The document outlines a construction project schedule spanning from September 2024 to May 2025, detailing various tasks, their durations, and milestones. Key phases include mobilization, sub-structure works, and finishing works, with specific tasks such as excavation, concrete works, and flooring. The project is divided into several phases, each with designated start and finish dates, ensuring a structured timeline for completion.

Uploaded by

Rabee Batayneh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views2 pages

Adnan 2

The document outlines a construction project schedule spanning from September 2024 to May 2025, detailing various tasks, their durations, and milestones. Key phases include mobilization, sub-structure works, and finishing works, with specific tasks such as excavation, concrete works, and flooring. The project is divided into several phases, each with designated start and finish dates, ensuring a structured timeline for completion.

Uploaded by

Rabee Batayneh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID Task

Task Name Duration Start Finish Task


Mode Calendar
Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1 Building project 182 days Sun 01 Sep '24 Mon 12 May '25 Standard
2 Construction phase 182 days Sun 01 Sep '24 Mon 12 May '25 Standard
3 Mobilization Works 11 days Sun 01 Sep '24 Sun 15 Sep '24 None
4 Cleaning & Leveling 6 days Sun 01 Sep '24 Sun 08 Sep '24 Standard Cleaning & Leveling
5 Fixing the fence 3 days Mon 09 Sep '24 Wed 11 Sep '24 Standard Fixing the fence
6 Supply & Erection of Site office 5 days Mon 09 Sep '24 Sun 15 Sep '24 Standard Supply & Erection of Site office
7 Sub_ Structure Works 41 days Mon 16 Sep '24 Mon 11 Nov '24 None
8 Soil Works: 41 days Mon 16 Sep '24 Mon 11 Nov '24 None
9 Excavation 10 days Mon 16 Sep '24 Sun 29 Sep '24 Standard Excavation
10 Back filling 5 days Tue 05 Nov '24 Mon 11 Nov '24 Standard Back filling
11 Bitumen &insulation 4 days Wed 30 Oct '24 Mon 04 Nov '24 Standard Bitumen &insulation
12 Concrete Works: 22 days Mon 30 Sep '24 Tue 29 Oct '24 None
13 Shuttering P.C Footing 2 days Mon 30 Sep '24 Tue 01 Oct '24 Standard Shuttering P.C Footing
14 Placing P.C Footing 2 days Wed 02 Oct '24 Thu 03 Oct '24 Standard Placing P.C Footing
15 De shuttering P.C Footing 7 days Sun 06 Oct '24 Mon 14 Oct '24 Standard De shuttering P.C Footing
16 Shuttering R.C Footing 2 days Tue 15 Oct '24 Wed 16 Oct '24 Standard Shuttering R.C Footing
17 Steel Fixing R.C Footing 2 days Tue 15 Oct '24 Wed 16 Oct '24 Standard Steel Fixing R.C Footing
18 Placing R.C Footing 2 days Thu 17 Oct '24 Sun 20 Oct '24 Standard Placing R.C Footing
19 De shuttering R.C Footing 7 days Mon 21 Oct '24 Tue 29 Oct '24 Standard De shuttering R.C Footing
20 MILESTONE 0 days Tue 29 Oct '24 Tue 29 Oct '24 None 29-10
21 Super _ Structure Works 130 days Tue 12 Nov '24 Mon 12 May '25 None
22 Ground Floor Works 90 days Tue 12 Nov '24 Mon 17 Mar '25 None
23 concreatre work 40 days Tue 12 Nov '24 Mon 06 Jan '25 None
24 Shuttering G _ Floor R.C Columns3 days Tue 12 Nov '24 Thu 14 Nov '24 Standard Shuttering G _ Floor R.C Columns
25 Steel Fixing G _ Floor R.C Columns
3 days Tue 12 Nov '24 Thu 14 Nov '24 Standard Steel Fixing G _ Floor R.C Columns
26 Placing G _ Floor R.C Columns 2 days Sun 17 Nov '24 Mon 18 Nov '24 Standard Placing G _ Floor R.C Columns
27 De shuttering G _ Floor R.C Column
7 days Tue 19 Nov '24 Wed 27 Nov '24 Standard De shuttering G _ Floor R.C Column
28 Shuttering G _ Floor R.C Slab 5 days Thu 28 Nov '24 Wed 04 Dec '24 Standard Shuttering G _ Floor R.C Slab
29 Steel Fixing G _ Floor R.C Slab 5 days Thu 28 Nov '24 Wed 04 Dec '24 Standard Steel Fixing G _ Floor R.C Slab
30 Placing G _ Floor R.C Slab 2 days Thu 05 Dec '24 Sun 08 Dec '24 Standard Placing G _ Floor R.C Slab
31 De shuttering G _ Floor R.C Slab 21 days Mon 09 Dec '24 Mon 06 Jan '25 Standard De shuttering G _ Floor R.C Slab
32 MILESTONE 0 days Mon 06 Jan '25 Mon 06 Jan '25 None 06-01
33 Finishing Works 50 days Tue 07 Jan '25 Mon 17 Mar '25 None
34 Brick Works 10 days Tue 07 Jan '25 Mon 20 Jan '25 Standard Brick Works
35 Preliminary Carpentry Works 5 days Tue 21 Jan '25 Mon 27 Jan '25 Standard Preliminary Carpentry Works
36 Preliminary Electrical Works 5 days Tue 21 Jan '25 Mon 27 Jan '25 Standard Preliminary Electrical Works
37 Preliminary Sanitary Works 5 days Tue 21 Jan '25 Mon 27 Jan '25 Standard Preliminary Sanitary Works
38 Plastering 10 days Tue 28 Jan '25 Mon 10 Feb '25 Standard Plastering
39 Painting 10 days Tue 11 Feb '25 Mon 24 Feb '25 Standard Painting

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project1
Milestone Inactive Summary Start-only Critical
Date: Fri 23 Aug '24
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
ID Task
Task Name Duration Start Finish Task
Mode Calendar
Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
40 Flooring 10 days Tue 25 Feb '25 Mon 10 Mar '25 Standard Flooring
41 Finishing of Carpentry Works 5 days Tue 11 Mar '25 Mon 17 Mar '25 Standard Finishing of Carpentry Works
42 Finishing of Electrical Works 5 days Tue 11 Mar '25 Mon 17 Mar '25 Standard Finishing of Electrical Works
43 MILESTONE 0 days Mon 17 Mar '25 Mon 17 Mar '25 None 17-03
44 First Floor Works 90 days Tue 07 Jan '25 Mon 12 May '25 None
45 concreatre work 40 days Tue 07 Jan '25 Mon 03 Mar '25 None
46 Shuttering F _ Floor R.C Columns3 days Tue 07 Jan '25 Thu 09 Jan '25 Standard Shuttering F _ Floor R.C Columns
47 Steel Fixing F _ Floor R.C Columns
3 days Tue 07 Jan '25 Thu 09 Jan '25 Standard Steel Fixing F _ Floor R.C Columns
48 Placing F _ Floor R.C Columns 2 days Sun 12 Jan '25 Mon 13 Jan '25 Standard Placing F _ Floor R.C Columns
49 De shuttering F _ Floor R.C Column
7 days Tue 14 Jan '25 Wed 22 Jan '25 Standard De shuttering F _ Floor R.C Column
50 Shuttering F _ Floor R.C Slab 5 days Thu 23 Jan '25 Wed 29 Jan '25 Standard Shuttering F _ Floor R.C Slab
51 Steel Fixing F _ Floor R.C Slab 5 days Thu 23 Jan '25 Wed 29 Jan '25 Standard Steel Fixing F _ Floor R.C Slab
52 Placing F _ Floor R.C Slab 2 days Thu 30 Jan '25 Sun 02 Feb '25 Standard Placing F _ Floor R.C Slab
53 De shuttering F _ Floor R.C Slab 21 days Mon 03 Feb '25 Mon 03 Mar '25 Standard De shuttering F _ Floor R.C Slab
54 MILESTONE 0 days Mon 03 Mar '25 Mon 03 Mar '25 None 03-03
55 Finishing Works 50 days Tue 04 Mar '25 Mon 12 May '25 None
56 Brick Works 10 days Tue 04 Mar '25 Mon 17 Mar '25 Standard Brick Works
57 Preliminary Carpentry Works 5 days Tue 18 Mar '25 Mon 24 Mar '25 Standard Preliminary Carpentry Works
58 Preliminary Electrical Works 5 days Tue 18 Mar '25 Mon 24 Mar '25 Standard Preliminary Electrical Works
59 Preliminary Sanitary Works 5 days Tue 18 Mar '25 Mon 24 Mar '25 Standard Preliminary Sanitary Works
60 Plastering 10 days Tue 25 Mar '25 Mon 07 Apr '25 Standard Plastering
61 Painting 10 days Tue 08 Apr '25 Mon 21 Apr '25 Standard Painting
62 Flooring 10 days Tue 22 Apr '25 Mon 05 May '25 Standard Flooring
63 Finishing of Carpentry Works 5 days Tue 06 May '25 Mon 12 May '25 Standard Finishing of Carpentry Works
64 Finishing of Electrical Works 5 days Tue 06 May '25 Mon 12 May '25 Standard Finishing of Electrical Works
65 MILESTONE 0 days Mon 12 May '25 Mon 12 May '25 None 12-05

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project1
Milestone Inactive Summary Start-only Critical
Date: Fri 23 Aug '24
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 2

You might also like