Internship Report 220170109027
Internship Report 220170109027
Submitted by
220170109027
BACHELOR OF ENGINEERING
in
1
DEPARTMENT OF ELECTRICAL ENGINEERING
VISION
MISSION
learning M2: To produce competent and disciplined electrical engineers to serve the
nation.
M3: To help in building national capabilities for excellent energy management and to
explore non conventional energy sources.
2
VISHWAKARMA GOVERNMENT ENGINEERING COLLEGE CHANDKHEDA
CERTIFICATE
This is to certify that Mr. DEDUN ROHITKUMAR RAMESHBHAI (En. No: 220170109027) Sem:-6
B.E (Electrical Engineering), has completed the Summer Internship/Industrial training entitled “220KV
GETCO under my guidance and the report has been submitted to Electrical Engineering Department.
3
[Company/Industry letterhead]
No. Date:
Student of Electrical Engineering, Vishwakarma Government Engg. College Chandkheda, has successfully
completed a two week Internship in the field of 220 KV SANTEJ SUB-STATION,GETCO during the
period of _02-07-2025 TO 16-07-2025.During the period of his internship program with us, He had been
4
Acknowledgement
First, I would like to thank Head of The Department Dr. S.N. Pandya of
Vishwakarma Government Engineering College, Ahmedabad for giving
permission to commence this Internship.
5
Abstract
6
Table of content
Acknowledgement 5
Abstract 6
1 Introduction 10
1.1 About Company
3 Switchyard 15
3.1 Lightening Arrester
3.2 Isolator
3.3 Circuit Breaker
3.4 Current Transformer
3.4.1 Current Transformer Tests
3.5 Potential Transformer
4 Power Transformers 29
4.1 Cooling Mechanism
4.1.1 Oil natural air natural
4.1.2 Oil natural air forced
4.1.3 Oil forced air forced
4.2 Transformer Detail
4.3 Important Part Of Power Transformer
4.3.1 OLTC
4.3.2 PRV
4.3.3 Buchholz relay
4.3.4 Breather
4.3.5 NIFPS
5 Battery Room 37
6 Control Room 39
6.1 Types Of Panels In Substation
7 Protection systems 43
7.1 Distance protection
7.2 Busbar protection
7
7.2 Protection of transformer
7.2.1 Differential protection
7.2.2 Restricted earth fault
7.2.3 Backup protection
7.2.4 Buchhloz relay
7.2.5 Thermal protection
7.2.6 Pressure relief valve
8 Equipment testing 53
8.1 Lightening arrester testing
8.2 Circuit breaker testing
8.3 Battery testing
8.4 Transformer testing
10 Conclusion 60
Reference 61
8
List of figures
Figure 1.1 overview of industry 10
9
Chapter 1 : Introduction
1.1 Overview of industry
( Figure 1.1)
The central government of india passed the electricity act in 2003, 3hile the Gujarat
government approved the Gujarat electricity industry act in 2003. And other items of
former Gujarat electricity board to new entities. As a result GEB divides into seven
firms with operational responsibility for trading, generation, transmission and
distribution as of 1 april 2005.
10
Company type Public sector utility
Industry power
predecessor Gujarat Electricity
Board(GEB)
Founded 1999
Headquarter Vadodara
Area reserved Gujarat
Service Power transmission
Number of employees 13,000+
400 16 6,096
132 57 5,566
11
Chapter 2 : Single line diagram
12
Chapter 3 : Switchyard
13
■ Bus bar differential:- detects the fault within the busbar
protected zone.
■ Transformer differential:- protects the transformer in case of
faults within the transformer or the differential protection
zone.
○ Distance protection:- Mho relays are used to detect the faults
along the zones decided by the relay CT and PT are used for the
measurement. As this method of protection has a large time delay
hence the line differential protection system is also used to
protect the system.
○ REF (restricted earth fault):- during an internal fault, the neutral
current transformer only carries the unbalanced fault current,
and operation of the Restricted Earth Fault Relay takes place.
14
3.1 Lighting Arrester
Figure 4.2
The arrester which uses zinc oxide semiconductor as a resistor material, such
type of arrester is known as a metal oxide lighting arrester.
This arrester provides protection against all types of AC and DC over
voltages. It is mainly used for overvoltage protection at all voltage level in a
power system.
15
the zinc oxide is a semiconducting material of N-type. It is pulverized and
finely grained. More than ten doping materials are added in the form of fine
powder of insulating oxides such as bismuth, antimony trioxide, cobalt
oxide, manganese oxide, chromium oxide. The powder is treated with some
processes and the mixture is spray dried to obtain a dry powder.
The ZnO element eliminates series sparks gaps in diverter. The voltage drop
in ZnO diverter takes place at the grain boundaries. There is a potential
barrier at the boundary of the each grain ZnO and this potential barrier
control the flow of current from one grain to the next.
At normal voltage, the potential barrier does not allow the current to flow
through it. At over voltage the barrier collapse and sharp transition of
current from insulating to conducting state take place. The current start
flowing and the surge is diverted to ground.
16
3.2 Isolator
An isolator, also known as a disconnector or disconnecting switch, is a
mechanical switch that's manually operated to isolate a faulty section of
a substation's circuit. This separation, called an air break, allows the
healthy section of the circuit to remain intact while the faulty section is
being repaired. Isolators are often used on both ends of a breaker for
safe replacement or repair
Isolators are different from circuit breakers, which are on-load devices
that detect and trip when an electric fault occurs. Isolators, on the other
hand, are off-load devices that are only used when there is no load, or
zero current flowing through them. Isolators also have a locking system
or external lock to prevent accidental use, which is especially important
for high-voltage devices like transformers. The line isolator has an
earthing switch for line current discharge.
17
3.3 Circuit Breaker
19
Core-1 is used of 0.5 class. (used for metering)
Core-3 PS class used in numerical relays. (for differential protection) CTs are
marked P1 and P2.
In 220kV CT there are 5 cores which include the the main 3 cores of the 66 kV
CT and the other two cores are
Core-4/5- is PS class which is used for numerical relays. (may be used for
20
3.4.1 current transformer test
polarity test
ratio test
IR test
Knee point voltage test
Tan-delta test
3.4.1.1 Polarity test
Ratio test Fig. indicated in Suppose the current injection kit should be
100Amp for the ratio test of CT used in the line. And MA must be a
measurable A meter.
By connecting a wire across P1 and P2 of CT, 30 Amp is given between
1S1 and 1S2 i.e. 300 ratio is to be tested, if 30Amp current is given on
the primary side, 100mA current should be getting between 1S1 and
21
1S2 in the secondary. So the ratio is correct. In this way, the ratio test of
each CT
22
can be taken.
3.4.1.3 IR test
Megger is used to test the insulation of the CT. 5kV is applied to the test
terminals and these are used to check the resistance between the two
test terminals.
The IR test is used to get the resistance between at 5KV potential,
P1 to core
P1 to core
At 500V
Core 1 to Core 2
Core 2 to Core 3
Core 3 to Core
1 Core 1 to
earth Core 2
to earth Core
3 to earth
This data is noted and compared with new data as this is a yearly test. And that is
called conditioning monitoring.
23
3.4.1.4 IR test
Megger is used to test the insulation of the CT. 5kV is applied to the test
terminals and these are used to check the resistance between the two
test terminals.
The IR test is used to get the resistance between at 5KV potential,
P1 to earth
P1 to core
2 P1 to core
3
At 500v,
Core 1 to core 2
Core 2 to core 3
Core 3 to core
1 Core 1 to
earth Core 2 to
earth Core 3 to
earth
This data is noted and compared with new data as this a yearly test. And that is
called conditioning monitoring.
24
3.4.1.5 Knee Point Voltage Test
This test should have a point voltage test kit with a meter capable of
measuring 0 to 2kV and 0 to 100mAof current. Fig. has shown.
Accordingly this test is taken in Ps class. By connecting as shown in Fig,
first mA is measured at 100v, then mA is measured at 500v, then the CT
shown above should be given 1000v or 1400v giving 25mA or 30mA as
the case may be.
25
3.4.1.6 Tan-Delta test
26
values indicate deterioration.
27
3.5 Potential Transformer
A potential transformer (PT), also known as a voltage transformer (VT),
is a measuring device used in power systems to convert high voltage
values to lower ones for protection and measurement purposes. PTs are
designed to have an accurate voltage ratio and phase relationship and to
present a negligible load to the supply being measured. This allows for
accurate secondary connected metering.
They are also used in protective relay devices and metering devices.
PTs are electromagnetic, outdoor type, single phase, oil-filled, and self-
cooled. They have shaded porcelain bushing or insulators and are
suitable for operation without protection from sun, rain, and dust.
The primaries of PTs are rated from 400 V to several thousand volts, and
secondaries are always for 110 V. Up to voltages of 5,000, PTs are
usually of the dry type. If the voltage is between 5,000 and 13,800 volts,
then the transformer
may be either dry type or oil-immersed type.
28
Chapter 4 : Power Transformers
29
according to the temperature the speed of the fans will
30
automatically adjusted.
31
Litre Line Current HV (OFAF):- 419.891A
32
No Load Loss (guaranteed):-
1399.637A
354.344KW(Max.)
33
4.3 Important parts of the Power Transformers
34
4.3.2 Pressure Relief Valve (PRV):- A pressure relief
valve (PRV) is a safety device that protects transformers from
damage caused by high oil pressure buildup during fault
conditions. The PRV is usually mounted on top of the
transformer but can be installed in any position on the cover
or wall. When the pressure inside the transformer exceeds a
pre-set limit, the PRV opens its valve clap, which a spring
holds in place. The valve clap releases the internal pressure
until it declines. PRVs are adjustable and can be set to relieve
pressure within a specific range, making them suitable for
processes with varying pressure requirements.
PRVs can be used in transformers, pressure tanks, and pressure
lines for both indoor and outdoor applications. They are also
suitable for repeated operation, unlike conventional explosion
vents.
35
4.3.3. Buchholz Relay:- A Buchholz relay is a safety device
that protects and monitors insulated liquid-filled transformers
with expansion tanks and earth leakage coils. It's installed in the
cooling circuit of the transformer and monitors internal gas
accumulation and oil flow. The relay responds to faults such as
gas or excessive flow of the insulating liquid with a warning or
disconnection signal. This prevents damage to the transformer
or even its destruction.
The relay operates based on mechanical phenomena to detect
minor faults through gas accumulation or major faults indicated by
oil surges. When a serious fault occurs, the generation of gas is so
rapid that an oil surge is set up through the relay. This oil flow
impinges upon a flap fitted to the trip element, causing it to rotate
and bring the mercury switch to the closed position. This in turn
operates the tripping devices.
36
4.3.4 Breather:- A transformer breather, also known as a
dehydrating breather, is a cylindrical vessel that removes moisture
from the air that flows into a transformer's conservator tank while
the transformer is cooling down. The breather contains silica gel
beads or crystals that absorb moisture from the air, protecting the
transformer's insulating liquid and preventing condensation in the
expansion tank.
37
the issue and activate valves to drain oil from the tank and inject
nitrogen gas to displace oxygen. The nitrogen acts as a cooling
and insulating medium, and can quickly extinguish fires. NIFPS
systems have several advantages over other fire prevention
systems, including:
Low cost: compared to other systems, NIFPS systems are relatively
inexpensive.
Low maintenance: NIFPS systems require minimal maintenance and
running costs.
Unaffected by climate: NIFPS systems are not affected by changes in the
weather.
38
Chapter 5 : Battery Room
1. 110 V
2. 48 V
39
The float charger is directly connected to the load & Boost charger is
connected directly to the battery. During normal operation, the Float
charger is on and continues to supply the DC load, and the battery is
floated with it. If the battery is discharged and demands current over a
set limit, the Boost charger is switched on. The boost charger is switched
off automatically on the battery reaches the desired level.
40
Chapter 6 : Control room
The Control Room contains relay panels and control panels.
41
6.1 Types of Panels in Substation
42
6.1.1 Line control and relay panel
43
This panel includes a circuit breaker, current transformer, relay,
ammeter, MW meter, KVAR meter, KWh meter, voltmeter, indication
LED, annunciator, alarm, and control switches.
A bus coupler panel is used to connect two buses and it is used for
increase power reliability during maintenance and also fault conditions.
The transformer control and relay panel are used for controlling
transformer CB manually as well as automatically by relay and
transformer protection relays are placed in this panel.
The transformer panel indicates the type of fault that occurs in the
transformer by annunciator window and alarm.
The remote tap changer panel's main function is to change the tap
position of the transformer and another function is to show transformer
winding and oil temperature, and control the cooling fan and oil pump.
PLCC panel is used for communication which is the power line carrier
communication.
DCDB panel used for DC distribution for control room Capacitor bank use for
improving power factor.
44
Chapter 7 : Protection systems
45
7.2. Busbar protection
only the faulty section while keeping the rest of the system stable
and functional.
46
6.2 Protection of transformer
47
Figure 8.3
In the Restricted Earth Fault scheme the common terminals of phase CTs
are connected to the secondary of Neutral CT in such a manner that the
secondary unbalance current of phase CTs, and the secondary current of
Neutral CT will oppose each other. If both currents are equal in
amplitude there will not be any resultant current circulating through the
said closed path. The Restricted Earth Fault Relay is connected in this
closed path. Hence the relay will not respond even if there is an
unbalancing in-phase current of the power transformer.
The restricted earth-fault stage operates exclusively on earth faults
inside the area of protection. The area of protection is limited by the
phase current transformers and the current transformer of the neutral
earthing circuit.
The earth fault relay is placed in the residual part of the current
transformers shown in the figure below. This relay protects the delta or
unearthed star winding of the power transformer against the fault
current. The connection of earth fault relay with the star or delta
48
winding
49
of the transformer.
50
7.3.3 Backup protection
Figure 8.4
51
Whenever a small fault happens within the electrical device, heat is made by the
fault currents. The heat causes the decomposition of electrical devices oil and
gas bubbles are made. These gas bubbles run in the upward direction and are
collected .
The insulating transformer oil will be decomposed in different hydrocarbon
gases, co2 and co.
The lower element consists of a baffle plate and a merqury switch. This plate is
fitted on a hinge just in front of the inlet of the buchhloz relay in a transformer
in such way that when oil enters in the relay from that inlet in high pressure
the alignment of the baffle plate along with the mercury switch attached to it,
will change.
Sometimes, oil leakage in the main tank can lead to air bubbles accumulating in
the upper part of the buchhloz container, causing the oil level to fall and
triggering the alarm circuit.
52
7.3.5 Thermal Protection
53
7.3.6 Pressure Relief Valve (PRV)
54
55
Chapter 8 : Equipment testing
Resistance testing is crucial for verifying that the insulating material that
makes up the molded case breakers are performing correctly. To test for
insulation resistance, an instrument known as a “megger” is used. A
megger instrument applies a known DC voltage to a given wire for a
given
56
period to test the resistance within the insulation on that particular wire
or winding. Voltage must be applied because resistance tested with an
ohm meter may vary when there are no potential differences present. It
should also be noted that if you apply a voltage that is too high for that
insulation to withstand, then you could potentially damage the
insulation. Meggers are rated and have specific settings that range from
300, 600, 1000, and 3000 Volt settings
57
8.3. Battery testing
8.3.1 Voltagetest
58
gravity
59
also increases as the battery is recharged.
A hydrometer measures the specific gravity of the electrolyte solution in
each cell. It's a tool used to measure the density or weight of a liquid
compared to the density of an equal amount of water.
8.4.4 IR Test
61
least 100 times the
62
operating voltage.
63
8.4.7 SCADA SYSTEM
64
Chapter 9 : Maintenance and LCP
Substation Maintenance is a process of periodic, planned
inspection of and, if necessary, repair, and replacement of all
switchgear and ancillary equipment in the substation. If 220 KV
Substation Maintenance is required, then 48 hours ago inform the
state load dispatch center ( SLDC). If SLDC allows the maintenance
will occur at a particular date and time limit.
The LCP(Line clearance Permit) system is used for safety
purposes. LCP is one type of permission to do maintenance in the
substation which is given by the service operator to the
maintenance operator. In LCP also mentioned that which switch
yard or bays parts maintenance occurs. When all work is done the
LCP is returned to the substation on service operator.
Cleaning and oiling of contacts of an isolator switch in the yard for
PMM work in 220 KV Substation. Cleaning the insulator in the
yard and tightening the jumper and its jo-contacts. If the JO
contacts heated then replace it and put new contacts. Cleaning the
breakers, and their wiring and cleaning the panels of the control
room. Check the 11 KV Bus Bar and the cable box and check the
cable insulation and bus nut bolt. To remove a hot point by
checking the previous hot point. Whenever doing maintenance the
earthing is compulsory. Check the all relays of the transformer
and lines.
65
Chapter 10 : Conclusion
66
67