Page 1 of 1
Project Name: 75.214MWp Palauig Solar Power Project
Project Location: Sitio Luan Brgy. Lipay Palauig zambales
PUNCHLIST 010 Date: Dec. 27, 2024
Item Raised Responsible Raised Indicative Rectification Photos Date
No.
Description of Deviation
Date Contractor By
Location Defect Photos
Cost Completed Photos Completed
Remarks
FM 200 Actuator must be
Control Building
100 terminated to cylinder prior to 20 Dec 28 NPCC/MNE BQC/MM
MVSG Room
hand Over the room or System
mne
To Closed all NCR and QCIR
110 28 Dec 28 NPCC/MNE BQC/MM
related to this Area
mne
To Submit All required
111 Documentation required prior to 28 Dec 28 NPCC/MNE BQC/MM
hand over the Area
mne
Prepared By: Reviewed By: Received By:
B. Cuenta/M. Marigza/O. Encio Gladys Morales ___________
Owners Engineer Shizen P.M. NEPC