Central Bearings & Machinery CBM Building Iii: MR - Sunil Shantha

Quantity Take-Off (QTO) is a fundamental process in construction cost estimation, project planning, and resource management. It involves systematically measuring, listing, and quantifying the various materials, components, and works required for a project directly from architectural and engineering drawings. This process serves as the basis for preparing the Bill of Quantities (BOQ), cost estimates, procurement schedules, and construction budgets.

Uploaded by

Richard Miller
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views2 pages

Central Bearings & Machinery CBM Building Iii: MR - Sunil Shantha

Quantity Take-Off (QTO) is a fundamental process in construction cost estimation, project planning, and resource management. It involves systematically measuring, listing, and quantifying the various materials, components, and works required for a project directly from architectural and engineering drawings. This process serves as the basis for preparing the Bill of Quantities (BOQ), cost estimates, procurement schedules, and construction budgets.

Uploaded by

Richard Miller
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CENTRAL BEARINGS & MACHINERY

CBM BUILDING III


TAKE OFF SHEET

Sub-Contractor : Mr.Sunil Shantha Floor Level : Third Floor

Brick Work/ Block Work/ Internal Plastering/ Bottom Ledge/ Lintel/ Stiffner Column

Sub Total Sub Total Total Area/ Total


Description Unit No. Length Breadth Height Total
(m2 or m) (ft2 or ft) Lintel (ft2 or ft)

4" Brick Work


Grid 5 / A - C m2 0.585 3.135 1.83 1.83 19.70
Grid 5a / A - C m2 0.870 3.135 2.73 2.73 29.39
Grid 5b / A - C m2 2.900 3.135 9.09 9.09 97.84
Grid 5c / A - C m2 4.890 3.135 15.33 15.33 165.01
Grid A1 / 5 - 6 m2 2.200 3.135 6.90 6.90 74.27
Grid A2 / 5 - 6 m2 2.210 3.135 6.93 6.93 74.59
Grid A3 / 5 - 6 m2 1.950 3.135 6.11 6.11 65.77
526.57

9" Brick Work


Grid F / 1 - 7 m2 21.700 2.650 57.51 19.62 211.19
Ddt Stru. Col. m2 (1.650) 2.650 (4.37)
Ddt Stiff. Col. m2 7 (0.100) 2.650 (1.86)
Ddt DW6-W m2 (1.000) 1.750 (1.75)
Ddt DW6-D m2 (1.000) 2.650 (2.65)
Ddt W20 m2 (4.800) 1.750 (8.40)
Ddt W19 m2 (4.850) 1.750 (8.49)
DW5-W m2 (4.550) 1.750 (7.96)
DW5-D m2 (0.910) 2.650 (2.41)
Grid 7 / A - F m2 15.460 2.650 40.97 12.13 130.57
Ddt Stru. Col. m2 (1.500) 2.650 (3.98)
Ddt Stiff. Col. m2 4 (0.100) 2.650 (1.06)
Ddt W17 m2 (9.450) 1.750 (16.54)
Ddt W10 m2 (4.150) 1.750 (7.26)
Grid A / 5 - 7 m2 11.500 2.650 30.48 11.29 121.52
Ddt Stru. Col. m2 (0.865) 2.650 (2.29)
Ddt Stiff. Col. m2 3 (0.100) 2.650 (0.80)
Ddt W18 m2 2 (1.680) 1.650 (5.54)
Ddt DW4 - W m2 (4.670) 1.750 (8.17)
Ddt DW4 - D m2 (0.900) 2.650 (2.39)
Grid A / 1 - 3 m2 5.750 2.700 15.53 13.43 144.56
Ddt W3 m2 (1.200) 1.750 (2.10)
Grid 1 / C - F m2 12.060 2.650 31.96 5.20 55.97
Ddt Stru. Col m2 (0.900) 2.650 (2.39)
Ddt W2 m2 (0.500) 1.700 (0.85)
Ddt W21 m2 (8.500) 2.650 (22.53)
Ddt W15 m2 (0.600) 1.650 (0.99)
Grid 3 / B - C(Fire) m2 1.100 1.386 1.52 1.52 16.36
680.17

Block Work
Grid D / 1 - 3 m2 6.560 2.650 17.38 14.07 151.45
Ddt Stru. Col. m2 (1.050) 2.650 (2.78)
Ddt Stiff. Col. m2 2 (0.100) 2.650 (0.53)
Nos. 209.38

Internal Plastering
4" Brick Wall
Grid 5 / A - C m2 0.585 3.135 1.83 1.83 19.70
Grid 5a / A - C m2 0.870 3.135 2.73 2.73 29.39
Grid 5b / A - C m2 2.900 3.135 9.09 9.09 97.84
Grid 5c / A - C m2 4.890 3.135 15.33 15.33 165.01
Grid A1 / 5 - 6 m2 2.200 3.135 6.90 6.90 74.27
Grid A2 / 5 - 6 m2 2.210 3.135 6.93 6.93 74.59
Grid A3 / 5 - 6 m2 1.950 3.135 6.11 6.11 65.77
1,053.14
9" Brick Wall
Grid F / 1 - 7 m2 21.700 2.650 57.51 19.62 211.19
Ddt Stru. Col. m2 (1.650) 2.650 (4.37)
Ddt Stiff. Col. m2 7 (0.100) 2.650 (1.86)
Ddt DW6-W m2 (1.000) 1.750 (1.75)
Ddt DW6-D m2 (1.000) 2.650 (2.65)
Ddt W20 m2 (4.800) 1.750 (8.40)
Ddt W19 m2 (4.850) 1.750 (8.49)
DW5-W m2 (4.550) 1.750 (7.96)
DW5-D m2 (0.910) 2.650 (2.41)
Grid 7 / A - F m2 15.460 2.650 40.97 12.13 130.57
Ddt Stru. Col. m2 (1.500) 2.650 (3.98)
Ddt Stiff. Col. m2 4 (0.100) 2.650 (1.06)
Ddt W17 m2 (9.450) 1.750 (16.54)
Ddt W10 m2 (4.150) 1.750 (7.26)
Grid A / 5 - 7 m2 11.500 2.650 30.48 11.29 121.52
Ddt Stru. Col. m2 (0.865) 2.650 (2.29)
Ddt Stiff. Col. m2 3 (0.100) 2.650 (0.80)
Ddt W18 m2 2 (1.680) 1.650 (5.54)
Ddt DW4 - W m2 (4.670) 1.750 (8.17)
Ddt DW4 - D m2 (0.900) 2.650 (2.39)
Grid A / 1 - 3 m2 5.750 2.700 15.53 13.43 144.56
Ddt W3 m2 (1.200) 1.750 (2.10)
Grid 1 / C - F m2 12.060 2.650 31.96 5.20 55.97
Ddt Stru. Col m2 (0.900) 2.650 (2.39)
Ddt W2 m2 (0.500) 1.700 (0.85)
Ddt W21 m2 (8.500) 2.650 (22.53)
Ddt W15 m2 (0.600) 1.650 (0.99)
Grid 3 / B - C(Fire) m2 1.100 1.386 1.52 1.52 16.36
-
Block Wall
Grid D / 1 - 3 m2 6.560 2.650 17.38 14.07 151.45
Ddt Stru. Col. m2 (1.050) 2.650 (2.78)
Ddt Stiff. Col. m2 2 (0.100) 2.650 (0.53) -
-

Lintels
4" Brick Wall
Grid 5 / A - C m2 0.585 0.59 1.46 4.79
Grid 5a / A - C m2 0.870 0.87
Grid 5b / A - C m2 2.900 2.90 7.79 25.56
Grid 5c / A - C m2 4.890 4.89
Grid A1 / 5 - 6 m2 2.200 2.20 4.41 14.47
Grid A2 / 5 - 6 m2 2.210 2.21
Grid A3 / 5 - 6 m2 1.950 1.95 1.95 6.40 51.21

9" Brick Wall


Grid F / 1 - 7 m2 21.700 21.70 19.35 63.48
Ddt Stru. Col. m2 (1.650) (1.65)
Ddt Stiff. Col. m2 7 (0.100) (0.70)
Grid 7 / A - F m2 15.460 15.46 13.56 44.49
Ddt Stru. Col. m2 (1.500) (1.50)
Ddt Stiff. Col. m2 4 (0.100) (0.40)
Grid A / 5 - 7 m2 11.500 11.50 10.33 33.89
Ddt Stru. Col. m2 (0.865) (0.87)
Ddt Stiff. Col. m2 3 (0.100) (0.30)
Grid A / 1 - 3 m2 5.750 5.75 5.75 18.86
Grid 1 / C - F m2 12.060 12.06 11.16 36.61
Ddt Stru. Col m2 (0.900) (0.90)
Grid 3 / B - C(Fire) m2 1.100 1.10 1.10 3.61
200.95
Block Wall
Grid D / 1 - 3 m2 6.560 6.56 5.31 17.42
Ddt Stru. Col. m2 (1.050) (1.05)
Ddt Stiff. Col. m2 2 (0.100) (0.20)
-

252.17

Stiffner Column
4" Brick Wall
Grid F / 1 - 7 m 8 0.900 7.20
Grid 7 / A - F m 4 0.900 3.60
Grid A / 5 - 7 m 3 0.900 2.70 13.50 44.29
Block Wall
Grid D / 1 - 3 m 2 2.650 5.30 5.30 17.39

61.68

Bottom Ledge
4" Brick Wall
Grid F / 1 - 7 m2 21.700 21.70 19.35 63.48
Ddt Stru. Col. m2 (1.650) (1.65)
Ddt Stiff. Col. m2 7 (0.100) (0.70)
Grid 7 / A - F m2 15.460 15.46 13.56 44.49
Ddt Stru. Col. m2 (1.500) (1.50)
Ddt Stiff. Col. m2 4 (0.100) (0.40)
Grid A / 5 - 7 m2 11.500 11.50 10.33 33.89
Ddt Stru. Col. m2 (0.865) (0.87)
Ddt Stiff. Col. m2 3 (0.100) (0.30)
Grid A / 1 - 3 m2 5.750 5.75 5.75 18.86
Grid 1 / C - F m2 12.060 12.06 11.16 36.61
Ddt Stru. Col m2 (0.900) (0.90)
Grid 3 / B - C(Fire) m2 1.100 1.10 1.10 3.61

200.95