ME 323
Instructor: Ramesh Singh
                                                       HW#1
                                     PHD QUALIFYING EXAM – SeptemberDate
                                                                     2021assigned: 16.08.2025
                                          MANUFACTURING PROCESSES -Date
                                                                   I    due: 24.08.2025
1.  You areMaximum
               designingmarks:
                             cylindrical
                                     100 risers for a gear housing that will be sand cast from          Time:aluminum
                                                                                                                3 hours
    alloy (This is an insulating mold). The risers are coated with an insulating sleeve so that
                  Only handwritten notes are allowed
    their heat transfer rate is 2.5 times lower than the sand mold. If the characteristic dimension
                  Make suitable assumptions, if required and clearly mention them.
    for heat transfer for the casting is 25 mm (V/A), determine the diameter of the risers. Assume
          -----------------------------------------------------------------------------------------------------------------
    there is no heat loss from the top surface of the risers.
2. You 1. are You
               designing     a sprue/runner/gate system to sand cast a component. The top of the sprue
                    are designing cylindrical risers for an engine block that will be sand cast from cast
    is 6 cm above the gate (hₜ), and has a pouring basin 1.5 cm deep (hb). The diameter of the top
              iron is(this
    of the sprue            is anThe
                      2.5 cm.     insulating
                                      molten mould).
                                               metal hasThe     characteristic
                                                            viscosity   2.0×10⁻³ dimension
                                                                                   N·s/m² and for density
                                                                                                   heat transfer
                                                                                                            2700 for   the
                                                                                                                   kg/m³.
    The mold     is top-gated.
              casting    is 30 mm (V/A). Assume that the riser is placed on the top of the casting and the
   • Use appropriate Reynolds number for gating design and comment on whether the flow is
              top or
        laminar   surface    of the and
                      turbulent,    riserthe
                                          is fully insulated.
                                              possible  implications for the casting quality.
   • Determine  a. Determine
                       a plausiblethediameter
                                      diameter ofof the
                                                     the runner
                                                         riser to avoid aspiration.                                     [5]
                 b. If we improve the insulation of the riser so that the rate of heat transfer in the riser is
3.   Determine the solidification time of the following two iron castings when both are poured
                 one-third
     with no superheats intoofsand
                               the sand mould,
                                    molds       determine
                                          at initial      the diameter
                                                     temperature       of the riser. Physically explain
                                                                 of 280C.
                     your findings.                                                                                  [10]
          •   A slab shaped casting 10 cm thick (h =10 cm) (Hint: Assume l, b >> h)
          •   A sphere 10 cm in diameter
          2. While casting an L section, a shrinkage cavity is formed as shown in (a) of Figure 1.Q2.
4.   While casting
            Explain an L section,
                     physically whyathe
                                     shrinkage
                                        shrinkagecavity
                                                  cavityisis formed
                                                             avoided as  shown
                                                                     in (b)      in of
                                                                            and (c) Figure   1. Explain
                                                                                       the Figure 1.Q2.
     physically why the shrinkage cavity is avoided in (b) and (c) in Figure 1.
                                                                                                                       [5]
                                                             Figure 1.Q2
                                            Fig. 1. Casting of L-section
          3. We need to fill a hemispherical mould cavity having a diameter of 100 mm using a middle
               gate arrangement shown in the Figure 2.Q3. The sprue height is 120 mm and the gate cross-
               section are 5 mm2. In order to fill the 3/4th volume of this mould, how much time would be
               required. Assume g = 10 m/s2.                1                                                        [15]
5.
     •   Find the cycle time for casting one part in a sand mold shown in Figure 1. The initial setup
         time to prepare the mold and melt (molten metal) and transport the melt to the pouring
         basin is 30 minutes. The post casting time for cooling, breaking and finishing is another 20
         minutes. Assume liquid metal level at X-X is constant and the time to fill the runner and
         vent is negligible. The cross-section of the mold is shown in Figure 1 and the depth (into
         the page) of the mold is 1.0 m. Assume that the iron is poured at melting temperature and
         ambient temperature is 250C.                                                           [15]
     •   If the top of the riser is insulated and there is 10% liquid volume shrinkage over the total
         volume, design a cylindrical riser for this casting.                                   [10]
     Properties:
     For Iron,
     Tm = 15400C, Hf = 272 KJ/kg, rcasting = 7850 kg/m3, kcasting = 83 W/mK
     For sand mold,
     cm = 1.17 KJ/kg.K, km = 0.8655 W/mK, rm = 1600 kg/m3
                       8*%492P)+DA#:+)99X+)
                  !                           !
              ,-.#%
                                                               8*%492P)+DA#:+)99X+)
               ,-/#%                                                                  ,-.0#%
                                        "#A%#&D(%)*)+
                                                                                       ,-"#%
                                         1)2*P#45#%46#.#%
                                                                       ,-"#%
                                  Figure 2: Cross-section of the mold