour
1.2 Removing loose debris and substances 10/01/2022 10/01/2022 1 hour
1.3 Inspection for any damages or deffects 10/01/2022 10/01/2022 30 mins
1.4 Segregating items (keep or ditch) 10/01/2022 10/01/2022 30 mins
2 Main Cleaning 10/01/2022 10/01/2022 3 hours
2.1 Thorough cleaning of tools that will be kept 10/01/2022 10/01/2022 1 hour
2.2 Coiling cords and wires 10/01/2022 10/01/2022 25 mins
2.3 Wiping storage area 10/01/2022 10/01/2022 20 mins
2.4 Cleaning racks with detergent 10/01/2022 10/01/2022 1 hour
2.5 Rinsing racks 10/01/2022 10/01/2022 10 mins
2.6 Throwing unecessary items 10/01/2022 10/01/2022 5 mins
3 Disinfection 10/01/2022 10/01/2022 30 mins
3.1 Disinfecting storage area 10/01/2022 10/01/2022 30 mins
4 Organizing 10/01/2022 10/01/2022 2 hrs / 35 mins
4.1 Buying shelves and storage tubs 10/01/2022 10/01/2022 1 hour
4.2 Sorting items 10/01/2022 10/01/2022 20 mins
4.3 Storing 10/01/2022 10/01/2022 35 mins
4.4 Labeling 10/01/2022 10/01/2022 40 mins
5 Checking 10/01/2022 10/01/2022 14 mins
5.1 Final checking 10/01/2022 10/01/2022 10 mins
5.2 Locking storage area for safety purposes 10/01/2022 10/01/2022 4 mins
Task complete 10/01/2022 10/01/2022 ~end~