Tender Pali
Tender Pali
B-1
TENDER PAPERS
Name of work : - Construction of Multipurpose Center under Prime
Minister Janman Central Scheme at Dokshet
Dharanachiwadi, Dokshet- Jambhulwadi, Parali-
Adihvasiwadi, Kalamb- Adhivasiwadi, Tal.Sudhagad Dist.
Raigad
EXECUTIVE ENGINEER,
P.W. TRIBAL DIVISION,
THANE
(b)
1 Disclaimer 1 1
3 i) E- Tendering Procedures 8 28
ii)From I to V 29 36
iii) Affidavit 37 38
11 Bar chart
12 Drawing
महारा शासन
सा. बां.(आिदवासी) िवभाग, ठाणे
संि त ई-िनिवदा सुचना मांक-34 सन 2023-24
कायकारी अिभयंता, सा.बां.(आिदवासी) िवभाग, ठाणे दुर वनी .022-25410046 हे ई-िनिवदा दारे
(ऑनलाईन) खालील कामां करीता बी-1 नमु यातील िनिवदा महारा शासनाकडील यो य या वग तील आिदवासी
िवकास िवभागाकडील न दणीकृ त कं ाटदार यांचेकडू न मागिवत आहे .
अ. कामाचे नाव िनिवदा र कम कं ाटदाराचा
(अ+ब) ( .ल ) वग
1. धानमं ी जनजाती योजनतगत )PM JANMAN) कोचाळे - कारेगांव, करोळ-पाचघर,
वग-3 व
सावदे- जोगलवाडी, सातुल -पळसुड
ं े ता.मोखाडा िज.पालघर येथे आिदवासी बहु ेिशय क ाचे 1,86,64,396/-
यावरील
बांधकाम करणे.
धानमं ी जनजाती योजनतगत )PM JANMAN) ध डिमरीचीमेठ-खोच, साखरी-ग दे वग-3 व
2. )खु(., पोशेरा, ता.मोखाडा िज.पालघर भुरीटे क, झाप-काटकरीव ती ता.ज हार िज.पालघर 2,33,30,495/- यावरील
येथे आिदवासी बहु ेिशय क ाचे बांधकाम करणे.
धानमं ी जनजाती योजनतगत )PM JANMAN) कातकरीवाडी-नांदगांव, राजकोटपाडा- वग-3 व
3. नांदगांव , नांदगांव◌े- जांभळ
ू वाडी, नांदगांव-नवीवाडी, राजेवाडी)नांदगांव ( ता.ज हार 2,33,30,495/- यावरील
िज.पालघर येथे आिदवासी बहु ेिशय क ाचे बांधकाम करणे.
धानमं ी जनजाती योजनतगत )PM JANMAN) रायतळे-आिदमव ती, रायतळे - वग-3 व
4. ू वाडी, धुमपाडा-कासटवाडी, रामनगर )कोरतड(, आपटाळे ता.ज हार िज.पालघर
जांभळ 2,33,30,495/- यावरील
येथे आिदवासी बहु ेिशय क ाचे बांधकाम करणे.
धानमं ी जनजाती योजनतगत )PM JANMAN) गरडवाडी-कासटवाडी, जये वर-
वग-3 व
5. कासटवाडी, गणेशनगर-कासटवाडी, देवीचापाडा-कासटवाडी, जूनी ज हार ता.ज हार 2,33,30,495/-
यावरील
िज.पालघर येथे आिदवासी बहु ेिशय क ाचे बांधकाम करणे.
धानमं ी जनजाती योजनतगत )PM JANMAN) माण, खो ते ता.िव मगड, खुपरी वग-4 व
6. 1,39,98,297/-
ता.वाडा िज.पालघर येथे आिदवासी बहु ेिशय क ाचे बांधकाम करणे. यावरील
धानमं ी जनजाती योजनतगत )PM JANMAN) - तारखेडवाडी, फणसवाडी, वग-3 व
7. 1,86,64,396/-
मालवाडी, बडीचीवाडी ता.पेण िज.रायगड येथे आिदवासी बहु ेिशय क ाचे बांधकाम करणे. यावरील
धानमं ी जनजाती योजनतगत )PM JANMAN) -डोकशेत धरणाचीवाडी, डोकशेत-
वग-3 व
8. ु वाडी, परळी -आिदवासीवाडी, कळं ब-आिदवासीवाडी ता.सुधागड िज.रायगड येथे
जांभळ 1,86,64,396/-
यावरील
आिदवासी बहु ेिशय क ाचे बांधकाम करणे.
धानमं ी जनजाती योजनतगत )PM JANMAN) -ताडगाव आिदवासीवाडी, उंबरवाडी,
वग-3 व
9. नवघर आिदवासीवाडी, खांडसांबळे , िस े वर आिदवासीवाडी ता.सुधागड िज.रायगड येथे 2,33,30,495/-
यावरील
आिदवासी बहु ेिशय क ाचे बांधकाम करणे.
10. धानमं ी जनजाती योजनतगत )PM JANMAN) -लांदरवाडी, वासगाव-आिदवासीवाडी,
वग-3 व
ता.रोहा िज.रायगड कातलाचीवाडी, रामवाडी ता.खालापुर िज.रायगड येथे आिदवासी 1,86,64,396/-
यावरील
बहु ेिशय क ाचे बांधकाम करणे.
11 . धानमं ी जनजाती योजनतगत (PM JANMAN) नाईकपाडा (माणीपाडा) , सातवीपाडा
वग-4 व
(क ढान), खानीवडे (दाभोणरोड) ता.डहाणू िज.पालघर येथे आिदवासी बहु ेिशय क ाचे 1,39,98,297/-
यावरील
बांधकाम करणे.
1. Detailed Time Table for the various activities to be performed in e-tendering process by the
Tenderer for quoting their offer is given in this Tender Document under "Tender Schedule".
Contractor should carefully note down the cut-off dates for the carrying out each e-tendering
process / activity.
2. Every effort is being made to keep the Website up to date and running smoothly 24 x 7 by the
Government and the Service Provider. However, Government takes no responsibility, and
will not be liable for, the website being temporarily unavailable due to any technical issue
at any point of time.
3. In that event Tribal Development Department will not be liable or responsible for any damages or
expenses arising from any difficulty, error, imperfection or inaccuracy with this Website. It
includes all associated services or due to such unavailability of the Website or any part thereof or
any contents or any associated services.
4. Tenderer must follow the time table of e-tendering process and get their activities of e-
tendering processes done well in advance so as to avoid any inconvenience due to unforeseen
technical problem if any.
5. Tribal Development Department will not be responsible for any incomplete activity of e-
tendering process of the tenderer due to technical error/ failure of website and it cannot be
challenged by way of appeal, arbitration and in the Court of Law. Contractors must get done
all the e-tendering activities well in advance.
GOVERNMENT OF MAHARASHTRA
TRIBAL DEVELOPMENT DEPARTMENT
ORIGINAL AGREEMENT NO. B-1
1. Name of Contractor :
5. Percentage quoted. :
6. Amount of Contract. :
7. Date of Commencement. :
8. Time stipulated for completion of work. : 180 (One Hundred & Eighty Days)
(Including public holidays & monsoon)
9. Date of completion as per Agreement :
1………………………………………
2……………………………………....
3…………………………………….....
Certified that this original agreement contains Pages 1 to fly leaves Nos. Drawings
Nos.
DETAILS OF WORK
➢ I/WE have quoted my/our offer in percentage rate in words as well as in figures.
➢ I/WE further undertake to enter into contract in regular "B-1" form in TRIBAL
DEVELOPMENT DEPARTMENT
TENDER SCHEDULE
1. Online percentage rate tenders in 'B-1' Form are invited by the Executive Engineer,
P.W. (Tribal) Division, Thane for the following work from Capable an Eligible Civil Contractor
registered in Class III & Above with TRIBAL DEVELOPMENT DEPARTMENT of Maharashtra
State. The Name of Work, Estimated Cost, Earnest Money, Security Deposit, Time limit for
Completion etc. are as under
Sr. Name of Work EstimatedCost in Earnest Security Class of Contractor Time limit
Rupees Money in Calendar
No. Deposit
Months
Part A –
1 Construction of Rs. Rs.1,50,000/- Rs.1,88,000/- Class III & Above 180 (One
Multipurpose Center under 1,84,60,728/- Registered with Hundred &
Prime Minister Janman Part B – Tribal Development Eighty
Central Scheme at Dokshet Rs. 2,03,668/- Department in Days)
Dharanachiwadi, Dokshet- Total – Maharashtra
Jambhulwadi, Parali- Rs.
Adihvasiwadi, Kalamb- 1,86,64,396/-
Adhivasiwadi,
Tal.Sudhagad Dist. Raigad
1.1 Tender form, conditions of contract, specifications and contract drawings can be downloaded
from the e-tendering portal of Government of Maharashtra i.e. https://mahatenders.gov.in after
entering the details of payment of tender document Fee of Rs.1,180/- (Rupees One
Thousand One Hundred & Eighty Only) Tender Document Fees shall be paid online
using payment gateway. The fees of tender document will be non-refundable.
Further information regarding the work can be obtained from the Office of the Executive
Engineer, P.W. (Tribal) Division, Thane.
1.2 The tender form, conditions of contract, specifications & contract drawings can be downloaded
online using payment gateway. The EMD applicable amount shall be paid via online mode from
the authorized account in the name of Bidder only. Bids will be opened as per tender schedule,
in the presence of such intending tenderer or his/their authorized representatives who may be
present at the time opening
The Pre-bid meeting will be held on Date- 23/2/2024 @ Nashik (As per e- tender schedule
uploaded on e-portal https://mahatenders.gov.in/ tribal development department) in
the presence of bidders who wish to attend in the office of the Superintending Engineer,
P.W.(Tribal) Circle, Nashik as per Tender Schedule
Physical Submission:
The bidder shall submit the Hard Copy in "Sealed Envelope" of Technical & Financial
Bids as specified in NIT within 72 hours after the online submission of Bid ("Bid Lock").
Address :- Office of the Executive Engineer, P.W. (Tribal) Division, Thane
P.W.D.Compound, Station Road, Thane (West) – 400 601.
1.4 The tender notice shall form a part of contract agreement. The tenders are invited on the
departmental designs only
1.5 The tenderer if firm or company shall in their forwarding letter mention names of all the partners
of the firm or company (as the case may be) and the name of the partner who holds the power
of attorney in any, authorizing him to conduct transaction on behalf of the firm or company.
1.6 The right is reserved to revise or amend the contract documents prior to the date notified
for the receipt of the tenders or extended date. Such deviations, amendments or extensions, if
any, shall be communicated in the form of corrigendum by letter or / and by notice in News
paper as may be considered suitable
1.7 The tenderer shall enter his percentage rates in words and figures “below / above” on estimated
cost of (Part A) only. In case there is difference between percentage written in figures and
words, the lower offer will be taken as final.
1.8 No pages should be removed from, added in or replaced in the tender documents.
1.9 Right is reserved to reject any or all tenders without assigning any reasons thereof.
1.10 Tenders who do not fulfill any or all conditions or are incomplete in any respect are liable
for summery rejection.
1.11 The tenderer may, in forwarding letter, mention any points he may wish to make clear but right is
reserved to reject the same in the whole of the tenders if the same become conditional tender
thereby.
1.12 All Cement Concrete items under this contract shall be carried out with Standard
specification book.
2.1 Earnest money of Rs.1,50,000/- ( Rs. One Lakhs Fifty Thousands Only) shall be paid via
online using NEFT/RTGS or payment gateway mode from the authorized account in the name
of bidder only. The said amount of earnest money shall not carry any interest
whatsoever. EMD exemption certificate will not be accepted. Vide GR No.
CAT/06/2014/LTN 242/Bldg.2, Dt. 24/2/2017.
2.2 Tender of those who do not deposit earnest money in one of the above acceptable
forms shall be summarily rejected. Earnest money in any other form of cash or cheque will not be
accepted.
2.3 The amount of earnest money will be refunded to the unsuccessful tenderer on deciding
about the acceptance or otherwise of the tender or on expiry of the validity period whichever
is earlier
In case of the successful tenderer, it will be refunded on his paying the initial security deposit
and completing the tender documents or will be transferred towards a part of security deposit to
be paid after awarding of the work. If successful tenderer does not pay the security deposit in the
prescribed time limit and complete the agreement bond, his earnest money deposit will be
forfeited to the Government
2.4 Earnest money of the un-successful tenderer will be refunded on their application only after
an intimation of rejection of their tender is sent to them or on the expiry of the validity period
whichever is earlier.
However, the User agrees that under no circumstances the Payment Gateway Service
Provider shall be held responsible for such fraudulent/duplicate transactions and hence no
claims should be raised to Payment Gateway Service Provider No communication received
by the Payment Gateway Service Provider(s) in this regard shall be entertained by the
Payment Gateway Service Provider.
27. Miscellaneous Conditions:-
Any waiver of any rights available to Merchant under these Terms and Conditions shall not mean
that those rights are automatically waived.
28. The User agrees, understands and confirms that his/ her personal data including without
limitation details relating to debit card/ credit card transmitted over the Internet may be
3. The Merchant, the Payment Gateway Service Provider(s) and its affiliates and
associates shall not be liable, at any time, for any failure of performance, error,
omission, interruption, deletion, defect, delay in operation or transmission, computer
virus, communications line failure, theft or destruction or unauthorized access to,
alteration of, or use of information contained on the Website.
4. The User may be required to create his/ her own User ID and Password in order to register
and/ or use the Services provided by Merchant on the Website. By accepting these
Terms and Conditions the User agrees that his/ her User ID and Password are very
important pieces of information and it shall be the User’s own responsibility to keep
them secure and confidential. In furtherance hereof, the User agrees to:
(a) Choose a new password, whenever required for security reasons.
(b) Keep his/ her User ID & Password strictly confidential.
(c) Be responsible for any transactions made by User under such User ID andPassword.
The User is hereby informed that Merchant will never ask the User for the User’s
password in an unsolicited phone call or in an unsolicited email. The User is hereby
required to sign out of his/ her Merchant account on the Website and close the web browser
window when the transaction(s) have been completed. This is to ensure that others
cannot access the User’s personal information and correspondence when the User
happens to share a computer with someone else or is using a computer in a public place
like a library or Internet café.
5. Debit Card / Credit Card OR Bank Account Details
30. The User agrees that the debit/credit card details provided by him/ her for use of the aforesaid
Service (s) must be correct and accurate and that the User shall not use a debit/ credit card, that
is not lawfully owned by him/ her or the use of which is not authorized by the lawful owner
thereof. The User further agrees and undertakes to provide correct and valid debit/credit card
details.
31. The User may make his/ her payment (Tender Fee/Earnest Money deposit) to Merchant by
using a debit/credit card or through online banking account. The User warrants, agrees and
confirms that when he/ she initiates a payment transaction and/or issues an online payment
instruction and provides his/ her card / bank details.
FY Multiplying factor
2022-23 1.0
2021-22 1.10
2020-21 1.21
2019-20 1.33
2018-19 1.46
2017-18 1.61
Applicant should indicate actual figures of costs and amount for the works executed by them
without accounting for the above-mentioned factors.
3.5.3. GENERAL EXPERIENCE
A. The Applicant shall meet the following minimum qualifying criteria:
1. Maximum of the annual financial turnover in, last 5 (Five) years (in all Classes of civil
engineering construction work only) worked out for base year shall not be less than
Rs.*283.85 lakhs., In support of this, scanned copy certificate by the Chartered
Accountant showing sources of receipt should be produced.
*The amount shall be 75 % of the value of work per year = Total value of work x 75%
Period of completion in year
B. The works may have been executed by the Applicant as prime contractor or as a member of
joint venture or sub contractor. As per G.R. T.D.D. No. CAT/2017 / Pra.Kr. 08 / Mantralaya,
Mumbai Dt. 27.09.2018 Para No. 2:9: E As a sub contractor, he should have acquired the
experience of execution of all major items of works under the proposed contract.
3. Minimum Quantity of items executed in any one year during last Five years.
No. Item of Work Minimum Unit
Quantity
Required = 30 %
1 Reinforced Cement Concrete M-20 & above 0.00 Cubic Meter
(2018-19, 2019-20, 2020-21, 2021-22, 2022-23) (updated to the current price level)
rate of inflation may be taken as 10 per cent per year which will take into account the
completed as well as works in progress;
B = Value at current price level of the existing commitments and ongoing works to be
Completed.
N = Number of years prescribed for completion of the works for which the bids are
Invited,
3.5.7. Disqualification
Even though the Applicants meet the above criteria, they are subject to be disqualified if
Records of poor performance such as abandoning the work, record of poor performance
such as abandoning the works, not properly completing the contract, inordinate delays in
completion, litigation history, or financial failures etc.; and/or
Participated in the previous bidding for the same work and had quoted unreasonably
high or low bid prices and could not furnish rational justification for it to the Employer.
iv. If the amount of Performance Security Deposit as required above (under A + B + C) is not
submitted by the bidder then his offer will be treated as ''Non Responsive" and will not be
considered.
v. The D.D./F.D.R/B.G. should bear the MICR and IFSC Code Number of the issuing bank.
vi. The Hard Copy of D.D./F.D.R/B.G. Shall be submitted in the office of the Executive
Engineer, P.W. (Tribal) Division, Thane within 8 (Eight) Days from the date of
opening of Envelope No. 1 and 2.
vii. If it is found that the D.D./F.D.R./B.G. as above submitted by the bidder is False / Forged
then the Earnest Money submitted by such bidder shall be Forfeited and his registration as
a contractor of Tribal Development Department will be suspended & he willbe entered in
the Black List.
viii. The Additional Performance Security shall be returned immediately upon satisfactory
completion of work, the certificate of which shall be issued by the Executive Engineer,
P.W. (Tribal) Division, Thane before releasing the additional security.
ix. The above referred Government Resolution is the part of this tender.
Information regarding contract as well as blank tender forms can be downloaded from the e-
tendering website upon providing the details of the payment of cost as detailed in the N.I.T.
8. The tenders who do not fulfill the condition of the notification and the general rules and
directions for the guidance of contractor in the agreement form or are incomplete in any
respect are likely to be rejected without assigning any reason therefore.
10. The quarries for extraction of metal, murum etc. provided in the sanctioned estimate are as
per survey conducted by the Department. The Contractor should however examine these quarries
and see whether full quantity of materials required for execution of the work strictly as per
specification are available in these source before quoting the rates. In case the materials are
not available due to reasons whatsoever, the contractor will have to bring the materials from any
other source with no extra cost to Government. The rates quoted, should therefore be for all
leads and lifts from wherever the materials are brought at site of work and inclusive of royalty to
be paid to the Revenue.
The offer shall remain open for acceptance for minimum period of 90 days from the Date of
opening of Envelope No.2 (Financial Bid) and thereafter until it is withdrawn by the contractor
by notice in writing duly addressed to the authority opening the tender and sent by
Registered Post Acknowledgment due.
20. After completion of the e-tendering process, the successful bidder will have to submit the
hard copy of downloaded tender document and drawings duly signed on each page by the
contractor or his authorized signatory. The tender should bear full signature of the tenderers, or
his authorized power of attorney holder in case of Firm.
23. महारा शासन महसु ल व वन वभाग शासन प रप क द.18.03.2021 अ वये ा त झाले या आदेशा वये मु ांक
अ ध नयम या च लत तरतु द नु सार या कायकं ाटाबाबत मु ांक शु क आकारणी करावयाची अस याने आपण या
कायवाह संबध
ं ीत आव यक असलेले मु ांक शु क सह. िज हा नबंधक (वग-1) तथा/ कं वा मु ांक िज हा धकार
यांचेकडे पर पर भ न या यथ ा त होणार मु ांक शु क भरणा पावती / पोहोच काम सु कर यापु व या
कायालयाकडे ता काळ जमा करावी.
Sr. Name Agreement Tendered Date of Stipulated Value Value of Probable Remarks
No of No. Amount Commencement date of of work Balance date of
work Completion already work to completion
done be
executed
during
next
……...
months
1 2 3 4 5 6 7 8 9 10
SAMPLE FORM
Sr. Name of Name & Tendered Time Probable date when Other relevant
No work Address of Amount limit decision is expected details, if any,
Client
1 2 3 4 5 6 7
SAMPLE FORM
Note :-This is only a standard form. Details are to be furnished in this format in the form of type
written statements which shall be Scanned and enclosed in Envelope No.1 duly singed. The
documentary proof of work in handed shall also be Scanned and submitted with this statement duly
attested by Gazette officer. Work done certificate shall be signed by the Authority not below the rank of
Executive Engineer.
Signature of Contractor
1 2 3 4 5 6
SAMPLE FORM
Note :- Atleast 50% of Amount of Tender work was mandatory to be done in Tribal Area during
last 7 (Seven ) Years..
\
Signature of Contractor
NAME OF CONTRACTOR:-
Sample form
Note :-
1) This is only a standard form. Details are to be furnished in this format in the form of
type written statements which shall be Scanned and enclosed in Envelope No.1 duly
signed.
2) The documentary proof of Own machinery shall be Scanned and submitted with this
statement duly attested by Gazetted officer
Name of Contractor:-
Sr. Name of Equipment No of Kind & Capacity Age and Present Remark
No unit Make condition Location
Sample form
Note :-
1. The Documentary proof i.e. Agreement of Hire on original stamp paper of Rs.100/-. Between
Contractor & Owner of Machinery is Compulsory and shall be scanned and submitted with
this statement in the standard form. i.e. Form-
2. Documentary proof of owner of machinery is compulsory and shall be scanned & Submitted
with this statement.
Signature of Contractor
NAME OF CONTRACTOR:-
Sr. Name Name & address of the Place & Agreement Date of Tendered Total Actual date Remarks
No of work organization for whom Country No. and Date commen Cont. Cost. Of of comple (Principal
the work was done. cement Work tion features in
Done brief)
1 2 3 4 5 6 7 8 9 10
SAMPLE FORM
Note :-
This is only a standard form. Details are to be furnished in this format in the form of type written
statements which shall be Scanned and enclosed in Envelope No.1 duly signed. The Documentary
proof of Similar type and magnitude attested by Gazetted Officer shall be Scanned and submitted with
this statement. Work Done Certificate shall be signed by the Authority not below the rank of
Executive Engineer.
Signature of Contractor
NAME OF CONTRACTOR :-
SAMPLE FORM
Note : - This is only a standard form. Details are to be furnished in this format in the form of
type written statements which shall be Scanned and enclosed in Envelope No.1 duly signed. The
Documentary proof of Qualification of technical person shall be Scanned and attached with this
statement. Similarly consent letters of technical personal shall be scanned and attached with this
statement.
Signature of Contractor
NAME OF CONTRACTOR:-
SAMPLE FORM
Note :- This is only a standard form. Details are to be furnished in this format in the form of
type written statements which shall be Scanned and Enclosed in Envelope No.1 duly
signed. The Documentary proof of work done certificate attested by Gazetted Officer
shall be Scanned and attached with this statement. Work done certificate shall be signed
by the Authority not below the rank of Executive Engineer.
Signature of Contractor
I/We hereby declare that I/We have made myself/ourselves thoroughly conversant with
the sub-soil conditions, the local conditions regarding all materials (suchmas stone,
murum, sand, etc.) and labour on which I/We have based my/our rates for this work.
The specifications, conditions, bore results and lead of materials on this work have been
carefully studied and understood by me/us before submitting this tender.
I/We undertake to use only the best materials approved by the Executive Engineer,
Public Works (Tribal) Division, Thane or his duly authorized assistant, before starting the work
and to abide by his decision.
I/We hereby further declare that my/our tender is unconditional in every manner of
whatsoever in nature.
I/We hereby undertake to pay the laborer’s engaged on the work as per minimum wages
Act, 1948 applicable to the zone concerned.
AUTHORITY LETTER
1. That I have submitted on line Tender for the work (Name of Work) on portal
http://mahatenders.gov.in of Government of Maharashtra.
2. That I have carefully gone through, read, thoroughly studied and understood all terms and
conditions, specification included in the tender document (Tender Form, Detail Tender
Notice, Conditions and Specifications common set of Deviations drawings etc.) I hereby
accept all these conditions. I agree to abide by the terms and condition in the tender
document and agree to execute the work as per terms and conditions, specifications laid
down in the tender document.
3. That I have furnished EMD (Earnest Money Deposit) from the Bank Account in the name
of my firm only.
4. I do hereby state on oath that the documents uploaded by in Envelope No. 1 of this tender
are true, correct and bonafide. There are no errors and omissions in the uploaded
documents.
5. I do hereby the state on oath that the value of work in hand (Value of B) is accurate on the
date of submission of this tender. If in the future it is found wrong or misleading. I am
liable for action under Indian Penal Code, if any papers are found false/ fraudulent during
contract period and even after the completion of contract.
6. I am liable for action under Indian Penal Code for submission of any false/ fraudulent paper /
information submitted in Envelope No. 1.
7. The undersigned hereby authorize(s) and request(s) any bank, person, firm or corporation
to furnish pertinent information deemed necessary and requested by the Department to
verify this statement or regarding my (our) competence and general reputation.
Place :
[The Bond of the above Affidavit should be submitted on a Rs. 500/- Non Judicial Stamp
Paper and it shall be notarized along with the Tender fees’ D.D. / Pay Order & EMD.)
Name of Agency :-
Agreement No. :-
The contractor hereby declares that the water proofing work carried out under
contract shall be of the best quality and workman particulars contained / mentioned in the
clause hereof and the contactor hereby guarantee that the said work would continue to
confirm to the description and quality aforesaid for a period of Ten Years from the date of
handing over the said work to the department and notwithstanding the fact that the
Department may have inspected and or approved the said work be discovered not to
confirm to the description and quality aforesaid or have deteriorated (and the decision of
the Engineer-in-charge in that behalf will be final and conclusive)the Department will be
entitled to reject the said work or such portion thereof as may be discovered not to conform to
the said description and quality.
On such rejection, the work will be at the contractor’s risk and all the provisions
herein contained relating to rejection of the work etc. shall apply. The contractor shall, if so
called upon have to make good the work etc. or such portion thereof, as is rejected by the
engineer in charge, otherwise the contractor shall pay to the department, such damages, as
may arise be the reason of the breach of the condition herein contained. Nothing herein
contained shall prejudice any otherright of the Department on that behalf under this contract
or otherwise. 25 % amount of executed amount of water proofing (in addition to his bond)
will be recovered from running / final bill as aretention money this amount will be refunded
to contractor after completion of defect liability period of Seven years prescribed for water
proofing items.
Date :
Place :
Contractor
Name of Agency :-
Agreement No. :-
The contractor hereby declares that the Anti Termite Treatment carried out under this
contract shall be of the best quality and workmanship and shall be strictly in accordance with the
specifications and particulars contained / mentioned in the clause hereof and the contractor
hereby guarantees that said work would continue to confirm to the description and quality
aforesaid for a period of Ten years from the date of handing over the said work Department
and notwithstanding the fact that may have inspected and or approved the said work, if
during the aforesaid period of Ten years, the said work be discovered not to decision
conform to the description and quality aforesaid or have deteriorated (and the decision of
Engineer in charge in the behalf will be final and conclusive) the Department will be entitled
to reject the said work or such portion thereof as may be discovered the work will be at the
contractors risk and all provisions herein contain relation to not conform to the said
description and quality. On such rejection, the rejection of work etc. shall apply. The
contractor shall, if so called upon have to make good the work etc. or such portion thereof,
as is rejected by the Engineer in charge otherwise the contractor shall pay to the department,
such damages, as may arise by the reason of the breach of the condition herein contained.
Nothing herein contained shall prejudice any other right of the department on the behalf under
this contact or otherwise.
Date :
Place :
Contractor
1 Foundation : The structure proposed in R.C.C. framed type R.C.C. Box footing (M25)
with 0.15 m thick , PCC (1:2:4) below footing columns, beams etc. , Brick
masonry 0.23 m thick in C.M. 1:6 for plinth wall
2 Structure : R.C.C. M-25 framed structure G+1 Storey
3 Roof : R.C.C. M-25 grade slab for all floors with waterproofing at terrace level
4 External wall : A.A.C. block masonary walls 23 centimeters thick and 3.60 meter floor
height
5 Internal Wall : A.A.C. block masonary walls 10 centimeters thick Bath, Toilet blocks only
6 Plastering & : Cement Plaster 12 & 20 mm For Internal
finishing Sand Faced Plaster For External
7 Flooring & : Floor – Vitrified mat finish Tile Floor
Dado Floor -WC& Bath - Vitrified mat finish
Dado - Vitrified mat finish
8 Doors, : Factory made steel door with frame of single leaf external grantek Texture
Windows & with powder coating/ factory made steel window with frame as per
Ventilator specification
9 Water : Waterproofing Treatment by using Acrylic Polymer with Fiber glass mesh
proofing
10 Water supply 10 cm P.V.C. nahani trap, Orrissa type W.C. pan, wash hand basin, S.W.
and sanitary gulley trap, inspection chamber of 60 x 45 & 90 x 45 cms, S.W. sewer lines
fitting and P.V.C. rain, water pipe, CPVC water supply line with necessary fittings
11 Coloring : Acrylic Emulsion Paint -External
Plastic Emulsion Paint – Internal
12 Miscellaneous
This form will state the work to be carried out as well as the date for submitting and opening
tenders and the time allowed for carrying out the work as per e-tendering schedule , also the
amount of earnest money to be deposited with the tender, and the amount of the
security deposit to be deposited by the successful tenderer and the percentage, if any, to
be deducted from bills, It will also state whether a refund of a quarry fees, royalties, and
ground rents will be granted. Copies of the specifications, designs and drawings estimated
rates; scheduled rates and any other documents required in connection with the work shall
be signed by the Executive Engineer for the purpose of identification and shall also be open
for inspection by contractors at the office of the Executive Engineer, during office hours.
In the event of the tender being submitted by a firm, it must be signed separately by each
partner thereof, or in the event of the absence of any partner, it shall be signed on
his behalf by a person holding a power of attorney authorizing him to do so.
2.
1.1. The contractor shall pay as per e-tendering schedule the sum of Rs.1,50,000/- (Rs.
One Lakhs Fifty Thousands Only) as and by way of earnest money. Earnest money
shall be paid via online mode using NEFT/RTGS or payment gateway mode.
1.2. In the event of his tender being accepted, subject to the provisions of sub-clause(iii) below,
the said amount of earnest money shall be appropriated towards the amount of security
deposit payable by him under conditions of General conditions of contract.
1.3. If, after submitting the tender, the contractor withdraws his offer, or modifies the
same, or if after the acceptance of his tender the contractor fails or neglects to furnish
the balance of security deposit without prejudice to any other rights and powers of the
Government, hereunder, or in law, Government shall be entitled to forfeit the full
amount of the earnest money deposited by him.
1.4. In the event of his tender not being accepted, the amount of earnest money deposited by
the contractor, shall unless it is prior thereto forfeited under the provisions of sub-clause
4. Any person who submits a tender shall fill up the usual printed form stating at what
percentage below or above the rates specified in Schedule 'B' (Memorandum
showing items of work to be carried out ) he is willing to undertake the work. Only
one rate or such percentage of all the estimated rates/scheduled rates shall be named.
Tenders which propose any alteration in the work specified in the said form of invitation to
tender, or in the time allowed for carrying out the work, or which contain any other
conditions of any sort will be liable to rejection. No printed form of tender shall include a
tender for more than one work, but if Contractor who wish to tender for two or more works
shall submit a separate tender for each. Tender shall have the name and the number of work
to which they refer written outside the envelope.
5. The Executive Engineer, PW (Tribal) Division, THANE shall open tenders as per e-
tendering schedule and intimated the results through e-mail. In the event of a tender being
accepted, the contractor shall, for the purpose of identification, sign copies of the
specifications and other documents mentioned in Rule 1.
6. The officer competent to dispose of the tender shall have the right of rejecting all or any of
the tenders without assigning any reason.
7. No receipt for any payment alleged to have been made by a contractor in regard to
any matter relating to this tender or the contract shall be valid and binding on Government
unless it is signed by the Executive Engineer.
8. The memorandum of work to be tendered for and the schedule of materials to be supplied by
the Tribal Development Department and their rates shall be filled in and completed by the
office of the Executive Engineer, before the tender form is issued. If a form issued to an
intending tenderer has not been so filled in and completed he shall request the said office to
have this done before he completes and delivers this tender.
9. All work shall be measured net by standard measure and according to the rules and customs
adopted by the Tribal Development Department and without reference to any local
custom.
10. Under no circumstances shall any contractor be entitled to claim enhanced rates for any
items in this contract.
13. The measurements of work will be taken according to the usual methods in use in the Tribal
Development Department and no proposals to adopt alternative methods will be accepted.
The Executive Engineer's decision as to what is " the method in use in the Tribal
Development Department" will be final.
14. The tendering contractor shall furnish a declaration along with the tender showing all
works for which he has already entered into contract and the value of the work that
remains to be executed in each case on the date of submitting the tender (with certificate
from the head of the office concerned).
15. Every tenderer shall scan and furnish along with the tender, information regarding the
Income tax circle or ward of the district in which he is assessed to income tax the reference
to the number of the assessment year
16. No foreign Exchange would be released be the department for the purchase of plant and
Machinery required for the Execution of the Work Contracted for
17. The contractor will have to construct shed for storing controlled and valuable materials
brought by him at work site at contractors cost. The material will be taken for use in the
presence of the departmental person. No material will be allowed to be removed from the
site of work.
18. Successful tenderer will have to produce to the satisfaction of the accepting authority a valid
and current license issued in his favor under the provision of Contract Labour (Regulation
and Abolition) Act 1970 before starting work, failing which acceptance of the tender will be
liable for withdrawal and earnest money will be forfeited to Government.
19. The contractor shall comply with the provision of the Apprentices Act 1961. and the rules
and orders issued there under from time to time. If he fails to do so, his failure will be breach
of contract and the Superintending Engineer, may in his discretion cancel the contract. The
contractor shall also be liable for any pecuniary liability arising on account of any violation
by him of the provisions of the Act.
(b)Estimated cost:
a. abide by the stipulation to keep the offer open for the period mentioned above or
b. Sign and complete the contract documents as required by the Engineer and furnish the
security deposit as specified in item (d) of the memorandum contained in paragraph
(i) above within the limit laid down in clause (I) of annexed General conditions of
contract. The amount of earnest money may be adjusted towards the security deposit or
refunded to me / us if so desired by me/us in writing, unless the same or any part
thereof has been forfeited as aforesaid.
Contractor
Signature of contractor
Address :
before submission of
tender .
The above tender is here by accepted by me for and behalf of the Govt. Of Maharashtra
Dated: … ./ … . / 2 0 2 4
Security Clause 1:The person / persons whose tender may be accepted (hereafter
Deposit called the contractor, which expression shall unless excluded by or repugnant
to the context include his, heirs, executors, administrators, and assigns) shall
(A) within 10 days (which may be extended by the Executive Engineer/
Superintending Engineer/or the Chief Engineer concerned up to one
month/two months/three months respectively if the Executive Engineer/
Superintending Engineer / Chief Engineer thinks fit to do so) of the receipt
by him of the notification of the acceptance of his tender deposit with the
Executive Engineer in cash or Government securities endorsed to the
Executive Engineer (if deposited for more than 12 months) of sum
sufficient which will make up the full security deposit specified in the
tender or (B) Permit Government at the time of making any payment to
him for work done under the contract to deduct such sum as will amount to
* One percent‚ of all moneys so payable such deductions to be held by
Government by way of security deposit, provided always that in the event
of the contractor depositing a lump sum by way of security deposit as
contemplated at (A) above then and in such case if the sum so deposited shall
not amount to *One percent‚ of the total estimated cost of the work it
shall be lawful for Government at the time of making any payment to the
contractor for work done under the contract to make up the full amount of‚
*One percent‚ by deducting a sufficient sum from every such payment as
last aforesaid until the full amount of the security deposit is made up. All
compensation or other sums of money payable by the contractor to
Government under the terms of his contract may be deducted from, or paid
by the sale of a sufficient part of his security deposit or from the interest
arising there from, or from any sums which may be due or may become
due by Government to the contractor under any other contract or transaction
of any nature on any account whatsoever and in the event of his security
deposit being reduced by reason of any such deduction or sale as
aforesaid, the contractor shall, within 10 days there after make good in
cash or Government securities endorsed as aforesaid any sum or sums which
may have been deducted from or raised by sale of his security deposit or
any part thereof. The security deposit referred to when paid in cash may,
at the cost of the depositor, be converted into the interest bearing securities
provided that the depositor has expressly desired this in writing. If the
amount of the security deposit to be paid in a lump sum within the
period specified at (A) above is not paid, the tender/contract already
accepted shall be considered as Cancelled and legal steps taken against
the contractor for recovery of the amounts. The amount of the security
deposit lodged by a contractor shall be refunded along with the payment
of the final bill, if the date up to which the contractor has agreed to
maintain the work in good order is over. If such date is not over, only 50
percent amounts of security deposit shall be refunded along with the
payment of the final bill. The amount of the security deposit retained by the
Government shall be released after expiry of period up to which the
contractor has agreed to maintain the work in good order is over. In the
Compensation Clause-2:The time allowed for carrying out the work as entered in the
for delay tender shall be strictly observed by the contractor and shall be reckoned
from the date on which the order to commence work is given to the
contractor. The work shall throughout stipulated period of the contract be
proceeded with, with all due diligence (time being deemed to be of the
essence of the contract on the part of the contractor) and the contractor
shall pay as compensation an amount equal to one per cent or such smaller
amount as the Superintending Engineer (whose decision in writing shall be
final) may decide, of the amount of the estimated cost of the whole work
as shown by the tenderer for every day that the work remains
uncommented, or unfinished after the proper dates. And further to ensure
good progress during execution of the work, the contractor shall be bound,
in all cases in which the time allowed for any work exceeds one month to
complete.
The contractor should complete the work as per phase period given below
15% of the work in 1/4 of the time
40% of the work in 1/2 of the time
70% of the work in 3/4 of the time
Full of the work in full of the time
Full work will be completed in 180 (One Hundred & Eighty Days)
(Including public holidays & monsoon.)
Note: The quantity of the work to be done within the particular time to be
specified above shall be fixed and inserted in the blank space kept for the
purpose by the Officer competent to accept the Contracts after taking into
consideration the circumstances of each case and abide by the programmed
of detailed progress laid down by the Executive Engineer
In the event of the contractor failing to comply with this conditions he shall
be liable to pay as compensation an amount equal to one percent or such
smaller amount as the Superintending Engineer (whose decision in writing
shall be final) may decide of the said estimated cost of the whole work for
every day that the due quantity of work remains incomplete. Provided
always that the total amount of compensation to be paid under the
provisions of this clause shall not exceed 10 percent of the estimated cost
of the work as shown in tender.
The Superintending Engineer Shall is Final Authority in this
respect, irrespective of the fact that the Tender is Accepted by the Chief
Engineer
Action when Clause 4 : If the progress of any particular portion of the work is
process of unsatisfactory the PMC/ Executive Engineer shall not withstanding that the
particular work general progress of the work is satisfactory in accordance with clause 2 be
is unsatisfactory entitled to take action under clause 3 (b) after giving the contractor 10 days
notice in writing and the contractor will have no claim for compensation for
any loss sustained by him owing to such action.
Contractor Clause 5 : In any case in which any of the powers conferred upon the PMC/
remains liable Executive Engineer by clause 3 and 4 hereof shall have become exercisable
to pay and the same shall not have been exercised, the non-exercise thereof shall not
compensation if constitute a waver of any of the conditions hereof and such powers shall not-
action not taken with standing be exercisable in any future case of default by the contractor for
under clause 3. which by under any clause or clauses hereof he is declared liable to pay
compensation amounting to the whole of his security deposit and the liability
of the contractor for past and future compensation shall remain unaffected. In
the event of the PMC/ Executive Engineer taking action under sub-clause (a)
or (c) of clause (3) he may, if he so desires, take possession of all or any tool
plant, materials and stores in or upon the works or the site thereof or belonging
to the contractor or procured by him and intended to be used for the execution
Power to take
of the works or the site thereof or belonging to the contractor, or procured by
possession of or
him and intended to be used for the execution of the work or any part thereof,
required
paying or allowing, for the same in account at the contract rates, or in the case
removal of or all
of contract rates not being applicable at current market rates, to be certified by
contractor’s
the PMC/ Executive Engineer whose certificate there of shall be final. In the
plant
alternative the PMC/ Executive Engineer may, by notice in writing to the
contractor or to his clerk of the works, foreman or other authorized agent
require him to remove such tools, plant materials or stores from the premises
within a time to be specified in such notice and in the event of contractor
failing to comply with any such requisition the PMC/ Executive Engineer may
remove them at the contractor’s expenses or sale them by auction or private
sale, at risk and account of the contractor in all such removal and the amount
of the proceeds and expenses of any such sale be final and conclusive against
the contractor.
Extension of Clause 6: If the contractor desires an extension of the time for completion of
the work on the ground of his having unavoidable hindering in it execution or
Clause 6 A : In the case of delay in handing over the land required for the
work due to unforeseen cause, the contractor shall not be entitled for any
compensation what so ever from the Government on the ground that the
machinery or the labor was idle for certain period. Contractor may, however
apply for extension of time limit which may be granted on the merit of the
case.
Final Certificate Clause 7 : On completion of the work the contractor shall be finished with a
certificate by the PMC/ Executive Engineer (Hereinafter called the Engineer-
in-charge) in such completion but no certificate shall be given nor shall the
work be considered to be complete until the contractor shall have removed
from the premises on which the work shall have been executed, all
scaffolding, surplus materials and rubbish and shall have cleaned of the dirt
from all wood work, doors, floors or other parts of any building in or upon
which the work has been executed or on which he may have had possession
for the purpose of executing the work or until the work shall have been
measured by the Engineer-in-charge or where the measurements have been
taken by his subordinates until they have received the approval of the Engineer
-in charge the said measurement being binding and conclusive against the
contractor. If the contractor fails to comply with the requirement of the clause
as to the removal of scaffolding, surplus material and rubbish and cleaning of
dirt on or before the date fixed for the completion of the work. The Executive-
in- charge may at the expense of the contractor, remove such scaffolding,
surplus materials and rubbish and dispose off the same as he think fit and
clean of such dirt as aforesaid and the contractor shall forthwith pay the
amount of all expenses so incurred but shall have no claim in respect of any
such scaffolding or surplus materials as aforesaid except for any sum actually
realized by the sale thereof.
Payments on Clause 8: No payment shall be made for any work estimated to cost less than
intermediate Rs. One thousand till after the whole of the said work shall have been
certificate to be completed and a certificate of completion given. But in the case of the works
regarded as estimated to cost more than Rs. One thousand, the contractor shall not
advance. submitting a monthly bill there off be entitled to receive payment
proportionate to the part of the work then approved and passed by the
Engineer-in-charge whose certificate of such approval and passing of the sum
payable shall final and conclusive against the contractor. All such intermediate
Payment at Clause 9: The rates for several items of work estimated to cost more than Rs.
reduced rates on 10000/- agreed to within shall be valid only when the item concerned is
account of items
of work not accepted as having been completed fully in accordance with the sanctioned
accepted as specifications. In case where the items of work are not accepted as so
completed to be completed the Engineer-in-charge may make payment on account of such
at the discretion
items at such reduced rates as he may consider reasonable in preparation of
of the Engineer
in charge. final or on account bills.
Bill to be on Clause 11 : The contractor shall submit all bills on the printed forms to be had
printed form. on application at the office of the Engineer-in-charge. The charges to be made
in the bills shall always be entered at the rates specified in the bid or in the
case of any extra work ordered in pursuance of these conditions and not
mentioned or provided for in the bid , at the rate hereinafter provided for such
work.
Stores supplied Clause 12 : If the specification or estimate of the work provides for the use of
by Government any special description of materials to be supplied from the T.D.D. store or if
it is required that the contractor shall use certain stores to be provided by the
Engineer-in-charge (such material and stores, and the prices to be charged
therefore as hereinafter mentioned being so far as practicable for the
Store Material Clause 12 A : All store of contractor material such as cement ,steel Bitumen
etc Supplied by the contractor at his own cost should be kept by the contractor
under lock and key and will be accessible for inspection by the PMC/
Executive Engineer or his agent at all times.
Work to be Clause 13: The contractor shall execute the whole and every part of the work
executed in like manner and both as regards materials and every other respect in strict
accordance with accordance with specifications. The contractor shall also confirm exactly fully
specification, and faithfully to the designs, drawings and instructions in writing relating to
drawing, orders the work signed by the Engineer-in-charge and lodged in his office and to
etc. which the contractor shall be entitled to have access for the purpose of
inspection at such office or at the site of work during office hours. The
contractor will be entitled to receive three sets of contracts drawings and
working drawings as well as one certified copy of the accepted bid along with
the work order free of cost. Further copies of the contract drawings and
working drawings, if required by him, shall be supplied at the rate of Rs. 548
/- per set of contact drawing and Rs. 150/- per working drawing except where
otherwise specified.
Alteration in Clause 14 : The Engineer-in-charge shall have power to make any alterations
Specifications in, or additions to, the original specifications, drawings, designs and
and designs not instructions, that may appear to him to be necessary or advisable during the
to invalidate progress of the work and the contractor shall be bound to carry out the work in
contract. accordance with any instructions in this connection which may be given to
him in writing signed by the Engineer-in-charge and such alteration shall not
invalidate the contract, and any additional work which the contractor may be
directed to do in the manner above specified as a part of the work shall be
Extension of The time limit for the completion of work shall be extended in the proportion
time in that the increase in its cost occasioned by alterations or additions bears to the
consequence of cost of the original contact work and the certificate of the Engineer-in-charge
addition or as to such proportion shall be conclusive.
alteration.
No claim to any Clause 15 : (1) If at any time after the execution of the contract documents,
payment or the engineer shall for any reason whatsoever (other than default on the part of
compensation for the contractor and for which Government is entitled to rescind the contract)
alteration in or desire that the whole or any part of the work specified in the bid should be
restriction of suspended for any period or that the whole or part of the work should not be
work. carried out at all he shall give to the contractor a notice in writing of such
desire and upon the receipt of such notice the contractor shall forthwith
suspend or stop the work wholly or in part as required, after having due regard
to the appropriate state at which the work should be stopped or suspended so
as not to cause any damage or injury to the work already done or endanger the
safety thereof provided the decision of the Engineer as to the stage at which
the work or any part or it could be or could have been safely stopped or
suspended shall be final and conclusive against the contractor. The contractor
(2) Where the total suspension of the work ordered as aforesaid continued for
a continuous period exceeding 90 days the contractor shall be at liberty to
withdraw from the contractual obligations under the contract so far as it
pertains to the unexecuted part of the work by giving a 10 days prior notice in
writing to the Engineer, within 30 days of the expiry of the said period of 90
days of such Intention and requiring the Engineer to record the final
measurements of the work already done and to pay the final bill. Upon given
such notice, the contractor shall be deemed to have been discharged from his
obligation to complete the remaining unexecuted work under this contract. On
receipt of such notice the Engineer shall proceed to complete the measurement
and make such payment as may be finally due to the contractor within a period
of 90 days from the receipt of such notice in respect of the work already done
by the contractor. Such payment shall not in any manner prejudice the right of
the contractor to any further compensation under the remaining provision of
this clause.
(3) Where the Engineer requires the contractor to suspend the work for a
period in excess of 30 days at anytime or 90 days in the aggregate, the
contractor shall be entitled to apply to the Engineer within 30 days of the
resumption of the work after such suspension for payment of compensation to
the extent of pecuniary loss suffered by him in respect of working machinery
rendered idle on the site or on account of his having, had to pay the salary or
wages of labour engaged by him during the said period of suspension.
Provided always that, the contractor shall not be entitled to any claim in
respect of any such working machinery, salary or wages for the first 30 days
whether consecutive or in the aggregate of such suspension or in respect of
any suspension what-so-ever occasioned by unsatisfactory work or any other
default on his part. The decision of the Engineer in this regard shall be final
and conclusive against the contractor.
(i) Any total stoppage of work on notice from the engineer under sub-
clause (1).
It shall be open to the contractor within 90 days from the service of (i)
the notice of stoppage of work or (ii) the notice of withdrawal from the
contractual obligation under the contract on account of the continued
suspension of the work (iii) notice under clause 14(1) resulting such
curtailment or produce to the Engineer satisfactory documentary
evidence, that he had purchased or agreed to purchase material for use
in the contracted work, before receipt by him of the notice of stoppage,
suspension or curtailment and require the Government to take over on
payment such material at the rates determined by the Engineer,
provided however, such rates shall in no case exceed the rates at which
the same were acquired by the contractor. The Government shall
thereafter take over the material so offered, provided the quantities
offered are not in excess of the requirement of the unexecuted work as
specified in the accepted bid and are of quality and specification
approved by the Engineer.
Time limit for Clause 16: Under no circumstance what so ever shall the contractor be entitled
unforeseen to any compensation from Government on any account unless the contractor
claims. shall have submitted claim in writing to the Engineer -in Charge within one
month of the cause of such claim occurring.
Action and Clause 17: If any time before the security deposit or any part thereof is
compensation refunded to the contractor it shall appear to the Engineer -in Charge or his
payable in case subordinate in-charge or the work, that any work has been executed with
of bad work. unsound, imperfect unskilled workmanship or with materials of inferior
quality, or that any materials or articles provided by him for the execution of
the work are unsound or of a quality inferior to that contracted for or are
otherwise not in accordance with the contractor, it shall be lawful for the
Engineer-in-charge to intimate this fact in writing to the contractor and then
not withstanding the fact that the work, materials or articles complained of
may have been inadvertently passed, certified and paid for, the contractor shall
be bound forthwith to rectify, or remove and reconstruct the work so specified
in whole or in part, as the case may be require or if so required, shall remove
the materials or articles so specified and provided other proper and suitable
materials or article at his own charge and cost and in the event of his failing to
do so within a period to be specified by the Engineer-in-charge in the written
intimation aforesaid, the contractor shall be liable to pay compensation at the
rate of 1% on the amount of the estimate for every day not exceeding 10 days,
during which the failure so continues and in the case of any such failure, the
Engineer-in-charge may rectify or remove and re-execute the work or remove
and replace the materials or article complained of, as the case may be, at the
risk and expense in all respects of the contractor. Should the Engineer-in-
Work to be open Clause 18: All works under or in course of execution or executed in
to inspection. pursuance of the contract shall at all times be open to the inspection to
inspection and supervision of the Engineer-in-charge and his subordinates
and the contractor shall at all times during the usual working hours, and at all
other times at which reasonable notice of the intention of the Engineer-in-
Contractor or charge of his subordinates to visit the works shall have been given to the
responsible contractor, either himself be present to receive order and instructions, or have
agent to be a responsible agent duly accredited in writing, present for that purpose.
present. Orders given to the contractor’s duly authorised agent shall be considered to
have the same force and effect as if they had been given to the contractor
himself.
Notice to be Clause 19 : The contractor shall give not less than 5 days notice in writing to
given before the the Engineer-in-charge or his subordinates in charge of the work before
work is covered covering up or otherwise placing beyond the reach of measurement any work
up. in order that the same may be measured and correct dimensions hereof taken
before the same is so covered up or placed beyond the reach of measurement
and shall not cover up or placed beyond the reach of measurement any work
without the consent in writing of the Engineer-in-charge or his subordinate in
charge of the work, and if any work shall be covered up or placed beyond the
reach of measurement without such notice having been given or consent
obtained the same shall be uncovered at the contractors expense and in default
thereof payment or allowance shall be made for such work or for the materials
with which the same was executed.
Contractor liable Clause 20 : If during the period of 10 (TEN ) Year from the date of
for damage done completion or from the date of commissioning, whichever is earlier as
and for certified by the Engineer-in-charge pursuant to the clause 7 of the contract, the
imperfection. said work is defective in any manner whatsoever, the contractor shall
forthwith on receipt on the notice in that behalf from the PMC/ Executive
Engineer duly commence execution and completely carry out at his cost in
every respect all the work that may be necessary for rectifying and setting
right the defects specified therein including dismantling and reconstruction of
unsafe portions strictly in accordance with and in the manner prescribed and
under the supervision of the Executive Engineer. In the event of the contractor
failing and neglecting to commence execution of the said rectification work
within the period prescribed therefore in the said notice the PMC/ Executive
Engineer may get the same executed and carried out departmentally or by
other agency at the risk on account and at the cost of the contractor. The
contractor shall forthwith on demand pay to the government the amount of
such costs, charges and expenses sustained or incurred by the government of
which the certificate of the PMC/ Executive Engineer shall be final and
Contractors to Clause 21 : The contractor shall supply at his own cost all material (except
supply plant, such special materials, if any, as may in accordance with the contract, be
ladders, supplied from the TRIBAL DEVELOPMENT DEPARTMENT’s. stores),
scaffolding etc. plant, tools, appliances, implements, ladders, cordage, tackle, scaffolding and
temporary works which may required for the proper execution of the work,
whether in the original, altered or substituted form, and whether included in the
specification or other documents forming part of the contract or referred to in
these conditions or not and which may be necessary for the purpose of
satisfying or complying with the requirements of the Engineer-in- charge as to any
matter as to which under these conditions he is entitled to be satisfied, or which
he is entitled to require together with the carriage therefor to and from the
work. The contractor shall also supply without charge the requisite number of
persons with the means and materials necessary for the purpose of setting out
works and counting, weighing and assisting in the measurement or examination
at any time and from time to time of the work or the materials. Failing which
the same may be provided by the Engineer-in-charge at the expense of the
contractor and the expenses may be deducted from any money due to the
contractor under the contract or from his security deposit or the proceeds of
sale thereof, or of a sufficient portion thereof.’
And is liable for The contractor shall provide all necessary fencing and lights required to protect
damages arising the public from accident, and shall also be bound to bear the expenses of
from non- defense of every suit, action or other legal proceedings that may be brought by
provisions of any person for injury sustained owing to neglect of the above precautions, and
lights, fencing to pay any damages and costs which may be awarded in any such suit action or
etc. proceedings to any such person, or which may with consent of the contractor
be paid for compromising any claim by any such person.
Clause 21A: The contractor shall provide suitable scaffolds and working
platforms, gangways, and stairways and shall comply with the following
regulations in connection therewith:
a) Suitable scaffolds shall be provided for workmen for all work that
cannot be safely done from a ladder or by other means.
i) Be of sound material
Measure for Clause 22: The contractor shall not set fire to any standing jungle, trees, bush
prevention of wood or grass without a written permit from the Executive Engineer.
fire.
When such permit is given and also in all cases when destroying cut or dug up
trees, bush wood grass etc. by fire, the contractor shall take necessary
measures to prevent such fire spreading to or otherwise damaging surrounding
property.
The contractor shall make his own arrangement for drinking water for the
labour employed by him.
Liability of Clause 23: Compensation for all damage done intentionally or unintentionally
contractors for by contractors labour whether in or beyond the limits of contractor for
any damage done government property including any damage caused by the spreading of any
in or outside damage fire mentioned in clause 22 shall be estimated by the Engineer-in-
work area. charge or such other officer as he may appoint and the estimates of the
Engineer-in-charge subject to the decision of the Superintending Engineer on
appeal shall be final and the contractor shall be bound to pay the amount of the
assessed compensation on demand, failing which the same will be recovered
from the contractor as damages in the manner prescribed in clause 1 or
deducted by the Engineer-in-charge from any sum that may be due to or
become due from government to the contractor under this contract or
otherwise. The contractor shall bear the expenses of defending any action or
other legal proceeding that may be brought by any person for injury sustained
Work on Sunday Clause 25 : No work shall be done on a Sunday without the sanction in
writing of the Engineer-in-charge.
Work not to be Clause 26 : The contract shall not be assigned or sublet without the written
sublet. Contract approval of the Engineer-in-charge. And if the contractor shall assign or sublet
may rescind and his contract, or attempt so to do, or become insolvent or commence any
security deposit
forfeited for proceedings to be adjudicated and insolvent or make any composition with his
subletting it creditors, or attempt so to do the Engineer-in-charge may be notice in writing
without approval rescind the contract. Also if any bribe, gratuity, gift, loan, perquisite, reward or
or for bribing a advantage, pecuniary or otherwise, shall either directly or indirectly be given,
public officer or promised by the contractor or any of his servants or agents to any public
if contractor
becomes officer or person in the employment of government in any way relating to his
insolvent. office or employment, or if any such officer or person shall become in any
way directly or indirectly interested in the contract, the Engineer-in-charge
may be giving notice in writing rescind the contract. In the event of a contract
being rescinded, the security deposit of the contractor shall thereupon stand
forfeited and be absolutely at the disposal of the Government and same
consequences shall as ensure as if the contract has been rescinded under clause
3 hereof and in addition the contractor shall not be entitled to recover or be
paid for any work therefore actually performed under the contract.
Sum payable by Clause 27 : All sum payable by a contractor by way of compensation under
way of any of these condition shall be considered as a reasonable compensation to be
compensation to applied of the use of Government without reference to the actual loss or
be considered as damage sustained and whether any damage has or has not been sustained.
reasonable
compensation
without reference
to actual loss.
Changes in the Clause 28 : In the case of a bid by partners any change in the construction of
constitution of a firm shall be forthwith notified by the contractor to the Engineer-in-charge
the firm to be for his information
notified.
Work to be under Clause 30 (1) : Except where otherwise specified in the contract and subject to
direction and the power delegated to him by Government under the code rules then in force,
control of the decision of the Superintending Engineer the Circle for the time being shall
Superintending be final, conclusive and binding on all parties to the contract upon all
Engineer. questions relating to the meaning of the specifications ,designs ,drawings and
instructions herein before mentioned and as to the quality of the workmanship
or material used on the work or as to any other question, claim, right, matter or
things whatsoever, in any way arising out of or relating to the contract designs,
drawing, specifications, estimates, instructions , orders of these conditions or
otherwise concerning the works or the execution or failure to execute the same
whether arising during the progress of the work or after the completion or
abandonment thereof.
(2) The contractor may within thirty days of receipt by him of any order
passed by the Superintending Engineer the Circle as aforesaid appeal against
it to the Chief Engineer concerned with the contract, work or project provided
that -
(a) The accepted value of the contract exceeds Rs. 10 lakhs (Rupees Ten
Lakhs)
(b) Amount of claim is not less than Rs. 1.00 lakh (Rupees one lakh)
(3) If the contractor is not satisfied with the order passed by the Chief
Engineer as aforesaid the contractor may within thirty days of receipt by him
of any such order, appeal against it to the concerned Secretary, TRIBAL
DEVELOPMENT DEPARTMENT who, if convinced the prima-facie the
contractor’s claim rejected by the Member Secretary/ Chief Engineer is not
frivolous and that there is some substance in the claim of the contractor as
would merit a detailed examination and decision by the Standing Committee,
shall put up to the Standing Committee at Government level for suitable
decision.
Store of Clause 31 : The contractor shall obtain from the T.D.D. stores all stores and
European or article of European or American manufacture which may be required for the
American work, or any part of the work or in making up any article required therefore or
manufactures to in connection therewith unless he has obtained permission in writing from the
be obtained from Engineer-in-charge to obtain such stores and articles elsewhere. The value of
the Government such stores and articles as may be supplied to the contractor by Engineer-in-
charge will be debited to the contractor in his account at the rates shown in the
Schedule in form “A” attached to contract and if they are not entered in the
said Schedule, they shall be debited to him at cost price which for the purpose
of this contract shall include the cost of carriage and all other expenses
whatsoever, which may have to be incurred in obtaining delivery of the same
Lump sums in Clause 32 : When the estimate on which a bid is made includes lump sumps
estimates. in respect of parts of the work the contractor shall be entitled to payment in
respect of items of work involved or the part of the work in question at the
same rates as are payable under this contract for such items, or if part of the
work question is not in the opining of the Engineer-in-charge capable of
measurement the Engineer-in-charge may at his discretion pay lump sum
amount entered in the estimate, and the certificate in writing of the Engineer-
in-charge shall be final and conclusive against the contractor with regard to
any sum or sums payable to him under the provision of this clause.
Action where no Clause 33 : In the case of any class of work for which there is no such
specification. specification as in mentioned in Rule-1, such work shall be carried out in
accordance with the Divisional specifications, and in the event of there being
no Divisional specification, then in such case the work shall be carried out in
all respects in accordance with the instruction and requirement of the
Engineer-in-charge.
Definition of Clause 34 : The expression ‘works’ or ‘work’ where used in these condition
work. shall, unless there be something in the subject or context repugnant to such
construction be constructed to mean the work or the work contractor to be
executed under or in virtue of the contract, whether temporary or permanent
and whether original altered substituted or additional.
Contractor’s Clause 35 : The percentage referred to in the bid shall be deducted from /
percentage added to the gross amount of the bill before deducting the value of any stock
whether applied issued.
to net or gross
amount of bill.
Quarry fees and Clause 36 : All quarry fees, royalties, octroi dues and ground rent for stacking
royalties materials if any, should be paid by the contractor.
Compensation Clause 37 : The contractor shall be responsible for and shall pay
under compensation to his Workmen payable under the Workmen’s compensation
Workman’s Act, 1923 (VIII of 1923), (hereinafter compensation is payable and or paid by
Compensation Government as principal under the subsection 91) of section 12 of the said Act
Act. on behalf of the contractor this shall be recoverable by Government from the
contractor under sub section 92) of the said section. Such compensation shall
be recovered in the manner laid down in clause 1 above.
Clause 37 A : The contractor shall be responsible for and shall pay expenses
of providing Medical aid to any workmen who may suffer a bodily injury as a
result on an accident. If such expenses are incurred by Government the same
shall be recoverable from the contractor forthwith and be deducted without
prejudice to any other remedy of Government from any amount due or that
(a) The worker shall be required to use the equipment so provided by the
contractor and the contractor shall take adequate steps to ensure proper
use of the equipment by those concerned.
(b) When work carried on in proximity to any place where there is no risk of
drawing, all necessary equipment’s shall be provided and kept ready for
use and all necessary steps shall be taken prompt rescue of any person in
danger.
(c) Adequate provision shall be made for prompt first-aid treatment for all
injuries likely to be sustained during the course of the work.
Clause 37 C : The contractor shall duly comply with the provision of “The
Apprentices Act 1961 (III of 1961) the rules made there under and the orders
that may be issued from time under the said Act and the said Rules and on his
failure or neglect to do so he shall be subject to all the liabilities and penalties
provided by the said Act and said Rules”.
Claim for Clause 38: Excess quantity shall be executed only after prior permission of
quantity of works the authority granting Administrative Approval to the work. It shall be paid at
entered in the bid bid rate only.
or estimate.
Clause 38: (1) Quantities in respect of the several items shown in the bid are
approximate and no revision in the bid ed rates shall be permitted in respect of
any of the items so long as, subject to any special provision contained in the
specification prescribed a different percentage of permissible variation, the
quantity of the items does not exceed the bid quantity by more than 25% and
so long as the value of excess quantity beyond this limit at the rate of the
items specified in the bid , is not more than Rs. 10,000/-
(3) Claim arising out of reduction in the bid ed quantity of any item beyond 25
percent will be governed by the provisions of clause 15 only when the amount
reduction beyond 25% at the rate of the item specified in the bid is more than
Rs. 5000/-.
Claim for Clause - 39: The contractor shall employ any famine convict or other labor of
compensation for a particular kind or class, if ordered in writing to do so by the Engineer-in-
delaying starting charge.
of work
Claim for Clause - 40: No compensation shall be allowed for any delay caused in the
compensation for starting of the work on account of acquisition of land or in the case of
delaying starting clearance works on account of any delay in according to sanction of estimates
of work
Claim for Clause - 41: No compensation shall be allowed for any delay in the
compensation for execution of the work on account of water standing in borrow pits or
delaying starting compartments. The rates are inclusive of hard or cracked soil excavation in
of work mud, subsoil water or water standing in borrow pits and no claim for an
extra rate shall be entertained, unless otherwise expressly specified
Entering upon or Clause 42 : The contractor shall not enter upon or commence any portion of
commencing any work except with the written authority and instructions of the Engineer-in-
portion of work. charge or of his subordinate in charge of the work failing such authority the
contractor shall have no claim to ask for measurements of or payment for
work.
Minimum age of Clause 43 : (i) No contractor shall employ any person who is under the age of
persons 18 years.
employed, the
employment of (ii) No contractor shall employ donkeys or other animals with breeching of
donkey and/or string or thin rope. The breeching must be at lease 3 inches wide and should be
other animals of tape (Newar)
and the payment
(iii) No animals suffering from sores, lameness or emaciation or which is
of fair wages.
immature shall be employed on the work.
(iv) The Engineer-in-charge or his agent authorised to remove from the work
any person or animal found working which does not satisfy these conditions
and no responsibilities shall be accepted by the Government for any delay
caused in the completion of the work by such removal.
(v) The contractor shall pay fair and reasonable wages to the workmen
employed by him in the contract undertaken by him. In the event of any
disputes arising between the contractor and his workmen on the grounds that
(vi) The contractor shall provide drinking water facilities to the workers.
Similar amenities shall be provided to the workers engaged on large work in
urban areas.
Method of Clause 44: Payments to contractor shall be made by cheques drawn on any
payment. treasury within the Division convenient to them. Provided the amount exceeds
Rs. 100/- Amount not exceeding Rs. 100/- will be paid in cash.
Acceptance of Clause 45 : Any contractor who does not accept these conditions shall not be
conditions allowed to bid for works.
compulsory
before bid ing the
work.
Employment of Clause 46: If Government declares a state of scarcity or famine to exist in any
scarcity labour. village situated within 1 Kms. of work, the contractor shall employ upon such
parts of the work as suitable for unskilled labour any person certified to him
by the PMC/ Executive Engineer or by any person to whom PMC/ Executive
Engineer may have delegated this duty in writing to be in need of relief and
shall be bound to pay to such persons wages not below minimum which may
arise in connection with the implementation of this clause shall be decided by
the PMC/ Executive Engineer whose decision shall be final and binding on the
contractor.
Clause 47: The price quoted by the contractors shall not in any case exceed
the control price, if any, fixed by Government or reasonable price which is
permissible for him to charge as private purchaser for the same class and
description of goods under the provisions of Hoarding and profiteering
Prevention Ordinance 1984 as amended from time to time. If the price quoted
exceeds the controlled price or the price permissible under Hoarding and
Profiteering Prevention Ordinance, the contractor will specifically mention
this fact in his bid along with reasons for quoting such higher price. The
purchaser at his bid along with reasons for quoting such higher price. The
purchaser at his discretion will in such higher price. The purchaser at his
discretion will in such case exercises the right of revising the price at any stage
so as to confirm with the controlled price on the permissible under the
Hoarding and Profiteering Ordinance. This discretion will be exercised
without prejudice to any other action that may be taken against the contractor.
Clause - 48:
GST shall be payable on the accepted contract value at prevailing
rates separately. Contractor shall quote his rates excluding GST.
Provisional amount of GST @ 2% i.e.1% C.G.S.T. + 1% S.G.S.T. will be
deducted at source (TDS) after the enforcement of Sections 51 of Maharashtra
Goods and Services Act.2017
Clause 49: In case of materials that remains surplus with the contractor for
those issued for the work contracted from the date of ascertainment of the
materials being surplus be taken as the date of sale for the purpose of sales tax
and the sale tax will be recovered on such sale.
Clause 50: The contractor shall employ the unskilled labour to be employed
by him on the said work only from locally available labours and shall give
preference to those persons enrolled under Maharashtra Government
Employment and Self Employment Department Scheme.
Provided, however, that if the required unskilled laboured are not available
locally, the contractor shall in the first instance employ such number of
Clause 52: All amount whatsoever which the contractor is liable to pay to the
Government in connection with the execution of the work including the
amount payable in respect of (1) Material and / or stores supplied / issued
hereunder by the Government to the contractor, (2) Hire charges in-respect of
heavy plant machinery and equipment given on hire by the Government to the
contractor, for execution by him of the work and / or on which the advance
have been given by the Government to the contractor shall be deemed to be
arrears of the lands revenue and the Government may without prejudice to any
other rights and remedies of the Government recover the same from the
contractor as arrears of land revenue.
Clause 53: The contractor shall duly comply with all the provisions of the
contract labour (Regulation and Abolition) Act 1970. (37 of 1970) and the
Maharashtra Contract Labour (Regulation and Abolition) Rules 1971 as
amended from time to time and all other relevant statutes and statutory
provision concerning payment of wages particularly to workmen employed by
the contractor and working on the site of the work. In particular the Contractor
shall pay wages to each worker employed by him on the site of the work at the
rates prescribed under the Maharashtra Contract Labour (Regulation and
Abolition) Rules 1971. If the contractor fails or neglects to pay wages at the
said rates or make short payment and the Government makes such payment of
wages in full or part thereof less paid by the contractor, as the case may be the
amount so paid by the Government to such worker shall be deemed to be
arrears of land revenue and the Government shall be entitled to recover the
same as such from the contractor or deduct the same from the amount payable
by the Government to the contractor hereunder or from any other amounts
payable to him by the Government (Minimum Wages Act, as per Government
Circular (AT / 1284 / (120) / Building, dated 14/08/1988).
Price Variation Clause 54 : If during the operative Period of the Contract as defined in
Clause condition (i) below, there shall be any variation in the Consumer Price Index
(New Series) for Industrial Workers for Mumbai Center as per the Labour
Gazette published by the Commissioner of Labour, Government of
Maharashtra and/or in the Whole-sale Price Index for all commodities prepared
by the Office of Economic Adviser, Ministry of Industry, Government of India
or in the price of petrol / oil, and lubricants and major construction materials
like bitumen, cement, steel, various types of metal pipes etc., then subject to
1. Labour component
2. Material component
3. Petrol, Oil and Lubricants Component
4. Bitumen Component
5. HYSD & Mild. Steel Component
6. Cement Component
7. C.I. and D.I. Pipes Component
calculated as per the formula hereinafter appearing, shall be made. Apart from
these, no other adjustments shall be made to the contract price for any reasons
whatsoever. Component percentage as given below are as of the total cost of
work put to tender. Total of Labour, Material & POL components shall be 100
and other components shall be as per actuals.
Note :- If Cement, HYSD & Mild. Steel, Bitumen, C.I. and D.I. Pipes are
Supplied on Schedule “A” then respective component shall not be considered.
Also if particular component is not relevant same shall be deleted.
0.85 P K1 L1 - L0
V1 = X
x 100 L0
Where,
V1 = Amount of price variation in Rupees to be allowed for Labour
component.
P = Cost of work done during the quarter under consideration
minus
the cost of Cement, HYSD &Mild Steel, Bitumen, C.I. and D.I. Pipes
calculated at the basic star rates as applicable for the tender,
consumed during the quarter under consideration.
Where,
V2 = Amount of price variation in Rupees to be allowed for Materials
component.
P = Same as worked out for Labour component.
K2 = Percentage of Materials Component as indicated above.
M0 = Basic wholesale Price Index shall be average wholesale price index for
the quarter preceding the month in which the last date prescribed for
receipt of tender falls.
M1 = Average wholesale Price Index during the quarter under
consideration.
3) FORMULA FOR PETROL, OIL AND LUBRICANT
COMPONENT :-
0.85 P K3 P1 - P0
V3 = x
x 100 P0
Where,
V4= QB ( B1 – B0)
Where,
V4 = Amount of price variation in Rupees to be allowed for Bitumen
component
QB = Quantity of Bitumen (Grade 30/40 & Grade 60/70) in metric tonnes
used in the permanent works and approved enabling works during the
quarter under consideration
B1 = Current, average ex-refinery price per metric tonne of Bitumen (Grade
30/40 & Grade 60/70) under consideration including taxes (octroi,
excise, sales tax, GST) during the quarter under consideration.
B0 = Basic rate of Bitumen in rupees per metric ton as considered for
working out value of P or average ex-refinery price in rupees per
metric ton including taxes (octroi, excise sales tax,GST) of Bitumen
for the grade of bitumen under consideration prevailing quarter
preceding the month in which the last date prescribe for receipt of
tender; falls, whichever is higher.
S0 (SI1 - SI0)
V5 = xT
Sl0
Where,
V5 = Amount of price variation in Rupees to be allowed for H.Y.S.D. Steel
component.
S0 = Basic rate of H.Y.S.D. Steel in rupees per metric tonne as considered
for working out value of P.
SI1 = Average Steel Index as per RBI Bulletin during the quarter under
consideration.
SI0 = Average of Steel Index as per RBI Bulletin for the quarter preceding
the month in which the last date prescribed for receipt of tender falls.
T = Tonnage of steel used in the permanent works for the quarter under
consideration.
C0 (CI1 - CI0)
V6 = xT
Cl0
Where,
V6 = Amount of price escalation in Rupees to be allowed for Cement
component.
C0 = Basic rate of cement in rupees per metric tonne as considered for
working out value of P.
CI1 = Average of Cement Index published in the RBI Bulletin for the quarter
i) The operative period of the Contract shall mean the period commencing
from the date of work order issued to the Contractor and ending on the
date on which the time allowed for the completion of the works specified
in the Contract for work expires, taking into consideration the extension of
time, if any, for completion of the work granted by the Engineer under the
relevant clause of the Conditions of Contract in cases other than those
where such extension is necessitated on account of default of the
Contractor. The decision of the Engineer as regards the operative period of
the Contract shall be final and binding on the Contractor. Where any
compensation for liquidated damages is levied on the Contractor on
account of delay in completion or inadequate progress under the relevant
Contract provisions, the price adjustment amount for the balance of work
from the date of levy of such compensation shall be worked out by
pegging the indices, L1, M1, C1, P1, B1, S11 and C11 to the levels
corresponding to the date from which such compensation is levied.
ii) This price variation clause shall be applicable to all contracts in B1/B2 &
C from but shall not apply to piece works. The price variation shall be
determined during each quarter as per formula given above in this clause.
iii) The price variation under this Clause shall not be payable for the extra
items required to be executed during the completion of the work and also
on the excess quantities of items payable under the provisions of Clause
38/37 of the contract from B1/B2 respectively. Since the rates payable for
extra items or the extra quantities under Clause 38/37 are to be fixed as per
current DSR or as mutually agreed to yearly revision till completion of
such work. In other words, when the completion/ execution of extra items
as well as extra quantities under Clause 38/37 of the contract from B1/B2
extends beyond the operative date of the DSR then rates payable for the
same beyond the date shall be revised with reference to the current DSR
prevalent at that time on year to year basis or revised in accordance with
(A)The ant malaria and other health measures shall be as directed by the Joint
Director (Malaria and Filarial) of Health Services, Pune.
(B.) Contractor shall see that mosquito genie conditions a r e not created
so as to keep vector populations to the minimum level.
(C) Contractor shall carry out anti- malaria measures in the area as per
guidelines prescribed under National Malaria Eradication Programmed and
as directed by the Joint Director(M & F) of Health Services, Pune.
(D.) In case of default in carrying out prescribed ant malaria measure
resulting increasing in malaria incidence contractor shall be liable to pay to
Government the amount spent by Government on antimalaria measures to
control the situation in addition to fine.
(E.) RELATION WITH PUBLIC AUTHORITIES:
The contractor shall make sufficient arrangement for draining away the
sullage water as well as water coming from the bathing and washing places
and shall dispose off this water in such a way as not to cause any nuisance.
He shall also keep the premises clean by employing sufficient number of
sweepers. The contractor shall comply with all rules regulation, byelaws
and direction given time to time by any local or public authority in
connection with this work and shall pay fees or charges which are livable on
him without any extra cost to Government.
In addition to the condition of contract described before, following General Condition shall
also become part of this bid document and will later become part of the contract.
1. COMPETANCY OF TENDERER :
The work will be awarded only to those contractors who are considered to be substantially
responsive bidders, capable of performing the class of work to be completed. Before passing
the final award any or all bidders may have to show that they have the necessary experience,
facilities, ability and financial resources to execute the work in satisfactory manner and also
within the stipulated time.
2. PAYMENTS :
The tenderer’s must understand clearly that the rates quoted are for completed work and
include all costs due to labor, all leads and lifts involved and if further necessitated,
scaffolding plant, supervision, service works, power, royalties, octroi taxes etc. and to include
all to cover the cost of lighting on night work if any and round the clock work as and when
required and no claim for additional payment beyond the prices or rates quoted will be
entertained and the tenderer shall not be entitled subsequently to make any claim on the
ground of any representation or on any promise by any person (whether member in the
employment of any Public Works Department or not) or on the ground of any failure on his
part to obtain all necessary information for the purpose of making his tender and fixing the
several prices and rates therein relieve him from any risks or liabilities arising out of the
tender.
3. INDEMNITY :
The Contractor shall indemnify the Government against all actions, suits, claims and demands
brought or made against it in respect of anything done of committed to be done by the
contractor in execution of or in connection with the work of this contract and against any loss
or damage to the Government in consequence to any action or suit being brought against the
Contractor for anything done or committed to be done during the execution of this contract.
The Government may at its discretion and entirely at the cost of the contractor defend such
suit, either jointly with the Contractor or single in case the latter chooses not to defend the
case.
4. ACCEPTANCE :
Intimation of acceptance of tender will be given by a telegram or a letter sent by Registered
Post to the address given below the signature of the tenderer in the tenders. The tenders
which do not fulfill any of the above conditions or those in the form and which are incomplete
in any respect shall be liable for rejection.
5. PRECAUTIONS TO BE TAKEN BY THE CONTRACTOR TO PREVENT
The Contractor shall be responsible for the quality of the work in the entire construction work
within the contract. He shall, therefore, have his own independent and adequate set up for
ensuring the same. This shall include establishing field laboratory for testing required for
works. The laboratory shall be equipped with the equipment’s and apparatus required for the
testing. The list of various equipment’s/apparatus is enclosed on Page 124-125 for
information and guidance of the Contractor. These equipment’s shall be in working
condition. The Engineer in charge of the work will verify these equipment’s in the laboratory
at site. The work shall not be started unless and until the laboratory is equipped with
equipment’s. (Ref. Page 124-125 ). If the field laboratory is not established before
starting on Concrete items, Rs. 10 Lakh will be withheld from the next immediate RA
bill and field tests of construction material (70 % of the tests required as per frequency)
7.2 CO-ORDINATION :
When several agencies for different sub-works of the project are to work simultaneously on
the project site, there must be full coordination between the contractors to ensure timely
completion of the whole project smoothly. The scheduled dates for completion specified in
each contract shall therefore, be strictly adhered to. Each contractor may make his
independent arrangements for water, power, housing etc. if they so desire. On the other hand
the Contractor are at liberty to come to mutual agreement in this behalf and make joint
arrangements with the approval of the Engineer . No Contractor shall take or cause to be
taken any steps or action that may cause, distruption, discontent, or disturbance of work,
labour or arrangement etc. of the contractor in the project localities. Any action by any
Contractor which the Engineer in his unquestioned discretion may consider as infringement of
the above code, would be considered as a breach of the contract conditions and shall be dealt-
with accordingly.
In case of any dispute of disagreement between the Contractors, the Engineer’s
decision regarding the co-ordination, co-operation and facilities to be provided by any of the
Contractor shall be final and binding on the contractors concerned and such a decision shall
not vitiate any contract nor absolve the Contractor of his obligations under the contract nor
consider from the grounds for any claim or compensation.
7.3 TEMPORARY QUARTER AND SITE OFFICE
i. The Contractor shall at his own expense maintain sufficient experienced supervisory staff etc.
required for the work and shall make his own arrangements for housing such staff with all
necessary amenities. General layout plan for such structures shall be got approved from the
Engineer-in-charge. It will be the responsibility of the Contractor to get his lay out plan of
temporary structure approved from the local competent authority.
ii. The contractor shall provide furnish, maintain and remove on completion of the work; a
suitable office on the work site for the use of Executive Engineer or his representative. The
covered area exclusive of verandah should not be less than 40.00 sqm. It may have brick
walls and asbestos or corrugated iron roof, paved floor should be 45 cm. above ground level.
He should provide latrines, urinals and keep them clean daily. This will be supposed to be
included in his offer.
iii. If the site office is not established before starting on Concrete items, Rs. 5 lakh will be
withheld from the next immediate RA bill and will be released after establishment of field
laboratory. If the laboratory is not established by the contractor, the amount kept in deposit
8.3 EXPLOSIVE :
The Contractor shall at his own expense construct and maintain proper magazines, if such are
required for the storage of explosives for use in connection with the work and such
magazines, being situated constructed and maintained in accordance with the Government
Rules applicable in that behalf. The Contractor shall at his own expenses obtain such license
or licenses as may be necessary for storing and using explosives. Notwithstanding that the
location etc. or storage of explosives are approved by the Engineer , the Government , shall
not bear any responsibility whatsoever in connection with the storage and use of explosives
on the site or any accident or occurrence what -so-ever in connection, therewith, all operations
of the Contractor in or for which explosives employed being at the risk of contractor and upon
his sole responsibility and the Contractor hereby gives to Government an absolute indemnity
in respect thereof.
9.2 In case it becomes necessary for the due fulfillment of contract for the Contractor to occupy
land outside the Department limits, the Contractor will have to make his own arrangements
with the land owners and pay such rents, if any, are payable as mutually agreed between
them.
9.3 The Contractor shall duly comply with the provision of the Apprentices Act 1961 (iii of
1961) and the rules and orders made thereunder from time to time under the said Rules and
on his failure or neglect to do so he shall be subject to all the liabilities and penalties
provided by the said Act and Rules.
9.4 It is presumed that the Contractor has gone carefully through the Standard Specification
(Vol. I & II 1981 Edition) M.O.R.T. & H specifications (edition 2013) and Schedule of Rate
of the division, and studied the site conditions before arriving at rates quoted by him. The
special provisions and detailed specification of wording of any item shall gain precedence
over the corresponding contrary provisions (if any) in the standard specification given
without reproducing the details in contract. Decision of Engineer-in-charge shall be final in
case of interpretation of specification.
9.5 If the standard specifications fall short for the items quoted in the schedule of this contract
reference shall be made to the latest Indian Standard specifications, I.R.C. codes. If any of
items of this contract do not fall in reference quoted above, the decision and specifications
as directed by the Engineer-in-charge shall be final.
9.6 The stacking and storage of building materials at site shall be in such a manner as to prevent
deterioration or inclusion of foreign materials and to ensure the preservation of the quantity,
properties and fitness of the work. Suitable precautions shall be taken by Contractor to
protect the materials against atmospheric action fire and other hazards. The materials likely
to be carried away by wind shall be stored in suitable stores or with suitable barricades and
where there is likelihood of subsidence of soil, heavy materials shall be stored on paved
platforms. Suitable separating barricades and enclosure as directed shall be provided to
separate materials brought by contractor and from different sources of supply.
9.7 The contractor should provide at his risk and cost One Technical Supervisor having a valid
Diploma in Civil Engineering obtained from Government affiliated Engineering College
with minimum three year of field experience, out of which minimum two years of
experience in Multistoried Building (G+3) works. His service will be utilized by the
Engineer-in-Charge for period of Project Completion.
10. DEFINITIONS:
Unless excluding by or repugnant to the context :-
a) The expression "Government" as used in the tender documents shall mean the Tribal
Development Department of the Government of Maharashtra.
b) The expression "The Chief Engineer" as used anywhere in the tender papers shall mean
21 SPECIAL CONDITIONS:
21.1 The Contractor should ensure that all safety precautions are observed by their laboures,
working closed to the State Highway and while closing the State Highway precautions are
taken including insurance etc., for their labour at the cost of the contractor and the contractor
will bear all the expenses, compensation etc. if any accident occurs to the labour etc. No
claim in this regard on whatsoever account shall be entertained and this decision of the
Department will be final and conclusive.
21.2 The Contractor shall observe the rules and regulation imposed by traffic police for smooth
flow of traffic on the diversion road and shall not be entitled for claims any compensation
arising thereof.
21.3 In case of delay in handing over the land required for the work, due to unforeseen cause, the
Contractor shall not be entitled for any compensation what-so-ever form the Government on
ground that the machinery or labour was idle for certain period. Contractor may, however
apply for extension of time limit which may be granted on the merit of the case.
22. REJECTION OF MATERIALS NOT CONFORMING TO SPECIFICATIONS:
Any stock or batch of material(s) of which sample(s) does not conform to the prescribed test
and quality, shall be rejected by the Engineer or his representative and such materials shall be
removed from site by the Contractor at his own cost. Such rejected materials shall not be
made acceptable by any modifications.
Materials not corresponding in character and Quality with approved samples will be rejected
by the Engineer or his representative and shall be removed from site at the Contractor’s own
cost.
29. DIARY :
Contractor shall maintain, throughout the construction period, a diary in the from of a register
regarding the following :-
i) Daily presence of all categories of labours.
ii) Daily availability and use of machinery and equipment’s on work.
iii) Daily procurement, Consumption and balance of materials on site.
iv) Daily record of various visiting authorities alongwith name of the officers visited and
timing.
v) Details of work executed per day.
vi) The register shall be closed on daily basis and signature of Engineers in charge or his
representative should be taken over it.
30. The execution of Electrical work through Joint venture or subletting shall be the responsibility
of the tenderer.
31. ADDITIONAL TECHNICAL CONDITIONS
31.1 The work shall be carried out in the best workmanship like manner and in strict accordance
with P.W.D. hand book Volume I & II 1960. Edition supplemented by specification attached
and as per Standard Specifications Book of Government of Maharashtra of 1979 and as per
32. MAINTENANCE
i. The Contractor shall maintain the Completed Work for a period mentioned in Clause No.
20 after the completion of work without any extra cost to Government irrespective of the
designs, standards and specifications etc. 5% amount of the total work done shall be
recovered from running account bill and shall be withheld for period mentioned in clause
20 from the date of actual completion at the work as maintenance charges of maintaining and
keep Structure in good condition. This 5% amount withheld towards maintenance charges
shall be allowed to be replaced with bank guarantee or other recognised forms
Specifications for Structure and Bridge Work, 5th Revision, 2013. In the absence of relevant
Indian Standards, sampling and testing procedures shall be as approved by the Engineer.
C. The laboratory should be manned by a qualified Materials Engineer assisted by Materials
Inspector / Technicians, and the set up should be got approved by the Engineer.
D. The Contractor should prepare printed proforma for according readings and results of
each type of test, after getting the formats of the performance approved from the Engineer.
E. He should keep a daily record of all the tests conducted by him. Two copies of the test
results should be submitted to the Engineer for his examination and approval, of which one
copy will be returned to the Contractor for being kept at site of work.
The Material Engineer of the Contractor should keep close liaison with the Quality
Control Unit of the Engineer and keep the later informed of the sampling and testing
programme so that the Engineer's representative could be present during this activity, if
considered necessary
39. Quality Assurance Manual : Contractor shall prepare the quality assurance manual booklet
in consultation with the Executive Engineer. Quality assurance manual shall be
comprehensive document covering every aspect of the work. Superintending Engineer shall
approve this document. The quality manual document shall be used only after approval from
Superintending Engineer. Provision of the quality manual be binding on the contractor.
Quality manual shall be treated as a legal document as per with this contract document. It
shall be used till the work is completed in full respect.
2. In support of the bills, required measurements, drawings, quality control reports (field lab and
VQCC lab as per clause 24 of Additional General Condition), site supervision data
(SCADA) shall be submitted, the data so submitted shall have a facility to Tightly integrate it
with the contract conditions, provisions in the Maharashtra Public Works manual,
Maharashtra Public Works Account Code (updated to date of submission of this tender) and
current general engineering practices (issued through various govt. resolutions, govt. circulars,
Chief Engineer's Circulars etc. issued up to date of submission of this tender.) followed in
Public Works Department /Tribal Development Department.
b. Submission of printed and authenticated reports to the Engineer In charge as and when
required.
c. All data generated as per this special condition of contract shall be the property of TDD.
d. The architectural and RCC design plan mentioning measurement of items considered shall be
submitted with bill along with photographs.
Note : If frequency of tests for any material to be used for work is not mentioned in above table,
the frequency mentioned in relevant BIS codes / IRC Code / MoRTH specifications shall
be followed. The decision of the Engineer in Charge will be final in that case and the
tests will have to be carried out by the contractor at his own costs.
4. Cube moulds for concrete/ Cube moulds for cement mortar 6 Sets
10. Water bath- electrically operated and thermostatically controlled with 1 No.
0
adjustable shelves, sensitivity 1 C.
15. Atterberg Limits (liquid and plastic limits) Determination apparatus 1 Set
22. Compression testing machine, 100 Metric Tonne capacity with 1 No.
additional dial for flexural testing.
1.8 HOLLOWS IN CONCRETE: After concreting is complete the concrete surface particularly
where there is congestion of reinforcement, shall be tested by light hammering or if possible
by Schmitz hammer. Any portion showing signs of hollowness should be grouted
immediately.
I) FORMWORK :-
1.1 Formwork :- Formwork shall include all temporary forms of moulds required for forming the
concrete which is cast-in-situ, together with all temporary construction required for their
support. Unless otherwise stated all formwork shall conform to I.S. Specification.
1.2 Design of Formwork :- Formwork including complete false work shall be designed by the
contractor in accordance with I.S.: 2750 (1964), 4041 (1987) and all other relevant I.S. codes
without any extra cost to the Government and these shall be got approved from Engineer in
charge before any formwork is taken up for concreting.
1.3 The contractor shall entirely be responsible for the adequacy and safety for false work not-
withstanding any approval or review by the Engineer of his drawing and design. Proprietary
system of formwork if used a detailed information shall be furnished to the Engineer for
approval.
2. QUALITY OF SHUTTERING :
The shuttering shall have smooth and even surface and its joints shall not permit leakage of
cement slurry.
2.1 Ply-board shuttering materials to be used shall be marine plywood well seasoned free from
projecting nails, splits or other defects that may mark on the surface of concrete. It shall not
be so dry as to absorb water from concrete, or so green or wet as to shrink after erection.
2.2 The timber shall be accurately spawned planed on the sides and the surface coming in contact
with concrete.
2.3 So far as practicable, clamps shall be used to hold the forms together. Where use of nails is
unavoidable minimum number of nails shall be used and these shall be left projecting so that
they can be easily with drawn. use of double headed nails shall be preferred.
3. TOLERANCE :-
3.1 The formwork shall be made so as to produce finished concrete true to shape, lines, levels
plumb and dimensions as shown on the drawings, subject to the following tolerance unless
otherwise specified in these documents or drawings or as directed by the Engineer :
a) Section dimension = 5 mm
b) Plumb = 1 in 1000 of height
c) Levels = 3 mm before any deflection takes place.
3.2 Tolerance given above are specified for local aberrations in the finished concrete surface and
should not be taken as tolerance for the entire structure taken as a whole or for the setting and
alignment of formwork which should be as accurate as possible to the entire satisfaction of
the Engineer, Errors if noticed in any lift/ tilt of the structure after stripping of forms, shall be
corrected in the subsequent work to bring back the surface of the structure to its true
alignment.
Rates for respective items shall include for the additional specification
1. The work of waterproofing described in the following items shall be carried out by The contractor
only through a renowned specialist waterproofing agency using cement waterproofing
compounds, as approved in writing by the Engineer-in-charge.
2. The Contractor shall give before execution, detailed specifications for each item of works of
waterproofing to be executed according to the specifications of the specialized agency, he
proposes to employ, for approval. The work shall not be started unless approval in writing is
given by the Engineer in charge to the said specification.
3. The Contractor shall give a guarantee bond on requisite stamp paper for a minimum period of 10
years for all the items of waterproofing done. During the guarantee period the Contractor shall
entirely be responsible to rectify any defect at his own cost to maintain the work in waterproof
condition. The waterproofing Contractor shall also have to make good all the surroundings
disturbed by him during the rectification work at his own cost. The form of written guarantee
shall be on a legal stamped agreement acceptable to the Government. The Guarantee shall be
given within one month from the date of completion of water proofing treatment but any delay in
furnishing the guarantee shall not relieve the contractor from implications of the clause.
4. 10% (Ten percent) of the cost of the waterproofing work executed shall be retained as "Retention
Money" for a period of 10 years covering the guarantee, and the same shall be released only after
satisfactory performance of the treatment during guarantee period of 10 years. This amount may
be converted into any approved interest bearing security (for 10 years after completion of defect
liability period), in the name of Executing Engineer, Public Works Tribal Division, Thane on
receipt of such written request from the contractor.
5. The waterproofing agency as approved by Engineer-in-charge shall provide and install at his own
cost the following for his own use and remove the same after completion of the work: I) Two
pumps electrical/ diesel operated for watering and curing of work at any level in the building.
Curing for all items shall be carried out for a minimum period of 14 days. Temporary Mild Steel
Water storage tanks. Temporary galvanized iron piping and fittings for water line. Flexible hose
lengths. Cement Godown, site office.
6. Injections .to reinforced cement concrete slab, wherever required, have to be undertaken by the
Contractor free of cost.
7. Before starting the waterproofing work, the surface receiving the treatment shall be cleaned
properly.
8. The item of waterproofing as given in the Schedule `B' applies for work in any position and on
any floors and at any heights. The lift of materials shall not form any criteria for extra payment.
To ensure the specified quality of work which shall also include necessary surveys, temporary
works etc., the contractor shall prepare a quality assurance plan and get the same approved from the
Engineer in charge within eight days from the date of work order. For this, contractor shall submit an
organization chart of his technical personnel to be deployed on the work along with their
qualification, job descriptions defining the functions of reporting, supervising inspecting and
approving. The contractor shall also submit a list of tools, equipment’s and the machinery and
instrumentation which he proposes to use for the construction and for testing in the field and/or in the
laboratory and monitoring. The contractor shall modify/supplement the organization chart and the list
of machinery, equipment etc. as per the direction of the Superintending Engineer and shall deploy the
personnel and equipment on the field as per the approved chart and list respectively. The contractor
shall submit written method statements detailing his exact proposals of execution of the work in
accordance with the specifications. He shall get these approved from the Engineer in charge. The
quality of the work shall be properly documented through certificates, records, check-lists and
logbooks of results etc. Such records shall be complied from the beginning of the work and be
continuously updated and supplemented and this shall be the responsibility of the contractor. The
forms should be got approved from the Executive Engineer-in-charge.
The contractor shall prepare detailed completion drawings after completion of the work. He
shall also prepare and submit a maintenance manual giving procedure for maintenance, with the
period of maintenance works including inspections, tools and equipment to be used, means of
accessibility for all parts of the structure. He shall also include in the manual, the specifications for
maintenance work that would be appropriate for his design and technique of construction. This
manual shall be submitted within the contract period.
I/We hereby declare that I/we have made myself / ourselves thoroughly conversant with the
local conditions regarding all materials and labour on which I/we have based my/our rates for this
tender. The specifications and lead of materials on this work have been carefully studied and
understood by me/us before submitting this tender. I/we undertake to use only the best materials
approved by the Executive Engineer, P.W (Tribal ) Division, Thane or his duly authorized
representative before starting the work and to abide by his decision.
I/We hereby undertake to pay the laborers engaged on the work as per minimum wages Act
1948 applicable to the Zone concerned.
Signature of Contractor
CONTRACT DRAWINGS :-
The Contract Drawings provided for tendering purpose with the tender documents
shall be used as a reference only. Contractor should visualize the nature and type of work
contemplated and to ensure that the rates and prices quoted by him in the bill of quantities
take due consideration of the complexities of work involved during actual execution /
construction as experienced contractors in the field.
The tendered rates / prices for the work shall be deemed to include the cost of
preparation, supply and delivery of all necessary drawings, prints, tracings and negatives
which the contractor is required to provide in accordance with the contract.
DOCUMENTATION :
If so ordered by the Engineer-in-charge, the contractor will prepare drawings of the
work as constructed and will supply original and three copies to the Engineer who will verify
and certify these drawings.
Final as constructed drawings shall then be prepared by the contractor and applied in
triplicate along with a micro-film of the same to Engineer for record and reference purpose at
the contractor’s cost.
- - - - - - - - - - - - N I L - - - - - - - - - - - -
Executive Engineer
225.00 8.13 Rupees eight and paise thirteen only One Square 1829.25
Metre
2 Excavation for roadway in earth, soil of all sorts, sand, gravel or soft
murum including dressing section to the required grade, camber and
side slopes and conveying the excavated materials with all lifts upto
a lead of 50 metre and spreading for embankment or stacking as
directed.
67.50 130.78 Rupees one hundred thirty and paise One Cubic 8827.65
seventy-eight only Metre
3 Conveying materials obtained from road cutting including all lifts,
laying in layers of 20 centimetre to 30 centimetre breaking clods,
dressing to the required lines, curves, grades and section, watering
and compacting to not less than 97% of standard proctor density for
a lead of 300 metre to 500 metre inclusive, from the site of excavation
to the site of deposition as directed.
33.75 431.91 Rupees four hundred thirty-one and paise One Cubic 14576.96
ninety-one only metre
47.15 227.49 Rupees two hundred twenty-seven and One Cubic 10726.15
paise forty-nine only Metre
5 Excavation for foundation in hard murum including removing
the excavated material upto distance of 50 metres beyond the
building area and stacking and spreading as directed,
dewatering, preparing the bed for the foundation and necessary
back filling, ramilimetering, watering including shoring and
strutting et- cetra complete. (Lift upto 1.50 m) By Manual Means
15.61 401.14 Rupees four hundred one and paise One Cubic 6261.80
fourteen only Metre
6 Providing dry trap rubble stone soling 15 centimetre to 20 centimetre
thick including hand packing and compacting etcetera complete as
directed. (including all leads and lifts)
57.89 1840.81 Rupees one thousand eight hundred forty One Cubic 106564.49
and paise eighty-one only Metre
21.16 6976.75 Rupees six thousand nine hundred One Cubic 147628.03
seventy-six and paise seventy-five only Metre
8.32 8374.18 Rupees eight thousand three hundred One Cubic 69673.18
seventy-four and paise eighteen only metre
10 Providing and laying Cast in situ/ Ready Mix cement concrete Mix
20 of trap/ granite/ quartzite/ gneiss metal for Reinforced Cement
Cocrete columns as per detailed designs and drawing or as directed
including steel centering, formwork, cover blocks, laying/ pumping,
compaction finishing the formed surfaces with cement mortar 1:3 of
sufficient minimum thickness to give a smooth and even surface or
roughening if special finish is to be provided and curing etcetera
complete. (Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic Controller
with Supervisory Control and data Aquisition enabled reversible
Drum Type mixer/ concrete Batch mix plant (Pan mixer) etcetera
complete. With fine aggregate (Crushed sand Vertical Shaft Impactor
Grade)
8.50 15714.40 Rupees fifteen thousand seven hundred One Cubic 133572.40
fourteen and paise forty only metre
23.64 14050.51 Rupees fourteen thousand fifty and paise One Cubic 332154.06
fifty-one only metre
12 Providing second class Burnt Brick masonry with conventional/
Indian Standard type bricks in cement mortar 1:6 in foundations and
plinth of inner walls/ in plinth external walls including bailing out
water manuall, striking joints on unexposed faces, raking out joints
on exposed faces and watering Including all lead and lifts etcetera
complete.
13.67 8928.88 Rupees eight thousand nine hundred One Cubic 122057.79
twenty-eight and paise eighty-eight only Metre
46.05 910.52 Rupees nine hundred ten and paise fifty- One Cubic 41929.45
two only Metre
14 Filling in plinth and floors with approved excavated material in
15centimeter to 20 centimeter layers including watering and
compacting etcetera complete.
28.13 1277.64 Rupees one thousand two hundred One Square 35940.01
seventy-seven and paise sixty-four only Metre
17 Providing and fixing M-40 grade precast concrete door frame of size
60 millimetre x 100 millimetre vibrated pull cast or similar type with
chamfer conforming to Indian Standard 6524-1983 having 6
millimetre diametres bars 3 Numbers and stirrups at the rate of 250
millimetre centre to centre and fixing in wall with 6 Numbers of hold
fast of 12 millimetre diametre bars 500 millimetre long including
cleaning the frame surface, necessary primer and oil painting of
appoved make and colour shade etcetera complete as directed
including all leads and lifts.
56.40 1171.53 Rupees one thousand one hundred One Running 66074.29
seventy-one and paise fifty-three only metre
0.85 15878.15 Rupees fifteen thousand eight hundred One Cubic 13496.43
seventy-eight and paise fifteen only Metre
19 Providing and laying Cast in situ/ Ready Mix cement concrete M-20
of trap/ granite/ quartzite/ gneiss metal for Reiforced Cement
Concrete slabs and landings as per detailed designs and drawings
including steel centering, formwork, cover blocks, laying/ pumping,
compaction finishing the formed surfaces with cement mortar 1:3 of
sufficient minimum thickness to give a smooth and even surface or
roughening if special finish is to be provided and curing etcetera
complete, (Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic Controller
with Supervisory Control and data Aquisition enabled reversible
Drum Type mixer/ concrete Batch mix plant (Pan mixer) etcetera
complete. With fine aggregate (Crushed sand Vertical Shaft Impactor
grade)
4.71 15878.15 Rupees fifteen thousand eight hundred One Cubic 74786.09
seventy-eight and paise fifteen only Metre
3.37 111926.56 Rupees one lakhs eleven thousand nine One Metric 377192.51
hundred twenty-six and paise fifty-six Tonne
only
21 Puf Roof Panel: Sandwich panel for roof 50 milimetre thick(puf) The
base material being Mangalore Tile shape profile Pre-painted
coating.External face brick Red.PCT 0.4 milimetre Cover Width of
the panel will be 990 milimetre. Crest height of 30 milimetre pitch of
198 milimetre.The length of panel as per site length requirement the
side lapping and over lapping joints of the self supporting panels
shall be vapour tight.The PUF panels external and internal sides
have guard film protection and confirmd Indian Standard-123436-
1988.The to sheet have profiled and bottom sheet have a micro rib
finishing thermal conductivity of 0.024 w/mk. Density shall be 40+/.
2 kilogram per metercube CFC/HCFC free Installation shall be
Using Hourse Power or equivalent Hex head self drilling Screws
with washer 12-14*100 milimeter size of required.Make:Therm:shield
include Ridge Tiles of Width 990 milimeter and end batterns
301.99 2335.38 Rupees two thousand three hundred One Square 705261.41
thirty-five and paise thirty-eight only Metre
16.80 4282.36 Rupees four thousand two hundred One Square 71943.65
eighty-two and paise thirty-six only Metre
23 Providing sand faced plaster externally in cement mortar using
approved screened sand, in all positions including base coat of 15
millimetre thick in cement mortar 1:4 using waterproofing
compound at 1 kilogram per cement bag curing the same for not less
than 2 days and keeping the surface of the base coat rough to receive
the sand faced treatment 6 to 8 millimetre thick in cement mortar 1:4
finishing the surface by taking out grains and curing for fourteen
days scaffolding etceteracomplete as directed. (including all leads
and lifts)
258.35 719.35 Rupees seven hundred nineteen and paise One Square 185844.07
thirty-five only Metre
24 Providing and laying full body vitrified matt fininsh tiles having size
590 milimeter to 605 milimeter x to 605 milimeter of 8 to 10
milimeter thickness and confirming Indian Standard 15622-2006
(Group Bla) of approved make, shade and pattern for flooring in
required position laid on a bed of 1:4 cement morar including neat
cement float, filling joints, curing and cleaning etcetera complete.
181.88 1768.52 Rupees one thousand seven hundred One Square 321658.42
sixty-eight and paise fifty-two only Metre
13.40 1851.66 Rupees one thousand eight hundred fifty- One Square 24812.24
one and paise sixty-six only Metre
26 Providing and laying ceramic tiles having size 30 centimeter. x 45
centimeter. confirming to corresponding Indian Standard for dado
and skirting in required position with readymade adhesive mortar of
approved quality on plaster of 1:2 cement mortar including joint
filling with white or colour cement slurry cleaning curing etcetra
complete.
28.89 1415.35 Rupees one thousand four hundred One Square 40889.46
fifteen and paise thirty-five only Metre
27 Providing internal cement plaster 12 milimetre thick in single coat in
cement mortar 1:5 without neeru finish to concrete or brick surfaces,
in all positions including scaffolding and curing etcetera complete.
512.91 305.26 Rupees three hundred five and paise One Square 156570.91
twenty-six only Metre
28 Providing and fixing Orissa type white glazed earthenware 575
milimeter water closet pan including S trap with earthenware foot
rests, cast iron soil and vent pipe upto outside face of the wall 1:2:4
brick bat lime concrete bedding without flushing tank and its
accessories et- cetra complete.
2.00 4403.69 Rupees four thousand four hundred three One Number 8807.38
and paise sixty-nine only
2.00 12741.03 Rupees twelve thousand seven hundred One Number 25482.06
forty-one and paise three only
2.00 7715.01 Rupees seven thousand seven hundred One Number 15430.02
fifteen and paise one only
31 Providing and fixing on walls/ ceiling/ floor 25 milimetre diametre
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/
Astral make with necessary fittings, remaking good the demolished
portion etcetera complete. Including removing existing pipe line if
necessary and conveying and stacking the same in Public Works
Department chowky or as directed etcetera complete.
50.00 390.15 Rupees three hundred ninety and paise One Running 19507.50
fifteen only Metre
20.00 452.79 Rupees four hundred fifty-two and paise One Running 9055.80
seventy-nine only Metre
33 Providing, laying and fixing Poly Vinyl Chloride pipe of 110
millimetre diameter of Finolex/ Supreme/ Jain/ Astral make for
soil/ vent pipes including fixing Galvanised Iron bracket of required
size to keep the pipe 40 to 65 millimetre away from face of walls and
fixing with U clamps nut bolt with fittings such as bends, tees,
reducers etcetera including necessary excavation, trench filling
etcetera complete as directed.
35.00 652.81 Rupees six hundred fifty-two and paise One Running 22848.35
eighty-one only Metre
34 Providing and constructing Brick Masonry Inspection Chamber 60
centimetre x 45 centimetre x 90 centimetre average depth including
1:4:8 cement concrete foundation 1:2:4 cement concrete channels half
round Glazed Stone Ware pipes, brick masonry, plastering from
inside and with frame fixed in cement concrete with Reinforced
Cement Concrete Cover etcetera complete as directed. (including all
leads and lifts)
4.00 10496.43 Rupees ten thousand four hundred ninety- One Number 41985.72
six and paise forty-three only
35 Providing soak pit of size 120 centimetre x 120 centimetre x 120
centimetre including excavating and filling with brick-bats.
15.00 1627.62 Rupees one thousand six hundred twenty- One Running 24414.30
seven and paise sixty-two only Metre
37 Providing and fixing High Density Polyethelyne container one piece
moulded water tank made out of low density polythyler and built
corrugation including of delivery up to destination hoisting and
fixing of accessories such as inlet, outlet overflow of all tanks
capacity above 1000 to 20,000 litres Including all lead and lifts
etcetera complete.
1500.00 12.09 Rupees twelve and paise nine only One Litre 18135.00
38 Providing and fixing 40 milimetre diametre Ball cock medium type
with Poly vinyl Chloride float including sockets and necessary
fittings and tested as per municipal requirements etcetera complete.
2.00 1329.79 Rupees one thousand three hundred One Number 2659.58
twenty-nine and paise seventy-nine only
30.00 300.03 Rupees three hundred and paise three only One Running 9000.90
Metre
42 Providing and laying in trenches 20 millimetre diametre Chlorinated
Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/ Astral make
for water supply including necessary excavation, fittings. Refilling
trenches etcetera complete as directed.
30.00 341.79 Rupees three hundred forty-one and paise One Running 10253.70
seventy-nine only Metre
43 Providing fine cement finish 1.5 millimetre thick over green plaster
surface including scaffolding curing etcetera complete.
24.42 79.75 Rupees seventy-nine and paise seventy- One Square 1947.50
five only Metre
22.50 5345.54 Rupees five thousand three hundred forty- One Square 120274.65
five and paise fifty-four only Metre
45 Providing and fixing in position powder coated aluminium louvered
windows/ ventilator of various sizes with powder coating as per
detailed drawing and specifications including aluminium frames 80
x 38 millimetre x 1.22 millimetre box type, 5 millimetre thick sheet
glass louvers, of approved quality etcetera complete.
3.24 3810.23 Rupees three thousand eight hundred ten One Square 12345.15
and paise twenty-three only Metre
24.66 1875.99 Rupees one thousand eight hundred One Square 46261.91
seventy-five and paise ninety-nine only Metre
7.56 1328.92 Rupees one thousand three hundred One Square 10046.64
twenty-eight and paise ninety-two only Metre
48 Providing and fixing 90 centimeter x 60 centimeter Marble plate
engraving 10 centimeter. height letter, figures including painting
the lefters or figures with approved colour and shade complete
1.00 8400.76 Rupees eight thousand four hundred and One Number 8400.76
paise seventy-six only
49 Providing and laying Polished Tandur Stone flooring 25 millimetre
to 30 millimetre thick required width in plain pattern for courtyard
on a bed of Cement Mortar 1:6 including cement float, filling joints
with neat cement slurry, curing, polishing and cleaning etcetera
complete.
10.70 1195.66 Rupees one thousand one hundred ninety- One Square 12793.56
five and paise sixty-six only Metre
14.90 818.24 Rupees eight hundred eighteen and paise One Square 12191.78
twenty-four only Metre
51 Providing and fixing frame with or without ventilator of size as
specified with Country non teak wood for doors and windows
including chamfering, rounding, rebating, iron holdfast of size
300milimeter x 40milimeter x 5milimeter with oil painting, etcetra
complete.
0.15 117716.09 Rupees one lakhs seventeen thousand One Cubic 17657.41
seven hundred sixteen and paise nine only metre
7.20 7196.25 Rupees seven thousand one hundred One Square 51813.00
ninety-six and paise twenty-five only Metre
53 Providing and fixing solid core flush door shutter in single leaf 32
millimetre thick decorative type of exterior grade as per detailed
drawings approved veneers 3 millimetre thick on both faces or as
directed, all necessary beads, mouldings and lipping, wrought iron
hold fasts, approved chromium plated fixtures and fastenings with
brass mortise lock, approved chromium plated handles on both sides
and finishing with french polish etcetera complete as directed.
532.01 98.91 Rupees ninety-eight and paise ninety-one One Square 52621.11
only Metre
55 Providing and applying two coats of exterior acraylic emulsion paint
confirming to corresponding Indian Standard of Asian/ Nerolac/
Berger/ Dulux/ Shalimar make and of approved colour to the
plastered surfaces including cleaning, preparing the plaster surface,
applying primer coat, scaffolding if necessary, and watering the
surface for two days etcetera complete as directed.
258.35 286.84 Rupees two hundred eighty-six and paise One Square 74105.11
eighty-four only Metre
56 Providing and applying washable oil-bound distemper of approved
colour and shade to old and new surfaces in two coats including
scaffolding, preparing the surfaces. (excluding the primer coat.)
Including all lead and lifts etcetera complete.
532.01 52.75 Rupees fifty-two and paise seventy-five One Square 28063.53
only Metre
4615182.60
SCHEDULE - 'B' [ Part (B) : Testing Charges & Royalty Charges ]
57) Royalty Charges :-
57.89 For Other Material 216.18 Rupees two hundred sixteen and paise Cubic Metre 12514.66
eighteen only
A Crush Metal
2.00 Specific Gravity, Water Absorption, Crushing Value, Impact Value 2730.00 Rupees two thousand seven hundred One Set of Test 5460.00
thirty and paise nil only
B Cement Concrete
8.00 Compressive Strength of Cube 725.00 Rupees seven hundred twenty-five and One Set of Test 5800.00
paise nil only
C Rubble
1.00 Crushing Value, Comp. Strength, Water Absorption, Specific Gravity 2120.00 Rupees two thousand one hundred One Set of Test 2120.00
twenty and paise nil only
D Cement
1.00 Standard Consistancy, Fineness. Specific Gravity, Setting Time, 3960.00 Rupees three thousand nine hundred One Set of Test 3960.00
Comp. Strength, Soundness sixty and paise nil only
E Steel
1.00 Tensile Strength, Percentage Elongation, Yeild Stress, Weight per 1275.00 Rupees one thousand two hundred One Set of Test 1275.00
Running Meter, Bend/Rebend Test, Proof Stress seventy-five and paise nil only
F Bricks
1.00 Water Absorption, Compressive Strength, Efflorescence 2175.00 Rupees two thousand one hundred One Set of Test 2175.00
seventy-five and paise nil only
J Vetrified Tiles
Say ₹ 46,66,099.00
67.50 130.78 Rupees one hundred thirty and paise One Cubic 8827.65
seventy-eight only Metre
3 Conveying materials obtained from road cutting including all lifts,
laying in layers of 20 centimetre to 30 centimetre breaking clods,
dressing to the required lines, curves, grades and section, watering
and compacting to not less than 97% of standard proctor density for
a lead of 300 metre to 500 metre inclusive, from the site of excavation
to the site of deposition as directed.
33.75 431.91 Rupees four hundred thirty-one and paise One Cubic 14576.96
ninety-one only metre
4 Excavation for foundation in earth, soil of all types, sand, gravel and
soft murum including removing the excavated material up to
required distance beyond the building area, stacking and spreading
as directed, dewatering if required, preparing the bed for the
foundation and necessary back filling, ramming, watering including
shoring and strutting etcetera complete as directed for all leads and
lifts.
47.15 227.49 Rupees two hundred twenty-seven and One Cubic 10726.15
paise forty-nine only Metre
15.61 401.14 Rupees four hundred one and paise One Cubic 6261.80
fourteen only Metre
6 Providing dry trap rubble stone soling 15 centimetre to 20 centimetre
thick including hand packing and compacting etcetera complete as
directed. (including all leads and lifts)
57.89 1840.81 Rupees one thousand eight hundred forty One Cubic 106564.49
and paise eighty-one only Metre
7 Providing and laying Cast in situ/ Ready Mix cement concrete M-10
of trap metal for foundation and bedding including bailing out water
if required, formwork, laying/ pumping, compacting, finishing
uneven and honey combed surface if required, curing etcetera
complete with fully automatic micro processor based Programmable
Logic Controller with Supervisory Control and Data AcquIndian
Standard Institutetion enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) with fine aggregate as finely
washed Natural Sand/ Vertical Shaft Impactor Grade Crushed sand
etcetera complete as directed. (including all leads and lifts)
21.16 6976.75 Rupees six thousand nine hundred One Cubic 147628.03
seventy-six and paise seventy-five only Metre
8.50 15714.40 Rupees fifteen thousand seven hundred One Cubic 133572.40
fourteen and paise forty only metre
11 Providing and laying Cast in situ/ Ready Mix cement concrete Mix
20 of trap/ granite/ quartzite/ gneiss metal for Reinforced Cement
Cocrete beams and lintels as per detailed designs and drawings or as
directed including steel centering, formwork, cover blocks, laying/
pumping, compactionand roughening the surface if special finish is
to be provided and curing etcetera complete. (Excluding
reinforcement and structural steel). with fully automatic micro
processor based Programmable logic Controller with Supervisory
Control and data Aquisition enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) etcetera complete. With fine
aggregate (Crushed sand Vertical Shaft Impactor Grade)
23.64 14050.51 Rupees fourteen thousand fifty and paise One Cubic 332154.06
fifty-one only metre
13.67 8928.88 Rupees eight thousand nine hundred One Cubic 122057.79
twenty-eight and paise eighty-eight only Metre
46.05 910.52 Rupees nine hundred ten and paise fifty- One Cubic 41929.45
two only Metre
14 Filling in plinth and floors with approved excavated material in
15centimeter to 20 centimeter layers including watering and
compacting etcetera complete.
23.33 131.88 Rupees one hundred thirty-one and paise One Cubic 3076.76
eighty-eight only Metre
15 Providing second class Burnt Brick masonry with conventional/
Indian Standard type bricks in cement mortar 1:6 in superstructure
including striking joints, raking out joints, watering and scaffolding
etcetera Complete
45.64 8785.41 Rupees eight thousand seven hundred One Cubic 400966.11
eighty-five and paise forty-one only Metre
28.13 1277.64 Rupees one thousand two hundred One Square 35940.01
seventy-seven and paise sixty-four only Metre
17 Providing and fixing M-40 grade precast concrete door frame of size
60 millimetre x 100 millimetre vibrated pull cast or similar type with
chamfer conforming to Indian Standard 6524-1983 having 6
millimetre diametres bars 3 Numbers and stirrups at the rate of 250
millimetre centre to centre and fixing in wall with 6 Numbers of hold
fast of 12 millimetre diametre bars 500 millimetre long including
cleaning the frame surface, necessary primer and oil painting of
appoved make and colour shade etcetera complete as directed
including all leads and lifts.
56.40 1171.53 Rupees one thousand one hundred One Running 66074.29
seventy-one and paise fifty-three only metre
18 Providing and laying Cast in situ/ Ready Mixcement concrete M-20
of trap/ granite/ quartzite/ gneiss metal for Reinforced Cement
Concrete chajja as per detailed design and drawings including steel
centering, formwork, cover blocks, laying/ pumping, compacting
and roughening the surface if special finish is to be provided and
curing complete. (Excluding reinforcement and structural steel). with
fully automatic micro processor based Programmable logic
Controller with Supervisory Control and data Aquisition enabled
reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer)
etcetera complete. With fine aggregate (Crushed sand Vertical Shaft
Impactor Grade)
19 Providing and laying Cast in situ/ Ready Mix cement concrete M-20
of trap/ granite/ quartzite/ gneiss metal for Reiforced Cement
Concrete slabs and landings as per detailed designs and drawings
including steel centering, formwork, cover blocks, laying/ pumping,
compaction finishing the formed surfaces with cement mortar 1:3 of
sufficient minimum thickness to give a smooth and even surface or
roughening if special finish is to be provided and curing etcetera
complete, (Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic Controller
with Supervisory Control and data Aquisition enabled reversible
Drum Type mixer/ concrete Batch mix plant (Pan mixer) etcetera
complete. With fine aggregate (Crushed sand Vertical Shaft Impactor
grade)
4.71 15878.15 Rupees fifteen thousand eight hundred One Cubic 74786.09
seventy-eight and paise fifteen only Metre
3.37 111926.56 Rupees one lakhs eleven thousand nine One Metric 377192.51
hundred twenty-six and paise fifty-six Tonne
only
301.99 2335.38 Rupees two thousand three hundred One Square 705261.41
thirty-five and paise thirty-eight only Metre
22 Providing sills of required material 20 milimetre to 25 milimetre
thick, on a bed of cement mortar 1:4 including cement float, filling
joints with neat cement slurry, curing, moulding edges, polishing,
cleaning complete.
b) Granite
16.80 4282.36 Rupees four thousand two hundred One Square 71943.65
eighty-two and paise thirty-six only Metre
258.35 719.35 Rupees seven hundred nineteen and paise One Square 185844.07
thirty-five only Metre
24 Providing and laying full body vitrified matt fininsh tiles having size
590 milimeter to 605 milimeter x to 605 milimeter of 8 to 10
milimeter thickness and confirming Indian Standard 15622-2006
(Group Bla) of approved make, shade and pattern for flooring in
required position laid on a bed of 1:4 cement morar including neat
cement float, filling joints, curing and cleaning etcetera complete.
181.88 1768.52 Rupees one thousand seven hundred One Square 321658.42
sixty-eight and paise fifty-two only Metre
25 Providing and laying full body vitrified matt finish tiles having size
590 milimeter to 605 milimeter x to 605 milimeter of 8 to 10
milimeter thickness and confirming Indian Standard 15622-2006
(Group Bla) of approved make, shade and pattern for dado and
skirting in required position fixed in 1:4 cement mortar including
neat cement float, filling joints, curing and cleaning etcetera
complete.
13.40 1851.66 Rupees one thousand eight hundred fifty- One Square 24812.24
one and paise sixty-six only Metre
28.89 1415.35 Rupees one thousand four hundred One Square 40889.46
fifteen and paise thirty-five only Metre
27 Providing internal cement plaster 12 milimetre thick in single coat in
cement mortar 1:5 without neeru finish to concrete or brick surfaces,
in all positions including scaffolding and curing etcetera complete.
512.91 305.26 Rupees three hundred five and paise One Square 156570.91
twenty-six only Metre
28 Providing and fixing Orissa type white glazed earthenware 575
milimeter water closet pan including S trap with earthenware foot
rests, cast iron soil and vent pipe upto outside face of the wall 1:2:4
brick bat lime concrete bedding without flushing tank and its
accessories et- cetra complete.
2.00 4403.69 Rupees four thousand four hundred three One Number 8807.38
and paise sixty-nine only
29 Providing and fixing European type Colour glazed earthenware
water closet pan with UPolyvinyl Chloride seat and lid with
chromium plated brass hinges and rubber buffers including
UPolyvinyl Chloride and vent pipe up to the outside face of wall 10
liter enameled low level flushing cistern with fittings pipe stop tap
brackets for fixing cistern 32 milimeter dia. UPolyvinyl Chloride
flush pipe with fittings and clamps,20 milimeter dia.UPolyvinyl
Chloride overflow pipe ,mosquito proof couplings Galvanized Iron
chain and pulley,with water Jet and fitting including cutting and
making good to the walls and floors testing etcetra complete.(
prior approval of sample and brand by Executive Engineer is
necessary before use)
2.00 7715.01 Rupees seven thousand seven hundred One Number 15430.02
fifteen and paise one only
31 Providing and fixing on walls/ ceiling/ floor 25 milimetre diametre
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/
Astral make with necessary fittings, remaking good the demolished
portion etcetera complete. Including removing existing pipe line if
necessary and conveying and stacking the same in Public Works
Department chowky or as directed etcetera complete.
50.00 390.15 Rupees three hundred ninety and paise One Running 19507.50
fifteen only Metre
32 Providing and fixing on walls/ ceiling/ floor 32 millimetre diametre
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/
Astral make for water supply including fixing Galvanised Iron
bracket of required size to keep the pipe 40 to 65 millimetre away
from face of walls and fixing with U clip nut bolt with necessary
fittings, remaking good the demolished portion etcetera complete as
directed.
20.00 452.79 Rupees four hundred fifty-two and paise One Running 9055.80
seventy-nine only Metre
35.00 652.81 Rupees six hundred fifty-two and paise One Running 22848.35
eighty-one only Metre
34 Providing and constructing Brick Masonry Inspection Chamber 60
centimetre x 45 centimetre x 90 centimetre average depth including
1:4:8 cement concrete foundation 1:2:4 cement concrete channels half
round Glazed Stone Ware pipes, brick masonry, plastering from
inside and with frame fixed in cement concrete with Reinforced
Cement Concrete Cover etcetera complete as directed. (including all
leads and lifts)
4.00 10496.43 Rupees ten thousand four hundred ninety- One Number 41985.72
six and paise forty-three only
35 Providing soak pit of size 120 centimetre x 120 centimetre x 120
centimetre including excavating and filling with brick-bats.
1.00 3244.25 Rupees three thousand two hundred forty- One Number 3244.25
four and paise twenty-five only
15.00 1627.62 Rupees one thousand six hundred twenty- One Running 24414.30
seven and paise sixty-two only Metre
1500.00 12.09 Rupees twelve and paise nine only One Litre 18135.00
38 Providing and fixing 40 milimetre diametre Ball cock medium type
with Poly vinyl Chloride float including sockets and necessary
fittings and tested as per municipal requirements etcetera complete.
2.00 1329.79 Rupees one thousand three hundred One Number 2659.58
twenty-nine and paise seventy-nine only
30.00 300.03 Rupees three hundred and paise three only One Running 9000.90
Metre
42 Providing and laying in trenches 20 millimetre diametre Chlorinated
Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/ Astral make
for water supply including necessary excavation, fittings. Refilling
trenches etcetera complete as directed.
30.00 341.79 Rupees three hundred forty-one and paise One Running 10253.70
seventy-nine only Metre
43 Providing fine cement finish 1.5 millimetre thick over green plaster
surface including scaffolding curing etcetera complete.
24.42 79.75 Rupees seventy-nine and paise seventy- One Square 1947.50
five only Metre
22.50 5345.54 Rupees five thousand three hundred forty- One Square 120274.65
five and paise fifty-four only Metre
45 Providing and fixing in position powder coated aluminium louvered
windows/ ventilator of various sizes with powder coating as per
detailed drawing and specifications including aluminium frames 80
x 38 millimetre x 1.22 millimetre box type, 5 millimetre thick sheet
glass louvers, of approved quality etcetera complete.
3.24 3810.23 Rupees three thousand eight hundred ten One Square 12345.15
and paise twenty-three only Metre
24.66 1875.99 Rupees one thousand eight hundred One Square 46261.91
seventy-five and paise ninety-nine only Metre
7.56 1328.92 Rupees one thousand three hundred One Square 10046.64
twenty-eight and paise ninety-two only Metre
1.00 8400.76 Rupees eight thousand four hundred and One Number 8400.76
paise seventy-six only
49 Providing and laying Polished Tandur Stone flooring 25 millimetre
to 30 millimetre thick required width in plain pattern for courtyard
on a bed of Cement Mortar 1:6 including cement float, filling joints
with neat cement slurry, curing, polishing and cleaning etcetera
complete.
10.70 1195.66 Rupees one thousand one hundred ninety- One Square 12793.56
five and paise sixty-six only Metre
14.90 818.24 Rupees eight hundred eighteen and paise One Square 12191.78
twenty-four only Metre
51 Providing and fixing frame with or without ventilator of size as
specified with Country non teak wood for doors and windows
including chamfering, rounding, rebating, iron holdfast of size
300milimeter x 40milimeter x 5milimeter with oil painting, etcetra
complete.
0.15 117716.09 Rupees one lakhs seventeen thousand One Cubic 17657.41
seven hundred sixteen and paise nine only metre
7.20 7196.25 Rupees seven thousand one hundred One Square 51813.00
ninety-six and paise twenty-five only Metre
21.60 3383.82 Rupees three thousand three hundred One Square 73090.51
eighty-three and paise eighty-two only Metre
532.01 98.91 Rupees ninety-eight and paise ninety-one One Square 52621.11
only Metre
55 Providing and applying two coats of exterior acraylic emulsion paint
confirming to corresponding Indian Standard of Asian/ Nerolac/
Berger/ Dulux/ Shalimar make and of approved colour to the
plastered surfaces including cleaning, preparing the plaster surface,
applying primer coat, scaffolding if necessary, and watering the
surface for two days etcetera complete as directed.
258.35 286.84 Rupees two hundred eighty-six and paise One Square 74105.11
eighty-four only Metre
56 Providing and applying washable oil-bound distemper of approved
colour and shade to old and new surfaces in two coats including
scaffolding, preparing the surfaces. (excluding the primer coat.)
Including all lead and lifts etcetera complete.
532.01 52.75 Rupees fifty-two and paise seventy-five One Square 28063.53
only Metre
4615182.60
57.89 For Other Material 216.18 Rupees two hundred sixteen and paise Cubic Metre 12514.66
eighteen only
58.08 For Sand 237.37 Rupees two hundred thirty-seven and Cubic Metre 13786.45
paise thirty-seven only
A Crush Metal
2.00 Specific Gravity, Water Absorption, Crushing Value, Impact Value 2730.00 Rupees two thousand seven hundred One Set of Test 5460.00
thirty and paise nil only
B Cement Concrete
8.00 Compressive Strength of Cube 725.00 Rupees seven hundred twenty-five and One Set of Test 5800.00
paise nil only
C Rubble
1.00 Crushing Value, Comp. Strength, Water Absorption, Specific Gravity 2120.00 Rupees two thousand one hundred One Set of Test 2120.00
twenty and paise nil only
D Cement
1.00 Standard Consistancy, Fineness. Specific Gravity, Setting Time, 3960.00 Rupees three thousand nine hundred One Set of Test 3960.00
Comp. Strength, Soundness sixty and paise nil only
E Steel
1.00 Tensile Strength, Percentage Elongation, Yeild Stress, Weight per 1275.00 Rupees one thousand two hundred One Set of Test 1275.00
Running Meter, Bend/Rebend Test, Proof Stress seventy-five and paise nil only
1.00 Water Absorption, Compressive Strength, Efflorescence 2175.00 Rupees two thousand one hundred One Set of Test 2175.00
seventy-five and paise nil only
J Vetrified Tiles
1.00 Water Absorption, Modulus of Rupture 1595.00 Rupees one thousand five hundred ninety- One Set of Test 1595.00
five and paise nil only
K Sand
1.00 Fineness Modulus 1380.00 Rupees one thousand three hundred One Set of Test 1380.00
eighty and paise nil only
1.00 Silt Factor 850.00 Rupees eight hundred fifty and paise nil One Set of Test 850.00
only
Total (Testing Charges) :- 24615.00
Say ₹ 46,66,099.00
67.50 130.78 Rupees one hundred thirty and paise One Cubic 8827.65
seventy-eight only Metre
3 Conveying materials obtained from road cutting including all lifts,
laying in layers of 20 centimetre to 30 centimetre breaking clods,
dressing to the required lines, curves, grades and section, watering
and compacting to not less than 97% of standard proctor density for
a lead of 300 metre to 500 metre inclusive, from the site of excavation
to the site of deposition as directed.
33.75 431.91 Rupees four hundred thirty-one and paise One Cubic 14576.96
ninety-one only metre
4 Excavation for foundation in earth, soil of all types, sand, gravel and
soft murum including removing the excavated material up to
required distance beyond the building area, stacking and spreading
as directed, dewatering if required, preparing the bed for the
foundation and necessary back filling, ramming, watering including
shoring and strutting etcetera complete as directed for all leads and
lifts.
47.15 227.49 Rupees two hundred twenty-seven and One Cubic 10726.15
paise forty-nine only Metre
15.61 401.14 Rupees four hundred one and paise One Cubic 6261.80
fourteen only Metre
6 Providing dry trap rubble stone soling 15 centimetre to 20 centimetre
thick including hand packing and compacting etcetera complete as
directed. (including all leads and lifts)
57.89 1840.81 Rupees one thousand eight hundred forty One Cubic 106564.49
and paise eighty-one only Metre
7 Providing and laying Cast in situ/ Ready Mix cement concrete M-10
of trap metal for foundation and bedding including bailing out water
if required, formwork, laying/ pumping, compacting, finishing
uneven and honey combed surface if required, curing etcetera
complete with fully automatic micro processor based Programmable
Logic Controller with Supervisory Control and Data AcquIndian
Standard Institutetion enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) with fine aggregate as finely
washed Natural Sand/ Vertical Shaft Impactor Grade Crushed sand
etcetera complete as directed. (including all leads and lifts)
21.16 6976.75 Rupees six thousand nine hundred One Cubic 147628.03
seventy-six and paise seventy-five only Metre
8.32 8374.18 Rupees eight thousand three hundred One Cubic 69673.18
seventy-four and paise eighteen only metre
8.50 15714.40 Rupees fifteen thousand seven hundred One Cubic 133572.40
fourteen and paise forty only metre
11 Providing and laying Cast in situ/ Ready Mix cement concrete Mix
20 of trap/ granite/ quartzite/ gneiss metal for Reinforced Cement
Cocrete beams and lintels as per detailed designs and drawings or as
directed including steel centering, formwork, cover blocks, laying/
pumping, compactionand roughening the surface if special finish is
to be provided and curing etcetera complete. (Excluding
reinforcement and structural steel). with fully automatic micro
processor based Programmable logic Controller with Supervisory
Control and data Aquisition enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) etcetera complete. With fine
aggregate (Crushed sand Vertical Shaft Impactor Grade)
23.64 14050.51 Rupees fourteen thousand fifty and paise One Cubic 332154.06
fifty-one only metre
13.67 8928.88 Rupees eight thousand nine hundred One Cubic 122057.79
twenty-eight and paise eighty-eight only Metre
46.05 910.52 Rupees nine hundred ten and paise fifty- One Cubic 41929.45
two only Metre
14 Filling in plinth and floors with approved excavated material in
15centimeter to 20 centimeter layers including watering and
compacting etcetera complete.
23.33 131.88 Rupees one hundred thirty-one and paise One Cubic 3076.76
eighty-eight only Metre
15 Providing second class Burnt Brick masonry with conventional/
Indian Standard type bricks in cement mortar 1:6 in superstructure
including striking joints, raking out joints, watering and scaffolding
etcetera Complete
45.64 8785.41 Rupees eight thousand seven hundred One Cubic 400966.11
eighty-five and paise forty-one only Metre
28.13 1277.64 Rupees one thousand two hundred One Square 35940.01
seventy-seven and paise sixty-four only Metre
17 Providing and fixing M-40 grade precast concrete door frame of size
60 millimetre x 100 millimetre vibrated pull cast or similar type with
chamfer conforming to Indian Standard 6524-1983 having 6
millimetre diametres bars 3 Numbers and stirrups at the rate of 250
millimetre centre to centre and fixing in wall with 6 Numbers of hold
fast of 12 millimetre diametre bars 500 millimetre long including
cleaning the frame surface, necessary primer and oil painting of
appoved make and colour shade etcetera complete as directed
including all leads and lifts.
56.40 1171.53 Rupees one thousand one hundred One Running 66074.29
seventy-one and paise fifty-three only metre
18 Providing and laying Cast in situ/ Ready Mixcement concrete M-20
of trap/ granite/ quartzite/ gneiss metal for Reinforced Cement
Concrete chajja as per detailed design and drawings including steel
centering, formwork, cover blocks, laying/ pumping, compacting
and roughening the surface if special finish is to be provided and
curing complete. (Excluding reinforcement and structural steel). with
fully automatic micro processor based Programmable logic
Controller with Supervisory Control and data Aquisition enabled
reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer)
etcetera complete. With fine aggregate (Crushed sand Vertical Shaft
Impactor Grade)
19 Providing and laying Cast in situ/ Ready Mix cement concrete M-20
of trap/ granite/ quartzite/ gneiss metal for Reiforced Cement
Concrete slabs and landings as per detailed designs and drawings
including steel centering, formwork, cover blocks, laying/ pumping,
compaction finishing the formed surfaces with cement mortar 1:3 of
sufficient minimum thickness to give a smooth and even surface or
roughening if special finish is to be provided and curing etcetera
complete, (Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic Controller
with Supervisory Control and data Aquisition enabled reversible
Drum Type mixer/ concrete Batch mix plant (Pan mixer) etcetera
complete. With fine aggregate (Crushed sand Vertical Shaft Impactor
grade)
4.71 15878.15 Rupees fifteen thousand eight hundred One Cubic 74786.09
seventy-eight and paise fifteen only Metre
3.37 111926.56 Rupees one lakhs eleven thousand nine One Metric 377192.51
hundred twenty-six and paise fifty-six Tonne
only
301.99 2335.38 Rupees two thousand three hundred One Square 705261.41
thirty-five and paise thirty-eight only Metre
22 Providing sills of required material 20 milimetre to 25 milimetre
thick, on a bed of cement mortar 1:4 including cement float, filling
joints with neat cement slurry, curing, moulding edges, polishing,
cleaning complete.
b) Granite
16.80 4282.36 Rupees four thousand two hundred One Square 71943.65
eighty-two and paise thirty-six only Metre
23 Providing sand faced plaster externally in cement mortar using
approved screened sand, in all positions including base coat of 15
millimetre thick in cement mortar 1:4 using waterproofing
compound at 1 kilogram per cement bag curing the same for not less
than 2 days and keeping the surface of the base coat rough to receive
the sand faced treatment 6 to 8 millimetre thick in cement mortar 1:4
finishing the surface by taking out grains and curing for fourteen
days scaffolding etceteracomplete as directed. (including all leads
and lifts)
181.88 1768.52 Rupees one thousand seven hundred One Square 321658.42
sixty-eight and paise fifty-two only Metre
25 Providing and laying full body vitrified matt finish tiles having size
590 milimeter to 605 milimeter x to 605 milimeter of 8 to 10
milimeter thickness and confirming Indian Standard 15622-2006
(Group Bla) of approved make, shade and pattern for dado and
skirting in required position fixed in 1:4 cement mortar including
neat cement float, filling joints, curing and cleaning etcetera
complete.
13.40 1851.66 Rupees one thousand eight hundred fifty- One Square 24812.24
one and paise sixty-six only Metre
26 Providing and laying ceramic tiles having size 30 centimeter. x 45
centimeter. confirming to corresponding Indian Standard for dado
and skirting in required position with readymade adhesive mortar of
approved quality on plaster of 1:2 cement mortar including joint
filling with white or colour cement slurry cleaning curing etcetra
complete.
28.89 1415.35 Rupees one thousand four hundred One Square 40889.46
fifteen and paise thirty-five only Metre
27 Providing internal cement plaster 12 milimetre thick in single coat in
cement mortar 1:5 without neeru finish to concrete or brick surfaces,
in all positions including scaffolding and curing etcetera complete.
2.00 4403.69 Rupees four thousand four hundred three One Number 8807.38
and paise sixty-nine only
29 Providing and fixing European type Colour glazed earthenware
water closet pan with UPolyvinyl Chloride seat and lid with
chromium plated brass hinges and rubber buffers including
UPolyvinyl Chloride and vent pipe up to the outside face of wall 10
liter enameled low level flushing cistern with fittings pipe stop tap
brackets for fixing cistern 32 milimeter dia. UPolyvinyl Chloride
flush pipe with fittings and clamps,20 milimeter dia.UPolyvinyl
Chloride overflow pipe ,mosquito proof couplings Galvanized Iron
chain and pulley,with water Jet and fitting including cutting and
making good to the walls and floors testing etcetra complete.(
prior approval of sample and brand by Executive Engineer is
necessary before use)
2.00 12741.03 Rupees twelve thousand seven hundred One Number 25482.06
forty-one and paise three only
2.00 7715.01 Rupees seven thousand seven hundred One Number 15430.02
fifteen and paise one only
50.00 390.15 Rupees three hundred ninety and paise One Running 19507.50
fifteen only Metre
32 Providing and fixing on walls/ ceiling/ floor 32 millimetre diametre
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/
Astral make for water supply including fixing Galvanised Iron
bracket of required size to keep the pipe 40 to 65 millimetre away
from face of walls and fixing with U clip nut bolt with necessary
fittings, remaking good the demolished portion etcetera complete as
directed.
20.00 452.79 Rupees four hundred fifty-two and paise One Running 9055.80
seventy-nine only Metre
33 Providing, laying and fixing Poly Vinyl Chloride pipe of 110
millimetre diameter of Finolex/ Supreme/ Jain/ Astral make for
soil/ vent pipes including fixing Galvanised Iron bracket of required
size to keep the pipe 40 to 65 millimetre away from face of walls and
fixing with U clamps nut bolt with fittings such as bends, tees,
reducers etcetera including necessary excavation, trench filling
etcetera complete as directed.
35.00 652.81 Rupees six hundred fifty-two and paise One Running 22848.35
eighty-one only Metre
4.00 10496.43 Rupees ten thousand four hundred ninety- One Number 41985.72
six and paise forty-three only
35 Providing soak pit of size 120 centimetre x 120 centimetre x 120
centimetre including excavating and filling with brick-bats.
1.00 3244.25 Rupees three thousand two hundred forty- One Number 3244.25
four and paise twenty-five only
36 Providing and fixing Poly Vinyl Chloride Rain water pipes of 160
millimetre outer diameter and having wall thickness of 2.2 to 2.7
millimetre of Finolex/ Supreme/ Jain/ Astral make confirming to
Indian Standard 13592-1992 including proper rainwater receiving
recess with Poly Vinyl Chloride plug, bend, necessary fittings, such
as, offsets, shoes, including fixing Galvanised Iron bracket of
required size to keep the pipe 40 to 65 millimetre away from face of
walls and fixing with U clamps nut bolt of approved quality and
number, filing the joint using rubber gasket with solvent cement and
properly resting the shoe of pipes on cement concrete or masonry
blocks including necessary scaffolding and maintenance for 3 years
for any leakages or dislocations of pipes. All the Poly Vinyl Chloride
fittings and additional 2 piece socket clips shall be got approved
from engineer in charge etcetera complete. (The contractor shall give
3 years guarantee bond for payment)
15.00 1627.62 Rupees one thousand six hundred twenty- One Running 24414.30
seven and paise sixty-two only Metre
1500.00 12.09 Rupees twelve and paise nine only One Litre 18135.00
38 Providing and fixing 40 milimetre diametre Ball cock medium type
with Poly vinyl Chloride float including sockets and necessary
fittings and tested as per municipal requirements etcetera complete.
2.00 1329.79 Rupees one thousand three hundred One Number 2659.58
twenty-nine and paise seventy-nine only
39 Providing and fixing Chromium Plated BIB cock with wall flange of
approved make including necessary sockets/ union nut etcetera
4.00 1217.69 Rupees one thousand two hundred One Number 4870.76
seventeen and paise sixty-nine only
40 Providing and fixing in position Unplasticized Poly Vinol Chloride
ultra violet stabilized 110 millimetre outer diameter cowl dome
confirming to Indian Standard-4985 including making joints with
solvent cement etcetera complete
1.00 185.73 Rupees one hundred eighty-five and paise One Number 185.73
seventy-three only
41 Providing and laying in trenches 15 millimetre diametre Chlorinated
Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/ Astral make
for water supply including necessary excavation, fittings. refilling
trenches etcetera complete as directed.
30.00 300.03 Rupees three hundred and paise three only One Running 9000.90
Metre
30.00 341.79 Rupees three hundred forty-one and paise One Running 10253.70
seventy-nine only Metre
43 Providing fine cement finish 1.5 millimetre thick over green plaster
surface including scaffolding curing etcetera complete.
24.42 79.75 Rupees seventy-nine and paise seventy- One Square 1947.50
five only Metre
44 Providing and fixing in position. (as per Indian Standard 1868/ 1982)
Aluminium sliding window of two tracks with rectangular pipe
having overall dimension 63.50 x 38.10 x 1.02 milimetre at weight
0.547 Kilogram/One Running Metre. and window frame bottom
track section 61.85 x 31.75 x 1.20 milimetre at weight 0.695
Kilogram/One Running Metre. Top and side track section 61.85 x
31.75 x 1.30 milimetre at weight 0.659 Kilogram/One Running
Metre. The shutter should be of bearing bottom 40 x 18 x 1.25
milimetre at weight 0.417 Kilogram/One Running Metre. Inter
locking section 40 x 18 x 1.10 milimetre at weight 0.469
Kilogram/One Running Metre. And handle section 40 x 18 x 1.25
milimetre at weight 0.417 Kilogram/One Running Metre. and top
section 40 x 18 x 1.25 milimetre at weight 0.417 Kilogram/Running
metre. As per detailed drawings and as directed by Engineer in
charge with all necessary Aluminium sections fixtures and
fastenings such as roller bearing in nylon casting and self locking
catch fitted in vertical section of shutter including 5 milimetre thick
plain glass with all required screws and nuts etcetera complete. With
powder coating without box
22.50 5345.54 Rupees five thousand three hundred forty- One Square 120274.65
five and paise fifty-four only Metre
3.24 3810.23 Rupees three thousand eight hundred ten One Square 12345.15
and paise twenty-three only Metre
46 Providing and fixing mild steel grill work for windows, ventilators,
etcetra 15 Kilogram per Square Metre as per drawing including
fixtures necessary welding and painting with one coat of
anticorrosive paint and two coats of oil painting complete.
24.66 1875.99 Rupees one thousand eight hundred One Square 46261.91
seventy-five and paise ninety-nine only Metre
7.56 1328.92 Rupees one thousand three hundred One Square 10046.64
twenty-eight and paise ninety-two only Metre
1.00 8400.76 Rupees eight thousand four hundred and One Number 8400.76
paise seventy-six only
10.70 1195.66 Rupees one thousand one hundred ninety- One Square 12793.56
five and paise sixty-six only Metre
50 Providing and laying chequered tiles of approved quality of size 30
centimetre x 30 centimetre confirming to corresponding Indian
Standard for flooring in required position laid on a bed of 1:4 cement
mortar including cement float, filling joint with cement slurry
cleaning curing etcetera complete.
14.90 818.24 Rupees eight hundred eighteen and paise One Square 12191.78
twenty-four only Metre
51 Providing and fixing frame with or without ventilator of size as
specified with Country non teak wood for doors and windows
including chamfering, rounding, rebating, iron holdfast of size
300milimeter x 40milimeter x 5milimeter with oil painting, etcetra
complete.
0.15 117716.09 Rupees one lakhs seventeen thousand One Cubic 17657.41
seven hundred sixteen and paise nine only metre
7.20 7196.25 Rupees seven thousand one hundred One Square 51813.00
ninety-six and paise twenty-five only Metre
53 Providing and fixing solid core flush door shutter in single leaf 32
millimetre thick decorative type of exterior grade as per detailed
drawings approved veneers 3 millimetre thick on both faces or as
directed, all necessary beads, mouldings and lipping, wrought iron
hold fasts, approved chromium plated fixtures and fastenings with
brass mortise lock, approved chromium plated handles on both sides
and finishing with french polish etcetera complete as directed.
532.01 98.91 Rupees ninety-eight and paise ninety-one One Square 52621.11
only Metre
55 Providing and applying two coats of exterior acraylic emulsion paint
confirming to corresponding Indian Standard of Asian/ Nerolac/
Berger/ Dulux/ Shalimar make and of approved colour to the
plastered surfaces including cleaning, preparing the plaster surface,
applying primer coat, scaffolding if necessary, and watering the
surface for two days etcetera complete as directed.
258.35 286.84 Rupees two hundred eighty-six and paise One Square 74105.11
eighty-four only Metre
56 Providing and applying washable oil-bound distemper of approved
colour and shade to old and new surfaces in two coats including
scaffolding, preparing the surfaces. (excluding the primer coat.)
Including all lead and lifts etcetera complete.
532.01 52.75 Rupees fifty-two and paise seventy-five One Square 28063.53
only Metre
4615182.60
SCHEDULE - 'B' [ Part (B) : Testing Charges & Royalty Charges ]
57) Royalty Charges :-
57.89 For Other Material 216.18 Rupees two hundred sixteen and paise Cubic Metre 12514.66
eighteen only
A Crush Metal
2.00 Specific Gravity, Water Absorption, Crushing Value, Impact Value 2730.00 Rupees two thousand seven hundred One Set of Test 5460.00
thirty and paise nil only
B Cement Concrete
8.00 Compressive Strength of Cube 725.00 Rupees seven hundred twenty-five and One Set of Test 5800.00
paise nil only
C Rubble
1.00 Crushing Value, Comp. Strength, Water Absorption, Specific Gravity 2120.00 Rupees two thousand one hundred One Set of Test 2120.00
twenty and paise nil only
D Cement
1.00 Standard Consistancy, Fineness. Specific Gravity, Setting Time, 3960.00 Rupees three thousand nine hundred One Set of Test 3960.00
Comp. Strength, Soundness sixty and paise nil only
E Steel
1.00 Tensile Strength, Percentage Elongation, Yeild Stress, Weight per 1275.00 Rupees one thousand two hundred One Set of Test 1275.00
Running Meter, Bend/Rebend Test, Proof Stress seventy-five and paise nil only
F Bricks
1.00 Water Absorption, Compressive Strength, Efflorescence 2175.00 Rupees two thousand one hundred One Set of Test 2175.00
seventy-five and paise nil only
J Vetrified Tiles
Say ₹ 46,66,099.00
67.50 130.78 Rupees one hundred thirty and paise One Cubic 8827.65
seventy-eight only Metre
3 Conveying materials obtained from road cutting including all lifts,
laying in layers of 20 centimetre to 30 centimetre breaking clods,
dressing to the required lines, curves, grades and section, watering
and compacting to not less than 97% of standard proctor density for
a lead of 300 metre to 500 metre inclusive, from the site of excavation
to the site of deposition as directed.
33.75 431.91 Rupees four hundred thirty-one and paise One Cubic 14576.96
ninety-one only metre
4 Excavation for foundation in earth, soil of all types, sand, gravel and
soft murum including removing the excavated material up to
required distance beyond the building area, stacking and spreading
as directed, dewatering if required, preparing the bed for the
foundation and necessary back filling, ramming, watering including
shoring and strutting etcetera complete as directed for all leads and
lifts.
47.15 227.49 Rupees two hundred twenty-seven and One Cubic 10726.15
paise forty-nine only Metre
15.61 401.14 Rupees four hundred one and paise One Cubic 6261.80
fourteen only Metre
6 Providing dry trap rubble stone soling 15 centimetre to 20 centimetre
thick including hand packing and compacting etcetera complete as
directed. (including all leads and lifts)
57.89 1840.81 Rupees one thousand eight hundred forty One Cubic 106564.49
and paise eighty-one only Metre
7 Providing and laying Cast in situ/ Ready Mix cement concrete M-10
of trap metal for foundation and bedding including bailing out water
if required, formwork, laying/ pumping, compacting, finishing
uneven and honey combed surface if required, curing etcetera
complete with fully automatic micro processor based Programmable
Logic Controller with Supervisory Control and Data AcquIndian
Standard Institutetion enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) with fine aggregate as finely
washed Natural Sand/ Vertical Shaft Impactor Grade Crushed sand
etcetera complete as directed. (including all leads and lifts)
21.16 6976.75 Rupees six thousand nine hundred One Cubic 147628.03
seventy-six and paise seventy-five only Metre
8.50 15714.40 Rupees fifteen thousand seven hundred One Cubic 133572.40
fourteen and paise forty only metre
11 Providing and laying Cast in situ/ Ready Mix cement concrete Mix
20 of trap/ granite/ quartzite/ gneiss metal for Reinforced Cement
Cocrete beams and lintels as per detailed designs and drawings or as
directed including steel centering, formwork, cover blocks, laying/
pumping, compactionand roughening the surface if special finish is
to be provided and curing etcetera complete. (Excluding
reinforcement and structural steel). with fully automatic micro
processor based Programmable logic Controller with Supervisory
Control and data Aquisition enabled reversible Drum Type mixer/
concrete Batch mix plant (Pan mixer) etcetera complete. With fine
aggregate (Crushed sand Vertical Shaft Impactor Grade)
23.64 14050.51 Rupees fourteen thousand fifty and paise One Cubic 332154.06
fifty-one only metre
13.67 8928.88 Rupees eight thousand nine hundred One Cubic 122057.79
twenty-eight and paise eighty-eight only Metre
46.05 910.52 Rupees nine hundred ten and paise fifty- One Cubic 41929.45
two only Metre
14 Filling in plinth and floors with approved excavated material in
15centimeter to 20 centimeter layers including watering and
compacting etcetera complete.
23.33 131.88 Rupees one hundred thirty-one and paise One Cubic 3076.76
eighty-eight only Metre
15 Providing second class Burnt Brick masonry with conventional/
Indian Standard type bricks in cement mortar 1:6 in superstructure
including striking joints, raking out joints, watering and scaffolding
etcetera Complete
45.64 8785.41 Rupees eight thousand seven hundred One Cubic 400966.11
eighty-five and paise forty-one only Metre
28.13 1277.64 Rupees one thousand two hundred One Square 35940.01
seventy-seven and paise sixty-four only Metre
17 Providing and fixing M-40 grade precast concrete door frame of size
60 millimetre x 100 millimetre vibrated pull cast or similar type with
chamfer conforming to Indian Standard 6524-1983 having 6
millimetre diametres bars 3 Numbers and stirrups at the rate of 250
millimetre centre to centre and fixing in wall with 6 Numbers of hold
fast of 12 millimetre diametre bars 500 millimetre long including
cleaning the frame surface, necessary primer and oil painting of
appoved make and colour shade etcetera complete as directed
including all leads and lifts.
56.40 1171.53 Rupees one thousand one hundred One Running 66074.29
seventy-one and paise fifty-three only metre
18 Providing and laying Cast in situ/ Ready Mixcement concrete M-20
of trap/ granite/ quartzite/ gneiss metal for Reinforced Cement
Concrete chajja as per detailed design and drawings including steel
centering, formwork, cover blocks, laying/ pumping, compacting
and roughening the surface if special finish is to be provided and
curing complete. (Excluding reinforcement and structural steel). with
fully automatic micro processor based Programmable logic
Controller with Supervisory Control and data Aquisition enabled
reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer)
etcetera complete. With fine aggregate (Crushed sand Vertical Shaft
Impactor Grade)
19 Providing and laying Cast in situ/ Ready Mix cement concrete M-20
of trap/ granite/ quartzite/ gneiss metal for Reiforced Cement
Concrete slabs and landings as per detailed designs and drawings
including steel centering, formwork, cover blocks, laying/ pumping,
compaction finishing the formed surfaces with cement mortar 1:3 of
sufficient minimum thickness to give a smooth and even surface or
roughening if special finish is to be provided and curing etcetera
complete, (Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic Controller
with Supervisory Control and data Aquisition enabled reversible
Drum Type mixer/ concrete Batch mix plant (Pan mixer) etcetera
complete. With fine aggregate (Crushed sand Vertical Shaft Impactor
grade)
4.71 15878.15 Rupees fifteen thousand eight hundred One Cubic 74786.09
seventy-eight and paise fifteen only Metre
3.37 111926.56 Rupees one lakhs eleven thousand nine One Metric 377192.51
hundred twenty-six and paise fifty-six Tonne
only
301.99 2335.38 Rupees two thousand three hundred One Square 705261.41
thirty-five and paise thirty-eight only Metre
22 Providing sills of required material 20 milimetre to 25 milimetre
thick, on a bed of cement mortar 1:4 including cement float, filling
joints with neat cement slurry, curing, moulding edges, polishing,
cleaning complete.
b) Granite
16.80 4282.36 Rupees four thousand two hundred One Square 71943.65
eighty-two and paise thirty-six only Metre
23 Providing sand faced plaster externally in cement mortar using
approved screened sand, in all positions including base coat of 15
millimetre thick in cement mortar 1:4 using waterproofing
compound at 1 kilogram per cement bag curing the same for not less
than 2 days and keeping the surface of the base coat rough to receive
the sand faced treatment 6 to 8 millimetre thick in cement mortar 1:4
finishing the surface by taking out grains and curing for fourteen
days scaffolding etceteracomplete as directed. (including all leads
and lifts)
181.88 1768.52 Rupees one thousand seven hundred One Square 321658.42
sixty-eight and paise fifty-two only Metre
25 Providing and laying full body vitrified matt finish tiles having size
590 milimeter to 605 milimeter x to 605 milimeter of 8 to 10
milimeter thickness and confirming Indian Standard 15622-2006
(Group Bla) of approved make, shade and pattern for dado and
skirting in required position fixed in 1:4 cement mortar including
neat cement float, filling joints, curing and cleaning etcetera
complete.
13.40 1851.66 Rupees one thousand eight hundred fifty- One Square 24812.24
one and paise sixty-six only Metre
26 Providing and laying ceramic tiles having size 30 centimeter. x 45
centimeter. confirming to corresponding Indian Standard for dado
and skirting in required position with readymade adhesive mortar of
approved quality on plaster of 1:2 cement mortar including joint
filling with white or colour cement slurry cleaning curing etcetra
complete.
28.89 1415.35 Rupees one thousand four hundred One Square 40889.46
fifteen and paise thirty-five only Metre
27 Providing internal cement plaster 12 milimetre thick in single coat in
cement mortar 1:5 without neeru finish to concrete or brick surfaces,
in all positions including scaffolding and curing etcetera complete.
2.00 4403.69 Rupees four thousand four hundred three One Number 8807.38
and paise sixty-nine only
29 Providing and fixing European type Colour glazed earthenware
water closet pan with UPolyvinyl Chloride seat and lid with
chromium plated brass hinges and rubber buffers including
UPolyvinyl Chloride and vent pipe up to the outside face of wall 10
liter enameled low level flushing cistern with fittings pipe stop tap
brackets for fixing cistern 32 milimeter dia. UPolyvinyl Chloride
flush pipe with fittings and clamps,20 milimeter dia.UPolyvinyl
Chloride overflow pipe ,mosquito proof couplings Galvanized Iron
chain and pulley,with water Jet and fitting including cutting and
making good to the walls and floors testing etcetra complete.(
prior approval of sample and brand by Executive Engineer is
necessary before use)
2.00 12741.03 Rupees twelve thousand seven hundred One Number 25482.06
forty-one and paise three only
2.00 7715.01 Rupees seven thousand seven hundred One Number 15430.02
fifteen and paise one only
50.00 390.15 Rupees three hundred ninety and paise One Running 19507.50
fifteen only Metre
32 Providing and fixing on walls/ ceiling/ floor 32 millimetre diametre
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/
Astral make for water supply including fixing Galvanised Iron
bracket of required size to keep the pipe 40 to 65 millimetre away
from face of walls and fixing with U clip nut bolt with necessary
fittings, remaking good the demolished portion etcetera complete as
directed.
20.00 452.79 Rupees four hundred fifty-two and paise One Running 9055.80
seventy-nine only Metre
33 Providing, laying and fixing Poly Vinyl Chloride pipe of 110
millimetre diameter of Finolex/ Supreme/ Jain/ Astral make for
soil/ vent pipes including fixing Galvanised Iron bracket of required
size to keep the pipe 40 to 65 millimetre away from face of walls and
fixing with U clamps nut bolt with fittings such as bends, tees,
reducers etcetera including necessary excavation, trench filling
etcetera complete as directed.
35.00 652.81 Rupees six hundred fifty-two and paise One Running 22848.35
eighty-one only Metre
4.00 10496.43 Rupees ten thousand four hundred ninety- One Number 41985.72
six and paise forty-three only
35 Providing soak pit of size 120 centimetre x 120 centimetre x 120
centimetre including excavating and filling with brick-bats.
1.00 3244.25 Rupees three thousand two hundred forty- One Number 3244.25
four and paise twenty-five only
36 Providing and fixing Poly Vinyl Chloride Rain water pipes of 160
millimetre outer diameter and having wall thickness of 2.2 to 2.7
millimetre of Finolex/ Supreme/ Jain/ Astral make confirming to
Indian Standard 13592-1992 including proper rainwater receiving
recess with Poly Vinyl Chloride plug, bend, necessary fittings, such
as, offsets, shoes, including fixing Galvanised Iron bracket of
required size to keep the pipe 40 to 65 millimetre away from face of
walls and fixing with U clamps nut bolt of approved quality and
number, filing the joint using rubber gasket with solvent cement and
properly resting the shoe of pipes on cement concrete or masonry
blocks including necessary scaffolding and maintenance for 3 years
for any leakages or dislocations of pipes. All the Poly Vinyl Chloride
fittings and additional 2 piece socket clips shall be got approved
from engineer in charge etcetera complete. (The contractor shall give
3 years guarantee bond for payment)
15.00 1627.62 Rupees one thousand six hundred twenty- One Running 24414.30
seven and paise sixty-two only Metre
1500.00 12.09 Rupees twelve and paise nine only One Litre 18135.00
38 Providing and fixing 40 milimetre diametre Ball cock medium type
with Poly vinyl Chloride float including sockets and necessary
fittings and tested as per municipal requirements etcetera complete.
2.00 1329.79 Rupees one thousand three hundred One Number 2659.58
twenty-nine and paise seventy-nine only
39 Providing and fixing Chromium Plated BIB cock with wall flange of
approved make including necessary sockets/ union nut etcetera
4.00 complete. 1217.69 Rupees one thousand two hundred One Number 4870.76
seventeen and paise sixty-nine only
40 Providing and fixing in position Unplasticized Poly Vinol Chloride
ultra violet stabilized 110 millimetre outer diameter cowl dome
confirming to Indian Standard-4985 including making joints with
solvent cement etcetera complete
1.00 185.73 Rupees one hundred eighty-five and paise One Number 185.73
seventy-three only
41 Providing and laying in trenches 15 millimetre diametre Chlorinated
Poly Venyl Chloride pipe of Finolex/ Supreme/ Jain/ Astral make
for water supply including necessary excavation, fittings. refilling
trenches etcetera complete as directed.
30.00 300.03 Rupees three hundred and paise three only One Running 9000.90
Metre
30.00 341.79 Rupees three hundred forty-one and paise One Running 10253.70
seventy-nine only Metre
43 Providing fine cement finish 1.5 millimetre thick over green plaster
surface including scaffolding curing etcetera complete.
24.42 79.75 Rupees seventy-nine and paise seventy- One Square 1947.50
five only Metre
44 Providing and fixing in position. (as per Indian Standard 1868/ 1982)
Aluminium sliding window of two tracks with rectangular pipe
having overall dimension 63.50 x 38.10 x 1.02 milimetre at weight
0.547 Kilogram/One Running Metre. and window frame bottom
track section 61.85 x 31.75 x 1.20 milimetre at weight 0.695
Kilogram/One Running Metre. Top and side track section 61.85 x
31.75 x 1.30 milimetre at weight 0.659 Kilogram/One Running
Metre. The shutter should be of bearing bottom 40 x 18 x 1.25
milimetre at weight 0.417 Kilogram/One Running Metre. Inter
locking section 40 x 18 x 1.10 milimetre at weight 0.469
Kilogram/One Running Metre. And handle section 40 x 18 x 1.25
milimetre at weight 0.417 Kilogram/One Running Metre. and top
section 40 x 18 x 1.25 milimetre at weight 0.417 Kilogram/Running
metre. As per detailed drawings and as directed by Engineer in
charge with all necessary Aluminium sections fixtures and
fastenings such as roller bearing in nylon casting and self locking
catch fitted in vertical section of shutter including 5 milimetre thick
plain glass with all required screws and nuts etcetera complete. With
powder coating without box
22.50 5345.54 Rupees five thousand three hundred forty- One Square 120274.65
five and paise fifty-four only Metre
3.24 3810.23 Rupees three thousand eight hundred ten One Square 12345.15
and paise twenty-three only Metre
46 Providing and fixing mild steel grill work for windows, ventilators,
etcetra 15 Kilogram per Square Metre as per drawing including
fixtures necessary welding and painting with one coat of
anticorrosive paint and two coats of oil painting complete.
24.66 1875.99 Rupees one thousand eight hundred One Square 46261.91
seventy-five and paise ninety-nine only Metre
7.56 1328.92 Rupees one thousand three hundred One Square 10046.64
twenty-eight and paise ninety-two only Metre
1.00 8400.76 Rupees eight thousand four hundred and One Number 8400.76
paise seventy-six only
10.70 1195.66 Rupees one thousand one hundred ninety- One Square 12793.56
five and paise sixty-six only Metre
50 Providing and laying chequered tiles of approved quality of size 30
centimetre x 30 centimetre confirming to corresponding Indian
Standard for flooring in required position laid on a bed of 1:4 cement
mortar including cement float, filling joint with cement slurry
cleaning curing etcetera complete.
14.90 818.24 Rupees eight hundred eighteen and paise One Square 12191.78
twenty-four only Metre
51 Providing and fixing frame with or without ventilator of size as
specified with Country non teak wood for doors and windows
including chamfering, rounding, rebating, iron holdfast of size
300milimeter x 40milimeter x 5milimeter with oil painting, etcetra
complete.
0.15 117716.09 Rupees one lakhs seventeen thousand One Cubic 17657.41
seven hundred sixteen and paise nine only metre
7.20 7196.25 Rupees seven thousand one hundred One Square 51813.00
ninety-six and paise twenty-five only Metre
53 Providing and fixing solid core flush door shutter in single leaf 32
millimetre thick decorative type of exterior grade as per detailed
drawings approved veneers 3 millimetre thick on both faces or as
directed, all necessary beads, mouldings and lipping, wrought iron
hold fasts, approved chromium plated fixtures and fastenings with
brass mortise lock, approved chromium plated handles on both sides
and finishing with french polish etcetera complete as directed.
532.01 98.91 Rupees ninety-eight and paise ninety-one One Square 52621.11
only Metre
55 Providing and applying two coats of exterior acraylic emulsion paint
confirming to corresponding Indian Standard of Asian/ Nerolac/
Berger/ Dulux/ Shalimar make and of approved colour to the
plastered surfaces including cleaning, preparing the plaster surface,
applying primer coat, scaffolding if necessary, and watering the
surface for two days etcetera complete as directed.
258.35 286.84 Rupees two hundred eighty-six and paise One Square 74105.11
eighty-four only Metre
56 Providing and applying washable oil-bound distemper of approved
colour and shade to old and new surfaces in two coats including
scaffolding, preparing the surfaces. (excluding the primer coat.)
Including all lead and lifts etcetera complete.
532.01 52.75 Rupees fifty-two and paise seventy-five One Square 28063.53
only Metre
4615182.60
SCHEDULE - 'B' [ Part (B) : Testing Charges & Royalty Charges ]
57) Royalty Charges :-
57.89 For Other Material 216.18 Rupees two hundred sixteen and paise Cubic Metre 12514.66
eighteen only
A Crush Metal
2.00 Specific Gravity, Water Absorption, Crushing Value, Impact Value 2730.00 Rupees two thousand seven hundred One Set of Test 5460.00
thirty and paise nil only
B Cement Concrete
8.00 Compressive Strength of Cube 725.00 Rupees seven hundred twenty-five and One Set of Test 5800.00
paise nil only
C Rubble
1.00 Crushing Value, Comp. Strength, Water Absorption, Specific Gravity 2120.00 Rupees two thousand one hundred One Set of Test 2120.00
twenty and paise nil only
D Cement
1.00 Standard Consistancy, Fineness. Specific Gravity, Setting Time, 3960.00 Rupees three thousand nine hundred One Set of Test 3960.00
Comp. Strength, Soundness sixty and paise nil only
E Steel
1.00 Tensile Strength, Percentage Elongation, Yeild Stress, Weight per 1275.00 Rupees one thousand two hundred One Set of Test 1275.00
Running Meter, Bend/Rebend Test, Proof Stress seventy-five and paise nil only
F Bricks
1.00 Water Absorption, Compressive Strength, Efflorescence 2175.00 Rupees two thousand one hundred One Set of Test 2175.00
seventy-five and paise nil only
J Vetrified Tiles
Say ₹ 46,66,099.00
SUMMARY OF SCHEDULE-B
2 Excavation for roadway in earth, soil of all sorts, sand, gravel or MORTH 301 The work shall be carried out as directed by Engineer in Charge
soft murum including dressing section to the required grade,
camber and side slopes and conveying the excavated materials
with all lifts upto a lead of 50 metre and spreading for
embankment or stacking as directed.
3 Conveying materials obtained from road cutting including all MORTH 305 The work shall be carried out as per the directions of Engineer-
lifts, laying in layers of 20 centimetre to 30 centimetre breaking in-charge
clods, dressing to the required lines, curves, grades and section,
watering and compacting to not less than 97% of standard
proctor density for a lead of 300 metre to 500 metre inclusive,
from the site of excavation to the site of deposition as directed.
Executive Engineer
Executive Engineer
6 Providing dry trap rubble stone soling 15 centimetre to 20 Bd.A.10 Page a) Only approved excavated material shall be used for filling.
centimetre thick including hand packing and compacting Number 262 b) The work shall be executed as per directions of the Engineer
etcetera complete as directed. (including all leads and lifts) in charge.
C) Work To be exicuted with vibroplate.
Executive Engineer
8 Providing and fixing in position Thermo Mechanically Treated - Bd.F.17, Page a) The work shall be carried out as per the directions of Engineer-
Ferrous - 500 bar reinforcement of various diameters of Number 306 in-charge.
TISCON, SAIL, TATA Steel, RINL (Rashtriya Ispat Nigam b) The payment shall be made as per Metric Tonne instead of
Limited - Vizag), JSW or with embossing of Indian Standard per Quintal as specified in the standard specification book.
Institute Trade Mark and Thermo Mechanically Treated T c) Re-rolled Steel shall not be used.
Brand at every 1.00 meter interval on every bar confirming to d) Thermo Mechanically Treated (T.M.T. Steel) bar
Indian Standard 1786 for Reinforced Cement Concrete footings, reinforcement of TISCON (TATA Iron and Steel company ),
columns, beams, lintels, chajjas, canopies, slabs, staircase, waist SAIL (Steel Authority of India Limited),TATA Steel, RINL
slas, pardis, copings, fins, arches etcetera as per detailed (Rashtriya Ispat Nigam Limited - Vizag) with embossing of
designs, drawings and schedules including cutting, bending, Indian Standard Institute Trade Mark and T.M.T. Brand at every
hooking the bars, binding with Galvanised Iron binding wires 1.00 meter interval on every bar confirming to Indian Standard
of appropriate gauge and supporting etcetera complete as 1786 shall only be approved by the Engineer-in-charge and the
required. (including all leads and lifts) same shall be brought by the contractor.
e) The charges of Reinforced Cement Conceret Design shall be
borne by Contractor and duly get approved from Engineer in
Charge.
Executive Engineer
Executive Engineer
Executive Engineer
Executive Engineer
13 Filling in plinth and floors with contractors material brought Bd.A.11 Page a) Only approved excavated material shall be used for filling
from outside and approved by Engineer in charge including Number 263 b) The work shall be executed as per directions of the Engineer
watering and compacting in layers of 15 centimetre to 20 in charge. C) Work To be exicuted with vibroplate.
centimetre etcetera complete as directed. (including all leads
and lifts)
14 Filling in plinth and floors with approved excavated material in Bd.A.10 Page a) Only approved excavated material shall be used for filling
15centimeter to 20 centimeter layers including watering and Number 262 b) The work shall be executed as per directions of the Engineer
compacting etcetera complete. in charge. C) Work To be exicuted with vibroplate.
15 Providing second class Burnt Brick masonry with Bd.G.5 Page Number a) The testing of bricks shall be done at prescribed frequency in
conventional/ Indian Standard type bricks in cement mortar 1:6 315 Government/ Government approved laboratory only.
in superstructure including striking joints, raking out joints, b) Testing charges shall be paid by the contractor.
watering and scaffolding etcetera Complete c) One set of 15 bricks to be tested for each consignment of
50,000 number for (I) water absorption and (ii) crushing strength
in dry and wet conditions.
d) The work shall be carried out as per the direction of Engineer-
in-charge.
Executive Engineer
17 Providing and fixing M-40 grade precast concrete door frame of As directed by The work shall be carried out as directed by Engineer in Charge
size 60 millimetre x 100 millimetre vibrated pull cast or similar Engineer in
type with chamfer conforming to Indian Standard 6524-1983 charge.
having 6 millimetre diametres bars 3 Numbers and stirrups at
the rate of 250 millimetre centre to centre and fixing in wall
with 6 Numbers of hold fast of 12 millimetre diametre bars 500
millimetre long including cleaning the frame surface, necessary
primer and oil painting of appoved make and colour shade
etcetera complete as directed including all leads and lifts.
Executive Engineer
19 Providing and laying Cast in situ/ Ready Mix cement concrete Bd.F.8 Page Number The work shall be carried out as directed by Engineer in Charge
M-20 of trap/ granite/ quartzite/ gneiss metal for Reiforced 302 and B.7, Page
Cement Concrete slabs and landings as per detailed designs Number38
and drawings including steel centering, formwork, cover
blocks, laying/ pumping, compaction finishing the formed
surfaces with cement mortar 1:3 of sufficient minimum
thickness to give a smooth and even surface or roughening if
special finish is to be provided and curing etcetera complete,
(Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic
Controller with Supervisory Control and data Aquisition
enabled reversible Drum Type mixer/ concrete Batch mix plant
(Pan mixer) etcetera complete. With fine aggregate (Crushed
sand Vertical Shaft Impactor grade)
Executive Engineer
21 Puf Roof Panel: Sandwich panel for roof 50 milimetre thick(puf) As directed by 1. The work shall be carried out as per the directions of Engineer-
The base material being Mangalore Tile shape profile Pre- Engineer in charge. in-charge
painted coating.External face brick Red.PCT 0.4 milimetre 2. The Contractor shall be obtain the various test results from the
Cover Width of the panel will be 990 milimetre. Crest height of Govt. Laboratory as directed by Engineer in Charge. The
30 milimetre pitch of 198 milimetre.The length of panel as per Original bills of such test condutcted shall be produced at the
site length requirement the side lapping and over lapping joints time of payment. The payment of only those test shall be
of the self supporting panels shall be vapour tight.The PUF released which are acceptable as per relevant specification
panels external and internal sides have guard film protection
and confirmd Indian Standard-123436-1988.The to sheet have
profiled and bottom sheet have a micro rib finishing thermal
conductivity of 0.024 w/mk. Density shall be 40+/. 2 kilogram
per metercube CFC/HCFC free Installation shall be Using
Hourse Power or equivalent Hex head self drilling Screws with
washer 12-14*100 milimeter size of
required.Make:Therm:shield include Ridge Tiles of Width 990
milimeter and end batterns
Executive Engineer
23 Providing sand faced plaster externally in cement mortar using Bd.L.7 Page Number a) This item includes Dhar-core, water patti, grooves in plaster
approved screened sand, in all positions including base coat of 369 etcetera complete as directed.
15 millimetre thick in cement mortar 1:4 using waterproofing b) The waterproofing compound shall be got approved by the
compound at 1 kilogram per cement bag curing the same for Engineer-in-charge before use. The sand for plaster work shall
not less than 2 days and keeping the surface of the base coat be free from silt and shall be washed before use.
rough to receive the sand faced treatment 6 to 8 millimetre thick c) The work shall be carried out as per the directions of Engineer-
in cement mortar 1:4 finishing the surface by taking out grains in-charge
and curing for fourteen days scaffolding etceteracomplete as
directed. (including all leads and lifts)
24 Providing and laying full body vitrified matt fininsh tiles Bd.M.12 Page The work shall be carried out as per the directions of Engineer-
having size 590 milimeter to 605 milimeter x to 605 milimeter of Number 385 in-charge
8 to 10 milimeter thickness and confirming Indian Standard
15622-2006 (Group Bla) of approved make, shade and pattern
for flooring in required position laid on a bed of 1:4 cement
morar including neat cement float, filling joints, curing and
cleaning etcetera complete.
Executive Engineer
26 Providing and laying ceramic tiles having size 30 centimeter. x Bd.M.13 Page The work shall be carried out as per the directions of Engineer-
45 centimeter. confirming to corresponding Indian Standard for Number 386. in-charge
dado and skirting in required position with readymade
adhesive mortar of approved quality on plaster of 1:2 cement
mortar including joint filling with white or colour cement
slurry cleaning curing etcetra complete.
27 Providing internal cement plaster 12 milimetre thick in single Bd. L.2 Page Number The work shall be carried out as per the directions of Engineer-
coat in cement mortar 1:5 without neeru finish to concrete or 368 in-charge
brick surfaces, in all positions including scaffolding and curing
etcetera complete.
28 Providing and fixing Orissa type white glazed earthenware As directed by a) Sample shall be got approved from the Engineer-in-charge
575 milimeter water closet pan including S trap with Engineer in charge. prior to start of work.
earthenware foot rests, cast iron soil and vent pipe upto outside b) The work shall be carried out as per the directions of
face of the wall 1:2:4 brick bat lime concrete bedding without Engineer-in-charge
flushing tank and its accessories et- cetra complete.
Executive Engineer
30 Providing and fixing white glazed earthenware Wash Hand Bd.V.30 Page The work shall be carried out as directed by Engineer in Charge
Basin of 63centimeter x 45centimeter size including Bib cock Number 565
stop tap brass heavy 15milimeter, brackets, rubber plugs and
brass chain, stop tap and necessary pipe connection including
Polyvinyl Chloride waste pipe and trap up to the outside face
of the wall.
31 Providing and fixing on walls/ ceiling/ floor 25 milimetre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
diametre Chlorinated Poly Venyl Chloride pipe of Finolex/ as directed by Institute mark shall be used.
Supreme/ Jain/ Astral make with necessary fittings, remaking Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
good the demolished portion etcetera complete. Including prior to start of work.
removing existing pipe line if necessary and conveying and c) This item includes the cost of making Hot/ cold water
stacking the same in Public Works Department chowky or as pipeline concealed in brickwork, by chasing brickwork, fixing
directed etcetera complete. clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
Executive Engineer
33 Providing, laying and fixing Poly Vinyl Chloride pipe of 110 As directed by a) Pipe of standard make and brand and with Indian Standard
millimetre diameter of Finolex/ Supreme/ Jain/ Astral make Engineer in charge. Institute mark shall be used.
for soil/ vent pipes including fixing Galvanised Iron bracket of b) Sample shall be got approved from the Engineer-in-charge
required size to keep the pipe 40 to 65 millimetre away from prior to start of work.
face of walls and fixing with U clamps nut bolt with fittings c) This item includes the cost of making Hot/ cold water
such as bends, tees, reducers etcetera including necessary pipeline concealed in brickwork, by chasing brickwork, fixing
excavation, trench filling etcetera complete as directed. clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
34 Providing and constructing Brick Masonry Inspection Chamber Bd.V.43, Page The work shall be carried out as per the directions of Engineer-
60 centimetre x 45 centimetre x 90 centimetre average depth Number 574 in-charge
including 1:4:8 cement concrete foundation 1:2:4 cement
concrete channels half round Glazed Stone Ware pipes, brick
masonry, plastering from inside and with frame fixed in cement
concrete with Reinforced Cement Concrete Cover etcetera
complete as directed. (including all leads and lifts)
35 Providing soak pit of size 120 centimetre x 120 centimetre x 120 Bd.V.46, Page The work shall be carried out as per the directions of Engineer-
centimetre including excavating and filling with brick-bats. Number 576 in-charge
Executive Engineer
37 Providing and fixing High Density Polyethelyne container one Bd.K.1 Page The work shall be carried out as directed by Engineer in Charge.
piece moulded water tank made out of low density polythyler Number359
and built corrugation including of delivery up to destination
hoisting and fixing of accessories such as inlet, outlet overflow
of all tanks capacity above 1000 to 20,000 litres Including all
lead and lifts etcetera complete.
38 Providing and fixing 40 milimetre diametre Ball cock medium As directed by The work shall be carried out as directed by Engineer in Charge
type with Poly vinyl Chloride float including sockets and Engineer in
necessary fittings and tested as per municipal requirements charge.
etcetera complete.
Executive Engineer
41 Providing and laying in trenches 15 millimetre diametre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ as directed by Institute mark shall be used.
Jain/ Astral make for water supply including necessary Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
excavation, fittings. refilling trenches etcetera complete as prior to start of work.
directed. c) This item includes the cost of making Hot/ cold water
pipeline concealed in brickwork, by chasing brickwork, fixing
clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
42 Providing and laying in trenches 20 millimetre diametre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ as directed by Institute mark shall be used.
Jain/ Astral make for water supply including necessary Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
excavation, fittings. Refilling trenches etcetera complete as prior to start of work.
directed. c) This item includes the cost of making Hot/ cold water
pipeline concealed in brickwork, by chasing brickwork, fixing
clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
43 Providing fine cement finish 1.5 millimetre thick over green As directed by The work shall be carried out as directed by Engineer in Charge.
plaster surface including scaffolding curing etcetera complete. Engineer in charge.
Executive Engineer
45 Providing and fixing in position powder coated aluminium As directed by The work shall be carried out as directed by Engineer in Charge
louvered windows/ ventilator of various sizes with powder Engineer in
coating as per detailed drawing and specifications including charge.
aluminium frames 80 x 38 millimetre x 1.22 millimetre box
type, 5 millimetre thick sheet glass louvers, of approved quality
etcetera complete.
Executive Engineer
47 Providing and laying Antiskid Ceramic tiles of approved Bd. M-12 Page a) Sample shall be got approved from the Engineer-in-charge
quality of company Johnson/ RAK/ Kajaria/ Nitco/ Asian or Number 385 prior to start of work.
equivalent make of size 30 centimetre x 30 centimetre and b) The work shall be carried out as per the directions of Engineer
confirming to Indian Standard 15622-2006 (Group-B HA) for in charge.
antiskid flooring in toilet area laid on a bed of cement mortar
1:4 including cement float, filling joint with cement slurry
cleaning curing etcetera complete as directed.
48 Providing and fixing 90 centimeter x 60 centimeter Marble Bd.W.7 Page The work shall be carried out as per the directions of Engineer-
plate engraving 10 centimeter. height letter, figures Number586 in-charge
including painting the lefters or figures with approved colour
and shade complete
49 Providing and laying Polished Tandur Stone flooring 25 Bd.M.3 Page Number a) Sample shall be got approved from the Engineer-in-charge
millimetre to 30 millimetre thick required width in plain 380 prior to start of work.
pattern for courtyard on a bed of Cement Mortar 1:6 including b) The work shall be carried out as per the directions of
cement float, filling joints with neat cement slurry, curing, Engineer-in-charge
polishing and cleaning etcetera complete.
50 Providing and laying chequered tiles of approved quality of Bd. M-12 Page a) Sample shall be got approved from the Engineer-in-charge
size 30 centimetre x 30 centimetre confirming to corresponding Number 385 prior to start of work.
Indian Standard for flooring in required position laid on a bed b) The work shall be carried out as per the directions of Engineer
of 1:4 cement mortar including cement float, filling joint with in charge.
cement slurry cleaning curing etcetera complete.
Executive Engineer
52 Providing and Fixing 30 milimetre thick BOTH SIDE As directed by The work shall be carried out as per the directions of Engineer-
PRELAMINATED SOLID PANEL Poly Vernyl Chloride DOOR Engineer in charge. in-charge
SHUTTER consisting of frame made out of Mild Steel tubes of 19
guage thickness and, size 19 x 19 milimetre for styles and 15 x15
milimetre for the top and bottom rails, Mild Steel frame shall have a
coat of metel primer of approved make and manufacture. Mild Steel
frame shall be covered with heat mouled Poly Vernyl Chloride 'C'
channel made from 5 milimetre (+/ 0.25) thick prelaminated sheet of
density 600 Kilogram/ cubic Metre, of size 30 milimetre thickness 70
milimetre width out of which 50 milimetre shall be flat and 20
milimetre shall be tapered in 45 angle on either side forming stiles; and
5 milimetre thick, 95 milimetre wide Poly Vernyl Chloride sheet out of
which 75 milimetre shall be falt and 20 milimetre shall be tapered in 45
on the inner side to form top and bottom rail and 115 milimetre wide
Poly Vernyl Chloride sheet out of which 75 milimetre shall be falt and
20 milimetre shall be tapered on both sides to form lock rail. Top,
bottom and lock rail shall be provided either side of the panel. An
additional 5 milimetre (+/ 0.25) thick Poly Vernyl Chloride strip of 20
milimetre width is to be stuck on the bottom side of the 'C' channel
prelaminated paneling of 5 milimetre (+/ 0.25) thick Poly Vernyl
Chloride sheet to be fitted inside the Mild Steel frame welded/ sealed
to the styles and rails with 5 milimetre (+/ 0.25) x 30 milimetre Poly
Vernyl Chloride sheet beading on either side and joined together with
solvent cement adhesive etcetera 10 milimetre thickness (5 milimetre
(+/ 0.25) x 2 nos ) 20 milimetre wide cross Poly Vernyl Chloride sheet
as gap insert for the rail and bottom rail. Door to be fixed to frames
with 3 numbers Mild Steel powder coated but hinges of size 100
milimetre long steel screws drilled suitable to pass through both the
walls of the M.S tube.other hardwares
Executive Engineer
54 Providing and applying two coats of wall care putty of As directed by The work shall be carried out as directed by Engineer in Charge
approved make on plastered surface and ceiling and walls to Engineer in charge.
prepare surface even and smooth to receive painting, etcetera
complete as directed.
55 Providing and applying two coats of exterior acraylic emulsion As directed by a) The Paint shall be of approved make only.
paint confirming to corresponding Indian Standard of Asian/ Engineer in charge. b) The shade and quality of paint shall be got approved by the
Nerolac/ Berger/ Dulux/ Shalimar make and of approved Engineer in charge prior to start of work.
colour to the plastered surfaces including cleaning, preparing c) The work shall be carried out as per the directions of Engineer
the plaster surface, applying primer coat, scaffolding if in charge
necessary, and watering the surface for two days etcetera
complete as directed.
56 Providing and applying washable oil-bound distemper of Bd. L.2 Page Number a) The Paint shall be of approved make only.
approved colour and shade to old and new surfaces in two 368 b) The shade and quality of paint shall be got approved by the
coats including scaffolding, preparing the surfaces. (excluding Engineer in charge prior to start of work.
the primer coat.) Including all lead and lifts etcetera complete. c) The work shall be carried out as per the directions of Engineer
in charge
Executive Engineer
58 Royalty Charges as per Revenue and Forest Department's As directed by a) The contractor is entitled to pay all Royalty charges as per
notification dated 11/02/2010 as per Maharashtra Minor Engineer in charge. Government rules and regulations and according to the
Mineral Extraction Rules,2010 and as per Instruction in general ammendments made from time to time.
notes on SSR 2020-21 in P.W. Sanctioned schedule of rates for b) In case, the contractor fails to pay the royalty completely (or if
year 2020-2021 for items of lime stone,lime it is paid partially), the Engineer - in - charge reserves the right
shell,stones,rubble,stone to recover the same by deducting that amount from the Running
dust,shingles,gravels,murum,kankar,ordinary earth (to be used account bills or final bill of the contractor.
for embankment and filling),slate and shell etcetera
2 Excavation for roadway in earth, soil of all sorts, sand, gravel or MORTH 301 The work shall be carried out as directed by Engineer in Charge
soft murum including dressing section to the required grade,
camber and side slopes and conveying the excavated materials
with all lifts upto a lead of 50 metre and spreading for
embankment or stacking as directed.
Executive Engineer
4 Excavation for foundation in earth, soil of all types, sand, gravel Bd.A.10 Page a) The sizes of Length, width and depth of excavation shown on
and soft murum including removing the excavated material up Number 262 drawing are probable and may vary in actual execution. The
to required distance beyond the building area, stacking and contractor is not entitled to claim extra payment for changes in
spreading as directed, dewatering if required, preparing the size of Excavation.
bed for the foundation and necessary back filling, ramming, b) The decIndian Standard Instituteon regarding strata
watering including shoring and strutting etcetera complete as classification will be taken by the Engineer-in-charge and shall
directed for all leads and lifts. be final and binding on the Contractor.
c) Only approved material shall be used for backfilling.
d] Soil strata :- This shall include all kinds of Soil, silt, sand, soft
murum, which can be best removed with showel after after
loosening with pick axe or crow bar. It shall also include isolated
boulders upto 0.10 cu.mt. which do not need blasting and cold
be removed with pick axe, showel and crow bar. The strata on
final excavation shall be broght to the notice and got approved
by the Engineer-in-charge, before commencing further work.
e) The work shall be carried out as per directions of the Engineer-
in-charge.
Executive Engineer
6 Providing dry trap rubble stone soling 15 centimetre to 20 Bd.A.10 Page a) Only approved excavated material shall be used for filling.
centimetre thick including hand packing and compacting Number 262 b) The work shall be executed as per directions of the Engineer
etcetera complete as directed. (including all leads and lifts) in charge.
C) Work To be exicuted with vibroplate.
Executive Engineer
8 Providing and fixing in position Thermo Mechanically Treated - Bd.F.17, Page a) The work shall be carried out as per the directions of Engineer-
Ferrous - 500 bar reinforcement of various diameters of Number 306 in-charge.
TISCON, SAIL, TATA Steel, RINL (Rashtriya Ispat Nigam b) The payment shall be made as per Metric Tonne instead of
Limited - Vizag), JSW or with embossing of Indian Standard per Quintal as specified in the standard specification book.
Institute Trade Mark and Thermo Mechanically Treated T c) Re-rolled Steel shall not be used.
Brand at every 1.00 meter interval on every bar confirming to d) Thermo Mechanically Treated (T.M.T. Steel) bar
Indian Standard 1786 for Reinforced Cement Concrete footings, reinforcement of TISCON (TATA Iron and Steel company ),
columns, beams, lintels, chajjas, canopies, slabs, staircase, waist SAIL (Steel Authority of India Limited),TATA Steel, RINL
slas, pardis, copings, fins, arches etcetera as per detailed (Rashtriya Ispat Nigam Limited - Vizag) with embossing of
designs, drawings and schedules including cutting, bending, Indian Standard Institute Trade Mark and T.M.T. Brand at every
hooking the bars, binding with Galvanised Iron binding wires 1.00 meter interval on every bar confirming to Indian Standard
of appropriate gauge and supporting etcetera complete as 1786 shall only be approved by the Engineer-in-charge and the
required. (including all leads and lifts) same shall be brought by the contractor.
e) The charges of Reinforced Cement Conceret Design shall be
borne by Contractor and duly get approved from Engineer in
Charge.
Executive Engineer
Executive Engineer
Executive Engineer
Executive Engineer
13 Filling in plinth and floors with contractors material brought Bd.A.11 Page a) Only approved excavated material shall be used for filling
from outside and approved by Engineer in charge including Number 263 b) The work shall be executed as per directions of the Engineer
watering and compacting in layers of 15 centimetre to 20 in charge. C) Work To be exicuted with vibroplate.
centimetre etcetera complete as directed. (including all leads
and lifts)
14 Filling in plinth and floors with approved excavated material in Bd.A.10 Page a) Only approved excavated material shall be used for filling
15centimeter to 20 centimeter layers including watering and Number 262 b) The work shall be executed as per directions of the Engineer
compacting etcetera complete. in charge. C) Work To be exicuted with vibroplate.
15 Providing second class Burnt Brick masonry with Bd.G.5 Page Number a) The testing of bricks shall be done at prescribed frequency in
conventional/ Indian Standard type bricks in cement mortar 1:6 315 Government/ Government approved laboratory only.
in superstructure including striking joints, raking out joints, b) Testing charges shall be paid by the contractor.
watering and scaffolding etcetera Complete c) One set of 15 bricks to be tested for each consignment of
50,000 number for (I) water absorption and (ii) crushing strength
in dry and wet conditions.
d) The work shall be carried out as per the direction of Engineer-
in-charge.
Executive Engineer
17 Providing and fixing M-40 grade precast concrete door frame of As directed by The work shall be carried out as directed by Engineer in Charge
size 60 millimetre x 100 millimetre vibrated pull cast or similar Engineer in
type with chamfer conforming to Indian Standard 6524-1983 charge.
having 6 millimetre diametres bars 3 Numbers and stirrups at
the rate of 250 millimetre centre to centre and fixing in wall
with 6 Numbers of hold fast of 12 millimetre diametre bars 500
millimetre long including cleaning the frame surface, necessary
primer and oil painting of appoved make and colour shade
etcetera complete as directed including all leads and lifts.
Executive Engineer
19 Providing and laying Cast in situ/ Ready Mix cement concrete Bd.F.8 Page Number The work shall be carried out as directed by Engineer in Charge
M-20 of trap/ granite/ quartzite/ gneiss metal for Reiforced 302 and B.7, Page
Cement Concrete slabs and landings as per detailed designs Number38
and drawings including steel centering, formwork, cover
blocks, laying/ pumping, compaction finishing the formed
surfaces with cement mortar 1:3 of sufficient minimum
thickness to give a smooth and even surface or roughening if
special finish is to be provided and curing etcetera complete,
(Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic
Controller with Supervisory Control and data Aquisition
enabled reversible Drum Type mixer/ concrete Batch mix plant
(Pan mixer) etcetera complete. With fine aggregate (Crushed
sand Vertical Shaft Impactor grade)
Executive Engineer
21 Puf Roof Panel: Sandwich panel for roof 50 milimetre thick(puf) As directed by 1. The work shall be carried out as per the directions of Engineer-
The base material being Mangalore Tile shape profile Pre- Engineer in charge. in-charge
painted coating.External face brick Red.PCT 0.4 milimetre 2. The Contractor shall be obtain the various test results from the
Cover Width of the panel will be 990 milimetre. Crest height of Govt. Laboratory as directed by Engineer in Charge. The
30 milimetre pitch of 198 milimetre.The length of panel as per Original bills of such test condutcted shall be produced at the
site length requirement the side lapping and over lapping joints time of payment. The payment of only those test shall be
of the self supporting panels shall be vapour tight.The PUF released which are acceptable as per relevant specification
panels external and internal sides have guard film protection
and confirmd Indian Standard-123436-1988.The to sheet have
profiled and bottom sheet have a micro rib finishing thermal
conductivity of 0.024 w/mk. Density shall be 40+/. 2 kilogram
per metercube CFC/HCFC free Installation shall be Using
Hourse Power or equivalent Hex head self drilling Screws with
washer 12-14*100 milimeter size of
required.Make:Therm:shield include Ridge Tiles of Width 990
milimeter and end batterns
Executive Engineer
23 Providing sand faced plaster externally in cement mortar using Bd.L.7 Page Number a) This item includes Dhar-core, water patti, grooves in plaster
approved screened sand, in all positions including base coat of 369 etcetera complete as directed.
15 millimetre thick in cement mortar 1:4 using waterproofing b) The waterproofing compound shall be got approved by the
compound at 1 kilogram per cement bag curing the same for Engineer-in-charge before use. The sand for plaster work shall
not less than 2 days and keeping the surface of the base coat be free from silt and shall be washed before use.
rough to receive the sand faced treatment 6 to 8 millimetre thick c) The work shall be carried out as per the directions of Engineer-
in cement mortar 1:4 finishing the surface by taking out grains in-charge
and curing for fourteen days scaffolding etceteracomplete as
directed. (including all leads and lifts)
24 Providing and laying full body vitrified matt fininsh tiles Bd.M.12 Page The work shall be carried out as per the directions of Engineer-
having size 590 milimeter to 605 milimeter x to 605 milimeter of Number 385 in-charge
8 to 10 milimeter thickness and confirming Indian Standard
15622-2006 (Group Bla) of approved make, shade and pattern
for flooring in required position laid on a bed of 1:4 cement
morar including neat cement float, filling joints, curing and
cleaning etcetera complete.
Executive Engineer
26 Providing and laying ceramic tiles having size 30 centimeter. x Bd.M.13 Page The work shall be carried out as per the directions of Engineer-
45 centimeter. confirming to corresponding Indian Standard for Number 386. in-charge
dado and skirting in required position with readymade
adhesive mortar of approved quality on plaster of 1:2 cement
mortar including joint filling with white or colour cement
slurry cleaning curing etcetra complete.
27 Providing internal cement plaster 12 milimetre thick in single Bd. L.2 Page Number The work shall be carried out as per the directions of Engineer-
coat in cement mortar 1:5 without neeru finish to concrete or 368 in-charge
brick surfaces, in all positions including scaffolding and curing
etcetera complete.
28 Providing and fixing Orissa type white glazed earthenware As directed by a) Sample shall be got approved from the Engineer-in-charge
575 milimeter water closet pan including S trap with Engineer in charge. prior to start of work.
earthenware foot rests, cast iron soil and vent pipe upto outside b) The work shall be carried out as per the directions of
face of the wall 1:2:4 brick bat lime concrete bedding without Engineer-in-charge
flushing tank and its accessories et- cetra complete.
Executive Engineer
30 Providing and fixing white glazed earthenware Wash Hand Bd.V.30 Page The work shall be carried out as directed by Engineer in Charge
Basin of 63centimeter x 45centimeter size including Bib cock Number 565
stop tap brass heavy 15milimeter, brackets, rubber plugs and
brass chain, stop tap and necessary pipe connection including
Polyvinyl Chloride waste pipe and trap up to the outside face
of the wall.
31 Providing and fixing on walls/ ceiling/ floor 25 milimetre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
diametre Chlorinated Poly Venyl Chloride pipe of Finolex/ as directed by Institute mark shall be used.
Supreme/ Jain/ Astral make with necessary fittings, remaking Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
good the demolished portion etcetera complete. Including prior to start of work.
removing existing pipe line if necessary and conveying and c) This item includes the cost of making Hot/ cold water
stacking the same in Public Works Department chowky or as pipeline concealed in brickwork, by chasing brickwork, fixing
directed etcetera complete. clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
Executive Engineer
33 Providing, laying and fixing Poly Vinyl Chloride pipe of 110 As directed by a) Pipe of standard make and brand and with Indian Standard
millimetre diameter of Finolex/ Supreme/ Jain/ Astral make Engineer in charge. Institute mark shall be used.
for soil/ vent pipes including fixing Galvanised Iron bracket of b) Sample shall be got approved from the Engineer-in-charge
required size to keep the pipe 40 to 65 millimetre away from prior to start of work.
face of walls and fixing with U clamps nut bolt with fittings c) This item includes the cost of making Hot/ cold water
such as bends, tees, reducers etcetera including necessary pipeline concealed in brickwork, by chasing brickwork, fixing
excavation, trench filling etcetera complete as directed. clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
34 Providing and constructing Brick Masonry Inspection Chamber Bd.V.43, Page The work shall be carried out as per the directions of Engineer-
60 centimetre x 45 centimetre x 90 centimetre average depth Number 574 in-charge
including 1:4:8 cement concrete foundation 1:2:4 cement
concrete channels half round Glazed Stone Ware pipes, brick
masonry, plastering from inside and with frame fixed in cement
concrete with Reinforced Cement Concrete Cover etcetera
complete as directed. (including all leads and lifts)
35 Providing soak pit of size 120 centimetre x 120 centimetre x 120 Bd.V.46, Page The work shall be carried out as per the directions of Engineer-
centimetre including excavating and filling with brick-bats. Number 576 in-charge
Executive Engineer
37 Providing and fixing High Density Polyethelyne container one Bd.K.1 Page The work shall be carried out as directed by Engineer in Charge.
piece moulded water tank made out of low density polythyler Number359
and built corrugation including of delivery up to destination
hoisting and fixing of accessories such as inlet, outlet overflow
of all tanks capacity above 1000 to 20,000 litres Including all
lead and lifts etcetera complete.
38 Providing and fixing 40 milimetre diametre Ball cock medium As directed by The work shall be carried out as directed by Engineer in Charge
type with Poly vinyl Chloride float including sockets and Engineer in
necessary fittings and tested as per municipal requirements charge.
etcetera complete.
Executive Engineer
41 Providing and laying in trenches 15 millimetre diametre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ as directed by Institute mark shall be used.
Jain/ Astral make for water supply including necessary Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
excavation, fittings. refilling trenches etcetera complete as prior to start of work.
directed. c) This item includes the cost of making Hot/ cold water
pipeline concealed in brickwork, by chasing brickwork, fixing
clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
42 Providing and laying in trenches 20 millimetre diametre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ as directed by Institute mark shall be used.
Jain/ Astral make for water supply including necessary Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
excavation, fittings. Refilling trenches etcetera complete as prior to start of work.
directed. c) This item includes the cost of making Hot/ cold water
pipeline concealed in brickwork, by chasing brickwork, fixing
clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
43 Providing fine cement finish 1.5 millimetre thick over green As directed by The work shall be carried out as directed by Engineer in Charge.
plaster surface including scaffolding curing etcetera complete. Engineer in charge.
Executive Engineer
45 Providing and fixing in position powder coated aluminium As directed by The work shall be carried out as directed by Engineer in Charge
louvered windows/ ventilator of various sizes with powder Engineer in
coating as per detailed drawing and specifications including charge.
aluminium frames 80 x 38 millimetre x 1.22 millimetre box
type, 5 millimetre thick sheet glass louvers, of approved quality
etcetera complete.
Executive Engineer
47 Providing and laying Antiskid Ceramic tiles of approved Bd. M-12 Page a) Sample shall be got approved from the Engineer-in-charge
quality of company Johnson/ RAK/ Kajaria/ Nitco/ Asian or Number 385 prior to start of work.
equivalent make of size 30 centimetre x 30 centimetre and b) The work shall be carried out as per the directions of Engineer
confirming to Indian Standard 15622-2006 (Group-B HA) for in charge.
antiskid flooring in toilet area laid on a bed of cement mortar
1:4 including cement float, filling joint with cement slurry
cleaning curing etcetera complete as directed.
48 Providing and fixing 90 centimeter x 60 centimeter Marble Bd.W.7 Page The work shall be carried out as per the directions of Engineer-
plate engraving 10 centimeter. height letter, figures Number586 in-charge
including painting the lefters or figures with approved colour
and shade complete
49 Providing and laying Polished Tandur Stone flooring 25 Bd.M.3 Page Number a) Sample shall be got approved from the Engineer-in-charge
millimetre to 30 millimetre thick required width in plain 380 prior to start of work.
pattern for courtyard on a bed of Cement Mortar 1:6 including b) The work shall be carried out as per the directions of
cement float, filling joints with neat cement slurry, curing, Engineer-in-charge
polishing and cleaning etcetera complete.
50 Providing and laying chequered tiles of approved quality of Bd. M-12 Page a) Sample shall be got approved from the Engineer-in-charge
size 30 centimetre x 30 centimetre confirming to corresponding Number 385 prior to start of work.
Indian Standard for flooring in required position laid on a bed b) The work shall be carried out as per the directions of Engineer
of 1:4 cement mortar including cement float, filling joint with in charge.
cement slurry cleaning curing etcetera complete.
Executive Engineer
52 Providing and Fixing 30 milimetre thick BOTH SIDE As directed by The work shall be carried out as per the directions of Engineer-
PRELAMINATED SOLID PANEL Poly Vernyl Chloride DOOR Engineer in charge. in-charge
SHUTTER consisting of frame made out of Mild Steel tubes of 19
guage thickness and, size 19 x 19 milimetre for styles and 15 x15
milimetre for the top and bottom rails, Mild Steel frame shall have a
coat of metel primer of approved make and manufacture. Mild Steel
frame shall be covered with heat mouled Poly Vernyl Chloride 'C'
channel made from 5 milimetre (+/ 0.25) thick prelaminated sheet of
density 600 Kilogram/ cubic Metre, of size 30 milimetre thickness 70
milimetre width out of which 50 milimetre shall be flat and 20
milimetre shall be tapered in 45 angle on either side forming stiles; and
5 milimetre thick, 95 milimetre wide Poly Vernyl Chloride sheet out of
which 75 milimetre shall be falt and 20 milimetre shall be tapered in 45
on the inner side to form top and bottom rail and 115 milimetre wide
Poly Vernyl Chloride sheet out of which 75 milimetre shall be falt and
20 milimetre shall be tapered on both sides to form lock rail. Top,
bottom and lock rail shall be provided either side of the panel. An
additional 5 milimetre (+/ 0.25) thick Poly Vernyl Chloride strip of 20
milimetre width is to be stuck on the bottom side of the 'C' channel
prelaminated paneling of 5 milimetre (+/ 0.25) thick Poly Vernyl
Chloride sheet to be fitted inside the Mild Steel frame welded/ sealed
to the styles and rails with 5 milimetre (+/ 0.25) x 30 milimetre Poly
Vernyl Chloride sheet beading on either side and joined together with
solvent cement adhesive etcetera 10 milimetre thickness (5 milimetre
(+/ 0.25) x 2 nos ) 20 milimetre wide cross Poly Vernyl Chloride sheet
as gap insert for the rail and bottom rail. Door to be fixed to frames
with 3 numbers Mild Steel powder coated but hinges of size 100
milimetre long steel screws drilled suitable to pass through both the
walls of the M.S tube.other hardwares
Executive Engineer
54 Providing and applying two coats of wall care putty of As directed by The work shall be carried out as directed by Engineer in Charge
approved make on plastered surface and ceiling and walls to Engineer in charge.
prepare surface even and smooth to receive painting, etcetera
complete as directed.
55 Providing and applying two coats of exterior acraylic emulsion As directed by a) The Paint shall be of approved make only.
paint confirming to corresponding Indian Standard of Asian/ Engineer in charge. b) The shade and quality of paint shall be got approved by the
Nerolac/ Berger/ Dulux/ Shalimar make and of approved Engineer in charge prior to start of work.
colour to the plastered surfaces including cleaning, preparing c) The work shall be carried out as per the directions of Engineer
the plaster surface, applying primer coat, scaffolding if in charge
necessary, and watering the surface for two days etcetera
complete as directed.
56 Providing and applying washable oil-bound distemper of Bd. L.2 Page Number a) The Paint shall be of approved make only.
approved colour and shade to old and new surfaces in two 368 b) The shade and quality of paint shall be got approved by the
coats including scaffolding, preparing the surfaces. (excluding Engineer in charge prior to start of work.
the primer coat.) Including all lead and lifts etcetera complete. c) The work shall be carried out as per the directions of Engineer
in charge
Executive Engineer
58 Royalty Charges as per Revenue and Forest Department's As directed by a) The contractor is entitled to pay all Royalty charges as per
notification dated 11/02/2010 as per Maharashtra Minor Engineer in charge. Government rules and regulations and according to the
Mineral Extraction Rules,2010 and as per Instruction in general ammendments made from time to time.
notes on SSR 2020-21 in P.W. Sanctioned schedule of rates for b) In case, the contractor fails to pay the royalty completely (or if
year 2020-2021 for items of lime stone,lime it is paid partially), the Engineer - in - charge reserves the right
shell,stones,rubble,stone to recover the same by deducting that amount from the Running
dust,shingles,gravels,murum,kankar,ordinary earth (to be used account bills or final bill of the contractor.
for embankment and filling),slate and shell etcetera
2 Excavation for roadway in earth, soil of all sorts, sand, gravel or MORTH 301 The work shall be carried out as directed by Engineer in Charge
soft murum including dressing section to the required grade,
camber and side slopes and conveying the excavated materials
with all lifts upto a lead of 50 metre and spreading for
embankment or stacking as directed.
Executive Engineer
4 Excavation for foundation in earth, soil of all types, sand, gravel Bd.A.10 Page a) The sizes of Length, width and depth of excavation shown on
and soft murum including removing the excavated material up Number 262 drawing are probable and may vary in actual execution. The
to required distance beyond the building area, stacking and contractor is not entitled to claim extra payment for changes in
spreading as directed, dewatering if required, preparing the size of Excavation.
bed for the foundation and necessary back filling, ramming, b) The decIndian Standard Instituteon regarding strata
watering including shoring and strutting etcetera complete as classification will be taken by the Engineer-in-charge and shall
directed for all leads and lifts. be final and binding on the Contractor.
c) Only approved material shall be used for backfilling.
d] Soil strata :- This shall include all kinds of Soil, silt, sand, soft
murum, which can be best removed with showel after after
loosening with pick axe or crow bar. It shall also include isolated
boulders upto 0.10 cu.mt. which do not need blasting and cold
be removed with pick axe, showel and crow bar. The strata on
final excavation shall be broght to the notice and got approved
by the Engineer-in-charge, before commencing further work.
e) The work shall be carried out as per directions of the Engineer-
in-charge.
Executive Engineer
6 Providing dry trap rubble stone soling 15 centimetre to 20 Bd.A.10 Page a) Only approved excavated material shall be used for filling.
centimetre thick including hand packing and compacting Number 262 b) The work shall be executed as per directions of the Engineer
etcetera complete as directed. (including all leads and lifts) in charge.
C) Work To be exicuted with vibroplate.
Executive Engineer
8 Providing and fixing in position Thermo Mechanically Treated - Bd.F.17, Page a) The work shall be carried out as per the directions of Engineer-
Ferrous - 500 bar reinforcement of various diameters of Number 306 in-charge.
TISCON, SAIL, TATA Steel, RINL (Rashtriya Ispat Nigam b) The payment shall be made as per Metric Tonne instead of
Limited - Vizag), JSW or with embossing of Indian Standard per Quintal as specified in the standard specification book.
Institute Trade Mark and Thermo Mechanically Treated T c) Re-rolled Steel shall not be used.
Brand at every 1.00 meter interval on every bar confirming to d) Thermo Mechanically Treated (T.M.T. Steel) bar
Indian Standard 1786 for Reinforced Cement Concrete footings, reinforcement of TISCON (TATA Iron and Steel company ),
columns, beams, lintels, chajjas, canopies, slabs, staircase, waist SAIL (Steel Authority of India Limited),TATA Steel, RINL
slas, pardis, copings, fins, arches etcetera as per detailed (Rashtriya Ispat Nigam Limited - Vizag) with embossing of
designs, drawings and schedules including cutting, bending, Indian Standard Institute Trade Mark and T.M.T. Brand at every
hooking the bars, binding with Galvanised Iron binding wires 1.00 meter interval on every bar confirming to Indian Standard
of appropriate gauge and supporting etcetera complete as 1786 shall only be approved by the Engineer-in-charge and the
required. (including all leads and lifts) same shall be brought by the contractor.
e) The charges of Reinforced Cement Conceret Design shall be
borne by Contractor and duly get approved from Engineer in
Charge.
Executive Engineer
Executive Engineer
Executive Engineer
Executive Engineer
13 Filling in plinth and floors with contractors material brought Bd.A.11 Page a) Only approved excavated material shall be used for filling
from outside and approved by Engineer in charge including Number 263 b) The work shall be executed as per directions of the Engineer
watering and compacting in layers of 15 centimetre to 20 in charge. C) Work To be exicuted with vibroplate.
centimetre etcetera complete as directed. (including all leads
and lifts)
14 Filling in plinth and floors with approved excavated material in Bd.A.10 Page a) Only approved excavated material shall be used for filling
15centimeter to 20 centimeter layers including watering and Number 262 b) The work shall be executed as per directions of the Engineer
compacting etcetera complete. in charge. C) Work To be exicuted with vibroplate.
15 Providing second class Burnt Brick masonry with Bd.G.5 Page Number a) The testing of bricks shall be done at prescribed frequency in
conventional/ Indian Standard type bricks in cement mortar 1:6 315 Government/ Government approved laboratory only.
in superstructure including striking joints, raking out joints, b) Testing charges shall be paid by the contractor.
watering and scaffolding etcetera Complete c) One set of 15 bricks to be tested for each consignment of
50,000 number for (I) water absorption and (ii) crushing strength
in dry and wet conditions.
d) The work shall be carried out as per the direction of Engineer-
in-charge.
Executive Engineer
17 Providing and fixing M-40 grade precast concrete door frame of As directed by The work shall be carried out as directed by Engineer in Charge
size 60 millimetre x 100 millimetre vibrated pull cast or similar Engineer in
type with chamfer conforming to Indian Standard 6524-1983 charge.
having 6 millimetre diametres bars 3 Numbers and stirrups at
the rate of 250 millimetre centre to centre and fixing in wall
with 6 Numbers of hold fast of 12 millimetre diametre bars 500
millimetre long including cleaning the frame surface, necessary
primer and oil painting of appoved make and colour shade
etcetera complete as directed including all leads and lifts.
Executive Engineer
19 Providing and laying Cast in situ/ Ready Mix cement concrete Bd.F.8 Page Number The work shall be carried out as directed by Engineer in Charge
M-20 of trap/ granite/ quartzite/ gneiss metal for Reiforced 302 and B.7, Page
Cement Concrete slabs and landings as per detailed designs Number38
and drawings including steel centering, formwork, cover
blocks, laying/ pumping, compaction finishing the formed
surfaces with cement mortar 1:3 of sufficient minimum
thickness to give a smooth and even surface or roughening if
special finish is to be provided and curing etcetera complete,
(Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic
Controller with Supervisory Control and data Aquisition
enabled reversible Drum Type mixer/ concrete Batch mix plant
(Pan mixer) etcetera complete. With fine aggregate (Crushed
sand Vertical Shaft Impactor grade)
Executive Engineer
21 Puf Roof Panel: Sandwich panel for roof 50 milimetre thick(puf) As directed by 1. The work shall be carried out as per the directions of Engineer-
The base material being Mangalore Tile shape profile Pre- Engineer in charge. in-charge
painted coating.External face brick Red.PCT 0.4 milimetre 2. The Contractor shall be obtain the various test results from the
Cover Width of the panel will be 990 milimetre. Crest height of Govt. Laboratory as directed by Engineer in Charge. The
30 milimetre pitch of 198 milimetre.The length of panel as per Original bills of such test condutcted shall be produced at the
site length requirement the side lapping and over lapping joints time of payment. The payment of only those test shall be
of the self supporting panels shall be vapour tight.The PUF released which are acceptable as per relevant specification
panels external and internal sides have guard film protection
and confirmd Indian Standard-123436-1988.The to sheet have
profiled and bottom sheet have a micro rib finishing thermal
conductivity of 0.024 w/mk. Density shall be 40+/. 2 kilogram
per metercube CFC/HCFC free Installation shall be Using
Hourse Power or equivalent Hex head self drilling Screws with
washer 12-14*100 milimeter size of
required.Make:Therm:shield include Ridge Tiles of Width 990
milimeter and end batterns
Executive Engineer
23 Providing sand faced plaster externally in cement mortar using Bd.L.7 Page Number a) This item includes Dhar-core, water patti, grooves in plaster
approved screened sand, in all positions including base coat of 369 etcetera complete as directed.
15 millimetre thick in cement mortar 1:4 using waterproofing b) The waterproofing compound shall be got approved by the
compound at 1 kilogram per cement bag curing the same for Engineer-in-charge before use. The sand for plaster work shall
not less than 2 days and keeping the surface of the base coat be free from silt and shall be washed before use.
rough to receive the sand faced treatment 6 to 8 millimetre thick c) The work shall be carried out as per the directions of Engineer-
in cement mortar 1:4 finishing the surface by taking out grains in-charge
and curing for fourteen days scaffolding etceteracomplete as
directed. (including all leads and lifts)
24 Providing and laying full body vitrified matt fininsh tiles Bd.M.12 Page The work shall be carried out as per the directions of Engineer-
having size 590 milimeter to 605 milimeter x to 605 milimeter of Number 385 in-charge
8 to 10 milimeter thickness and confirming Indian Standard
15622-2006 (Group Bla) of approved make, shade and pattern
for flooring in required position laid on a bed of 1:4 cement
morar including neat cement float, filling joints, curing and
cleaning etcetera complete.
Executive Engineer
26 Providing and laying ceramic tiles having size 30 centimeter. x Bd.M.13 Page The work shall be carried out as per the directions of Engineer-
45 centimeter. confirming to corresponding Indian Standard for Number 386. in-charge
dado and skirting in required position with readymade
adhesive mortar of approved quality on plaster of 1:2 cement
mortar including joint filling with white or colour cement
slurry cleaning curing etcetra complete.
27 Providing internal cement plaster 12 milimetre thick in single Bd. L.2 Page Number The work shall be carried out as per the directions of Engineer-
coat in cement mortar 1:5 without neeru finish to concrete or 368 in-charge
brick surfaces, in all positions including scaffolding and curing
etcetera complete.
28 Providing and fixing Orissa type white glazed earthenware As directed by a) Sample shall be got approved from the Engineer-in-charge
575 milimeter water closet pan including S trap with Engineer in charge. prior to start of work.
earthenware foot rests, cast iron soil and vent pipe upto outside b) The work shall be carried out as per the directions of
face of the wall 1:2:4 brick bat lime concrete bedding without Engineer-in-charge
flushing tank and its accessories et- cetra complete.
Executive Engineer
30 Providing and fixing white glazed earthenware Wash Hand Bd.V.30 Page The work shall be carried out as directed by Engineer in Charge
Basin of 63centimeter x 45centimeter size including Bib cock Number 565
stop tap brass heavy 15milimeter, brackets, rubber plugs and
brass chain, stop tap and necessary pipe connection including
Polyvinyl Chloride waste pipe and trap up to the outside face
of the wall.
31 Providing and fixing on walls/ ceiling/ floor 25 milimetre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
diametre Chlorinated Poly Venyl Chloride pipe of Finolex/ as directed by Institute mark shall be used.
Supreme/ Jain/ Astral make with necessary fittings, remaking Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
good the demolished portion etcetera complete. Including prior to start of work.
removing existing pipe line if necessary and conveying and c) This item includes the cost of making Hot/ cold water
stacking the same in Public Works Department chowky or as pipeline concealed in brickwork, by chasing brickwork, fixing
directed etcetera complete. clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
Executive Engineer
33 Providing, laying and fixing Poly Vinyl Chloride pipe of 110 As directed by a) Pipe of standard make and brand and with Indian Standard
millimetre diameter of Finolex/ Supreme/ Jain/ Astral make Engineer in charge. Institute mark shall be used.
for soil/ vent pipes including fixing Galvanised Iron bracket of b) Sample shall be got approved from the Engineer-in-charge
required size to keep the pipe 40 to 65 millimetre away from prior to start of work.
face of walls and fixing with U clamps nut bolt with fittings c) This item includes the cost of making Hot/ cold water
such as bends, tees, reducers etcetera including necessary pipeline concealed in brickwork, by chasing brickwork, fixing
excavation, trench filling etcetera complete as directed. clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
34 Providing and constructing Brick Masonry Inspection Chamber Bd.V.43, Page The work shall be carried out as per the directions of Engineer-
60 centimetre x 45 centimetre x 90 centimetre average depth Number 574 in-charge
including 1:4:8 cement concrete foundation 1:2:4 cement
concrete channels half round Glazed Stone Ware pipes, brick
masonry, plastering from inside and with frame fixed in cement
concrete with Reinforced Cement Concrete Cover etcetera
complete as directed. (including all leads and lifts)
35 Providing soak pit of size 120 centimetre x 120 centimetre x 120 Bd.V.46, Page The work shall be carried out as per the directions of Engineer-
centimetre including excavating and filling with brick-bats. Number 576 in-charge
Executive Engineer
37 Providing and fixing High Density Polyethelyne container one Bd.K.1 Page The work shall be carried out as directed by Engineer in Charge.
piece moulded water tank made out of low density polythyler Number359
and built corrugation including of delivery up to destination
hoisting and fixing of accessories such as inlet, outlet overflow
of all tanks capacity above 1000 to 20,000 litres Including all
lead and lifts etcetera complete.
38 Providing and fixing 40 milimetre diametre Ball cock medium As directed by The work shall be carried out as directed by Engineer in Charge
type with Poly vinyl Chloride float including sockets and Engineer in
necessary fittings and tested as per municipal requirements charge.
etcetera complete.
Executive Engineer
41 Providing and laying in trenches 15 millimetre diametre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ as directed by Institute mark shall be used.
Jain/ Astral make for water supply including necessary Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
excavation, fittings. refilling trenches etcetera complete as prior to start of work.
directed. c) This item includes the cost of making Hot/ cold water
pipeline concealed in brickwork, by chasing brickwork, fixing
clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
42 Providing and laying in trenches 20 millimetre diametre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ as directed by Institute mark shall be used.
Jain/ Astral make for water supply including necessary Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
excavation, fittings. Refilling trenches etcetera complete as prior to start of work.
directed. c) This item includes the cost of making Hot/ cold water
pipeline concealed in brickwork, by chasing brickwork, fixing
clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
43 Providing fine cement finish 1.5 millimetre thick over green As directed by The work shall be carried out as directed by Engineer in Charge.
plaster surface including scaffolding curing etcetera complete. Engineer in charge.
Executive Engineer
45 Providing and fixing in position powder coated aluminium As directed by The work shall be carried out as directed by Engineer in Charge
louvered windows/ ventilator of various sizes with powder Engineer in
coating as per detailed drawing and specifications including charge.
aluminium frames 80 x 38 millimetre x 1.22 millimetre box
type, 5 millimetre thick sheet glass louvers, of approved quality
etcetera complete.
Executive Engineer
47 Providing and laying Antiskid Ceramic tiles of approved Bd. M-12 Page a) Sample shall be got approved from the Engineer-in-charge
quality of company Johnson/ RAK/ Kajaria/ Nitco/ Asian or Number 385 prior to start of work.
equivalent make of size 30 centimetre x 30 centimetre and b) The work shall be carried out as per the directions of Engineer
confirming to Indian Standard 15622-2006 (Group-B HA) for in charge.
antiskid flooring in toilet area laid on a bed of cement mortar
1:4 including cement float, filling joint with cement slurry
cleaning curing etcetera complete as directed.
48 Providing and fixing 90 centimeter x 60 centimeter Marble Bd.W.7 Page The work shall be carried out as per the directions of Engineer-
plate engraving 10 centimeter. height letter, figures Number586 in-charge
including painting the lefters or figures with approved colour
and shade complete
49 Providing and laying Polished Tandur Stone flooring 25 Bd.M.3 Page Number a) Sample shall be got approved from the Engineer-in-charge
millimetre to 30 millimetre thick required width in plain 380 prior to start of work.
pattern for courtyard on a bed of Cement Mortar 1:6 including b) The work shall be carried out as per the directions of
cement float, filling joints with neat cement slurry, curing, Engineer-in-charge
polishing and cleaning etcetera complete.
50 Providing and laying chequered tiles of approved quality of Bd. M-12 Page a) Sample shall be got approved from the Engineer-in-charge
size 30 centimetre x 30 centimetre confirming to corresponding Number 385 prior to start of work.
Indian Standard for flooring in required position laid on a bed b) The work shall be carried out as per the directions of Engineer
of 1:4 cement mortar including cement float, filling joint with in charge.
cement slurry cleaning curing etcetera complete.
Executive Engineer
52 Providing and Fixing 30 milimetre thick BOTH SIDE As directed by The work shall be carried out as per the directions of Engineer-
PRELAMINATED SOLID PANEL Poly Vernyl Chloride DOOR Engineer in charge. in-charge
SHUTTER consisting of frame made out of Mild Steel tubes of 19
guage thickness and, size 19 x 19 milimetre for styles and 15 x15
milimetre for the top and bottom rails, Mild Steel frame shall have a
coat of metel primer of approved make and manufacture. Mild Steel
frame shall be covered with heat mouled Poly Vernyl Chloride 'C'
channel made from 5 milimetre (+/ 0.25) thick prelaminated sheet of
density 600 Kilogram/ cubic Metre, of size 30 milimetre thickness 70
milimetre width out of which 50 milimetre shall be flat and 20
milimetre shall be tapered in 45 angle on either side forming stiles; and
5 milimetre thick, 95 milimetre wide Poly Vernyl Chloride sheet out of
which 75 milimetre shall be falt and 20 milimetre shall be tapered in 45
on the inner side to form top and bottom rail and 115 milimetre wide
Poly Vernyl Chloride sheet out of which 75 milimetre shall be falt and
20 milimetre shall be tapered on both sides to form lock rail. Top,
bottom and lock rail shall be provided either side of the panel. An
additional 5 milimetre (+/ 0.25) thick Poly Vernyl Chloride strip of 20
milimetre width is to be stuck on the bottom side of the 'C' channel
prelaminated paneling of 5 milimetre (+/ 0.25) thick Poly Vernyl
Chloride sheet to be fitted inside the Mild Steel frame welded/ sealed
to the styles and rails with 5 milimetre (+/ 0.25) x 30 milimetre Poly
Vernyl Chloride sheet beading on either side and joined together with
solvent cement adhesive etcetera 10 milimetre thickness (5 milimetre
(+/ 0.25) x 2 nos ) 20 milimetre wide cross Poly Vernyl Chloride sheet
as gap insert for the rail and bottom rail. Door to be fixed to frames
with 3 numbers Mild Steel powder coated but hinges of size 100
milimetre long steel screws drilled suitable to pass through both the
walls of the M.S tube.other hardwares
Executive Engineer
54 Providing and applying two coats of wall care putty of As directed by The work shall be carried out as directed by Engineer in Charge
approved make on plastered surface and ceiling and walls to Engineer in charge.
prepare surface even and smooth to receive painting, etcetera
complete as directed.
55 Providing and applying two coats of exterior acraylic emulsion As directed by a) The Paint shall be of approved make only.
paint confirming to corresponding Indian Standard of Asian/ Engineer in charge. b) The shade and quality of paint shall be got approved by the
Nerolac/ Berger/ Dulux/ Shalimar make and of approved Engineer in charge prior to start of work.
colour to the plastered surfaces including cleaning, preparing c) The work shall be carried out as per the directions of Engineer
the plaster surface, applying primer coat, scaffolding if in charge
necessary, and watering the surface for two days etcetera
complete as directed.
56 Providing and applying washable oil-bound distemper of Bd. L.2 Page Number a) The Paint shall be of approved make only.
approved colour and shade to old and new surfaces in two 368 b) The shade and quality of paint shall be got approved by the
coats including scaffolding, preparing the surfaces. (excluding Engineer in charge prior to start of work.
the primer coat.) Including all lead and lifts etcetera complete. c) The work shall be carried out as per the directions of Engineer
in charge
Executive Engineer
58 Royalty Charges as per Revenue and Forest Department's As directed by a) The contractor is entitled to pay all Royalty charges as per
notification dated 11/02/2010 as per Maharashtra Minor Engineer in charge. Government rules and regulations and according to the
Mineral Extraction Rules,2010 and as per Instruction in general ammendments made from time to time.
notes on SSR 2020-21 in P.W. Sanctioned schedule of rates for b) In case, the contractor fails to pay the royalty completely (or if
year 2020-2021 for items of lime stone,lime it is paid partially), the Engineer - in - charge reserves the right
shell,stones,rubble,stone to recover the same by deducting that amount from the Running
dust,shingles,gravels,murum,kankar,ordinary earth (to be used account bills or final bill of the contractor.
for embankment and filling),slate and shell etcetera
2 Excavation for roadway in earth, soil of all sorts, sand, gravel or MORTH 301 The work shall be carried out as directed by Engineer in Charge
soft murum including dressing section to the required grade,
camber and side slopes and conveying the excavated materials
with all lifts upto a lead of 50 metre and spreading for
embankment or stacking as directed.
Executive Engineer
4 Excavation for foundation in earth, soil of all types, sand, gravel Bd.A.10 Page a) The sizes of Length, width and depth of excavation shown on
and soft murum including removing the excavated material up Number 262 drawing are probable and may vary in actual execution. The
to required distance beyond the building area, stacking and contractor is not entitled to claim extra payment for changes in
spreading as directed, dewatering if required, preparing the size of Excavation.
bed for the foundation and necessary back filling, ramming, b) The decIndian Standard Instituteon regarding strata
watering including shoring and strutting etcetera complete as classification will be taken by the Engineer-in-charge and shall
directed for all leads and lifts. be final and binding on the Contractor.
c) Only approved material shall be used for backfilling.
d] Soil strata :- This shall include all kinds of Soil, silt, sand, soft
murum, which can be best removed with showel after after
loosening with pick axe or crow bar. It shall also include isolated
boulders upto 0.10 cu.mt. which do not need blasting and cold
be removed with pick axe, showel and crow bar. The strata on
final excavation shall be broght to the notice and got approved
by the Engineer-in-charge, before commencing further work.
e) The work shall be carried out as per directions of the Engineer-
in-charge.
Executive Engineer
6 Providing dry trap rubble stone soling 15 centimetre to 20 Bd.A.10 Page a) Only approved excavated material shall be used for filling.
centimetre thick including hand packing and compacting Number 262 b) The work shall be executed as per directions of the Engineer
etcetera complete as directed. (including all leads and lifts) in charge.
C) Work To be exicuted with vibroplate.
Executive Engineer
8 Providing and fixing in position Thermo Mechanically Treated - Bd.F.17, Page a) The work shall be carried out as per the directions of Engineer-
Ferrous - 500 bar reinforcement of various diameters of Number 306 in-charge.
TISCON, SAIL, TATA Steel, RINL (Rashtriya Ispat Nigam b) The payment shall be made as per Metric Tonne instead of
Limited - Vizag), JSW or with embossing of Indian Standard per Quintal as specified in the standard specification book.
Institute Trade Mark and Thermo Mechanically Treated T c) Re-rolled Steel shall not be used.
Brand at every 1.00 meter interval on every bar confirming to d) Thermo Mechanically Treated (T.M.T. Steel) bar
Indian Standard 1786 for Reinforced Cement Concrete footings, reinforcement of TISCON (TATA Iron and Steel company ),
columns, beams, lintels, chajjas, canopies, slabs, staircase, waist SAIL (Steel Authority of India Limited),TATA Steel, RINL
slas, pardis, copings, fins, arches etcetera as per detailed (Rashtriya Ispat Nigam Limited - Vizag) with embossing of
designs, drawings and schedules including cutting, bending, Indian Standard Institute Trade Mark and T.M.T. Brand at every
hooking the bars, binding with Galvanised Iron binding wires 1.00 meter interval on every bar confirming to Indian Standard
of appropriate gauge and supporting etcetera complete as 1786 shall only be approved by the Engineer-in-charge and the
required. (including all leads and lifts) same shall be brought by the contractor.
e) The charges of Reinforced Cement Conceret Design shall be
borne by Contractor and duly get approved from Engineer in
Charge.
Executive Engineer
Executive Engineer
Executive Engineer
Executive Engineer
13 Filling in plinth and floors with contractors material brought Bd.A.11 Page a) Only approved excavated material shall be used for filling
from outside and approved by Engineer in charge including Number 263 b) The work shall be executed as per directions of the Engineer
watering and compacting in layers of 15 centimetre to 20 in charge. C) Work To be exicuted with vibroplate.
centimetre etcetera complete as directed. (including all leads
and lifts)
14 Filling in plinth and floors with approved excavated material in Bd.A.10 Page a) Only approved excavated material shall be used for filling
15centimeter to 20 centimeter layers including watering and Number 262 b) The work shall be executed as per directions of the Engineer
compacting etcetera complete. in charge. C) Work To be exicuted with vibroplate.
15 Providing second class Burnt Brick masonry with Bd.G.5 Page Number a) The testing of bricks shall be done at prescribed frequency in
conventional/ Indian Standard type bricks in cement mortar 1:6 315 Government/ Government approved laboratory only.
in superstructure including striking joints, raking out joints, b) Testing charges shall be paid by the contractor.
watering and scaffolding etcetera Complete c) One set of 15 bricks to be tested for each consignment of
50,000 number for (I) water absorption and (ii) crushing strength
in dry and wet conditions.
d) The work shall be carried out as per the direction of Engineer-
in-charge.
Executive Engineer
17 Providing and fixing M-40 grade precast concrete door frame of As directed by The work shall be carried out as directed by Engineer in Charge
size 60 millimetre x 100 millimetre vibrated pull cast or similar Engineer in
type with chamfer conforming to Indian Standard 6524-1983 charge.
having 6 millimetre diametres bars 3 Numbers and stirrups at
the rate of 250 millimetre centre to centre and fixing in wall
with 6 Numbers of hold fast of 12 millimetre diametre bars 500
millimetre long including cleaning the frame surface, necessary
primer and oil painting of appoved make and colour shade
etcetera complete as directed including all leads and lifts.
Executive Engineer
19 Providing and laying Cast in situ/ Ready Mix cement concrete Bd.F.8 Page Number The work shall be carried out as directed by Engineer in Charge
M-20 of trap/ granite/ quartzite/ gneiss metal for Reiforced 302 and B.7, Page
Cement Concrete slabs and landings as per detailed designs Number38
and drawings including steel centering, formwork, cover
blocks, laying/ pumping, compaction finishing the formed
surfaces with cement mortar 1:3 of sufficient minimum
thickness to give a smooth and even surface or roughening if
special finish is to be provided and curing etcetera complete,
(Excluding reinforcement and structural steel). with fully
automatic micro processor based Programmable logic
Controller with Supervisory Control and data Aquisition
enabled reversible Drum Type mixer/ concrete Batch mix plant
(Pan mixer) etcetera complete. With fine aggregate (Crushed
sand Vertical Shaft Impactor grade)
Executive Engineer
21 Puf Roof Panel: Sandwich panel for roof 50 milimetre thick(puf) As directed by 1. The work shall be carried out as per the directions of Engineer-
The base material being Mangalore Tile shape profile Pre- Engineer in charge. in-charge
painted coating.External face brick Red.PCT 0.4 milimetre 2. The Contractor shall be obtain the various test results from the
Cover Width of the panel will be 990 milimetre. Crest height of Govt. Laboratory as directed by Engineer in Charge. The
30 milimetre pitch of 198 milimetre.The length of panel as per Original bills of such test condutcted shall be produced at the
site length requirement the side lapping and over lapping joints time of payment. The payment of only those test shall be
of the self supporting panels shall be vapour tight.The PUF released which are acceptable as per relevant specification
panels external and internal sides have guard film protection
and confirmd Indian Standard-123436-1988.The to sheet have
profiled and bottom sheet have a micro rib finishing thermal
conductivity of 0.024 w/mk. Density shall be 40+/. 2 kilogram
per metercube CFC/HCFC free Installation shall be Using
Hourse Power or equivalent Hex head self drilling Screws with
washer 12-14*100 milimeter size of
required.Make:Therm:shield include Ridge Tiles of Width 990
milimeter and end batterns
Executive Engineer
23 Providing sand faced plaster externally in cement mortar using Bd.L.7 Page Number a) This item includes Dhar-core, water patti, grooves in plaster
approved screened sand, in all positions including base coat of 369 etcetera complete as directed.
15 millimetre thick in cement mortar 1:4 using waterproofing b) The waterproofing compound shall be got approved by the
compound at 1 kilogram per cement bag curing the same for Engineer-in-charge before use. The sand for plaster work shall
not less than 2 days and keeping the surface of the base coat be free from silt and shall be washed before use.
rough to receive the sand faced treatment 6 to 8 millimetre thick c) The work shall be carried out as per the directions of Engineer-
in cement mortar 1:4 finishing the surface by taking out grains in-charge
and curing for fourteen days scaffolding etceteracomplete as
directed. (including all leads and lifts)
24 Providing and laying full body vitrified matt fininsh tiles Bd.M.12 Page The work shall be carried out as per the directions of Engineer-
having size 590 milimeter to 605 milimeter x to 605 milimeter of Number 385 in-charge
8 to 10 milimeter thickness and confirming Indian Standard
15622-2006 (Group Bla) of approved make, shade and pattern
for flooring in required position laid on a bed of 1:4 cement
morar including neat cement float, filling joints, curing and
cleaning etcetera complete.
Executive Engineer
26 Providing and laying ceramic tiles having size 30 centimeter. x Bd.M.13 Page The work shall be carried out as per the directions of Engineer-
45 centimeter. confirming to corresponding Indian Standard for Number 386. in-charge
dado and skirting in required position with readymade
adhesive mortar of approved quality on plaster of 1:2 cement
mortar including joint filling with white or colour cement
slurry cleaning curing etcetra complete.
27 Providing internal cement plaster 12 milimetre thick in single Bd. L.2 Page Number The work shall be carried out as per the directions of Engineer-
coat in cement mortar 1:5 without neeru finish to concrete or 368 in-charge
brick surfaces, in all positions including scaffolding and curing
etcetera complete.
28 Providing and fixing Orissa type white glazed earthenware As directed by a) Sample shall be got approved from the Engineer-in-charge
575 milimeter water closet pan including S trap with Engineer in charge. prior to start of work.
earthenware foot rests, cast iron soil and vent pipe upto outside b) The work shall be carried out as per the directions of
face of the wall 1:2:4 brick bat lime concrete bedding without Engineer-in-charge
flushing tank and its accessories et- cetra complete.
Executive Engineer
30 Providing and fixing white glazed earthenware Wash Hand Bd.V.30 Page The work shall be carried out as directed by Engineer in Charge
Basin of 63centimeter x 45centimeter size including Bib cock Number 565
stop tap brass heavy 15milimeter, brackets, rubber plugs and
brass chain, stop tap and necessary pipe connection including
Polyvinyl Chloride waste pipe and trap up to the outside face
of the wall.
31 Providing and fixing on walls/ ceiling/ floor 25 milimetre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
diametre Chlorinated Poly Venyl Chloride pipe of Finolex/ as directed by Institute mark shall be used.
Supreme/ Jain/ Astral make with necessary fittings, remaking Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
good the demolished portion etcetera complete. Including prior to start of work.
removing existing pipe line if necessary and conveying and c) This item includes the cost of making Hot/ cold water
stacking the same in Public Works Department chowky or as pipeline concealed in brickwork, by chasing brickwork, fixing
directed etcetera complete. clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
Executive Engineer
33 Providing, laying and fixing Poly Vinyl Chloride pipe of 110 As directed by a) Pipe of standard make and brand and with Indian Standard
millimetre diameter of Finolex/ Supreme/ Jain/ Astral make Engineer in charge. Institute mark shall be used.
for soil/ vent pipes including fixing Galvanised Iron bracket of b) Sample shall be got approved from the Engineer-in-charge
required size to keep the pipe 40 to 65 millimetre away from prior to start of work.
face of walls and fixing with U clamps nut bolt with fittings c) This item includes the cost of making Hot/ cold water
such as bends, tees, reducers etcetera including necessary pipeline concealed in brickwork, by chasing brickwork, fixing
excavation, trench filling etcetera complete as directed. clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
34 Providing and constructing Brick Masonry Inspection Chamber Bd.V.43, Page The work shall be carried out as per the directions of Engineer-
60 centimetre x 45 centimetre x 90 centimetre average depth Number 574 in-charge
including 1:4:8 cement concrete foundation 1:2:4 cement
concrete channels half round Glazed Stone Ware pipes, brick
masonry, plastering from inside and with frame fixed in cement
concrete with Reinforced Cement Concrete Cover etcetera
complete as directed. (including all leads and lifts)
35 Providing soak pit of size 120 centimetre x 120 centimetre x 120 Bd.V.46, Page The work shall be carried out as per the directions of Engineer-
centimetre including excavating and filling with brick-bats. Number 576 in-charge
Executive Engineer
37 Providing and fixing High Density Polyethelyne container one Bd.K.1 Page The work shall be carried out as directed by Engineer in Charge.
piece moulded water tank made out of low density polythyler Number359
and built corrugation including of delivery up to destination
hoisting and fixing of accessories such as inlet, outlet overflow
of all tanks capacity above 1000 to 20,000 litres Including all
lead and lifts etcetera complete.
38 Providing and fixing 40 milimetre diametre Ball cock medium As directed by The work shall be carried out as directed by Engineer in Charge
type with Poly vinyl Chloride float including sockets and Engineer in
necessary fittings and tested as per municipal requirements charge.
etcetera complete.
Executive Engineer
41 Providing and laying in trenches 15 millimetre diametre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ as directed by Institute mark shall be used.
Jain/ Astral make for water supply including necessary Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
excavation, fittings. refilling trenches etcetera complete as prior to start of work.
directed. c) This item includes the cost of making Hot/ cold water
pipeline concealed in brickwork, by chasing brickwork, fixing
clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
42 Providing and laying in trenches 20 millimetre diametre BD.V 5 Page 551 and a) Pipe of standard make and brand and with Indian Standard
Chlorinated Poly Venyl Chloride pipe of Finolex/ Supreme/ as directed by Institute mark shall be used.
Jain/ Astral make for water supply including necessary Engineer in charge b) Sample shall be got approved from the Engineer-in-charge
excavation, fittings. Refilling trenches etcetera complete as prior to start of work.
directed. c) This item includes the cost of making Hot/ cold water
pipeline concealed in brickwork, by chasing brickwork, fixing
clamps, etcetera
d) The work shall be carried out as per the directions of
Engineer in charge.
43 Providing fine cement finish 1.5 millimetre thick over green As directed by The work shall be carried out as directed by Engineer in Charge.
plaster surface including scaffolding curing etcetera complete. Engineer in charge.
Executive Engineer
45 Providing and fixing in position powder coated aluminium As directed by The work shall be carried out as directed by Engineer in Charge
louvered windows/ ventilator of various sizes with powder Engineer in
coating as per detailed drawing and specifications including charge.
aluminium frames 80 x 38 millimetre x 1.22 millimetre box
type, 5 millimetre thick sheet glass louvers, of approved quality
etcetera complete.
Executive Engineer
47 Providing and laying Antiskid Ceramic tiles of approved Bd. M-12 Page a) Sample shall be got approved from the Engineer-in-charge
quality of company Johnson/ RAK/ Kajaria/ Nitco/ Asian or Number 385 prior to start of work.
equivalent make of size 30 centimetre x 30 centimetre and b) The work shall be carried out as per the directions of Engineer
confirming to Indian Standard 15622-2006 (Group-B HA) for in charge.
antiskid flooring in toilet area laid on a bed of cement mortar
1:4 including cement float, filling joint with cement slurry
cleaning curing etcetera complete as directed.
48 Providing and fixing 90 centimeter x 60 centimeter Marble Bd.W.7 Page The work shall be carried out as per the directions of Engineer-
plate engraving 10 centimeter. height letter, figures Number586 in-charge
including painting the lefters or figures with approved colour
and shade complete
49 Providing and laying Polished Tandur Stone flooring 25 Bd.M.3 Page Number a) Sample shall be got approved from the Engineer-in-charge
millimetre to 30 millimetre thick required width in plain 380 prior to start of work.
pattern for courtyard on a bed of Cement Mortar 1:6 including b) The work shall be carried out as per the directions of
cement float, filling joints with neat cement slurry, curing, Engineer-in-charge
polishing and cleaning etcetera complete.
50 Providing and laying chequered tiles of approved quality of Bd. M-12 Page a) Sample shall be got approved from the Engineer-in-charge
size 30 centimetre x 30 centimetre confirming to corresponding Number 385 prior to start of work.
Indian Standard for flooring in required position laid on a bed b) The work shall be carried out as per the directions of Engineer
of 1:4 cement mortar including cement float, filling joint with in charge.
cement slurry cleaning curing etcetera complete.
Executive Engineer
52 Providing and Fixing 30 milimetre thick BOTH SIDE As directed by The work shall be carried out as per the directions of Engineer-
PRELAMINATED SOLID PANEL Poly Vernyl Chloride DOOR Engineer in charge. in-charge
SHUTTER consisting of frame made out of Mild Steel tubes of 19
guage thickness and, size 19 x 19 milimetre for styles and 15 x15
milimetre for the top and bottom rails, Mild Steel frame shall have a
coat of metel primer of approved make and manufacture. Mild Steel
frame shall be covered with heat mouled Poly Vernyl Chloride 'C'
channel made from 5 milimetre (+/ 0.25) thick prelaminated sheet of
density 600 Kilogram/ cubic Metre, of size 30 milimetre thickness 70
milimetre width out of which 50 milimetre shall be flat and 20
milimetre shall be tapered in 45 angle on either side forming stiles; and
5 milimetre thick, 95 milimetre wide Poly Vernyl Chloride sheet out of
which 75 milimetre shall be falt and 20 milimetre shall be tapered in 45
on the inner side to form top and bottom rail and 115 milimetre wide
Poly Vernyl Chloride sheet out of which 75 milimetre shall be falt and
20 milimetre shall be tapered on both sides to form lock rail. Top,
bottom and lock rail shall be provided either side of the panel. An
additional 5 milimetre (+/ 0.25) thick Poly Vernyl Chloride strip of 20
milimetre width is to be stuck on the bottom side of the 'C' channel
prelaminated paneling of 5 milimetre (+/ 0.25) thick Poly Vernyl
Chloride sheet to be fitted inside the Mild Steel frame welded/ sealed
to the styles and rails with 5 milimetre (+/ 0.25) x 30 milimetre Poly
Vernyl Chloride sheet beading on either side and joined together with
solvent cement adhesive etcetera 10 milimetre thickness (5 milimetre
(+/ 0.25) x 2 nos ) 20 milimetre wide cross Poly Vernyl Chloride sheet
as gap insert for the rail and bottom rail. Door to be fixed to frames
with 3 numbers Mild Steel powder coated but hinges of size 100
milimetre long steel screws drilled suitable to pass through both the
walls of the M.S tube.other hardwares
Executive Engineer
54 Providing and applying two coats of wall care putty of As directed by The work shall be carried out as directed by Engineer in Charge
approved make on plastered surface and ceiling and walls to Engineer in charge.
prepare surface even and smooth to receive painting, etcetera
complete as directed.
55 Providing and applying two coats of exterior acraylic emulsion As directed by a) The Paint shall be of approved make only.
paint confirming to corresponding Indian Standard of Asian/ Engineer in charge. b) The shade and quality of paint shall be got approved by the
Nerolac/ Berger/ Dulux/ Shalimar make and of approved Engineer in charge prior to start of work.
colour to the plastered surfaces including cleaning, preparing c) The work shall be carried out as per the directions of Engineer
the plaster surface, applying primer coat, scaffolding if in charge
necessary, and watering the surface for two days etcetera
complete as directed.
56 Providing and applying washable oil-bound distemper of Bd. L.2 Page Number a) The Paint shall be of approved make only.
approved colour and shade to old and new surfaces in two 368 b) The shade and quality of paint shall be got approved by the
coats including scaffolding, preparing the surfaces. (excluding Engineer in charge prior to start of work.
the primer coat.) Including all lead and lifts etcetera complete. c) The work shall be carried out as per the directions of Engineer
in charge
Executive Engineer
58 Royalty Charges as per Revenue and Forest Department's As directed by a) The contractor is entitled to pay all Royalty charges as per
notification dated 11/02/2010 as per Maharashtra Minor Engineer in charge. Government rules and regulations and according to the
Mineral Extraction Rules,2010 and as per Instruction in general ammendments made from time to time.
notes on SSR 2020-21 in P.W. Sanctioned schedule of rates for b) In case, the contractor fails to pay the royalty completely (or if
year 2020-2021 for items of lime stone,lime it is paid partially), the Engineer - in - charge reserves the right
shell,stones,rubble,stone to recover the same by deducting that amount from the Running
dust,shingles,gravels,murum,kankar,ordinary earth (to be used account bills or final bill of the contractor.
for embankment and filling),slate and shell etcetera
Executive Engineer
BAR CHART
No. Item Of Work 30 Days 60 Days 90 Days 120 Days 150 Days 180 Days
2 M20 Beam
3 M20 Column
8 Internal Plaster
9 External Plaster
10 Flooring
12 Misc. Work
PROPOSED MULTIPURPOSE
18.55
CENTER UNDER PRIME MINISTERS
0.23 0.10 0.10 0.23 0.23 0.10 0.10 0.23
1.05 1.05 1.05 10.93 1.05 1.05 1.05 JANMAN SCHEME FOR TRIBAL
DEPARTMENT.
0.23
0.10
0.60 0.60 0.10
0.23 0.23 0.22 0.23 0.60 0.60
0.89 1.50 0.88 1.00 1.50 1.00 0.88 1.50 0.89 0.22 0.23 0.22 0.23
WC WC 0.45 0.45 WC WC
1.40
1.40
0.30 0.10 0.30 0.30 0.10 0.30
1.64
1.64
0.75 0.75 0.75 0.75
2.85
0.10
0.10
FEMALE TOILET MALE TOILET
1.35
1.35
0.99
0.99
0.23
MULTIPURPOSE HALL
0.55
0.55
7.68
UP UP
3.35 10.93 3.35
1.50
1.50
CLASSROOM ANGANWADI
3.35
10.46
1.08
1.08
2.35 1.00
0.23
0.45 0.45
0.89 1.80 0.58 1.00 1.50 1.00 0.58 1.80 0.89
0.93
1.00
0.67
3.35
1.50
VERANDAH
2.35
0.74
0.92
0.45 0.45 0.23
0.92 1.50 0.93 1.21 1.60 1.44 0.77 3.05 0.57 1.64 1.40 1.21 0.93 1.50 0.92
0.23
All Door Lintel - 2.10m Ht.
All Window Sill - 0.75m Ht.
All Window HT.- 1.50m Ht.
Toilet Ventilator - 0.60 X 0.90
Toilet Ventilator Sill - 2.25m Ht.
DATE:
SCALE: N. T . S
FLOOR PLAN DRAWN BY: HA R SHA L
PROPOSED MULTIPURPOSE
CENTER UNDER PRIME MINISTERS
JANMAN SCHEME FOR TRIBAL
DEPARTMENT.
FABRICATED ROOF
AS PER DETAILS
22°
+4.35 ROOF LVL
FRONT ELEVATION
FABRICATED ROOF
AS PER DETAILS
+6.91 ROOF LVL
2.13
+3.00 ROOF LVL
4.68
+2.70 LINTEL LVL 0.75
0.75
1.20
1.20
2.55
2.10
2.10
0.90
0.90
0.60
± 0.00 GROUND LVL.
SECTION
NISHANK Group
3,Shree Sakshi,Garden Colony,
Indira Nagar, Nashik - 422009
Tel: +91-253-2328182
DATE:
SCALE: N. T . S
ELEVATION & SECTION DRAWN BY: HA R SHA L