Sub Project

The document outlines various construction and rehabilitation projects under the Anuradhapura Integrated Urban Development Project, including packages for civil works such as landscaping, underpasses, and sanitary facilities. It details the allocated costs, procurement methods, and target completion dates for each package. Additionally, it provides progress updates on the preparation of bidding documents and architectural designs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views11 pages

Sub Project

The document outlines various construction and rehabilitation projects under the Anuradhapura Integrated Urban Development Project, including packages for civil works such as landscaping, underpasses, and sanitary facilities. It details the allocated costs, procurement methods, and target completion dates for each package. Additionally, it provides progress updates on the preparation of bidding documents and architectural designs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 11

No Package/Sub-Project

Civil Works

Package 13 - Construction at Kubichchankulama riprap and retaining wall for islands


1.0 with rehabilitation of walk ways (SCDP/AFD/WK/15)

2.0 Package 14 - Rehabilitation of Kubichchankulama underground spillway section of


Mitheepala Senanayake Mawatha and Construction of Underpasses in front of
Southern Multimodal Transport Center (SCDP/AFD/WK/16)
2.1 Construction of underpasses in front of southern Multimedia Transport Center
2.2 Rehabilitation of Kubichchankulama underground spillway

3.0 Package 15 - Landscaping works at Nuwarawewa & Ranmasu Uyana,Development &


Landscaping works at Senanayake children Park and Inprovemenr to Kadapanaha
Tank area including Wolk way (SCDP/AFD/WK/17)
3.1 Nuwara wewa Landscaping works

3.2 Ranmasu Uyana Landscaping Work

3.3 Landscaping work and Development of Senanayake Children park

3.4 Improvements to Kadapanaha Tank Area and Walkway

package 16- Renovation of old Railway quarters for the tourism purpose ( between
4.0 Raihway plana and Lion Pillar ) ( SCDP/AFD/WK/18)

Package 17 - Construction of Sri Maha Bodhi Eastern Gate ( Dwara ) & Landscaping
of Sri Maha Bodhi Mawatha, Development of Abayagiriya Car Park and Construction
5.0 of sanitary facilities for jethavanaramaya. ( SCDP/AFD/WK/19)

Construction of Sri Maha Bodhi Eastern Gate ( Dwara ) & Landscaping of Sri Maha
5.1 Bodhi Mawatha

5.2 Development of Abayagiriya Car Park

5.3 Construction of Sanitary facilities for Jethawanaramaya

package 18 - Establishment of Shuttle Service and Construction of Bicycle Track in


6.0 sacred city (SCDP/AFD/WK/20)

Sub Total ( LKR )

Consultancy Services
7.0 Package 19 - E Heritage and Heritage valorization ( SCDP/AFD/CS)
Sub Total ( EUR )

8.0

9.0

10.0

11.0
procurement plan for additional sub - projects - Anuradhapura

Allocated Cost -
Procurement Bid/RFP Notice
LKR.Mn (without Approval
Method Publication
VAT)
Procument Category
works/goods/service
or consultancy service

450.00 works NCB MPC May,19.2022

works
600.00
450.00
150.00 NCB MPC June 14,2022

650.00
200.00
works
200.00

100.00

150.00 NCB MPC June 25,2022

950.00 NCB MPC July 19,2022

325.00

250.00

50.00

25.00 works NCB MPC July 13,2022

167.00 works NCB MPC August 2,2022

3,142.00
EUR 1,600,000 Consultancy NCB MPC June 21,2022
EUR 1,600,000
ub - projects - Anuradhapura Integrated Urban Development Project ( AIUDP )

Perion of the Target Completion


Target Award Date Target start Date
Conrtact (Days) Date

424 August 19,2022 October 18,2023


August 3,2022

August 27,2022 424 September 13,2022 November 11,2023

September 7,2022 424 August 19,2022 October 18,2023

September 30,2022 424 October 17,2022 December 15 , 2023

September 24,2022 211 October 11,2023 May 11 , 2023

October 17,2022 211 November 2 ,2022 June 2,2023


September 2,2022 371 September 09,2023 September 9, 2023
( AIUDP )

Progress
(As at April 25,2022)

preparation BOQ, Cost


Estimale and Bidding
Documents are in progress

detailed designs are being


finalized by Road
development Authority
( RDA )

Conseptual Architectural
designs have been
completed,Stakeholder
Consultation Meeting is
scheduled on April
26,2022
Conseptual Architectural
designs have been
completed,Stakeholder
Consultation Meeting yet
to be scheduled

Architectural designs and


structurat designs have
been completed.BOQ and
Costing will be starled
soon

Paths for suttle service


and Bicycle track are
being identified physically
by walking along the
paths
Concept and the TOR for
the Consultant yet to be
finalized