No Package/Sub-Project
Civil Works
Package 13 - Construction at Kubichchankulama riprap and retaining wall for islands
1.0 with rehabilitation of walk ways (SCDP/AFD/WK/15)
2.0 Package 14 - Rehabilitation of Kubichchankulama underground spillway section of
Mitheepala Senanayake Mawatha and Construction of Underpasses in front of
Southern Multimodal Transport Center (SCDP/AFD/WK/16)
2.1 Construction of underpasses in front of southern Multimedia Transport Center
2.2 Rehabilitation of Kubichchankulama underground spillway
3.0 Package 15 - Landscaping works at Nuwarawewa & Ranmasu Uyana,Development &
Landscaping works at Senanayake children Park and Inprovemenr to Kadapanaha
Tank area including Wolk way (SCDP/AFD/WK/17)
3.1 Nuwara wewa Landscaping works
3.2 Ranmasu Uyana Landscaping Work
3.3 Landscaping work and Development of Senanayake Children park
3.4 Improvements to Kadapanaha Tank Area and Walkway
package 16- Renovation of old Railway quarters for the tourism purpose ( between
4.0 Raihway plana and Lion Pillar ) ( SCDP/AFD/WK/18)
Package 17 - Construction of Sri Maha Bodhi Eastern Gate ( Dwara ) & Landscaping
of Sri Maha Bodhi Mawatha, Development of Abayagiriya Car Park and Construction
5.0 of sanitary facilities for jethavanaramaya. ( SCDP/AFD/WK/19)
Construction of Sri Maha Bodhi Eastern Gate ( Dwara ) & Landscaping of Sri Maha
5.1 Bodhi Mawatha
5.2 Development of Abayagiriya Car Park
5.3 Construction of Sanitary facilities for Jethawanaramaya
package 18 - Establishment of Shuttle Service and Construction of Bicycle Track in
6.0 sacred city (SCDP/AFD/WK/20)
Sub Total ( LKR )
Consultancy Services
7.0 Package 19 - E Heritage and Heritage valorization ( SCDP/AFD/CS)
Sub Total ( EUR )
8.0
9.0
10.0
11.0
procurement plan for additional sub - projects - Anuradhapura
Allocated Cost -
Procurement Bid/RFP Notice
LKR.Mn (without Approval
Method Publication
VAT)
Procument Category
works/goods/service
or consultancy service
450.00 works NCB MPC May,19.2022
works
600.00
450.00
150.00 NCB MPC June 14,2022
650.00
200.00
works
200.00
100.00
150.00 NCB MPC June 25,2022
950.00 NCB MPC July 19,2022
325.00
250.00
50.00
25.00 works NCB MPC July 13,2022
167.00 works NCB MPC August 2,2022
3,142.00
EUR 1,600,000 Consultancy NCB MPC June 21,2022
EUR 1,600,000
ub - projects - Anuradhapura Integrated Urban Development Project ( AIUDP )
Perion of the Target Completion
Target Award Date Target start Date
Conrtact (Days) Date
424 August 19,2022 October 18,2023
August 3,2022
August 27,2022 424 September 13,2022 November 11,2023
September 7,2022 424 August 19,2022 October 18,2023
September 30,2022 424 October 17,2022 December 15 , 2023
September 24,2022 211 October 11,2023 May 11 , 2023
October 17,2022 211 November 2 ,2022 June 2,2023
September 2,2022 371 September 09,2023 September 9, 2023
( AIUDP )
Progress
(As at April 25,2022)
preparation BOQ, Cost
Estimale and Bidding
Documents are in progress
detailed designs are being
finalized by Road
development Authority
( RDA )
Conseptual Architectural
designs have been
completed,Stakeholder
Consultation Meeting is
scheduled on April
26,2022
Conseptual Architectural
designs have been
completed,Stakeholder
Consultation Meeting yet
to be scheduled
Architectural designs and
structurat designs have
been completed.BOQ and
Costing will be starled
soon
Paths for suttle service
and Bicycle track are
being identified physically
by walking along the
paths
Concept and the TOR for
the Consultant yet to be
finalized