KAMATCHI CONSTRUCTION PTE LTD
37D, Benoi Road, Pioneer lot, Singapore-627797.
Tel: +65-9100 6494, Mob: +65-6406 7425, Company Reg No & GST No: 202129261M
Website: www.kamatchi-construction.com, Email: info@kamatchi-construction.com
ALL CONSTRUCTION WORKS ~ DEMOLITION ~ OTHER ENGINEERING WORKS
QUOTATION
ATTENTION : Ms. NAYCHI DATE : 15/03/2022
IGM CONSTRUCTION PTE LTD Qt. No. : IGM-01-KC-03-22(R2)
20 Ang Mo Kio Industrial Park 2a
#05-12, Amk Techlink
Singapore 169633,
PROJECT : 3 TANK ROAD
SUBJECT : DEMOLITION WORKS
1) Cost Break Down for Demolition Works
S.No Description Quantity unit Rate Amount
1 Mobilization 1 Lot $ 2,500.00 $ 2,500.00
2 1st Storey
2.1 Removal of tiles 92 M² $ 22.00 $ 2,024.00
2.2 Removal of Ceilings 92 M² $ 20.00 $ 1,840.00
2.3 Removal of partition 90 M² $ 20.00 $ 1,800.00
2.4 Removal of Door 2 Nos $ 200.00 $ 400.00
2.5 Removal of timber door 3 Nos $ 200.00 $ 600.00
2.6 Removal of roof sheet (Salvage considered) 68 M² $ 90.00 $ 6,120.00
2.7 Dismantling of staircase 1 lot $ 1,500.00 $ 1,500.00
6.8 Braking of Toilet and Zacuzzi 1 lot $ 3,500.00 $ 3,500.00
3 2nd Storey
Scaffolding and Court yard Glass+Steel
3.1 members 1 Lot $ 1,500.00 $ 1,500.00
3.2 Scaffolding removal of glass roof 1 Lot $ 1,000.00 $ 1,000.00
3.3 Removal of tiles and screed 24 M² $ 22.00 $ 528.00
3.4 Existing Toilet 2 nos $ 1,500.00 $ 3,000.00
3.5 Removal of Raise floor / Deck 1 lot $ 5,000.00 $ 5,000.00
4 3rd Storey
4.1 Existing Toilet 2 nos $ 1,500.00 $ 3,000.00
4.2 Making opening on wall to access open space 2 nos $ 900.00 $ 1,800.00
4.3 removal of Flooring 24 M² $ 22.00 $ 528.00
5 4th Storey
5.1 Removal of tiles 40 M² $ 22.00 $ 880.00
5.2 Removal of Ceilings 40 M² $ 20.00 $ 800.00
5.3 Existing Toilet 2 nos $ 1,500.00 $ 3,000.00
Page 1 of 3
37D, Benoi Road, Pioneer lot, Singapore-627797,
www.kamatchi-construction.com / Phone: +65-9100 64.
info@kamatchi-construction.com / Mobile: +65-6406 74.
KAMATCHI CONSTRUCTION PTE LTD
37D, Benoi Road, Pioneer lot, Singapore-627797.
Tel: +65-9100 6494, Mob: +65-6406 7425, Company Reg No & GST No: 202129261M
Website: www.kamatchi-construction.com, Email: info@kamatchi-construction.com
ALL CONSTRUCTION WORKS ~ DEMOLITION ~ OTHER ENGINEERING WORKS
S.No Description Quantity unit Rate Amount
6 Attic
6.1 Removal of tiles 33 M² $ 22.00 $ 726.00
6.2 Removal of tiles 22 M² $ 22.00 $ 484.00
6.3 Removal of ceiling 33 M² $ 20.00 $ 660.00
Removal of slab(assume 300mm thk).
6.4 22 M² $ 300.00 $ 6,600.00
Adjacent wall support by Main Con
6.5 Dismantle of steel canopy and terracotta roof 1 Lot $ 1,500.00 $ 1,500.00
Decomissioning of electrical andremoval of
7 1 Lot $ 4,000.00 $ 4,000.00
wire (Slvage considered)
8 Dismantling of Aircon (Salvage considered) 1 Lot $ 2,000.00 $ 2,000.00
9 Windows 19 nos $ 350.00 $ 6,650.00
10 Removal of furniture &Debris 1 Lot $ 4,500.00 $ 4,500.00
Salavage belong to us
11 Hacking and Strengthening of structures By others
Making good and reinstatement By Others
Façade scaffolding and demolition By Others
Total Amount (Before GST) $ 68,440.00
(i) ITEMS TO BE PROVIDED BY CLIENT AT NO COST TO US
1. All insurances including Contractor’s All Risks and Workman’s Compensation.
2. Asbestos and Any Licensee’s Material inspection and removal by main con.
3. Provide and maintain all necessary preventions and protection to preserve the stability of adjacent structures and all
other Properties
4. Proper access and sufficient working space and clearance.
5. Termination / decommissioning of service, detachment, protection, Noise barrier, relocation, make good surface,
detection of utilities services done by main contractor period to dismantle or Demolition.
6. Water, Electricity supply: (3 Phase, 63A) – 8 Nos., (Single phase, 230V) - 12 Nos., come with DB with one to one basis.
(Electricity, Water tapping point shall be provided no further than 10m from work area).
7. Any P.E design, which is not included in our scope by Main Contractor.
8. Setting out, marking and survey to be provided by main contractor. (Main contractor to physically confirm marked out
area before commencement of work).
9. Site storage location for our machinery to be provided by main contractor.
10. Price quoted is strictly valid for the above mentioned items only. Any additional work done or materials consumed (not
listed / quoted) will be charged accordingly.
Page 2 of 3
37D, Benoi Road, Pioneer lot, Singapore-627797,
www.kamatchi-construction.com / Phone: +65-9100 64.
info@kamatchi-construction.com / Mobile: +65-6406 74.
KAMATCHI CONSTRUCTION PTE LTD
37D, Benoi Road, Pioneer lot, Singapore-627797.
Tel: +65-9100 6494, Mob: +65-6406 7425, Company Reg No & GST No: 202129261M
Website: www.kamatchi-construction.com, Email: info@kamatchi-construction.com
ALL CONSTRUCTION WORKS ~ DEMOLITION ~ OTHER ENGINEERING WORKS
11. Any Additional works will be considered as variation order.
12. Removal of communication systems and firefighting system done by others.
13. Mobilization upon two weeks confirmation.
(ii) OTHER TERMS AND CONDITIONS
1. The price submitted is based on Unit Price.
2. This Quotation is valid for 15 Days from date of submission.
3. No deduction of cost is allowed if there is omission of any part of the works or reduction in quantity of the work.
(iii) PAYMENT TERMS
1. Progress claim fortnightly.
2.30 days payment term
Thank You,
Kamatchi Construction Confirmed and Accepted by
Sekar MAHALINGAM Authorized Signature & Stamp
mp Mobile: +65 91006494
Page 3 of 3
37D, Benoi Road, Pioneer lot, Singapore-627797,
www.kamatchi-construction.com / Phone: +65-9100 64.
info@kamatchi-construction.com / Mobile: +65-6406 74.