THE COLOMBIAN 2007 BLACK OUT
c. A. Ruiz, N. J. Orrego and J. F. Gutierrez
                                                                            area caused by the failure of some power device for example:
 Abstract--On April 26th, 2007, at 9:58 a.m., a fault on the                a line short circuit or the outage of a substation braker.
 colombian power system caused by maintenance in the 230 kV                     In Colombia, it could be as a result of a terrorist attack to
 Torca Bus gave origin to black out.                                        the energy infrastructure, but in other countries, could be
    The consequent loss of those important branches caused                  caused by investment delays as a result of a tight power
 cascading outages of tie lines that turned out in cascade events
                                                                            system regulation that leads to devices obsolescence.
 that concluded in an electrical separation with Ecuador, causing
 many economical losses for the country. The Colombian power                    A blackout can be produced by load increments or
 system frequency suffered a mayor imbalance that leaded to a               decrements beyond a safe level, if the protection system fails
 disoperation of the automatic load shedding system and this                in shedding load or disconnecting generators in order to keep
 resulted out in the Colombian blackout.                                    the load flow in a secure value.
    This paper provides a short description of the power system                 A blackout can be prevented if the vulnerability of the
 analysis operation and of the main events that triggered the               system is determined in the planning stages of the operation in
 blackout, identifying some of the main causes that could lead to
                                                                            order to establish the actions that must be followed to assure
 those events.
    Index Terms-- Blackouts, power system security, power                   the safe operation of the system.
 system stability, power system restoration.                                    CND-XM, the Colombian system operator issues every day
                                                                            the colombian generation dispatch considering the system
                           I.   INTRODUCTION                                reliability using the VERPC (Valor Esperado de
  W       HEN cascading outages happen the lights tum out and               Racionamiento Programado Condicionado - Expected Value
          everything stops. With the facility down and in the               Of Conditioned Loss Of Load) in order to reduce lost of load
  dark, there is nothing to do but to sit and wait until the utility        supply and providing energy in an economical way.
  company finds out the problem and solves it. This process
  usually takes only few minutes but sometimes it takes hours                                           II.   ANTECEDENTS
  and to complete system restoration, it can even take days.                    There are about 82 main blackouts registered in countries
      Blackouts are by sure the most troublesome problem that a             as: United States, France, Canada, Brazil, Portugal, Chile,
  utility company will have to deal with. Statistics show that              Mexico, Italy, Sweden and Colombia among others. In the
  power failures are, in general, a strange situation in most               Fig. 1 it is presented the incidence of blackouts from 1966 to
  countries. Blackouts are also short in duration. Studies have             present time. It can be seen that from 2003 the occurrence of
  shown that 50 percent of blackouts last to 6 s. And 35 percent            those contingencies is been drastically increasing. Notice that
  are less than 11 min long. These failure times are not a cause            in this year it is been registered 8 events by may [2-10].
  to concern for most commercial users, but for those industries
  where there are computer-based operations, transportation                  18                    bleck outs In the world          17
  control systems, medical facilities, and communications sites              16
  they can be a problem.
      When service continuity is critical, redundancy must be
                                                                             14
                                                                                   I                                           la        12
  carried throughout the system. It means that some sites should
  never depend upon one critical path for ac power. For
                                                                             12
                                                                             10
                                                                                   J
                                                                                   15
  example, if the facility is fed by a single step-down
  transformer, a lightning flash or other catastrophic event could
                                                                              8
                                                                              6
                                                                                   I•
                                                                                    ::I
                                                                                                                                              8
  result in a transformer failure that would bring down the
  electric supply.
      A blackout is the total failure of the electric supply in an
      This work was supported by the Universidad Nacional de Colombia and
  XM Los Expertos en Mercados an ISA Group enterprise.
      Cesar Augusto Ruiz is from Universidad Nacional de Colombia sede      Fig. 1: Blackouts by year
  Manizales (e-mail: caruiz@3g.telme.sg).
      Jorge Fernando Gutierrez is from Universidad Nacional de Colombia,
  Serle Manizales(e-mail: jfgutierrez@unal.edu.co)
                                                                            Some of the effects (duration and people affected) of the main
      Nolasco de Jesus Orrego is from XM - ISA, Medellin, (e-mail:          events are presented in Table I.
  njorrego@xm.com.co)
978-1-4244-2218-0/08/$25.00 ©2008 IEEE.
                                                                                                                                 2
                                                                           system that affected the whole country for about 1,5
                                                                           hours [4].
                                  TABLE I.
                    CIVILIANS AFFECTED BY BLACKOUTS                    7. Colombia on April 26, 2007. This event affected
                                          time   civilians                 almost the whole country and will be detailed in the
           year         country                                            next section.
                                        (hours) (millions)             8. Argentina on May 17th, 2007. A fire in a Transener
          1989        CANADA                9        6                     substation caused a blackout that lasted for 3 hours
          1999         BRASIL                 9        90                  affecting a mayor area in Buenos Aires.
          2003      USA-CANADA                9        50              9. Spain Barcelona on July 23,2007. The whole city was
          2003        CANADA                  5       4,3                  affected and in some parts of it the blackout lasted
          2003          ITALY                24        56                  for 78 hours.
          2005      JAVA ISLAND               7       100
          2007      COSTA RICA               1,5        5            III.   THE COLOMBIAN SCENARIO BEFORE THE BLACKOUT
          2007       COLOMBIA                4,5       38             The system operator of the Colombian power system
          2008        CANADA                 3        0,1         (Centro Nacional de Despacho - CND-XM) solves everyday
          2008       AUSTRALIA               72       0,42        the energy dispatch process observing the market regulator
                                                                  reliability guidelines. In this process it is included a blackout
In Fig. 2, it is presented the percentage of blackouts by         risk equalizing policy called VERPC. CND must find a
country. It can be seen that developed countries are taking the   solution of the dispatch problem so that the expected relative
bigger share of the main blackouts.                               load shedding in the different sub-areas of the interconnected
                                                                  system (SIN - Sistema Interconectado Nacional) are equalized
                        BLACK OUTS PERCENTAGE                     among the different sub-areas and minimized. This criteria is
                                                                  equivalent to the worldwide well-known N-l criteria [13].
                                                                      On March 15 th , 2007 ISA the main transmission system
                                                                  operator in Colombia, announce about some maintenance
                                                                  works on Torca substation to CND. Those works will be done
                                                                  on line with the substation equipment energized. That
                                                                  substation is double bus and a sectioned transfer bus. That
                                                                  maintenance was approved to be done on April 26 th • On April
                                                                  25 th the system operator, solved the day-ahead energy dispatch
                                                                  considering the risk of failure on the 230 kV Torca - Guavio
                                                                  power line during the maintenance, and approved that
                                                                  maintenance to be done by 9:20 AM.
Fig. 2: Blackouts density by country                                  On Fig. 3, can be seen the normal state before the
                                                                  maintenance. The power line flows were below the limits and
  A list of the most important events, by their socio -           the frequency and voltages were between their normal values.
economic impacts should include the following:
    1. USA Northeast blackout on November, 1965.
    2. USA New York blackout on July 13, 1977. During
         this event there were disturbs and riots registered
         along the city.
    3. Canada - Hydro Quebec on March 13, 1989. It was
         caused by GMD (Geomagnetic Disturbances) and
         was one of the largest ever recorded. The entire
         Quebec Interconnection was blacked out as a result
         of this disturb 6 million people were affected during
         about 9 hours.
    4. USA California on 2000 - 2001 experienced several
         power shortages as a result of its electricity
         deregulation process.
    5. U.S.-Canada blackout on August 14,2003. This event
         affected 50 millions of people in 8 American states
         and 2 Canadian provinces and 63 GW of load was           Fig. 3. SIN state before contingency
         curtailed [7].
    6. Italy on September 28th, 2003. As a result of two             On Fig. 4, can be seen the transfer limits between areas
         Swiss power lines overloaded a loss of synchronism       (blue) and the real values before contingency (white). At that
         between the Italian system and the UCTE power            moment the system was generating 7083 MW and there were
                                                                                                                                        3
not any international power transfers with Ecuador. This           In spite of that situation, Guavio and Chivor, the biggest
power interchange with Ecuador it is been done using the        generation plants in that area were on line, but the
Jamondino - Pomasqui tie line and the political agreement       transmission corridor that carries out the energy was overload
between the countries is called TIES.                           so frequency and bus voltages were decreasing beyond the
                                                                safe limits causing this area insulation from the rest of the
                                                                system. That caused that thermo plants of Paipa and Yopal
                                                                were shut down. At that moment there was a lost of generation
                                                                close to 2100 MW that corresponds to 31 % of the load (6644
                                                                MW). That causes separation of the network into islands and
                                                                the disconnection of:
                                                                        • Guavio-Tunal transmission line
                                                                        • Tunal- Reforma transmission line
                                                                   In Fig. 6 can be seen that the disconnection of those lines
                                                                causes the islanding of Boyaca and Santander regions.
                                                                Disparo de Guavio - Tunal/Reforma                    Boyee' y santanderes
        .~   .a:".,~".~~~
Fig. 4 Pre-contingency power flows between areas
                      IV. EVENT DEVELOPMENT
   At 09:58 during the maintenance on one the Torca bus 1
disconnect switch L 141 an operation of the M240 circuit
breaker that couples the substation buses occurred. That
operation caused the desenergization of the entire substation
and the circuit opening of Chivor 1 y 2, Bacata 1 y 2, Guavio
1 y 2 and 230/115 kV Torca transformers 2, 3 y 4. Those lines
and transformers are the power supply to Bogota [11].              In Fig. 7, is presented the frequency evolution during the
    A cascading event result as a consequence of Torca          contingency. Note the frequency deviations between the
outage. First, Guavio-Circo power circuits were opened as can   system islands. The oriental area were experience over
be seen on Fig. 5. That outage caused low voltage levels in     frequency and for rest of the country the lost of generation
some bars (blue), overloads flow on 220kV Villavicencio -       caused a low frequency.
Tunal transmission line (red) and the outage of Termo Zipa
gen~ration plant [11].
                                                                   ..                    •
                                                                                ....
                                                                 ~f~·---~.,.~--~---~--~...L-_-~
                                                                                                 ,. ..
                                                                   " "            m   1_'_'-- ..
                                                                                                •      .
                                                                   -'""
                                                                      tr,,'IQ'::-CA.·...
                                                                         T....-;~T
                                                                                        '..:-~t
                                                                                    ......:.:hlO._I._'.-.
                                                                                       :~~
                                                                                                         ~·   1lQ!
                                                                         ....   .........,.Ull"'"'*_~.·ot:
                                                                Fig. 7 Frequency response during the contingency
                                                                   After that, Colombia and Ecuador were insulated by the
                                                                opening of Jamondino-Pomasqui circuits. Finally, other plants
                                                                of the Colombian system were shut down in the sequence
Fig. 5 Guavio-Circo transmission line outage.                   described below:
                                                                         Calderas Generator 1, at 9:58.42.885
                                                                                                                                            4
         Calderas Generator 2, at 9:58.43.130                                                VI. CONCLUTIONS
         Guaca Generator 3, at 9:58.43.000                           The Colombian power system operator XM, after analyzing
         San Carlos Generator 8, at 9:58.43.940                   this event, issued a document with some conclusions about the
         San Carlos Generator 6, at 9:58.44.240                   system behavior during this contingency and its restoration
        San Carlos Generator 5, at 9:58.44.290                    process [11]. Some of those conclusions are presented below:
        Tennocentro Generator 1, at 9:58.51.708                       • The load shedding system EDAC system and the
        Tennocentro Generator 2, at 9:58.51.951                           primary and secondary generation reserves had
        Playas Generator 1, at 9:58.50.567                                operated as they were intended to do.
        Playas Generator 3, at 9:58.59.393                            •   It is necessary to install a contingency alann device in
        Playas Generator 2, at 9:58.50.890                                order to improve time responses during contingencies.
   That lost of generation caused the frequency response              •   It is necessary to reinforce communication channels
presented in Fig. 8.                                                      between the regional transmission operators and the
     lOi...--------..".......--------------,                              main system operator increasing its redundancy and
                                                                          developing new communication protocols.
                                                                      •   It is important to analyze the system vulnerability to
                                                                          the substation failure in order to know which of them
                                . ...·_-·--·----·------··-·;
     .o+---------------~
                                                                          are critical
    Iss
    J••                                                                                  VII. ACKNOWLEDGMENT
                                                                     The authors gratefully acknowledge the contributions of
     !ltoi----------"",...,.--------~lJIIr_----l
                                                                  Corredor P., Murcia A., et Al and XM for their work on the
     tlU+-------~IloOoI.JO\UUi..--------~---I                     original version of this document.
     t60+-------...---.....--_...------,---__- ~
          o
                                                                                            VIII. REFERENCES
Fig. 8Frequency response to generation shut down                  [1] Corredor P., Murcia A., et AI. "Evento del 26 de Abril de 2007 en el SIN
                                                                       Colombiano", 2007
                                                                  [2] US-Canada Power System Outage Task Forces. Final Report on the
That lack of generation causes an active power imbalance that          August 14, 2003, Black-Out in the US and Canada: causes and
could not be corrected by the load shedding system                     recommendations. April 2004
implemented in Colombia called (EDAC - Esquema                    [3] Taylor C. Preventing Black Outs. IEEE/PES 2004
                                                                  [4] Berizzi A. The Italian 2003 blackout, IEEE PES General Meeting,
Automatico de Desconexi6n de Carga) because of the extreme             Denver, CO, June 6-12, 2004.
situation presented, so the system totally collapsed.             [5] "Report on the blackout in Italy on 28 September 2003," available at
                                                                       http://www.energie-schweiz.ch. November 2003.
                     V. SYSTEM RESTORATION                        [6] Dagle 1. E. Data Management Issues Associated with the August 14,
                                                                       2003 Blackout Investigation, IEEE, IEEE PES General Meeting,
   The system restoration was planned by XM who                        Denver, CO, June 6-12, 2004.
coordinated the actions between 40 transmission control           [7] Hauer J. F., Bhatt N, Shah K. et AI. "Performance of 'WAMS East' in
                                                                       Providing Dynamic Information for the North East Blackout of August
centers, generation companies and regional transmission                14,2003". IEEE PES General Meeting, Denver, CO, June 6-12, 2004.
operators.                                                        [8] Corsi S. and Sabelli C. General Blackout in Italy Sunday September 28,
   The strategy relied in those plants with black star capacity        2003. IEEE PES General Meeting, Denver, CO, June 6-12, 2004.
                                                                  [9] Gomes P. New Strategies to Improve Bulk Power System Security:
and the tie-lines operation with Ecuador and Venezuela. Post           Lessons Learned From Large Blackouts;. IEEE PES General Meeting,
contingency guides developed previously were used in the               Denver, CO, June 6-12, 2004.
system operation restoration in every area. Those guides are      [10] Larsson S. and Ek Svenska E. The Black-out in Southern Sweden and
developed by XM and the system agents and are continually              Eastern Denmark. IEEE PES General Meeting, Denver, CO, June 6-12,
                                                                         2004.
actualized.                                                       [11]   ISA XM. Evaluacion del Esquema de Desconexion Automatica de Carga
   After 4, 5 hours the system was totally reestablished to              por Baja Frecuencia - EDAC- 2007 Gerencia Centro Nacional de
nonnal. The restoration process duration can be considered               Despacho Direccion Planeacion de la Operacion XM Mayo 28, 2007
                                                                  [12]   NERC. August 14, 2003 Blackout: NERC Actions to Prevent and
appropriate in comparison with others, for example:                      Mitigate the Impacts of Future Cascading Blackouts February 10, 2004
   • 07/12/2006 Auckland, New Zeeland took 10 hours.              [13]   Lopez L 1. M., Murillo S C. E. Gutierrez G J. F. A Contingency-Based
   • 08/22/2005 Iraq took 7 hours                                        Security-Constrained Optimal Power Flow Model for Revealing The
   •    11/25/2005 Musterland, took six days because of the              Marginal Cost of a Blackout Risk-Equalizing Policy in the Colombian
                                                                         Electricity Market. 2006 IEEE PES Transmission And Distribution
        heavy weather conditions.                                        Conference and Exposition Latin America. 2006.
   But those 4,5 hours of inactivity had a cost of nearly US$     [14]   ELECTRICITY RESTRUCTURING 2003 Blackout Identifies Crisis
130 millions to the country.                                             and Opportunity for the Electricity Sector Report to the Chairman,
                                                                         Senate Committee on Governmental Affairs United States General
                                                                         Accounting Office GAO November 2003
                                                                  [15]   Imai S. TEPCO's Observations on August 14 Blackout and
                                                                         Recommendations to Prevent Future Blackouts based on TEPCO's
                                                                         Experience. IEEE PES General Meeting, Denver, CO, June 6-12, 2004.
                                                                                    5
[16] Van Hulst N. Lessons Learned from the Power Outage in North America
     and Europe Director, Long-Term Co-operation and Policy Analysis
     RIETI Policy Symposium Tokyo, 15 December 2004
[17] Illic M. Granger M. et AI. Electrical Blackouts: A Systemic Problem.
[18] Mandozzi M., Menditto V., Moreschini G. et AI. "Recent improvements
     of emergency automatic control of Enel power system in interconnected
     and isolated operation", CIGRE Session, paper, Paris, 1992.
[19] Veloza O. P. and Cespedes R.H. "Vulnerability of the Colombian
     Electric System to Blackouts and Possible Remedial Actions", IEEE PW
     2006.
                            IX. BIOGRAPHIES
               Cesar Augusto Ruiz Beltran: He received a degree in
               electrical engineering from the Universidad Nacional de
               Colombia - Manizales in 2008. He was a passant student at XM
               S.A E.S.P, owned by Interconexi6n Electrica S.A (ISA).
               Currently, his working as an engineer at CODENSA S.A. ESP.
   Nolasco De Jesus Orrego: studied electrical engineering at the
Universidad de antioquia, then he studied at the University of Wisconsin-
Madison, where he obtained a Master of Science in electrical power systems,
he is currently working at XM S.A E.S.P, owned by Interconexi6n Electrica
S.A (ISA).
    Jorge Fernando Gutierrez Gomez: studied electrical engineering at the
Universidad Industrial de Santander, where he also obtained a Master of
Science in electrical power systems; he is currently a full time professor at the
Universidad Nacional de Colombia Sede Manizales. His main areas of
interests include power systems operation and control, transmission lines and
energy markets.