Maintanance OFCdtp
Maintanance OFCdtp
TENDER DOCUMENT
FOR
AUGUST- 2024
Contractor MADC
Page | 2
TENDER DOCUMENT
FOR
VOLUME – I
_________________________________________________
Contractor MADC
Page | 3
CONTENTS
________________ __________________________________
Signature of Bidder Authorized Representative (MADC)
Date : Date :
Contractor MADC
Page | 4
INDEX
Volume I
SECTION-II-
SECTION-II
________________ ________________________________
Signature of Bidder Authorized Signature (MADC)
Date : Date :
Contractor MADC
Page | 5
SECTION – I
A. GENERAL
1. SCOPE OF BID:
As per Bidding Data in Section-II of Volume-II.
2. ELIGIBLE BIDDERS:
This invitation to bid is open to any bidder meeting following requirements:
3. QUALIFICATION OF BIDDER:
3.1 To be eligible for award of the contract the bidder shall provide satisfactory
evidence to the Employer (MADC) of their eligibility, capability and
adequacy of resources to carry out the work / contract effectively. For the
purpose of this, all the bids submitted shall include the information in the
relevant formats as stated in Clause 18.2 of ITB.
3.2 For the purpose of this contract, the bidder shall meet the qualifying criteria as
mentioned in Bidding Data in Volume-II as a minimum.
3.3 Bids from joint ventures are not acceptable.
Contractor MADC
Page | 6
5. COST OF BIDDING:
The bidder shall bear all cost associated with the preparation and submission
of his bid and the Employer will in no case shall be responsible or liable for
these costs, regardless of the conduct or outcome of the bidding procedure.
6. SITE VISIT:
The bidder is advised to visit and examine the site of work and it surrounding
and obtain himself at his own responsibility and cost, all information such as
availability of labour, material, machineries, fuel, water, electricity and such
similar information that may be necessary for preparation of the bid. A
declaration to this effect will have to be signed by the bidder in the format
given in Form - 7 (Declaration of the Contractor) attached to the bid in
Section-V of Volume I.
B. BIDDING DOCUMENT
Contractor MADC
Page | 7
8.1 A Prebid conference open to all prospective bidders will be held at (As per
bidding data in Volume-II) in the office of the (As per Bidding Data in
Volume-II) where in the prospective bidders will have an opportunity to
obtain clarifications regarding the bid conditions and the work.
8.2 The prospective bidders are free to ask any additional information or
clarification, either in writing or orally and reply to the same will be given by
the Employer. The copies of the question raised and the replies given will be
furnished to all those attending the meeting (and subsequently to all
purchasers). Any modifications of bid documents, which may become
necessary as a result of prebid conference, shall be through issuance of an
addendum pursuant to Clause 9 of ITB of these instructions.
C. PREPARATION OF BIDS
Contractor MADC
Page | 8
a. The percentage quoted by the bidder shall include all the costs towards
executing and completing the works including remedying any defects
therein. The offer shall provide for all superintendence, labour, material,
plant, equipments and all other things required for work including all
taxes, duties, royalties, octroi and such charges except for the exemption if
any provided for the contract.
b. The percentage above or below quoted by bidder shall be valid for the
original contract period as well as during extensions if any duly granted
and shall not be subject to any other further adjustment by way of claim
except as detailed in Clause 13.8 of Conditions of Particular
Applications under Section-II Part-II (A).
c. The bid shall be exclusive of Royalty under Minor mineral Act 1968
payable directly to Revenue Department as per Rates in force. The Royalty
to be paid shall be reimbursed by Government or MADC, Ltd.
Contractor MADC
Page | 9
15.2 The Bid Security to be furnished shall be in the form of Demand Draft/ any
nationalized / scheduled bank, in favor of Maharashtra Airport Development
Co. Ltd. payable at Nagpur / Mumbai before due date for submission of bid
(As per Bidding Data in Section-II of Volume II).
15.3 Any bid not accompanied by the Bid Security will be rejected.
15.4 In the event of his bid being accepted subject to provisions of the Sub Clause
15.5 below, the said amount if so requested by the bidder be appropriated
towards the amount of Performance security payable by successful bidder
under the conditions of contract.
15.5 If after submitting the bid or during the bid validity period if the bidder
withdraws his offer or modifies the same or if after acceptance of his bid fails
or neglects to furnish the performance security, without prejudice to any rights
and powers of the Employer here under or in law, the employer shall be
entitled to forfeit the full amount of Bid Security deposited by the bidder.
15.6 If the bidder does not accept the correction of the bid price, pursuant to Clause
26 of ITB, the bid security shall be forfeited.
15.7 In the event of bid being not accepted, the amount of Bid Security deposited
by the bidder shall unless it is prior thereto to forfeit under provision of Sub
Clause 15.5 above, be refunded to him on passing of receipt thereto without
any interest.
16. ALTERNATIVE PROPOSAL OF BIDDERS:
If asked for alternative proposal from bidders, the bidders shall submit the
offers that comply with the requirements of various stipulations of the bidding
document, requirements as indicated in the design criteria, drawings,
specifications, and technical scope of work. In this respect no alterations to the
requirements are permissible.
Contractor MADC
Page | 10
17.2 The Bid shall contain no alterations or additions, except those to comply with
instructions issued by the Employer, or as necessary to correct errors made by
the bidder in which case such corrections shall be initiated by the person or
persons signing the bid.
17.3 At the time of executing the agreement, the successful bidder shall sign all
pages of bid document.
Contractor MADC
Page | 12
18.4 The bidder shall quote his offer on the bid as prescribed in Volume-III at the
appropriate place of Volume-III. Bidder shall not quote his offer anywhere
directly or indirectly in Technical & Financial Bid except at appropriate place
in Volume-III of the bid document, otherwise bid will stand rejected.
MADC reserves right to withdraw the entire offer or delete any Part from the
scope of the work.
The bid shall be received by the (As per Bidding Data in Section-II of
Volume-II) at the address mentioned in IFB not later than (As per Bidding
Data in Section-II of Volume-II). The Employer may at his discretion extend
the dead line for submission of bid issuing an addendum in accordance with
Clause-9 of ITB in which case all rights and obligations of the employer and
bidders previously subjected to the original dead line shall therefore be
subjected to new dead line as extended.
If after submission of the bid the bidder withdraws his offer or modifies the
same, without prejudice to any other rights and power of the Employer
hereunder or in law, the employer shall be entitled to forfeit the full amount of
the Bid Security deposited by bidder.
22 BID OPENING:
22.1 The bids will be opened through e-tender portal only after the last date of
submission of bids.
22.2 The documents in the technical bid will be verified by the bid opening
authority to check their validity as per requirement. If any particular document
of any bid is either missing or does not meet the requirements specified then a
Contractor MADC
Page | 13
note to that effect will be made by the bid opening authority. After opening of
the technical bid the Employer will carry out the process of scrutiny and
analysis of various documents / data submitted in technical bid.
22.3 In case of lump sum Bid with Contractor’s alternative technical proposal, the
alternative technical proposal submitted in technical bid will be scrutinized to
confirm the requirements of technical specifications, design criteria and scope
of work. The financial bid of the bids will be opened of those bidders only,
whose alternative technical proposal is found to be as per the requirements of
various stipulations, technical specifications, design criteria and scope of
work.
22.4 The financial bids whose technical bid does not contain the specified
documents or any of the specified document is missing, will be separated out.
A note on the financial bid of such bids indicating the nature of deficiency will
be made. The financial bid of such bid shall not be opened and a note to that
effect will be made on the financial bid.
22.5 After the analysis and scrutiny of documents with respect to requirements of
bidding is over, then employer shall declare the outcome of scrutiny and shall
intimate the date and time of opening of financial bid to the qualified bidders.
22.6 On the specified date the financial bid of the successful bidder shall be opened
serially. The percentage above or below over the estimated cost of the
employer quoted by each bidder will be read out loudly by bid opening
authority for information of those present.
in case of very high / very low offer. Such request shall be in writing and the
response shall also be in writing. But no change in the price or substance of
the bid shall be sought, offered or permitted except as required to confirm the
correction of the arithmetic errors discovered by the Employer in the
evaluation of the bids in accordance with Clause 27 of ITB.
Contractor MADC
Page | 15
26.2 The amount stated in the bid will be adjusted by the employer in accordance
with the above procedure for the correction of errors and with the concurrence
of the bidder, shall be considered as binding upon the bidder.
26.3 If the bidder does not accept the corrected bid price, the bid will be rejected
and the bid security shall be forfeited in accordance with Sub Clause 15.6 of
ITB.
Contractor MADC
Page | 16
a) Defines, for the purposes of this provision, the terms set forth below as
follows:
v) “Obstructive practice” is
i) Deliberately destroying, altering or concealing of evidence material to the
investigation or making false statements to investigators in order to materially
impede an investigation into allegations of a corrupt, coercive or collusive
practice; and/or threatening, harassing or intimidating any party to prevent it
Contractor MADC
Page | 17
28.2 DELETE
d. The Employer reserves the right to reject any or all offers received from
the Bidders without assigning any reasons.
28.4 If the bid of the successful Bidder is imbalanced in relation to the Engineer's
estimate of the cost of work to be performed under the contract, the Employer
may require the Bidder to produce detailed price analysis to demonstrate the
internal consistency at those prices with the construction methods and
schedule proposed. After evaluation of the price analysis, the Employer may
require that the amount of the Performance Security set forth in Clause-31 of
ITB be increased at the expense of the successful Bidder to a level sufficient to
protect the Employer against financial loss in the event of default of the
successful Bidder under the contract.
________________ ____________________________
Signature of Bidder Authorized Signature (MADC)
Date: Date:
Contractor MADC
Page | 19
CONDITIONS OF CONTRACT
NOTE:
2. It is intended that Bidders shall purchase directly their own individual copies
of the General Conditions of Contract, as specified herein above.
_________________ ____________________________________
Signature of Bidder Authorized Signature (MADC)
Date: Date:
Contractor MADC
Page | 20
CONDITIONS OF CONTRACT
NOTE
________________ ______________________
Signature of Bidder Authorized Signature (MADC)
Date: Date:
Contractor MADC
Page | 21
CLAUSE-1
DEFINITIONS:
Sub Clause: 1.1.2.2 The Employer is VC & MD, Maharashtra Airport Development
Co. Ltd., Mumbai.
Address : 8th Floor, World Trade Centre,
Cuffe Parade,
Mumbai-400 005
Telephone No : (022) 49212121
Fax No : (022) 2216 3814
E-mail ID : contact@madcindia.org
Sub Clause: 1.1.2.4 The Engineer is Executive Engineer, MADC, Nagpur or any
other firm / person nominated by VC & MD, MADC
Address : Central Facility Building-B Wing (North) 1st floor,
MIHAN, SEZ, Khapri, Railway, Nagpur- 441108
Contractor MADC
Page | 22
The following additional words and expressions shall have the meanings assigned
to them, except where the context otherwise required:
i) Corporations or Department shall mean the Successors in office and assigns.
ii) The “Vice Chairman and Managing Director” shall mean the official who is
designated as the employer for the time being.
iii) The “Engineer” shall mean PMC or any other representative of MADC,
Nagpur or any other firm / person nominated by VC & MD, MADC.
iv) A “Day” shall mean a day of 24 hours from midnight to midnight irrespective
of number of hours worked in that day.
v) A “Week” shall mean 7 consecutive days without regard to the number of
hours worked in any day in that week.
vi) Month and Year and all dates shall be as per the Gregorian calendar time
referred to shall be Indian Standard Time.
vii) The “Site” shall mean the lands and / or other places, on, under, in or through
which the work is to be executed under the contract including any other
lands or places which may be allotted by the Department or used for the
purpose of contract.
viii) “Urgent Works” shall mean any measures, which in the opinion of
Engineer becomes necessary during the progress of the work to obviate
any risk or accident of failure or which becomes necessary for security of
the work or the persons working thereon.
ix) “Lead Firm” shall mean the firm acting as lead firm representing the joint
venture duly supported by Power of Attorney.
x) Works: Works shall mean Renewal of Asphalt Roads in MIHAN SEZ Area at
Nagpur
xi) “MADC” shall mean Maharashtra Airport Development Company Ltd.
xii) “GC” shall means General Conditions of Contract
xiii) “SC” shall mean Special Conditions of contracts
xiv)“ICAO” Shall means International Civil Aviation Organization
Contractor MADC
Page | 23
Contractor MADC
Page | 24
Contractor MADC
Page | 25
CLAUSE 3
Sub Clause 3.1.1 Engineers Duties and Authority
The Engineer shall obtain the specific approval of the Employer before carrying out
his duties in accordance with the following Clauses of Part 1:
(a) Clause 8
(b) Clause 14
Notwithstanding the obligation, as set out above, to obtain approval, if, in the opinion
of the Engineer an emergency occurs affecting the safety of life or of the works or of
adjoining property, he may, without relieving the Contractor of any of his duties and
responsibilities under the contract, instruct the Contractor to execute all such work or
to do all such things as may, in the opinion of the Engineer, be necessary to abate or
reduce the risk. The Contractor shall forthwith comply, despite the absence of
approval of the Employer, with any such instruction of the Engineer. The Engineer
shall determine an addition to the Contractor Price, in respect of such instruction in
accordance with Clause 14 and shall notify the Contractor accordingly, with a copy to
the Employer.
Contractor MADC
Page | 26
e. Waiving off the penalty and arranging the repayment of compensation for
delay.
f. Issuing of variation order.
g. Ordering any work/test beyond the scope of the contract.
h. Determining rates for the extra items / extra work from
i. Any variations in the contract condition from.
j. Approval to designs and working drawings.
k. Issuing a variation under Clause 13 except if such variation would be within
the limits as indicated below:-
CLAUSE 4
Sub Clause 4.1.1: Maintenance of the Records by the Contractor
The Contractor shall maintain all the records till the completion of defect liability
period and or till the claims and court matters pertaining to the work are settled
whichever is later.
Sub Clause 4.2.1: Source of Performance Security
The performance security, amounting rupees (as per Contract Data in Section-II of
Volume-I) submitted by the Contractor in accordance with Sub Clause 4.2, shall be
either in the form of demand draft drawn on any nationalized/scheduled bank, in the
name of MADC Mumbai, payable at Mumbai or in the form of bank guarantee
furnished by Nationalised Bank or State Bank of India, or Banks promoted by all India
Financial Institutions including HDFC, issued from its any branch in Maharashtra
State. The terms and conditions for submitting the Performance Security shall be
furnished within 15 days from the date of issue of acceptance letter else. The
contractor will be liable for action as per Sub Clause 15.5 of IBT Section-I of Volume-
I and action as per Clause 15.1.1 of Conditions of Particular Application Part II (B).
The Performance Security submitted shall be valid till completion of defect liability
period. The performance security will be released after successful completion of works
and rectification of defects during defect liability period. In case contractor fails to
rectify the defects during defects during defect liability period, MADC will carry out
the works at contractor’s risk and cost .the cost along with Administrative charges of
12% will be recovered from the performance security. Additional Performance
Security shall be submitted by Contractor as per appendix to tender (Contract Data)
Section II-B, if bid found imbalance.
Sub Clause 4.3.1: Contractor's Representative
The Contractor shall supply to the Engineer the details of all the Supervisory and other
staffs employed by the Contractor and notify changes when made and satisfy the
Engineer regarding the quantity and sufficiency of the staff thus employed. The
Engineer will have the unquestionable right to ask for changes in the quality and
number of Contractor's Supervisory staff. The Contractor shall comply with such
orders and effect replacement to the satisfaction of the Engineer.
Contractor MADC
Page | 28
The checking of any setting- out or of any line or level by the Engineer shall not
in any way relieve the Contractor of his responsibility for the accuracy thereof and
the Contractor shall carefully protect and preserve all bench- marks, sight-rails,
pegs and other things used in setting- out the Works. In addition to above the
checking at all the setting out of the proposed works relative to existing ground
features to be undertaken prior to the commencement of fabrication of structural
steel works for superstructures complete, including providing the facility for the
Engineer to undertake a timely check on this setting out and alerting the Engineer
to any likely problems foreseen.
The Contractor shall give to the Engineer not less than 48 hours of notice of his
intention to set out or give layout for any part of the works so that timely
assignment can be made for checking the same.
Contractor MADC
Page | 29
Contractor MADC
Page | 30
Contractor MADC
Page | 31
Contractor MADC
Page | 33
h. The Contractor shall be responsible for the return to the place from where they
were recruited or to their domicile of all such persons as he recruited and
employed for the purpose of or in connection with the contract and shall
maintained such persons as are to be referred in a suitable manner until they
shall have left the site.
i. The register of workmen and the register of wages cum muster roll required to
be maintained under these Regulation shall be preserved for 3 years after the
date on which the last entry is made therein.
j. On any question as to the application, interpretations or effect of these Rules,
the decision of the Chief Labour Commissioner or Deputy Labour
Commissioner shall be final and binding.
Contractor MADC
Page | 34
Contractor MADC
Page | 35
Contractor MADC
Page | 36
Contractor MADC
Page | 37
CLAUSE 8
Sub Clause 8.2.1:
Time for completion
Time for completion shall be period as mentioned in Contract Data in Section-II of
Volume-II.
The Contractor shall furnish within the period stipulated in writing by the Engineer a
detailed programme schedule using suitable computerized technique along with the
soft copy of the same in quadruplicate indicating the date of actual start, the monthly
progress expected to be achieved and the anticipated completion data of each major
item of work to be done by him, also indicating dates of procurement and setting up
of materials, plant and machinery.
Contractor MADC
Page | 38
The liquidated damages shall be levied for failure to reach, any or all of the
intermediate milestones as indicated in the Contract Data in Section-II of Volume-I
are not achieved. The liquidated damages thus recovered for failure to reach each
individual milestone will be refunded without interest, if the overall project is
completed in time.
Contractor MADC
Page | 39
CLAUSE 10
Sub Clause 10.3.1: Prevention from Testing
If the Contractor is prevented from carrying out the tests on completion by a cause for
which the Employer or the Engineer or other Contractors employed by the Employer
are responsible, the Employer shall be deemed to have taken over the works on the
date when the tests on completion would have been completed. But for such
prevention, the Engineer shall issue a Taking over Certificate accordingly, provided
always that the works shall not be deemed to have been taken over if they are not
substantially completed in accordance with the contract.
If the works are taken over under this sub-clause the contractor shall nevertheless
carry out the tests on completion during the Defects Liability period. The Engineer
shall require the tests to be carried out by giving 14 days notice.
Any additional costs to which the Contractor may be put, in making the tests on
completion during the Defects Liability Period shall be added to contract price.
CLAUSE 11
Sub Clause 11.1.1
Visit of Contractor during Defect Liability Period
Contractor would carry one inspection in every 3 months during the first year after
completion of the work and carry minimum 2 inspections per year for the remaining
years of Defect Liability Period.
CLAUSE 12
Sub Clause 12.2: Method of Measurements
Add at the end of this clause:
“The Engineer/Engineer’s Representative shall be responsible for ensuring that all
measurements are taken from the approved RFI as per specifications and drawings for
the Works and are recorded in the measurement book of the Employer.
Contractor MADC
Page | 40
CLAUSE 13
Sub Clause 13.1.1:
Valuations of Variations
All variations referred to in Clause 13.1 and any additions to the Contract price which
are required to be determined in accordance with Clause 13 (for the purposes of this
Clause referred to as “Variations & Adjustments”), shall be valued at the rates and
prices set out in the Contract if, in the opinion of the Engineer, the same shall be
applicable. If the Contract does not contain any rates or prices applicable to the
Variations & Adjustments, the rates and prices in the Contract shall be used as the
basis for valuation so far as may be reasonable, failing which, after due consultation
by the Engineer with the Employer and the Contractor, suitable rates or prices shall be
agreed upon between the Engineer and the Contractor. In the event of disagreement,
the Engineer shall fix such rates or prices as are, in his opinion, appropriate and shall
notify the Contractor accordingly, with a copy to the Employer. Until such time as
rates or prices are agreed or fixed, the Engineer shall determine provisional rates or
prices to enable on–account payments to be included in certificates issued in
accordance with Clause 14.
Sub Clause 13.1.2: Power of Engineer to fix Rates
Provided that if the nature or amount of any Variations & Adjustments relative to the
nature or amount of the whole of the Works or to any part thereof, is such that, in the
opinion of the Engineer, the rate or price contained in the Contract for any item of the
Works is, by reason of such varied work, rendered inappropriate or inapplicable,
then, after due consultation by the Engineer with the Employer and the Contractor, a
suitable rate or price shall be agreed upon between the Engineer and the Contractor.
In the event of disagreement, the Engineer shall fix such other rate or price as is, in
his opinion, appropriate and shall notify the Contractor accordingly, with a copy to
the Employer. Until such time as rates or prices are agreed or fixed, the Engineer shall
determine provisional rates or prices to enable on–account payments to be included in
certificates issued in accordance with Clause 14.
Contractor MADC
Page | 41
Provided also that no Variations & Adjustments instructed to be done by the Engineer
pursuant to Clause 13 shall be valued under Sub Clause 13.1.1 or under this Sub
Clause unless, within 14 days of the date of such instruction and, other than in the
case of omitted work, before the commencement of the varied work, notice shall have
been given either:
(a) By the Contractor to the Engineer of his intention to claim extra payment or a
varied rate or price, or
(b) By the Engineer to the Contractor of his intention to vary a rate or price,
(c) Provided further that no change in the rate or price for any item contained in
the Contract shall be considered unless such item accounts for an amount more
than 1 percent of the Contract Price.
(d) In case of increase in the overall contract value due to increase in the
quantities of work is upto and including 25%, no separate claim for payment
shall be entertained. However, any increase beyond 25%, the client shall take
a decision whether or not to get extra work done from same contractor. If the
client so decides to execute the extra work by the same contractor, the rates for
such items shall be in accordance with the procedure laid down in the Clause
No. 13 of Sub clause 13.8 (Contract Data) in Section II of Volume II.
In case of decrease in the overall contract value due to decrease in the
quantities of work by more than 25 %, the rate for the quantity shall be fixed
on the basis of prevailing DSR of the region or by working out the rate for
such items which are not covered in the DSR, in accordance with the
procedure laid down in the Clause No. 13 of Sub clause 13.8 (Contract
Data) in Section II of Volume II.
Contractor MADC
Page | 42
Contractor MADC
Page | 43
Contractor MADC
Page | 44
Sub Clause 13.8.1 The following conditions shall prevail for adjustment of
changes in cost:
i) The operative period of the contract shall mean the period commencing
from the date of work order issued to the Contractor and ending on the
date on which the time allowed for the completion of the works
specified in the contract for work expires, taking into consideration the
extension of time, if any, for completion of the work granted by the
Engineer under the relevant clause of the Conditions of Contract in
cases other than those where such extension is necessitated on account
of default of the Contractor. The decision of the Engineer as regards the
operative period of the contract shall be final and binding on the
Contractor. Where any liquidated damages is levied on the contractor
on account of delay in completion or inadequate progress under the
relevant contract provisions, the price adjustment amount for the
balance of work from the date of levy of liquidated damages shall be
worked out by pegging the respective indices to the levels
corresponding to the date from which such liquidated damages are
levied.
The price variation under this clause shall not be payable for any
additional items required to be executed during the completion of the
work and also on the excess quantities of B.O.Q. items payable under
the provisions of Clause 13.1.2 of the contract respectively. Since the
rates payable for additional items or the extra quantities under Clause
13.1.2 are to be fixed as mutually agreed between the Engineer,
Employer and Contractor subject to yearly revision till completion of
such work. In other words, when the completion / execution of extra
items as well as additional quantities under Clause 13.1.2 of the contract
extends beyond the operative date of the contract then rates payable for
the same beyond that date shall be revised with reference to the current
market price prevalent at that time on year to year basis or revised in
accordance with mutual agreement thereon, as provided for in the
contract, whichever is less.
Contractor MADC
Page | 45
ii) This clause is operative both ways, i.e. if the price variation as
calculated above is on the plus side, payment on account of the price
variation shall be allowed to the Contractor and if it is on the
negative side, the Employer shall be entitled to recover the same
from the Contractor and the amount shall be deductable from any
amounts due and payable under the contract.
To the extent that full compensation for any rise or fall in costs to
the Contractor is not entirely covered by the provision of this or
other clauses in the contract, the unit rate and prices included in the
contract shall be deemed to include amount to cover the contingency
of such other actual rise or fall in costs.
13.8.2 If secured advance is paid to the Contractor on any of the above base
materials as per Sub Clause 14.2.3, which is likely to be consumed in
reasonable time on the usual conditions, the escalation towards that supply
can be paid based on the above formula by considering price indices in the
month of supply for which the secured advance is paid.
CLAUSE 14
Add Sub Clause 14.2: Advance Payment (Mobilization Advance)
The Employer will pay mobilization advance to the Contractor if the same is
requested by the Contractor in writing within three months of the date of notice to
proceed with the work, towards mobilization in respect of the works in a lump sum
amount equivalent to as per Contract Data.
Payment of the advance will be due under separate certification by the Engineer after:
i) Execution of the form of agreements by the parties thereto,
ii) Provision by the Contractor of the performance security in accordance with
Clause 4.2,
Contractor MADC
Page | 46
(f) The sum payable for such materials on site shall not exceed seventy five
(75) percent of the related
i) CIF price of imported materials or
ii) Ex-factory / Ex-warehouse price of locally manufactured materials or
iii) Stockpile value of locally produced materials such as coarse
aggregates and crushed stone.
(g) The materials are of an imperishable nature.
(h) A formal agreement is drawn up with the Contractor under which the
Employer secure a lien on the materials and is safe-guarded against losses
due to the Contractor postponing the execution of the work or to the
shortage or misuse of the materials and against the expenses entailed for
their proper watch and safe custody. (Sample form enclose-Page no. 80)
(i) a) No advances are made for any materials unless they are to be used
within three months at the most, and
b) Material on which advance is made shall be consumed on the work
within three months from the date of advance. In case material remains
unutilized beyond 3 months the balance quantity shall be recovered in
next IPC.
(j) Recoveries of advances so made shall be made from the intermediate bills
for work done as the materials are used, the necessary deduction being
made whenever the items of work in which they are used are billed for.
Guarantees will be released by the Employer one by one in such a manner that
the total amount of Bank Guarantees left in hand with the Employer will be
sufficient to cover the outstanding amount of advance and likely interest
thereon.
Sub Clause 14.3: Retention money.
The percentage of retention money to be deducted shall be as per Contract Data in
Section-II of Volume-II and the limit of Retention Money shall be as per Contract
Data in Section-II of Volume-II.
Sub Clause 14.6.1:
The minimum amount of Interim Payment Certificate shall be as per Contract Data
in Section-II of Volume-II.
Contractor MADC
Page | 50
Contractor MADC
Page | 51
CLAUSE 18
Sub Clause 18.1: General Requirement for Insurance.
General Requirement for Insurance shall be as per Contract Data in Section-II of
Volume-II.
Sub Clause 18.3: Insurance against injury to persons and damage to property
Insurance against injury to persons and damage to property shall be as per Contract
Data in Section-II of Volume-II.
Contractor MADC
Page | 52
CLAUSE 19
Sub Clause 19.1 Force Majuro
(a) For the purposes of this contract, “Force Majuro” means an event which is
beyond the reasonable control of a party and which makes parties performance
of its obligations hereunder impossible or so impractical as reasonably to be
considered impossible in the circumstances, and includes, but is not limited to,
war, riots, civil disorder, earthquake, fire explosion, storm, flood or other
adverse weather conditions, strikes, lockouts or other industrial action (except
where such strikes, lockouts or other industrial action are within the power of
the party invoking Force Majuro to prevent), confiscation or any other action
by government agencies or by an order of any court of law.
(b) Force Majuro shall not include (i) any event which is caused by the negligence
or intentional action of a party or such party’s sub consultants or agents or
employees, nor (ii) any event which a diligent party could reasonably have
been expected to both [A] take into account at the time of the conclusion of this
contract and [B] avoid or overcome in the carrying out its obligations
hereunder.
(c) Force Majuro shall not include insufficiency of funds or failure to make any
payment required hereunder.
Contractor MADC
Page | 53
i) No Arbitration is allowed.
ii) In case of disputes or differences of opinion arising between the Engineer and
the Contractor, the Contractor shall refer the matter to the Engineer within 15
days of the rejection of the claim by the Engineer. The Engineer upon receipt
of such representation shall decide the matter within 15 days. In case the
Engineer’s decision is not acceptable the Contractor shall refer the matter to
the Vice Chairman and Managing Director, Maharashtra Airport Development
Co. Ltd. within 15 days of the decision of the Engineer. The Vice Chairman
and Managing Director shall decide the matter within 45 days upon receipt of
such representation. The decision of the Vice Chairman and Managing
Director shall be final and binding on the Contractor.
(a) (i) The Employer is Vice Chairman and Managing Director, Maharashtra Airport
Development Co. Ltd.,
Contractor MADC
Page | 54
(b) (i) The Engineer is Superintending Engineer, MADC or any other firm / person
nominated by VC & MD, MADC
Address : Central Facility Building-B Wing (North) 1st floor,
MIHAN, SEZ, Khapri, Railway, Nagpur-441108
________________ ____________________________
Signature of Bidder The Engineer (MADC)
Date: Date:
Contractor MADC
Page | 55
PART-II-B
SPECIAL CONDITIONS OF CONTRACT / SUPPLEMENTARY
INFORMATION
Contractor MADC
Page | 56
Contractor MADC
Page | 57
site or provide any other service of whatsoever nature, for any such the
Employer shall pay to the Contractor in respect of such use of service such
sum or sums as shall in the opinion of the Engineer be reasonable.
11.0 ENVIRONMENTAL SAFEGUARDS
The Contractor shall take action of following points and note the stipulations
as under as regards environmental safeguards as stipulated by the Ministry of
Environment and Forests.
11.1 Appropriate measures shall be undertaken while undertaking digging activities
to avoid degradation of water quality.
11.2 Borrow pits and other scars created during the road construction shall be
properly levelled and treated.
11.3 Adequate provision for infrastructural facilities, i.e. water supply, fuel,
sanitation, etc. shall be ensured for labours during construction period in order
to avoid damage to the environment.
11.4 No excavation from or dumping of waste materials into any water body /
wetlands shall be done.
11.5 Borrow sites for earth, quarry sites for road construction and dump site shall
be identified keeping in view:
a) No excavation or dumping on private property is carried out without
written consent of the owner.
b) No excavation or dumping shall be allowed or wetlands, forests areas or
other ecologically valuable or sensitive locations.
c) The excavation work shall be done in consultation with soil conservation
and watershed development agencies working in the area:
d) Construction spoil including bituminous material and other hazardous
material must not be allowed to contaminate water course and the dump
sites for such materials must be identified well in advances before
construction and lined properly so that they do not leach into the ground
water.
11.6 The trees, which are necessary to be felled should be identified before hand
and necessary approval from the competent authority should be obtained for
felling the same. Sufficient number of trees of suitable species should be
planted in lieu of the trees felled.
11.7 A contingency plan shall be prepared to combat with accidents so that the
victims of accident can be provided immediate medical help. Some essential
equipment, building and other facilities may be required for the purpose.
Contractor MADC
Page | 59
11.8 The Employer or any other competent authority may stipulate any other
condition for environmental safeguard, subsequently, if deemed necessary,
which should be compiled with.
11.9 The above mentioned stipulations shall be enforced among others under the
Water (Prevention and Control of Pollution) Act, 1974, the Air (Prevention
and Control of Pollution) Act, 1981 the Environment (Protection) Act 1986,
the Hazardous Chemicals (Manufacture, Storage and Import) Rule, 1989, the
Environmental Impact Assessment (EIA) Notification 1994 and its
amendment of May 1994, April 1997, January 2000, the Public Liability
Insurance Act 1991 and these rules amended under from time to time.
12.0 DELETED
14.0 TAXES
15.0 QUARRIES
The contractor will have to make his own arrangement of acquiring land for
quarries. The contractor shall carry out all quarrying operations without
endangering the environment and natural beauty of surrounding.
Contractor MADC
Page | 60
Annexure-AI
Salient features of some major Labour Laws applicable to establishments
engaged in Construction of Civil Works
(i) Workmen Compensation Act, 1923 or Amendment thereof
The Act provides for compensation in case of injury by accident arising out of
and during the course of employment.
(v) Contract Labour (Regulation and Abolition) Act, 1970 or Amendment thereof
The Act provides for certain welfare measures to be provided by the Contractor
to contract labour and in case the Contractor fails to provide, the same are
required to be provided by the Principal Employer by Law. The principal
employer is required to take Certificate of Registration and the Contractor is
required to take a License from the designated Officer. The Act is applicable to
the establishments or Contractor of principal employer if they employ 20 or
more contract labour.
Contractor MADC
Page | 61
(xiii) Child Labour (Prohibition and Regulation) Act, 1986 or Amendment thereof
The Act prohibits employment of children below 14 years of age in certain
occupations and processes and provides for regulation of employment of
children in all other occupations and processes. Employment of child labour is
prohibited in Building and Construction Industry.
(xiv) Inter-State Migrant Workmen's (Regulation of Employment and Conditions of
Service) Act, 1979 or Amendment thereof
The Act is applicable to an establishment which employs 5 or more inter-state
migrant workmen through an intermediary (who has recruited workmen in one
state for employment in the establishment situated in another state). The inter-
state migrant workmen, in an establishment to which this Act becomes
applicable, are required to be provided certain facilities such as housing,
medical aid, travelling expenses from home upto the establishment and back, etc
(vi) Minimum Wages Act, 1948 or Amendment thereof
The employer is supposed to pay not less than the Minimum Wages fixed by
appropriate Government as per provisions of the Act if the employment is a
scheduled employment. Construction of Buildings, Roads, and Runways are
scheduled employment.
(vii) Payment of Wages Act, 1936 or Amendment thereof
It lays down as to by what date the wages are to be paid, when it will be paid
and what deductions can be made from the wages of the workers.
(xv) The Building and Other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 and the Cess Act of 1996 or Amendment
thereof
All the establishments who carry on any building or other construction work and
employs 10 or more workers are covered under this Act. All such establishments
are required to pay Cess at rate not exceeding 1% of the cost of construction as
may be notified by the Government. The employer of the establishment is
required to provide safety measures at the Building or Construction work and
other welfare measures, such as Canteens, First-aid facilities, Ambulance,
Housing accommodation for Workers near the workplace etc. The employer to
whom the Act applies has to obtain a registration certificate from the
Registering Officer appointed by the Government.
Annexure-A II
Safety & Welfare Provisions for labour to be employed by the Contractor
All necessary personal safety equipment as considered adequate by the Engineer shall
be available for use of persons employed on the Site and maintained in a condition
suitable for immediate use; and the Contractor shall take adequate steps to ensure
proper use of such equipment by those concerned in accordance with updated
provisions under code.
1. Safety Provisions:
The Contractor shall comply with all the precautions as required for the safety
of the workmen.
(i) All workmen at site shall be provided with safety helmets and
yellow/orange jackets. Workmen required on site during night hours
shall be provided with fluorescent yellow jackets with reflective lopes.
(ii) Workers employed on mixing asphaltic materials, cement, lime
mortars, concrete etc. shall be provided with protective footwear,
protective goggles.
(iii) Those engaged in handling any material, which is injurious to the
eyes, shall be provided with protective goggles.
(iv) Those engaged in welding works shall be provided with welder's
protective eye-shield.
(v) Stone breakers shall be provided with protective goggles and
protective clothing and seated at sufficiently safe intervals.
Suitable scaffolds shall be provided for workmen for all work that
cannot safely be done from the ground, or from solid construction
except for such short period work as can be done safely from ladders.
When a ladder is used, an extra labourer shall be engaged for holding
the ladder and if the ladder is used for carrying materials as well,
suitable foot-holds and hand-holds shall be provided on the ladder,
which shall be given an inclination not steeper than 1/4 to 1.
(vii) Scaffolding or staging more than 3.25 metres above the ground or
floor, swung or suspended from an overhead support or erected with
stationary support, shall have a guard rail properly attached, bolted,
braced and otherwise secured at least 1 metre high above the floor or
platform of such scaffolding or staging and extending along the entire
length of the outside and ends thereof with only such openings as may
be necessary for the delivery of materials. Such scaffolding or staging
shall be so fastened as to prevent it from swaying from the support or
structure.
Contractor MADC
Page | 64
Contractor MADC
Page | 65
(xiii) When workers are employed in sewers and manholes, which are in
use, the Contractor shall ensure that manhole covers are open and
manholes are ventilated at least for an hour before workers are allowed
to go into them. Manholes so open shall be cordoned off with suitable
railing and provide warning signals or boards to prevent accidents to
the public.
(xiv) Demolition: Before any demolition work is commenced and also
during the process of the work:
a) All roads and open areas adjacent to the work site shall either be
closed or suitably protected.
b) No electric cable or apparatus, which is liable to be a source of
danger other than a cable or apparatus used by operators, shall
remain electrically charged:
c) All practical steps shall be taken to prevent danger to persons
employed by the Employer, from risk of fire or explosion, or
flooding. No floor, roof or other part of a building shall be so
overloaded with debris or materials as to render it unsafe.
(xv) When work is performed near any place where there is risk of
drowning all necessary equipment shall be provided and kept ready for
use and all necessary steps taken for prompt first aid treatment of all
injuries likely to be sustained during the course of the work.
Contractor MADC
Page | 66
(xviii) All scaffolds, ladders and other safety devices mentioned or described
herein shall be maintained in a safe condition and no scaffold, ladder
or equipment shall be altered or removed while it is in use. Adequate
washing facilities shall be provided at or near places of work.
(xix) These safety provisions shall be brought to the notice of all concerned
by displaying on a notice board at a prominent place at the work
location. Persons responsible for ensuring compliance with the Safety
Code shall be named therein by the Contractor.
No. of Seats
2 (a) Where number of persons does not exceed 50
In particular cases, the Engineer shall have the power to increase the
requirement, wherever necessary.
Contractor MADC
Page | 68
Contractor MADC
Page | 69
SECTION-III
Note:- This letter to be included in Volume-III and to be sealed as per CI. 17.4 of ITB
Name of Work:-
To,
The _________________
Maharashtra Airport Development Co. Ltd.
_____________________
(As per Invitation for Bid)
2. We acknowledge that the Volume I, Volume II, Volume III and Volume IV
together with any addendum and common set of deviations thereto form part
of Bid.
Contractor MADC
Page | 71
4. We agree to abide by this bid for the period of (as per Invitation for Bids
(IFB) in volume II) days from the date fixed for receiving the same and it
shall remain binding upon us and may be accepted at any time before the
expiration of that period. We acknowledge that the appendix forms the part
of this letter.
5. Unless and until a formal Agreement is prepared and executed for this bid,
together with your written acceptance thereof, shall constitute a binding
contract between us.
6. We understand that you are not bound to accept the lowest or any bid you
may receive.
Address….…………………………………………………………………………
Occupation. …………………………………………..
(To be filled in by the Bidder, together with his particulars and date of submission at
the bottom of the form of Bid)
Contractor MADC
Page | 72
SECTION-IV
No.: Date:-
To,
----------------------------------------
----------------------------------------
----------------------------------------
-----------------------------------------
Subject:- (Name of Work)
Dear Sirs,
You are hereby requested to furnish performance security in the form as detailed in
clause 4.2.1 of Particular Conditions of Volume I- Section II- part II of bid document
for an amount equivalent to Rs…………………………….. within 15 days of the
receipt of this letter of acceptance and sign the Contract, failing which action as
stated in para 15.5 of I.T.B will be taken.
Yours faithfully,
Contractor MADC
Page | 73
No.: Date.:-
To,
__________________________
__________________________
__________________________
Subject.:- (Name of Work)
Reference.:- 1. __________________________________________________
2. __________________________________________________
Sir,
Your offer for Rs. ____________ (Rs. _________________________) only is
accepted by Corporation vide letter under reference no. 1.
You have submitted performance security deposit of Rs. ____________
(Rupees_______________________________only) in the form of Bank guarantee
vide your letter under reference no. 2.
The agreement for the work is also signed by your authorized signatory on dated.
________ Therefore, you are requested to commence the work immediately and
complete it within _____ (_____________________________________) Calendar
months including monsoon from the date of issue of this work order.
Certified copy of agreement (Agmt. No. _____________________________) is
enclosed herewith.
Encl.: - One Agreement Copy.
Yours faithfully,
Contractor MADC
Page | 74
SECTION-V
SAMPLE FORM OF CONTRACT AGREEMENT
(Agreement will be drawn separately on the stamp paper of Rs. 100/-
denomination)
Contractor MADC
Page | 75
1. The document which forms part of the Contract will be the Bid Notice, General
Bid Notice including Corrigendum to Bid Notice, Volume - I, Volume - II,
Volume - III (Financial offer), Volume - IV (Specifications & Drawings),
Appendix to Tender, common set of deviations, addendums to bid, accepted
technical proposal, letters of correspondence for negotiation and letter of
acceptance thereof. It is further agreed that the work order/ letter of
commencement No. _______________ Dated _________shall construe the
Contract between the parties.
3. In consideration of the due provision, execution and completion of the said works,
the Company does hereby agree that the Company will pay to the Contractor the
respective amount for the work actually done by him as per the terms and
conditions of the Contract.
4. All disputes arising out of or in any way connected with this agreement shall be
deemed to have arisen in Mumbai and only the courts in Mumbai shall have
jurisdiction to try and adjudication over them.
Contractor MADC
Page | 76
Signature
Designation
In the presence of :
1)____________________________ Address
_________________________________
2)___________________________ Address _________________________________
In the presence of :
1)____________________________Address _______________________________
2)____________________________Address _______________________________
Contractor MADC
Page | 77
SECTION-VI
FORM F1
1 2 3 4 5 6 7
Contractor MADC
Page | 78
FORM F2
Sr. Name and Name Place Tendered Time Date Cost of Cost of
No Address of of of Cost Period of work work to
the work work work completed be
Organization order On ( $ ) completed
for whom during
work is The years
being
carried out
Rs. In
Lakh months
1 2 3 4 5 6 7 8 9
Contractor MADC
Page | 79
FORM F3
Sr. Name of No. Kind Capacity Age of Present Present Whether the
No Equipment of and Machinery condition Location machinery is
Units Make of with name hypothecated
Machinery and address to any bank
of or institution
organization
where
machinery
is in use
1 2 3 4 5 6 7 8 9
Signature of Bidder
Contractor MADC
Page | 80
FORM F4
1 2 3 4 5
Signature of Bidder
Contractor MADC
Page | 81
FORM – F5
1st, 2nd etc are weeks from the start of work order
Sr. Item of 1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th 12th
No. Activity
(Work)
Note: Indicate clearly which responsibility and what authority have been delegated
to site management.
Contractor MADC
Page | 82
FORM F6
QUALITY ASSURANCE REQUIREMENTS
ELEMENT OF QUALITY SYSTEM
The applicant(s) are required to provide details of their Quality Assurance Systems for
criteria stipulated below, preferably in the form of their Quality Manual to be
enclosed separately within 15 days of the acceptance of tender in case the system is
not finished in total, the extent to which it is completed and documented may be
submitted.
1. Management
1.1 Quality Policy
Responsibility
1.2 Organisation
a) Responsibility and authority
b) Resources
c) Management Representative
1.3 Management Review
2. Quality System
2.1 General Quality Manual
(ISO : 10013)
2.2 Quality System Procedure
2.3 Quality Planning
3. Contract Review
3.1 General Document Procedure
3.2 Review
3.3 Amendment to a Contract
3.4 Records
4. Design Control
4.1 General Document Procedure to DC
4.2 Design & Development Planning
4.3 Organization & Technical Inter Phases
4.4 Design Input
4.5 Design Output
4.6 Design Review
4.7 Design Verification
4.8 Design Validation
4.9 Design Charges
Contractor MADC
Page | 83
6. Process Control
a) Documented Procedures
b) Suitable Equipment
c) Compliance of Quality Plan with respect to relevant codes.
d) Monitoring and Control of Indicator Properties.
e) Approval of Process and equipment
f) Workmanship
9. Control of Non-conforming
9.1 General Product.
9.2 Review & Disposition of nonconforming product.
Contractor MADC
Page | 84
14. Training
15. Servicing
Contractor MADC
Page | 85
FORM 7
SAMPLE FORM OF
DECLARATION OF THE CONTRACTOR
SIGNATURE OF CONTRACTOR
Contractor MADC
Page | 86
AND
Contractor MADC
Page | 87
3. a) The guarantee herein contained shall remain in full force and effect during the
subsistence of the said Agreement and that the same will continue to be
enforceable till all the dues of the Maharashtra Airport Development Co. Ltd.
under or by virtue of the said Agreement have been duly paid and its claims
satisfied or discharged and till the Maharashtra Airport Development Co. Ltd.
certifies that the terms and conditions of the said Agreement have been fully
properly carried out by the Contractor.
b) We shall not be discharged or released from the liability under this Guarantee
by reasons of :
(i) Any change in the constitution of the Bank or the Contractor;
(ii) Any agreement entered into between the Maharashtra Airport Development
Co. Ltd. and the Contractor with or without our consent;
(iii)Any forbearance or indulgence shown to the Contractor;
(iv) Any variation in the terms, covenants or conditions contained in the said
Agreement;
(v) Any time given to the Contractor; or
(vi) Any other conditions or circumstances under which, in law; a surety would be
discharged.
c) Our liability hereunder shall be joint and several with that of the Contractor as
if we were the principal debtors in respect of the said sum of
Rs.___________________(Rupees
_________________________________only).
We shall not revoke this guarantee during its currency except with the
previous consent in writing of the MADC.
Shri _________________________________________________________________
Son of _______________________________________________________________
Resident of ___________________________________________________________
Carrying on business of _________________________________________________
Under the name and style of _____________________________________________
At __________________________________________________________________
Hereinafter called “The Contractor” which expression shall where the context does
not so admit include his heirs, executors and administrators.
1. Shri______________________________________________________________
Son of _______________________________________________________________
Resident of ___________________________________________________________
And _________________________________________________________________
2. Shri ______________________________________________________________
Son of _______________________________________________________________
Resident of ___________________________________________________________
and carrying on business in partnership under the firm name and style of _________
_____________________________________________________________________
at ___________________________________________________________________
hereinafter collectively referred to as “the Contractor” (which expression shall where
the context does not so admit include them the survivors) of them, the heirs, executors
and administrators of the last survivor the partners or partner for the time being of the
said firm of
_________________________________________________________________
(*) In case of Limited Company.
(**) In case of individual.
(***) In case of partnership firm.
Contractor MADC
Page | 89
SCHEDULE – ‘D’
SAMPLE FORM OF DETAILS OF PROPOSED SUB-CONTRACTORS /
SPECIALISED SUB-CONTRACTORS
Proposal for subcontracting components of the works amounting to more than 10% of
the contract price
Note:- In no case, the Contractor will be permitted to sublet more than 50% of value
of work including those to specialized sub-contractors.
Contractor MADC
Page | 90
Information regarding Litigation / Arbitration during last five years in which the
bidder is involved, the parties concerned and disputed amount.
($) Preceding 5 years to be reckoned from the 31st March of the last financial
year.
Contractor MADC
Page | 91
Tender Document
FOR
Volume-II
AUGUST- 2024
Contractor MADC
Page | 92
Volume – II
Contractor MADC
Page | 93
TENDER DOCUMENT
FOR
VOLUME - II
_________________________________________________
(MADC)
Contractor MADC
Page | 94
INDEX
_________________ ___________________________________
Signature of Bidder Authorized Representative (MADC)
Date : Date :
Contractor MADC
Page | 95
SECTION I
The MADC invites sealed bids from reputed contractors having experience in execution of similar
nature of work for the construction of following work.
Description of work : Repair and Maintenance work of RCC trench and Manholes for OFC along
roads in MIHAN area at Nagpur.
Estimated cost of work : Rs.20,08,332/-
Time limit for : 06 Months (Six Months) Including Monsoon.
completion
Earnest Money Deposit /Bid : Rs 21,000/- (Rupees Twenty One Thousand only) to be paid via online
security payment gateway mode. The information of e- Payment Gateway is
available on E-Tendering Website http://mahatender.gov.in Valid payment
receipt of appropriate amount in PDF format to be uploaded vide technical
bid
Note: -
1. Request for sending the tender form by post / courier will not be entertained under any circumstance.
Tender shall be downloaded from the e-tender Portal & submitted online through e-tender
portal only.
2. MADC reserves right to accept or reject any bid or all bids without assigning any
reasons whatsoever.
( )
Authorized Representative MADC).
Contractor MADC
Page | 96
SECTION II A
BIDDING DATA
1.0 SCOPE OF BID:
1.1 Vice Chairman & Managing Director, Maharashtra Airport Development
Co. Ltd., 8th Floor, World Trade Centre, Cuffe Parade, Mumbai – 400005
(hereinafter referred to as Employer in these documents) invites bids for
construction of works (as defined in these documents and referred to as
“the works”) detailed in Section –III.
2.1.4 The bidder should have achieved a minimum average annual turnover in
the last three years equal to 75% of the estimated cost put to bid (As per
audited profit & Loss account)
2.1.5 The bidder should have experience of having successfully completed
during last Seven years.
a) Three similar works completed of costing not less than the amount equal
to 40% of the estimated cost OR
b) Two similar works completed of costing not less than the amount equal
to 50% of the estimated cost OR
c) One similar works completed of costing not less than the amount equal
to 80% of the estimated cost
Contractor MADC
Page | 97
2.1.6 In case of bidder applying for this bid, has earlier worked with MADC,
then in that case bidder while applying for this bid, mandatorily needs to
submit a satisfactory work performance certificate (for
complete/incomplete work) from MADC for all the works/assignments
undertaken by him in Last three years.
It is further to specify that, said certificate should have been issued by
MADC in the preceding one year. If the said certificate is prior to
preceding one year, then bidder shall get the said certificate revalidated
from MADC.
3.2.3-A Financial Criteria
The prospective bidders will be qualified only if they have minimum
financial capacities as below:
i) Working capital (current assets-current liabilities) –
Working capital (Net cash flow) of the prospective bidder during last
audited financial year shall be greater than 1.00 Crore (should be
certified by the Chartered Accountant).
ii) Profit after tax shall be positive For “Two Years” out of last three
consecutive financial years, such that it should be positive for
immediate last financial year and one year out of two previous years.
iii) Net worth of the prospective bidder shall be 50% of cost put to tender
certified by CA.
3.2.3-B The bidder should have bid capacity more than the estimated cost put to
tender as per bid capacity formula indicated as below.
Available Bid Capacity = (A x N x 2.5) – B
where A = Maximum value of Civil Engineering works executed in any
one year during the last 3 years (updated to the current year by a factor of
escalation of 8% per year) which will take into account the completed and
ongoing works.
B = Value of existing commitments and works (Ongoing) to be completed
in the period stipulated for completion of work in present tender.
N = Number of years prescribed for completion of work for which bids are
invited.
Note :- The statements showing the value of existing commitments and
ongoing works as well as the stipulated period of completion
remaining for each of the works listed should be counter signed by
the respective Employer or his authorized representative.
Contractor MADC
Page | 98
3.2.3-C The bidder should have following minimum machinery in the name of the
firm:
S. Name of Equipment Minimum Minimum
No Capacity Quantity (Nos.)
1 JCB 2
2 Drum type Hot Mix Plant (DM 60) 40/60 TPH 1
3 Tandem Vibratory Roller 1
4 Sensor Paver Finisher Up to 5.5 m 1
5 Mechanical Bitumen Sprayer 6 MT 1
6 Air Compressor / Tractor Sweeper 1
7 Dumper/Tipper 16 Ton 6
8 Water tanker 8000-10000 Lit. 2
Note: a) Drum type Hot Mix Plant should be in working condition and should
be certified by competent authority.
b) The distance from the hot mix plant site to the farthest point of the
work shall not more than 60Km
3.2.4 The bidder shall also submit the following qualification documents.
i) Authority to seek references from the bidder's bankers.
ii) Justification of the bidder for their capability of completing the work as
per milestone specified within the stipulated period of completion with
the following documents:
● Proposed Work Plan.
● Methodology of construction.
● Equipment, Planning and Development with broad calculation.
● Quality control procedure.
3.2.5 For executions of similar nature of work under Para 2.1.5 a certificate from the
Officer In-charge not below the rank of Executive Engineer of the concerned
Department (Government/Semi Government) shall be furnished. Certificate
for executions of similar nature of work under Para 2.1.5 from Private
Organization will not be accepted.
3.2.6 The bidder shall submit the documents specified under Para 17.2 of ITB of
Volume-I in Envelop No. 1.
Contractor MADC
Page | 99
_________________ ___________________________________
Signature of Bidder Authorized Representative (MADC)
Date : Date :
Contractor MADC
Page | 100
SECTION II - B
Clause If sub clause 13.8 applies Adjustment for Changes in Cost Table(s) of
13.8 Adjustment Data
Components Percentages
Labour 16.89%
Material 74.43%
POL 8.68%
Materials (*) Rate/Base rate
(excluding GST)
Bitumen Base Rate of Bitumen
(respective grade)
VG-30=Rs.28040/-
VG-10=Rs.27240/-
Consumer price index Nagpur
for Industrial workers
for centre
Average price of HSD HSD rate for Nagpur
Centre on 28 days prior
to the last date of
receipt of the Bid.
Contractor MADC
Page | 103
________________ ________________________________
Contractor MADC
Page | 104
SECTION-III
SCOPE OF WORK
1.0 Introduction
Scope of work:-
(3) No extra payment for scaffolding to be used during work. Cost put to bid
is inclusive of all.
(4) All the items / materials required as per BOQ should be finalised /
certified through engineer in charge at Project Office Nagpur.
i) Repair and maintenance work of RCC Trench and Manholes for OFC
along roads in MIHAN area at Nagpur.
Contractor MADC
Page | 105
3.0 Terrain
Generally plain terrain is seen.
5.0 Temperature
June to September
Average annual rainfall 1000 mm
_________________ _________________________________
Signature of Bidder Authorized Representative (MADC)
Date : Date :
Contractor MADC
Page | 106
SECTION-IV
Adequately equipped field laboratory for quality of materials and the works
shall be provided. The items of equipment shall be provided in the field
laboratory depending upon the items to be executed, as per table 100-2
(Section 120 of MORT&H Specifications – Fifth Revision-2013)
_________________ ___________________________
Signature of Bidder Authorized Representative (MADC)
Date : Date :
Contractor MADC
Page | 107
Volume – III
Contractor MADC
Page | 108
Copy No.
TENDER DOCUMENT
FOR
VOLUME - III
_________________________________________________
Contractor MADC
Page | 109
VOLUME-III
BILL OF QUANTITY
INDEX
________________ ________________________________
Signature of Bidder Authorized Representative (MADC)
Date : Date :
Contractor MADC
Page | 110
PART-A
PREAMBLE
2. The bidder must quote his offer at the specified space in BOQ both in
words and figures.
3. The offer quoted shall except in so far as it is otherwise provided under the
contract, include all constructional plant, labour, supervision, materials, all
leads and lifts, erection, maintenance, insurance, profits, taxes, octroi, royalty,
LBT and duties together with all general risks, liabilities and obligations set
out or implied in the contract. Materials to be used in embankments and
unserviceable materials to be disposed should be with all leads and lifts.
Contractor MADC
Page | 111
6. Selected contractor has to execute the work in coordination with the other
contractors engaged by the employer for developing other Infrastructure works
like Water supply, Sewerage, Electrical T&D etc., in the area in order to
complete the respective works within the stipulated completion time.
7. Abbreviations Used
a) LM/Lm/RMT = Linear Meter / Running Meter
b) Cum. = Cubic Meter.
c) Sqm. = Square Meter.
d) Cucm = Cubic Centimetre
e) No. = Numbers
f) MT / Tonne = Metric Tonne
g) Hr = Hours
h) Ha = Hector
________________ ___________________________
Signature of Bidder Authorized Representative
(MADC)
Date : Date :
Contractor MADC
Page | 112
PART-B
FORM OF BID
(For Percentage Rate Bid)
Name of Work:-
To,
The _________________
Maharashtra Airport Development Co. Ltd.
_____________________
_____________________
(As per Invitation for Bid)
2. We acknowledge that the Volume I, Volume II, Volume III and Volume IV
together with any addendum and common set of deviations thereto form part
of Bid.
4 We agree to abide by this bid for the period of (as per Invitation for Bids
(IFB) in volume II) days from the date fixed for receiving the same and it
shall remain binding upon us and may be accepted at any time before the
expiration of that period.
5. Unless and until a formal Agreement is prepared and executed for this bid,
together with your written acceptance thereof, shall constitute a binding
contract between us.
Contractor MADC
Page | 113
6. We understand that you are not bound to accept the lowest or any bid you may
receive.
Address______________________________________________________
___________________________________________________________
Occupation. _______________________________________________
(To be filled in by the Bidder, together with his particulars and date of submission at
the bottom of the form of Bid)
Contractor MADC
Page | 114
NAME OF WORK: REPAIR AND MAINTENANCE WORK OF RCC TRENCH AND MANHOLES FOR OFC ALONG ROADS IN MIHAN AREA AT
NAGPUR.
BILL OF QUANTITIES
Contractor MADC
Page | 115
Contractor MADC
Page | 116
Contractor MADC
Page | 117
Contractor MADC
Page | 118
Volume – IV
Contractor MADC
Page | 119
TENDER DOCUMENT
FOR
VOLUME - IV
_________________________________________________
Contractor MADC
Page | 120
VOLUME-IV
SPECIFICATIONS
INDEX
_________________ _____________________________
Signature of Bidder Authorized Representative (MADC)
Date : Date :
Contractor MADC
Page | 121
PART-A
1. PREAMBLE
The Technical Specifications contained herein shall be read in conjunction with the
other Bidding Documents as specified in Volume-I
All defective works are liable to be demolished, rebuilt and defective materials
replaced by the contractor at his own cost. In the event of such work accepted by
carrying out repairs etc. as specified by the Engineer, the cost of repairs will be borne
by the contractor.
1.2.1 The information given hereunder and provided elsewhere in these documents is
given-in good faith by the Employer but the contractor shall satisfy himself regarding
all aspects of site conditions and no claim will be entertained on the plea that the
information supplied by the Employer is erroneous or insufficient.
Contractor MADC