15 Subordinate Legislation 27
15 Subordinate Legislation 27
(PRESENTED ON 28.8.2012)
PRICE: Rs.
INTRODUCTION (v)
REPORT
I.    Background                                       1.1-1.10        1
II.  Interim Relief to the victims of Nuclear 2.1-2.8                  7
     Damage
III. Right of Recourse                        3.1-3.15                 10
APPENDICES
                                        (ii)
COMPOSITION OF THE COMMITTEE ON SUBORDINATE LEGISLATION
                            (2011-2012)
3.    The Committee considered and adopted this Report at their sitting held on
27.8.2012.
5.    Extracts of the Minutes of the fourth sitting of the Committee (2011-12) held
on 16.4.2012 and Minutes of the Ninth sitting of the Committee (2011-12) held on
27.8.2012 relevant to this Report are included in Appendix-II.
                                             P. KARUNAKARAN
New Delhi;                                       Chairman,
August, 2012                       Committee on Subordinate Legislation
Bhadra, 1934 (Saka)
                                        (v)
                                     REPORT
BACKGROUND
1.4 Indian nuclear industry has developed over a period of time within
the context of a domestic framework established by the Atomic Energy
Act, 1962. There is no provision in the Atomic Energy Act, 1962, about
nuclear liability or compensation for nuclear damage due to nuclear
accident or incident and no other law deals with nuclear liability for
nuclear damage in the event of nuclear incident.          It was, therefore,
considered necessary to enact a legislation which provides for nuclear
liability that might arise due to a nuclear incident and also on the necessity
of joining appropriate international liability regime.
1.5 The Civil Liability for Nuclear Damage Act, 2010 (CLND Act) received
the assent of the President on 21 September, 2010 and enforced with
effect from 11 November, 2011.
1.6 The Act provides for Civil Liability for Nuclear Damage and prompt
compensation to the victims of a nuclear incident through a no-fault
liability regime channelling liability to the operator, appointment of Claims
Commissioner, establishment of Nuclear Damage Claims Commission
(NDCC) and for matters connected therewith or incidental thereto. It
extends to the whole of India. It applies to nuclear damage suffered (i) in
or over the maritime areas beyond the territorial waters of India, (ii) in or
over exclusive economic zones of India, (iii) on board or by a ship/aircraft
registered in India, and; (iv) on or by an artificial island, installation or
structure under the jurisdiction of India. It applies only to the nuclear
installation owned or controlled by the Central Government either by itself
or through any authority or corporation established by it or a Government
company.
1.7 As per Section 48 of the Act, the Central Government may make rules
for carrying out the purposes of this Act by notification. Such rules may
provide for (i) the other financial security and the manner thereof; (ii) the
salary and allowances payable to and the other terms and conditions of
service of Claims Commissioner; (iii) the procedure to be followed by
Claims Commissioner; (iv) the person to be associated by Claims
Commissioner and the manner thereof; (v) the remuneration, fee or
allowances of associated person; (vi)       the form of application, the
particulars it shall contain and the documents it shall accompany; (vii) the
salary and allowances payable to and other terms and conditions of
service of Chairperson and other Members of Nuclear Damage Claims
Commission;     (viii) the powers of Chairperson; (ix) the salary and
allowances payable to and the terms and other conditions of service of
officers and other employees of the Commission; (x) the form of
application, the particulars it shall contain and the documents it shall
accompany; (xi) the form and the time for preparing annual report by the
Commissioner , and; (xi) the manner of transfer of officers and other
employees of the Commission.
2.1 As per section 9 (1) of the Act, whoever suffers nuclear damage is
entitled to claim compensation in accordance with the provisions of the
Act. The Central Government, as per section 9(2) of the Act is required to
appoint one or more Claims Commissioner to adjudicate upon claims for
compensation in respect of nuclear damage. As per section 19, the Central
Government may also appoint Nuclear Damage Claims Commission, if it is
of the opinion that it is expedient in public interest that such claims for
such damage be adjudicated by the Commission instead of a Claims
Commissioner.
2.2   Section 13 of the CLND Act provides for inviting applications for
claims by Claims Commissioner, after notification of the nuclear incident
under sub section 1 of section 3 of the Act, from the persons affected by
the nuclear incident for damages.
2.4 Section 16(5) of the Act specifies that every award made under
section 16 (1) shall be final. The DAE, in post evidence written reply to a
query as to whether section 16(1) of the Act implies that no appeal lie
against the compensation for nuclear damage given by the Claims
Commissioner, stated as follows:
      “The orders of the Claims commissioners and the Commission are
      final under the Act in the absence of any appellate provision in the
      Act. However, the same are subject to judicial review by the High
      Courts and Supreme Court as provided under Section 35 of the Act.”
2.6 Elaborating further on the issue, the Secretary, DAE stated as follows-
      “With regard to interim relief, the issue is that it has to be settled so
      quickly that there will be no requirement of interim relief”
2.7   Reiterating their stand that there is no need for interim relief, the
DAE, in written reply to a post evidence query as to whether it was
desirable to have a provision for interim relief in the rules in view of the
sensitivity/severity of the nuclear incidents and also the time involved in
providing compensation to the losses suffered, stated as follows:
      “The Act prescribes under sub-section 16 and sub-section (6) of Section
      32 a period of 3 months from the date of application for disposal of the
      claim. This period is short and pre-empts the need for a provision for
      interim relief.”
2.8    The Civil Liability for Nuclear Damage Act, 2010 provides that the
Claims Commissioner or the            Nuclear Damage Claims Commission
(NDCC) are required to adjudicate claims and award claims for nuclear
damage within three months of receipt of application. The Committee
observe that though there is no provision in the Act for appeal against
the award of Claims Commissioner/NDCC, any applicant not satisfied
with the award, can seek judicial review of the awards. The Committee
feel that in the event of an applicant seeking judicial review of the award
given by Claims Commissioner/NDCC, the amount awarded as
compensation should be treated as interim relief and be disbursed
pending verdict of the court.        The Committee desire that a suitable
enabling provision be incorporated in this regard either in the CLND Act
or the CLND Rules as may be deemed appropriate.
                                           III
                                 Right of Recourse
3.1 Rule 24 dealing with right of recourse provides that any contract under
sub section (a) of Section 17 of the Act shall not be for an amount less than
the amount of operator liability under the Act or the value of the contract
itself, whichever is less.
3.2. Section 17 of the Act which provides for right of recourse to the
operators of the nuclear installations reads as follows:
    “The Operator of the nuclear installation, after paying the compensation for
    nuclear damage in accordance with section 6, shall have a right of recourse
    where
     (a) such right is expressly provided for in a contract in writing;
     (b) the nuclear incident has resulted as a consequence of an act of
            supplier or his employee, which includes supply of equipment
            or material with patent or latent defects or sub-standard
            services;
     (c)    the nuclear incident has resulted from the act of commission
            or omission of an individual done with the intent to cause
            nuclear damage.”
3.3 Rule 24 of Civil Liability for Nuclear Damage Rules, 2011 on the right of
recourse states as follows:
      “(1):- A contract referred to in clause (a) of section 17 of the Act shall
      include a provision for right of recourse for not less than the extent of the
      operator’s liability under sub-section (2) of Section 6 of the Act or the
      value of the contract itself, whichever is less.
     (2) The provision for right of recourse referred to in sub-rule (1) (1)
     shall be for the duration of initial license issued under the Atomic Energy
     (Radiation Protection) Rules, 2004, or the product liability period,
     whichever is longer
3.4 Section 17 of the Act enables the operator of the nuclear installation
after paying compensation for nuclear damage in accordance with section
6 of the Act to have the right of recourse in case inter-alia such right is
expressly provided for in a contract in writing. Explaining the rationale for
the provision, the Secretary, DAE during the evidence held on 16.04.2012
stated as under:-
    ‘’Supplier shall also include a person who manufactures and supplies either
    directly or through an agent a system, equipment or component or he builds
    a structure on the basis of functional specifications. There is a difference
    between functional specifications and engineering drawings. If the operator
    provides all the details and has the quality control, then he cannot go to the
    supplier and say this is because of you because you have provided everything.
    They have only provided the service.
      When the operator is giving a functional specification and not a detailed
    drawing and design, to a vendor for manufacturing a system, then the
    supplier is responsible. If the operator is giving complete details, even
    manufacturing details, equipment or components for building a structure,
    then he is responsible for design and quality assurance. Only when you can
    pinpoint the responsibility of the supplier, then only it should be possible to
    make the supplier liable for the damage. Otherwise, because of the fault of
    somebody else, you will make the supplier responsible. That should not be
    done. That is what has been explained by the rules related to the provision of
    the CLND Act.
    How will you make the contract between the two parties? At present contract
    between the two parties take care of the product liability for covering. That is
    for their own damage. This will allow that to happen for external damages
    also, that is nuclear damage.”
3.5. Section 6 (2) of the Act which prescribes the liability of the operator
for nuclear incidents reads as under:
         ‘’ the liability of an operator for each nuclear incident shall be
3.7 Rule 24 prescribes that the contract between the supplier and the
operator shall include a provision for the right of recourse for not less
than the extent of operator’s liability as mentioned under section 6 (2) (i)
of the Act or the value of the contract itself. In reply to a query as to
whether Rule 24 (1) violates the substantive provisions of the Act as it
restricts the liability prescribed by the Act, the Department of Atomic
Energy vide their reply dated 21.2.2012 inter-alia stated as follows:
      “Under the right of recourse, an operator will have the right to claim
      reimbursement from the supplier and reimbursement cannot be more
      than what he has paid. Liability of operator is prescribed by sub-section 2
      of section 6. The Rule 24 automatically links sub-section 2 of section 6
      and section 17. Rule 24 prescribes minimum requirements for contract
      made under clause (a) of section 17 of the Act. It does not restrict the
      parties from entering into a contract involving an amount higher than the
      contract value (limited of course to the provision of sub section 2 of
      section 6) or a longer duration.”
3.8 The following are the main principles of the liability regimes under
1960 Paris convention and 1963 Vienna Convention:
     (ii)    Liability of the operator is absolute, i.e. the operator is held liable
             irrespective of fault
     (iii)   Liability is limited in amount. Under the Vienna Convention, it may
             be limited to not less than US$ 5 million (value in gold on 29 April
             1963), but an upper ceiling is not fixed. The Paris Convention sets a
             maximum liability of 15 million SDR provided that the installation
             State may provide for a greater or lesser amount but not below 5
             million SDRs taking into account the availability of insurance
             coverage.
     (iv)    Liability is limited in time. Compensation rights are extinguished
             under both Conventions if an action is not brought within ten years
             from the date of the nuclear incident. Longer periods are
             permissible if, under the law of the installation State, the liability of
             the operator is covered by financial security. National law may
             establish a shorter time limit, but not less than two years (the Paris
             Convention) or three years(the Vienna Convention) from the date
             the claimant knew or ought to have known of the damage and the
             operator liable;
     (v)     The operator must maintain insurance of other financial security for
             an amount corresponding to his liability; if such security is
             insufficient, the installation State is obliged to make up the
             difference up to the limit of the operator´s liability;
     (vi)    Jurisdiction over actions lies exclusively with the courts of the
             Contracting Party in whose territory the nuclear incident occurred;
     (vii)   Non-discrimination of victims on the grounds of nationality, domicile
             or residence.”
3.9 On the issue of liability regime fixed under 1960 Paris Convention,
1963 Vienna Convention, and the Protocol to amend the Vienna
convention, the Secretary, DAE , deposing before the Committee on 16
April, 2012 , stated as under-
      “Today, in the world over, if you see liability law, the Indian Liability Act
      has become most strict. All over the world the trend is that you have to fix
      the liability to the operator. If you can’t fix the liability to the operator,
      then you go to the litigation and it can never be settled within short time ,
      So, that was the reason for which the Parliament has also cleared the act
      on the spirit that it has to be done by Claims Commissioner in the time
      frame
      ... In the nuclear liability regime internationally, this third party damage is
      not there in other places. We have introduced it in the Act. Now the
      question is there is a question of cause - effect relationship that is
      because of the fault of somebody’s supply that this damage is caused.
      This fault is not fault of one particular company. A series of companies
      have to have a cause ...”
      Limiting the Liability Period
3.10 Rule 24(2) of the Rules          imposes restrictions in terms of time period
during which liability is applicable – five years or the product liability period
whichever is longer.
3.11 On being inquired that the Rule 24(2) not only inhibits the very purpose of
the Act but is in conflict with the Act itself as the right of recourse has been
restricted to duration of initial license issued under the Atomic Energy Rules
2004 (which is 5 years) or the product liability whichever is longer, the
Department of Atomic Energy vide their reply dated 21.2.2012 furnished
following comments:
     “Section 17 (b) refers to the liability for patent or latent defect in the
     nuclear material, equipment or sub-standard services and therefore,
     refers to the product liability which is dependent on the relevant clause in
     the contract. The equipment and components are subject to periodic
     inspection and quality check throughout the process of contraction of a
     nuclear installation. When the plant goes into operation, checks on the
     health of components, equipment and systems are carried out by the
     operator based on a planned schedule. Any weakness or defects in the
     plant would invariably manifest themselves during commissioning or
     during the first few days and months of operation. Atomic Energy
     Regulatory Board gives license for a limited period so as to be in a position
     to keep checking that operator maintains the plant in a healthy condition
     and also asks operator to keep upgrading the plant safety system in
     accordance with any new safety requirements that might emerge due to
     operating experience anywhere in the world or development in science
     and technology. The equipment and components requiring replacement is
     changed as and when their useful life is over and this ensures that reactor
     always remains healthy even as the reactor ages. Since significant changes
     might be done during initial operation of the plant and the fact that
     operation and maintenance is the responsibility of the operator, it is not
     desirable to hold the supplier responsible beyond certain initial period.
     Period of initial license becomes a natural choice for the period for the
     supplier’s liability.
     “Each contract has a product liability clause and the product liability period
     is regulated in accordance therewith. General conditions of contract
     generally include a period of 12 months for patent defects and 5 years for
     latent defects.”
3.15   Rule 24 of the CLND Rules has the effect of diluting the stringent
liability provided in section 17 of the CLND Act by imposing limitations in
terms of the amount which can be claimed by exercising right of recourse
(limiting to the extent of operator’s liability or the value of the contract
whichever is less) and also the duration for which a supplier can be held
liable, not contemplated under the CLND Act. The Committee hold that
delegated legislation (viz. rules made by the Executive) should be
consistent with the substantial provisions of the Act and should not
contain any limitations or excesses which are not contemplated under
the Act. The Committee are of the firm view that rule 24 has inserted
limitations not   mandated by the CLND Act as brought out above. The
Committee, therefore, exhort DAE to amend rule 24 suitably to remove
the limitations imposed on the liability as well as the duration of the
liability period.
                                        IV
4.1 As per Section 3(1) of the CLND Act, 2010 the Atomic Energy
Regulatory Board (AERB) constituted under the Atomic Energy Act,
1962 shall notify nuclear incidents within a period of fifteen days from
the date of occurrence of a nuclear incident.
5.2 In response to the query on the reasons for delay of about thirteen
months in enforcing the Act, the Department of Atomic Energy, in a
written reply dated 16.05.2012, submitted as follows:
     “It was necessary to notify the Act and the Rules together. The drafting of
     Rules took quite some time as the Department had to go through legal
     consultations including multiple consultations with the Attorney General
     for India.”
5.4 The Committee are distressed to note that delay in framing of rules
under the CLND Act has caused delay of thirteen months in notification /
enforcement of the Act. Had the Department of Atomic Energy initiated
action to frame the rules along with drafting of the legislation, there
would not have been such inordinate delay in enforcement of the Act.
The Committee hope that the Department will initiate timely action in
framing rules while drafting any legislation in future.
5.7 The Committee regret to note that the CLND Rules notified more
than one year after the Bill was assented to by the President are not
complete and “the other terms and conditions of service” of the Claims
Commissioner and the Chairperson and the members of the Commission
are stated to be still under the consideration of a departmental
committee of DAE. The Committee do not expect such lackadaisical
approach in framing of rule by the DAE The Committee hope that the
Departmental Committee would complete its task without any further
loss of time and DAE will notify the rules under intimation to the
Committee.
                                          VI
Legislation by reference
6.1 In rule 5(1) and 24 (2) reference is made to the Atomic Energy Act,
1962 and the Atomic Energy (Radiation Protection) Rules, 2004
respectively. The Committee on Subordinate Legislation have time and
again recommended that the legislation by reference should be avoided
and the rules should be self-contained.
      “The provision for right of recourse referred to in sub rule (1) shall be for
      the duration of initial license issued under the Atomic Energy (Radiation
      Protection) Rules, 2004 or the product liability period, whichever is
      longer.”
 6.4 Asked about their comments for not making the rules self contained
and making references to other Act and Rules in the CLND Rules, 2011
[Reference to Atomic Energy Act, 1962 and Atomic Energy (Radiation
Protection) Rules, 2004], the Department of Atomic Energy (DAE)
submitted as follows:
      “Reference to the Atomic Energy Act, 1962 and the rules made there
      under is necessary in order to avoid duplication. Since the licensing of
      facilities is regulated by the Atomic Energy (Radiation Protection) Rules,
      2004, reference to the same adds clarity to the provision. A reference
      to Atomic Energy Act and the Atomic Energy (Radiation Protection) Rules
      would mean that any change therein will automatically be reflected in
      the Rules.”
7.1 The term ‘Supplier’ is occurring in section 17 of the Act, but the term
is not defined in Section 2 of the Act. However, the same has been defined
in the rule 24.
7.3 The term ‘supplier’ which appears in Section 17 of the CLND Act has
not been defined in the Act but defined in CLND Rule 24. Definition of a
term appearing in an Act should be made in the very statute and not in
the rules made thereunder. It is not for the Executive to lay down the
contours of a term or to interpret it through the rules.                This again
amounts to Executive exceeding the authority delegated by the
Parliament. The Committee, therefore expect the DAE to amend the Act
to incorporate the definition regarding ‘supplier’.
7.6. The term ‘representative’ used in rule 6(1) (c) of the CLND Rules has
not been defined and leaves scope for different interpretations. The
contention of the DAE that the term ‘representative’ carries same
meaning as the term ‘legal representative’ is not convincing as it fails to
explain the reason for not using the term ‘legal representative’ in Rule
6(1)(c). There should be uniformity in usage of terms in the Rules as
these have legal implications. The Committee, therefore, desire that the
term ‘representative’ should be replaced with the term ‘legal
representative’ in the rule.
                                         P. KARUNAKARAN
New Delhi;                                    Chairman,
August, 2012                   Committee on Subordinate Legislation
Bhadra, 1934 (Saka)
                                      APPENDIX –I
                2.8         The Civil Liability for Nuclear Damage Act, 2010 provides
                            that the Claims Commissioner or the Nuclear Damage
                            Claims Commission (NDCC) are required to adjudicate
                            claims and award claims for nuclear damage within three
                            months of receipt of application. The Committee observe
                            that though there is no provision in the Act for appeal
                            against the award of Claims Commissioner/NDCC, any
                            applicant not satisfied with the award, can seek judicial
                            review of the awards.      The Committee feel that in the
                            event of an applicant seeking judicial review of the award
                            given by Claims Commissioner/NDCC, the amount
                            awarded as compensation should be treated as interim
                            relief and be disbursed pending verdict of the court. The
                            Committee desire that a suitable enabling provision be
                            incorporated in this regard either in the CLND Act or the
                            CLND Rules as may be deemed appropriate.
2 Right of Recourse
     5.4
           The Committee are distressed to note that delay in framing
           of rules under the CLND Act has caused delay of thirteen
           months in notification / enforcement of the Act. Had the
           Department of Atomic Energy initiated action to frame the
           rules along with drafting of the legislation, there would not
           have been such inordinate delay in enforcement of the
           Act. The Committee hope that the Department will initiate
           timely action in framing rules while drafting any legislation
           in future.
     5.7   The Committee regret to note that the CLND Rules notified
           more than one year after the Bill was assented to by the
           President are not complete and “the other terms and
           conditions of service” of the Claims Commissioner and
           the Chairperson and the members of the Commission are
           stated to be still under the consideration of a departmental
           committee of DAE. The Committee do not expect such
           lackadaisical approach in framing of rule by the DAE The
           Committee hope that the Departmental Committee would
           complete its task without any further loss of time and DAE
           will notify the rules under intimation to the Committee.
5. Legislation by reference
7.6   The term ‘representative’ used in rule 6(1) (c) of the CLND
      Rules has not been defined and leaves scope for different
      interpretations. The contention of the DAE that the term
      ‘representative’ carries same meaning as the term ‘legal
      representative’ is not convincing as it fails to explain the
      reason for not using the term ‘legal representative’ in
      Rule 6(1)(c). There should be uniformity in usage of
      terms in the Rules as these have legal implications. The
      Committee, therefore, desire that the term ‘representative’
      should be replaced with the term ‘legal representative’ in
      the rule.
                                    APPENDIX –II
                   (Vide Para 5 of the Introduction of the Report)
         The Fourth sitting of the Committee held on Monday, the 16th April, 2012 from
1400 to 1600 hours in Committee Room No. G-074, Parliament Library Building, New
Delhi.
PRESENT
                                        MEMBERS
LOK SABHA
SECRETARIAT
2. At the outset, the Chairman welcomed the Members of the Committee and the
representatives of the Department of Atomic Energy and drew the attention of the
Department of Atomic Energy in connection with examination of the Civil Liability for
Nuclear Damage Rules, 2011, particularly on the issues such as exceeding the power
of delegation, right of recourse, time limit for settlement of claims, period of liability of
supplier, etc.
4. The Chairman then desired that the Department may furnish written replies to
                                              -----
MINUTES OF THE NINTH SITTING OF THE COMMITTEE ON SUBORDINATE
LEGISLATION (2011-2012)
                                       ______
      The Ninth sitting of the Committee held on Monday, the 27th August, 2012 from
1500 to 1530 hours in Chairman’s Room No. 143, Parliament House, New Delhi.
PRESENT
MEMBERS
SECRETARIAT
3. The Committee, then, considered the draft ‘Twenty Seventh Report’ and
adopted the same without any modification. The Committee authorized the Chairman to
-----