ID Task Name Duration Start Finish
Half 2, 2024 Half 1, 2025
A S O N D J F M
1 Building project 103 days? Sun Sep 1, '24 Tue Jan 21, '25
2 design phase 28 days Sun Sep 1, '24 Tue Oct 8, '24
3 draft concept 5 days Sun Sep 1, '24 Thu Sep 5, '24 draft concept
4 client feedback 3 days Tue Sep 17, '24 Thu Sep 19, '24 client feedback
5 final concept 7 days Sun Sep 8, '24 Mon Sep 16, '24 final concept
6 detailed design drawings 8 days Sun Sep 22, '24 Tue Oct 1, '24 detailed design drawings
7 client approval on design 5 days Wed Oct 2, '24 Tue Oct 8, '24 client approval on design
8 authorities phase 103 days? Sun Sep 1, '24 Tue Jan 21, '25
9 follow up with authorities for approval 8 days Wed Oct 9, '24 Sun Oct 20, '24 follow up with authorities for approval
10 update drawings based on authorities feed back 5 days Mon Oct 14, '24 Sun Oct 20, '24 update drawings based on authorities feed back
11 final authorities approval 0 days Sun Oct 20, '24 Sun Oct 20, '24 10/20
12
13 constructions phase 95 days? Sun Sep 1, '24 Thu Jan 9, '25
14 site preperation 9 days Mon Oct 21, '24 Thu Oct 31, '24
15 site cleaning 3 days Mon Oct 21, '24 Wed Oct 23, '24 site cleaning
16 supply water and electrical 5 days Thu Oct 24, '24 Tue Oct 29, '24 supply water and electrical
17 site fence 2 days Wed Oct 30, '24 Thu Oct 31, '24 site fence
18 sub-structuer phase 20 days Sat Nov 2, '24 Sun Nov 24, '24
19 Excavation 3 days Sat Nov 2, '24 Mon Nov 4, '24 Excavation
20 Foundation 5 days Sun Nov 17, '24 Thu Nov 21, '24 Foundation
21 Backfill 2 days Sat Nov 23, '24 Sun Nov 24, '24 Backfill
22 super structure 1 day? Sun Sep 1, '24 Sun Sep 1, '24 super structure
23 ground floor 40 days Mon Nov 25, '24 Thu Jan 9, '25
24 civil works 10 days Mon Nov 25, '24 Thu Dec 5, '24 civil works
25 finishing work 15 days Sat Dec 7, '24 Mon Dec 23, '24 finishing work
26 electromechanical works 10 days Tue Dec 24, '24 Sat Jan 4, '25 electromechanical works
27 final work 5 days Sun Jan 5, '25 Thu Jan 9, '25 final work
28 first floor 40 days Sat Dec 7, '24 Tue Jan 21, '25
29 civil works 10 days Sat Dec 7, '24 Tue Dec 17, '24 civil works
30 finishing work 15 days Wed Dec 18, '24 Sat Jan 4, '25 finishing work
31 electromechanical works 10 days Sun Jan 5, '25 Wed Jan 15, '25 electromechanical works
32 final work 5 days Thu Jan 16, '25 Tue Jan 21, '25 final work
Task Project Summary Manual Task Start-only Deadline
Project: Project1 Split Inactive Task Duration-only Finish-only Progress
Date: Fri Aug 23, '24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone