Schedule Laguna

The document outlines the construction activities for Rockwell South at Carmelray, detailing tasks such as preparation of documents, layout and staking, earthworks, and various installation works including reinforcing steel bars, concreting, formworks, masonry, structural steel, electrical, and plumbing. Each section specifies the specific tasks involved, such as excavation, fabrication, installation, and finishing works. The project spans a total of 89 days.

Uploaded by

hulogmonthly
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views26 pages

Schedule Laguna

The document outlines the construction activities for Rockwell South at Carmelray, detailing tasks such as preparation of documents, layout and staking, earthworks, and various installation works including reinforcing steel bars, concreting, formworks, masonry, structural steel, electrical, and plumbing. Each section specifies the specific tasks involved, such as excavation, fabrication, installation, and finishing works. The project spans a total of 89 days.

Uploaded by

hulogmonthly
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 26

1.

00 Preparation of documents for rockwell south at carmelray


5.00 Layout and staking
6.00 Hauling of materials
7.00 Earthworks
Excavation for footings
Excavation for rw1
Excavation for rw2
Backfilling and compaction for footings
Backfilling and compaction for rw1
Backfilling and compaction for rw2
Backfilling and compaction for slab on fill
8.00 Reinforcing Steel Bars
Fabrication of steel bars for footings
Fabrication of column ties at ground floor
Fabrication of column ties at second floor
Fabrication of stirrups for grade beams
Fabrication of stirrups for 2nd floor framing beams
Fabrication of stirrup for roof beams
Installation of steel bars for footings
installation of vertical bars and ties of columns at ground floor
installation of vertical bars and ties of columns at second floor
Installation of steel bars for rw1
Installation of steel bars for rw2
Installation of main bars and stirrups for grade beams
Installation of main bars and stirrups for 2nd floor framing beams
Installation of main bars and stirrups for roof beams
Installation of rebars for suspended slab
Installation of rebars for slab on fill
9.00 Concreting Works
Concreting of footings
Concreting of column-footings
Concreting of rw1
Concreting of rw2
Concreting of grade beams
Concreting of 2f floor framing beams
Concreting of roof beams
Concreting of ground floor columns
Concreting of 2f floor columns
Concreting of suspended slab
Concreting of slab on fill
10.00 Formworks and Scaffolding
Installation of forms for footings
Installation of forms for column-footing
Installation of forms for rw1
Installation of forms for rw2
Installtion of forms for grade beam
Installation of forms for 2f framing beams
Instllation of forms for roof beams
Installation of forms for columns at gf
Installation of forms for columns at 2f
Installation of forms for suspended slab
Installation of forms for stairs
Shoring and bracing for roof beam
Shoring and bracing for 2f framing beam
Shoring and bracing for suspended slab
Shoring and bracing for stair
11.00 Masonry Works
Chb layering at ground floor
Chb layering at second floor
Chb layering at roof beam
Plastering works at ground floor
Plastering works at second floor
Plastering works at roof beam-roof's apex
12.00 Structural Steel Works
Installation of steel columns
Installation of c-purlins
Installation of steel rafter
14.00 Electrical Works
Installation of conduits and hangers
installation of utility box
Installation of junction box
Installation of electrical wires at ground floor
Installation of electrical wires at second floor
Installation of panels board and circuit breakers
15.00 Plumbing Works
Installation of waterline at ground floor
Installation of waterline at second floor
Installation of sanitary line at ground floor
Installation of sanitary line at second floor
Installation of plumbing fixtures at ground floor
installation of plumbing fixtures at second floor
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72
73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90
91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108
89 days
109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126
127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144
114
145 146 147 148 149 150 151 152 153 154 155 156 157 10 11 12 13 14 15 16
17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31