UPGRADATION/ REHABALITATION AND CONSTRUCTION OF ROADS IN KHYBER PAKHTUNKHWA
8
ADP NO. 1525/240288 (2024-25). SUB HEAD:
Rehabilitation/Widening & Improvement of Jamal Ghari Bazar to Pathe Kali Road UC Jamal
i. 62,000,235.00
Ghari District Mardan.
Construction and Black Topping of Shekh Yousaf Thanidar Village Road (0.550 KM) Uc Saro
ii. 10,999,751.36
Shah Pk-59 District Mardan.
iii. Rehabilitation and B/T of Manga Dheri Road (0.850-Km) UC Manga District Mardan. 7,000,013.64
Grand Total 80,000,000.00
i. Rehabilitation/Widening & Improvement of Jamal Ghari Bazar to Pathe Kali Road UC Jamal
Ghari District Mardan.
S. No. Item Code Description Unit Rate Qty Amount
1 03-70-c Formation of Embankment from Borrow Excavation in m3 892.81 1,098.00 980,305.00
Common Material including compaction Modified
AASHTO 90% by power roller.
2 16-79 Providing & Laying stone soling in water logged area m3 4,085.87 1,194.07 4,878,835.00
including grannular filling & Compaction complete.
3 16-04-a Granular Sub Base Course using Pit Run Gravel m3 2,442.84 1,541.25 3,765,027.00
4 16-05-b Water Bound Macadam Base Course m3 4,236.07 1,137.26 4,817,524.00
5 16-09-a Bitumenous Prime coat as spfd m2 257.77 7,581.75 1,954,348.00
6 16-14-b Asphalt wearing course(Asphalt Batch Plant Hot m3 35,026.91 379.09 13,278,264.00
Mixed)as Spfd.
7 03-67-a Structural Excavation in common material By m3 657.80 1,331.00 875,531.00
Mechnical means.
8 04-19-b Dismantling of P.C.C 1:3:6 m3 3,957.01 521.55 2,063,779.00
9 04-20-a Transportation of earth all types beyond 250m and m3 312.16 521.55 162,807.00
upto 500m.
10 04-20-b Transportation of earth all types for every 100m m3 48.36 521.55 25,222.00
extra lead beyond 500m upto 1.5 km.
11 04-20-c Transportation of earth all types for every 500m m3 43.97 521.56 22,933.00
extra lead beyond 1.5 km. upto 8 km.
12 06-05-h PCC including placing, compacting, finishing & curing m3 12,859.69 1,079.51 13,882,143.00
(Ratio 1:3:6)
13 06-44-a P.C.C 1:3:6 massconcrete using 50% boulders. m3 8,499.99 1,127.25 9,581,614.00
14 06-05-f PCC including placing, compacting, finishing & curing m3 15,436.87 151.04 2,331,662.00
(Ratio 1:2:4)
15 23-03-a-01 Providing and Laying RCC pipe sewers complete As m 2,285.90 21.90 50,061.00
per ASTM C-76-79, Class II : 12" i/d, Wall B
16 23-03-a-03 Providing and Laying RCC pipe sewers complete As m 3,418.70 14.60 49,913.00
per ASTM C-76-79, Class II : 18" i/d, Wall B
17 23-03-a-05 Providing and Laying RCC pipe sewers complete As m 4,525.06 18.25 82,582.00
per ASTM C-76-79, Class II : 24" i/d, Wall B
18 06-46-b Erecting & removing formwork to concrete in any m2 750.75 3,930.00 2,950,448.00
shape / position (Vertical)
19 06-07-a-03 RCC including Precast/Prestressed slab, column, m3 17,793.23 2.67 47,540.00
beam, lintel, girder etc. (1:2:4).
20 06-08-c Supply & fabricate M.S. reinforcement for cement Ton 324,224.31 0.62 199,697.00
concrete (Hot rolled deformed bars Grade 40)
Total 62,000,235.00
ii. Construction and Black Topping of Shekh Yousaf Thanidar Village Road (0.550 KM) Uc Saro
Shah Pk-59 District Mardan.
S. No. Item Code Description Unit Rate Qty Amount
1 03-70-c Formation of Embankment from Borrow Excavation in m3 892.81 778.07 694,672.84
Common Material including compaction Modified
AASHTO 90% by power roller.
2 16-67 Formation of shoulder with permeable material m3 1,703.80 321.52 547,802.00
Passing less than 7 % from 200 seive and P.I less
than 4 as specified.
3 16-04-a Granular Sub Base Course using Pit Run Gravel m3 2,442.84 454.19 1,109,505.00
4 16-05-b Water Bound Macadam Base Course m3 4,236.07 397.41 1,683,470.00
5 16-09-a Bitumenous Prime coat as spfd m2 257.77 1,806.42 465,642.00
6 16-14-b Asphalt wearing course(Asphalt Batch Plant Hot m3 35,026.91 90.32 3,163,672.00
Mixed)as Spfd.
7 03-67-a Structural Excavation in common material By m3 657.80 74.41 48,949.53
Mechnical means.
8 06-05-h PCC including placing, compacting, finishing & curing m3 12,859.69 42.84 550,860.00
(Ratio 1:3:6)
9 06-05-i PCC including placing, compacting, finishing & curing m3 11,471.96 3.17 36,423.00
(Ratio 1:4:8)
10 06-05-f PCC including placing, compacting, finishing & curing m3 15,436.87 3.17 49,012.00
(Ratio 1:2:4)
11 06-44-a P.C.C 1:3:6 massconcrete using 50% boulders. m3 8,499.99 216.00 1,835,998.00
12 23-02-c Providing and Laying RCC pipe sewers complete As m 1,428.75 6.00 8,573.00
per ASTM C-76-79, Class II : 9" i/d, Wall B
13 23-03-a-01 Providing and Laying RCC pipe sewers complete As m 2,285.90 12.00 27,431.00
per ASTM C-76-79, Class II : 12" i/d, Wall B
14 23-03-a-03 Providing and Laying RCC pipe sewers complete As m 3,418.70 12.00 41,024.00
per ASTM C-76-79, Class II : 18" i/d, Wall B
15 23-03-a-05 Providing and Laying RCC pipe sewers complete As m 4,525.06 6.00 27,150.00
per ASTM C-76-79, Class II : 24" i/d, Wall B
16 06-46-b Erecting & removing formwork to concrete in any m2 750.75 840.00 630,630.00
shape / position (Vertical)
17 06-07-a-03 RCC including Precast/Prestressed slab, column, m3 17,793.23 1.83 32,473.00
beam, lintel, girder etc. (1:2:4).
18 06-08-c Supply & fabricate M.S. reinforcement for cement Ton 324,224.31 0.14 46,464.00
concrete (Hot rolled deformed bars Grade 40)
Total 10,999,751.36
iii. Rehabilitation and B/T of Manga Dheri Road (0.850-Km) UC Manga District Mardan.
S. No. Item Code Description Unit Rate Qty Amount
1 27-93 Scarifying old road surface, including removal of m2 66.98 2,740.79 183,578.11
debris within one chain
2 16-04-a Granular Sub Base Course using Pit Run Gravel m3 2,442.84 217.75 531,928.41
3 16-05-b Water Bound Macadam Base Course m3 4,236.07 205.00 868,394.35
4 16-09-b Bitumenous Tack coat as spfd m2 96.23 2,740.79 263,746.22
5 16-09-a Bitumenous Prime coat as spfd m2 257.77 1,366.64 352,278.79
6 16-14-b Asphalt wearing course (Asphalt Batch Plant Hot m3 35,026.91 137.04 4,800,087.75
Mixed) as Spfd.
Total 7,000,013.64
Grand Total 80,000,000.00
In Million 80.000
Note: 1. Carraige of Asphalt concrete from plant to the work site would not be paid and contrcator would himself make
the arrangement for transportation of premix.
2. All other items not included in the BOQ but required at site will be paid on MRS-2024 (1st Bi-Annual) with
approved contractor premium __________% above/below in BOQ rates based on MRS-2024 (1st Bi-Annual).
Signature of Contractor
SUB DIVISIONAL OFFICER
C&W HIGHWAY DIVISION MARDAN