Control Building Mne

The document outlines a punch list for the 75.214MWp Palauig Solar Power Project, detailing deviations that need to be addressed before project handover. Key items include the termination of the FM 200 Actuator and the submission of required documentation, with responsibilities assigned to the contractor. The document is dated December 27, 2024, and includes sections for raised dates, responsible parties, and completion remarks.

Uploaded by

Jamie Castillo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views1 page

Control Building Mne

The document outlines a punch list for the 75.214MWp Palauig Solar Power Project, detailing deviations that need to be addressed before project handover. Key items include the termination of the FM 200 Actuator and the submission of required documentation, with responsibilities assigned to the contractor. The document is dated December 27, 2024, and includes sections for raised dates, responsible parties, and completion remarks.

Uploaded by

Jamie Castillo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Page 1 of 1

Project Name: 75.214MWp Palauig Solar Power Project


Project Location: Sitio Luan Brgy. Lipay Palauig zambales

PUNCHLIST 010 Date: Dec. 27, 2024


Item Raised Responsible Raised Indicative Rectification Photos Date
No.
Description of Deviation
Date Contractor By
Location Defect Photos
Cost Completed Photos Completed
Remarks

FM 200 Actuator must be


Control Building
100 terminated to cylinder prior to 20 Dec 28 NPCC/MNE BQC/MM
MVSG Room
hand Over the room or System
mne

To Closed all NCR and QCIR


110 28 Dec 28 NPCC/MNE BQC/MM
related to this Area

mne

To Submit All required


111 Documentation required prior to 28 Dec 28 NPCC/MNE BQC/MM
hand over the Area
mne

Prepared By: Reviewed By: Received By:

B. Cuenta/M. Marigza/O. Encio Gladys Morales ___________


Owners Engineer Shizen P.M. NEPC