3A. Station (STR) EA
3A. Station (STR) EA
GREEN LINE BUS RAPID TRANSIT SYSTEM FROM KESC POWER SURJANI TO MUNCIPAL PARK, SADDAR KARACHI
Abstract
Revised
Actual Executed Remaining Contract
Actual Total Saving
Pay
Item Item Description Unit Remarks Rate
Previous Current
No Qty Amount % Qty Amount % Amount % Qty Amount Qty Amount % Qty Amount %
week Qty week Qty
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 905.824 17,301,238 100.00% 905.824 17,301,238 100.00% 19,100 960 18,336,000 905.824 17,301,238 94.357% 54.176 1,034,762 5.643%
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 216.104 4,430,132 100.00% 216.104 4,430,132 100.00% 20,500 350 7,175,000 216.104 4,430,132 61.744% 133.896 2,744,868 38.256%
a Super-Structure M.Ton 209.480 23,671,240 100.00% 209.480 23,671,240 100.00% 113,000 230 25,990,000 209.480 23,671,240 91.078% 20.520 2,318,760 8.922%
AGE # KAR/BRTS/GL/06
stract
Increase
Remarks
Qty Amount %
-
BALANCE QUANTITY DETAILS
GREEN LINE BRTS - GL-06
STATION # 2A (KDA CHOWRANGI)
CIVIL WORK a) Structre Work (Station) Date: 04-08-2020
Revised
Pay Actual Executed Remaining Contract Actual Total Saving
Item Item Description Unit Remarks Rate
No Qty Amount % Qty Amount % Previous Amount % Current Qty Amount Qty Amount % Qty Amount %
week Qty week Qty
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 113.228 2,162,655 100.00% 113.228 2,162,655 100.00% 19,100 120 2,292,000 113.228 2,162,655 94.357% 6.772 129,345 5.643%
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 27.013 553,767 100.00% 27.013 553,767 100.00% 20,500 44 896,875 27.013 553,767 61.744% 16.737 343,108 38.256%
a Super-Structure M.Ton 26.185 2,958,905 100.00% 26.185 2,958,905 100.00% 113,000 29 3,248,750 26.185 2,958,905 91.078% 2.565 289,845 8.922%
Total Station Work 24,581,431 24,014,248 567,183 26,687,625 24,581,431 92.108% 2,106,194 7.892%
GL-06 (IPC No.-17)
Increase
Remarks
Qty Amount %
-
BALANCE QUANTITY DETAILS
GREEN LINE BRTS - GL-06
STATION # 3A (KARIMI CHOWRANGI)
CIVIL WORK a) Structre Work (Station) Date: 04-08-2020
Revised
Pay Actual Executed Remaining Contract Actual Total Saving Increase
Item Item Description Unit Remarks Rate
Previous Current
No Qty Amount % Qty Amount % Amount % Qty Amount Qty Amount % Qty Amount % Qty
week Qty week Qty
CONCRETE WORKS (SUPER STRUCTURE)
Providing and laying RCC cement concrete with
Betocrete G-2000 or approved equivalent (Super
plasticizer concrete admixture / retarder mix according
1 to supplier instruction) where required using OPC
cement & approved quarry of crushed stone 25 mm (1
inch) and down gauge with approved quarry of sand
having 28 days preliminary
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 113.228 2,162,655 100.00% 113.228 2,162,655 100.00% 19,100 120 2,292,000 113.228 2,162,655 94.357% 6.772 129,345 5.643%
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 27.013 553,767 100.00% 27.013 553,767 100.00% 20,500 44 896,875 27.013 553,767 61.744% 16.737 343,108 38.256%
a Super-Structure M.Ton 26.185 2,958,905 100.00% 26.185 2,958,905 100.00% 113,000 29 3,248,750 26.185 2,958,905 91.078% 2.565 289,845 8.922%
Increase
Remarks
Amount %
-
BALANCE QUANTITY DETAILS
GREEN LINE BRTS - GL-06
STATION # 4A (SURJANI CHOWRANGI)
CIVIL WORK a) Structre Work (Station) Date: 04-08-2020
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 113.228 2,162,655 100.00% 113.228 2,162,655 100.00%
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 27.013 553,767 100.00% 27.013 553,767 100.00%
Revised
Contract
Actual Total Saving Increase
Rate Remarks
Qty Amount Qty Amount % Qty Amount % Qty Amount %
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 113.228 2,162,655 100.00% 113.228 2,162,655 100.00% 19,100 120 2,292,000 113.228 2,162,655 94.357% 6.772 129,345 5.643%
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 27.013 553,767 100.00% 27.013 553,767 100.00% 20,500 44 896,875 27.013 553,767 61.744% 16.737 343,108 38.256%
a Super-Structure M.Ton 26.185 2,958,905 100.00% 26.185 2,958,905 100.00% 113,000 29 3,248,750 26.185 2,958,905 91.078% 2.565 289,845 8.922%
Increase
Remarks
Amount %
-
BALANCE QUANTITY DETAILS
GREEN LINE BRTS - GL-06
STATION # 6A (2400 ROAD)
CIVIL WORK a) Structre Work (Station) Date: 04-08-2020
Revised
Actual Executed Remaining Contract
Actual Total Saving Increase
Pay
Item Item Description Unit Remarks Rate
Previous Current
No Qty Amount % Qty Amount % week Qty Amount % week Qty Qty Amount Qty Amount % Qty Amount % Qty
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 113.228 2,162,655 100.00% 113.228 2,162,655 100.00% 19,100 120 2,292,000 113.228 2,162,655 94.357% 6.772 129,345 5.643%
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 27.013 553,767 100.00% 27.013 553,767 100.00% 20,500 44 896,875 27.013 553,767 61.744% 16.737 343,108 38.256%
a Super-Structure M.Ton 26.185 2,958,905 100.00% 26.185 2,958,905 100.00% 113,000 29 3,248,750 26.185 2,958,905 91.078% 2.565 289,845 8.922%
Increase
Remarks
Amount %
-
BALANCE QUANTITY DETAILS
GREEN LINE BRTS - GL-06
STATION # 7A (POWER HOUSE CHOWRANGI)
CIVIL WORK a) Structre Work (Station) Date: 04-08-2020
Revised
Pay Actual Executed Remaining Contract
Actual Total Saving Increase
Item Item Description Unit Remarks Rate
Previous Current
No Qty Amount % Qty Amount % week Qty Amount % week Qty Qty Amount Qty Amount % Qty Amount % Qty
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 113.228 2,162,655 100.00% 113.228 2,162,655 100.00% 19,100 120 2,292,000 113.228 2,162,655 94.357% 6.772 129,345 5.643%
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 27.013 553,767 100.00% 27.013 553,767 100.00% 20,500 44 896,875 27.013 553,767 61.744% 16.737 343,108 38.256%
a Super-Structure M.Ton 26.185 2,958,905 100.00% 26.185 2,958,905 100.00% 113,000 29 3,248,750 26.185 2,958,905 91.078% 2.565 289,845 8.922%
Increase
Remarks
Amount %
-
BALANCE QUANTITY DETAILS
GREEN LINE BRTS - GL-06
STATION # 8A (4200 ROAD)
CIVIL WORK a) Structre Work (Station) Date: 04-08-2020
Revised
Actual Executed Remaining Contract
Actual Total Saving
Pay
Item Item Description Unit Remarks Rate
Previous Current
No Qty Amount % Qty Amount % Amount % Qty Amount Qty Amount % Qty
week Qty week Qty
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 113.228 2,162,655 100.00% 113.228 2,162,655 100.00% 19,100 120 2,292,000 113.228 2,162,655 94.357% 6.772
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 27.013 553,767 100.00% 27.013 553,767 100.00% 20,500 44 896,875 27.013 553,767 61.744% 16.737
a Super-Structure M.Ton 26.185 2,958,905 100.00% 26.185 2,958,905 100.00% 113,000 29 3,248,750 26.185 2,958,905 91.078% 2.565
Saving Increase
Remarks
Amount % Qty Amount %
129,345 5.643%
343,108 38.256%
289,845 8.922%
1,343,895 6.637%
2,106,194 7.892% -
BALANCE QUANTITY DETAILS
GREEN LINE BRTS - GL-06
STATION # 9A (UP MORE)
CIVIL WORK a) Structre Work (Station) Date: 04-08-2020
Revised
Pay
Actual Executed Remaining Contract
Actual Total Saving Increase
Item Item Description Unit Remarks Rate
Previous Current
No Qty Amount % Qty Amount % week Qty Amount % week Qty Qty Amount Qty Amount % Qty Amount % Qty
a Station Platform/ Slab i/c Projections (35 Mpa 5000 Psi) Cum 113.228 2,162,655 100.00% 113.228 2,162,655 100.00% 19,100 120 2,292,000 113.228 2,162,655 94.357% 6.772 129,345 5.643%
b Station Platform Beam /Wall/Purdi (35 Mpa 5000 Psi) Cum 27.013 553,767 100.00% 27.013 553,767 100.00% 20,500 44 896,875 27.013 553,767 61.744% 16.737 343,108 38.256%
a Super-Structure M.Ton 26.185 2,958,905 100.00% 26.185 2,958,905 100.00% 113,000 29 3,248,750 26.185 2,958,905 91.078% 2.565 289,845 8.922%
Increase
Remarks
Amount %