Quote PT&Top Coat Line
Quote PT&Top Coat Line
Dear Sir,
We thank you for your enquiry and interest shown in our organization.
Further on your RFQ and details, we are pleased to submit our techno-commercial proposal
for the supply of Conveyorized Paint shop and Dip type pre-treatment line for combine
components with I beam 678 Conveyor.
• Component size is 5 Mtr. X 2.25 Mtr. X 2.5 Mtr. (L x W x H) + Hanger Height 1500 mm
from top conveyor ‘I’ beam.
• Have taken provision for powder coating booth for straw reaper coating, if required in
future.
• Oven shall be designed in such way which is suitable for both the application.
All our equipment is supported by the technical after-sales service and troubleshooting, if
required. In short, we can provide all the related services under one roof, ably backed with an
efficient after-sales service to ensure a trouble-free operation.
We look forward to your response in the matter and no sooner we hear from you in this regard,
we shall be available for any further discussions in this regard.
Yours faithfully
2 of 31
1. MAKE LIST OF BOUGHT OUT ITEMS
3 of 31
2. BASIS OF DESIGN
4 of 31
3. BRIEF SCOPE OF SUPPLY
Our brief scope of supply would include the design, manufacturing, supply and commissioning
of the paint shop, having following items:
A. Pre-treatment Line :
Sl. No ITEMS Qty
1. PT Line:
5 of 31
B. Liquid Painting Plant
6 of 31
4. PROCESS SCHEDULE
7 of 31
PRE-TREATMENT TANKS - TECHNICAL SPECIFICATION (SECTION - 1)
4.1 PRE - TREATMENT PLANT
8 of 31
4.2 PRE - TREATMENT PLANT
S. No Description Activation Phosphating
• Type DIP Type. DIP Type.
• Process Temperature Ambient. 45 - 50 Deg C.
• Risers Inside/ Zone Length NA. NA.
• Tank Capacity (liters) 40000 40000
Length (Meters) 5.5 5.5
Width (Meters) 2.7 2.7
Height (Meters) 3.0 3.0
Tank Construction Details Sloping Tank Sloping Tank Construction
Construction with Over with Over Flow Weir.
Flow Weir.
MOC (Tank) SS 304, 3 mm thick, SS 304, 3 mm thick,
suitably reinforced by suitably reinforced by MS
MS sq. tube sq. tube
• Agitation (Optional) Air agitation will be Air agitation will be
provided. provided..
MOC – Piping CPVC Piping. CPVC Piping.
• Heating system NA. Provided.
Type NA. Indirect SS coil and HWG
MOC NA. SS 304.
Temp. Control system NA. DTC with RTD Sensor.
Heating Load/ Hr NA. 3,00,000 Each
• Instrumentation NA. DTC with Sensor
• Tank Insulation & cladding NA. NA
Hot water (Piping) NA. MS C Class Insulated.
Insulation material NA. Rock Wool 64 Kg Density
Thickness NA. 50mm
Cladding material NA. GI.
• Drain Valves 100 NB Butterfly 100 NB Butterfly Valve.
Valve.
• Fresh Water Inlet RO/ DM Water. RO/ DM Water.
9 of 31
4.3 PRE - TREATMENT PLANT
Piping CPVC
10 of 31
Technical specifications
2. Maximum load carrying 2000 KG (Designed with flight bar and water
capacity weight)
5. Motor for horizontal drive 5 hp with Brake (Same shall reconfirm after
detailed design)
6. Motor for vertical drive 15 HP With Brake (Same shall reconfirm after
detailed design)
• A walkway platform for operator movement along the entire span of PT line shall be
provided.
• This will be made from MS section and grids made of MS flat and square bars.
• The width of the platform shall be 1200 mm and 3700 mm, total length shall be app. 48mtr.
• The height of the platform shall be approx. 2100 mm from the ground level.
• Access to the platform shall be through an inclined staircase.
• Railing made from MS pipe shall be provided for safety purposes.
• The legs shall be made from ISMC 75x40 sections.
11 of 31
7. OIL SEPARATION SYSTEM – FOR KOD & DEG
One oil separation system having MS tank, with heating arrangement and oil removing Disc
coupled to Geared Motor and accessories for KOD / Degreasing stage shall be provided. The
total circulation system will be designed that cascading effect will also be there, to save on
chemical consumption.
Technical details: -
S. No. Specifications Description
1. Tank Made from 2 mm thk. M.S. sheet, with duly
strengthened with M.S. stiffeners. – 2500 Ltr. Capacity
tanks will be provided
2. Circulation Pump One no. shall be provided from KOD. tank to oil
separation tank for circulating the tank chemical
4. Piping and Other Piping from KOD to Oil Separation Tank and return to
accessories Degreasing Tank.
Construction Details:
Hot water generator would consist of a Heat exchanger, consisting of two closely wound,
helical, concentric coils. A blow down connection is provided for periodically blowing down any
sludge or accumulated dissolved solids during operation of the generator.
• Dust protected pre-wired foot mounted air-cooled control panel housing a Burner
Management system, Switch gear consisting of contactors, overload relays, fuses
etc. Hot water temperature display on digital temperature controller.
• Automatic fuel burner cut off and automatic restart at desired hot water
temperature.
12 of 31
• Centrifugal pump with drive motor assembly for hot water circulation.
2. The hot water generator is supplied with complete mountings and fittings as follows:
• Drain valve.
13 of 31
9. LOAD BAR FOR MATERIAL HANDLING IN PT
Load bar for material handling of the size 5100 mm – 2300 mm – 2400 mm (L, W, H) shall be
provided. Initially we will provide 06 nos.
More load bars shall be fabricated by you as per our sample load bar with the
required modification at site.
14 of 31
17. Exhaust Blower Required Capacity of Exhaust Blower will be
Provided.
18. Heat exchanger cabin Suitable Direct fired, insulated cabin to house
direct Fired heat exchanger, burner and blowers
shall be provided. Utmost precautions shall be
taken to get the maximum heat transfer from the
heat source.
19. Heat Exchanger Shall be fabricated in S.S. The shell shall be made
in S.S. 304, 3 mm thick
20. Air delivery duct Shall be provided in the oven throughout its cross
section. The duct shall have properly placed grills
to get the uniform air all through the oven.
21. Entry Exit Doors Insulated Doors of Dimension 1 Nos. of 5500 x
2700 shall be provided at the Exit and entry end.
22. Support structure Made from MS pillars made of Sq. Pipe duly
supported at the bottom for providing proper
support to the pillars. The total bottom structure
of the oven cabin shall rest on the running
section, thus providing self-supporting structure
to the oven.
23. Painting Inside MS parts shall be painted with heat
resistant paint, and outside synthetic enamel
spray painted.
There will be exhaust blowers provided for suction of paint fumes. Exhaust blowers suck the
paint fumes (washed by water) and hence preventing paint from going into the blowers. Air
velocities are regulated to meet international pollution control norms and are maintained over
Lowest Explosive Level.
15 of 31
TECHNICAL & CONSTRUCTIONAL DETAILS:
1. Type of application Down draft type paint booth for manual application.
2. No. of units One Nos.
3. Working Dimension (L) 12000mm x (W) 6000mm x (H) 5000mm
4. Overall dimensions (L) 12200mm x (W) 6100mm x (H) 6000mm
5. Entry / exit 2500 mm x 3000 mm (WxH).
6. Filters Ceiling filters shall be provided having dust holding
capacity of 5 micron down to 85%.
7. Exhaust Blower
• Qty. 04
• Capacity 30000 CMH each, Vee Belt driven arrangement.
• Pressure 150 mm WC
• Make DM Ventilation.
• Exhaust Damper 1 No. manual Damper with bellows shall be
provided on each blower.
8. Blower motor
• Power 4 Nos. x 20 hp, with each blower. This may final confirm
• Specs. after design of the booth.
2/4 pole, 3 phase, ABB/ BB
9. Air Velocity Considered 0.5 meter/sec, at a level of 1.5 mtr. Height from
ground.
10. Water Circulation 2000 LPM Approx. 15 HP x 2 Nos., (In centralized
Pump sludge pit)
Make : Kirloskar, MOC: CI/CI. For each booth
11. Bottom Pit Civil Construction. Shall be constructed by Client.
We shall provide the drawing for the same. The Pit
depth shall be Approx 1500 / 2000mm.
12. Grating on Bottom Shall be provided, fabricated out of M.S. Flat & Bars,
easily removable for maintenance purpose.
13. Illumination Level - 800 Lux (LED - Non flame proof type)
14. Glass Panels on Suitable Width X 1500 mm Height 5/6 mm thk along the
16 of 31
FABRICATION
❖ Booth Support Structure shall be made out in MS 2.5 / 3.0 mm thick sheet / pipe
section / standard channel and angle.
❖ Venturi shall be made in MS 2.0 mm Thk sheet.
❖ Exhaust plenum shall be made out of GI 1.2 mm thick sheet metal.
❖ Tank Grating shall be provided in M.S. Flat & Sq. Bar
❖ Modular design ensures easy installation and expansion.
❖ Exhaust Ducting – Client Scope.
17 of 31
13. PAINT KITCHEN ENCLOSURE
Fabrication:
[A] Self-supporting frame: ISMA 40 X 40 X 5 mm.
[B] Cassettes panels (inside): GI Sheet thickness 1.2 mm.
[C] Cassettes panels (outside): Pre-coated Sheet thickness 0.5 mm.
[D] Cassette support structure: HR 2.5 mm.
18 of 31
[E] GI Sheet thickness 1.2 mm for Air circulation wall
The complete oven structure shall be elevated to MS pillar structure having UDL on each
member. Insulated ramp shall be provided for access inside the oven.
Ducting:
Internal ducts have openings with fabricated grills are provided to uniformly distribute the
air throughout the oven. These distribution ducts are laid on the floor panel and in between
the conveyor tracks. The suction duct is placed on the roof of the Oven.
The design and placement of air duct with louvers/grills would be in such a way to minimize
the heat loss and to provide overall uniformity of temperature. Moreover, the easy movement
of articles at entry and exit point is provided so that no damage could occur to the painted
surface of articles.
All external ducts will be designed to avoid unnecessary bend and suitably insulated and
laded. The external ducts will be nut bolted to heat exchanger with the help of flanges thus
making maintenance easier.
In-Direct GAS Fired Heat Exchanger:
The heat Exchanger consists of SS 304 combustion chamber with proper arrangement of
suction and discharge connection of hot air circulation blower. The heat exchanger box is
duly insulated to reduce heat losses.
A burner is mounted on the combustion chamber with necessary controls and interlocks.
Maintenance Features:
Doors are provided for maintenance of the heat exchanger during the soothing operation.
Indirect gas fired burner will be back pull-out type for easy fitting.
Safety Features:
The circulating blower is inter-locked with the burner such that the blower is always ‘ON’
before the burner is ‘ON’.
19 of 31
PICS. FOR REFERNCE PLEASE.
TECHNICAL DETAIL
Heating source : Through Indirect Gas fired system
Design Air Temperature : 2200 +/- 10 Deg C
Temperature controller : Digital single set point ON/OFF control with PT-100
sensor
(Overall) : 40000 - 8300 – 5250 + 4000 mm for camel back effect
Curing time : 2200 C +/- 10
Residence time : 40 min. inside the oven
1 Material of Construction – GI
Panel of nut bolt
construction
--Panel material thickness 1.2
--Head mm w.g. 65 mm
20 of 31
--Heat exchanger SS 304, having shell 3 thk, insulated in a
specifications chamber
8 Painting
21 of 31
15. OVER-HEAD MOTORIZED CONVEYOR WITH SUPPORTS, AML ETC.
Technical Specification:
Sl. Items Specification
Capacity
Type Caterpillar
Qty. 01
Synchronization Provided
5. Chain
Pitch 4”
10. Bends All horizontal and vertical bends are provided as per the
given layout. Horizontal bends are provided with
horizontal guide rollers and fitted with anti-friction ball
bearing and sealed for life.
22 of 31
11. Take up unit One no. weighted type will be provided.
23 of 31
16. WET TYPE AIR SUPPLY UNIT
The Wet Type Air supply unit provides dust free air inside the Booths for Pressurization. The
air is filtered at two stages. Pre – filtration and Water Washing giving the dust free air up to 5
~ 6 microns air inside the enclosed Booth chamber. The air thus fed into the enclosure also
helps in maintaining positive pressure inside the enclosure. This further prevents the chances
of dust entering into the enclosed chamber / flash -off zones from environment.
24 of 31
17. PLC BASED ELECTRIC CONTROL PANEL FOR PT & PAINT LINE
General
Incoming Section
8. Voltmeter/Ammeter 96 x 96 AE / RISHABH
Outgoing Section
25 of 31
All cables being taken out would pass through grommet to avoid ingress. All wiring would be
aesthetically routed through proper channels and secured well wherever possible. All switches
and indicator lamps would have legend engraves on black name plate. All cabling would be
routed properly with saddle clamp/trays in aesthetic manner. The panel would have a pocket
to contain circuit diagram. Temperature controllers would be tampering proof.
Note: - Client must provide main incomer cable for the control panels in the plant.
Client has also to provide the Individual Earthing for all Motors / Equipment’s.
Earthing for Individual Motors, for required Equipment’s will be in Client Scope.
26 of 31
19. PRICE SCHEDULE
Our price schedule would include the design, manufacturing and supply of the paint shop,
having following items:
A. DIP TYPE PT LINE
Unit Cost Total Cost
Sl. No ITEMS Qty
(INR) (INR)
1. Pre-treatment included with drain
01 Set 79,55,000/- 79,55,000.00
and overflow.
2. PLC Based transporter system
01 Set 69,50,000/- 69,50,000.00
consisting of five nos. wagon
3. Fresh water line for RO & DM from
01 Set 1,80,000/- 1,80,000.00
one points to each tank.
4. Cage / flight bar transfer 06
1,75,000/- 10,50,000.00
arrangement to loading station Nos.
5. FRP Based Walkway platform 01 Set 3,50,000/- 3,50,000.00
6. Oil separation system for Degreasing
01 Set 4,50,000/- 4,50,000.00
tanks
7. Hot water generator system with
insulated piping, having capacity is
of 12.0 Lac K Cal/ hr.
01 Set 33,40,000/- 33,40,000.00
• Heating coils for HWR, KOD
and Degreasing.
• Heating coils for Phosphate
8. Sludge removal system with filter
01 Set 7,50,000/- 7,50,000.00
press for phosphate chemical.
9. Air agitation for agitation in pre-
treatment line, in all tanks with 01 Set 5,80,000/- 5,80,000.00
diffusers
10. Water Dry Off Oven (Tank Type):
• Direct fired heating system 01 set 24,50,000/- 24,50,000.00
• Top sliding doors with
motorized control.
11. PLC Based Control panel, cable tray
01 Set 8,50,000/- 8,50,000.00
& wiring
12. Painting and finishing material 01 Lot 1,50,000/- 1,50,000.00
Sub Total Cost (A) = 2,50,55,000.00
27 of 31
B. PAINT SHOP:
28 of 31
20. TERMS AND CONDITIONS OF SALES
Sl. Item
1. The quoted prices are from our Ex works Greater Noida.
5. Packing: Nil
6. Inspection:
If necessary, the goods will be offered for visual inspection only at our works/our
supplier's works.
Installation and Erection & Commissioning would take approx. 10 ~ 12 weeks after
handing over of the site. After 10 weeks both the activities shall go side by side.
8. Payment terms:
Supply: 30% amount of order value shall be made along-with the firm order. 60%
of order value plus 100% of taxes and duties would be made against Performa
invoice on pro rata basis before dispatch, 5% shall be payable after erection and
balance 5% after 15 days of successful commissioning.
9. Validity: Our offer shall remain valid for a period of 30 days from the date of offer.
10. Jurisdiction: All the contracts between purchaser & ourselves are deemed to be
entered at Noida and therefore subject to jurisdiction of civil court in Noida.
11. Warranty
a. All our equipments are thoroughly tested before dispatch and therefore can be
depended upon for long trouble free service. We undertake to make good, by
replacement or repair, defects arising out of faulty design, material or
workmanship, excluding those due to wear and tear within 15 months of the
date of dispatch or 12 months from the date of commissioning, whichever is
29 of 31
earlier, providing that if we do so require, the parts in respect of which
complaint is made, must be dispatched from the purchaser’s site to our works
at the expense of purchaser. Before liability can be entertained under this
clause such expenses will be refunded if our liability is admitted.
b. Bought out components such as motor, pumps, burners, etc. are guaranteed
by us only to the extend of guarantee given to us by respective suppliers.
We shall have a lien on the equipment supplied by us till all payments due to us
are released. The equipment will not be put into commercial operation or to
beneficial use without our written consent till we withdraw our lien.
13. Cancellation:
In case of Projects, we may send excess material to site to avoid any delay in the
project schedule due to material shortage. Such excess material will accompany
30 of 31
the regular material, but on the invoice only the value of the regular material will
be reflected. Therefore, after the execution excess material shall be taken back
without commercial invoice from your side. You shall provide the Challan for the
same.