MDL Rev02

The document outlines the details of a 100MW solar PV project in Tamil Nadu, executed by Premier Solar Powertech Pvt. Ltd. It includes various design and approval documents related to electrical systems, equipment layouts, and vendor specifications, along with comments and timelines for each drawing. The project documentation emphasizes the technical requirements and compliance for the successful implementation of the solar power plant.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views1 page

MDL Rev02

The document outlines the details of a 100MW solar PV project in Tamil Nadu, executed by Premier Solar Powertech Pvt. Ltd. It includes various design and approval documents related to electrical systems, equipment layouts, and vendor specifications, along with comments and timelines for each drawing. The project documentation emphasizes the technical requirements and compliance for the successful implementation of the solar power plant.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

EPC CONTRACTOR : PREMIER SOLAR POWERTECH PVT. LTD.

2018
Project - 100MW solar PV project in Tamilnadu
Ref. LOA No. CO CONTS/S709PRMIER/S709PRMIER/2018 Dt.: 04/04/2018
NLC NLC
Drawing No. Drawing Title Category Division System Equipment R0 R1 NLC COMMENTS R2 NLC COMMENTS NLC COMMENTS
COMMENTS COMMENTS R3 R4
PSPT_NLC100_2018_19_E_R000_001 Design Basis Report (Annual Energy Yield for 25 Years, PV Syst Report, Shadow Analysis Report ) Information Electrical TN709 General 23.01.2019 24.01.2019 28.01.2019 08.02.2019 01.03.2019
PSPT_NLC100_2018_19_E_R000_002 Power Evacuation Scheme Information Electrical TN709 General

PSPT_NLC100_2018_19_E_R000_003 Soil Resistivity Reports Information Electrical TN709 General 08.01.2019 21.01.2019 21.01.2019 25.01.2019 06.02.2019 08.02.2019 10.02.2019 19.02.2019
PSPT_NLC100_2018_19_E_R000_004 Electrical System Calculation & Parameters of PV Plant Information Electrical TN709 General 22.01.2019 07.02.2019 26.02.2019 27.02.2019 01.03.2019 02.03.2019
PSPT_NLC100_2018_19_E_R000_005 DC Single Line Diagram & Capacity Calculation Approval Electrical TN709 General 16.11.2018 19.11.2018 29.01.2019 31.01.2019 02.02.2019 08.02.2019
PSPT_NLC100_2018_19_E_R000_006 AC Single Line Diagram Approval Electrical TN709 General 16.11.2018 19.11.2018 08.01.2019 11.01.2019 05.02.2019 08.02.2019
PSPT_NLC100_2018_19_E_R000_007 Equipment Layout - PCSS Room Approval Electrical TN709 General 23.01.2019 05.02.2019 06.02.2019 12.02.2019
PSPT_NLC100_2018_19_E_R000_008 Equipment Layout - PESS Room Approval Electrical TN709 General 22.01.2019 29.01.2019 30.01.2019 31.01.2019
PSPT_NLC100_2018_19_E_R000_009 PV Modules - Vendor 1 - GTP, GA, vendor document and Type Test Certificates, MQP Approval Electrical TN709 PV Modules

PSPT_NLC100_2018_19_E_R000_010 PV Modules - Vendor 2 - GTP, GA, vendor document and Type Test Certificates, MQP Approval Electrical TN709 PV Modules

PSPT_NLC100_2018_19_E_R000_011 PV Modules - Vendor 3 - GTP, GA, vendor document and Type Test Certificates, MQP Approval Electrical TN709 PV Modules

PSPT_NLC100_2018_19_E_R000_012 PV Modules - Vendor 4 - GTP, GA, vendor document and Type Test Certificates, MQP Approval Electrical TN709 PV Modules

PSPT_NLC100_2018_19_E_R000_013 PV Modules - Vendor 5 - GTP, GA, vendor document and Type Test Certificates, MQP Approval Electrical TN709 PV Modules

PSPT_NLC100_2018_19_E_R000_014 PV Modules - Vendor 6 - GTP, GA, vendor document and Type Test Certificates, MQP Approval Electrical TN709 PV Modules

PSPT_NLC100_2018_19_E_R000_015 DC solar Cables (EBC) - Sizing & Drop calculation Approval Electrical TN709 DC Solar Cable 22.01.2019 02.02.2019 04.02.2019 05.02.2019
PSPT_NLC100_2018_19_E_R000_016 DC solar Cables (EBC) - GTP, GA, vendor document and Type Test Certificates Approval Electrical TN709 DC Solar Cable 01.03.2019 02.03.2019
PSPT_NLC100_2018_19_E_R000_017 DC solar Cables (EBC) - MQP Approval Electrical TN709 DC Solar Cable 01.03.2019
PSPT_NLC100_2018_19_E_R000_018 DC solar Cables (EBC) - Schedule Information Electrical TN709 DC Solar Cable

PSPT_NLC100_2018_19_E_R000_019 String Combiner Box - GTP, GA, Schematic Diagrams, vendor document and Type Test Certificates Approval Electrical TN709 SCB 07.02.2019 08.02.2019 11.02.2019 12.02.2019
PSPT_NLC100_2018_19_E_R000_020 String Combiner Box - MQP Approval Electrical TN709 SCB 07.02.2019 08.02.2019 11.02.2019 12.02.2019
PSPT_NLC100_2018_19_E_R000_021 DC Cable (SCB to Inverter) - Sizing & Drop calculation Approval Electrical TN709 DC Cable 22.01.2019 02.02.2019 04.02.2019 05.02.2019 06.02.2019 15.02.2019
PSPT_NLC100_2018_19_E_R000_022 DC Cable (SCB to Inverter) - GTP, GA, vendor document and Type Test Certificates Approval Electrical TN709 DC Cable 01.03.2019
PSPT_NLC100_2018_19_E_R000_023 DC Cable (SCB to Inverter) - MQP Approval Electrical TN709 DC Cable

PSPT_NLC100_2018_19_E_R000_024 DC Cable (SCB to Inverter) - Schedule Information Electrical TN709 DC Cable

PSPT_NLC100_2018_19_E_R000_025 DC Cables - Overall Cable Routing Layout & Trench Details Information Electrical TN709 DC Cable

PSPT_NLC100_2018_19_E_R000_026 Inverter - GTP, GA, Schematic Diagrams, vendor document and Type Test Certificates Approval Electrical TN709 Inverter 09.01.2019 21.01.2019 23.01.2019 29.01.2019 04.03.2019
PSPT_NLC100_2018_19_E_R000_027 Inverter - MQP Approval Electrical TN709 Inverter 09.01.2019 21.01.2019
PSPT_NLC100_2018_19_E_R000_028 AC LT Power Cables - Sizing & Drop calculation Approval Electrical TN709 AC LT Cable 22.01.2019 05.02.2019 06.02.2019 15.02.2019 26.02.2019 02.03.2019 05.03.2019
PSPT_NLC100_2018_19_E_R000_029 AC LT Power Cables - GTP, GA, vendor document and Type Test Certificates Approval Electrical TN709 AC LT Cable 01.03.2019
PSPT_NLC100_2018_19_E_R000_030 AC LT Power Cables - MQP Approval Electrical TN709 AC LT Cable

PSPT_NLC100_2018_19_E_R000_031 AC LT Power Cables - Schedule Information Electrical TN709 AC LT Cable

PSPT_NLC100_2018_19_E_R000_032 Inverter Power Transformer -GTP, GA, Schematic Diagrams, vendor document and Type Test Certificates Approval Electrical TN709 Inverter Transformer 06.02.2019 13.02.2019 16.02.2019 19.02.2019
PSPT_NLC100_2018_19_E_R000_033 Inverter Transformer - MQP Approval Electrical TN709 Inverter Transformer 06.02.2019 10.02.2019 10.02.2019 13.02.2019
PSPT_NLC100_2018_19_E_R000_034 Inverter Transformer - Fire Protection System GTP, GA, vendor documents & MQP Approval Electrical TN709 Inverter Transformer

PSPT_NLC100_2018_19_E_R000_035 AC HT Power Cables - Sizing & Drop calculation Approval Electrical TN709 AC HT Cable 22.01.2019 07.02.2019 07.02.2019 14.02.2019
PSPT_NLC100_2018_19_E_R000_036 AC HT Power Cables - GTP, GA, vendor document and Type Test Certificates Approval Electrical TN709 AC HT Cable 01.03.2019
PSPT_NLC100_2018_19_E_R000_037 AC HT Power Cables - MQP Approval Electrical TN709 AC HT Cable

PSPT_NLC100_2018_19_E_R000_038 AC HT Power Cables - Schedule Information Electrical TN709 AC HT Cable

PSPT_NLC100_2018_19_E_R000_039 AC HT & LT Power Cables - Overall Cable Routing Layout & Trench Detail Information Electrical TN709 AC HT Cable

PSPT_NLC100_2018_19_E_R000_040 HT Switch Board/Switch Gear - GTP, GA, Vendor documents and Type Test Reports for CB & Enclosoure. Approval Electrical TN709 HT Switch Gear 01.03.2019 02.03.2019
PSPT_NLC100_2018_19_E_R000_041 HT Switch Board/Switch Gear - GTP, GA, Vendor documents and Type Test Reports for Accessories. Approval Electrical TN709 HT Switch Gear 01.03.2019 02.03.2019
PSPT_NLC100_2018_19_E_R000_042 HT Switch Board/Switch Gear - GA, Schematic Diagram for all type of verticals (IC/OG/BC/Bus PT etc) Approval Electrical TN709 HT Switch Gear 01.03.2019 02.03.2019
along with Earthing Scheme for PCSS, PESS etc.
PSPT_NLC100_2018_19_E_R000_043 HT Switch Board/Switch Gear with Accessories - MQP Approval Electrical TN709 HT Switch Gear 01.03.2019
PSPT_NLC100_2018_19_E_R000_044 Auxiliary Transformers for PESS, PCSS Etc - Sizing Calculation Approval Electrical TN709 Aux. Supply 01.02.2019 08.02.2019 10.02.2019 14.02.2019
PSPT_NLC100_2018_19_E_R000_045 Auxiliary supply System for PESS, PCSS Etc - SLD Approval Electrical TN709 Aux. Supply 01.02.2019 08.02.2019 12.02.2019 14.02.2019
PSPT_NLC100_2018_19_E_R000_046 Auxiliary Transformer for PCSS Etc - GTP, GA and vendor documents Approval Electrical TN709 Aux. Supply

PSPT_NLC100_2018_19_E_R000_047 Auxiliary Transformer for PCSS Etc - MQP Approval Electrical TN709 Aux. Supply

PSPT_NLC100_2018_19_E_R000_048 Auxiliary Transformer for PESS - GTP, GA and vendor documents Approval Electrical TN709 Aux. Supply 23.02.2019 26.02.2019
PSPT_NLC100_2018_19_E_R000_049 Auxiliary Transformer for PESS - MQP Approval Electrical TN709 Aux. Supply 23.02.2019 26.02.2019
PSPT_NLC100_2018_19_E_R000_050 UPS for PESS, PCSS Etc - Sizing Calculation including Battery capacity Approval Electrical TN709 UPS -PCSS 04.02.2019 05.02.2019 07.02.2019 08.02.2019
PSPT_NLC100_2018_19_E_R000_051 UPS for PESS, PCSS Etc - GTP, GA & vendor documents Approval Electrical TN709 UPS -PCSS

PSPT_NLC100_2018_19_E_R000_052 UPS for PESS, PCSS Etc - MQP Approval Electrical TN709 UPS -PCSS

PSPT_NLC100_2018_19_E_R000_053 DC System with Batteries for PESS, PCSS Etc - Sizing Calculation Approval Electrical TN709 Control DC System

PSPT_NLC100_2018_19_E_R000_054 DC System with Batteries for PESS, PCSS Etc - GTP, GA & vendor documents and DCDB details. Approval Electrical TN709 Control DC System

PSPT_NLC100_2018_19_E_R000_055 DC System with Batteries for PESS, PCSS Etc - MQP Approval Electrical TN709 Control DC System

PSPT_NLC100_2018_19_E_R000_056 Lightning arrestors of PV Array - Design calculation Approval Electrical TN709 LA 22.01.2019 29.01.2019 04.02.2019 08.02.2019
PSPT_NLC100_2018_19_E_R000_057 Lightning arrestors of PV Array - GTP, GA & vendor documents Approval Electrical TN709 LA 12.02.2019 13.02.2019 23.02.2019 26.02.2019
PSPT_NLC100_2018_19_E_R000_058 Layout for Overall Lightning Protection Approval Electrical TN709 LA

PSPT_NLC100_2018_19_E_R000_059 Lighting system PCSS etc - Design & Luminaire details. Approval Electrical TN709 Lighting

PSPT_NLC100_2018_19_E_R000_060 Lighting system PCSS etc - Layout Approval Electrical TN709 Lighting

PSPT_NLC100_2018_19_E_R000_061 Lighting system PESS - Design & Luminaire details Approval Electrical TN709 Lighting

PSPT_NLC100_2018_19_E_R000_062 Lighting system PESS - Layout Approval Electrical TN709 Lighting

PSPT_NLC100_2018_19_E_R000_063 Lighting system security building and Watch Tower - Design & Luminaire details Approval Electrical TN709 Lighting

PSPT_NLC100_2018_19_E_R000_064 Lighting system security building and Watch Tower - Layout Approval Electrical TN709 Lighting

PSPT_NLC100_2018_19_E_R000_065 Lighting system Outdoor Yard and Roads - Design & Luminaire details. Approval Electrical TN709 Lighting

PSPT_NLC100_2018_19_E_R000_066 Lighting system Outdoor Yard and Roads - Layout Approval Electrical TN709 Lighting

PSPT_NLC100_2018_19_E_R000_067 AC Earthing for PESS, PCSS Etc. - Design calculation with Touch & Step potential Verification Approval Electrical TN709 Earthing

PSPT_NLC100_2018_19_E_R000_068 AC Earthing PCSS Etc - GA and Layout Approval Electrical TN709 Earthing

PSPT_NLC100_2018_19_E_R000_069 AC Earthing PESS - GA and Layout Approval Electrical TN709 Earthing

PSPT_NLC100_2018_19_E_R000_070 DC Earthing for PV Array & SCB - Design calculation with Touch & Step potential Verification Approval Electrical TN709 Earthing

PSPT_NLC100_2018_19_E_R000_071 DC Earthing for PV Array & SCB- GA and Layout Approval Electrical TN709 Earthing

PSPT_NLC100_2018_19_E_R000_072 AC DB - GTP, GA, vendor documents, SLD & Schematics Approval Electrical TN709 Aux. Supply

PSPT_NLC100_2018_19_E_R000_073 AC DB - MQP Approval Electrical TN709 Aux. Supply

PSPT_NLC100_2018_19_E_R000_074 SCADA - Configuration /Architecture Diagram with list of I/O signals Approval Electrical TN709 SCADA 12.02.2019 13.02.2019 13.02.2019 18.02.2019 23.02.2019 23.02.2019 26.02.2019 26.02.2019
PSPT_NLC100_2018_19_E_R000_075 SCADA - Vendor Documents, GA drawing & Schematics Approval Electrical TN709 SCADA

PSPT_NLC100_2018_19_E_R000_076 SCADA - MQP Approval Electrical TN709 SCADA 15.02.2019 18.02.2019


PSPT_NLC100_2018_19_E_R000_077 Control and Communication Cables - GTP, GA and vendor documents Approval Electrical TN709 Comm Cables

PSPT_NLC100_2018_19_E_R000_078 Control and Communication Cables - MQP Approval Electrical TN709 Comm Cables

PSPT_NLC100_2018_19_E_R000_079 Control and Communication Cables - Schedule Information Electrical TN709 Comm Cables

PSPT_NLC100_2018_19_E_R000_080 IP Telecom System - Block Diagram, GTP, GA & Vendor Documents Approval Electrical TN709 IP Telecom

PSPT_NLC100_2018_19_E_R000_081 Weather monitoring System - GTP, GA and vendor documents Approval Electrical TN709 WMS

PSPT_NLC100_2018_19_E_R000_082 Weather monitoring System - MQP Approval Electrical TN709 WMS

PSPT_NLC100_2018_19_E_R000_083 Fire Detection Alarm System - MFA panel & Repeater panel and other accessories - GTP, GA, Approval Electrical TN709 FDA
Schematic Diagram , Layout vendor documents.
PSPT_NLC100_2018_19_E_R000_084 Fire protection system - DCP fire extinguisher and Clean agent gas extinguishing system etc. - GTP and Information Electrical TN709 FDA
vendor documents
PSPT_NLC100_2018_19_E_R000_085 ABT Metering System with CT and PT for each O/G feeders @ PESS - GTP, GA and Scheme, Type test Approval Electrical TN709 Metering
certificates
PSPT_NLC100_2018_19_E_R000_086 ABT Metering System with CT and PT - MQP Approval Electrical TN709 Metering

PSPT_NLC100_2018_19_E_R000_087 AC Works - FQP Approval Electrical TN709 Field 30.01.2019 07.02.2019 15.02.2019 18.02.2019
PSPT_NLC100_2018_19_E_R000_088 DC Works - FQP Approval Electrical TN709 Field 30.01.2019 07.02.2019 15.02.2019 18.02.2019
PSPT_NLC100_2018_19_E_R000_089 TANGEDCO approved drawings for the Project - set 1 Information Electrical TN709 Evacuation

PSPT_NLC100_2018_19_E_R000_090 TANGEDCO approved drawings for the Project - set 2 Information Electrical TN709 Evacuation

PSPT_NLC100_2018_19_E_R000_091 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_092 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_093 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_094 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_095 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_096 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_097 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_098 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_099 For Future Use Approval Electrical TN709 Reserve

PSPT_NLC100_2018_19_E_R000_100 Contract Award volumes Information Electrical TN709 Contract

PSPT_NLC100_2018_19_C_R000_101 Topographical survey Approval Civil TN709 Preliminary civil 13.02.2019 21.02.2019
PSPT_NLC100_2018_19_C_R000_102 Overall plant layout Approval Civil TN709 Preliminary civil 24.01.2019 31.01.2019 12.02.2019 13.02.2019 24.02.2019 25.02.2019 27.02.2019
PSPT_NLC100_2018_19_C_R000_103 Soil investigation report Approval Civil TN709 Preliminary civil 20.11.2018 03.12.2018 08.01.2019 10.01.2019 21.01.2019 02.02.2019 06.02.2019 08.02.2019 10.02.2019 12.02.2019
PSPT_NLC100_2018_19_C_R000_104 Design Basis Report (DBR) - Civil works Approval Civil TN709 Preliminary civil 04.01.2019 11.01.2019 24.01.2019 29.01.2019
PSPT_NLC100_2018_19_C_R000_105 Field Quality Plan for Civil works (FQP) Approval Civil TN709 Preliminary civil 25.01.2019 06.02.2019 07.02.2019 12.02.2019
PSPT_NLC100_2018_19_C_R000_106 Internal road & Approach road cross section details Approval Civil TN709 Aux. Civil Structure 07.01.2019 18.01.2019 28.01.2019 29.01.2019 07.02.2019 12.02.2019
PSPT_NLC100_2018_19_C_R000_107 Peripheral road cross section details Approval Civil TN709 Aux. Civil Structure 07.01.2019 18.01.2019 28.01.2019 29.01.2019 07.02.2019 12.02.2019
PSPT_NLC100_2018_19_C_R000_108 Road layout Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_109 Peripheral Fencing Details Approval Civil TN709 Aux. Civil Structure 07.01.2019 21.01.2019 23.01.2019 28.01.2019
PSPT_NLC100_2018_19_C_R000_110 Fencing & Gate details for Inverter duty transformer Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_111 Overall fencing layout/coordinates Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_112 Main gate & wicket gate details Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_113 Stormwater drain layout Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_114 Storm water drain cross section details Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_115 Storm water drain design document Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_116 Security cabin - Architectural details Approval Civil TN709 Aux. Civil Structure 31.01.2019 05.02.2019 13.02.2019 15.02.2019 16.02.2019 20.02.2019
PSPT_NLC100_2018_19_C_R000_117 Security cabin - Foundation & Structural details Approval Civil TN709 Aux. Civil Structure 31.01.2019 06.02.2019 13.02.2019 15.02.2019 16.02.2019 18.02.2019
PSPT_NLC100_2018_19_C_R000_118 Security cabin - Septic tank & soak pit details Approval Civil TN709 Aux. Civil Structure 31.01.2019 05.02.2019 13.02.2019 21.02.2019
PSPT_NLC100_2018_19_C_R000_119 Security cabin - Coordinate layout Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_120 Watch Tower - Architectural details Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_121 Watch Tower - Foundation and structural details Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_122 Watch Tower - Coordinate layout Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_123 Two wheeler/Four wheeler Parking shed Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_124 Module Cleaning system - Design document Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_125 Module cleaning system - Pipeline netwrok details Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_126 Landscaping layout details Approval Civil TN709 Aux. Civil Structure

PSPT_NLC100_2018_19_C_R000_127 Sign board - Structure and foundation details Approval Civil TN709 Aux. Civil Structure 31.01.2019 05.02.2019
PSPT_NLC100_2018_19_C_R000_128 Door, window, ventilator & rolling shutter details Approval Civil TN709 Aux. Civil Structure 28.02.2019 01.03.2019
PSPT_NLC100_2018_19_C_R000_129 Module Mounting Structure - Design document Approval Civil TN709 MMS 03.01.2019 09.01.2019 19.01.2019 25.01.2019 28.01.2019 30.01.2019
PSPT_NLC100_2018_19_C_R000_130 Module Mounting Structure (MMS)- General Arrangement details (Type I) Approval Civil TN709 MMS 03.01.2019 09.01.2019 19.01.2019 25.01.2019 29.01.2019 31.01.2019
PSPT_NLC100_2018_19_C_R000_131 Module Mounting Structure (MMS)- General Arrangement details (Type II) Approval Civil TN709 MMS

PSPT_NLC100_2018_19_C_R000_132 Module Mounting Structure (MMS)- General Arrangement details (Type III) Approval Civil TN709 MMS

PSPT_NLC100_2018_19_C_R000_133 MMS Coordinate layout Approval Civil TN709 MMS 26.02.2019 27.02.2019 27.02.2019 02.03.2019
PSPT_NLC100_2018_19_C_R000_134 Pile test report (Pullout and lateral load test) Approval Civil TN709 MMS 02.01.2019 04.01.2019 04.01.2019 05.01.2019 23.01.2019 29.01.2019 29.01.2019 30.01.2019
PSPT_NLC100_2018_19_C_R000_135 MMS - Fabrication details (Type I) Approval Civil TN709 MMS 21.01.2019 28.01.2019 28.01.2019 31.01.2019 25.02.2019 26.02.2019
PSPT_NLC100_2018_19_C_R000_136 MMS - Fabrication details (Type II) Approval Civil TN709 MMS

PSPT_NLC100_2018_19_C_R000_137 MMS - Fabrication details (Type III) Approval Civil TN709 MMS

PSPT_NLC100_2018_19_C_R000_138 Module Mounting Structure (MMS)- Foundation details Approval Civil TN709 MMS 30.01.2019 05.02.2019 13.02.2019 14.02.2019 15.02.2019 16.02.2019
PSPT_NLC100_2018_19_C_R000_139 MMS- Manufacturing Quality Plan (MQP) Approval Civil TN709 MMS 08.02.2019 12.02.2019 15.02.2019 18.02.2019
PSPT_NLC100_2018_19_C_R000_140 MMS- Field Quality Plan for Civil works (FQP) Approval Civil TN709 MMS 25.01.2019 05.02.2019 11.02.2019 14.02.2019
PSPT_NLC100_2018_19_C_R000_141 PCSS Building - Design document Approval Civil TN709 PCSS/PEB

PSPT_NLC100_2018_19_C_R000_142 PCSS - Coordinate layout Approval Civil TN709 PCSS/PEB

PSPT_NLC100_2018_19_C_R000_143 PCSS Building- Architectural details Approval Civil TN709 PCSS/PEB 23.02.2019 25.02.2019
PSPT_NLC100_2018_19_C_R000_144 PCSS Building - Foundation details Approval Civil TN709 PCSS/PEB

PSPT_NLC100_2018_19_C_R000_145 PCSS Building - Structural details Approval Civil TN709 PCSS/PEB

PSPT_NLC100_2018_19_C_R000_146 PCSS Building - Cable Trench details Approval Civil TN709 PCSS/PEB

PSPT_NLC100_2018_19_C_R000_147 PESS Building - Design document Approval Civil TN709 PESS 20.02.2019 25.02.2019
PSPT_NLC100_2018_19_C_R000_148 PESS - Coordinate layout Approval Civil TN709 PESS 26.02.2019 26.02.2019 26.02.2019 27.02.2019 27.02.2019 28.02.2019
PSPT_NLC100_2018_19_C_R000_149 PESS Building- Architectural details Approval Civil TN709 PESS 06.02.2019 08.02.2019 16.02.2019 18.02.2019
PSPT_NLC100_2018_19_C_R000_150 PESS Building - Foundation details Approval Civil TN709 PESS 20.02.2019 25.02.2019 27.02.2019 01.03.2019
PSPT_NLC100_2018_19_C_R000_151 PESS Building - Plinth beam details Approval Civil TN709 PESS 26.02.2019 28.02.2019
PSPT_NLC100_2018_19_C_R000_152 PESS Building - Staircase details Approval Civil TN709 PESS 26.02.2019 02.03.2019
PSPT_NLC100_2018_19_C_R000_153 PESS Building - Lintel beam & roof beam details Approval Civil TN709 PESS

PSPT_NLC100_2018_19_C_R000_154 PESS Building - Roof slab details Approval Civil TN709 PESS

PSPT_NLC100_2018_19_C_R000_155 PESS Building - Septic tank & soak pit details Approval Civil TN709 PESS 26.02.2019
PSPT_NLC100_2018_19_C_R000_156 PESS Building - Cable trench details Approval Civil TN709 PESS

PSPT_NLC100_2018_19_C_R000_157 String Monitoring Unit (SMU) - Foundation & Structural details Approval Civil TN709 Elec. Equip. Support 01.03.2019 02.03.2019
PSPT_NLC100_2018_19_C_R000_158 Weather Monitoring Unit (WMU) - Foundation details Approval Civil TN709 Elec. Equip. Support

PSPT_NLC100_2018_19_C_R000_159 Inverter Duty Transformer (IDT) - Foundation details & Burnt oil pit details. Approval Civil TN709 Elec. Equip. Support

PSPT_NLC100_2018_19_C_R000_160 Auxilliary Transformer - Foundation details Approval Civil TN709 Elec. Equip. Support 26.02.2019 27.02.2019
PSPT_NLC100_2018_19_C_R000_161 Firewall details Approval Civil TN709 Elec. Equip. Support

PSPT_NLC100_2018_19_C_R000_162 Lighting post foundation details Approval Civil TN709 Elec. Equip. Support

PSPT_NLC100_2018_19_C_R000_163 Lightning Arrestor foundation details Approval Civil TN709 Elec. Equip. Support 23.02.2019 25.02.2019
PSPT_NLC100_2018_19_C_R000_164 MMS Fabrication Details - Front leg/Back leg Approval Civil TN709 Future Civil 29.01.2019 30.01.2019
PSPT_NLC100_2018_19_C_R000_165 MMS Manufacturing Quality Plan (for TATA) Approval Civil TN709 Future Civil 08.02.2019 12.02.2019 19.02.2019 20.02.2019
PSPT_NLC100_2018_19_C_R000_166 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_167 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_168 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_169 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_170 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_171 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_172 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_173 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_174 For Future Civil Use Approval Civil TN709 Future Civil

PSPT_NLC100_2018_19_C_R000_175 For Future Civil Use Approval Civil TN709 Future Civil