Taking A New Rig Into Use: Original Instructions

This document provides essential instructions for safely taking a new rig into use, emphasizing the importance of following operator and maintenance manuals to avoid hazards. It outlines procedures for inspecting the rig, including visual checks, functional tests, and ensuring proper assembly and lubrication. Additionally, it details the requirements for warranty validity and the necessary steps for engine registration and start-up documentation.

Uploaded by

EDI HARTANTO
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views14 pages

Taking A New Rig Into Use: Original Instructions

This document provides essential instructions for safely taking a new rig into use, emphasizing the importance of following operator and maintenance manuals to avoid hazards. It outlines procedures for inspecting the rig, including visual checks, functional tests, and ensuring proper assembly and lubrication. Additionally, it details the requirements for warranty validity and the necessary steps for engine registration and start-up documentation.

Uploaded by

EDI HARTANTO
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

Original instructions

en-US 10 2023-02-16

Taking a new rig into use

GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E
Taking a new rig into use

WARNING
IGNORING INSTRUCTIONS HAZARD!
To avoid death or injury you MUST read, understand and follow
operator's and maintenance manuals before installing, inspecting,
operating, servicing, testing, cleaning, transporting, storing,
dismantling or disposing of the product or a part or accessory of the
product. Keep this publication for future reference.

Copyright © Sandvik Group


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

This page is intentionally left blank

Copyright © Sandvik Group


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

Table of Contents
1 Introduction.......................................................................7
1.1 The purpose of these instructions............................................................ 7
1.1.1 Validity of the manuals...................................................................... 7
1.2 Preface, warranty and start up...................................................................7

2 Inspecting a new rig......................................................... 9


2.1 General.........................................................................................................9
2.2 Finalizing the rig..........................................................................................9
2.3 Visual inspection.......................................................................................10
2.4 Check fuel level and oil levels................................................................. 10
2.5 Functional inspection............................................................................... 11
2.5.1 Carrier functions.............................................................................. 11
2.5.2 Drilling functions.............................................................................. 12

Copyright © Sandvik Group


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

This page is intentionally left blank

Copyright © Sandvik Group


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

1 INTRODUCTION
1.1 The purpose of these instructions
This manual contains important information for inspecting the rig after the
transportation and for preparing and taking the new rig safely into use at
the site.
These instructions must be followed along with other manuals of the rig,
any instructions given in local laws and regulations, any orders given by
local authorities, and all protective measures specific for the site.
Before performing any actions, maintenance or repair procedures for the rig
described in this manual, read and understand the information in operator´s
and maintenance manuals supplied with the machine. Pay special attention
to the safety information in chapter Safety and environmental instructions of
those manuals.
1.1.1 Validity of the manuals
This manual, and especially the safety information, is valid only if no
unauthorized changes to the product are made.
Continuing improvement and advancement of product design might have
caused changes to your product which are not included in this publication.
Note also that if a third party has made changes to the product after
delivery from the manufacturer, this publication does not include information
on these changes or their influences on the product.
Whenever a question arises regarding your product, or this manual, please
consult your local Sandvik representative for the latest available
information.

1.2 Preface, warranty and start up

Preface
The purpose of this instruction is to give some advices needed when taking
a new rig into use.

Warranty
Sandvik gives the warranty on the rig according to warranty clauses of
Sandvik.
The filling of warranty clauses requires that:
• The machine is operated and serviced according to the instructions
which are given in the Sandvik manuals.
• The machine is serviced by trained maintenance personnel.
• The recommended lubrications and fuel instructions are followed.
• Only original spare parts are used.

Copyright © Sandvik Group 7 (14)


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

Start up
The form of Start-up is in the appendix. The warranty of the rig begins when
the form of start-up has been filled by Sandvik representative and has been
returned to Sandvik.
The engine registration must be done at the same time as filling the unit
start-up form when commissioning the machine.
Note! Without this separate registration, the warranty for the engine is not
valid.
See the following addresses for the different supplier’s engine registration
forms:
• Product registration for Cummins engines
https://www.cummins.com/support/product-registration
• Engine registration for Deutz engines
https://www.deutz.com/en/service/e-services/engine-registration/
• Registration for Mercedes Benz engines
warranty@mtu-online.com

8 (14) Copyright © Sandvik Group


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

2 INSPECTING A NEW RIG


2.1 General
New rig shall be finalized, inspected and tested so that the use of the rig is
safe, and the rig is suitable for its intended use. During the inspection the
Start-up document shall be filled, and all noticed lacks or damages on the
rig or rig's components are to be documented with good quality photos.

2.2 Finalizing the rig

WARNING
IGNORING INSTRUCTIONS HAZARD!
If you do not understand any information related to your duties, you
MUST make sure that you get clarification from a person who is well
trained with regard to the task you want to do. When necessary, you
or your representative must contact a Sandvik representative to seek
clarification as to how you should do the task.

If the rig was delivered in components or partly disassembled, finalize the


rig by assembling the detached parts and components. Observe the
following points:
• Use a proper assembly site (clean, good lighting, good hoisting
equipment, etc.).
• Use a proper tools and accessories.
• Check that the delivery contains all components.
• Install all bolts and fasten the connections carefully.
• Observe cleanliness when connecting hydraulic components and hoses
(prevent dirt from entering the hydraulic system).
• Wash the rig before taking it into use.
• Lubricate all greasing points.
• Check the pressure accumulators for correct pressures:
- Brakes
- Retainer
- Rock drill
- Compressor hydraulic accumulator (if equipped)

Copyright © Sandvik Group 9 (14)


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

WARNING! HIGH PRESSURE HAZARD!


A high pressure gas discharge could cause death or severe injury.
Service of the pressure accumulators is only allowed to persons
specially trained for this. The maintenance instructions for hydraulic
rock drill pressure accumulators must be followed precisely. Ignoring
instructions may cause risk of accidents.

Pressurize the pressure accumulators as instructed when needed.


• If the rig does not have the trailing cable installed by the factory, install
correctly sized trailing cable, cable connector, relief sock and cable
stopper.
• Adjust the limits of the cable reel after the cable installation according to
instructions in Maintenance Manual.
• Adjust the reeling hydraulics corresponding to the installed cable size.
• If the rig has multi-voltage options, setup the rig's multi-voltage
transformer correctly for the voltage of the main power supply center.
Installation of electrical devices is permitted only for persons with
appropriate training and the qualifications required by the authorities.

2.3 Visual inspection


Take the rig to a horizontally level area. By walking around the rig couple of
times, visually check the condition of the rig. Open the covers if needed.
Check that all components and devices are intact. Fix and document all
noticed quality issues with Start-up document before taking the rig to
operation.
• Check the rig for lacking parts/components.
• Check the covers and painting for cracks, dents and other damages.
• Check the air pressure and condition of tires of the rig.
• Check the rig for visible oil, fuel or coolant leaks.
• Check the hoses for squeezing or bending.
• Check the water hoses and water pump for freezing.
• Check that electric devices are intact.
• Check the electric cables and wires for squeezing and mechanical
damages.

2.4 Check fuel level and oil levels


• Check the oil level in the diesel engine. Oil level must be between the
min. and max. marks on the dipstick.
• Check the engine coolant level in the expansion tank. Coolant level
must be between the min. and max. marks on the sight glass.
• Check the oil level in the compressor. Oil level must be between the
min. and max. marks on the sight glass.

10 (14) Copyright © Sandvik Group


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

• Check the hydraulic oil level. Oil level must be between the min. and
max. marks on the sight glass.
• Check the oil level in the gear box.
• Check the oil level in the differential gear.
• Check the oil level in the planetary gears.
• Check the oil level in the shank lubrication tank.
• Check fuel level in the fuel gauge.

2.5 Functional inspection


Functional inspection of the rig can be done after the rig is finalized, the
visual inspection and checking of oil levels are completed and the rig is
identified being in good condition from those parts.
Make sure the main power supply center is safe and suitable for rig's
electric system. Install the trailing cable connector, relief sock and cable
stopper to the cable before connecting the rig to main power supply center.
If the rig does not have the trailing cable installed by the factory, install
correctly sized trailing cable according to instructions in cable reel manual.
If the rig has multi-voltage options, setup the rig's multi-voltage transformer
correctly for the voltage of the main power supply center according to
instructions in Electric system technical manual.
Installation of electrical devices is permitted only for persons with
appropriate training and the qualifications required by the authorities.
2.5.1 Carrier functions
Inspection of carrier functions includes the functions related to tramming of
the rig.
• Make sure there is no service work ongoing on the rig or there are no
unauthorized persons near the rig.
• Check that the hydraulic control levers, if equipped, are in middle
position.
• Make sure that all emergency stop buttons have been released, the
electrical cabinet door is closed and the main switch Q1 is in position 1
(ON).
• Check that parking brake is engaged.
Start the diesel engine and continue as follows:
• Test the functionality of the emergency stop buttons.
• Start the diesel engine
• Walk around the rig and observe for oil leaks
• Monitor possible notices and alarms on the tramming display.
• Complete the brake test procedure.

Copyright © Sandvik Group 11 (14)


ID:GUID-D9CF98D5-363B-4EDC-AA38-763DC144430E en-US 10 2023-02-16
Taking a new rig into use

• Test the forward and reverse tramming directions.


• Test the steering.
2.5.2 Drilling functions
Inspection of drilling functions includes the functions related to drilling with
a rig.
• Make sure there is no service work ongoing on the rig or there are no
unauthorized persons near the rig.
• Connect the supply cable to the main power supply center.
• Connect water (optional) and air (optional) hoses to their supplies.
• Check that the hydraulic system control levers, if equipped, are in the
middle position.
• Make sure that all emergency stop buttons have been released, the
electrical cabinet door is closed and the main switch Q1 is in position 1
(ON).
• Check that parking brake is engaged.
• Start the power pack(s).
• Start the compressor.
• If water supply is available, start the water pump.
• Test the boom and drilling module movements.
• Test the functionality of the emergency stop buttons.
• Start the power pack(s).
During testing the rock drill functions, monitor the temperatures of hydraulic
oil and compressor. Check that the automatic draining sequence of the SLU
is working.
• Test the rock drill functions.
• Observe for possible hydraulic oil leaks.
After all inspections and tests are completed, finalize and sign the start-up
document and return it to the local Sandvik representative.