Civil Construction- Bill of Quantity (BOQ) with Price :
S.L Description of Item Qty. Unit Price Amount
01 Site Mobilization Work: L.T ----
02 Layout and Marking: 600.0 sft 5.0 3000.0
03 Earthwork in excavation: 1512.0 cft 15.50 23436.0
04 Side Earth filling: 504.0 cft 6.0 3024.0
05 Under Sand Filling: 300.0 cft 28.0 8400.0
06 One layer of brick flat soling: 600.0 sft 56.0 33600.0
07 Mass concrete work: 00.0 sft 95.0 0.0
08 Polythene sheet: 650.0 sft 4.5 2925.0
09 Reinforced Cement Concrete (RCC) Works: 1044.0 cft 225.0 234900.0
10 5” Brick works: 1320.0 sft 125.0 165000.0
11 Chemical/Admixture: 40.0 ltr 175.0 7000.0
12 Reinforcement Fabrication Work: 3700.0 Kg 92.0 340400.0
13 Cement Plaster works: 2640.0 sft 30.0 79200.0
14 Neat cement finishing: 350.0 sft 7.0 2450.0
15 Tiles Work: 755.0 sft 95.0 26425.0
16 Door Work (as per requirement): 7 Pcs 4000.0 28000.0
17 Weather coat & Inner Paint: 2650.0 sft 32.0 84800.0
18 Form Work /Shuttering work: 975.0 sft 35.0 92625.0
19 Scaffolding Work: 750.0 sft 10.0 7500.0
Amount = 1142685.0