RFD Report
RFD Report
1 Narendra New (GIS) to Pune 765 kV Adani D/C 765 637 Sep-25 795 565 383 59.92 RoW (148 loc )
D/c Line (ISTS Network Expansion a) Sangli District (5), Solapur District (3),
scheme in Western Region & Southern Satara District (3), Pune District (83) in
Region for export of surplus power Maharashtra State
during high RE scenario in Southern b) Vijaypura District (54) in Karnataka
Region) district.
2 NK – Gaya 400 kV D/c line (Immediate Adani D/C 400 196 Dec-25 285 267 229 55.72 Forest: Tree Cutting Permission awaited
evacuation for North Karanpura under Chatra North Forest Division 61.7
(3x660 MW) generation project of NTPC (Ha), 5 Locations affected in Chatra North &
(ERSS XIX) 4 locations in Latehar Forest Division 15.3
(Ha). Support required for expediting the
pending approval of tree cutting
permissions from Govt of Jharkhand (DFO,
Chatra North).
3 KPS2 (GIS) to Halvad 765 kV D/C Line Adani D/C 765 492 Dec-25 690 324 159 8.34 ROW- 127 Loc's under Morbi District
(Transmission System for evacuation of (Tehsils- Morbi, Maliya) Order under section
additional 7 GW RE Power from 16 (1) is pending,
Khavda RE Park under Phase-III Part ROW- 102 Loc's under Kutch district (Tehsil-
A) Bhuj & Bacchau). Order under section 16
(1) is pending.
Forest (266.6997 Ha, 91 locs) in Gujarat
State.
Wildlife (36.6493 Ha, 16 locs.) in Gujarat
State.
4 LILO of Lakadia – Ahmedabad 765 kV Adani D/C 765 68 Dec-25 102 52 6 0 ROW- 50 Loc's Order under section 16 (1) is
D/c line at Halvad (Transmission pending.
System for evacuation of additional 7 Intervention required for ROW resolution
GW RE Power from Khavda RE Park
under Phase-III Part A)
5 Polavaram to Guddigudem line APTRANSCO D/C 400 48 Jun-25 Dec-25 72 68 67 40 i) 3No. Location in Forest Region (Loc Nos.
7, 8 & 11). Approval from Forest authorities
is under process.
ii) Loc No. 9/1 (River Crossing): Tower
structure design approved, procurement of
Tower parts under process.
6 LILO of both ckts of Vemagiri - APTRANSCO M/C 400 102 Jun-25 Dec-25 90 89 82 26 Line will be completed by June-2025 but
Sattenapalli line at Gudiwada SS could be charged only after completion of
connected (Gudiwada SS) SS which will get
delayed to Dec-25 as ICT is yet to be
received at site.
7 Hindupur to Pampanurthanda line APTRANSCO D/C 220 148 Jun-25 268 262 254 117 Severe ROW in 4 locations for laying Tower
Foundation (i.e, 8/0, 9/1, 11/3, 11/7)
8 LILO of both ckts of Gudivada (220 kV APTRANSCO M/C 220 38 Dec-25 Jun-26 63 41 41 0 1) RoW issues arised for 17 Nos. locations
SS)-Akiveedu-Bhimavaram line at and farmers had filed W.P.No.503, 4469 at
Gudivada (400 kV SS) High Court.
9 Fatehgarh 3- Bhadla-3 400 kV D/C Apraava D/C 400 446 Sep-25 564 364 202 36.20 RoW (91 loc.): Barmer (8), Jaisalmer (61),
line (Transmission system for Energy Phalodi (22) in Rajasthan State
evacuation of power from REZ in Forest (22.2778, 8.966ckm) in Rajasthan
Rajasthan (20 GW) under phase III Stage I Pending Applied on 31.07.2024
–Part A3) (SPV: Fatehgarh-III Proposal found complete during 43rd PSC
Transmission Ltd.) Meeting on 24.02.2025.
PSC recommed to DCF for completion of
Part II.
Current Status : Pending at DFO/CF/Nodal
Officer after acceptance in PSC-I
Sl.No. Name of Transmission Lines CPSU's/Priv Circuits Voltage Total line Targeted Revised Total Foundation Tower Stringing Remarks/Reason for delay
ate (S/C)/ Level length (in COD Anticipated Tower completed Erected completed
Developer/S (D/C)/( (kV) ckm) COD (as on Locations (Nos.) (Nos.) (ckm)
tate M/C) 30-04-2025)
Transco's
10 Fatehgarh-4 PS- Fatehgarh-3 PS 400 Apraava D/C 400 42 Jun-25 61 33 19 0.00 25 RoW locs: Barmer (25)
kV D/c line (Transmission system for Energy Forest (1.6054 Ha, 5 locs, 0.7 ckm ) in
evacuation of power from REZ in Rajasthan
Rajasthan (20 GW) under phase III Stage I pending. Applied on 30.09.2024
–Part A1) (SPV: Fatehgarh-IV EDS replied on 01.01.2025. Presently
Transmission Ltd.) pending at Technical Officer IRO from
02.04.2025
17 Raipur pool (PGCIL 765 kV SS) - CSPTCL D/C 220 119 Sep-25 Sep-25 208 124
Gendpur (Kawardha) line
18 Raipur pool (PGCIL 765 kV SS) - CSPTCL D/C 220 89 Sep-25 Sep-25 155 73
Bemetara line
19 Bilaspur Pool (PGCIL, Sipat) - Dhardehi CSPTCL D/C 400 100 Oct-25 Oct-25 174 77 9
line
20 Raita-Daldalseoni line CSPTCL D/C 220 55 Dec-25 Dec-25 91 79 39
21 LILO of MTPS (A) - Borjora line at MTPS DVC M/C 220 86 May-25 May-25 76 76 76 86 All works completed. CEA clearance
(B) received. Stage - II Forest Clearance
received. Awating charging clearance from
Department of Forest, Govt. of West Bengal
24 Gavasad - Salejada line GETCO D/C 220 194 May-25 326 319 307 165.39 Severe RoW issuE. Work to be executed in
Police Protection.Work in progress
25 Motigop Babarzar line (AP 7 to Motigop GETCO D/C 220 32 Dec-25 57 41 32 0 Row issue. Collector order awaited for 6 nos
gantry)(from Babarzar to AP 7 charged of locations in Devbhumi Dwarka &
by connecting to stopgap SS) ) Jamnagar District
26 Balance work of Vadavi - halvad Line GETCO D/C 400 149 Dec-25 214 190 188 118.608 Collector Order awaited for 3 nos of
(PACKAGE-2) (AP-41 to Halvad) locations in Morbi district (Hearing done)
27 Varsana - Halvad line GETCO D/C 400 240 Dec-25 360 348 347 167.788 Severe RoW issue. Work to be executed
under Police & SRPF protection. Work in
progress
28 LILO of one circuit of Amreli - Dhasa GETCO D/C 220 78 Jun-25 133 129 95 17.08 Severe RoW issue. Work to be executed
line at Gariyadhar S/S under Police.Collector Order awaited for 3
nos of locations.Work in progress
29 LILO of one ckt of Soja - Zerda line at GETCO D/C 400 61 Jul-25 94 94 84 7.938 Work in progress
Sankhari (Veloda 400 kV S/s)
30 Shapar - Pachcham (Fedra) Line (GEC- GETCO D/C 400 200 Jun-25 302 290 287 139.8 Severe ROW Issue in various Villages like
I) Vantavachchh, Khandiya, Zinzavadar,
Bhanejada, Sudamda and Adval.
Mostly collector & SP Order received for
ROW issue. In some villages work initated
with police protection however severe
objection from land owners due to change of
name (land ownershipe disputes), support
required from DILR committee. And in some
villages Police Protection availed but work
could not possible due to heavy
hindrance.Work dealyed due to Monsoon.
Work in progress
31 Botad - Chorania line GETCO D/C 220 103 Jun-25 170 166 151 64.56 Delay due to Severe RoW issue
32 Shapar - Ghiyavad line GETCO D/C 220 85 Jun-25 151 132 127 47.216 Delay due to Severe RoW issue
Sl.No. Name of Transmission Lines CPSU's/Priv Circuits Voltage Total line Targeted Revised Total Foundation Tower Stringing Remarks/Reason for delay
ate (S/C)/ Level length (in COD Anticipated Tower completed Erected completed
Developer/S (D/C)/( (kV) ckm) COD (as on Locations (Nos.) (Nos.) (ckm)
tate M/C) 30-04-2025)
Transco's
33 LILO of both circuits of Shapar - GETCO D/C 220 42 Oct-25 43 36 23 0 Delay due to Severe RoW issue
Babara line at Kamlapur (220 kV
SS)(GEC-II)
34 LILO of Tepla - Madanpur line and HVPNL M/C 220 103 May-25 June-25 128 128 125 75.6 Delay was mainly due to ROW issue in
Tepla -Raiwali line at Sadhaura SS racheri village from T.L No 1 to T.L No 7.
Now Row has been resolved and tentevily
all the work will be completed by June 2025
35 Panchkula (400 kV PGCIL SS) to HVPNL D/C 220 72 Jul-25 Jul-25 163 141 84 6.8 Delay was mainly due to ROW issue in
Sadhaura SS Rihod, Khatioli , haripur etc village from T.L
No 13 to T.L No 37 .Now the work on these
locations have been started and tentevily
will be completed by july 25
36 Sonipat SS (PGCIL) to IMT Pocket-A, HVPNL D/C 220 44 May-25 Jun-25 89 89 82 10.78 Grap Imposed during Nov/Dec 2024. Forest
Kharkhoda Clearance is pending.
37 Bahadurgarh SS (PGCIL) to IMT Pocket- HVPNL D/C 220 56 Jan-26 Jan-26 106 44 26 0 RoW issues at few locations. Grap Imposed
B, Kharkhoda during Nov/Dec 2024. Forest Clearance is
pending. One NHAI Clearance is pending.
38 Bhiwani (765 kV PGCIL SS) to Isherwal HVPNL D/C 220 100 Jun-25 Sep-25 212 209 193 37.8 Delay due to Severe RoW issue. Work is
(220 kV SS) stopped due Row in Village Nimriwali
39 Prithla (400 kV SS) to Sector 78, FBD HVPNL D/C 220 59 Jun-25 Jul-25 169 168 144 3.182 1. ROW issues created by farmers of
(220 kV SS) Villages Bukharpur, Nawada, Tigaon,
Dayalpur.
2. Slow progress by firm.
Work is being executed with the help of
District administration and police
protection.
40 Creation of 220 kV D/C overhead line HVPNL D/C 220 42 Dec-25 Mar-26 83 59 6 Nil Slow progress by the firm and RoW issues
on M/C & D/C towers from 400 kV at certain tower locations. RoW issues being
ISTS substation Prithla to 220 kV resolved with the help of District
substation Harfali with Line length on Administration.
D/C 21 km Line length of M/C 19 km.
41 Along with LILO of one circuit at 220 HVPNL M/C 220 38 Dec-25 Mar-26 143 116 0 Nil Slow progress by the firm and RoW issues
kV substation Meerpur Kurali on M/C at certain tower locations. RoW issues being
& D/C towers resolved with the help of District
Administration.
42 Bhadson (800 kV SS) to Ramana HVPNL D/C 220 47 Aug-25 112 112 112 19 At present, the line construction work is
Ramani SS underway, and according to the contract,
this work will be completed by 04.08.2025.
43 LILO of both circuits of Kirori – Jind HVPNL M/C 220 80 Mar-26 Mar-26 79 57 -- -- Work is expected to be completed as
line at Petwar SS on M/C towres schediled.
62 LILO of one ckt of Kanhan- Umred line MSETCL D/C 220 22 Jun-25 38 28 17 0 Work in progress
at Pachgaon SS
63 LILO of one ckt of Mhaisal-Jath at MSETCL D/C 220 45 May-25 78 76 71 25.276 Work in progress
Alkud (400 kV S/S)
Sl.No. Name of Transmission Lines CPSU's/Priv Circuits Voltage Total line Targeted Revised Total Foundation Tower Stringing Remarks/Reason for delay
ate (S/C)/ Level length (in COD Anticipated Tower completed Erected completed
Developer/S (D/C)/( (kV) ckm) COD (as on Locations (Nos.) (Nos.) (ckm)
tate M/C) 30-04-2025)
Transco's
64 Shikrapur (Pune) (PGCIL SS) - Khed MSETCL D/C 220 26 Nov-25 53 34 20 0 Work in progress
city SS (using the existing corridor of
Bableshwar- Ranjangaon)
65 Umred-Nagbhid line Part-II MSETCL D/C 220 50 Jun-25 94 92 90 28.64 Work in progress
66 LILO of Kolshet-Wada & Padghe-Wada MSETCL M/C 220 36 Mar-26 50 29 27 14.88 Forest approval awaited.
line at 400 kV Kudus S/s
67 LILO of one ckt of Beed - MSETCL D/C 220 36 Mar-26 65 17 0 0 Work in progress
Manjarsumbha at Sarul S/S
68 Dimapur - Zhadima line PD, D/C 220 120 Dec-25
Nagaland
69 LILO of TTPS -Joda Line at Keonjhar OPTCL D/C 220 27 Jul-25
GIS (Ranki)
70 Keonjhar (PGCIL SS) to Turumunga OPTCL D/C 220 34 Jun-25
GSS
71 LILO of Balimela-Malkangiri line at OPTCL D/C 220 75 Feb-26
Govindpalli
72 LILO of Bhanjanagar-Meramundali line OPTCL D/C 220 59 Dec-25
at Daspalla
73 LILO of 765 kV S/C MEERUT – POWERGRID S/C 765 68 Jun-25 97 85 84 45.21 RoW (12 loc.) in North Delhi District
BHIWANI line at NARELA
(Transmission system strengthening Forest Delhi (0.71 Ha, Nil locs, 19.6 Ckm):
scheme for evacuation of power from Pending Tree felling permission
solar energy zones in Rajasthan (8.1 Online proposal submitted on 14.10.23.
GW) under phase-II- Part G) SPV Stage-I received on 22.10.2024.
Name: POWERGRID Narela Stage-II received on 21.02.2025.
Transmission Ltd) Tree felling permission case in forest area
for both lines with CEC
1) CEC committee along with Nodal officer,
Delhi and DFO, North has done site visit on
24.02.2025 and requested to submit the
Geo-Tagged reference with different colour
code for Tree felling/Pruning /Non-Tree
felling and requisite map submitted on
04.03.2025.
2) On 24.03.2025, CEC, New Delhi has
submitted report to the Hon’ble Supreme
Court of India
3)Hearing in SC held on 08.04.25. During
hearing, SC has asked for submission of
compliance for conditions levied by CEC.
Main Condition is plantation of trees. SC
Order issued on 21.04.25. Details
submitted to CEC on 23.04.25.
74 KHETRI-NARELA 765 kV D/C Line POWERGRID D/C 765 340 Sep-25 463 412 362 166.57 RoW (49 loc.): Jhajjar District in Haryana.
(Transmission system strengthening RoW (14 locs.) inNorth West Delhi District
scheme for evacuation of power from
solar energy zones in Rajasthan (8.1 Forest Delhi (0.95 Ha, 3 locs, 82.58 Ckm):
GW) under phase-II- Part G) SPV Pending tree felling permission
Name: POWERGRID Narela Stage I received on 05.02.24, Stage-II
Transmission Ltd)) received on 19.02.2025. However, Tree
felling permission case in forest area for
both lines with CEC.
1) CEC committee along with Nodal officer,
Delhi and DFO, North has done site visit on
24.02.2025 and requested to submit the
Geo-Tagged reference with different colour
code for Tree felling/Pruning /Non-Tree
felling and requisite map submitted on
04.03.2025.
2) On 24.03.2025, CEC, New Delhi has
submitted report to the Hon’ble Supreme
Court of India
3)Hearing in SC held on 08.04.25. During
hearing, SC has asked for submission of
compliance for conditions levied by CEC.
Main Condition is plantation of trees. SC
Order issued on 21.04.25. Details
submitted to CEC on 23.04.25.
75 765 kV D/C KPS2-KPS3 line POWERGRID D/C 765 30 Apr-25 May-25 40 40 40 29.26 The Tx. Line is ready however work affected
(Establishment of Khavda Pooling due to delay in the supply of 765kV Gas
Station-3 (KPS3) in Khavda RE Park) Insulated Bus (GIB) and Gas Insulated
(SPV Name: POWERGRID KPS3 Switchgear (GIS) material for KPS2 S/s
TRANSMISSION LIMITED) subsequently the extension package for
KPS2-KPS3 line in KPS2 got delayed.
76 400 kV D/C Jeypore (POWERGRID)- POWERGRID D/C 400 136 Apr-25 May-25 173 173 156 104.00 Work affected due to :-
Jagdalpur (CSPTCL) line (Inter-regional (i)Change in rules related to land
ER-WR Interconnection) (SPV Name: compensation in Chhattisgarh
ER WR TRANSMISSION Ltd) (ii) Delay in approval of Forest Cleranace.
(iii) Delay in shutdown of 33KV & 11KV LT
Lines by state utilities.
77 Navsari (New) (South Gujarat)-Kala 400 POWERGRID D/C 400 283 May-25 Jun-25 454 412 405 411.06 Forest (24.62 Ha) in Maharashtra:
kV D/C line (Transmission Network Stage-I received on 30.08.2024
Expansion in Gujarat to increase its Working permission Received on
ATC from ISTS Part B) 25.11.2024
Stage-II received on 07.01.2025
Sl.No. Name of Transmission Lines CPSU's/Priv Circuits Voltage Total line Targeted Revised Total Foundation Tower Stringing Remarks/Reason for delay
ate (S/C)/ Level length (in COD Anticipated Tower completed Erected completed
Developer/S (D/C)/( (kV) ckm) COD (as on Locations (Nos.) (Nos.) (ckm)
tate M/C) 30-04-2025)
Transco's
78 NAVSARI (NEW) (SOUTH GUJARAT) POWERGRID D/C 765 452 Jun-25 Sep-25 616 577 399 57.596 Forest (305.476 Ha) in Maharashtra:
(GIS)-PADGHE (GIS) 765 kV D/C LINE Forest proposal re-submitted on
(Transmission Network Expansion in 23.11.2023.
Gujarat to increase its ATC from ISTS Stage -I received on 30.08.2024.
Part B) Working permission received on
11.10.2024.
Stage-II received on 07.01.2025.
79 765 kV D/C LAKADIA PS- POWERGRID D/C 765 369 Jun-25 476 464 204 77.40 RoW (15 loc.):
AHMEDABAD LINE (Transmission Kutch District (15) in Gujarat.
scheme for evacuation of 4.5 GW RE
injection at Khavda PS under Phase II- Forest Area (69.5597 Ha, 9 locs, 20.8 Ckm):
Part B (SPV Name: POWERGRID Proposal applied on 24.06.2023.
KHAVDA II-B TRANSMISSION Stage-I received on 05.11.2024.
LIMITED)) Stage-II received on 11.03.2025.
80 AHMEDABAD – SOUTH GUJARAT/ POWERGRID D/C 765 590 Jun-25 803 771 529 238.15 RoW (8 loc.):
NAVSARI (NEW) 765 kV D/C LINE Ahmedabad District (5), Surat District (2) &
(Transmission scheme for evacuation Navsari District (1) in Gujarat.
of 4.5 GW RE injection at Khavda PS
under Phase II- Part C (SPV Name: Forest (5.13 Ha):
POWERGRID KHAVDA II-C Proposal applied on
TRANSMISSION LIMITED)) 20.06.2023/28.01.2024.
Stage-I received on 05.11.2024.
Working permission received on
30.12.2024.
Stage-II received on 04.02.2025
81 REMOVAL of Lilo of Bawana- Mandola POWERGRID D/C 400 114 Sep-25 123 94 86 40.62 RoW (6 loc.):
line at Maharanibagh S/S and North Delhi District (6) in New Delhi.
extension of above Lilo from
Maharanibagh up to Narela S/S so as Forest:
to form 2x400 kV D/C Maharanibagh- North Delhi (5.188 Ha, 7 locs, 10 Ckm):
Narela line (Transmission System Stage-I Awaited
Strengthening Scheme for Evacuation 1) Online proposal submitted on
of Power from Solar Energy Zones in 10.11.2023. Revised proposal submitted
Rajasthan (8.1GW) under Phase-II-Part with forest area of 5.1642 ha on 14.11.24..
G1) PSC held on 26.12.24. Proposal
recommended. MoM issued on 02.01.25.
Proposal forwarded to DFO for Part II on
02.01.25.
2) Joint inspection done on 07.02.2025.
3) DFO (N) raised queries on 20.02.25 and
reply of the same submitted on 18.03.2025.
4) Proposal recommended in PSC II meeting
held on 15.04.25. Proposal forwarded to NO
on 17.04.25. NO forwarded proposal to SG
on 24.04.25. SG forwarded proposal to IRO
on 24.04.25.
82 RAMGARH (II)- BHADLA-3 765 D/C POWERGRID D/C 765 372 Sep-25 467 453 382 103.00 RoW (1 loc.):
LINE (Transmission system associated Phalodi District (1) in Rajasthan.
with LTA applications from Rajasthan
SEZ Phase-III Part-C1) (SPV: Rajasthan (49.45 Ha, 18 locs, 77km): Stage-
POWERGRID Ramgarh-II Transmission II Awaited
Ltd) Stage 1 clearence recieved on 07.03.2025 .
Working permission received on
11.04.2025.
Stage-II Awaited.
83 LILO of both ckts of AGRA–JAIPUR POWERGRID S/C 400 22 Sep-25 59 59 50 13.68 Work under progress
(SOUTH) 400 kV D/C at DAUSA
(Transmission system for evacuation of
power from REZ in Rajasthan (20 GW)
under Phase-III part H)( SPV:
POWERGRID Beawar
DausaTransmission Ltd))
84 LILO of both ckts of JAIPUR (PHAGI)- POWERGRID S/C 765 65 Sep-25 173 173 49
GWALIOR 765 kV D/C line at DAUSA
(Transmission system for evacuation of
power from REZ in Rajasthan (20 GW)
under Phase-III part H)( SPV:
POWERGRID Beawar Dausa
Transmission Ltd))
85 BEAWAR – DAUSA 765 kV D/C LINE POWERGRID D/C 765 474 Dec-25 634 561 377 127.30 Forest: (5.58 Ha, 02 locs, 2 Ckm): Working
(Transmission system for evacuation of permission Awaited
power from REZ in Rajasthan (20 GW) Stage-1 clearence recieved on 07.02.2025.
under Phase-III part H)(SPV: Payment details updated online on
POWERGRID Beawar Dausa 29.03.25. Compliance submitted to DFOs
Transmission Ltd)) on 03.04.25. DFO forwarded compliance to
CF on 17.04.25.
CF forwarded compilance to NO on
24.04.25.
Sl.No. Name of Transmission Lines CPSU's/Priv Circuits Voltage Total line Targeted Revised Total Foundation Tower Stringing Remarks/Reason for delay
ate (S/C)/ Level length (in COD Anticipated Tower completed Erected completed
Developer/S (D/C)/( (kV) ckm) COD (as on Locations (Nos.) (Nos.) (ckm)
tate M/C) 30-04-2025)
Transco's
86 765 kV BHADLA II-SIKAR II D/C line POWERGRID D/C 765 628 Sep-25 816 771 632 193.60 RoW (58 loc.):
(2ND) (Transmission system associated Phalodi District (1), Didwana Kuchaman
with LTA applications from Rajasthan District (3),
SEZ Part-E, Phase-II) (SPV: sikar District (54) in Rajasthan.
POWERGRID Bhadla Sikar
Transmission Limited))
87 765 kV D/C KURNOOL III (PS) POWERGRID D/C 765 504 Dec-25 674 674 428 87.586 RoW (19 loc.): Nandyal District (1) in Andhra
MAHESHWARAM (PG) LINE Pradesh, Nagarkurnool District (1) &
(Transmission System for Kurnool Rangareddy District (17) in Telangana.
Wind Energy Zone/ Solar Energy Zone
(AP) – Part-A & Part-B) Forest: 26.993 Ha. (Telangana)-Stage I
Awaited (8 loc., 8.04 Ckm)
Proposal submitted on 30.12.2023.
Pending at DFO due to EDS by Nodal
Officer as discussed in REC 31.01.2025.
Stage-I expected by 15th Mar,25.
88 BHADLA-III PS-SIKAR II 765 kV D/C POWERGRID D/C 765 648 Dec-25 846 734 464 80.22 RoW (130 loc.):
LINE (Transmission system for Bikaner District (21), Churu District (1),
evacuation of power from REZ in Didwana kuchaman District (22) & Sikar
Rajasthan (20 GW) under Phase-III District (86) in Rajasthan.
part B1)(SPV: POWERGRID Bhadla-3
Transmission Ltd) Forest (24.32 Ha, 5 locs, 25 km): Stage-I
Awaited
Proposal applied on 24.05.24. Proposal
recommended in PSC II on 24.02.25 and
proposal forwarded to NO on 28.02.25.
Proposal recommended in REC meeting on
29.04.25. MoM awaited.
89 KATHALGURI (NEEPCO)– NAMSAI (PG) POWERGRID D/C 220 142 Oct-25 221 221 221 142.00 Work completed. CEA inspection awaited.
220 kV D/C LINE (System
Strengthening Scheme for Eastern and
North Eastern Regions (ERSS-XXV &
NERSS-XV))(SPV Name: POWERGRID
ER NER Transmission Limited))
90 ANANTHPURAM PS - CUDDAPAH 400 POWERGRID D/C 400 368 Mar-26 491 401 279 48.00 RoW (26 loc.):
kV D/C LINE (Transmission scheme YSR kadapa District (21), Anantpur District
for Solar Energy Zone in Ananthpuram (5) in Andhra pradesh.
(Ananthapur) (2500 MW) and Kurnool
(1000 MW), Andhra Pradesh)
SPV: POWERGRID Ananthpuram
Kurnool Transmission Ltd))
91 ANANTHPURAM PS - KURNOOL-III POWERGRID D/C 400 167 Mar-26 222 188 84 RoW (4 loc.):
400 kV D/C LINE (Transmission Anantapur District (4) in Andhra pradesh.
scheme for Solar Energy Zone in
Ananthpuram (Ananthapur) (2500
MW) and Kurnool (1000 MW), Andhra
Pradesh
SPV: POWERGRID Ananthpuram
Kurnool Transmission Ltd))
92 765 kV D/C Banaskantha- POWERGRID D/C 765 270 Apr-25 Jun-25 362 361 352 114.08 Work was affected due to RoW issues,
Ahemadabad line (Transmission shortage of Tower Erection Gangs & Change
Network Expansion in Gujarat in rules related to land compensation.
associated with integration of RE
projects from Khavda potential RE
zone) (SPV: POWERGRID KHAVDA RE
TRANSMISSION LIMITED)
93 Koppal-II PS – Narendra (New) 765 kV POWERGRID D/C 765 237 Dec-25 308 139 5 RoW (86 loc.):
D/c line (Transmission Scheme for Koppal District (29), Vijaypura District (44),
integration of Renewable Energy Zone Bagalkote District (13) in Karnataka
(Phase-II) in Koppal-II (Phase-A & B)
and Gadag-II (Phase- A) in Karnataka) Karnataka, Koppal (0.657 Ha, Nil locs., 0.2
(SPV: POWERGRID Koppal II Gadag II Ckm)- Stage-I awaited
Transmission Ltd") Proposal applied on 16.06.2024. Part II
filled by DFO and proposal forwarded to NO
on 20.01.25. NO forwarded proposal to SG
on 06.02.25. SG forwarded proposal to IRO
on 22.04.25.
94 Gadag-II PS – Koppal-II PS 400 kV D/c POWERGRID D/C 400 77 Dec-25 104 35 3 RoW (53 loc.):
line (Transmission Scheme for Koppal District (46), Gadag District (7) in
integration of Renewable Energy Zone Karnataka
(Phase-II) in Koppal-II (Phase-A & B)
and Gadag-II (Phase- A) in Karnataka)
(SPV: POWERGRID Koppal II Gadag II
Transmission Ltd)
95 Koppal-II PS – Raichur 765 kV D/c line POWERGRID D/C 765 289 Dec-25 375 209 49 RoW (21 loc.):
(Transmission Scheme for integration Koppal District (19), Raichur District (2) in
of Renewable Energy Zone (Phase-II) in Karnataka
Koppal-II (Phase-A & B) and Gadag-II
(Phase- A) in Karnataka)(SPV:
POWERGRID Koppal II Gadag II
Transmission Ltd)
96 Halvad – Vataman 765 kV D/c line POWERGRID D/C 765 259 Dec-25 336 66 Gujarat (4.30 Ha, 1 loc, 1.28Ckm)-Stage-I
(Transmission System for evacuation of awaited
additional 7 GW RE Power from Proposal applied on 26.07.24.
Khavda RE Park under Phase-III Part IRO raised queries on 22.04.25 regarding
B) (SPV: POWERGRID Vataman CAF, Part III, area calculation sheet etc.
Transmission Ltd) Reply of same is under process & shall be
submitted shortly.
Sl.No. Name of Transmission Lines CPSU's/Priv Circuits Voltage Total line Targeted Revised Total Foundation Tower Stringing Remarks/Reason for delay
ate (S/C)/ Level length (in COD Anticipated Tower completed Erected completed
Developer/S (D/C)/( (kV) ckm) COD (as on Locations (Nos.) (Nos.) (ckm)
tate M/C) 30-04-2025)
Transco's
97 LILO of Lakadia – Vadodara 765 kV POWERGRID D/C 765 38 Dec-25 80 38 Gujarat (0.5424 Ha, Nil locs, 0.16Ckm)-
D/c line at Vataman 765 kV switching Stage-I awaited
station (Transmission System for Proposal applied on 31.05.24. DFO raised
evacuation of additional 7 GW RE multiple queries & reply of same was
Power from Khavda RE Park under submitted. DFO raised queries on
Phase-III Part B) (SPV: POWERGRID 01.04.2025. Reply of same is under process
Vataman Transmission Ltd) & shall be submitted shortly.
98 Vataman switching station – Navsari POWERGRID D/C 765 495 Dec-25 671 255 4 Gujarat (15.2371 Ha, 2 locs, 4.54 Ckm )-
(New)(GIS) 765 kV D/c line Stage-I awaited
(Transmission System for evacuation of Proposal applied on 27.05.24. Proposal
additional 7 GW RE Power from recommended in PSC I on 25.06.24. MoM
Khavda RE Park under Phase-III Part uploaded on 29.06.24 and proposal
B) (SPV: POWERGRID Vataman forwarded to DFO on 29.06.24. Part II filled
Transmission Ltd) by DFO.
Area revised from 5.7627 ha to 15.2371 ha
& revised proposal submitted for
consideration in PSC I meeting on 04.04.25.
99 Bikaner-II PS – Bikaner-III PS 400 kV POWERGRID D/C 400 62 Dec-25 84 21 15 i) Rajasthan,Bikaner (0.442 Ha, Nil locs,
D/c line (Transmission system for 0.5km) : Stage-I Awaited
evacuation of power from Rajasthan Proposal submitted on 23.07.24. Part II
REZ Ph-IV (Part-1) (Bikaner Complex): recommended by DFO and proposal
PART-A)(SPV: POWERGRID Bikaner III forwarded to NO on 05.12.24. NO raised
Neemrana Transmission Ltd) queries on on 23.12.24. Clarifications
submitted to NO on 07.02.25. Proposal
Pending at IRO.
100 Bikaner-III - Neemrana-II 765 kV D/c POWERGRID D/C 765 676 Dec-25 906 722 216 23.29 RoW (58 loc.):
line (Transmission system for Bikaner District (4), Churu District (11),
evacuation of power from Rajasthan Jhunjhunu (23), Mahendargarh (12),
REZ Ph-IV (Part-1) (Bikaner Complex): Kotputli behror(8) in Rajasthan.
PART-A)(SPV: POWERGRID Bikaner III
Neemrana Transmission Ltd) Forest
i) Haryana (0.8361 Ha,6 loc, 1 km): Stage-I
Awaited
Proposal submitted on 25.07.24. DFO
forwarded proposal to NO on 06.11.24. NO
raised queries on 17.01.25.Clarifications
forwarded by DFO to NO on 15.04.25.
101 LILO of both circuits of 400 kV Bikaner POWERGRID D/C 400 72 Dec-25 105 68 18 Work under progress
(PG)-Bikaner-II D/c line at Bikaner-III
PS (Transmission system for
evacuation of power from Rajasthan
REZ Ph-IV (Part-1) (Bikaner Complex):
PART-A)(SPV: POWERGRID Bikaner III
Neemrana Transmission Ltd)
102 Neemrana-II- Bareilly (PG) 765 kV D/c POWERGRID D/C 765 672 Dec-25 870 756 325 12.40 RoW (20 loc.):
line (Transmission system for Aligarh District (17), Bulandshar District (3),
evacuation of power from Rajasthan in UP
REZ Ph-IV (Part-1) (Bikaner Complex): Forest
PART-D)(SPV: POWERGRID Neemrana i) Rajasthan,Alwar (16.054 Ha,6 loc, 3km)
II Bareilly Transmission Ltd) Division: Stage-I Awaited
Proposal submitted on 15.06.24. Revised
proposal submitted on 14.01.25
recommended in PSC on 03.02.25. Proposal
discussed in PSC II forwarded to DFO for
modification in Part II on 17.04.25.
105 Sikar-II –Khetri 765 kV D/C line POWERGRID D/C 765 146 Aug-25 198 153 87 RoW (17 loc.):
(Transmission Scheme for Evacuation Neem Ka Thana District (10), Sikar District
of power from REZ in Rajasthan (20 (4) & Mahendargarh District (3) in
GW) under Phase-III Part D)(SPV: Rajasthan.
POWERGRIDSikar Khetri Transmission
Limited) Forest:
i)Rajasthan (29.82 Ha, 15 locs, 8km)- Stage-
I Awaited
Proposal submitted 22.07.24. PSC I held on
24.02.25.. Proposal discussed in PSC II on
15.04.25 and returned for correction in Part-
I as per DFO (Jhunjunu) observations in
part-II.
106 Bhadla-III - Bikaner-III 765 kV D/c POWERGRID D/C 765 256 Feb-26 330 3 Work under progress
line (Transmission System
Strengthening for interconnections of
Bhadla-III and Bikaner-III complex)
(SPV: POWERGRID BHADLA-III &
BIKANER-III TRANSMISSION LIMITED)
107 Mansa- Budhlada line PSTCL D/C 220 52 Aug-25 100 100 100 52 Work Completed line yet to be energised.
108 LILO of one ckt of Sadiq - Ferozpur line PSTCL D/C 220 22 Mar-26 38
at Jhoke Harihar (220 kV SS)
Upgraded from 66 kV to 220 kV)
109 Alwar (400 kV SS)- Sikri line RRVPNL D/C 220 106 Dec-25 168 97 18
111 LILO of Bhilwara -Beawer S/C line at RRVPNL D/C 220 28 Jun-25 49 41 15
Rayla (220 kV GSS)
112 Gadag PS- Koppal PS 400 kV D/c line Renew Power D/C 400 100 May-25 127 105 95 39.27 Foundation RoW (22 loc.): District Koppal -
(Transmission Scheme for Solar Energy Taluka Kuknoor (22 Loc). No work front
Zone in Gadag (1500 MW), Karnataka – available for foundation work since 5
Part-A, Phase-II) months
113 Mangalore (Udupi PCL) – Kasargode Sterlite D/C 400 231 Dec-25 278 167 134 6.18 1. Severe RoW issues (98 locs.) in
400 kV D/c line (Transmission System Karnataka: Dakshin Kannada (90 locs.),
for 400 kV Udupi (UPCL) – Kasargode Udupi (8 locs.).
D/C Line) 2. Row in Kerala: 88.4 ckm of stringing
affected due to non finalisation of land
compensation order by Govt. of Kerala.
115 Fatehgarh 3– Beawar 765 kV D/c line Sterlite D/C 765 635 Jul-25 806 717 455 134.44 1. Severe RoW issues (54 locs.) in
(Transmission System for Evacuation Rajasthan: Balotra (12 locs), Barmer (39
of Power from REZ in Rajasthan locs.), Jodhpur (3 locs.),
(20GW) under Phase-III Part F)
2. Forest (10.89 Ha, 4 locs, 3.26 cKm) in
Rajasthan: Stage II awaited. WP & TCP
pending. Delay in grant of FRA Certificates
by District administration of Jodhpur
district is delaying the grant of WP & TCP.
Stage I received on 05-07-2024.
116 LILO of both circuits of Ajmer – Sterlite D/C 765 136 Jul-25 178 168 118 0.00 Forest (22.66 Ha, 7 locs, 6.76 cKm) in
Chittorgarh 765 kV D/c at Beawar Rajasthan: Stage II awaited
(Transmission System for Evacuation WP & TCP are pending.
of Power from REZ in Rajasthan Stage I received on 05-11-2024.
(20GW) under Phase-III Part F) Applied on 27-12-2023.
117 LILO of of Kota – Merta 400 kV D/c at Sterlite D/C 400 66 Jul-25 88 73 47 0.00 Delay in replacement of existing earthwire
Beawar (Transmission System for with OPGW in Kota -Merta TL by PGCIL.
Evacuation of Power from REZ in
Rajasthan (20GW) under Phase-III Part
F)
118 Neemrana-II -Kotputli 400 kV D/c line Sterlite D/C 400 88 Dec-25 126 92 59 5.00 1. Severe RoW issues (13 locs.) in
(Quad) (Transmission system for Rajasthan: Kotputli-Behror (13 locs.) on
evacuation of power from Rajasthan account of demand for higher compensation
REZ Ph-IV (Part-1) (Bikaner Complex): or route diversion.
PART-B)
2. Forest (8.39 Ha, 6 locs, 7.09 cKm ) in
Rajasthan
119 LILO of both ckts of 400 kV Gurgaon Sterlite D/C 400 380 Dec-25 528 348 70 0.00 1. Severe RoW issues (10 locs.) in
(PG) - Sohna Road (GPTL) D/c line Rajasthan: Khairthal-Tijara (10 locs) on
(Quad) at Neemrana-II S/s account of demand for higher compensation
(Transmission system for evacuation of or route diversion.
power from 2. Severe RoW issues (3 locs.) in Haryana:
Rajasthan REZ Ph-IV (Part-1) (Bikaner Nuh (3 locs) on account of demand for
Complex): PART-B) higher compensation or route diversion.
120 Manali-Thervoikandigai 400 kV DC TANTRANSC D/C 400 73 May-25 May-25 104 104 104 73 Work completed. SRLDC clearance awaited
Line O to energise the line.
121 LILO of one ckt of Sunguvachatram- TANTRANSC D/C 400 33 Mar-26 Mar-26 Cable Laying work. 24/33sections
Alamaty feeder at Parivakkma village O completed. Work carried out whenever
in Guindy (UG Cable) workfront available after clearance from
CMRL.
122 Thiruvalam - S.P.Koil SC line TANTRANSC S/C 230 91.00 Mar-26 Mar-26 332 277 181 51.973 LC awaited to take up the work.
O
123 Unjanai SS to Nallur SS. TANTRANSC D/C 230 24.0 Oct-25 Oct-25 51 47 47 10.6 Work under progress
O
124 LILO of one circuit of Thappagundu- TANTRANSC D/C 400 40 Apr-25 Jun-25 60 60 60 36 RoW issue. Land Plan Survey(LPS) for 2 out
Anaikadavu line at Myvadi (udumalpet) O of 3 Nos. villages conducted.
(PGCIL SS) For the balance one village, severe protest
from land owners. Enter Upon awaited from
District Collector.
125 LILO of one ckt of Myvady - Kurukathi TANTRANSC D/C 230 46 Sep-25 Sep-25 100 99 95 41 Row issue. Land owners are demanding
line at Rasipalayam SS O land compensation prior to commencement
of work. Survey and compensation payment
under process.
126 LILO of one ckt of Kurukathi - TANTRANSC D/C 230 28 Sep-25 Sep-25 52 52 52 10.008 Row issue. Land owners of the line are
Palladam feeder at Rasipalayam SS. O demanding land &crop compensation
amount prior to commencement of further
work. 2.977 kms survey pending due to
land owners objection. District
administration's support requested to
complete the survey.
127 LILO of one ckt of Arasur –Ingur line at TANTRANSC D/C 230 31 Dec-25 Dec-25 70 67 66 23.52 RoW issues in 2 locations. Connected
Kalivelampatty 230 kV SS O (kalivelampatty) SS not ready.
128 LILO of one ckt of Abishekapatti - TANTRANSC D/C 230 40 Oct-25 Oct-25 84 84 84 40.16 Work completed. Connected SS work under
Udayathur feeder at Nanguneri SS O progress
129 Ariyalur to Thiruvalam ckt-I TANTRANSC S/C 765 175 Sep-25 Sep-25 Work completed. Awaiting for defective 765
O KV Reactor bushing replacement by M/s
BHEL
Sl.No. Name of Transmission Lines CPSU's/Priv Circuits Voltage Total line Targeted Revised Total Foundation Tower Stringing Remarks/Reason for delay
ate (S/C)/ Level length (in COD Anticipated Tower completed Erected completed
Developer/S (D/C)/( (kV) ckm) COD (as on Locations (Nos.) (Nos.) (ckm)
tate M/C) 30-04-2025)
Transco's
130 765 kV D/C Bikaner III Neemrana II Tata Power D/C 765 692 Dec-25 Dec-25 884 601 145 2 RoW (101 Loc.) : Bikaner (10 Loc), Churu (4
Transmission Line (2nd) (Transmission Loc), Sikar (4 Loc), Kotputli (4 Loc),
system for evacuation of power from JhunnJhunu (78 Loc) in Rajasthan State.
Rajasthan REZ Ph-IV (Part-1) (Bikaner Mahendrgarh (1 Loc)
Complex): PART-C)
Major ROW in Jhunjhunu (78 Locations) -
All resources demobilized and work
completely stopped at Jhunjhunu due to
local resistance (DLC rates unacceptable).
Additionally, Locations under ROW for
Tower Erection where foundations are
casted.
131 Koteshwar - Rishikesh 400 kV D/C Tata Power D/C 400 77 Sep-25 Sep-25 102 38 38 14.3 RoW Issue:
line (System strengthening in northern Tehri (1 loc- AP-22/0) - Administration help
region (NRSS XXXVI) along with LILO is sought to resolve the issue.
of Sikar-Neemrana 400 kV D/C line at Working Permission from Forest (103.5
Babai(RVPNL)) Ha):
1. Stage 1 Forest Clearance received on
29.10.2024
2. Demand Note from Uttarakhand Forest
department was received on 26.11.2024
3. Payment against the demand note was
done by NRSS on 30.11.2024.
4. However, Working permission is still
awaited.
5. Work in progress in non-forest area only
due to lack of Working permission.
PTCUL Final NOC
1.PTCUL on 18th March 2024 granted
Conditional NOC to NRSS XXXVI
Transmission Limited to start construction
work at their Rishikesh S/S.
2. However, final NOC from PTCUL to NRSS
XXXVI Transmission Limited is still awaited.
132 Yadadri TPP - Choutuppal TGTRANSCO D/C 400 185 Jun-25 259 259 258 130 severe ROW at Loc No 17/0 for erection of
tower & stringing works are under progress
133 Yadadri TPP - Jangaon TGTRANSCO D/C 400 278 Dec-25 402 384 298 44
134 Pulakurthy - Kakatiya Mega Textile TGTRANSCO D/C 220 60 Sep-25 110 105 103 47 Severe ROW issues at 4 Nos location for
Park laying foundation. Being pursued to resolve
the ROW issues
135 Veltoor - Yedula line TGTRANSCO D/C 400 94 Jun-25 139 139 139 94 All line works completed except SAS
integartion works at connecting bays at
Veltoor SS
136 Dichpally- YacharamThanda TGTRANSCO D/C 220 54 Jul-25 97 97 97 54
137 Vattem-Uddandapur line TGTRANSCO D/C 400 68 Mar-26 103 103 103 67.838 All works completed except stringing of line
from TT to Gantry at Uddandapur SS.
138 Maheshwaram - Uddandapur line TGTRANSCO D/C 400 121 Mar-26 179 179 179 120.36 All works completed except stringing of line
from TT to Gantry at Uddandapur SS.
139 LILO of Pirana (PG) – Pirana (T) 400 kV Torrent M/C 400 240 Jun-25 174 102 55 32 Severe ROW issues:
line at Ahmedabad S/s (Transmission •ROW (74 locs.) in Gujarat
scheme for evacuation of 4.5 GW RE • 43 RoW affected locations applied for
injection at Khavda PS under Phase II- Police Protection dt 17-03-2025 & order
Part D ) awaited at SP Ahmedabad.
• After the DM Order, two landowners ( loc.
no 21/3 &18/3) of Ahmedabad District
appealed to the High Court .Next Hearing on
dt 12-06-2025.
Bay upgradation work
• Outage required; however, due to system
constraints, WRLDC/SLDC has denied
permission until July 25.
140 Solapur PS – Solapur (PG) 400 kV D/c Torrent D/C 400 80 Mar-26 110 52 Severe ROW issues:
line (Transmission system for • Nos of Foundation Location : 26 Location
evacuation of power from RE projects in Solapur and Dharashiv District.
in Solapur (1500 MW) SEZ in
Maharashtra)
141 Mainpuri - Unnao line (Intra-state Tata Power S/C 765 194 Dec-25 477 473 424 131 Work is in progress.
TBCB)
142 Mainpuri - Bara line (Intra-state TBCB) Tata Power S/C 765 381 Jan-26 916 902 889 287 Work is in progress.
143 LILO of one ckt of Tanda - Basti Line at Tata Power D/C 400 168 Dec-25 225 200 174 40 Work is in progress.
Gonda (400 kV)(Intra-state TBCB)
144 Jalpura - THDC (Khurja Thermal) line Tata Power D/C 400 140 Dec-25 292 137 47 0 Work is in progress.
(Intra-state TBCB)
145 LILO of one ckt of Banda - Orai line at UPPTCL D/C 400 40 Jan-26 43 43 43 29.2 Line anti theft charged on 22.03.2025. LILO
Maheba (400 kV) (GEC-II) point connection is pending.
146 LILO of both ckt of Orai (765 kV PG UPPTCL M/C 400 212 Feb-26 313 313 54 7 Work in Progress
SS) - Orai line at Garautha (400 kV)
(GEC-II)
Sl.No. Name of Transmission Lines CPSU's/Priv Circuits Voltage Total line Targeted Revised Total Foundation Tower Stringing Remarks/Reason for delay
ate (S/C)/ Level length (in COD Anticipated Tower completed Erected completed
Developer/S (D/C)/( (kV) ckm) COD (as on Locations (Nos.) (Nos.) (ckm)
tate M/C) 30-04-2025)
Transco's
147 Jaitpur - Charkhari (220 kV) line (GEC- UPPTCL S/C 220 40 Sep-25 140 105 58 0 Work in Progress
II)
148 Kabrai - Charkhari (220 kV) Line (GEC- UPPTCL S/C 220 40 Sep-25 97 91 82 0.5 Work in Progress
II)
149 Charkhari - Garotha (400 kV) line UPPTCL D/C 220 134 Sep-25 222 125 0 0 Work in Progress
(GEC-II)
150 Dakaur - Maheba (400 kV) line (GEC- UPPTCL S/C 220 42 Sep-25 142 142 130 11.9 Work in Progress
II)
151 Bamaur - Garotha line (GEC-II) UPPTCL S/C 220 34 Jan-26 101 95 77 12.6 Work in Progress
152 Mandawra - Lalitpur (220 kV) line UPPTCL S/C 220 55 Feb-26 151 105 61 0 Work in Progress
(GEC-II)
153 Birdha - Lalitpur (220 kV) line (GEC-II) UPPTCL S/C 220 35 Feb-26 87 87 81 6.5 Work in Progress
154 Bangra - Garotha line (GEC-II) UPPTCL S/C 220 45 Feb-26 117 95 88 0 Work in Progress
155 Meerut - Mawana line UPPTCL D/C 220 36 Feb-26 56 55 54 34 Work is in progress.
156 LILO of one ckt of Sarnath (220 kV) - Megha D/C 220 59 Jan-26 98 30 0 0 Work is in progress.
Gajokhar line at Varanasi Cantt (220 Engineering
kV)(Intra-state TBCB)
157 Fatehpur (765 kV PG SS) - Khaga Megha D/C 220 48 Jan-26 86 33 0 0 Work is in progress.
Line(Intra-state TBCB) Engineering
158 LILO of one ckt of Mainpuri (220 kV) - Megha D/C 220 21 Jan-26 35 29 0 0 Work is in progress.
Bhauti (400 kV PG SS) line at Tirwa Engineering
(220 kV)(Intra-state TBCB)
159 Baram-Jauljivi Line PTCUL D/C 220 25 Apr-25
160 Maithon (400 kV PGCIL SS) to Asansol WBSETCL D/C 220 39 Mar-26 Mar-2026 73 66 60 6 Work under Progress
(220 kV SS)
161 LILO of one ckt of Domjur – Arambagh WBSETCL D/C 220 23 Jul-25 Jul-2025 47 47 47 22.336 The line was charged on 03.04.2025 in anti-
Line at Khanakul GIS (220 kV SS) theft measure from Arambag 400 KV
Substation.
162 STPS to Raghunathpur (220 kV SS) WBSETCL D/C 220 46 May-25 May-2025 94 94 94 46.292 Raghunathpur to STPS 220 KV D/C
(Upg) Transmission line with Zebra conductor has
been charged with 33 KV voltage source on
dated 23.09.2024. However, will be reported
in ach. when charged on rated voltage along
with connected SS.
Transformation Capacity (of 220 kV &
above) Targeted for FY 2025-26
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
1 Upgradation of Narendra New (GIS) to Adani 765/400 6000 Sep-25 95.00% 95.00% 89.00%
rated voltage of 765 kV alongwith 4x1500
MVA transformer (ISTS Network Expansion
scheme in Western Region & Southern
Region for export of surplus power during
high RE scenario in Southern Region)
2 Augmentation of transformation capacity Adani 765/400 500 Aug-25 5.00% ICT recieved at site
at 765/400 kV Lakadia S/s (WRSS XXI (A)
Transco Ltd.) in Gujarat-Part A (Bank 1)
3 Augmentation of transformation capacity Adani 765/400 500 Dec-25 0.00% 0.00% 0.00% Constraint in 2nd Transformer delivery
at 765/400 kV Lakadia S/s (WRSS XXI(A)
Transco Ltd.) in Gujarat-Part A (Bank 2)
4 Augmentation of 2x500 MVA, 400/230 kV Adani 400/230 1000 Jan-26 0.00% 0.00% 0.00% Delivery of ICTs scheduled in Nov’25
transformation capacity (3rd & 4th ICTs) at
Karur PS.
5 Augmentation of transformation capacity Adani 765/400 1500 Jul-25 100.00% 100.00% 95.00% Land required: NA
at KPS1 (GIS) by 1X1500 MVA, 765/400 kV 400KV GIS erections completed.
ICT (8th) on bus section-I 765KV GIS erection under progress
ICT Erection completed.
6 Kalapaka SS (Aug.) APTRANSCO 400/220 500 May-25 Oct-25 90 95 80 1) All major works completed. Metal spreading
works are under progress.
7 Gudivada SS APTRANSCO 400/220 1000 Dec-25 75 80 80 1) All structure Foundations and structure
erection works completed, Equipment erection
works under progress.
8 Rachagunneri SS (Aug.) (from 2*315 MVA APTRANSCO 400/220 500 Dec-25 90 80 60 i) All bay works completed.
to ii) Supply of ICT is under APTRANSCO scope.
2*315+1*500 MVA) iii) Transportation of ICT is halted due to
approach road problem.
iv) Construction of approach road is being taken
up with APTRANSCO CSR funds.
v) Tenders floated by Panchayat Raj Department
for laying of approcah road and awarded on
24.04.2025.
9 Racherla APTRANSCO 220/132 320 Dec-25 90 90 90 1) Due to pending court case of Sub-Station site
work was short closed and balance works
awarded to new agency on 29.11.2024.
10 Punganur (T/F-II) APTRANSCO 220/132 100 Dec-25 100 95 95 1. Charged with 1No. 100MVA PTR on
27.12.2024.
11 Dharmavaram APTRANSCO 220/132 200 Dec-25 80 95 95 90% of works completed. Contractor not
responding for arranging pre-commissioning test
works.
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
12 Pampanurtanda (GEC-I)(T/F-II) APTRANSCO 220/132 160 May-25 95 100 95 1. SS charged on 18.05.2023 without PTRs. PTR-
I Charged on 15.12.2023
13 Atchuthapuram APTRANSCO 220/132 200 Aug-25 65 75 75 1) 2 x 100MVA MVA PTRs to be supplied by the
Contractor. However, 1No. 220/132kV, 100MVA
released PTR from Kakinada SS was allotted by
APTRANSCO on 07.03.2025 in order to charge the
substation.Commissioning works are to be taken
up.
14 Vepakayaladibba APTRANSCO 220/33 100 Aug-25 45 60 50 1) Control room wall works under progress.
15 5x500 MVA, 400/220 kV pooling station at Apraava 400/220 2500 Jun-25 75.00% 97.00% 61.00% All land acquired (134.4 Acre, All Private)
Fatehgarh-4 (Transmission system for Energy
evacuation of power from REZ in Rajasthan
(20 GW) under phase III –Part A1)
(SPV: Fatehgarh-IV Transmission Ltd.)
34 220 kV Dhama (GEC-II) GETCO 220/66 320 Mar-26 47.00% 25.00% 0.00% Work in progress
35 220 kV Munjpur (GEC-II) GETCO 220/66 320 Mar-26 63.00% 40.00% 25.00% Work in progress
36 220 kV Maglana GETCO 220/66 320 Mar-26 95.00% 20.00% 15.00% Work in progress
37 400 kV Dholera GIS GETCO 400/220 1000 Mar-26 65.00% 10.00% 5.00% Work in progress
38 400 kV Kalawad GIS GETCO 400/220 1500 May-25 95.00% 100.00% 80.00% Work in progress
39 220 kV Mitha (Aug.) GETCO 220/66 100 Nov-25 100.00% Work in progress
40 400 kV Kansari (Aug.) GETCO 400/220 185 Mar-26 100.00% Work in progress
41 220 kV GIS Sector-89, Faridabad (2x100 HVPNL 220/33 200 Jul-25 Jul-25 87.00% 100.00% 85.00% Work in progress
MVA)
42 220 kV Sadhaura Ambala SS (2x100 MVA) HVPNL 220/66 200 Sep-25 Oct-25 95.00% 100.00% 95.00% The work was delayed due to non shifting of 11
KV feeders from substation location.Now 23 nos.
out of 28 nos. feeders have been shifted . The
substation work will temntevily be completed by
oct 2025
43 220 kV Sadhaura Ambala SS (1x100 MVA) HVPNL 220/33 100 Sep-25 Oct-25 95.00% 100.00% 95.00% The work was delayed due to non shifting of 11
KV feeders from substation location.Now 23 nos.
out of 28 nos. feeders have been shifted . The
substation work will temntevily be completed by
oct 2025
44 220 kV Chikenwas Hisar SS (2x100 MVA) HVPNL 220/33 200 Oct-25 Aug-25 40.00% 70.00% 14.00% 100 MVA 220/33 kV Power transformer has been
reached at site on dated 28.04.2025
45 220 kV GIS at Pocket A, IMT Kharkhoda HVPNL 220/33 200 Jul-25 Jun-25 72.00% 90.00% 44.00% Grap Imposed during Nov/Dec 2024.
Sonipat
(2x100 MVA)
46 220 kV GIS at Pocket B, IMT Kharkhoda HVPNL 220/33 200 Jun-25 Jun-25 87.00% 99.29% 55.00% Grap Imposed during Nov/Dec 2024.
Sonipat
(2x100 MVA)
47 220 kV Ramana-Ramani (Karnal) HVPNL 220/132 320 Jul-25 May-25 72.00% 99.00% 100.00% Delay to due work of AC Kiosks, C.R.B & ODCT
(2x160 MVA)
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
48 220 kV Ramana-Ramani (Karnal) HVPNL 220/33 200 Jul-25 May-25 72.00% 99.00% 100.00% Delay to due work of AC Kiosks, C.R.B & ODCT
(2x100 MVA)
49 220 kV GIS Sector-99 Gurugram (2x100 HVPNL 220/33 200 Oct-25 Jun-25 47.00% 95.00% 38.00% Delay in civil work by the firm & recent NGT Ban
MVA)
50 220 kV GIS Transport Hub, Sector-8 IMT HVPNL 220/66 100 Jun-25 100.00% 100.00% 100.00% 100 MVA Commissioned on 15.04.2025
Manesar (T/F-II)
51 220 kV Roj-Ka-Meo HVPNL 220/33 100 Sep-25 Dec-25 80% 80.00% 35.00% Previous turnkey contractor blacklisted. Now the
work is being executed departmentally.
52 220 kV Roj-Ka-Meo HVPNL 220/66 160 Oct-25 Dec-25 80% 80.00% 35.00% Previous turnkey contractor blacklisted. Now the
work is being executed departmentally.
53 220 kV Nain HVPNL 220/33 200 Dec-25 Dec-25 44.00% 10.00% 7.00% Work in progress
54 220 kV Nain HVPNL 220/132 320 Dec-25 Dec-25 44.00% 10.00% 7.00% work in progress
55 220 kV Dhanonda (Aug.) HVPNL 220/33 100 Sep-25 Mar-26 40.00% 0.00% 0 Detailed estimate is in progress on HEW Portal.
Transformer not supplied yet . Earlier the work
was to be executed on trunkey mode and
according BOQ was submitted. Later on , it was
decided to execute this work on departmental
mode . Subsequently, estimate has been framed
and detailed estimate is in progress on HEW
Portal.
56 220 kV Deroli Ahir (Aug.) HVPNL 220/33 100 Nov-25 Mar-26 80.00% 0.00% 0.00% Detailed estimate is in progress on HEW Portal.
Transformer not supplied yet . Earlier the work
was to be executed on trunkey mode and
according BOQ was submitted. Later on , it was
decided to execute this work on departmental
mode . Subsequently, estimate has been framed
and detailed estimate is in progress on HEW
Portal.
57 220 kV Sector-57, Gurugram (Aug.) HVPNL 220/33 100 Dec-25 Dec-25 Earlier work was planned to be excuted on
trunkey basis . But CE/PD&C, HVPNL Panchkula
vide memo no Ch-129/EPC-D-
106/XEN/Contracts dated 21.11.2024 intimated
that get the work done departmentally please as
decided by WTDs of HVPNL.
Matter taken up with Siemens for GIS Bay.
100MVA TF likely to be allocated in Dec2025.
58 220 kV Sector-20, Gurugram (Aug.)(100 to HVPNL 220/66 60 Jun-25 Aug-25 0% 50.00% 0% Transformers received at substation in April
160) 2025
59 220 kV Palla (Aug.) (100 to 160) HVPNL 220/66 60 Jun-25 100.00% 100.00% 100.00% Commissioned on 04.04.2025
60 220 kV Meerpur Kurali (Aug.) (100 to 160) HVPNL 220/66 60 Jun-25 Jun-25 0% 50.00% 0.00% Tender for execution of electrical and civil work
have been floated and scheduled to be opened on
09.05.2025.
61 220 kV A-4, Faridabad (Aug.)(100 to 160) HVPNL 220/66 60 Jun-25 Dec-25 50% 90.00% 0.00% T/F received on site, Work order issued.
62 220 kV Sector-46 Faridabad (Aug.) HVPNL 220/66 160 Aug-25 Mar-26 0.00% 0.00% 0.00% T/F is yet to be received.
63 220 kV Sector-32, Panchkula (Aug.) HVPNL 220/66 100 Oct-25 100.00% 100.00% 100.00% Commissioned on 28.03.2025 and also reported
in March-25 Ach. However, by the tym ach. report
for March-25 was submited by the utility, target
for FY 2025-26 was already finalized hence
included in the target.
64 220 kV PTPS Panipat (Aug.) (100 to 160) HVPNL 220/132 60 Mar-26 Dec-25 80.00% 0.00% 0.00% T/F is yet to be received.
65 400 kV Kirori (Aug.) (100 to 160) HVPNL 220/132 60 Nov-25 Dec-25 0.00% 0.00% 0.00% Work approved but not started yet due to non
availability of shutdown.
66 220 kV Bhuna (Aug.)(100 to 160) HVPNL 220/132 60 Sep-25 Dec-25 0.00% 0.00% 0.00% Work approved but not started yet due to non
availability of shutdown.
67 220 kV Kaul (Aug.)(Additional 160) HVPNL 220/132 160 Jan-26 Dec-25 0.00% 0.00% 0.00% T/F is yet to be received.
68 220 kV Nuna Majra (Aug.) (from 100 to HVPNL 220/132 60 Feb-26 Dec-25 0.00% 0.00% 0.00% T/F is yet to be received.
160)
69 Tahliwal GIS HPPTCL 220/132 100 Oct-25
71 Augmentation of transformation capacity Indigrid 400/220 315 Aug-25 80.00% 20.00% Civil work is progressing in full swing (ICT,
at Amargarh (GIS) S/s by 1x315MVA, Firewall, 400kV & 220 kV GIS bus duct
400/220 kV ICTs (3rd) (Augmentation of foundation & other equipment). GIS Supply done.
transformation capacity at Amargarh (GIS) Order for Supply of 315 MVA ICT placed with M/s
S/s) TELK (Manufacturing under Progress).
72 220/132/33 kV, 2X200 MVA Grid Sub- JUSNL 220/132/33 400 Sep-25
Station at Patratu
73 220/132/33,2x200 Grid Sub-Station at JUSNL 200/132/33 400 Jan-26
Baliyapur
74 220/132/33,2x200 Grid Sub-Station at JUSNL 200/132/33 400 Jan-26
Gomia
75 220/132/33 kV 2X15 +2x50 MVA Grid Sub- JUSNL 200/132 300 Jun-25
Station at Jainamore, Bokaro
76 Dudda: Establishing 1x100 MVA, 220/66 KPTCL 220/110 & 200 Dec-25
kV & 1X100 MVA, 220/110 kV substation 220/66
at Dudda, in Hassan Taluk& Hassan
District
82 Pathanamthitta KSEBL 220/110 100 Apr-25 May-25 99.00% 100.00% 100.00% Delay due to continuous rain at Pathanamthitta
area, Pathanamthitta GIS test charged from
110kV side on March 2025
83 Kakkad KSEBL 220/110 100 May-25 Jun-25 98.50% 100.00% 90.00% Delay due to continuous rain at Kakkad area
87 Barwaha (Aug. (220-160 MVA)) MPPTCL 220/132 40 Jun-25 40.00% 90.00% 0.00%
96 Mandideep GIS Substation (Intra-state Megha 400/220 1000 Dec-25 46.00% 5.00% 0.00% TBCB
TBCB) Engineering
97 Mandideep GIS Substation (Intra-state Megha 220/132 320 Dec-25 46.00% 5.00% 0.00% TBCB
TBCB)) Engineering
98 Bisonikala SS (Intra-state TBCB) Megha 220/132 320 Dec-25 32.00% 5.00% 0.00% TBCB
Engineering
99 Khargone SS (Intra-state TBCB) Megha 220/132 320 Dec-25 11.00% 0.00% 0.00% TBCB
Engineering
100 Shahpur SS (Intra-state TBCB) Megha 220/33 100 Nov-25 36.00% 5.00% 0.00% TBCB
Engineering
101 220/33 kV Pachgaon SS MSETCL 220/33 100 Jun-25 55% 70.00% 14.00% Work in progress
102 220/22 kV GIS s/s at Abhitghar MSETCL 220/22 100 Dec-25 99.00% 100.00% 95.00% Work in progress
103 220/22 kV Mankoli GIS substation MSETCL 220/22 100 Sep-25 92.00% 50.00% 30.00% Work in progress
104 220 kV Panchanand Taloja MSETCL 220/33 100 Dec-25 50.00% 20.00% 5.00% Work in progress
105 220/33 kV Sarul SS MSETCL 220/33 50 Mar-26 40.00% 5.00% 0.00% Work in progress
106 220/33 kV Deosane SS MSETCL 220/33 50 Mar-26 15.00% 0.00% 0.00% Work in progress
107 400 kV Thapti Tanda MSETCL 400/220 500 Dec-25 50.00% 60.00% 0.00% Work in progress
108 400 kV Nagothane MSETCL 400/220 500 Jun-25 80.00% 80.00% 50.00% Work in progress
109 220 kV Tilawani MSETCL 220/33 100 Jun-25 100.00% 100.00% 100.00% Commissioned on 28.03.2025 and also reported
in March-25 Ach. However, by the tym ach. report
for March-25 was submited by the utility, target
for FY 2025-26 was already finalized hence
included in the target.
110 220 kV Georai MSETCL 220/33 50 Mar-26 10.00% 0.00% 0.00% Civil work in progress
111 220 kV ONGC Panvel MSETCL 220/33 50 Dec-25 5.00% 50.00% 0.00% T/F received on site. Work in Progress
112 220 kV Vasai S/s MSETCL 220/22 50 Dec-25 80.00% 30.00% 5.00% Work in progress
113 220 kV Sayane S/s MSETCL 220/33 50 Dec-25 15.00% 0.00% 0.00% Work in progress
114 220 kV Tuljapur MSETCL 220/132 100 Dec-25 60.00% 60.00% 5.00% Work in progress
115 220 kV Malegaon (Zodga) MSETCL 220/132 100 Dec-25 0.00% 0.00% 0.00% LOA issued recently
116 220 kV Temghar MSETCL 220/22-22 50 Dec-25 0.00% 50.00% 0.00% T/F received on site.Tender under process for
ETC work
117 220 kV Anandnagar MSETCL 220/22 50 Mar-26 0.00% 0.00% 0.00% LOA will be issued shortly
118 220 kV Mahape MSETCL 220/22-22 100 Dec-25 0.00% 50.00% 0.00% T/F received on site.Tender under process for
ETC work
119 220 kV Kolshet MSETCL 220/22-22 50 Mar-26 0.00% 50.00% 0.00% T/F received on site.Tender under process for
ETC work
120 220 kV Bapgaon MSETCL 220/22 50 Mar-26 0.00% 0.00% 0.00% Tender under process for ETC work
121 220 kV Raymond MSETCL 220/33 25 Dec-25 0.00% 0.00% 0.00% Tender under process for ETC work
122 220 kV Alephata MSETCL 220/132 200 Mar-26 0.00% 0.00% 0.00% Tender under process for ETC & ICTs
procurement
123 220 kV Chakan-II MSETCL 220/132 200 Mar-26 0.00% 0.00% 0.00% Tender under process for ETC & ICTs
procurement
124 400 kV Lonikand-II MSETCL 220/132 200 Mar-26 0.00% 0.00% 0.00% Tender under process for ETC & ICTs
procurement
125 220 kV Bridgestone MSETCL 220/33 50 Mar-26 0.00% 0.00% 0.00% Tender under process for ETC & ICTs
procurement
126 220 kV Pirungut MSETCL 220/22 50 Mar-26 0.00% 0.00% 0.00% Tender under process for ETC & ICTs
procurement
127 220 kV Ranjangaon MSETCL 220/22 50 Mar-26 0.00% 0.00% 0.00% Tender under process for ETC & ICTs
procurement
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
128 400 kV Chakan MSETCL 220/22 50 Mar-26 0.00% 0.00% 0.00% Tender under process for ETC & ICTs
procurement
129 Parjang SS OPTCL 220/33 80 Mar-26
130 Dasapalla SS OPTCL 220/33 40 Dec-25
131 Balianta GIS OPTCL 220/132 320 Jun-25
132 New Duburi (3rd ICT) OPTCL 400/220 500 Jul-25
133 2X1500 MVA 765/400 kV ICT-1& 2 at POWERGRID 765/400 3000 Jun-25 99.00% 99.00% 99.00% Land acquired in Mar-23.
NARELA (Transmission system Ready for Charging
strengthening scheme for evacuation of
power from solar energy zones in
Rajasthan (8.1 GW) under phase-II- Part G
SPV Name: POWERGRID Narela
Transmission Ltd)
134 1X1500 MVA 765/400 kV ICT-3 at NARELA POWERGRID 765/400 1500 Sep-25 99.00% 99.00% 99.00% Land acquired in Mar-23.
(Transmission system strengthening Ready for Charging
scheme for evacuation of power from solar
energy zones in Rajasthan (8.1 GW) under
phase-II- Part G
SPV Name: POWERGRID Narela
Transmission Ltd)
135 1X1500 MVA, 765/400 kV ICT-1 at KPS- POWERGRID 765/400 1500 May-25 100.00% 100.00% 100.00% Commissioned in April-2025.
2(GIS) (Establishment of Khavda Pooling
Station-2 (KPS2) in Khavda RE Park (SPV:
POWERGRID KPS2 TRANSMISSION
LIMITED))
136 1X1500 MVA, 765/400 kV ICT-2 at KPS- POWERGRID 765/400 1500 May-25 98.00% 90.00% 80.00% Work under progress.
2(GIS) (Establishment of Khavda Pooling
Station-2 (KPS2) in Khavda RE Park (SPV:
POWERGRID KPS2 TRANSMISSION
LIMITED))
137 1X1500 MVA, 765/400 kV ICT-3 at KPS- POWERGRID 765/400 1500 Jun-25 98.00% 90.00% 80.00% Work under progress.
2(GIS)(Establishment of Khavda Pooling
Station-2 (KPS2) in Khavda RE Park (SPV:
POWERGRID KPS2 TRANSMISSION
LIMITED))
138 1X1500 MVA, 765/400 kV ICT-4 at KPS- POWERGRID 765/400 1500 Jul-25 98.00% 90.00% 80.00% Work under progress.
2(GIS)(Establishment of Khavda Pooling
Station-2 (KPS2) in Khavda RE Park (SPV:
POWERGRID KPS2 TRANSMISSION
LIMITED))
139 1X1500 MVA, 765/400 kV ICT-1 at KPS-3 POWERGRID 765/400 1500 May-25 98.00% 98.00% 80.00% Work under progress
SS (Establishment of Khavda Pooling
Station-3 (KPS3) in Khavda RE Park (SPV
Name: POWERGRID KPS3 TRANSMISSION
LIMITED))
140 1X1500 MVA, 765/400 kV ICT-2 at KPS-3 POWERGRID 765/400 1500 Jun-25 98.00% 98.00% 80.00% Work under progress
SS (Establishment of Khavda Pooling
Station-3 (KPS3) in Khavda RE Park (SPV
Name: POWERGRID KPS3 TRANSMISSION
LIMITED))
141 1X1500 MVA, 765/400 kV ICT-3 at KPS-3 POWERGRID 765/400 1500 Aug-25 98.00% 98.00% 80.00% Work under progress
SS (Establishment of Khavda Pooling
Station-3 (KPS3) in Khavda RE Park (SPV
Name: POWERGRID KPS3 TRANSMISSION
LIMITED))
142 1X1500 MVA 765/400 kV 4th ICT at POWERGRID 765/400 1500 Jun-25 95.00% 95.00% 75.00% Delayed due to unavilability of shutdown for
BIKANER SS (TS for evacuation of Power Shifting of Reactor. Reactor to ICT Foundation
from Rajasthan Phase-IV Part -I Bikaner Modification Under progress
Complex Part E)
143 1X500MVA,400/220 kV (3rd) ICT at POWERGRID 400/220 500 Jan-26 90.00% 90.00% 70.00%
KOTPUTLI (TS for evacuation of Power from
Rajasthan Phase-IV Part -I Bikaner
Complex Part E)
144 1X500 MVA, 400/220 kV ICT-2 at POWERGRID 400/220 500 May-25 Sep-25 95.00% 99.00% 85.00%
FATEHGARH-3 (NEW SECTION)
(Transmission system for evacuation of
power from REZ in Rajasthan (20GW)
under Phase-III Part E1- Given to PRTL
(POWERGRID Ramgarh Transmission
Limited)
145 1X500 MVA, 400/220 kV ICT-1 at POWERGRID 400/220 500 Jun-25 Sep-25 95.00% 99.00% 85.00%
FATEHGARH-3 (NEW SECTION)
(Transmission system for evacuation of
power from REZ in Rajasthan (20GW)
under Phase-III Part E1- Given to PRTL
(POWERGRID Ramgarh Transmission
Limited)
146 1X500 MVA, 400/220 kV ICT-3 at POWERGRID 400/220 500 Jul-25 Sep-25 95.00% 99.00% 85.00%
FATEHGARH-3 (NEW
SECTION)(Transmission system for
evacuation of power from REZ in Rajasthan
(20GW) under Phase-III Part E1- Given to
PRTL (POWERGRID Ramgarh Transmission
Limited)
147 1X1500 MVA, 765/400 kV ICT-1 at POWERGRID 765/400 1500 Apr-25 100.00% 100.00% 100.00% Commissioned in April-2025.
FATEHGARH-3 (NEW
SECTION)(Transmission system for
evacuation of power from REZ in Rajasthan
(20GW) under Phase-III Part E1- Given to
PRTL (POWERGRID Ramgarh Transmission
Limited)
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
148 2X1500 MVA, 765/400 kV ICT-2 & 3 at POWERGRID 765/400 3000 Sep-25 95.00% 99.00% 85.00%
FATEHGARH-3 (NEW
SECTION)(Transmission system for
evacuation of power from REZ in Rajasthan
(20GW) under Phase-III Part E1- Given to
PRTL (POWERGRID Ramgarh Transmission
Limited)
149 1X1500 MVA, 765/400 kV ICT-1 at POWERGRID 765/400 1500 Apr-25 Sep-25 45.00% 30.00% 20.00% Work affected due to delay in supply of ICT.
FATEHGARH-III (Transmission System for
Evacuation of Power from REZ in
Rajasthan (20GW) under Phase III- Part
E2)
150 1X1500 MVA, 765/400 kV ICT-2 at POWERGRID 765/400 1500 May-25 Sep-25 45.00% 30.00% 20.00% Work under progress
FATEHGARH-III (Transmission System for
Evacuation of Power from REZ in
Rajasthan (20GW) under Phase III- Part
E2)
151 2X500 MVA, 400/220 kV ICT -1 & 2 at POWERGRID 400/220 1000 Nov-25 45.00% 30.00% 20.00% Work under progress
FATEHGARH-III (Transmission System for
Evacuation of Power from REZ in
Rajasthan (20GW) under Phase III- Part
E2)
152 1X1500 MVA, 765/400 kV ICT -3 at POWERGRID 765/400 1500 Dec-25 Sep-25 45.00% 30.00% 20.00% Work under progress
FATEHGARH-III (Transmission System for
Evacuation of Power from REZ in
Rajasthan (20GW) under Phase III- Part
E2)
153 3X500 MVA 400/220 kV ICT-5, 8 & 9 at POWERGRID 400/220 1500 Dec-25 95.00% 98.00% 98.00% Work under progress
KURNOOL (III) PS (Transmission System
for Kurnool Wind Energy Zone/ Solar
Energy Zone (AP) – Part-A & Part-B)
154 1X1500 MVA, 765/400 kV ICT-3rd AT POWERGRID 765/400 1500 May-25 Jun-25 99.00% 99.00% 80.00% 1x1500 MVA ICT charged from 400KV side in
RAIGARH KOTRA SECTION B (Western April'25 but 765kV side not ready. Will be taken
Region Expansion Scheme-XXV (WRES- in achievement after completion of 765 kV also.
XXV))
155 1X1500MVA, 765/400 kV ICT-4th at POWERGRID 765/400 1500 Aug-25 99.00% 99.00% 80.00% 765 kV side not ready
RAIGARH KOTRA SECTION B GIS (Western
Region Expansion Scheme-XXV (WRES-
XXV)
156 3X500 MVA, 400/220 kV ICT-1, 2 & 3 at POWERGRID 400/220 1500 Sep-25 90.00% 75.00% 45.00% Land Acquired in Jul'2024
RAMGARH (II) (Transmission system
associated with LTA applications from
Rajasthan SEZ Phase-III Part-C1) SPV:
POWERGRID Ramgarh-II Transmission
Ltd)
157 2X1500 MVA, 765/400 kV ICT-1 & 2 at POWERGRID 765/400 3000 Sep-25 90.00% 75.00% 45.00% Land Acquired in Jul'2024
RAMGARH (II) (Transmission system
associated with LTA applications from
Rajasthan SEZ Phase-III Part-C1, SPV:
POWERGRID Ramgarh-II Transmission
Ltd))
158 1X500 MVA, 400/220 kV ICT (5TH) at POWERGRID 400/220 500 Aug-25 40.00% 30.00% 0.00% Work under progress.
FATEHGARH-III PS (SECTION 1)
159 1X1500 MVA , 765/400 kV ICT (3RD) at POWERGRID 765/400 1500 Sep-25 100.00% 75.00% 70.00% Work under progress.
NAVSARI (NEW) (SOUTH GUJARAT)
160 1X500 MVA, 400/220 kV ICT( 3rd) at POWERGRID 400/220 500 Aug-25 90.00% 80.00% 45.00% Work under progress.
HASSAN (Augmentation of Transformation
Capacity at 400/220 KV Hassan
Substation in Karnataka by 400/220 KV,
1x500 MVA ICT (3rd))
161 2X1500 MVA 765/400 kV ICT-1 & 2 at POWERGRID 765/400 3000 Aug-25 82.00% 85.00% 40.00% Land (114.879 Acre): All Acquired
DAUSA (Transmission system for Govt. (94.56 Acre) & Pvt. (21.26 Acre)
evacuation of power from REZ in Rajasthan
(20 GW) under Phase-III part H) (SPV:
POWERGRID Beawar DausaTransmission
Ltd))
162 1X500 MVA, 400/220 kV ICT (4TH) at POWERGRID 400/220 500 Sep-25 Jun-25 90.00% 85.00% 60.00%
NALAGARH (Augmentation of
Transformation Capacity at 400/220 kV
Nalagarh substation by 400/220 kV, 1x500
MVA (4th) ICT)
163 Upgradation of existing 132 kV Namsai POWERGRID 220/132 320 Oct-25 100.00% 100.00% 100.00% Both ICTs charged on no load in April 2025.
(PG) S/s to 220 kV including 2X160 MVA, Commissioning shall be considered only after
ICT-1 & 2 (System Strengthening Scheme Connecting lines are commissioned.
for Eastern and North Eastern Regions
(ERSS-XXV & NERSS-XV))(SPV Name:
POWERGRID ER NER Transmission
Limited))
164 2X1500 MVA 765/400 kV ICT-1 & 2 at POWERGRID 765/400 3000 May-25 100.00% 100.00% 100.00% Commissioned in April-2025.
NAVSARI (NEW) (SOUTH GUJARAT) (GIS)
(Transmission Network Expansion in
Gujarat to increase its ATC from ISTS Part
B)
165 1X500 MVA 400/220 kV ICT-3 at POWERGRID 400/220 500 Jun-25 99.00% 99.00% 99.00%
NAVSARI (NEW) (SOUTH GUJARAT) (GIS)
(Transmission Network Expansion in
Gujarat to increase its ATC from ISTS Part
B)
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
166 765/400 kV 3X1500 MVA ICT-1,2 & 3 at POWERGRID 765/400 4500 Jun-25 85.00% 70.00% 40.00% Work under progress
AHMEDABAD (NEW SS) ALONG WITH * Bays for Banaskantha line to be charged on
BAYS (Transmission scheme for evacuation priority by June'25
of 4.5GW RE injection at Khavda PS under
Phase II- Part C (SPV Name: POWERGRID
KHAVDA II-C TRANSMISSION LIMITED))
167 3X500 MVA, 400/220 kV ICT 1, 2 & 3 at POWERGRID 400/220 1500 Dec-25 75.00% 75.00% 20.00% Land Acquired
BHADLA-III (Transmission system for
evacuation of power from REZ in Rajasthan
(20 GW) under Phase-III part B1)(SPV:
POWERGRID Bhadla-3 Transmission Ltd))
168 2X1500 MVA, 765/400 kV ICT-1 & 2 at POWERGRID 765/400 3000 Dec-25 75.00% 75.00% 20.00% Land Acquired
BHADLA-III (Transmission system for
evacuation of power from REZ in Rajasthan
(20 GW) under Phase-III part B1)(SPV:
POWERGRID Bhadla-3 Transmission Ltd))
169 1X500 MVA, 400/220 kV ICT-1 at POWERGRID 400/220 500 Oct-25 65.00% 47.00% 18.00% Work under progress.
LAKHISARAI (ERES-XXXVII)
170 1X500 MVA, 400/220 kV ICT-2 at POWERGRID 400/220 500 Nov-25 65.00% 47.00% 18.00% Work under progress.
LAKHISARAI (ERES-XXXVII)
171 1X1500 MVA, 765/400 kV ICT(3rd) at POWERGRID 765/400 1500 Dec-25 30.00% 10.00% 0.00%
MAHESHWARAM (Augmentation of
Transformation Capacity by 1X1500 MVA
(3rd) , 765/400 KV ICT at Maheswaram
(PG) Substation in Telangana)
172 1X1500 MVA, 765/400 kV ICT( 4th) at POWERGRID 765/400 1500 Dec-25 60.00% 40.00% 10.00% Awarded in May'24.
BHIWANI (Augment by 1500MVA ICT(4th)
at Bhiwani)
173 1X1500 MVA, 765/400 kV 3rd ICT at POWERGRID 765/400 1500 Nov-25 80.00% 12.00% 0.00%
INDORE SS (Augmnt by 1x1500 MVA ICT
(3rd) at Indore)
174 1X500 MVA,400/220 kV ICT (4th) at POWERGRID 400/220 500 Feb-26 30.00% 70.00% 0.00% Work affected due to Mahakhumbh
ALLAHABAD (Augmentation of
Transformation Capacity at 400/220 kV
Allahabad (PG) substation by 400/220 kV,
1x500 MVA (4th) ICT)
175 7X500 MVA, 400/220/33 kV ICT 1 to 7 at POWERGRID 400/220 3500 Mar-26 10.00% 25.00% Land Required (62.19 Acre): Pending (2.27 Acre)
ANANTHPURAM (Transmission scheme for Govt. Land (48.11 Acre): acquired
Solar Energy Zone in Ananthpuram Pvt. Land (14.08 Acre): Pending (2.27 Acre).
(Ananthapur) (2500 MW) and Kurnool Alottment under process at DC Office.
(1000 MW), Andhra Pradesh) (SPV:
POWERGRID Ananthpuram Kurnool
Transmission Ltd)
176 1X500 MVA, 400/220 kV ICT (3rd) at POWERGRID 400/220 500 Jan-26 47.00% 7.00% 0.00% Work under progress.
BHACHAU (Augmentation of
Transformation Capacity at 400/220 KV
Bhachau Substation in Gujarat by
400/220 KV , 1x1500 MVA ICT (3rd))
177 1X500 MVA, 400/220 kV ICT (5th) at POWERGRID 400/220 500 Feb-26 2.00% 0.00% 0.00% Work under progress.
BOISAR (Augmt. 1x500 MVA ICT (5th) at
Boisar)
178 REPLACEMENT OF 315 MVA ICT WITH POWERGRID 400/220 185 Mar-26 ICT Reached at Bawana on 26.04.25, Erection on
500 MVA at BAWANA (DTL) hold for Outage
179 Establishment of 765/400 kV 2x1500 MVA, POWERGRID 765/400 3000 Dec-25 25.00% 10.00%
at Koppal-II (Phase- A)(Transmission
Scheme for integration of Renewable
Energy Zone (Phase-II) in Koppal-II (Phase-
A & B) and Gadag-II(Phase- A) in
Karnataka)(SPV: POWERGRID Koppal II
Gadag II Transmission Ltd)
180 Establishment of 400/220 kV, 2x500 MVA POWERGRID 400/220 1000 Dec-25 25.00% 10.00%
Koppal-II (Phase- A) (Transmission Scheme
for integration of Renewable Energy Zone
(Phase-II) in Koppal-II (Phase-A & B) and
Gadag-II (Phase- A) in Karnataka) (SPV:
POWERGRID Koppal II Gadag II
Transmission Ltd)
181 Establishment of 400/220 kV, 2x500 MVA POWERGRID 400/220 1000 Dec-25 30.00% 25.00%
Gadag-II (Phase -A) PS (Transmission
Scheme for integration of Renewable
Energy Zone (Phase-II) in Koppal-II (Phase-
A & B) and Gadag-II (Phase- A) in
Karnataka) (SPV: POWERGRID Koppal II
Gadag II Transmission Ltd)
182 Augmentation by 2x1500 MVA, 765/400 POWERGRID 765/400 3000 Dec-25 Engg. Under Progress
kV ICTs at Koppal-II PS (Transmission
Scheme for integration of Renewable
Energy Zone (Phase-II) in Koppal-II (Phase-
A & B) and Gadag-II (Phase- A) in
Karnataka) (SPV: POWERGRID Koppal II
Gadag II Transmission Ltd)
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
183 Augmentation by 2x500 MVA, 400/220 kV POWERGRID 400/220 1000 Dec-25 Engg. Under Progress
ICTs at Koppal-II PS (Transmission Scheme
for integration of Renewable Energy Zone
(Phase-II) in Koppal-II (Phase-A & B) and
Gadag-II (Phase- A) in Karnataka) (SPV:
POWERGRID Koppal II Gadag II
Transmission Ltd)
184 Establishment of 765/400 kV, 6x1500 MVA POWERGRID 765/400 9000 Dec-25 55.00% 40.00% Land (213.78 Acre): Acquired. Allotment letter
(along with one spare unit of 500 MVA) at received in Dec'24.
Bikaner-III PS (Transmission system for
evacuation of power from Rajasthan REZ
Ph-IV (Part-1) (Bikaner Complex): PART-
A)(SPV: POWERGRID Bikaner III Neemrana
Transmission Ltd)
185 Establishment of 400/220 kV, 5x500 MVA POWERGRID 400/220 2500 Dec-25 55.00% 40.00% Land (213.78 Acre): Acquired. Allotment letter
Bikaner-III PS (Transmission system for received in Dec'24.
evacuation of power from Rajasthan REZ
Ph-IV (Part-1) (Bikaner Complex): PART-
A)(SPV: POWERGRID Bikaner III Neemrana
Transmission Ltd)
186 Establishement of Bidar PS 3x1500 MVA, POWERGRID 765/400 4500 Feb-26 15.00% 10.00% Land required :162.07 Acre (all Pvt.)
765/400 kV ICTs (Transmission Scheme Pending: 10.77 Acre
for Solar Energy Zone in Bidar (2500 MW), Applied on 24.01.2024. Registry of 151.3 acres of
Karnataka)(SPV Name: POWERGRID Bidar land has been
Transmission Limited) completed till date. Registration of remaing land
in under progress.
187 Establishement of Bidar PS 5x500 MVA, POWERGRID 400/220 2500 Feb-26 15.00% 10.00% Land required :162.07 Acre (all Pvt.)
400/220 kV ICTs (Transmission Scheme Pending: 10.77 Acre
for Solar Energy Zone in Bidar (2500 MW), Applied on 24.01.2024. Registry of 151.3 acres of
Karnataka)(SPV Name: POWERGRID Bidar land has been
Transmission Limited) completed till date. Registration of remaing land
in under progress.
188 Aug. at KPS2 GIS by 2x1500 MVA, POWERGRID 765/400 6000 Feb-26 20.00% 2.00%
765/400 kV ICT on Bus Section-I (5th &
6th) & 2x1500 MVA, 765/400 kV ICT on
Bus Section-II (7th & 8th) (Transmission
Scheme for Evacuation of power from
potential renewable energy zone in Khavda
area of Gujarat under Phase-IV (7 GW):Part
E2)(SPV: POWERGRID Khavda IV E2 Power
Transmission Ltd)
189 Augmentation of 2x500 MVA , 400/220 kV POWERGRID 400/220 1000 Feb - 26 2.00% Engg under progress
at Bhadla-III PS (4th & 5th ICT) (Additional
Transmission System for evacuation of
Power from Bhadla-III PS as part of
Rajasthan REZ Phase III Scheme (20
GW))(SPV Name: POWERGRID Bhadla-III
Power Transmission Limited)
190 Augmentation of 1x1500 MVA 765/400 KV POWERGRID 765/400 1500 Feb - 26 2.00% Engg under progress
(3rd) ICT at Bhadla-III PS (Additional
Transmission System for evacuation of
Power from Bhadla-III PS as part of
Rajasthan REZ Phase III Scheme (20 GW))
(SPV Name: POWERGRID Bhadla-III Power
Transmission Limited)
191 Augmentation of 1x1500 MVA 765/400 KV POWERGRID 765/400 3000 Dec - 25 2.00% Engg under progress
(4th) ICT at Bhadla-III PS (Additional
Transmission System for evacuation of
Power from Bhadla-III PS as part of
Rajasthan REZ Phase III Scheme (20 GW))
(SPV Name: POWERGRID Bhadla-III Power
Transmission Limited)
192 Augmentation by 3x1500 MVA (5th, 6th & POWERGRID 765/400 4500 Dec - 25
7th), 765/400 kV ICTs at Koppal-II PS
(System Strengthening at Koppal-II and
Gadag-II for integration of RE generation
projects)
194 Dhanansu (400 kV SS) (Aug.) PSTCL 400/220 500 Apr-25 May-2025 70.00% 90.00% 70.00% Work likely to complete in May'25.
195 Patti (200 kV SS)(Aug.) PSTCL 220/66 100 Apr-25 100.00% 100.00% 100.00% T/f charged on 31.03.2025 (reported by utility
in April-25 Ach.
196 Dhandari Kalan-2 (220 kV SS) (Aug.) PSTCL 220/66 60 Apr-25 May-2025 75.00% 80.00% 70.00%
197 Wazirabad SS PSTCL 220/66 160 May-25 80.00% 90.00% 70.00%
198 Sherpur SS (Upgradation from 66 kV to PSTCL 220/66 160 May-25 70.00% 90.00% 70.00%
220 kV)
199 Sherpur SS (Aug.) PSTCL 220/66 160 Jul-25 70.00% 90.00% 70.00%
200 Moga (Singhawala)(220 kV SS)(Aug.) PSTCL 220/66 100 May-25 70.00% 90.00% 70.00%
201 220 kV Maur SS (Aug.) PSTCL 220/66 100 Jun-25 70.00% 90.00% 70.00%
202 220 kV Mohali-1(Aug.) PSTCL 220/66 60 Jun-25 100.00% 100.00% 100.00% T/f charged on 11.04..2025
203 220 kV Budhlada (Upgraded from 66 kV to PSTCL 220/66 160 Aug-25 70.00% 90.00% 70.00%
220 kV)
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
215 2x500 MVA, 400/220 kV Kasargode Sterlite 400/220 1000 Dec-25 99.93% 100.00% 99.86% Physically completed. CEA inspection Completed
(Transmission System for 400 kV Udupi on 13th Oct 2023 at Kasargod SS, CEA charging
(UPCL) – Kasargode D/C Line) approval received on 31st Oct 2023.
Commissioning is dependent on completion of
Udupi – Kasargode 400kV D/c line.
216 7x66.67 MVA, 400/132 kV Kishtwar Sterlite 400/132 400 Jun-25 50.24% 97.17% 44.18% Total Land (32 Acres): Pending 4.6 Acres.
(Transmission System for evacuation of Govt. (2.8 Acre Non-Forest): Penidng allotmnetof
power from Pakaldul HEP in Chenab Valley 2.8 Acres in Kishtwar by JKPDD. Applied in April
HEPs) 2024.
Pvt. (29.2 Acres): Pending 1.8 Acres.
217 2X1500 MVA , 765/400 kV Beawar S/s Sterlite 765/400 3000 Jul-25 79.63% 98.65% 66.80% Total Land (58.28 Ha): Pending 12.32 Ha
(Transmission System for Evacuation of Govt. Land (12.32 Ha): Pending 12.32 Ha.
Power from REZ in Rajasthan (20GW) Applied on 26-09-2023.
under Phase-III Part F) File is pending at Revenue Minister, Rajasthan
218 Establishment of 765/400 kV, 4x1500 MVA Sterlite 765/400 6000 Dec-25 0.46% 45.91% 0.00% 1. Total Land (112.5 Acre - All Pvt.): Pending
at Neemrana-II S/s (along with one spare 83.75 Acre.
unit of 500 MVA) (Transmission system for 2. Severe agitation from the landowners is
evacuation of power from Rajasthan REZ causing delay in land acquistion.
Ph-IV (Part-1) (Bikaner Complex): PART-B)
219 Maraimalai Nagar (upgradation from 110 TANTRANSCO 230/110 200 Jun-25 Jun-25 100.00% 100.00% 100.00% ROW issue in Railway crossing work
kV to 230 kV)
220 Thervoikandigai SS TANTRANSCO 400/230 315 Jun-25 Jun-25 100.00% 100.00% 100.00% SS backcharged at 230KV level.
221 Vembakkam (upgradation from 110 kV to TANTRANSCO 230/110 300 Jun-25 Jun-25 98.00% 95.00% 75.00% Control room work completed. Strucure erection
230 kV) completed. C&R panels and Breakers supply
getting delayed. Under pipeline and expected to
be completed soon.
222 Avadi SS (upgradation from 110 kV to 230 TANTRANSCO 230/110 200 Jun-25 Jun-25 95.00% 70.00% 50.00% Cable laying works completed. Connected (Avadi)
kV) SS work under progress. C&R panels and
Breakers supply getting delayed.
223 Korattur SS (upgradation from 230 kV to TANTRANSCO 400/230 1000 Apr-25 May-25 100.00% 100.00% 100.00% 1 No. 500MVA commissioned on 23.04.2025.
400 kV GIS) For 2nd 500MVA, SRLDC clearance awaited.
224 Korattur SS (upgradation from 230 kV to TANTRANSCO 400/110 400 Apr-25 Apr-25 100.00% 100.00% 100.00% Commissioned on 23.04.2025.
400 kV GIS)
225 Panjetty (upgradation from 110 kV to 230 TANTRANSCO 230/110 300 Aug-25 Aug-25 95.00% 75 75 Control Room, Structure Erection work
kV GIS) completed. C&R panels and Breakers supply
getting delayed. Under pipeline and expected to
be completed soon.
226 Tharamani SS( upgradation from 230 kV to TANTRANSCO 400/230 1000 May-25 May-25 100.00% 100.00% 100.00% SS backcharged at 230KV level. Cable work from
400 kV GIS) Ottiyambakkam to common point under progess
227 Tharamani SS( upgradation from 230 kV to TANTRANSCO 400/110 400 May-25 May-25 100.00% 100.00% 100.00% SS backcharged at 230KV level. Cable work from
400 kV GIS) Ottiyambakkam to common point under progess
228 Guindy 400 kV GIS SS TANTRANSCO 400/230 630 May-25 May-25 100.00% 100.00% 100.00% SS backcharged at 230KV level. Source cable
work under progress
229 Thiruvanmiyur 230/33 kV GIS SS TANTRANSCO 230/33 200 Dec-25 Dec-25 100.00% 95.00% 90.00% GIS breakers tested by P&C wing & GIS Wing
under progress.
230 Ganesh Nagar 230/33 kV GIS SS TANTRANSCO 230/33 200 Apr-25 Jun-25 80.00% 80.00% 70.00% Slow progress by the contractor
231 Mambakkam 230/110 kV SS TANTRANSCO 230 /110 200 Apr-25 May-25 95.00% 95.00% 95.00% P&C testing to be completed.
232 Sathumadurai 230/110 kV SS -New TANTRANSCO 230/ 110 320 Sep-25 Sep-25 95.00% 75.00% 60.00% C&R panels and Breakers supply getting delayed.
Under pipeline and expected to be completed
soon. Contractor's delay.
233 Nallur 230/110 kV SS TANTRANSCO 230/ 110 200 Oct-25 Oct-25 95.00% 75.00% 60.00% C&R panels and Breakers supply getting delayed.
Under pipeline and expected to be completed
soon. Contractor's delay.
234 Nanguneri (Aug.) TANTRANSCO 230/110 200 Oct-25 Oct-25 100.00% 80.00% 80.00% C&R panels and Breakers supply getting delayed.
Under pipeline and expected to be completed
soon. Contractor's delay.
235 Thiruvannamalai SS (Aug.) TANTRANSCO 230/110 60 Jun-25 Jun-25 Enhancement of Transformer capacity
236 Oragadam 230 kV SS (Aug.) TANTRANSCO 230/110 120 Jun-25 Jun-25 Enhancement of Transformer capacity
237 Vinnamangalm SS (Aug.) TANTRANSCO 230/ 110 100 Sep-25 Sep-25 Bay extension work under progress.
238 Hosur SS (Aug.) TANTRANSCO 230/ 110 60 Sep-25 Sep-25 Transformer erection under progress.
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
239 Hosur SS (Aug.) TANTRANSCO 230/ 110 60 Dec-25 Dec-25 Only after commissioning of 2nd 160 MVA
Transformer, work would be taken up after
dismantling of existing 3x100 MVA Auto
Transformers
240 K.R.Thoppur SS (Aug.) TANTRANSCO 400/230 500 Apr-25 100.00% 100.00% 100.00% Transformer commissioned on 05.04.2025
241 Kayathar SS in Tirunelveli Operation Circle TANTRANSCO 400/110 200 Jun-25 Jun-25 Tender under process for additional ICT Plinth
(Aug.) work
242 Alagarkovil SS in Madurai Operation TANTRANSCO 230 /110 60 Aug-25 Aug-25 LC required
Circle (Aug.)
243 Sembatty SS in Madurai Operation Circle TANTRANSCO 230 /110 160 Dec-25 Dec-25 Main tank and other main materials yet to be
(Aug.) received. Oil drum and NIFS system only received
at site
244 Kalivelampatty 230 /110 kV SS TANTRANSCO 230/110 200 Dec-25 Dec-25 100.00% 95.00% 70.00% C&R panels and Breakers supply getting delayed.
Under pipeline and expected to be completed
soon. Contractor's delay.
245 Kakatiya Mega Textile Park (KMTP) SS TGTRANSCO 220/ 132 320 Sep-25 90.00% 95.00% 85.00%
(2x160)
246 Yacharam Thanda SS TGTRANSCO 220/11 170 Dec-25 70.00% 98.00% 70.00%
247 Ammavaripet (T/F-II) TGTRANSCO 220/ 132 100 Sep-25 100.00% 90.00% 90.00%
248 Bhoopalapally (KTPP) SS 400/220/ 132 kV - TGTRANSCO 220/132 320 Jul-25 98.00% 90.00% 90.00% Procurment of 160MVA PTRs under progress
2 Nos 160 MVA PTR
249 Uddandapur LISS TGTRANSCO 400/11 545 Mar-26 10.00% 95.00% 0.00% Severe ROW for more than 1 year from Villagers
due to non payment of R&R by I&CAD.Resolved
partially recently in January'2025 and works
recommenced.
250 220/132 kV SS Wanaparthy (Aug.) TGTRANSCO 220/132 160 Apr-25 100.00% 100.00% 100.00% 160 MVA PTR idle charged on 30.04.2025
251 220/132 kV SS Banswada (Aug.) TGTRANSCO 220 / 132 100 May-25
252 220/132 kV SS Jurala (Aug.) TGTRANSCO 220 / 132 60 May-25
253 220/132 kV SS Mandamarri (Bellampally) TGTRANSCO 220 / 132 60 May-25
(Aug.)
254 220/132 kV Yeddumailaram SS (Aug.) TGTRANSCO 220 / 132 160 May-25
255 220/132/33 kV Fabcity SS (Aug.) TGTRANSCO 220 / 132 100 Jun-25
256 220/132 kV SS Jangaon (Aug.) TGTRANSCO 220 / 132 60 Jun-25
257 220/132 kV SS Siddipet (Aug.) TGTRANSCO 220 / 132 60 Jul-25
258 220/132/33 kV Peddagopathi SS (Aug.) TGTRANSCO 220 / 132 60 Jul-25
259 220/132 kV Thimmajipet SS (Aug.) (Aug.) TGTRANSCO 220 / 132 100 Jul-25
287 400 kV S/s Jewar, GB Nagar (Intra-state Megha 400/220 1000 Dec-25 5.00% 8.00% 0.00% Work is in progress.
TBCB) Engineering
288 400 kV S/s Gonda (Intra-state TBCB) Tata Power 400/220 630 Dec-25 100.00% 99.00% 100.00% Substation work completed, 400kV line will be
charged in Dec-25
289 400 kV S/s Metro Depot (Gr Noida), GB Tata Power 400/220 1000 Dec-25 83.00% 80.00% 39.00% Work is in progress.
Nagar (Intra-state TBCB)
290 400 kV S/s Jalpura (Gr Noida), GB Tata Power 400/220 1000 Jan-26 76.00% 48.00% 1.00% Work is in progress.
Nagar(Intra-state TBCB)
291 400 kV S/s Maheba, Jalaun (GEC-II) UPPTCL 400/220 1000 Jan-26 63.00% 35.00% 30.00% Work is in progress.
292 400 kV S/s Maheba, Jalaun (GEC-II) UPPTCL 220/132 320 Jan-26 63.00% 35.00% 30.00% Work is in progress.
293 400 kV S/s Garautha, Jhansi (GEC-II) UPPTCL 400/220 1500 Feb-26 62.00% 43.00% 40.00% Work is in progress.
294 220 kV S/s Jaitpur, Mahoba (GEC-II) UPPTCL 220/132 320 Sep-25 48.00% 55.00% 0.00% Work is in progress.
295 220 kV S/s Kabrai, Mahoba (GEC-II) UPPTCL 220/132 160 Nov-25 45.00% 80.00% 65.00% Work is in progress.
296 220 kV S/s Charkhari, Mahoba (GEC-II) UPPTCL 220/132 160 Sep-25 48.00% 65.00% 28.00% Work is in progress.
297 220 kV S/s Dakaur, Jalaun UPPTCL 220/132 160 Dec-25 54.00% 50.00% 10.00% Work is in progress.
298 220 kV System at Existing 400 kV S/s UPPTCL 220/132 320 Nov-25 82.00% 0.00% 0.00% Work is in progress.
Banda (GEC-II)
299 220 kV S/s Bamaur, Jhansi (GEC-II) UPPTCL 220/132 160 Dec-25 59.00% 61.00% 30.00% Work is in progress.
Sl.No. Name of Substation CPSU's/Privat Voltage Total Targeted Revised Civil Materials / Materials Remarks/Reason for delay
e Ratio Capacity (in COD Anticipated works (%) Equipments /
Developer/St (kV/kV) MVA) COD (as on 30- Received (%) Equipmen
ate Transco's 04-2025) ts erected
(%)
300 220 kV S/s Mandawra, Lalitpur (GEC-II) UPPTCL 220/132 160 Jan-26 40.00% 45.00% 2.00% Work is in progress.
301 220 kV S/s Birdha, Lalitpur (GEC-II) UPPTCL 220/132 160 Jan-26 45.00% 58.00% 25.00% Work is in progress.
302 220 kV S/s Bangra, Jhansi (GEC-II) UPPTCL 220/132 160 Jan-26 50.00% 60.00% 22.00% Work is in progress.
303 220 kV S/s Mawana UPPTCL 220/132 320 Feb-26 60.00% 75.00% 15.00% Work is in progress.
304 220 kV S/s Vasundhara, Ghaziabad (Intra- Megha 220/33 180 Jan-26 8.00% 8.00% 0.00% Work is in progress.
state TBCB) Engineering
305 220 kV S/s Varanasi Cantt (Intra-state Megha 220/33 120 Jan-26 5.00% 1.00% 0.00% Work is in progress.
TBCB) Engineering
306 220 kV S/s Khaga, Fatehpur (Intra-state Megha 220/132 320 Jan-26 5.00% 5.00% 0.00% Work is in progress.
TBCB) Engineering
307 220 kV S/s Tirwa, Kannauj(Intra-state Megha 220/132 320 Jan-26 9.00% 3.00% 0.00% Work is in progress.
TBCB) Engineering
308 220 kV Baram GIS PTCUL 220/33 50 Apr-25
309 Falakata 220 kV GIS WBSETCL 220/132 320 Jun-25 Jun-2025 80.00% 95.00% 80.00% Delay due to frequent stoppage of work for local
labour issues and defects found in GIS material
during installation.
310 Raghunathpur 220 kV GIS (Upg) WBSETCL 220/132 320 May-25 May-2025 85.00% 90.00% 85.00% Delay in transportation of Power Transformer
obstackled by Railway height bar.
311 Khanakul 220 kV GIS WBSETCL 220/33 100 Jul-25 Jul-2025 60.00% 90.00% 50.00% Delay due to sever flood in this area in 2024.
312 Satgachhia 400 kV GIS (Upg) WBSETCL 400/220 1000 Apr-25 May-2025 95.00% 99.00% 95.00% Delay in Building demolition occupied by State
Police Force.
313 Mahachanda 220 kV GIS WBSETCL 220/132 400 Mar-26 Mar-2026 35.00% 5.00% 0.00% Work under progress.