Saes X 700
Saes X 700
Contents
1 Scope ............................................................... 3
2 Conflicts and Deviations..................................... 5
3 References ....................................................... 5
4 Definitions and Abbreviations ............................. 7
5 Design Review and Approval ............................13
6 Design Technical Requirements ........................16
7 Installation, Records, Commissioning,
and Inspection..................................................40
Revision Summary..................................................41
1 Scope
1.1 This standard prescribes the minimum mandatory requirements governing the
design and installation of new cathodic protection (CP) systems protecting new
onshore metallic well casings. It may address existing wells if they are made
part of a group containing new wells.
Commentary Notes:
Replacements or in-kind replacements of existing, depleted or relocated anode
beds and/or CP systems do not need CSD approval except if they are part of a
new CP well installation. In such cases, existing wells do not need compliance
with the commissioning requirements specified in this standard, however
minimum monitoring current required shall be achieved as detailed in SAEP-333.
Existing well casings without flowlines that lasted more than 30 years with no CP
and no external corrosion leaks do not need a new CP system unless mandated by
the proponent organization. The application of new CP in this case is not
recommended as it could have adverse effects if gases resulting from the
application of CP promoted the removal the corrosion products that prevented
casing leaks. Exception is when CP systems are installed within 500 meters from
unprotected structures.
The cathodic protection requirements for offshore well casings are beyond the
scope of this standard and are addressed in SAES-X-300. Onshore well casings
with anodes installed offshore (i.e., Pyramid anode) however are within the scope
of this standard.
1.2 Cathodic protection systems for onshore well casings may be single dedicated,
shared (although not allowed by CSD) with negative bond, or multiple ICCP CP
systems.
Shared well casings are not allowed except for solar systems and multiple well
casings exceeding the limitations of multiple well casing CP system capacity
(more than 5 wells, requiring higher than 150 Amp TR, etc.) as detailed in
Section 6 below. In overlapping gas/oil fields, if a shared well CP system is
installed, then it will not be approved by CSD and it rather becomes the sole and
full responsibility of the proponent organization who approved/requested it,
Saudi Aramco: Company General Use
Page 3 of 49
Document Responsibility: Cathodic Protection Standards Committee SAES-X-700
Issue Date: 27 December 2017
Next Planned Update: 27 December 2020 Cathodic Protection of Onshore Well Casings
including the risk for well casing leak due to CP interference. Single well casing
CP system is not allowed where two wells are separated by less than 500 meters.
Drilling islands can have more than 5 wells connected to the same rectifier.
Galvanic anode are not normally used for well casing protection as the primary
permanent protection. Galvanic anode system could be used as a temporary
protection in areas where neither solar nor ICCP is practical if the soil resistivity
is promoting that option.
1.3 New, existing, carbon steel, stainless steel, coated, bare, onshore oil, gas,
unconventional gas, gas lift, observation, exploration, water injection, and water
supply metallic well casings with a predicted life expectancy greater than five
years shall be provided with cathodic protection within the time period specified
in Section 7 of this standard if:
a. The well casing is installed through a corrosive formation, or
b. The well casing is not installed through a corrosive formation, but has a
permanent buried metallic flow-line, in which case, sufficient CP shall be
provided to maintain the flow-line at an acceptable protection level in
accordance with SAES-X-400 without electrical isolation of the well
casing from the flow-line.
Commentary Notes:
Where CP is not needed because the well casing is expected to last less than
5 years, if the proponent requires CP then it can be made out of scrap steel
anodes.
1.4 A metallic well casing that is not installed through a corrosive formation and
does not have a permanent flow-line does NOT require cathodic protection.
However, if a foreign impressed current anode bed is within 500 meters radius
of this type of well, electrical bonding shall be implemented to minimize the
probability of downhole interference.
1.5 For oil and water wells only, a metallic well casing that has not been coated with
Fusion Bonded Epoxy (FBE) and is installed within a metallic or non-metallic
cellar and backfilled shall be provided with galvanic magnesium anodes.
Install two pre-packaged 27.3 kg (60 lb) magnesium anodes inside the wellhead
cellar. Alternatively, clamp two 100-lb bare bracelet magnesium anodes within
the top one meter of the well head and connect the cable to the well casing at the
cellar zone to provide supplemental cathodic protection for the landing base
area. When upgrading an existing CP system, depleted magnesium anodes at
the cellar area shall also be restored. Measuring the potential and/or anode
current output at the cellar area is not needed to meet any protection criteria,
rather to ensure that the anodes are physically and electrically connected.
Commentary Note:
1.6 Temporary cathodic protection for well casings that will be protected with ICCP
is not required except where a temporary galvanic system is applicable as
detailed in paragraph 1.2 above.
1.7 This standard shall not be attached to, nor made a part of a purchase order.
Requests to deviate from this standard shall be submitted electronically through the
SAP Waiver Process in accordance with SAEP-302, “Instructions for Obtaining a
Waiver.”
3 References
Referenced standards and specifications shall be the latest edition/revision unless stated
otherwise.
The following general list of definitions and abbreviations has been developed
specifically for application with Saudi Aramco cathodic protection standards
and specifications:
AA: The ANSI cooling class for a dry-type self-cooled transformer or reactor
that is cooled by the natural circulation of air. Syn.: AN (IEC), See definition
3.1 in IEEE C57.12.
Christmas Tree: The set of valves, spools and fittings connected to the top of a
well to direct and control the flow of formation fluids from the well.
Coated Casing: The term “coated casing” as used in this engineering standard
describes a well casing with an external non-conductive coating (typically Fusion
Bonded Epoxy or FBE). The coating must be applied to all sections of the casing
in contact with soil or formation, from surface to the bottom of the casing or to a
depth determined to facilitate external corrosion mitigation with cathodic
protection through the relevant down hole corrosive aquifers. Casings that have
been coated over the upper two or three joints of casing only are not “coated
casings”. Coating applied to well casings is not applied as a corrosion barrier.
It is applied to reduce the total amount of CP required or to extend the influence of
the applied CP.
Cross Country Pipeline: A pipeline between; two plant areas, another cross
country pipeline and a plant area, or between two cross country pipelines.
Design Agency: The organization responsible for the design of the pipeline and
associated CP system. The Design Agency may be the Design Contractor, the
Lump Sum Turn Key Contractor or an in house design organization of Saudi
Aramco.
Flare Line or Blow Down Line: A line for pumping out of unwanted gas or
hydrocarbon
Hazardous Areas: An area where fire or explosion hazards may exist due to
flammable gases or vapors, flammable liquids, combustible dust, or ignitable
fibers or filings (see NEC Article 500).
Kill Line: A high-pressure pipe leading from an outlet on the BOP stack to the
high-pressure rig pumps
Manufacturer: The Company that assembles the components for the finished
product and provides the finished product either through a Vendor or directly to
Saudi Aramco.
Mill (for anodes): An anode mill is a facility that produces anodes such as
MMO or Platinized Niobium (without lead wires) for cathodic protection
applications (or any other anode type that does not involve casting).
ONAN: The ANSI cooling class for a transformer or reactor having its core and
coils immersed in mineral oil or synthetic insulating liquid with a fire point less
than or equal to 300C, the cooling being effected by the natural circulation of air
over the cooling surface. (ONAN was previously termed OA). See definition
3.303 in IEEE C57.12.
Pipeline: The term “pipeline” is used generically to refer to any type of pipeline.
Plant Area: The area within the plot limits of a process or storage facility.
Plot Limit: The plot limit is the boundary around a plant or process facility.
The plot limit may be physical such as a fence, a wall, the edge of a road or pipe
rack, chains and posts or a boundary indicated on an approved plot plan.
Single Well Casing CP System: One well casing CP system protected by one
CP rectifier system.
Soil Transition Point: The surface location where a pipeline enters or exits the
soil, i.e., above grade to below grade transition, or below grade to above grade
transition.
Subject Matter Expert (SME): The SME is the assigned Consulting Services
Department cathodic protection specialist.
Shared Well Casing CP System: Two or more well casings protected by two or
more CP rectifier systems that are negatively bonded thru a Dedicated Bonding
Facility arrangement. Shared well casings are not allowed except for solar
systems.
Test Line: A pipeline that is used for testing an individual well or group of wells.
Utility Line: A pipeline that delivers a service product (typically water, gas, or
air).
Venturi Spool: A gas metering spool recording apparatus at gas well sites.
Well Casing: Large-diameter pipe lowered into an open hole and cemented in
place.
Well Head: The system of spools, valves, and assorted adapters that provide
pressure control of a production well.
5.1.2 Field measurements required for the design, survey, installation, walk-
through, pre-commissioning, commissioning, inspection, monitoring,
restoration, replacement, troubleshooting, field-investigation,
assessment, drill stem analysis, anode bed installation, etc. shall be
performed by an Engineer or Technician with a minimum industry
certification level of NACE CP Level 2. Indicate the NACE CP level,
certification number, name of designer and/or his signature/initial in the
design package.
Commentary Note:
As noted in GI-0428.001, PMT may request assistance from CSD for the
verification of the qualifications of the Design Contractor’s engineer responsible
for designing the CP systems and to approve new designers.
5.2.1 DBSP and project proposal does not require conducting a site visit unless
that is mandatory to complete the package. The proposed construction
drawings and the related cathodic protection design information for
every design package shall at minimum be submitted to the CP
Proponent organization (as defined by GI-0428.001) and to Saudi
Aramco’s Consulting Services Department (CSD) or where applicable to
the CSD approved local design office Engineers for review and approval.
The most up to date list of approved design offices is posted on ShareK.
5.2.2 The Design Agency shall not issue drawings for construction until the
design has been reviewed and approved in writing by CSD or where
applicable by the CSD approved local design office Engineers and the
CP Proponent organization.
5.4.1 Unless specifically requested by PMT, project proposal does not need to
be reviewed or approved by CSD Project Proposal packages submitted to
CSD for review shall provide all design considerations that can be
developed without requiring the measurement of field data or a site visit.
5.4.2 The Project Proposal package shall include a specific statement in the
scope of work that clearly identifies any requirement to provide CP for
existing well casings, flow-lines or trunk-lines.
5.4.3 The Project Proposal shall provide clear direction on the general design
approach with respect to the following:
a. The CP systems shall be designed as:
● single well CP systems, or
● multi-well CP systems
5.4.4 The Project Proposal shall clearly state if remote monitoring equipment
will be included per 17-SAMSS-018 with the CP power supplies and if
so it shall provide the following general design information:
a. Will the CP power supply be provided with:
● signal transmitters, or
● a Remote Monitoring Unit (RMU)
5.4.5 The Project Proposal shall contain a professionally drafted Index “X” CP
layout drawing using the cathodic protection symbols shown on Standard
Drawing AD-036785 “Symbols for Cathodic Protection”, illustrating:
a. All existing and new well casings, buried/above grade metallic/non-
metallic, shorted/isolated flow-lines, test lines, pipelines, blowdown
lines, flare lines, bypass lines and trunk-lines associated with or
affected by the proposed CP system within the 1,000 meter radius of
the new well casing.
b. The proposed location of all CP equipment associated with the new
CP system with general details for:
● the proposed anodes and anode bed(s), location, type (surface,
deep conventional, deep unconventional), depth, number of
anodes, anode bed derating, anode to anode spacing, anode bed
to anode bed spacing, anode bed to buried structures spacing
● output ratings and condition for the existing/proposed CP power
supply and available spare capacity
● cable locations/route, lengths, number and sizes
● underground/above grade, metallic/non-metallic, existing/new
junction boxes, splice boxes and bond stations and their
condition
5.5.2 Detailed Design packages shall contain the original completed and signed
by CSD or where applicable by the CSD approved local design offices
“Well Casing Design Quality Assurance Check List” attached to the cover
letter or transmittal sheet for the design package (See Appendix 1).
5.5.3 Detailed Design packages shall contain all calculations and applicable
field data required to verify design compliance with the Saudi Aramco
Cathodic Protection Engineering Standards including an electrical
simulation drawing for all multi-well and shared-well CP systems.
Shared well casings are not allowed except as detailed in Section 6 below.
6.1 General
6.1.1 Shared well casings are not allowed except for solar systems especially
bare and for multiple well casings exceeding the limitations of multiple
well casing CP system capacity (more than 5 wells and/or requiring
higher than 150 Amp TR, etc.). In overlapping gas/oil fields a shared
well casing is not allowed and thus it is a clear violation of this standard.
Requests for waivers will not be supported by CSD.
6.1.2 The design shall facilitate an integrated CP system for all associated
buried metallic structures, and shall comply with all spacing and access
restrictions detailed in SAES-B-062. The final design/IFC approval by
CSD can be thru an email, CRM or the like but does not necessarily need
to show the approval on every document/drawing. Rather, a list of
documents/drawings can be approved.
Saudi Aramco: Company General Use
Page 17 of 49
Document Responsibility: Cathodic Protection Standards Committee SAES-X-700
Issue Date: 27 December 2017
Next Planned Update: 27 December 2020 Cathodic Protection of Onshore Well Casings
6.1.3 Permanent stainless steel, carbon steel, bare, coated buried flare lines and
blow down lines on a well pad do not need a dedicated CP system, but
rather they shall be made permanently electrically continuous with the
well casing or the negative circuit of the well casing CP system to ensure
their adequate protection. If must be isolated, then protect them with
galvanic anode system. Bond across venturi spools with a metallic strap
at gas wells to ensure electrical continuity with the CP system and to
minimize the possibility of CP interference. Where non-metallic
pipelines are used (spools, flowlines, test lines and truck lines) bonding
across using a dedicated bond box is required. If isolation is a must, then
provide adequate CP for all metallic parts.
6.1.6 Well casings separated by less than 500 meters shall utilize a multiple
CP power source, provided the design protection criteria for each well as
stated in Tables 1A, 1B, and 1C of this standard are met without the use
of electrical resistors at the design stage. Electrical resistors maybe used
at the commissioning and/or operating stages provided that they are
intrinsically safe and are not installed in hazardous zones.
Exception:
If during commissioning of multi-well CP system, adequate current
distribution is not achieved, then resistors may be used. Resistors shall
be welded tap adjustable or fixed (non-adjustable) and shall be 0.15
ohms or less.
Commentary Note:
Coated well casings with normally above grade flowlines may use the
flowline for negative cable connection and hence do not require a
dedicated negative cable to each well but are still restricted by the
500 meter separation imposed on CP systems with multiple well casings
and shall meet all well casing and flowline protection requirements.
6.1.7 At sites where one CP power source is used to protect multiple well
casings, each uncoated well shall have a dedicated negative cable
connection. The negative cables shall be terminated in a negative
junction box located to optimize the current distribution between casings.
6.1.8 CSD approved underground junction box may be used for an anode bed
junction box, bond box, splice box, or a negative cable junction box.
Commentary Note:
Field data and site verification of existing equipment that may affect or be
affected by the proposed CP system are required for the detailed design.
The following field investigation and data collection shall be completed and the
results included with all detailed design packages submitted for approval.
wells and flowlines shall be met and all monitoring requirements for
existing wells and flowlines shall also be met.
Soil resistivity measurements are mandatory for all types of new and
existing anode beds; assumed or back calculated resistivities are not
allowed.
6.3.1 Size ICCP anode beds to discharge the CP power source rated current
at the anode consumption rate detailed in Table 2, for a minimum of
20 years for HSCI anodes. MMO anodes shall be designed for 25 years.
6.3.3 New Well Added to a CP System Less than 10 Years Old within 500
meters:
Use multiple CP systems for the addition of a new well within 500 meters
from an existing well(s), up to 5 wells and up to 150 Amp rectifier rating.
Otherwise PMT after securing the proponent approval may use a shared
CP system when in compliance with the exceptions for permitting the use
of shared CP systems as detailed in section 6 above. Upgrade the rectifier
to a higher level if needed and ensure that all new and existing well
casings within 500 m and flowlines within 1,000 are adequately protected.
While new structures shall meet the commissioning requirement, existing
structures shall meet the monitoring requirements.
6.3.4 New Well Added to a CP System more than 10 Years Old within
500 meters
6.4.1 Use externally coated casings for all new, onshore, oil, gas,
unconventional gas, gas lift, observation, exploration, water injection,
and water supply metallic wells regardless of the well depth. This will
minimize the CP current requirement, allow use of multiple well casings,
reduce AC consumption and permit deployment of solar systems at
remote areas. If a bare well casing is used, then it shall be pre-approved
by the proponent and shall not be violating the general decision chart of
coating in Appendix A3.3 of this standard. The cathodic protection
system design shall provide the minimum design currents detailed in
Tables 1A, 1B, and 1C of this standard.
Commentary Note:
6.4.3 The protection criteria for commissioning and monitoring are detailed in
Tables 1A, 1B, and 1C of this standard. Tolerance values of ±10% on
commissioning values during commissioning and on monitoring values
listed in Tables 1A, 1B, and 1C of this standard shall be implemented
where needed.
Exception:
Table 1B – CP Current Requirement for Water Injection and Oil Well Casings (6)
Oil Production and Water Injection Well Casings
Cathodic Protection Current Requirements – Single Well
Bare Casing Coated Casing
Com- Com- Operate/
Design Monitor Design
mission mission Monitor
Field Designation Minimum Current Optimum Minimum Current Optimum
Minimum Minimum
CP Power Included Casing CP Power Included Casing
Casing Casing
Supply For Operating Supply For Operating
Current Current
Rating Flow-line Current Rating Flow-line Current
(amps) (amps)
(amps) (amps) (amps) (amps) (amps) (amps)
Uthmaniyah
- T/R(2) 50 3 35 30-35 15 3 7 5-7
- Photovoltaic (1) 45 0(1) 35 30-35 10 0(1) 7 5-7
General Notes:
The following general notes are intended to address issues relating to tables 1A, 1B, and 1C.
Fields indicated between two parentheses did not result from actual CPET logging, rather they are extrapolated based on
their geological location
Bare well casings are not recommended unless mandated by the proponent provided bare casings are allowed per the
coating chart
Consider ±10 % tolerances in the power source size in all tables 1A, 1B, and 1C current values
Use 3 Amp of current for all flowlines at the design stage except for photovoltaic , rather use the values indicated in the tables
Verify the actual commissioning and monitoring currents using a clamp-on ammeter around the well casing
If needed, PMT shall coordinate with Drilling and Workover to conduct CPET logging for new fields while inviting CSD to witness
If the flowline is not constructed yet, then the pre-commissioning will be rejected unless a temporary cable is used to
replicate the flowline
A pre-commissioning report is approved if the well casing(s) is receiving the pre-commissioning current in the tables, rectifier
is not exceeding 90% (±10%) voltage, anodes are not exceeding the pre-commissioning current and the rectifier current is
compatible with the anodes while the system resistance does not exceed 90% and flowlines potential is meeting the criteria,
otherwise send back to the design for a re-design and re-modeling
It has been field demonstrated that a few gas fields such as Utmn, Hwyh, Sdgm and Hrdh measured higher t han normal
current thru the F/L; therefore, a plan B shall be considered at the design stage to be prepared for a rectifier upgrade in case
needed to satisfy the commissioning requirements.
Table Notes:
(1)
Solar flow line current shall be 3 Amps. CP current requirements for the flow-lines and trunk-lines of gas well casings
cathodically protected by temporary galvanic systems shall be determined on a site specific basis. If additional current is
necessary it shall be added to the current specified in tables 1A, 1B, and 1C. Include additional current for the grounding
system.
(2)
The current required for the flow-lines and trunk-lines for AC powered well casing CP systems is included in the “CP Power
Supply Rating (amps)” for T/Rs. If the flow-line or trunk-line is greater than 15 km long, additional current capacity
requirements shall be determined through calculations completed in accordance with SAES-X-400.
(3)
Table 1C applies to water supply wells that extend through the wet UER formation such as typical Wasia water supply wells.
Wells that do not extend below the UER (or other known corrosive formation), do not require CP. Wasia water wells drilled in
areas where the UER is dry, do not require cathodic protection unless mandated by the proponent
(4)
Regardless of the water well type, associated buried flow-lines must be cathodically protected in accordance with SAES-X-400.
(5)
Water wells without cathodic protection, and within 500 meters of an impressed current CP system anode bed, or
cathodically protected well casing must be bonded to the negative circuit of the CP system and supplied with sufficient CP
current to ensure down-hole interference does not create an external corrosion problem.
(6)
In this regard, the ∆V measured between the water well and the other protected structure within 500 meters should be less
than 200 mV measured with extended lead wires, well head to protected structure.
Commentary Note:
6.5.3 Deep anode beds shall be installed in accordance with the latest revision
of Saudi Aramco Standard Drawing AA-036385 “Cathodic Protection
Deep Anode Bed”.
Exception:
Where electrolyte resistivities or bore hole conditions are not suited to the
conventional installation detailed on AA-036385, alternative material and
installation configurations (unconventional deep anode bed) may be and
require CSD and proponent approval.
Where electrolyte resistivities at the anode bed are below 1,000 ohm-cm,
the distance between the anode bed and the nearest well casing may be
less than 150 meters, but must be far enough from the nearest well
casing such that the calculated anodic gradient (∆V) at the well casing is
less than 1.0 volt using the resistivity determined at the anode bed.
For multiple well casing locations, the calculated difference in the anodic
gradient between any two well casings must also be less than 200 mV.
6.5.5 For an anode bed discharging less than 25 amperes, a minimum distance of
75 meters shall be maintained between the nearest anode and the well
casing.
Exceptions:
Where electrolyte resistivities at the anode bed are below 1,000 ohm-cm,
the distance between the anode bed and the nearest well casing may be
less than 75 meters, but must be far enough from the nearest well casing
such that the calculated anodic gradient (∆V) at the well casing is less
than 1.0 volt using the resistivity determined at the anode bed.
For multiple well casing locations, the calculated difference in the anodic
gradient between any two well casings must also be less than 200 mV.
6.5.6 Both mixed metal oxide (MMO) and high silicon cast iron (HSCI)
anodes can be used for anode beds. Procure MMO and HSCI anodes
from approved sources as specified by 17-SAMSS-007. Design
parameters for HSCI and MMO impressed current anodes shall be as
detailed in Table 2A and 17-SAMSS-007. Procure galvanic anodes from
approved sources as specified by 17-SAMSS-006. The design
parameters for galvanic anodes shall be as detailed in Table 2B, 17-
SAMSS-006, and Saudi Aramco Standard Drawing AA-036389.
MMO anodes are more preferred than HSCI anodes due to their typical
Saudi Aramco: Company General Use
Page 30 of 49
Document Responsibility: Cathodic Protection Standards Committee SAES-X-700
Issue Date: 27 December 2017
Next Planned Update: 27 December 2020 Cathodic Protection of Onshore Well Casings
Commentary Note:
The consumption rates detailed in Table 2B include efficiency; include
0.85 utilization factor in the calculation.
6.5.7 The HSCI impressed current anodes most commonly used by Saudi
Aramco are listed in Table 3 below.
Commentary Note:
6.5.8 The ICCP current capacity of an ICCP anode bed shall be equal to or
greater than the design current for the associated CP power source and
shall be calculated as follows:
SA AB x Iφ Iθ
Where:
SA AB = The total surface area of all the anodes in the anode bed
I φ = Anode material current density per Table 2A
I θ = CP power source rated current output
6.5.9 Adjacent ICCP anode beds powered from separate CP power sources
shall be separated by a minimum distance of 50 meters. Adjacent ICCP
anode beds powered from the same CP power source shall be separated
by a minimum distance of 10 and max of 20 meters.
6.5.11 Adjacent deep anode beds can be treated as individual anode beds if the
separation between the anode beds meets or exceeds the minimum
distances detailed in Table 4. Use actual measured soil resistivities if
available.
Example:
Two 50 amp deep anode beds placed 75 meters apart in 2,500 ohm-
cm soil can be installed 75 meters away from a buried pipeline.
Exception:
The separation distance between an existing anode bed and a new buried
structure shall be acceptable if field measurements on the buried structure at the
nearest point to the anode bed demonstrate that the polarized (instant-off)
potential is less than -1.20 volts (w.r.t. Cu/CuSO4). Tolerance values of ±10% on
all values are permitted in Table 4 above.
Commentary Notes:
1) The distances detailed in Table 4 are provided to limit the structure polarized
(instant-off) potential to less than -1.20 volts and to minimize the interference
effects on other independent cathodically protected structures. Polarized
potentials may be measured using a CP Assessment Probe or a CP potential
coupon, as detailed in SAEP-333 Appendix A-2.
2) For a new ICCP system, the “Anode Bed Output Current” value for Table 4 is the
rated current output of the new CP power supply.
6.6.1 For a T/R, the CP system rated circuit resistance shall be defined as the
T/R rated voltage, divided by the T/R rated current. Rated voltages and
currents are as detailed on the manufacturer's data sheet/plate.
Example, 1 ohm is the rated resistance for a 50V/50A rectifier.
6.6.2 For a photovoltaic CP system, the rated circuit resistance shall be defined
as the photovoltaic system rated output voltage divided by the CP power
source minimum required rated current from Tables 1A, 1B, and 1C.
6.6.3 The CP system operating circuit resistance for an ICCP system shall be
defined as the total effective resistance seen by the output terminals of the
respective ICCP power supply, and for calculation purposes shall include:
a. Anode bed resistance-to-ground.
b. Positive cable resistance from CP power source to anodes.
c. Negative cable resistance from CP power source to structure(s).
d. Resistance of the casing to remote earth. This shall be as shown in
Table 5 unless site testing is completed to verify a more accurate
value.
e. Effective resistance caused by +0.8 volts anode bed back emf (for
HSCI/MMO in coke breeze) plus the structure back emf per Table 5
(example: + 0.8 volts anode bed back emf -1.2 volts casing back
emf = 2.0 volts total between the anode with coke breeze backfill
and a coated steel casing).
Exception:
A back emf of +1.0 volts (Cu/CuSO4) shall be used for MMO/HSCI
anodes in seawater, Subkha, or comparable high salinity wet
applications without coke breeze. This does not include the back
emf associated with the polarized potential of the structure.
Commentary Note:
6.6.4 ICCP system designs shall take into consideration the calculated
operating resistance and shall size the positive and negative cables and
voltage rating of the T/R such that the “calculated” operating output of
the T/R complies with all of the following:
a. At the design stage only, the target commissioning current shall be
achieved at a voltage between 40% and 60% of the T/R rated voltage
output. A pre-commissioning report is approved if the well casing(s)
is receiving the pre-commissioning current in the tables 1A, 1B, and
1C, rectifier is not exceeding 90% (±10%) voltage, anodes are not
Saudi Aramco: Company General Use
Page 34 of 49
Document Responsibility: Cathodic Protection Standards Committee SAES-X-700
Issue Date: 27 December 2017
Next Planned Update: 27 December 2020 Cathodic Protection of Onshore Well Casings
6.6.8 The drilling contractor is held accountable for the functioning of the
anode bed, must meet qualification requirements, either should have a
NACE CP 2 qualified technician onboard or subcontract this service,
prepare a clear procedure for anode bed installation with check and hold
points and to be qualified by CSD.
6.7.2 The maximum allowed output rating for a DC power supply is 100 volts.
6.7.3 For hazardous areas (maximum Class 1 Zone 2), the design agency shall
select a cathodic protection DC power supply (and other CP system
equipment) that complies with the requirements of NEC Articles 500 to
504 for hazardous (classified) areas. CP equipment shall not be placed
in Class 1 Zone 1 areas.
6.7.4 Rectifiers with NEMA Class 3R enclosures shall NOT be used inside
hydrocarbon plant areas, within 30 meters of the plant perimeter fencing
(outside), or within 1 km of a coastline.
6.8.2 Anode junction boxes used with DC power supplies with a rated output
greater than 50 volts and a rated load resistance equal to or greater than
10 ohms shall utilize one of the following alternatives:
a. Shall use a non-metallic anode junction box, or
b. Shall have a protective clear plastic plate mounted in front of the
shunts, with holes drilled to facilitate measurement of the current
through each shunt.
6.9 DC Cables
6.9.3 DC cables shall comply with the most recent edition of the National Fire
Protection Association NFPA 70, National Electric Code (NEC).
6.10 Monitoring
6.10.1 The column titled “Monitor” in tables 1A, 1B, and 1C of this standard
shall be used as a guideline for adjusting the output of cathodic
protection systems to the optimum current output.
6.10.2.5 Cables and field wiring used for the remote monitoring
systems shall comply with SAES-P-104.
6.11 Bonding
6.11.1 Well casings shall be electrically continuous with their associated piping.
Resistance bonding is not allowed during the design stage except to
balance the current during commissioning as detailed below.
Exception:
6.11.2 Electrically isolated flanged piping sections (spool pieces, i.e., Venturi
spool) installed in a flow-line or trunk-line for use with instrumentation
or other applications shall be bonded around using a metal bond strap
fabricated to facilitate a reliable bond around the isolated equipment and
ease of installation and removal, i.e., bolted.
Bond all flowlines, test lines, trunk lines and pipelines thru a dedicated
bonding facility if they fall within 1,000 meters radius from a new well.
Bond all crossing pipelines that fall within the 1,000 meter radius.
For others farther away, bond at the closest pipelines crossing.
The proponent is responsible to monitor and restore the bonding stations
and to upgrade the CP system to ensure adequate protection on all
affected pipelines within the 1,000 meter radius. If existing bonding is
already present within the 1,000 meter radius then no additional
dedicated bonding is required.
Electrical isolation shall not be installed between a well casing and the associated
flow-line.
Exceptions:
for cathodic protection of onshore well casings and the Supervisor of the CP
Proponent organization. If resistors are necessary, they shall be welded tap
adjustable or fixed (non-adjustable) resistors and shall be 0.15 ohms or less.
Where an electrical isolating gasket is used to isolate between two flange faces,
it shall be installed at a location where the pipe is in a vertical orientation if
practical.
7.3 Refer to Saudi Aramco Best Practice SABP-X-003 for detailed Installation,
Records, and Inspection requirements. SABP-X-003 shall be deemed a
mandatory document for this standard.
Revision Summary
5 December 2012 Major revision.
Revised protection criteria for photovoltaic systems for coated gas wells.
Added an exception for multiple bare well casings spaced more than 2 km apart.
Introduced statements to allow greater flexibility in the commissioning requirements.
Added the requirement for NACE certification for design engineers and field technicians.
Reworded the Scope and revised other relevant sections to allow the use of galvanic
anodes for CP of well casings.
Added Mazalij and Midyan areas to the tables defining current requirements.
Modified the statement in the current requirement tables that specified a general current
requirement for all fields not listed to stating that fields not listed require the criteria to be
determined by the CSD CP SME.
Updated resistance parameters for coated and bare well casings for Khurais area.
Revised and restated the time required before cathodic protection installation and
pre-commissioning is required.
Modified anode bed upgrade requirements for a new well at existing multi-well locations.
Changed the drill stem resistance measurement technique to a four wire method.
Added observation wells into the scope of this standard.
Standardized tables 1A, 1B, and 1C for flow-line current for photovoltaic CP systems
Added a statement mandating non-metallic anode junction boxes for rectifiers with a
rated voltage above 50 volts and a load resistance of 10 ohms or more.
Updated the Definitions.
Added sections to clarify the requirements for the DBSP, Project Proposal, and Detailed
Design.
Added the requirement for a simulation drawing for multi-well CP systems.
Added sections to clarify the requirements for field testing and data collection for the
design.
Added the requirement to contact the CSD SME for typical resistivity measurements for
deep anode holes where measurements haven’t been taken.
Added an exception to allow the installation of deep anode beds in an arrangement
different than detailed in the Standard Drawings.
Added an exception to allow anode beds to be closer to structures in low resistivity
environments.
7 November 2013 Minor revision.
Update to include protection criteria for gas wells in Haradh Satellite field.
Added clarification sketches to Appendix 2 (Drill Stem and Test Anode Analysis
Procedure).
Updated Table 1A for gas wells.
Updated commissioning and monitoring criteria to include an exception addressing well
casing CP systems with galvanic as the primary CP power source.
27 December 2017 Major revision.
Required coated casing
Did not allow shared well casing
Max no of wells is 5, max current 150 Amp
Revised flow line current
Permitted exceeding the 90% voltage if the current is met
Added ±10% tolerance on some tables
Reduced the voltage tolerance from 30-70 to 20-60% during commissioning.
Well
______________________ Submitted By: ____________ Date: ________
Designation:
New CP System Data Place an X in the box if no new CP power supply or anodes
CP Power Supply Anode Hole(s) Anodes
Target Maximum Max. What Type
DC Volts DC Amps Quantity Other
Hole____ of ____ Resistance Resistance Depth(m) TA-2, 4 or 5
Existing CP System Data Place an X in the box if no existing CP power supply or anodes
Existing CP Power Supply
Existing Anode Hole(s) Existing Anodes
Rated Volts____ Rated Amps____
Operating Operating Manufacture Shallow Number Measured Resistance What Type Installation
Quantity
DC Volts DC Amps Date or Deep? of Holes to Well Casing (Note 2) TA-2, 4, or 5 Year
Drill Stem and Test Anode Resistance Measurement Data (Report directly as read from meter)
Drill Stem(Note2) Test Anode (Note2)
Depth (m) Soil Type Remarks
Resistance (ohms) Resistance (ohms)
Water level in the anode hole must be at the top of the casing before taking each measurement!!!!!!!
6
9
12
15
18
21
24
27
30
33
36
39
42
45
48
51
54
57
60
63
66
69
72
75
Continued on next page.
Saudi Aramco: Company General Use
Page 43 of 49
Document Responsibility: Cathodic Protection Standards Committee SAES-X-700
Issue Date: 27 December 2017
Next Planned Update: 27 December 2020 Cathodic Protection of Onshore Well Casings
Notes:
1. Procedure to measure the resistance of the “test wires and connections”:
Unspool 25 meters of #14 AWG wire. Connect one end to terminal C1 on the Megger.
Unspool another 25 meters of #14 AWG wire. Connect one end to terminal P1 on the Meter.
Tightly twist the open ends of the two 25 meter wires together and clamp to a bolt or flange on the well
head (use vice grips or a “C” clamp – do not use alligator clip, spring clip or spring clamp).
Unspool 200 meters (typical) of #14 AWG. Connect one end to terminal C2 on the Meter.
Unspool another 200 meters (typical) of #14 AWG wire. Connect one end to terminal P2 on the Meter.
Tightly twist the open ends of the two 200 meter wires together and clamp to the same bolt or flange on
the wellhead (use vice grips or a “C” clamp – do not use alligator clip, spring type clamp).
Measure the resistance with the Meter. Record the resistance measured as shown on the meter. It will
typically be less than 0.01 ohms.
Production
Well Casing
Meter Connections
C1
P1
P2
C2
2. Procedure to measure the resistance of the drill stem, or test anode, or anode bed:
Unspool 25 meters of #14 AWG wire. Connect one end to terminal C1 on the Meter.
Unspool another 25 meters of #14 AWG wire. Connect one end to terminal P1 on the Meter.
For Drill Stem , twist the open ends of the two 25 meter wires together and clamp to the frame of the drill
truck (use vice grips or a “C” clamp – do not use alligator clip, spring clip or spring clamp).
For test anode resistance measurement, clamp these two wires to the end of the test anode cable
instead of the drill truck.
For anode bed resistance measurement, clamp these two wires to the bus bar in the anode junction
box instead of the drill truck.
Unspool 200 meters (typical) of #14 AWG wire. Connect one end to terminal C2 on the Meter.
Unspool another 200 meters (typical) of #14 AWG wire. Connect one end to terminal P2 on the Meter.
Twist the open ends of the two 200 meter wires together and clamp to a bolt or flange on the wellhead
(use vice grips or a “C” clamp – do not use alligator clip, spring clip or spring clamp)
Record the resistance shown on the Meter.
Wellhead
Meter Connections
C1
P1
P2
C2
Do NOT place a direct short Well Casing
between any of the terminals!
Meter Connections
C1
P1
P2
C2
Test Anode
Place a direct short
between Terminals C2
and P2 for this test only
To minimize corrosion of the well casings inside cellars, in the landing base area, or
near surface, the following procedures should be implemented:
Use an external FBE coating on the top two joints of all casings that extend to
surface.
Drilling operations should ensure that all cement is removed from the base of
the cellar after each cement job to prevent the formation of a cement floor.
Fill all annuli near surface with cement to displace air or water in the annuli.
Seal the annular space between casings in the landing base area by seal welding
the casings at surface (including the surface casing or conductor casing) to stop
the ingress of air into the annular space between the casings.
Seal (weld closed) any windows cut in the casings for top jobs, etc.
No
No
Yes
No
No
Apply FBE (max 25 mils) to the external side of Apply FBE (max 25 mils) to the casing surfaces
all casings, including the conductor, to at least in contact with the formation from surface to at
50’ below surface. No other coating on the least 500’ below the deepest corrosive
casing is recommended. formation to a maximum TVD of 8000’.
When running the log, the actual amount of current going to the casing
must be measured with a current clamp placed around the casing.
It would be misleading to use the output current of the CP power supply
because the flow-line and surface facilities associated with the rig will
also take some of the current.
For best results, the cathodic protection logging tool should be left
stationary at the lowest depth of the log for a period of 15 to
30 minutes before beginning the calibration part of the log. This delay
is required to facilitate temperature stabilization of the tool.
The use of the surface reference electrode (often termed “fish” by the
logging vendor) is not required.