Khargone Bid Document
Khargone Bid Document
Beej Bhawan, Mother Theresa Road, Arera Hills, Bhopal, Madhya Pradesh 462011
Page 1 of 553
INVITATION FOR BIDS (IFB)
THROUGH
E-PROCUREMENT SYSTEM
Page 2 of 553
M.P. URBAN DEVELOPMENT COMPANY LIMITED, BHOPAL, M.P.
(DEPARTMENT OF URBAN DEVELOPMENT AND HOUSING, MADHYA PRADESH)
This Invitation for Bids follows the General Procurement Notice for this Project that
was published in UNDB online on 2nd May 2016. The Government of Madhya
Pradesh (GoMP) through Government of India has applied for a loan from the World
Bank towards the cost of Madhya Pradesh Urban Development Project (MPUDP) and
intends to apply a portion of proceeds of this loantowards“Survey, Review the
Designs, Redesign where necessary, and Build water supply improvement scheme for
Khargone town, KHARGONE DISTRICT OF MADHYA PRADESH and operate and
maintain the built system for 5 years”and cover eligible payments under the contracts
for construction of works as detailed below. The operation and maintenance cost shall
be borne by the GoMP.
Page 3 of 553
category as prescribed under this contract invitation. Bidders are advised to note the
minimum qualification criterion specified in ITB section 1 of the Instructions to
Bidders to qualify for the award of the Contract.
The Biddermust submit Bid for the complete scope of the works contained in the
above table. Bidders submitting the Bidfor only one component (Design-Build or
Operation and Maintenance) shall be rejected.
The Bid document is available on-line and Bids are to be submitted on-line through the
Page 4 of 553
e-procurement portal http://mpeproc.gov.in. Bids submitted manually will not be
accepted. The Bidders would be required to register in the website. For submission of
Bids, the Bidders are required to have Digital Signature Certificate (DSC) from one of
the authorized certifying authorities.
Aspiring Bidders who have not obtained the user id and password for participating in
e-procurement may obtain the same by registering in the web-site
http://mpeproc.gov.in. The requirements to register with the e-procurement portal are
available on the website indicated.
The Bidders are required to submit (a) receipt of online payment towards the cost of
Bid Document (b) original bid security in approved form and (c) original notarized
power of attorney as per the provisions of ITB section 2.1 (2) 3.5(1) and 3.7, to the
Engineer-In-Chief, M.P. Urban Development Company Ltd. on or before the date and
time of opening of Part I – Technical Bid, either by registered post or by hand, failing
which the bids will be declared non-responsive.
Kindly note:
(i) The above documents shall be submitted in one envelope. The Bidders shall not
write their name or addresses on this envelope.
(ii) The number mentioned on acknowledgement of on-line submission of the Bid
by the Bidder shall be mentioned on envelope containing the documents as detailed
above.
(iii) Cost of Bid document; Rs50,000/- (Rupees Fifty Thousand Only) to be paid On-
line.
1. A pre-bid meeting will be held on 25th October 2016 at 11.00 hrs at the office of
Engineer-In-Chief M.P. Urban Development Company Limited, Beej Bhawan, Arera
Hills, Bhopalto clarify the issues and answer questions on any matter that may be
raised at that stage as stated in ITB section 2.5 of the Bidding document.
2. Other details can be seen in the Bidding documents. The owner shall not be held
liable for any delays due to the e-procurement systems failure beyond its control. Even
Page 5 of 553
though the e-procurement system will attempt to notify the Bidders of any Bid
updates, the owner shall not be liable for any information not received by the Bidder. It
is the Bidder’s responsibility to verify the website for the latest information related to
tender.
--sd--
(Prabha Kant Katare)
Engineer in Chief
Madhya Pradesh Urban Development Co. Ltd.,
Bhopal
Page 6 of 553
INDEX
Ref. Particulars Page No.
SECTION 1 – INTRODUCTION
1.1 Source of Funds and Scope of Work 18
1.2 Eligibleand Ineligible Bidders 18
1.3 Eligible Plant and Equipment 20
1.4 Qualification of the Bidder
(A) General 21
(B) Sub Contracting 22
(C) Bidder’s Responsibility 22
(D) General Experience 23
(E) Particular Water supply experience 23
(F) Financial Capabilities 24
(G) Critical Equipment 24
(H) Personnel capabilities 24
(I) Litigation history and legal matters 25
Page 9 of 553
6.5 Performance security 54
6.6 Failure to sign the form of contract or provide the performance 54
security
6.7 Adjudicator 54
6.8 Corrupt and fraudulent practices 54
SECTION 7 – BID DATA SHEET 57-66
ANNEX A- BIDDER’S BID FORM INCLUDING
QUALIFICATION INFORMATION
Technical Bid Submission Form 70
Qualification Information 74
Design Build Work Plan 87
Operations and Maintenance Work Plan 88
FinancialBid Submission Form 93
Form of Bid Security 95
Form of Performance Security 97
Form of Bank Guarantee- Advance Payment 99
Form of Clarifications 101
Declarations 102
Annex B to Bidding Documents (Form of Contract and GCC etc) 104
Form of Contract 105
Page 10 of 553
1.3.6 Entire Agreement 121
1.3.7 Amendment 121
1.3.8 Number of Days 121
1.3.9 Independent Contractor 122
1.3.10 Joint Venture or Consortium 122
1.3.11 Non-waiver 123
1.3.12 Severability 123
1.3.13 Country of Origin 124
1.3.14 Survival of Obligations 124
1.4 Notice 124
1.5 Governing Law 125
1.6 Settlement of Disputes 125
1.6.1 Adjudicator 125
1.6.2 Arbitration 126
1.6.3 Obligations During Arbitration 127
1.7 Assignment 127
1.8 Contract Records, Accounting and Auditing 127
1.8.1 Contract Records 127
1.8.2 Accounting 129
1.8.3 Auditing the Contractor’s Own Accounts and the Contract Records 129
1.8.4 Contractor’s Audited Accounts 129
1.8.5 Bank Audit 129
1.9 Contractor’s Claims During the Design-Build Period 130
B. SUBJECT MATTER OF THE CONTRACT 133
ARTICLE 2 – CONTRACT TERM, TIMING AND COMPLETION 133
2.1General 133
2.1.1Effectiveness of Contract 133
2.1.2Expiration of Contract 133
2.1.3Commencement of Services 133
2.2Design-Build Period and New Operations Period 134
2.3Design-Build Period – Commencement, Delays and Suspension 134
2.3.1Commencement of the Design-Build Services 134
2.3.2Time for Completion 134
Page 11 of 553
2.3.3Design-Build Time Schedule 134
2.3.4Extension of the Time for Completion 135
2.3.5Rate of Progress 136
2.3.6Delay of Completion – Liquidated Damages – Delay 137
2.3.7Design-Build Period – Special Operations Requirements 138
2.4New Operations Period 138
2.4.1Commencement of the Operations – Services 138
2.4.2Services After the End Date 138
2.4.3Extension of the Contract 138
ARTICLE 3 – OBLIGATIONS OF THE CONTRACTOR 140
General – Services, Standards of Performance and Upfront
3.1 Contribution 140
3.2Law Governing Services 140
3.3Conflict of Interest 140
Plant and Equipment, Contractor’s Equipment (Design-Build)
3.4 and Operations Equipment (Operations) 142
3.5Site Information and Investigation 142
3.6Access to the Site and New Facility 143
ARTICLE 4 – OBLIGATIONS OF THE OWNER 145
4.1Owner’s Assistance to the Contractor 145
4.2Access to the Site and New Facility 146
4.3Reviews and Approvals of Submissions 146
ARTICLE 5 – CONTRACT PRICE AND PAYMENT 148
5.1Contract Price 148
5.2Terms of Payment 149
5.3Performance Incentive Compensation 150
5.4Liquidated Damages – Operations 150
5.5Securities 150
5.6Taxes and Duties 151
ARTICLE 6 – COPYRIGHT – DESIGN-BUILD
DOCUMENTS
153
6.1Copyright – Design-Build Documents 153
Page 12 of 553
6.2Confidentiality 154
ARTICLE 7 – CONTRACT ADMINISTRATION AND
SUPERVISION DURING THE DESIGN-BUILD AND NEW
OPERATIONS PERIODS 155
7.1General 155
7.2Design-Build Supervision 155
Page 13 of 553
ARTICLE 10 – CHANGE IN CONTRACT ELEMENTS 183
10.1 Change to the Design-Build Services 183
10.1.1 Introducing a Change 183
10.1.2 Changes Originating from Owner 184
10.1.3 Changes Originating from Contractor 186
10.1.4 Payment in Applicable Currencies 186
10.1.5 Design-Build Period 186
10.2 Change to the Operations Services 186
ARTICLE 11 – SUSPENSION AND TERMINATION 188
11.1 Suspension 188
11.1.1 Suspension by the Owner 188
11.1.2 Suspension by the Contractor 188
11.2 Termination 190
11.2.1 Termination for Owner’s Convenience 190
11.2.2 Payment upon Termination by the Owner for Convenience 191
11.2.3 Termination for Contractor’s Default 192
11.2.4 Payment upon Termination for Contractor’s Default 194
11.2.5 Termination by Contractor 195
11.2.6 Payment upon Termination by Contractor 197
11.2.7 General Provisions – Termination 198
APPENDIX
1 Special Conditions of Contract 199
2 Terms and Procedures of Payments 210
3 Technical Specifications 229
3A Design Build Service 230
3A(1) Introduction to Technical Specifications 232
3A(2) Design and Build Specifications 237
3A(3) Technical Specifications 267
3A(4) Operation and Maintenance Specifications 446
Annexure A- Scope of Work 447
Annexure B- Indicative Raw Water Quality Test Report 448
Annexure C- Design Criteria 449
Annexure D- Institutional and Financial Arrangement 451
Page 14 of 553
Annexure E - Performance Criteria for O&M 452
Annexure F- ToR for Independent Verification Team 453
Annexure G - Milestones 459
Annexure H - Environment Management Plan 461
3B Operation and Maintenance Service Agreement 476
Schedule 1 – Water Supply Area 493
Schedule 2 – Technical Specifications for O&M Services 494
Schedule 3 – Assets under Management of the Contractor 501
Schedule 4 – Contractor Payments and Performance Standards
for O&M Services 502
Schedule 5 – Reporting Requirements 509
Schedule 6 – Tariff and Tariff Changes 512
Schedule 7 – Key Staff for Operations and Maintenance 513
3C Indicative Bill of Quantities 514
4 Detailed Project Report 542
5 Contract Price Adjustment 544
6 Contractor’s Price Schedule 546
Page 15 of 553
ABBREVIATIONS
Page 16 of 553
IVT - Independent Verification Team
JV - Joint Venture
LTHS - Long term Hydrostatic Strength
LPU - Lightning Protection Unit
MCCB - Moulded Case Circuit Breaker
MDPE - Medium Density Polyethylene
MFR - Melt Flow Rate
MPUDC - Madhya Pradesh Urban Development Company Ltd.
MPUDP - Madhya Pradesh Urban Development Project
MS - Mild Steel
NRW - Non Revenue Water
OMSA - Operation and Maintenance Service Agreement
PIU - Project Implementation Unit
PLC - Programmable Logic Controller
PMC - Project Management Consultant
PSC - Pre – Stressed Concrete
SBR - Styrene Butadiene Rubber
SCADA - Supervisory Control and Data Acquisition
SMF - Sealed Maintenance Free
UFW - Unaccounted for Water
UPS - Uninterruptible Power Supply
WTP - WaterTreatment Plant
Page 17 of 553
INSTRUCTIONS TO BIDDERS (ITB)
SECTION 1 - INTRODUCTION
(1) The Borrower named in the Bid Data Sheet has applied for a loan (hereafter
called “loan”) from the International Bank for Reconstruction and Development
(IBRD) towards the cost of the project named in the Bid-data sheet. The Borrower
intends to apply a portion of the proceeds of this loan to eligible payments under the
contract for which these Bidding Documents are issued. Bidders shall note that the
Borrower and the Owner named in the Bid Data Sheet may be the same entity.
(2) Payment by the Bank will be made only at the request of the Borrower and upon
approval by the Bank, in accordance with the terms and conditions of the loan
agreement, and will be subject in all respects to the terms and conditions of that
agreement. The loan agreement prohibits a withdrawal from the loan account for the
purpose of any payment to persons or entities, or for any import of Plant and
Equipment, if such payment or import, to the knowledge of the Bank, is prohibited by
a decision of the United Nations Security Council taken under Chapter VII of the
Charter of the United Nations. No party other than the Borrower shall derive any rights
from the loan agreement or have any claim to the loan proceeds.
1.2.1 This Invitation for Bids, issued by the Owner named in the Bid Data Sheet, is
open to all Bidders from the eligible countries as defined under the Guidelines:
Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans
and IDA Credits and Grants by World Bank Borrowers - July 2014.
All Bidders shall provide in Bidder’s Bid forms and qualification information, a
statement that the Bidder is not associated, nor has been associated in the past,
Page 18 of 553
INSTRUCTIONS TO BIDDERS (ITB)
directly or indirectly, with the Consultant or any other entity that has prepared
the design, specifications, and other documents for the project or being proposed
as project manager for the Contract. A firm that has been engaged by the
Borrower to provide Consulting Services for preparation or supervision of the
works, and any of its affiliates, shall not be eligible to Bid.
Government owned enterprises in the owner’s country may only participate if
they are legally and financially autonomous, operate under commercial law and
are not a dependent agency of the borrower or the sub-borrower.
(1) Bidder shall not be under a deceleration of the ineligibility for corrupt and
fraudulent practices issued by the Bank in accordance with ITB section 6.8.
(2) The Bidder shall not have a conflict of interest. Any Bidder found to have
a conflict of interest shall be disqualified. A Bidder may be considered to
have a conflict of interest for the purpose of this bidding process, if the
Bidder:
directly or indirectly controls, is controlled by or is under common control
with another Bidder; or
receives or has received any direct or indirect subsidy from another Bidder;
or
has the same legal representative as another Bidder; or
has a relationship with another Bidder, directly or through common third
parties, that puts it in a position to influence the bid of another Bidder, or
influence the decisions of the Owner regarding this bidding process; or
participates in more than one bid in this bidding process. Participation by a
Bidder in more than one Bid will result in the disqualification of all Bids in
which such Bidder is involved. However, this does not limit the inclusion
of the same subcontractor in more than one bid; or
any of its affiliates participated as a consultant in the preparation of the
design or technical specifications of the works that are the subject of the
bid; or
any of its affiliates has been hired (or is proposed to be hired) by the Owner
or Borrower as Engineer for the Contract implementation; or
Page 19 of 553
INSTRUCTIONS TO BIDDERS (ITB)
(1) For the purposes of these Bidding Documents, the words “Plant and Equipment”
and “Services” shall be construed in accordance with the respective definitions
given to them in the Contract.
(2) All Plant and Equipment to be supplied and installed and Services carried out
under the Contract may have their origin in any country, as defined in the
Guidelines: Procurement of Goods, Works, and Non-Consulting Services under
IBRD Loans and IDA Credits and Grants by World Bank Borrowers - July 2014
and subject to Instructions to Bidders (“ITB”) Section 1.3(3), and all
expenditures made under the Contract will be limited to such Plant and
Equipment and Services.
(3) For purposes of this ITB Section 1.3, “origin” means the place where the Plant
and Equipment or component parts thereof are mined, grown, or produced. Plant
and Equipment are produced when, through manufacturing, processing or
substantial and major assembling of components, a commercially recognized
product results that is substantially different in basic characteristics or in purpose
or utility from its components.
Page 20 of 553
INSTRUCTIONS TO BIDDERS (ITB)
(4) The origin of the Plant and Equipment and Services is distinct from the
nationality of the Bidder.
The Bank requires compliance with its policy in regard to corrupt and fraudulent
practices as set forth in ITB In further pursuance of this policy, Bidders shall
permit and shall cause its agents (whether declared or not), sub-contractors, sub-
consultants, service providers, or suppliers and any personnel thereof, to permit
the Bank to inspect all accounts, records and other documents relating to any
prequalification process, bid submission, and contract performance (in the case
of award), and to have them audited by auditors appointed by the Bank.
The Bidder shall bear all costs associated with the preparation and submission of
its bid, and the Owner will in no case be responsible for these costs, regardless of
the conduct or outcome of the bidding process.
(A) General
(1) Evaluation will be based on Bidders meeting all the following minimum pass-
fail criteria regarding their general design, build, operation and maintenance
experience and particular pipe water supply system (with surface source from
river) experience, financial position, personnel capabilities and other relevant
information as demonstrated by the Bidders’ responses in the Qualification
Information Forms that they submit attached to their Bids.
(B) Subcontracting
The bidder can sub-contract maximum upto 25% of the total contract value
(1) Sub contractor’s qualification may be added to the Bidders qualification only
if the subcontractors and sub-consultants are nominated in the bid. For the
purposes of ITB 1.4 H, Bidders may nominate personnel of subcontractors and
sub-consultants to fill the key positions listed in the BDS.
(2) The Bidder shall provide a detailed list of all nominated subcontractors and
sub-consultants and a record of their experience and qualifications in the
applicable Information Forms. The Bidder under the Contract shall be
prohibited from entering into a sub-contract/s that will result in the Bidder
exceeding the maximum percentage of subcontracting and sub-consulting
permitted by the Owner, as set out in the BDS.
(3) The Owner may require the Bidders to provide more information about sub-
Contractor and sub-consultants nominated in their Bid. If the owner
determines that any nominated sub-Bidder or sub-consultant is ineligible or
unsuitable to carry out the assigned task, the Owner may reject the bid.
(4) Bidders will not be permitted to change the subcontractors and sub-consultants
nominated in their Bid without the prior written consent of the Owner. The
Owner shall not unreasonably withhold such consent.
After award of the Contract, the subcontracting of any part of the work
(within the prescribed limit), except for those subcontractors and sub
Page 22 of 553
INSTRUCTIONS TO BIDDERS (ITB)
consultants nominated in the Bid, shall require the prior written consent of the
Owner. Notwithstanding such consent, the Bidder shall remain responsible for
the acts, defaults, and neglects of all subcontractors and sub consultants
during Contract implementation.
(a) it has been actively engaged in designing, building, operating, managing and
maintaining civil works facilities, for at least the period as stated in BDS; and,
(b) it has generated an average annual turnover, in respect of designing, building,
operating, managing and maintaining civil works facilities during the period
stated in the BDS, that is greater than the amount stated in BDS.
The average annual turnover is defined as the total payment received for
general design and construction work and work related to designing,
building, operating, managing and maintaining civil works facilities by the
firm or firms comprising the Bidder, divided by the number of years stated in
BDS.
(1) The Bidder shall provide evidence that (i) it has successfully carried out the
number and type of water supply projects or assignments stated in BDS within
the period stated in the respective contracts. The projects or assignments may
have been executed by the Bidder as prime Bidder, or as a member of a joint
venture, or as a sub-Bidder or sub-consultantwho must provide its contribution
proportion as JV partner/subcontractor/subconsultant, with references being
submitted to confirm satisfactory performance Documentary evidence;(ii)
Completion certificate issued by the Owner in case of Completed work has to
be submitted along with the bid. In no case, the Letter of Acceptance shall be
taken as document for calculation of financial capability as well as work
Page 23 of 553
INSTRUCTIONS TO BIDDERS (ITB)
experience.
(2) For the purpose of demonstrating its experience in accordance with ITB 1.4 D
(a), the Bidder, including a joint venture partner, may include the experience
of the nominated sub-Bidders also.
(1) The Bidder shall demonstrate that it has access to, or has available, liquid assets,
unencumbered real assets, lines of credit, and other means, independent of any
contractual advance payment, sufficient to meet the cash flow requirements for
the Contract in the event of stoppage, start-up, or other delays in payment, of the
minimum estimated amount as stated in the BDS, net of the Bidders’
commitments for other contracts.
(2) The Bidder shall also demonstrate, to the satisfaction of the Owner, that it has
adequate sources of finance to meet the cash flow requirements on works
currently in progress and for future contract commitmentsas stated in the BDS.
(3) The Bidder’s audited balance sheets or, if not required by the laws of the
Bidder’s country, other financial statements acceptable to the Owner, for the last
five years shall be submitted and must demonstrate the current soundness of the
Bidder’s financial position and indicate its prospective long-term profitability. If
deemed necessary by the Owner, the Owner shall have the authority to make
inquiries with the Bidder’s bankers.
Each Bidder shall demonstrate the availability (either owned or leased) of the
key and critical equipment for work as specified in the BDS.
The Bidder shall supply general information on the management structure of the
firm, and shall make provision for suitably qualified personnel to fill the key
Page 24 of 553
INSTRUCTIONS TO BIDDERS (ITB)
The Bidder shall provide accurate information about pending litigation with
respect to contractscompleted or ongoing under its execution over the last five
years. A consistent history of awards against the Bidder or any Partner of a joint
venture may result in rejection of the Bid.
(A) Eligibility
(1) Each partner of a joint venture Bidder shall provide the information set out in
ITB 1.5 B(2) and (3) as it applies to the participant’s own firm.
(2) For the purpose of satisfying the qualification criteria set out in ITB 1.4 the
following data of each participant in the joint venture may be added together to
meet qualifying criteria:
(b) average annual turnover as stated in ITB Section 1.4 D (b); (provided any
one Partner meets minimum 51% of the requirements, and each of the other
Partners meets at least 26% of the requirement; and
(c) Particular water supply experience as stated in ITB Section 1.4 E; and
(3) For the purpose of satisfying the qualification criteria set out in Section 1.4,
Joint Venture participants must satisfy the following qualification criteria as set
out in ITB 1.5 (B) (3) (c) individually:
(4) The Bidder shall include all information in respect of joint venture participants
that is required to meet the qualification criteria in Section 1.4, in accordance
with ITB 1.5 B, in the Bid.
One of the joint venture Partners who is responsible for performing a key
function in contract management or in executing a major component of the
proposed Contract shall be nominated as being in charge during the qualification
and bidding process periods and, in the event of a successful bid, during
Contract execution (the “Lead Partner”). The Lead Partner shall meet atleast
51% of the qualification criteria as defined in ITB 1.5 (B) (3) (b). The Lead
Partner shall be authorized to incur liabilities and receive instructions for and on
Page 26 of 553
INSTRUCTIONS TO BIDDERS (ITB)
behalf of any and all partners of the joint venture. This authorization shall be
evidenced by the submission of a power of attorney signed by legally authorized
signatories of each of the joint venture Partners as part of the Bid.
(D) Participant Limitation and Joint Venture Company – The maximum number
of members in a JV is limited to three (3).
All participants of the joint venture shall be legally liable, jointly, severally,
during the bidding process and for the execution of Contract in accordance with
the Contract terms, and a statement to this effect shall be included in the
authorization required under ITB 1.5 C
Page 27 of 553
THE BIDING DOCUMENTS
2.1.1 The nature of the service area, the services, the site and facility that are to be
designed, built, managed, operated and maintained by the Bidder, the
procedures that are to be followed during the bidding process and the contract
terms and technical requirements are prescribed in the Bidding Documents. The
Bidding Documents consist of:
(d) Annex B to the Bidding Documents – the contract (the “Draft Contract”)
consisting of:
(i) Form of Contract;
(ii) General Conditions of the Contract; and
(iii) Appendices to the General Conditions,
Appendix 1 : Special Conditions of Contract Appendix
Appendix 2 : Terms and Procedures of Payment Appendix
Appendix 3 : Technical Specifications Appendix
Appendix 3A : Design-Build Services Appendix
Appendix 3B :Operation and Maintenance Services Appendix
Appendix 3C : Indicative Bill of Quantities Appendix
Appendix 4 : Detailed Project Report (DPR) Appendix
Page 28 of 553
THE BIDING DOCUMENTS
(e) Addenda to the documents listed in ITB Section 2.1.1(a) to (e), if any are
issued by the Owner.
2.1.2 The documents listed in ITB Section 2.1.1 (a), (b), (c), (d), and (e) are
collectively the “Bidding Documents”. The Bidding document is available
online on the website http://www.mpeproc.gov.in. Thecost of the Bid document
is to be paid online. The Bidder is also required to pay portal charges which are
nominal.
2.1.3 Each Bidder shall examine all instructions, terms and conditions, forms,
specifications and other information contained in the Bidding Documents. If the
Bidder, fails to provide all documentation and information required by the
Bidding Documents; or submits a Bid which is not substantially responsive to
the terms and conditions of the Bidding Documents, such action is at the
Bidder’s risk and the Owner may determine that the Bid is non-responsive to the
Bidding Documents and may reject it.
2.3.1 Each Bidder is advised to visit and inspect the site of the proposed water supply
facility (the “Site Visit”) and its surroundings and obtain for itself on its own
responsibility all information that may be necessary for preparing the Bid and
entering into the Contract. The Owner will schedule a time on or after the date
set out in the timetable specified in the Bid Data Sheet and develop a procedure
for Bidders to conduct a Site Visit. The costs of visiting the site shall be at the
Bidder’s own expense.
2.3.2 Each Bidder and any of its personnel or agents will be granted permission by the
Owner to enter upon its premises and lands for the purpose of such a Site Visit,
but only upon the express condition that the Bidder, its personnel and agents
will release and indemnify the Owner, the Borrower and their personnel and
agents from and against all liability in respect thereof and will be responsible for
death or personal injury, loss of or damage to property and any other loss,
damage, costs and expenses incurred as a result of the Site Visit.
2.4.1 Unless otherwise stated in the Bid Data Sheet, the Owner will establish a data
room (the “Data Room”) with a collection of relevant data to be accessible to
Bidders or their representatives from the date set out in the timetable specified in
the Bid Data Sheet until the deadline for submission of Bids (the “Submission
Deadline”), in accordance with a schedule established by the Owner as per link
provided in the BDS.
2.4.2 The Owner may provide prospective Bidders with a separate background
information document (the “Background Information Document”) if indicated in
the Bid Data Sheet. The Background Information Document is not a Bidding
Document.
place at the venue and time stipulated in the BDS. While attendance at the Pre-
Bid Meeting is not mandatory, Bidders are strongly encouraged to attend it. The
purpose of the Pre-Bid Meeting is to clarify issues and answer questions on any
matter that may be raised at the meeting. The prospective Bidder is requested to
submit any questions online through the e-tendering portal
https://mpeproc.gov.inupto the Pre-Bid Meeting. It may not be practicable at the
meeting to answer questions received late, but questions and responses will be
transmitted as indicated hereafter. Minutes of the Pre-Bid Meeting, including the
text of questions raised (without identifying the source of inquiry) and the
responses given will be uploaded on the website https://mpeproc.gov.in. Any
modification of the bidding documents listed in ITB Section 2.1.1 (a) to (e)
which may become necessary as a result of the pre-bid meeting shall be made by
the Owner exclusively through the issue of an Addendum/Corrigendum pursuant
to ITB Section 2.6 & not through the minutes of the pre-bid meeting. The
Minutes of thePre-Bid Meeting, reply to the queries and corrigendum if any will
also be uploaded on the website specified above.
2.6.1 At any time prior to the Submission Deadline, the Owner may, for any reason,
whether at its own initiative, or in response to a clarification requested by a
prospective Bidder, amend the Bidding Documents by addendum/corrigendum
which shall be published on the e-procurement portal. No other communications
of any kind whatsoever, including, without limitation, the minutes of the Pre-
Bid Meeting or the Response to Questions Document, shall modify the Bidding
Documents.
2.6.2 Addenda, if any, will be uploaded on the e-procurement portal only and it will
be binding on all Bidders. It is the Bidder’s responsibility to check the e-
procurement portal for any update.
2.6.3 In order to afford prospective Bidders reasonable time in which to take the
amendment into account in preparing their Bids, the Owner may, at its
Page 31 of 553
THE BIDING DOCUMENTS
2.7.1 The electronic bidding system provides for submission of any queries from the
bidders only through the e-Procurement Portal. Therefore, a prospective bidder
requiring any clarifications shall follow the procedure specified in ITB 2.2.1.
2.8.1 Each Bidder is solely responsible for conducting its own independent research,
due diligence, and any other work or investigations and for seeking any other
independent advice necessary for the preparation of Bids, negotiation of
agreements, and the subsequent delivery of all services to be provided by the
Bidder that has been successful in the bidding process (the “Successful
Bidder”).
2.8.3 Bidders shall not rely on any oral statements made by the Owner or its advisors,
employees, consultants or agents.
2.8.4 All Bidders shall, prior to submitting their Bid, review all requirements with
Page 32 of 553
THE BIDING DOCUMENTS
2.9 Timetable
2.9.1 The estimated timetable, from the issuance of the Bidding Documents to the
identification by the Owner of the Successful Bidder and the execution of the
Contract, is set out in the Bid Data Sheet.
2.9.2 The Owner may, in its sole discretion and without prior notice to the Bidders,
amend the estimated timetable specified in the Bid Data Sheet. Bidders shall not
rely in any way whatsoever on the estimated timetable specified in the Bid Data
Sheet and the Owner shall not incur any liability whatsoever arising out of
amendments to the estimated timetable. The Owner shall give notice of
timetable changes, if any, by addenda specified in Section 2.6 (2).
Page 33 of 553
PREPARATION OF BIDS
3.1.1 The Bid prepared by the Bidder, all correspondence and documents related to
the Bid exchanged by the Bidder and the Owner and the bidding process shall be
written in the language specified in the Bid Data Sheet, provided that any
printed literature furnished by the Bidder may be written in another language, as
long as such literature is accompanied by a translation of its pertinent passages
in the language specified in the Bid Data Sheet, in which case, for purposes of
interpretation of the Bid, the translation shall govern.
3.2.1 Each Bidder shall submit only one Bid which shall consist of:
The documents and details mentioned in ITB section 3.2 (1) Part 1 above shall
be submitted online on website http://mpeproc.gov.in. Details and process of
online submission of the tender and relevant documents are given in the website
mentioned above. The above are to be submitted in the manner as prescribed
Page 34 of 553
PREPARATION OF BIDS
below:
3.2.2 Scanned copies of the following documents shall be uploaded on the website
https://mpeproc.gov. inin the appropriate place, as part I - Technical Bid.
3.2.3 Scanned copies of the following should be uploaded after converting the same
to PDF, as part I – Technical Bid:
(a) Certificates showing details of similar nature of works, work in hand and
machineries owned or possessed or hired;
(b) Annual Turnover Certificate from Chartered Accountant for the last five
financial years forms with breakup of civil works and total works for each
financial years required by ITB section 1.4 (F) (3);
(c) Similar nature of works executed required by ITB Section 1.4 (D) and (E);
(d) Critical Equipment/Machineries owned/brought on hire required by ITB
Section 1.4 (G)
(e) Project Manager and other Key Personnel with adequate experience as
required by ITB Section 1.4 (H)
The Bidders who qualify for second stage of bid, will have to submit all the
Page 35 of 553
PREPARATION OF BIDS
original documents, except for the financial quote, within five working days,
unless mentioned otherwise, from the date on which such Bidder is informed.
The owner shall be informing the Bidders through e-mail.Failure in submission
of original documents within stipulated time period will automatically disqualify
such Bidders. Those Bidders who submit the financial quote in hard copy will
also be automatically disqualified.
3.3.1 In the Technical Bid, each Bidder shall provide a completed Technical Bid
Submission Form contained in the Bidding Documents.
(i) Each Bidder shall provide detailed information listing all commissions and
gratuities, if any paid or to be paid by the Bidder to the agents relating to this
Bid or the Contract if the Bidder is awarded the Contract. The Bidder shall list
the name and address of any agents, the amount and currency paid or to be
paid to the agents and the purpose of the commission or gratuity. If no such
commissions and gratuities have been paid, the Bidder shall provide this
information in Technical Bid submission Form.
The Technical Bid shall consist of the following sub-parts in the following order:
A. An Executive Summary of the Technical Section;
B. A design-build workplan including a detailed program timetable (the “Design-
Build Workplan”) setting out the manner in which the Bidder proposes to carry
out the design-build services as defined in the Draft Contract (the “Design-Build
Services”) and meet the design-build technical standards in accordance with the
Technical Standards Appendix to the General Conditions.
C. (i) a section entitled “Required Plant and Equipment and Bidder’s Equipment”
Page 36 of 553
PREPARATION OF BIDS
which consists of a list of major Plant and Equipment required and Bidder’s
Equipment (Design-Build) and Bidder’s Equipment (Operations).
(ii) A section on “Operation Plan” as detailed in BDS.
D. A detailed staffing plan (the “Staffing Plan”) setting out the Bidder’s proposed
staffing arrangements for the carrying out of the Design-Build and Operations
Services. The Staffing Plan shall be divided into the following sections:
a A section entitled the “Staffing Chart” for the Design-Build and
Operations Services and consisting of a chart setting out a list of all
proposed Key-Staff, the role of each position, the duration of
existence of the position, and the location of the staff person filling
the position during the periods of assignment to carry out the
Design-Build and Operations Services;
b a section entitled “Summary of Staff Qualifications” which consists
of a summary table setting out,
(A) the Key Staff positions, the names of the Bidder’s employees
who will occupy the Key Staff positions; and
(B) all proposed positions for the Bidder’s Personnel and the
qualifications, years of experience and areas of expertise,
including a clear indication of the expertise that the staff will
provide consistent with the requirements set out in the BDS-
ITB 1.4 (H); and
c a section entitled, “Curriculum Vitae” which contains the signed
curriculum vitae for each of the Key Staff, in the format set out in
Annex A to the Bidding Documents;
Page 37 of 553
PREPARATION OF BIDS
(1) In the Technical Bid, the Bidder shall furnish, as part of its Bid, a Bid
security in the amount stipulated in the Bid Data Sheet in the currency of
the Owner’s country.
(2) The Bid Security shall, at the Bidder’s option, be in the form of a Bank
Guarantee or a fixed deposit issued by a Nationalized or Scheduled Bank
located in India in favour of the Managing Director, Madhya Pradesh
Urban Development Company and payable at Bhopal. If the institution
issuing the security is located outside the country of the Borrower, it shall
have a correspondent financial institution located in the country of the
Borrower to make it enforceable. The format of the bank guarantee
provided by a Bidder shall be in accordance with the form of Bid Security
contained in Annex A to the Bidding Documents. The Bidder shall ensure
that the Bid Security remains valid for a period of 45 days after the end of
the original Bid Validity Period, as defined in ITB Section 3.12(1), and 45
days after any extension subsequently requested by the Owner in
accordance with ITB Section 3.12(2). The bid security of a Joint Venture
must define as “Bidder” all Joint Venture Partners and list them in the
following manner:
“a Joint Venture consisting of ‘.......’, ‘..........’ and ‘............’.
(3) Any Bid not accompanied by an acceptable Bid Security shall be rejected
by the Owner as being non-responsive. The Bid Security of a joint venture
must be in the name of all of the participants in the joint venture
submitting the Bid.
(4) The Owner will return the Bid Securities of the unsuccessful Bidders as
promptly as possible, but not later than 45 days after the expiration of the
Bid Validity Period.
(5) The Bid Security of the Successful Bidder will be returned when the
Page 38 of 553
PREPARATION OF BIDS
Bidder has signed the Form of Contract pursuant to ITB Section 6.4 and
has provided the required performance security as set out in the Contract
and ITB Section 6.5.
(6) The Bid Security may, in the discretion of the Owner, be forfeited:
(a) if the Bidder withdraws its Bid during the Bid Validity Period; or
(b) in the case of the Successful Bidder, if the Successful Bidder fails to,
within the specified time limit, :
(i) to execute the Form of Contract in accordance with ITB Section 6.4; or
(ii) to furnish the performance security to the Owner in accordance with
ITB Section 6.5.
(1) Each Joint Venture Bidder shall submit, as Part of the Technical Bid, a
written commitment, in the form of a letter duly executed by an
authorized officer of each joint venture participant, which,
(i) confirms each joint venture participant’s commitment to the joint
venture and acceptance of the joint venture arrangements described in
the Bid in accordance with ITB Section 3.6(3);
(ii) confirms each joint venture participant’s willingness to provide a
joint and several guarantee to the Owner to underwrite the
performance of the joint venture in respect of the Contract; and
(iii) identifies which joint venture participant,
(a) will assume the leading role on behalf of the other joint venture
participants; and
(b) will have the authority to commit all joint venture participants.
(iv) A copy of the Joint Venture Agreement entered into by the Partners
(JV Participants) shall be submitted with the bid; or a Letter of
Intent to execute a Joint Venture Agreement in the event of a
successful bid shall be signed by all partners and submitted with the
bid together with a copy of the proposed Agreement.
Page 39 of 553
PREPARATION OF BIDS
Each Bidder shall provide, as Part of the Technical Bid, a written and duly
notarized power of attorney demonstrating the authority of the person or persons
signing of the Bid which shall bind the Bidder for the full length of the Bid
Validity Period.
(2) Each Bidder shall submit completed and properly executed Price
Schedules in the forms contained in Bidding Documents. Bidders shall
complete the Price Schedules in full and shall not amend or change the
form in any way.
3.9.1 Bidders shall quote their Bid Price for the entire facility and all of the services
on a “single responsibility” basis such that the total Bid Price covers all of the
Bidder’s obligations mentioned in or to be reasonably inferred from the
Bidding Documents in respect of the design, manufacture, including
procurement and subcontracting, if any, delivery, construction, installation and
completion of the facility and the performance of the Services as set out in the
Draft Contract. This includes all requirements under the Bidder’s
responsibilities for testing, pre-commissioning and commissioning of the site
and facility, the acquisition of all permits, approvals and licenses, the design,
Page 40 of 553
PREPARATION OF BIDS
building, operation, maintenance and training services, and such other items
and services as may be specified in the Bidding Documents, all in accordance
with the requirements of the General Conditions of the Contract.
3.9.2 For the purpose of submitting Bids, Bidders should note that the Bid Price
shall include all kinds of taxes, duties, levies or charges of the Owner’s
country in accordance with the Contract. However, the Bidder may take into
consideration any tax / duty exemptions, reductions available in the Owner’s
country (Refer format for declaration for excise duty). The owner, at the
request, of the Bidder shall provide the required certification to avail such
benefits. However, if the Bidder fails to get the benefit of exemption, the
owner shall not be responsible in any manner and shall not make any extra
payment to the Bidder.
3.9.3 In the Price Schedules, Bidders shall give the required details and a breakdown
of their prices as follows:
3.9.4 Prices quoted by the Bidder shall be fixed during the Bidder’s performance of
the Contract and shall not be subject to change on any account, except in
accordance with the price adjustment provisions set out in the Contract. A Bid
submitted with an adjustable price quotation where firm price is the basis, such
bids shall be treated as non-responsive and shall be rejected.
3.9.5 Bidders are strongly encouraged to review GC Section 5.6 and the Terms and
Procedures of Payment Appendix prior to completing their Price Schedules
and submitting their Bid Prices.
The Bidder shall furnish along with his bid a declaration regarding
customs/excise duty exemption for materials/ Construction equipment
bought for the work in the Declaration Format provided in Annex A to the
bidding documents.
Where the Bidder has quoted taking into account such benefits, he must give
all information required for issue of Project Authority/ Payment/Other
certificates in terms of the Export Import Policy or Central Excise Notification
and Customs Notification of the Government of India as perform stipulated in
Annex A to the bidding documents. In case the
To the extent the Owner determines the quantities indicated therein are
reasonable, the certificates will be issued and no subsequent changes will be
permitted. The certificate will be issued within 60 days of signing of the
contract for material, equipment and machinery.
Where such certificates are issued by the Owner, excise duty will not be
Page 42 of 553
PREPARATION OF BIDS
reimbursed separately.
Bids which do not conform to the above provisions or any condition by the
Bidder which makes the bid subject to availability of deemed export benefits or
compensation on (a) withdrawal of or (b) any variations to the deemed export
benefits scheme, will make the bid non-responsive and hence rejected.
Bidders may quote their price in the Indian Rupees only and all payments shall
be made in Indian Rupees.
(3) A Bidder shall not submit a Bid that proposes an arrangement between the
Owner and the Bidder which, in the discretion of the Owner, is different
than the arrangement set out in the Bidding Documents (an “Alternative
Bid”). The Owner intends to enter into a contract to design, build and
operate a Water Supply facility based on the terms and conditions of the
Bidding Documents. If a Bidder submits an Alternative Bid it will be
returned to the Bidder and will not be considered, in any way, by the
Owner.
(1) Bids shall remain valid for the period named in the Bid Data Sheet after
the Submission Deadline or any extension thereof prescribed by the
Owner for the receipt of Bids, pursuant to ITB Section 3.14(2) (the “Bid
Validity Period”). A Bid valid for a shorter period shall be rejected by the
Owner as being non-responsive.
(2) In exceptional circumstances, the Owner may solicit the Bidders’ consent
to an extension of the Bid Validity Period. The request and responses
thereto shall be made in writing and sent by air mail, courier or fax. If a
Bidder accepts to prolong the Bid Validity Period, the Bid Security shall
also be suitably extended. A Bidder may refuse the request without
forfeiting its Bid Security. A Bidder granting the request will not be
required nor permitted to modify its Bid, except as provided in ITB
Section 4.4.
Page 44 of 553
SUBMISSION OF BIDS
(1) The Bidder shall submit online two separate files marked as Part I:
Technical Bid and Part II: FinancialBid. The contents of the Financialbid
shall be as specified in ITB 3.2
(2) All the documents are required to be signed digitally by the Bidder.
(3) After electronic online bid submission, the system generates a unique bid
identification number which is time stamped. This shall be treated as
acknowledgement of bid submission.
(2) The Owner may, at its discretion, extend the Submission Deadline by
amending the Bidding Documents in accordance with ITB Sections 2.6
and 2.9(2), in which case all rights and obligations of Owner and Bidders
will thereafter be subject to the Submission Deadline as extended.
The electronic bidding system would not allow any late submission of bids after
due date and time as per server time, pursuant to ITB Section 4.2.
The original copies of required documents as in ITB 3.2 (4) shall also be
submitted within the specified otherwise the Bidder shall become non
responsive.
Page 45 of 553
SUBMISSION OF BIDS
(2) For bid modification and consequential re-submission, the Bidder is not
required to withdraw his bid submitted earlier.
(3) Once withdrawn, the system shall not allow resubmission of the same bid.
(4) No Bid may be modified or withdrawn in the interval between the Bid
Submission Deadline and the expiration of the original period of Bid
Validity specified in ITB Section 3.12. above or as extended pursuant to
ITB Section 2.6 and 2.9 (2) in the e-procurement system. If a Bidder does
the same through any other medium, then it may result in the forfeiture of
the Bid security pursuant to Section 3.5.
Page 46 of 553
BID OPENING AND EVALUATION
(1) The Owner inviting bids or its authorized representatives will open the
Bids online on the date mentioned in the BDS and this could be viewed by
the Bidders online. In the event of the specified date for opening of bids
being declared a holiday for the Owner, the bids will be opened at the
appointed time on the next working day.
(2) The Part I – Technical Bid will be opened first.
(3) In all the cases the amount of Bid security, cost of bid documents, and
validity of the bid shall be scrutinized. Thereafter, the Bidder’s name and
such other details as the Owner may consider appropriate, will be notified
as Part I bid opening summary by the authority inviting bids at the time of
online opening.
(4) The Owner shall prepare minutes of the Bid opening including the
information disclosed in accordance with ITB Sections 5.1(3) and upload
the same for viewing online.
(5) Evaluation of Part I of bids with respect to bid security, qualification
information and other information furnished in Part I of the bid in
pursuant to ITB section 3.2 (1) (a), shall be taken up and completed, and a
list will be drawn up of the qualified Bidders whose Part II of bids will be
eligible for opening.
(6) The result of evaluation of Part I of the Bids shall be made public on e-
procurement following which there will be a period of 5 working days
during which any Bidder may submit a complaint which shall be
considered for resolution before opening of Part II (FinancialBid) of the
bid. Any complaint shall be dealt with in accordance with complaint
handling protocol as available on e-procurement portal of http://
mpeproc.gov.in. Where only one bid is submitted, the stand still period
does not apply.
(7) The Owner shall inform, the Bidders, who have qualified during
evaluation of Part I of bids, of the date, time of online opening of Part II
Page 47 of 553
BID OPENING AND EVALUATION
of the bid.
(8) The Part II – Financial Bid of only those Bidders will be opened online,
who have qualified in Part I of the bid. The Bidder’s names, the Bid
prices, the total amount of each bid, and such other details as the Owner
may consider appropriate will be notified online by the Owner at the time
of bid opening. Any bid price, which is not declared and recorded, will
not be taken into account in Bid evaluation.
(9) The Owner shall prepare minutes of online opening of Pat II of Bids and
upload the same for viewing online.
During Bid evaluation, the Owner may, at its discretion, ask the Bidder
for a clarification of its Bid. The request for clarification and the response
shall be in writing, and no change in the price or substance of the Bid
shall be sought, offered or permitted.
(1) The Owner will examine each Bid to determine whether it is complete,
whether any computational errors have been made, whether required
securities have been furnished, whether the documents have been properly
signed, and whether the Bid is generally in order.
(2) In the online electronic bidding system, the total bid price is worked out
automatically be the system on the basis of the rates quoted online by the
bidders in the BOQ and shall be considered as binding upon the bidder
(4) Prior to the detailed evaluation, the Owner will determine whether each
Bid is of acceptable quality, is complete and is substantially responsive to
Page 48 of 553
BID OPENING AND EVALUATION
(a) that affects in any substantial way the scope, quality or performance
of the contract;
(b) that limits in any substantial way, inconsistent with the Bidding
documents, the Owner’s rights or the Successful Bidder’s
obligations under the contract; or
(c) whoserectification would unfairly affect the competitive position of
other Bidders who are presenting substantially responsive Bids.
(1) The Owner will evaluate and compareonly the Bids determined to be
substantially responsive pursuant to ITB Sections 5.3.
(2) The Owner will carry out a detailed evaluation of the Technical Sections
previously determined to be substantially responsive in order to determine
on a pass/fail basis whether the technical aspects are in accordance with
the requirements set forth in the Bidding Documents. Bidders
acknowledge that, in order to reach such a determination, the Owner will
examine and analyze the technical aspects of each Bid on the basis of the
information supplied by Bidders, taking into account the completeness,
consistency and level of detail of the following factors:
Page 49 of 553
BID OPENING AND EVALUATION
(3) For the purpose of ITB Section 5.4 (2) (c) (ii), the evaluation of the
overall quality of the Staffing Plan shall be based on,
(a) the clarity, comprehensiveness and level of detail of the Staffing
Page 50 of 553
BID OPENING AND EVALUATION
Plan;
(b) the extent to which the Staffing Plan addresses the specific Services
that are required by the Design-Build and Operations and
Maintenance Services Appendices to the General Conditions.
5.5 FinancialEvaluation
(2) Any effort by a Bidder to influence the Owner, its advisors, employees,
consultants or agents, in the Owner’s Bid evaluation, Bid comparison, or
Contract award decision may, in the discretion of the Owner, result in
rejection of the Bidder’s Bid.
Page 51 of 553
AWARD OF CONTRACT
6.1.1 Subject to ITB Section 6.2, the Owner will award the Contract to the Bidder
whose Bid has been determined, by the technical and price evaluation, to be
substantially responsive, has received a “pass” in the technical evaluation, and has the
lowest evaluated Bid Price.
The Owner will sign two separate agreements 1) covering Part A i.e Design, build
and commission of facilities(First Agreement)funded by IBRD; and (2) covering Part
B services of five years O&M ( Second Agreement ) funded by MPUDC. Both the
Agreements will have cross fall breach clauses which gives the Owner to terminate
both the agreements as if they are intergral to each other with remedies as available to
the Owner under each agreement. Each agreementwill be secured by its own
performance guarantee and will contain provisions that in case of encashment of
performance guarantee of one agreement, the performance security of the other
agreementbecomes automatically encashable at the discretion of the owner. The
Owner at its discretion may declare the First agreementas complete and take over the
facilities without afftecting the performance of the second agreement. Both the
agreementsmay have different effective date as decided by the Owner while entering
the contracts.
(2) Nothing in ITB Section 6.2(1) is intended to permit the Owner to refuse to
provide reasons for rejection to an unsuccessful Bidder.
Prior to the expiration of the Bid Validity Period, the Owner shall notify the Successful
Bidder in writing by email and post that its Bid has been accepted by the Owner (the
“Notification of Award”). The effectiveness of the Contract shall be as of the date of
the Owner’s signing of the Contract contingent on final approval by the Bank.
(1) At the same time as the Owner sends the Successful Bidder the Notification of
Award, the Owner shall send the Successful Bidder,
(2) No later than 15 days after the Successful Bidder’s receipt of the Notification
Award, the Form of Contract and the other Contract Documents pursuant to ITB
Sections 6.3 and 6.4(1), the Successful Bidder shall sign and date the Form of
Contract and initial each page of the Contract and return them to the Owner.
(3) The website has provision to display the details of award of contract. The Owner
shall publish on the website the result identifying the bid and the following
information: (a) name of each Bidder who submitted the bid; (b) bid prices as
announced online during the bid opening of Part II of each bids; (c) name and
evaluated prices of each bid; (d) name of Bidders whose bids were rejected
Page 53 of 553
AWARD OF CONTRACT
during evaluation of either Part I or Part II of the bids and the reasons for their
rejection; and (e) name of the winning Bidder, the price offered and summary
scope of the contract awarded.
No later than 15 days after the Successful Bidder’s receipt of the Notification of
Award, the Successful Bidder shall provide the Owner with the performance security
in the amount given in the Bid Data Sheet and in the substance and form set out in
Annex A or in another form approved by the Owner.
6.6 Failure to Sign the Form of Contract or Provide the Performance Security
If the Successful Bidder fails to comply with the provisions of ITB Sections 6.4(2) or
6.5, this failure shall constitute sufficient grounds for annulment of the award and
forfeiture of the Bid Security, and in which event the Owner may make the award to
the next lowest evaluated Bidder or call for new bids.
6.7 Adjudicator
The Owner proposes that the person named in the Bid Data Sheet be appointed as
Adjudicator under the contract, at a fee per sitting stated in the Bid Data Sheet. A
description of the expenses that would be considered reimbursable is attached to the
Bid Data Sheet. If a Bidder does not accept the Adjudicator proposed by the Owner, it
should so state in its Bid Form and make a counterproposal of an Adjudicator and a fee
per sitting. If, on the day the Form of Contract is signed, the Owner and the Bidder
have not agreed on the appointment of the Adjudicator, the Adjudicator shall be
appointed, at the request of either party, by the Appointing Authority specified in the
Special Conditions of Contract.
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) “corrupt practice” is the offering, giving, receiving, or soliciting, directly
or indirectly, of anything of value to influence the action of a public
official in the procurement process or in contract execution; and
Page 56 of 553
BID DATA SHEET
The following bid-specific data for the facility and services to be procured shall amend
or supplement the provisions in the Instructions to Bidders (ITB). Whenever there is a
conflict, the provisions herein shall prevail over those in the ITB.
Scope of Works :
(a) Part - A
Survey, Review the designs, Redesign where necessary and build
Water Supply Improvement Scheme for Khargone town,
ITB 1.1(3) Khargone District, Madhya Pradesh
(b) Part -B
Operation and Maintenance of water supply system including
complaint redressal and billing for supplying of water for 5 years
after commissioning of system.
ITB 1.2 Owner: M P Urban Development Company Ltd., through its
Managing Director
ITB 1.4 (D) General Design, Build, Operations and Maintenance Experience
ITB 1.4 (D) (a) Time Period: Last seven(7) Financial Years i.e. 2009-10 to
2015-16
distribution network
(May be met by sub- contractor. A Memorandum of Agreement
(MOA) with sub contactor is required to be submitted with the
bid
(b) Operations and Maintenance: Experience in operations
and management of a DMA based, pressurised / (24 x 7)urban
water supply distribution system, in the role of contractor / sub-
contractor or management contractor with prime contractual
responsibility, demonstrating successful operations for a
minimum of one (1) year over the last seven (7) years prior to the
application submission deadline.
(Manager with relevant experience must be committed)
Financial Capabilities
Liquid assets and/or availability of credit facilities of no
less than Rs 16 crores (RupeesTwenty Crores Only). (Credit lines/letter
ITB 1.4 (F) (1)
of credit/certificates from Banks for meeting the funds requirement
and (2)
etc.)
Minimum required Cash Flow amount in Rs 13 crores (Rupees
Seventeen Crores Only).
Availability of Critical Equipment
Personnel Capabilities
Suitably qualified personnel to fill the following key positions, with
the specified minimum years of experience of similar works in that
position,
No. of
# Key Personnel Qualification Key
Personnel
Design Stage
ME Civil +5 Year
Design Engineer
1 Experience in structure 1
(Structural)
designing
Design Engineer ME Environment
2 (Hydraulics/ Water Engineering+ 5 years 1
Supply) Exp.
3 Surveyor Dip. Civil + 02 years exp. 2
ITB 1.4 (H)
Construction Stage
M.E. Civil/Mech. + 6
4 Project Manager 1
years exp. In PHE works
Deputy Project B.E. Mech + 3 years Exp.
5 1
Manager in PHE works
B.E. Civil + 04 years
6 Site Engineer (Civil) exp./ Diploma in civil 8 3
Years Exp. in PHE works
BE (Instrumentation) + 5
7 Engineer (SCADA) years experience in 1
SCADA
ME/M. Sc. Environment+ 1 (Part
8 Environment Engineer
5 years relevant Exp time)
9 Quality Control B.E. Civil + 03 years Exp 1
Page 60 of 553
BID DATA SHEET
Graduate in business
mgmt. with 3 yrs.
Customer Relations
2 experience in 1
Manager
customer services of
any utility services
Supervisor /
Technician
Dip. Mech/Elec + 5
4 (Electrical/ 2
yrs. experience
Instrumentation &
Mechanical)
Page 61 of 553
BID DATA SHEET
Diploma in
Civil/Mech./Elec.
Water Treatment
Engg. With
6 Plant Contractor / 3
experience in WTP
Supervisor
operation for a
minimum of 5 years
UFW/NRW /
B.E + experience in
Leakage
7 water distribution 1
Management
mgmt.
Specialist
Page 62 of 553
BID DATA SHEET
ITB 3.2.4 Original documents, namely (a) original bid security (b) original
notarized power of attorney should reach the Owner at the address
mentioned below on or before the date and time of opening of Part I
Technical Bid, specified in BDS ITB 5.1 (1)
Engineer In Chief,
MP Urban Development Company limited,
2nd Floor, Beej Bhavan, Mother Theresa Road, Arera Hills,
Bhopal462011
3. Program, strategy and Staffing pattern for meter reading and billing
arrangement
4. Strategy and staffing pattern for Grievance Redressal System
Management
5.Duty Schedule of O&M.
ITB 5.1 (1) Date and time of Online opening of Technical Bids:
Date 16.11.2016Time : 15:00 Hrs
ITB 5.1 (5) Opening of FinancialBids:
Within 15 working days from the date of opening of
Technical Bids. However, if there is any delay due to
unforeseen circumstances, the Bidders will be informed in
due time.
ITB 5.5(2) Financial Evaluation :
The total Bid price shall be evaluated by determining the NPV of
Design-Build price (Part A), NPV of Fixed O&M Price (Part B) and
NPV of Variable O&M Price (Part C) as per details given below and
then adding these NPV components.
Page 64 of 553
BID DATA SHEET
quoted
5 Year 5 Price for KL*C3 0.703
yr. 3 of
O&M, as
quoted
6 Year 6 Price for KL*C4 0.660
yr. 4 of
O&M, as
quoted
7 Year7 Price for KL*C5 0.621
yr. 5 of
O&M, as
quoted
Where C2, C3, C4 and C5 represent the adjusted Base Rate of
Variable O&M Fee for yr.2, yr.3, yr. 4 and yr.5 of the Operations
and Maintenance Period respectively
Page 67 of 553
BID Forms
Table of Forms:
Page 68 of 553
BID Forms
Part I :
Technical Bid Submission Form
Qualification Information
Part II :
Page 69 of 553
BID Forms
Page 70 of 553
BID Forms
To:
Managing Director,
Madhya Pradesh Urban Development Company Limited,
Bhopal
Dear Sir,
We understand that construtions of the contracts as above does not dilute our single
resource responsility for all three parts of the scope.
Page 71 of 553
BID Forms
If our Bid is accepted, we undertake to provide the Performance Security in the form,
in the amounts, and within the times specified in the Bidding Documents.
The bid and your written acceptance of it shall constitute a binding contract between
us. We understand that you are not bound to accept the lowest or any Bid you receive.
We hereby certify that we have taken steps to ensure that no person acting for us or on
behalf will engage in bribery.
We also undertake that, in competing for (and, if the award is made to us, in executing)
the above contract, we will strictly observe the laws against fraud and corruption
inforce in India namely “Prevention of Corruption Act 1988”.
We hereby confirm that this Bid complies with the Eligibility, Bid Validity and Bid
Security required by the Bidding documents.
Yours faithfully,
Authorized Signature:
Page 72 of 553
BID Forms
Page 73 of 553
BID Forms
QUALIFICATION INFORMATION
Nationality of owners1
Name Nationality
1.
2.
3.
4.
5.
Name of City
Country
Population served
Contract Role (joint venture participant, subcontractor, sub consultant, lead, etc.) and
percentage share in the total contract
Page 75 of 553
BID Forms
All individual firms and all participants of a joint venture are requested to complete the
information in this form with regard to their experience in designing, building,
operating, managing and maintaining civil works facilities. The information supplied
should be the annual turnover and net worth of the Bidder (or each member of a joint
venture) in terms of the amounts billed to clients for each year for work in progress or
completed. The annual periods should be complete financial years or calendar years,
before the date of submission of Bids.
Bidders should not enclose testimonials, certificates, and publicity material with their
Application as they will not be taken into account in the evaluation of qualifications.
Page 76 of 553
BID Forms
1. Lead Participant
2. Participant
3. Participant
Total value of annual turnover relating to designing, building, operating, managing and
maintain civil works facilities at the end of the period reported.
Totals
Page 77 of 553
BID Forms
Bidders are reminded to submit the appropriate powers of attorney as required by ITB
Section 1.5 (C) and to provide all other information required in the powers of attorney
(see ITB Section 1.5, in particular Sections C, E and F).
Page 78 of 553
BID Forms
Name of Place
Country
Population served
Contract Role (joint venture participant, subcontractor, sub consultant, lead, etc.)
and percentage share in the total contract
Address, Telephone,
Fax for reference
Page 79 of 553
BID Forms
3 (B) Construction of a Water Supply Scheme [ref. ITB Section 1.4 (E)]
Description of Contract
Name of City
Country
Population served
Contract Role (joint venture participant, subcontractor, sub consultant, lead, etc.)
and percentage share in the total contract
Address, Telephone,
Fax for reference
Provide a complete description of the services provided under this contract
demonstrating that the definition of a water supply system in ITB Section 1.4 (E)
has been met.
Page 80 of 553
BID Forms
Name of City
Country
Population served
Contract Role (joint venture participant, subcontractor, sub consultant, lead, etc.)
and percentage share in the total contract
Address, Telephone,
Fax for reference
Provide a complete description of the services provided under this contract
demonstrating that the definition of a water supply system in ITB Section 1.4 (E)
has been met.
Page 81 of 553
BID Forms
All individual firms and all participants of a joint venture are requested to complete
the information in this form with regard to their experience in designing, building,
operating, managing and maintaining water supply systems.
Use a separate sheet for each participant of a joint venture.
Bidders should not enclose client’s certificates with their Bid as they will be taken
into account in the evaluation of qualifications.
Annual turnover data (civil works facilities only)
Year Turnover (amounts billed to clients)
[Year]
[Year]
[Year]
[Year]
[Year]
4. Financial Capabilities [ref. ITB Section 1.4 (F)]
Name of Bidder or participant of a joint venture
Bidders, including each partner of a joint venture, shall provide financial information
to demonstrate they meet the requirements stated in the ITB. Each participant of a joint
venture shall complete this form. If necessary, separate sheets shall be used to provide
complete banker information. A copy of the audited balance sheets shall be attached.
Banker Name of banker
Address of banker
Amount of available cash credit facility:
Telephone Contact name and title
Fax Telex
Summarize actual assets and liabilities for the previous five calendar years. Based
upon known comments, summarize projected assets and liabilities for the next two
calendar years, unless the withholding of such information by stock market listed
public companies can be substantiated by the Bidder.
Page 82 of 553
BID Forms
BANK CERTIFICATE
Signature
Name of Bank
Senior Bank Manager
Address of the Bank
This is to certify that M/s. ………………. Who has formed a JV with M/s. ……………..
and M/s.…………………… for participating in this bid, is a reputed company with a
good financial standing.
If the contract for the work, namely …………………………… [ funded by the World
Bank] is awarded to the above Joint Venture, we shall be able to provide
overdraft/credit facilities to the extent of Rs. ……….. to M/s. ………….. to meet the
working capital requirements for executing the above contract.
This should be given by the JV members in proportion to their financial participation.]
Page 83 of 553
BID Forms
2. Title of position*
Name of candidate
3. Title of position*
Name of candidate
4. Title of position*
Name of candidate
5. Title of position*
Name of candidate
Page 84 of 553
BID Forms
Position Candidate
Contact (manager/personnel
Telephone officer)
Fax Telex
Summarize professional experience over the last twenty years, in reverse chronological
order. Indicate particular technical and managerial experience relevant to the project.
Company/Project/Position/Relevant technical and management
From To experience
Page 85 of 553
BID Forms
The following table shall be filled in for the Bidder and for each partner of a Joint
Venture]
[ In the present section Bidders shall provide a detailed design-build work plan
including a detailed program timetable ( the “Design Build Work Plan”), setting out
the manner in which the Bidder proposes to carry out the design-build work as defined
in the Appendix 3A – Design-Build Services Appendix and meet the design build
specifications ( the “Scope of Work ”).
The Design-Build Work plan shall be divided into the following sections:
(i) a section entitled “Drawing” which consists of conceptual drawings that are
sufficiently detailed to communicate the Bidder’s design intent for all components of
the proposed water supply system and the site.
(A) a site plan showing all proposed works listed in the Bid Documents;
(B) a detailed narrative in support of the conceptual drawings setting out the
Bidder’s plan for compliance with the Design-Build Specifications, to include
construction quality assurance and control;
(C) a detailed program and schedule setting out the proposed sequence of
works to be undertaken, including estimated start date, finish date and time
allocations for individual components of the works, proposed resources to be
allocated and the identification of all the milestones, including the submission of
schematic design documents, design development documents, the Design-Build
Documents and the commissioning of individual components of the project; and
(D) an itemized lists of the principal codes of practice and standards proposed
to be used for the Design-Build Work; and
(ii) a section entitled “Plant and Equipment and Bidder’s equipment” which consists
of a list of major Plant and Equipment with theBidder as given in ITC/BDS 1.4
Prior to drawings up the Design Build Work Plan and Conceptual Design it is
imperative that the Bidders familiarize themselves with the Owner’s available
background surveys, maps and sketch designs.
Page 87 of 553
BID Forms
[ In the present section Bidders shall provide a detailed work plan ( the “Operations
Work plan”), setting out the manner in which the Bidder proposes to carry out the
operation of the project as set out in the Appendix 3B – Operations and Maintenance
Services Appendix and meet the Operations and Maintenance Specifications.
The Operations Work plan shall be divided into the following sections:
(i) a section entitled “Operations Start-up” which provides an outline contents and
overview of the Bidder’s proposed plans and program, including staffing, for
operational start-up of the water supply system after commissioning; and
(ii) a section entitled “Operations Plan” which provides an outline contents and
overview of the Bidder’s proposed plans and programs, including staffing for water
supply system operation, including the items listed in the Bid Data Sheet
Page 88 of 553
BID Forms
(i) A section entitled the “Staffing chart for the Design-Build Services” and
consisting of a chart setting out a list of all proposed Key Staff, the role of each
position, the duration of existence of the position, and the location of the staff person
filling the position during the period of assignment to carry out the Design-Build
Services;
(ii) A section entitled the “Staffing Chart for Operations and Maintenance Services”
and consisting of a chart setting out a list of all proposed Key Staff, the role of each
position, the duration of existence of the position, and the location of the staff person
filling the position during the period of assignment to carry out the Operations an
Maintenance Services;
(A) for the Key Staff positions, the name of the Bidder’s employees who will
occupy the Key Staff positions; and
(B) all proposed positions for the Key Staff and the qualifications, years of
experience and areas of expertise, including a clear indication of the expertise that the
staff will provide consistent with the requirements set out in the BDS-ITB 1.4 (H); and
(iv) a section entitled , “Curriculum vitae” which contains the signed curriculum
vitae for each of the Key Staff, in the format set out in Annex A to the Bidding
Documents;
Page 89 of 553
BID Forms
Proposed Position:
Name of Firm:
Name of Staff:
Profession:
Date of Birth:
Key Qualifications:
[Give an outline of staff member’s experience and training most pertinent to tasks on
assignment. Describe degree of responsibility held by staff member on relevant
previous assignments and give dates and locations. Use about half a page.]
Education:
[Summarize college/university and other specialized education of staff member, give
names of schools, dates attended, and degrees obtained. Use about one quarter of a
page.]
Page 90 of 553
BID Forms
Employment Record:
[Starting with present position, list in reverse order every employment held. List all
positions held by staff member since graduation, giving dates, names of employment
organizations, titles of positions held, and locations of assignments. For experience in
last ten years, also give types of activities performed and client references, where
appropriate. Use about two pages.]
Languages:
[For each language indicate proficiency: excellent, good, fair or poor in speaking,
reading and writing.]
Certification:
I, the undersigned, certify that to the best of my knowledge and belief, these data
correctly describe me, my qualifications, and my experience. I also certify that I have
only given permission for my CV to be included in the Bid submitted by
Date:
Page 91 of 553
BID Forms
Page 92 of 553
BID Forms
Address : MP UDC, Beej Bhawan, Mother Theresa Road, Arera Hills, Bhopal,
Dear Sir,
Irrespective of indicating the Contarct Prices for each part separately, we understand
that the scope of works is for the composite works covering all the parts and the above
is done for the purposes of funding requirements of IBRD and GoMP.
Page 93 of 553
BID Forms
This Bid and your written acceptance of it shall constitute a binding contract between
us. We understand that you are not bound to accept the lowest or any Bid you receive.
We hereby certify that we have taken steps to ensure that no person acting for us on
our behalf will engage in bribery.
We also undertake that, in competing for(and, if the award is made to us, in executing)
the above contract, we will strictly observe the laws against fraud and corruption in
force in India namely “Prevention of Corruption Act, 1988”.
We hereby confirm that this Bid complies with the Eligibility, Bid Validity and Bid
Security required by the Bidding documents.
Yours faithfully,
Authorized Signatory:
Address : _________________
Page 94 of 553
BID Forms
[The Contractor should insert the amount of the guarantee in words and in figures.
This figure should be the same amount as set out in ITB Section 3.4(1) and the Bid
Data Sheet. The details related to the Bid Security are set out in the same ITB Section
3.4.]
(1) if the Contractor withdraws its Bid during the Bid Validity Period; or
(2) if the Contractor, having been notified of the acceptance of its Bid by the
Managing Director, Madhya Pradesh Urban Development Company Limited,
Bhopalduring the period of Bid validity,
(a) fails to sign the Form of Contract in accordance with and when required by ITB
Section 6.4; or
(b) fails to provide the performance security to the Engineer in Chief,MPUDC
Madhya Pradesh, Bhopal in accordance with and when required by ITB Section 6.5.
demand, without the Engineer in Chief, UADD, Madhya Pradesh, Bhopal having to
substantiate its demand, provided that in its demand the Managing Director, Madhya
Pradesh Urban Development Company Limited, Bhopal will note that the amount
claimed by it is due to it owing to the occurrence of one or more of the conditions set
out above, specifying the occurred condition or conditions.
This Guarantee will remain in full force up to and including 30 days after the expiry of
the Bid Validity Period and it may be extended by the Owner in accordance with the
Bidding Documents, notice of which extension(s) to the Bank is hereby waived. Any
demand in respect of this Guarantee should reach the Bank not later than the above
date or the extended date.
Name:
Position:
Page 96 of 553
BID Forms
Date:
PERFORMANCE GUARANTEE NO.:
We have been informed that [name of Contractor] (hereinafter called“the Contractor”) has
entered into Contract No.[reference number of the contract] dated with you, concerning a
contract to SURVEY, REVIEW THE DESIGNS, REDESIGN WHERE NECESSARY AND
BUILD WATER SUPPLY IMPROVEMENT SCHEME FOR KHARGONE TOWN,
KHARGONE DISTRICT, MADHYA PRADESH(hereinafter called “the Contract”).
Furthermore, we understand that, according to the conditions of the Contract, a performance
guarantee is required.
At the request of the Contractor, we [name of Bank] hereby irrevocably undertake to pay youany sum or
sums not exceeding in total an amount of ______[amount in figures] (____) [amountin words], upon
receipt by us of your first demand in writing accompanied by a written statement statingthat
the Contract is in breach of its obligations under the Contract, without your needing to prove
or to show grounds for your demand or the sum specified therein.
This guarantee shall expire no later than the earlier of:
(a) six months after the ContractCompletion Date, as defined in the Contract; or
(b) six months after the date of termination of the Contract pursuant to its terms.
Consequently, any demand for payment under this guarantee must be received by us at this
office on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees, ICC Publication No.
458 except that subparagraph (ii) of Sub-article 20(a) is hereby excluded.
Yours truly,
[Name of Bank]
Authorized Signature
Page 97 of 553
BID Forms
Date:
PERFORMANCE GUARANTEE NO.:
We have been informed that [name of Contractor] (hereinafter called“the Contractor”) has
entered into Contract No.[reference number of the contract] dated with you, concerning
a contract to OPERATE AND MAINTAIN THE BUILT SYSTEM FOR 5 YEARS
(hereinafter called “the Contract”).
Furthermore, we understand that, according to the conditions of the Contract, a
performance guarantee is required.
At the request of the Contractor, we [name of Bank] hereby irrevocably undertake to pay you any
sum or sums not exceeding in total an amount of ______[amount in figures] (____) [amount in
words], upon receipt by us of your first demand in writing accompanied by a written
statement stating that the Contract is in breach of its obligations under the Contract,
without your needing to prove or to show grounds for your demand or the sum
specified therein.
This guarantee shall expire no later than the earlier of:
(c) six months after the Contract Completion Date, as defined in the Contract;
or
(d) six months after the date of termination of the Contract pursuant to its
terms.
Consequently, any demand for payment under this guarantee must be received by us at
this office on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees, ICC
Publication No. 458 except that subparagraph (ii) of Sub-article 20(a) is hereby
excluded.
Yours truly,
[Name of Bank]
Authorized Signature
Page 98 of 553
BID Forms
Dear Sir,
We refer to the Contract Agreement (“the Contract”) signed on [date] between you
and [name of Contractor] (“the Contractor”) concerning the Services set out in the
SURVEY, REVIEW THE DESIGNS, REDESIGN WHERE NECESSARY AND
BUILD WATER SUPPLY IMPROVEMENT SCHEME FOR KHARGONE TOWN,
KHARGONE DISTRICT OF MADHYA PRADESHof Khargone water supply
scheme in Madhya Pradesh.
Provided always that the Bank’s obligation shall be limited to an amount equal to the
outstanding balance of the advance payment, taking into account such amounts that
have been repaid by the Contractor from time to time in accordance with the terms of
payment of the Contract as evidenced by appropriate shipping documents or payments
certificates.
Page 99 of 553
BID Forms
This Guarantee shall remain in full force from the date upon which the advance
payment is received by the Contractor until the date upon which the Contractor has
fully repaid the amount is advanced to the Managing Director, MPUDC, Madhya
Pradesh, Bhopal in accordance with the terms of the Contract. At the time at which the
outstanding amount is nil, this Guarantee shall become null and void, whether the
original is returned to us or not.
Any claims to be made under this Guarantee must be received by the Bank during its
period of validity.
Yours truly,
Section Question/Query/Clarification/
Item No. Reference Page No. Section or Comment
.
Clause Ref
1.
2.
3.
4.
5.
6.
Survey, Review the Designs, Redesign where necessary and Build water supply
improvement scheme for Khargone town, KHARGONE DISTRICT OF MADHYA
PRADESH and operate and maintain the built system for 5 years
(Declaration regarding customs/excise duty exemption for materials/
Construction equipment bought for the work)
1. We confirm that we are solely responsible for obtaining customs /excise duty
waiver which we have considered in our bid and in case of failure to receive such
waivers for reasons whatsoever, the Owner will not compensate us separately.
2. We are furnishing below the information required by the Owner for issue of the
necessary certificates in terms of the Government of India Central Excise Notification
no. …….. and Customs Notification no
3. The goods/construction equipment for which certificates are required as under,
Make Capacity Quantity Value State Remarks
Items Brand (where whether it regarding
Name applicable) will be justification
procured for the
locally or quantity
imported [if and their
so from usage in
which works
country]
Goods
Page 102 of 553
BID Forms
a
b
Construction Equipment
a
b
c
4. We agree that no modification to the above list is permitted after bids are
opened.
5. We agree that the certificate will be issued only to the extent considered
reasonable by the Owner for the work, based on the Bill of Quantities and the
construction programme and methodology as furnished by us alongwith the Bid.
6. We conform that the above goods will be exclusively used for the construction
of the above work and construction equipment will not be sold or otherwise disposed
off in any manner for a period f 5 years from the date of acquisition.
(Designation) ________________________
Annex B
To the Bidding Documents
The Draft Contract
Form of Contract
General Conditions of Contract
Appendices to the General Conditions
FORM OF CONTRACT
THIS FirstAgreement is made and entered into this ____ day of _______, [Year]
Between Managing Director, Madhya Pradesh Urban Development Company
Limited, Madhya Pradesh, a company incorporated under the laws of Indiaand
having its principal place of business at Beej Bhawan, Mother Theresa Marg, Arera
Hills, Bhopal (hereafter the “Owner”)
– and –
[Name of Contractor Company] incorporated under the laws of [place of inCouncil]
with itsprincipal place of business at [Address of the Contractor]
(hereafter the “Contractor”)
– and –
[Name of the Contractor’s Parent Company or any other entities the Owner may be
required to be parties to the Contract]
WHEREAS:
1. The Owner has the jurisdiction to enter into the Contract, as defined in Section
1.1 below, pursuant to the Applicable Law;
2. The Owner has received all requisite approvals necessary and has conformed
with all requisite laws in accordance with the Applicable Law to permit the Owner to
enter into the Contract;
4. The Contractor has represented to the Owner that it has the skills and ability to
SURVEY, REVIEW THE DESIGNS, REDESIGN WHERE NECESSARY AND
BUILD WATER SUPPLY IMPROVEMENT SCHEME FOR KHARGONE TOWN,
Page 105 of 553
Form of Contract
5. The Contractor responded to the Bidding Documents No. …….. with Addenda/
Amendments organized by the MPUDC and was selected as the recommended
Contractor to fulfill the Design-Build and Operating Services set out in the Technical
Standards Appendix;
6. The Contractor has the corporate capacity and authority to enter into the
Contract; and
FORM OF CONTRACT
THIS Second Agreement is made and entered into this ____ day of _______, [Year]
Between Managing Director, Madhya Pradesh Urban Development Company
Limited, Madhya Pradesh, a company incorporated under the laws of Indiaand
having its principal place of business at Beej Bhawan, Mother Theresa Marg, Arera
Hills, Bhopal (hereafter the “Owner”)
– and –
[Name of Contractor Company] incorporated under the laws of [place of inCouncil]
with itsprincipal place of business at [Address of the Contractor]
(hereafter the “Contractor”)
– and –
[Name of the Contractor’s Parent Company or any other entities the Owner may be
required to be parties to the Contract]
WHEREAS:
1. The Owner has the jurisdiction to enter into the Contract, as defined in Section
1.1 below, pursuant to the Applicable Law;
2. The Owner has received all requisite approvals necessary and has conformed
with all requisite laws in accordance with the Applicable Law to permit the Owner to
enter into the Contract;
3. The Owner desires to engage the Contractor to OPERATE AND MAINTAIN
THE SYSTEM BUILT FOR WATER SUPPLY IMPROVEMENT OF Khargone town
of Khargone District of Madhya Pradesh (under Design Build Agreement) FOR 5
YEARS and ensure the effectiveness and viability of the Burhanpur water supply
scheme.
4. The Contractor has represented to the Owner that it has the skills and ability to
OPERATE AND MAINTAIN THE BUILT SYSTEM FOR FIVE (5) YEARS in an
economical and effective manner with reduced cost and increased profitability and
agrees to do so upon and subject to the terms and conditions of the Contract
Page 107 of 553
Form of Contract
Documents;
5. The Contractor responded to the Bidding Documents No. …….. with Addenda/
Amendments organized by the MPUDC and was selected as the recommended
Contractor to fulfill the Design-Build and Operating Services set out in the Technical
Standards Appendix;
6. The Contractor has the corporate capacity and authority to enter into the
Contract; and
1.3 Definitions
Capitalized words and phrases used herein shall have the same meanings as are
described to them in the General Conditions of Contract and Appendices to the
General Conditions of Contract.
The Effective Date, the Design-Build Starting Date and Operations and Maintenance
Starting Date for the Contract are as below
IN WITNESS WHEREOF the Owner and the Contractor have caused this Form of
Contract to be duly executed by their duly authorized representatives.
[OWNER]
By: ____________________________________
Name: ____________________________________
Title: ____________________________________
Witness: ____________________________________
[THE CONTRACTOR]
By: ____________________________________
Name: ____________________________________
Title: ____________________________________
Witness: ____________________________________
[PARTNER(S) OF THE CONTRACTOR]
By: ____________________________________
Name: ____________________________________
Title: ____________________________________
Witness: ____________________________________
TO
1.1 Definitions
Unless the context otherwise requires, the following terms wherever used in this
Contract have the following meanings:
“Adjudicator” means the person that is named in the SCC;
“Applicable Law” means the laws and any other instruments having the force of law in
the Country specified in the SCC, as they may be issued and in force from time to
time, including any decree of the President or government of the Country;
“Appointing Authority” is the authority specified in the SCC;
“Authorities” means the Owner and the Country as specified in the SCC;
“Background Information Document” means the Background Information Document
provided to the Contractor by the Owner during the bidding process that preceded this
Contract;
“Bank” means the World Bank;
“Bidding Documents” means the documents issued by the Owner in respect of the
bidding process for the selection of aContractor to design, build and operate the New
Facility and to perform the Services;
“Capital Investment Program” means the capital investment program of the Owner, if
any, referred to in OSA Section 10.2(2);
“Change” is defined in GC Section 10.1.1(1);
“Change Order” is defined in GC Section 10.1.2(4);
“Completion” means that the New Facility and all Design-Build Services have been
completed operationally and structurally and put in a tight and clean condition in
accordance with the Technical Standards Appendix, and the Contractor is entitled to
have a Completion Certificate issued in respect of the New Facility, or part thereof, in
Page 114 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
New Facility, or the relevant part thereof, as set out in GC Section 9.1(2);
“Design-Build Documents” means the plans, specifications, designs, models,
electronic models and other documents and materials relating to the design and
construction of the Site and New Facility as may be set out or contemplated in the
Design-Build Services Appendix or agreed to by the Parties from time to time during
the Contract Term;
“Engineer” means the engineer retained by the Owner to supervise the Contractor, in
accordance with the Contract Documents, in carrying out the Design-Build Services or
O&M services or any other services as notified from time to time ;
“Independent Verification Team (IVT)” means the consultant appointed by the
MPUDC to exercise independent check over design, construction material and quality,
and achievement of performance indicators.
“Design-Build Period” is defined in GC Section 2.2(a);
“Design-Build Services” means the design-build services to be performed by the
Contractor as contemplated by the General Conditions and the Design-Build Services
Appendix;
“Design-Build Starting Date” is defined in GC Section 2.1.3(1);
“Effective Date” means the date on which this Contract comes into force and effect
pursuant to GC Section 2.1.1;
“End Date” is defined in GC Section 2.1.2;
“Existing Equipment and Materials” is defined in GC Section 9.3.2(1);
“Existing Facility” means the operational water supply facility on the Site as it exists
on the Design-Build Starting Date;
“Existing Operations Services” is defined in DBSA Section 4.1;
“Extension Date” is defined in GC Section 2.4.3;
“Force Majeure” is defined in GC Section 9.8(1);
“GC Section” means General Conditions Section;
“IDA” means the International Development Agency;
Page 116 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
“including” means including without limitation and “includes” means includes without
limitation, unless expressly stated otherwise;
“Liquidated Damages – Delay” is defined in GC Section 2.3.6(2);
“Manager” is defined in GC Section 8.2(3);
“Monthly Operations Payment” is defined in Section 1.4 of the Terms and Procedures
of Payment Appendix;
“New Facility” means the water supply scheme designed and built by the Contractor
pursuant to this Contract;
“New Operations Period” is defined in GC Section 2.2(b);
“New Operations Starting Date” is defined in GC Section 2.1.3(2);
“Operational Acceptance” means the acceptance by the Owner of the New Facility, or
part thereof, in accordance with DBSA Section 7.3;
“Operations Services” means the Operations Services to be performed by the
Contractor as contemplated by the General Conditions and the Operations Services
Appendix;
“Contractor” means the water supply contractor and Contractor retained by the Owner
to carry out the Services and is the Party named as the Contractor in the Form of
Contract;
“Contractor’s Equipment (Design-Build)” means all machinery, apparatus, vehicles
and other equipment required for the execution and completion of the Design-Build
Services and the remedying of any defects, but does not include material, machinery,
apparatus and other equipment forming part of the Plant and Equipment of the New
Facility;
“Contractor’s Equipment (Operations)” means all things of any kind whatsoever,
including the equipment, materials, supplies, vehicles and consumables required to
operate, maintain and repair the Site and New Facility;
“Contractor’s Personnel” is defined in GC Section 8.3(1);
“Contractor’s Representative” is defined in GC Section 8.1.2(1);
“OSA Section” means Operations Services Appendix Section;
Page 117 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
Subject to the Form of Contract provisions, all documents forming part of the
Contract, and all parts thereof, are intended to be correlative, complementary and
mutually explanatory. The Contract shall be read as a whole. The following
appendices which are incorporated by reference into the Contract shall be referred to
as follows:
Page 119 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
1.3 Interpretation
1.3.1 Language
The singular shall include the plural and the plural shall include the singular except
where the context otherwise requires.
1.3.3 Headings
The headings in the Contract Documents are included for ease of reference and shall
neither constitute a part of the Contract nor affect its interpretation.
Page 120 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
1.3.4 Persons
Words importing persons or entities shall include firms, Councils and government
entities.
1.3.5 Incoterms
Unless inconsistent with any provision of the Contract, the meaning of any trade term
and the rights and obligations of the Parties thereunder shall be prescribed by the latest
version of Incoterms.
Incoterms means international rules for interpreting trade terms published by the
InternationalChamber of Commerce (latest edition), 38 Cours Albert 1er, 75008 Paris,
France.
This Contract constitutes the entire agreement between the Owner and the Contractor
with respect to the subject matter of the Contract and supersedes all communications,
negotiations and agreements, whether written or oral, made by the Parties with respect
thereto made prior to the date of the Contract.
1.3.7 Amendment
Except as expressly stated to the contrary elsewhere herein, in computing the number
of days for the purposes of the Contract all days shall be counted, including Saturdays,
Page 121 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
Sundays and legal holidays in the Country, provided, however, that if the final day of
any period shall fall on a Saturday, Sunday, or legal holiday in the Country, then the
final day shall be deemed to be the next day which is not a Saturday, Sunday or legal
holiday in the Country.
(2) Subject to the provisions of the Contract, the Contractor shall be solely
responsible for the manner in which the Contract is performed. All employees, agents,
representatives or Subcontractors engaged by the Contractor in connection with the
performance of the Contract shall be under the complete control of the Contractor and
shall not be deemed to be employees of the Owner, and nothing contained in the
Contract, or in any Subcontract awarded by the Contractor, shall be construed to create
any contractual relationship or legal obligation between the Contractor’s employees,
agents, representatives or Subcontractors and the Owner.
(1) If the Contractor consists of a joint venture company of more than one person,
the Shareholders hereby authorize the representative named in the SCC to act on their
behalf in exercising all the Shareholders’ and Contractor’s rights and obligations
toward the Owner under this Contract, including the receiving of approvals, consents,
orders, certificates, instructions and payments from the Owner, amendment of the
Contract and in all other matters under the Contract, including the settlement of
disputes.
(2) If the Contractor is a joint venture company of two or more persons, each
Shareholder of the joint venture company and its parent companies, shall be jointly
and severally bound to the Owner for the fulfillment of the provisions of the Contract
Page 122 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
by the Contractor. Claims against the parent companies or the Shareholders as the case
may be shall be subject to any legal defenses available to the Contractor, and to any
limits on the liability of the Contractor including those set out in GC Section 9.2.
(4) The Shareholders shall maintain the type and amount of equity set out in the
SCC.
1.3.11 Non-waiver
(a) be in writing;
(c) specify the right, power or remedy being waived and the extent to which it is
being waived.
1.3.12 Severability
“Origin” means the place where the materials, equipment and other supplies for the
New Facility are mined, grown, produced or manufactured, and from which the
services are provided.
Upon the termination or expiration of the Contract pursuant to the Contract, all rights
and obligations of the Parties hereunder shall cease, except those noted in the SCC.
1.4 Notice
(1) All notices to be given under the Contract shall be in writing and shall be sent
by personal delivery, courier or facsimile to the address for notice of the relevant Party
as set out in the SCC and the following provisions apply:
(a) Any notice sent by facsimile shall be confirmed by the sender no later than two
days after dispatch by a notice sent by courier;
(b) Any notice sent by courier shall be deemed to have been delivered 10 days after
dispatch. In proving the fact of dispatch, it shall be sufficient to show that the envelope
containing such notice was properly addressed, with proper payment for the courier,
and conveyed to the courier service for transmission; and
(c) Any notice delivered personally or sent by facsimile shall be deemed to have
been delivered on the date of dispatch.
(2) A Party may change its address for notice pursuant to this Contract by giving the
other Party notice of change in accordance with this GC Section 1.4.
Page 124 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(3) The Contractor’s address for the purpose of giving notice pursuant to this GC
Section 1.4 shall be in the Country named in the SCC.
(4) Notices shall be deemed to include any approvals, consents, instructions, orders,
certificates and similar communications to be given under the Contract.
1.6.1 Adjudicator
(1) If any dispute of any kind whatsoever arises between the Owner and the
Contractor in connection with or arising out of the Contract including,
(a) any question regarding the existence, validity or termination of the Contract; and
(b) any matter related to the performance of the Services,
the Parties shall seek to resolve any such dispute or difference by mutual consultation.
If the Parties fail to resolve such a dispute or difference by mutual consultation, the
dispute shall be referred in writing, by either the Contractor or the Owner, to the
Adjudicator with a copy to the other Party or Parties.
(a) during the execution of the Services and after the completion of the Services;
and
(b) before and after the termination, abandonment or breach of the Contract.
(3) The Adjudicator shall give its decision in writing to both Parties no later than 30
Page 125 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
days after the referral of a dispute. If the Adjudicator has rendered its decision within
the 30 day time limit, and no notice of intention to commence arbitration has been
given by either the Owner or the Contractor prior to the expiration of 60 days after the
reference of the dispute to the Adjudicator, the Adjudicator’s decision shall become
final and binding upon the Owner and the Contractor. Any decision that has become
final and binding shall be implemented by the Parties forthwith.
(4) The Adjudicator shall be paid a fee at the rate specified in the SCC plus
reasonable expenditures incurred in the execution of its duties as Adjudicator, and
these costs shall be divided equally between the Owner and the Contractor.
(5) If the Adjudicator resigns or dies, or the Owner and the Contractor agree that the
Adjudicator is not fulfilling its functions in accordance with the provisions of the
Contract, a new Adjudicator shall be jointly appointed by the Owner and the
Contractor. If the Owner and the Contractor cannot agree on a new Adjudicator within
30 days after the resignation, death or removal of the existing Adjudicator, the new
Adjudicator shall be appointed at the request of either Party by the Appointing
Authority specified in the SCC.
1.6.2 Arbitration
(1) If either the Owner or the Contractor is dissatisfied with the Adjudicator’s
decision, or if the Adjudicator fails to give a decision within 30 days after a dispute
being referred to it, then either the Owner or the Contractor may, within 60 days after
such reference, give notice to the other Party, with a copy for information to the
Adjudicator, of its intention to commence arbitration, as hereinafter provided, as to the
matter in dispute, and no arbitration in respect of this matter may be commenced
unless such notice is given.
(a) the Parties shall continue to perform their respective obligations under the
Contract unless they otherwise agree; and
(b) the Owner shall pay the Contractor any monies due to the Contractor.
1.7 Assignment
(1) The Contractor shall not assign to any Third Party the Contract, or any part
thereof, or any right, benefit, obligation or interest therein or thereunder without the
prior consent of the Owner, which consent may not be unreasonably withheld.
(2) The Contractor may assign, absolutely or by way of charge, any monies due and
payable to it or that may become due and payable to it under the Contract.
(3) To be a valid assignment which has been approved by the Owner pursuant to
GC Section 1.7(1), the assignment must,
(a) be in writing;
(b) all files, documents, plans, drawings, specifications, notes, minutes of meetings
and minutes of conversations;
(c) all the plans, programs, reports, surveys and guidelines prepared by the
Contractor in carrying out the Operations Services;
(d) the accounts of the water supply operations at the New Facility;
(e) all manuals, reports, condition surveys, safety records, audit records,
inventories, laboratory test results, procurement records, customer information,
financial information, financial statements, invoices, accounting records, subcontracts
and personnel records; and
(f) the Design-Build Documents, whether stored in hard copy or electronically.
(3) The Contractor shall provide the Owner with unrestricted access to the Contract
Records during the term of the Contract, including the right to make and retain copies.
(4) The Contractor may retain a copy of the Contract Records but shall not use them
for purposes unrelated to this Contract without the prior approval of the Owner. This
GC Section 1.8.1(4) does not in any way relieve the Contractor of its obligation of
confidentiality pursuant to GC Section 6.2.
(5) Except as provided in GC Section 6.1, the Contractor acknowledges that the
Page 128 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
Owner, as owner of the Contract Records, may deal with the Contract Records in any
way it determines, including making the Contract Records publicly available and
making those available to prospective Contractors who may be involved in the process
to select a Subsequent Contractor.
1.8.2 Accounting
The Contractor shall keep accurate and systematic accounts in respect of the Services
and the Contract in accordance with internationally accepted accounting principles.
1.8.3 Auditing the Contractor’s Own Accounts and the Contract Records
(a) the Contractor’s own accounts, financial information, financial statements and
technical information at any reasonable time and with 24 hour notice to the Contractor;
and
(b) the Contract Records and Design-Build Documents at any reasonable time and
without notice to the Contractor,
in respect of any matters related to the Contract.
2. The Owner may complete the audit or audits itself or may retain an independent
auditor, at the Owner’s expense, to complete the audit or audits.
The Contractor shall submit to the Owner, no later than 90 days after the end of the
Contractor’s fiscal year, the annual audited accounts of its own finances for each of the
Contractor’s fiscal years that occur during the Contract Term.
The Bank may, in its sole discretion, inspect or audit the Contractor’s accounts,
financial information, financial statements and technical information in respect of any
Page 129 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
matters related to the Contract at any reasonable time and without notice to the
Contractor and may have the audit carried out by auditors appointed by the Bank.
(1) If the Contractor considers itself to be entitled to any extension of the Time for
Completion or any additional payment, under any section related to the Design-Build
Services of these General Conditions, the Contractor shall give notice to the Project
Manager, describing the event or circumstance giving rise to the claim. The notice
shall be given as soon as practicable, and no later than 30 days, after the Contractor
became aware, or should have become aware, of the event or circumstance.
(2) If the Contractor fails to give notice of a claim within such period of 30 days,
the Time for Completion shall not be extended, the Contractor shall not be entitled to
additional payment, and the Owner shall be discharged from all liability in connection
with the claim. Otherwise, the following provisions of this GC Section 1.9 shall apply.
(3) The Contractor shall also submit any other notices related to the Design-Build
Services which are required by the Contract, and supporting particulars for the claim,
that are relevant to such event or circumstance.
(4) The Contractor shall keep such contemporary records as may be necessary to
substantiate any claim related to the Design-Build Services, either on the Site or at
another location acceptable to the Project Manager. Without admitting the Owner’s
liability, the Project Manager may, after receiving any notice under this GC Section
1.9, monitor the record-keeping or instruct the Contractor to keep further
contemporary records. The Contractor shall permit the Project Manager to inspect all
these records, and shall, if instructed, submit copies to the Project Manager.
(5) No later than 42 days after the Contractor became aware, or should have become
aware, of the event or circumstance giving rise to the claim, or within such other
period as may be proposed by the Contractor and approved by the Project Manager,
the Contractor shall send to the Project Manager a fully detailed claim which includes
Page 130 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
full supporting particulars of the basis of the claim and of the extension of time or
additional payment claimed. If the event or circumstance giving rise to the claim has a
continuing effect,
(a) this fully detailed claim shall be considered as interim;
(b) the Contractor shall send further interim claims at monthly intervals, giving the
accumulated delay or amount claimed, and such further particulars as the Project
Manager may reasonable require; and
(c) theContractor shall send a final claim no later than 30 days after the end of the
effects resulting from the event or circumstance, or within such other period as may be
proposed by the Contractor and approved by the Project Manager.
(6) No later than 42 days after receiving a claim or any further particulars
supporting a previous claim, or within such other period as may be proposed by the
Project Manager and approved by the Contractor, the Project Manager shall respond
with approval, or with disapproval and detailed comments. The Project Manager may
also request any necessary further particulars, but shall nevertheless give his response
on the principles of the claim within such time.
(7) Each invoice sent by the Contractor shall include such amounts for any claim as
have been reasonably substantiated as due under the relevant provision of the Contract.
Unless and until the particulars supplied are sufficient to substantiate the whole of the
claim, the Contractor shall only be entitled to payment for such part of the claim as it
has been able to substantiate.
(8) The Contractor shall proceed in accordance with GC Section 7.2.6 to request,
(a) an extension, if any, of the Time for Completion before or after its expiry in
accordance with GC Section 2.3.4; or
(b) an additional payment, if any, to which the Contractor believes it is entitled
under the Contract.
(9) The requirements of this GC Section 1.9 are in addition to those of any other
provision which may apply to a claim. If the Contractor fails to comply with this or
another provision in relation to any claim, any extension of or additional payment shall
Page 131 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
take account of the extent, if any, to which the failure has prevented or prejudiced
proper investigation of the claim, unless the claim is excluded under GC Section
1.9(2).
(10) This GC Section 1.9 shall apply only in respect of the Design-Build Services
excluding the Existing Operations Services.
2.1 General
The Form of Contract shall be signed by the Contractor, the Parent and the
Shareholders, if the Contractor is a joint venture company, prior to its signing by the
Owner. The Contract shall come into force and effect on the date the Form of Contract
is signed by the Owner (the “Effective Date”).
(a) the specified number of months after the New Operations Starting Date named
in the SCC;
(b) the Extension Date pursuant to GC Section 2.4.3; or
(c) the date of Contract termination pursuant to GC Section 11.2, (the “End Date”),
whichever is applicable.
(1) Unless otherwise stated in the SCC, the Design-Build Starting Date shall be no
later than 15 days after the Effective Date and the Owner shall give the Contractor at
least seven days prior notice of the Design-Build Starting Date.
(2) The “New Operations Starting Date” shall be the date of the Operational
Acceptance Certificate.
(a) the period commencing on the Effective Date and ending on the day
immediately prior to the New Operations Starting Date (the “Design-Build Period”);
and
(b) the period commencing on the New Operations Starting Date and ending on the
End Date (the “New Operations Period”).
The Contractor shall commence the Design-Build Services no later than the Design-
Build Starting Date, and shall then proceed with the Design-Build Services with due
expedition and without delay.
(a) the order in which the Contractor intends to carry out the Design-Build Services,
including the anticipated timing of each stage of design, Design-Build Documents,
procurement, manufacture, inspection, delivery to the Site, construction, erection,
Page 134 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(2) The Project Manager shall review each Time Schedule and provide comments to
the Contractor as to whether the Time Schedule complies with the Contract. If the
Project Manager fails to provide such comments prior to the expiration of 15 days after
receiving a Time Schedule, the Contractor shall proceed in accordance with the Time
Schedule, subject to its other obligations under the Contract. The Contractor shall be
entitled to rely upon the Time Schedule when planning its activities.
(3) The Contractor shall promptly give notice to the Project Manager of specific
probable future events or circumstances which may adversely affect the Design-Build
Services or delay the execution of the Design-Build Services. The Project Manager
may require the Contractor to submit an estimate of the anticipated effect of the future
event or circumstances, or a proposal under GC Section 10.1.3.
(4) If, at any time, the Project Manager gives notice to the Contractor that a Time
Schedule fails, to the extent stated, to comply with the Contract or to be consistent
with actual progress and the Contractor’s stated intentions, the Contractor shall submit
a revised Time Schedule to the Project Manager in accordance with this GC Section
2.3.3.
(a) Change, unless the Parties have already agreed to an adjustment to the Time
for Completion as part of the applicable Change;
(b) an occurrence of Force Majeure as provided in GC Section 9.8,
Unforeseeable physical conditions as provided for in GC Section 9.7, or loss
or damage as a result of the occurrences set out in GC Section 9.4(2);
(c) any suspension order given by the Owner pursuant to GC Section 11.1.1;
(d) any change in the Applicable Law in accordance with GC Section;
(e) any default or breach of the Contract by the Owner or any activity, act or
omission of any other contractors employed by the Owner; or
(f) any other matter specifically mentioned in the Contract;
(g) by such period as shall be fair and reasonable in all the circumstances and as
shall fairly reflect the actual delay or impediment sustained by the
Contractor.
(2) The Contractor shall submit, to the Project Manager, any notice of a claim for an
extension of the Time for Completion in accordance with GC Section 10.1.3.
(3) The Contractor shall, at all times, use reasonable efforts to minimize any delay
in the performance of its obligations under the Contract.
(1) If, at any time, the Contractor’s progress in respect of the Design-Build
Services,
(a) is too slow to complete the Design-Build Services in accordance with the Time
for Completion; or
(b) has fallen, or will fall, behind the current Time Schedule
other than as a result of a cause listed in GC Section 2.3.4, then the Project Manager
may instruct the Contractor to submit a revised Time Schedule and supporting report
describing the revised methods which the Contractor proposes to adopt in order to
expedite progress and complete the Design-Build Services.
2. Unless the Project Manager notifies otherwise, the Contractor shall adopt the
revised methods referred to in GC Section 2.3.5(2), which may require increases in,
at the risk and cost of the Contractor. If these revised methods cause the Owner to
incur additional costs, the Contractor shall, subject to GC Section 1.9, pay these costs
to the Owner, in addition to delay damages, if any, under GC Section 2.3.6.
(2) If the Contractor fails to attain Completion of the scope of services within the
Time for Completion, or any extension thereof in accordance with GC Section 2.3.4,
the Contractor shall pay to the Owner liquidated damages in the amount specified in
the SCC (“Liquidated Damages – Delay”). The aggregate amount of Liquidated
Damages – Delay shall in no event exceed the amount specified as “Maximum” in the
SCC. The Owner may terminate the Contract pursuant to GC Section 11.2.3 if the
Contractor reaches the “Maximum” level for Liquidated Damages – Delay.
(5) If the Contractor attains Completion of the New Facility before the Time for
Completion or any extension thereof pursuant to GC Section 2.3.4, and if the Owner
intends to pay a bonus to the Contractor for early completion, the amount of the bonus
is as set out in the SCC. The aggregate amount of such bonus shall in no event succeed
the amount specified as “Maximum” in the SCC.
Unless otherwise stated in the SCC, the Contractor shall carry out the Existing
Operations Services for the Existing Facility as set out in Section 4.1 of the Design-
Build Services Appendix during the Design-Build Period commencing on the Design-
Build Starting Date. GC Sections 2.3.1 to 2.3.6 do not apply to the Existing Operations
Services.
the End Date of Operations Contract. The Owner shall notify the Contractor no later
than 6 months prior to the End Date if it wishes to enter into negotiations in order to
extend the duration of the Contract. The Contractor must respond within one month if
it is willing for further extensions and terms and conditions for such extension. The
contractor may also refuse to further extensions at its discretion. The date on which
the Contract is to expire as a result of an extension shall be the Extension Date.
(a) perform the Existing Operations Services as set out in the Design-Build Services
Appendix;
(b) perform the Design-Build Services set out in the Design-Build Services
Appendix;
(c) perform the Operations Services set out in the Operations Services Appendix;
and
(d) perform the Services in accordance with the Technical Standards set out in the
Technical Standards Appendix, all with due care and diligence in accordance with the
Contract.
The Contractor shall comply with the Applicable Law and shall ensure that the
Contractor’s Personnel and Subcontractors comply with the Applicable Law. The
Contractor shall indemnify and hold harmless the Owner from and against any and all
liabilities, damages, claims, fines, penalties and expenses of whatever nature arising or
resulting from violation of theApplicable Law by the Contractor, the Contractor’s
Personnel the Subcontractors and the Subcontractors’ personnel.
(1) The compensation of the Contractor pursuant to GC Article 5 shall constitute the
Contractor’s sole compensation in connection with this Contract and, except as
provided in GC Article 5, the Contractor shall not accept for its own benefit any trade
Page 140 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(2) The Contractor, Subcontractors and any entity affiliated with the Contractor or
the Subcontractors, shall be disqualified, during the Contract Term from providing
goods, works or services, other than the Services, with respect to,
(a) the goods, works and services purchased from the Contingency Fund; and
(3) The Contractor, Contractor’s Personnel, Subcontractors and the employees and
affiliates of the Subcontractors shall not engage, either directly or indirectly, in any
business or professional activities which would conflict with the activities assigned to
them under this Contract.
(4) The Contractor and its Shareholders shall not participate in any discussions or
work and shall not provide any services or advice to the Owner related to,
(a) except with respect to their responsibilities as set out in the Operations Services
Appendix, institutional restructuring or reorganization of the Owner or a utility or
department of the Owner;
(b) the development or review of bidding documents to retain any Subsequent
Contractor; or
(c) the preparations for the procurement process to retain any Subsequent
Contractor.
(5) Failure of the Contractor or the Shareholders to comply with this GC Section
3.3, in addition to constituting a breach of this Contract, may result in the
disqualification of the Contractor and the Shareholders from bidding in the
Page 141 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(2) The Contractor shall prepare a list of all Contractor’s Equipment (Design-Build)
and Contractor’s Equipment (Operations) (the “Contractor’s Equipment Lists”).
The Contractor shall update the Contractor’s Equipment Lists on an annual basis
and shall provide the updated Contractor’s Equipment Lists to the Owner no
later than 30 days after the end of each of the Contractor’s fiscal years during
the Contract Term.
(1) The Contractor acknowledges that the Owner made available to the Contractor,
during the bidding process, either directly or by placing the data in the Data Room and
Background Information Document, all available data on hydrological and sub-surface
conditions of the Site, and studies on environmental impact that had been obtained by
or on behalf of the Owner from investigations in anticipation of the Design-Build and
Operations Services (the “Site Information”). The Contractor shall be responsible for
interpreting all data about the Site that is provided to it by the Owner.
(2) The Contractor shall be deemed to have inspected and examined the Site, its
surroundings, the Site Information and other available information, and to have
satisfied itself before entering into the Contract, as to,
(a) the form and nature of the Site, including the sub-surface conditions;
(b) the applicable hydrological, hydro geological and climatic conditions;
Page 142 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(c) the extent and nature of the work, Plant and Equipment, Contractor’s
Equipment (Design-Build) and Contractor’s Equipment (Operations)
necessary for the execution and completion of the Services, and the
remedying of any defects; and
(d) theContractor’s requirements for access to the Site, accommodation,
personnel, power, transport, water and other services.
(3) The Contractor shall be deemed to have obtained all necessary information as to
risks, contingencies and all other circumstances that may influence or affect the
performance of its obligations under the Contract.
(4) To the extent the Contractor did not make any of the interpretations,
investigations or examinations, or did not satisfy itself, or did not obtain such
information as called for in this GC Section 3.5, the Contractor represents and
warrants that it is willing to assume and does hereby assume responsibility for
any and all loss and damage from any cause whatsoever which the Contractor’s
interpretations, investigations, examinations and obtaining of information may
have avoided and agrees to indemnify the Owner from all risk thereof and from
conditions arising or developing in the course of performing the Services which
may make the performance of the Services more onerous and more expensive to
fulfill or perform than was contemplated on the Effective Date. Notwithstanding
anything in the Contract to the contrary, the Contractor acknowledges and
declares that in entering into the Contract it did not and does not rely upon any
information or report provided by or on behalf of the Owner or its agents,
representatives or employees.
(1) The Contractor shall, during both the Design-Build Period and the New
Operations Period, provide free and open access to the Site, the Existing Facility
and the New Facility at the Owner’s request. The Owner shall make reasonable
efforts to provide reasonable notice to the Contractor prior to the Owner’s
access but such notice is not mandatory. The Owner’s representative on the Site,
Page 143 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
the Existing Facility or at the New Facility shall observe all safety and health
regulations and reasonable instructions of the Contractor.
(2) The Contractor shall give all reasonable access to any other contractors
employed by the Owner on or near the Site to carry out their work.
(3) If the Contractor makes available to other contractors any roads or ways the
maintenance for which the Contractor is responsible, permits the use by such
other contractors of the Contractor’s Equipment (Design-Build) and
Contractor’s Equipment (Operations), or provides any other service of
whatsoever nature for such other contractors, the Owner shall fully compensate
the Contractor for any loss or damage caused or occasioned by such other
contractors in respect of any such use or service, and shall pay to the Contractor
reasonable remuneration for the use of such equipment or the provision of such
services.
(4) The Contractor shall also arrange to perform its work so as to minimize, to the
extent possible, interference with the work of other contractors. The Project
Manager or MPUDC, as applicable, shall determine the resolution of any
difference or conflict that may arise between the Contractor and other
contractors and the workers of the Owner in regard to their work.
(5) The Contractor shall notify the Project Manager orMadhya Pradesh Urban
Development Company Limited, Bhopal, as applicable, promptly of any defects
in the other contractors’ work that come to its notice, and that could affect the
performance of the Services by the Contractor. The Project Manager or Madhya
Pradesh Urban Development Company Limited, Bhopal, as applicable, shall
determine the corrective measures, if any, required to rectify the situation after
inspection of the Site, the Existing Facility and the New Facility. Decisions
made by the Project Manager orEngineer-in-Chief, Madhya Pradesh Urban
Development Company Limited, Bhopal, as applicable, shall be binding on the
Contractor.
(a) provide the Contractor, Subcontractors and Contractor’s Personnel with work
permits and such other documents as shall be necessary to enable the Contractor,
Subcontractors or Contractor’s Personnel to perform the Services;
(b) facilitate the prompt clearance through customs of any property required for the
Services and of the personal effects of the Contractor’s Personnel and their eligible
dependents; and
(c) issue to officials, agents and representatives of the Owner all such instructions
as may be necessary or appropriate for the prompt and effective implementation of the
Services.
(d) appoint Project Implementation Unit to supervise the works and act on behalf of
the owner, wherever needed. Project Manager of the PIU shall be the Project Manager
for the project during design –built period as well as during the operation –
maintenance period. The Contractor shall be directly responding to the PIU under
intimation to Engineer-in-Chief, MPUDC. PIU shall also co-ordinate between the
Contractor and MPUDC as well as the KNP.
(e) appoint a Project Management Consultant (PMC) to support and assist the PIU
and MPUDC in various tasks related to the project. The PMC will assist the PIU and
MPUDC in managing various project related tasks including daily supervision of
works on site and evaluation of drawings and designs submitted by the Contractor for
approval.
(f) appoint an engineer and his team from the Khargone Municipal Council to
involve in supervision and assistance of PIU during operation and maintenance period.
The Engineer deputed by the KNP will be the part of the team witnessing the
Page 145 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
C. PAYMENT
(2) Unless indicated otherwise in the SCC, the Contract Price shall be,
not subject to any alteration, except in the event of a Change to the Design-Build
Services in accordance with GC Section 10.1 or a change to the Operations
Services in accordance with GC Section 10.2 or as otherwise provided in the
Contract Price Adjustment Appendix.
(3) Subject to GC Section 9.7, the Contractor shall be deemed to have satisfied itself
as to the correctness and sufficiency of the Contract Price, which shall, except as
otherwise provided for in the Contract, cover all its obligations under the Contract,
including all costs and expenses for the design and building of the New Facility and
the operation of the New Facility and the Existing Facility.
(4) Provisional Sums: The total sum paid to the Contractor shall include only such
amounts, for the work, supplies or services to which the Provisional Sum relates, as the
Project Manager shall have instructed. For each Provisional Sum, the Project Manager
may instruct:
(a) work to be executed (including Plant, Materials or services to be supplied) by the
Contractor and valued under Sub-Clause 13.3 [Variation Procedure]; and/or
(ii) a sum for overhead charges and profit, calculated as a percentage of these
actual amounts by applying the relevant percentage rate (if any) stated in the
appropriate Schedule. If there is no such rate, the percentage rate stated in the
Contract Data shall be applied.
(iii) The Contractor shall, when required by the Project Manager, produce
quotations, invoices, vouchers and accounts or receipts in substantiation.
(1) The Contract Price shall be paid as specified in the corresponding Terms and
Procedures of Payment Appendix to the Contract Agreement. The procedures to be
followed in making application for and processing payments shall be those outlined in
the same Appendix.
(2) No payment made by the Owner herein shall be deemed to constitute acceptance
by the Owner of the New Facility or any part thereof.
(3) In the event that the Owner fails to make any payment by its respective due date
or within the period set forth in the Contract, the Owner shall pay to the Contractor
interest on the amount of such delayed payment at the rate shown in the SCC and as
specified in the SCC for the period of delay until payment has been made in full,
whether before or after judgment or arbitrage award.
(4) The currency in which payments are made to the Contractor under this Contract
shall be specified in the SCC, subject to the general principle that payments will be
made in the currency or currencies in which the Contract Price has been stated in the
Contractor’s Bid.
(5) All payments shall be made in the currency or currencies specified in the
corresponding Terms and Procedures of Payment Appendix pursuant to GC Section
5.2(3).
If the Owner intends to pay the Contractor performance incentive compensation, the
Owner will pay such compensation at the end of the New Operations Period and in
accordance with the Performance Incentive Compensation Appendix.
5.5 Securities
(1) The Contractor and, if applicable, its Parent and Shareholders shall each provide
a security for the Contractor’s proper performance of the Contract to the Owner no
later than the date specified in the Bidding Documents (the “Performance Security”).
(3) The Performance Security shall be valid until 180 days after the End Date, or
any extension to the End Date or as stated in the SCC.
(4) The Owner shall return the Performance Security no later than 45 days after
completion of Design Built works and submission of performance security for
Operation and Maintenance or as stated in the SCC.
(5) The Owner shall return the performance security for operation and maintenance
in annual installments. The installments will be 10% of the security amount at the end
of first and second year each, 20% of the security amount at the end of third and fourth
year each and remaining at the end of fifth year. The rest of the performance security
will be relased after 180 days of completion of he O&M period.
(1) The Contractor shall provide a security in an amount equal to the advance
payment calculated in accordance with the Terms and Procedures of Payment
Appendix and in the same currency or currencies.
(2) The advance payment security shall be in the form provided in the
Bidding Documents or in another form approved by the Owner. The amount of the
advance payment security may be progressively reduced as provided for in the Terms
and Procedures of Payment Appendix. The advance payment security shall be returned
to the Contractor immediately after its expiration.
(1) Except as otherwise specifically provided in the Contract, the Contractor shall
bear and pay all taxes, duties, levies and charges (the “Taxes”) assessed on the
Contractor, its Subcontractors or their employees by all municipal, state or national
government authorities in connection with the Services in and outside of the Country.
(2) If any tax exemptions, reductions, allowances or privileges may be available to
Page 151 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
the Contractor/Owner in the Country, the Owner shall use reasonable efforts to enable
the Contractor to benefit from any such tax savings to the maximum allowable extent.
(Refer Declaration regarding customs/excise duty exemption for materials/
Construction equipment bought for the work)
D. INTELLECTUAL PROPERTY
(1) As between the Parties, the Owner shall retain the copyright and other
intellectual property rights in the Design-Build Documents made by or on behalf of the
Contractor.
(2) The Contractor shall be deemed, by signing the Contract, to give the Owner a
non-terminable, transferable, non-exclusive, royalty-free license to copy, use and
communicate the Design-Build Documents, including making and using modifications
of them. This license shall,
(a) apply throughout the actual or intended working life, whichever is longer, of the
relevant parts of the Site, Existing Facility or New Facility;
(b) entitle any person in proper possession of the relevant part of the Site, Existing
Facility or New Facility to copy, use and communicate the Design-Build Documents
for the purposes of completing, managing, operating, maintaining, altering, adjusting,
repairing and demolishing the Existing Facility or the New Facility;
(c) in the case of Design-Build Documents which are in the form of computer
programs and other software, permit their use on any computer on the Site, Existing
Facility or at the New Facility and other places as envisaged by the Contract, including
replacements of any computers supplied by the Contractor; and
(d) entitle the Owner to make the Design-Build Documents available for inspection
by a prospective Contractor who may be involved in the process to select a Subsequent
Contractor.
(3) The Contractor shall not, without the Owner’s consent, use, copy or
Page 153 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
communicate the Design-Build Documents to a Third Party by, or on behalf of, the
Owner for purposes other than those permitted under GC Section 6.1(2).
6.2 Confidentiality
(1) The Contractor shall keep confidential and shall not, without the written
consent of the Owner, divulge to any Third Party any documents, data or other
information arising directly or indirectly from the performance of Services under the
Contract, whether such information has been furnished prior to, during or following
termination of the Contract. Notwithstanding this GC Section 6.2(1), the Contractor
may furnish to its Subcontractors such documents, data and other information to the
extent required for the Subcontractors to perform their work under the Contract, in
which event the Contractor shall obtain from such Subcontractors an undertaking of
confidentiality similar to that imposed on the Contractor under this GC Section 6.2(1).
(2) The Contractor shall not use such documents, data and other information
received from the Owner for any purpose other than the Services as are required for
the performance of the Contract. The Contractor shall not publish, permit to be
published, or disclose any particulars of the Services, Site, Existing Facility or New
Facility in any trade or technical paper or advertising materials without the prior
written consent of the Owner.
(3) The obligations of the Contractor under GC Sections 6.2(1) and 6.2(2),
shall not apply to that information which,
(a) now or hereafter enters the public domain through no fault of the Contractor;
(b) can be proven to have been possessed by the Contractor at the time of disclosure
and which was not previously obtained, directly or indirectly, from the Owner; or
(c) otherwise lawfully becomes available to the Contractor from a Third Party that
has no obligation of confidentiality.
7.1 General
The Parties acknowledge that two separate approaches to contract administration and
supervision will be in place during the Contract Term as follows:
(a) from the Effective Date until the New Operations Starting Date, the
Design-Build Supervision approach will be put in place by the Owner; and
(b) from the New Operations Starting Date until the End Date, the Operations
Supervision approach will be put in place by the Owner.
7.2.1 Supervision During the Design-Build Period and O&M Period will be
done by Project Manager of PIU of MPUDC.
(1) The Owner shall appoint the Project Manager (PIU) who shall be
responsible for day to day contract management and supervision during the Contract
Period. The Project Manager’s staff shall include suitably qualified engineers and
other professionals who are competent to carry out these duties.
(2) The Project Manager shall have no authority to amend the Contract.
(4) If the Project Manager is obligated to obtain the approval of the Owner
before exercising a specific authority, these restrictions shall be set out in the SCC.
(b) the Project Manager has no authority to relieve any Party of any
duties, obligations or responsibilities under the Contract; and
(1) The Project Manager may from time to time assign duties and delegate
authority to assistants, and may also revoke such assignment or delegation. These
assistants may include a resident engineer, or independent inspectors appointed to
inspect or test items of Plant or Equipment. The assignment, delegation or revocation
shall be in writing and shall not take effect until copies have been received by both
Parties. Unless otherwise agreed by both Parties, the Project Manager shall not
delegate the authority to determine any matter in accordance with GC Section 7.2.6.
Page 156 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(2) Assistants shall be suitably qualified persons, who are competent to carry
out these duties and exercise this authority, and who are fluent in the language for
communications defined in GC Section 1.3.1.
(3) Each assistant, to whom duties have been assigned or authority has been
delegated, shall only be authorized to issue instructions to the Contractor to the extent
defined by the delegation. Any approval, check, certificate, consent, examination,
inspection, instruction, notice, proposal, request, test, or similar act by an assistant, in
accordance with the delegation, shall have the same effect as though the act had been
an act of the Project Manager. However,
(a) any failure to disapprove any work or Plant and Equipment shall not
constitute approval, and shall therefore not prejudice the right of the Project Manager
to reject the work or the Plant and Equipment; and
(1) The Project Manager may issue to the Contractor, at any time during the
Design-Build Period, instructions which may be necessary for the execution of the
Design-Build Services and the remedying of any defects, all in accordance with the
Contract. The Contractor shall only take instructions from the Project Manager, or
from an assistant to whom the appropriate authority has been delegated under GC
Section 7.2.3. If an instruction constitutes a Change, GC Section 10.1 shall apply.
(2) The Contractor shall comply with the instructions given by the Project
Manager or delegated assistant, on any matter related to the Contract. These
instructions shall be given in writing.
If the Owner intends to replace the Project Manager, the Owner shall, not less than 15
days before the intended date of replacement, give notice to the Contractor of the
name, address and relevant experience of the intended replacement Project Manager.
The Ownershall not replace the Project Manager with a person against whom the
Contractor raises reasonable objection by notice to the Owner, with supporting
particulars.
(1) Whenever the Contract provides that the Project Manager shall proceed in
accordance with this GC Section 7.2.6 to agree or determine any matter, the Project
Manager shall consult with each Party in an endeavour to reach agreement. If
agreement is not achieved, the Project Manager shall make a fair determination in
accordance with the Contract, taking due regard of all relevant circumstances.
(2) The Project Manager shall give notice to the Parties of each agreement or
determination, with supporting particulars. Each Party shall give effect to each
agreement or determination unless and until revised under GC Section 1.9.
F. REPRESENTATIVES
8.1 Representatives
(1) During the contract, the Owner’s Representative shall be the Project Manager of
respective Project Implementation Unit (hereinafter called “PIU”); and
(2) The Owner shall name its representative, no later than 14 days after the
Effective Date for the Design Build period;
(3) The Owner may change its representative from time to time and shall give
notice of the change without delay. The Owner shall not change its representative at a
time and in such a manner as to impede the progress of either the Design-Build
Services or the Operations Services.
(4) The Owner’s Representative shall represent and act for the Owner at all times
during the performance of the Contract. All notices, instructions, orders, certificates,
approvals and all other communications under the Contract by the Owner shall be
given by the PIU or theMPUDC, as applicable, except as herein otherwise provided.
(5) All notices, instructions, information and other communications given by the
Contractor to the Owner under the Contract shall be given to the PIU, except as herein
otherwise provided.
(1) If the Contractor’s representative is not named in the SCC, the Contractor
shall name its representative (the “Contractor’s Representative”) no later than 14 days
after the Effective Date and shall request the Owner to approve the proposed
Page 159 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(3) The Contractor’s Representative shall represent and act for the Contractor
at all times during the performance of the Contract. All notices, instructions, orders,
certificates, approvals and all other communications under the Contract by the
Contractor shall be given by the Contractor’s Representative, except as herein
otherwise provided.
(5) The Contractor shall not revoke the appointment of the Contractor’s
Representative without the Owner’s prior written consent, which shall not be
unreasonably withheld. If the Owner consents thereto, the Contractor shall appoint
some other person as the Contractor’s Representative, pursuant to the procedure set out
in this GC Section 8.1.2.
(7) Any act or exercise by any person of powers, functions and authorities so
delegated to him or her in accordance with GC Section 8.1.2(6) shall be deemed to be
an act or exercise by the Contractor’s Representative.
(1) Throughout the term of the Contract, the Contractor shall provide all
necessary superintendence to plan, arrange, direct, manage, inspect and test the
Services.
(1) The Contractor shall provide and employ on the Site for the performance of the
Services such skilled, semi-skilled and unskilled labour as is necessary for the proper
and timely execution of the Contract (the “Contractor’s Personnel”). The Contractor is
encouraged to use local labour that has the necessary skills. The Contractor shall
provide all expertise needed to carry out the Services including the expertise listed in
Page 161 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(2) Unless otherwise provided in the Contract, the Contractor shall be responsible
for the recruitment, employment, transportation, accommodation and catering of all
labour, local or expatriate, required for the execution of the Contract and for all
payments in connection therewith.
(3) The Contractor shall be responsible for obtaining all necessary permits from the
appropriate authorities for the entry of all labour and personnel to be employed on the
Site into the Country.
(4) The Contractor shall at its own expense provide the means of repatriation to all
of its and its Subcontractor’s personnel employed on the Contract at the Site to their
various home countries. It shall also provide suitable temporary maintenance of all
such persons from the cessation of their employment on the Contract to the date
programmed for their departure. In the event that the Contractor defaults in providing
such means of transportation and temporary maintenance, the Owner may provide the
same to such personnel and recover the cost of doing so from the Contractor.
(5) The Contractor shall at all times during the progress of the Contract use its best
endeavours to prevent any unlawful, riotous or disorderly conduct or behaviour by or
amongst its employees and the labour of its Subcontractors.
(6) The Contractor shall, in all dealings with its labour and the labour of its
Subcontractors currently employed on or connected with the Contract, pay due regard
to all recognized festivals, official holidays, religious or other customs and all local
laws and regulations pertaining to the employment of labour.
(7) The Contractor shall be well conversed with the Local Labour Laws and
shall obey all the provisions of it. Defiance of labour laws may cause penalty or even
blacklisting of the Contractor. The Contractor shall keep the Owner indemnified in
case any action is taken against the Owner by the competent authority on account of
contraventions including amendments. If the Owner is caused to pay or reimburse,
Page 162 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(1) The Contractor warrants that the Site and New Facility or any part thereof shall
be free from defects in the design, engineering, materials and workmanship of the
Plant and Equipment supplied and of the work executed.
(2) The Defect Liability Period shall be 12 months from the date of Operational
Acceptance of the New Facility unless specified otherwise in the SCC.
(3) If during the Defect Liability Period any defect should be found in the design,
engineering, materials and workmanship of the Site, New Facility or Plant and
Equipment supplied or of the work executed by the Contractor, the Contractor shall
promptly, in consultation and agreement with the Owner regarding appropriate
remedying of the defects, and at its cost, repair, replace or otherwise make good, as the
Contractor shall, at its discretion, determine, such defect as well as any damage to the
New Facility caused by such defect. The Contractor shall not be responsible for the
repair, replacement or making good of any defector of any damage to the New Facility
arising out of or resulting from normal wear and tear.
(4) The Contractor’s obligations under this GC Section 9.1 shall not apply to,
(5) The Owner shall give the Contractor a notice stating the nature of any such
defect together with all available evidence thereof, promptly following the discovery
thereof. The Owner shall give all reasonable opportunity for the Contractor to inspect
Page 164 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(6) The Owner shall give the Contractor all necessary access to the New Facility
and the Site to enable the Contractor to perform its obligations under this GC Section
9.1.
(7) The Contractor may, with the consent of the Owner, remove from the Site any
Plant and Equipment, Contractor’s Equipment (Design-Build) and Contractor’s
Equipment (Operations) or any part of the New Facility that are defective if the nature
of the defect, or any damage to the New Facility caused by the defect, is such that
repairs cannot be expeditiously carried out at the Site.
(8) If the repair, replacement or making good is of such a character that it may
affect the efficiency of the New Facility or any part thereof, the Owner may give to the
Contractor a notice requiring that tests of the defective part of the New Facility shall
be made by the Contractor immediately upon completion of such remedial work,
whereupon the Contractor shall carry out such tests.
(9) If such part fails the tests, the Contractor shall carry out further repair,
replacement or making good, as the case may be, until that part of the New Facility
passes such tests. The tests shall be agreed upon by the Owner and the Contractor.
(10) If the Contractor fails to commence the work necessary to remedy such defect or
any damage to the New Facility caused by such defect within a reasonable time, which
shall in no event be considered to be less than 15 days, the Owner may, following
notice to the Contractor, proceed to do such work, and the reasonable costs incurred by
the Owner in connection therewith shall be paid to the Owner by the Contractor or
may be deducted by the Owner from any monies due the Contractor or claimed under
the Performance Security.
(11) If the New Facility or any part thereof cannot be used by reason of such defect
or making good of such defect, the Defect Liability Period of the New Facility or such
part, as the case may be, shall be extended by a period equal to the period during
Page 165 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
which the New Facility or such part cannot be used by the Owner because of any of
the aforesaid reasons.
(12) Except as provided in GC Sections 9.1 and 9.5, the Contractor shall be under no
liability whatsoever and howsoever arising, and whether under the Contract or at law,
in respect of defects in the New Facility or any part thereof, the Plant and Equipment,
design or engineering or work executed that appear after Completion of the Site, the
New Facility or any part thereof, except where such defects are the result of the gross
negligence, fraud, criminal or willful action of the Contractor.
(13) The Contractor shall also provide an extended warranty for any such component
of the New Facility and during the period of time as may be specified in the SCC.
Such obligation shall be in addition to the Defect Liability Period specified under GC
Section 9.1(2).
(a) the Contractor shall not be liable to the Owner in contract, tort, or otherwise, for
any indirect or consequential loss or damage, loss of use, loss of production, or loss of
profits of interest costs, provided that this exclusion shall not apply to any obligation
of the Contractor to pay liquidated damages to the Owner; and
(b) the aggregate liability of the Contractor to the Owner, whether under the
Contract, in tort or otherwise, shall not exceed the aggregate of the total Contract Price
(including the Monthly Operations Payment times the original estimate of months
during the New Operations Period) and the total available Performance Incentive
Compensation, provided that this limitation shall not apply to any obligation of the
Contractor to indemnify the Owner with respect to patent infringement.
(1) Ownership of the Plant and Equipment, including spare parts, to be imported
into the Country shall be transferred to the Owner upon delivery at the Site.
(2) Ownership of the Plant and Equipment procured in the Country shall be
transferred to the Owner when the Plant and Equipment are brought on to the Site.
(3) Ownership of any Plant and Equipment in excess of the requirements of the
New Facility shall revert to the Contractor upon Completion of the New Facility or
such earlier time if the Owner and the Contractor agree that the Plant and Equipment
in question are no longer required for the New Facility.
(5) The Owner may, in its sole discretion, purchase as of the End Date any of
the Contractor’s Equipment (Operations), including spare parts, at the fair market
value of such Contractor’s Equipment (Operations) as determined by an independent
valuator and the Contractor shall transfer ownership and possession of such
Contractor’s Equipment (Operations) to the Owner as of the End Date.
(1) The Owner shall transfer the care, control and responsibility for all
existing equipment, materials, supplies and consumables, if any, used to operate and
maintain the Existing Facility (the “Existing Equipment and Materials”) to the
Page 167 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(3) The Contractor shall return all Existing Equipment and Materials on the
list, as updated, to the Owner on the End Date in the same condition as they were
transferred to the Contractor, except for reasonable wear and tear and at no cost to the
Owner.
(1) Except as provided in GC Sections 9.9 and 9.4(2), the Contractor shall be
responsible for the care and custody of the Site, Existing Facility and New Facility or
any part thereof until the End Date and shall make good at its own cost any loss or
damage that may occur to the Site, Existing Facility or New Facility from any cause
whatsoever during such period. The Contractor shall also be responsible for any loss or
damage to the Site, Existing Facility or New Facility caused by the Contractor or its
Subcontractors in the course of any work carried out, pursuant to GC Section 9.1.
(2) If any loss or damage occurs to the Site, Existing Facility or New Facility
or any part thereof by reason of,
(b) any use or occupation by the Owner or any Third Party, other than
Page 168 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
a Subcontractor, authorized by the Owner of any part of the Site, Existing Facility or
New Facility; or
(3) The Contractor shall be liable for any loss of or damage to any
Contractor’s Equipment (Design-Build), Contractor’s Equipment (Operations) or any
other property of the Contractor used or intended to be used for purposes of the Site,
Existing Facility or the New Facility, except where such loss or damage arises by
reason of any of the matters specified in GC Sections 9.4(2)(b) and 9.9.
(4) With respect to any loss or damage caused to the New Facility or any part
thereof, the Contractor’s Equipment (Design-Build) or the Contractor’s Equipment
(Operations) by reason of any of the matters specified in GC Section 9.9(1), the
provisions of GC Section 9.9(3) shall apply.
9.5 Indemnification
(1) Subject to GC Section 9.5(5), the Contractor shall indemnify and hold
harmless the Owner and its employees and officers from and against any and all suits,
actions or administrative proceedings, claims, demands, losses, damages, costs, and
Page 169 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(2) If any proceedings are brought or any claim is made against the Owner
that might subject the Contractor to liability under GC Section 9.5(1), the Owner shall
promptly give the Contractor a notice thereof and the Contractor may at its own
expense and in the Owner’s name conduct such proceedings or claim and any
negotiations for the settlement of any such proceedings or claim.
(3) If the Contractor fails to notify the Owner prior to the expiration of 30
days after receipt of a notice given pursuant to GC Section 9.5(2) that it intends to
conduct any such proceedings or claim, then the Owner shall be free to conduct the
same on its own behalf. Unless the Contractor has so failed to notify the Owner within
the 30 day period, the Owner shall make no admission that may be prejudicial to the
defense of any such proceedings or claim.
(4) The Owner shall, at the Contractor’s request, provide all available
assistance to the Contractor in conducting such proceedings or claim, and shall be
reimbursed by the Contractor for all reasonable expenses incurred in so doing.
(5) The Owner shall indemnify and hold harmless the Contractor and its
employees, officers and Subcontractors from any liability for loss of or damage to
property of the Owner that is caused by fire, explosion or any other perils, in excess of
the amount recoverable from insurances procured under GC Section 9.6, provided that
such fire, explosion or other perils were not caused by any act or omission of the
Contractor.
(6) The Party entitled to the benefit of an indemnity under this GC Section
9.5 shall take all reasonable measures to mitigate any loss or damage which has
Page 170 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
occurred. If the Party fails to take such measures, the other Party’s liabilities shall be
correspondingly reduced.
9.6 Insurance
(1) To the extent specified in the SCC, the Contractor shall, at its own
expense, take out and maintain in effect or cause to be taken out and maintained in
effect, during the performance of the Contract, the insurances set forth below in the
sums and with the deductibles and other conditions specified in the SCC. The
identityof the insurers and the form of the policies shall be subject to the prior approval
of the Owner who shall not unreasonably withhold such approval. The Contractor shall
submit appropriate certificates of insurance demonstrating that the Contractor has met
its obligations pursuant to this GC Section 9.6 to the Owner no later than the Effective
Date.
(2) The Owner shall be named as co-insured under all insurance policies taken out
by the Contractor pursuant to GC Section 9.6(1), except for the Third Party Liability,
Workers’ Compensation and Employer’s Liability Insurances, and the Contractor’s
Subcontractors shall be named as co-insureds under all insurance policies taken out by
the Contractor pursuant to GC Section 9.6(1), except for the Cargo Insurance During
Transport, Workers’ Compensation and Employer’s Liability Insurances. All insurers’
rights of subrogation against such co-insureds for losses or claims arising out of the
performance of the Contract shall be waived under such policies.
(3) The Contractor shall deliver to the Owner certificates of insurance, or copies of
the insurance policies, as evidence that the required policies are in full force and effect.
The certificates shall provide that no less than 21 days notice shall be given to the
Owner by insurers prior to cancellation or material modification of a policy.
(4) The Contractor shall ensure that, where applicable, the Subcontractors take out
and maintain in effect adequate insurance policies for their employees and vehicles
and for work executed by them under the Contract, unless such Subcontractors are
Page 172 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(5) If the Contractor fails to take out or maintain in effect the insurances referred to
in GC Section 9.6(1), the Owner may take out and maintain in effect any such
insurances and may from time to time deduct from any amount due the Contractor
under the Contract any premium that the Owner shall have paid to the insurer, or may
otherwise recover such amount as a debt due from the Contractor.
(6) Unless otherwise provided in the Contract, the Contractor shall prepare and
conduct all and any claims made under the policies effected by it pursuant to this GC
Section 9.6, and all monies payable by any insurers shall be paid to the Contractor.
The Owner shall give to the Contractor all such reasonable assistance as may be
required by the Contractor. With respect to insurance claims in which the Owner’s
interest is involved, the Contractor shall not give any release or make any compromise
with the insurer without the prior consent of the Owner.
(7) When each insurance premium has been paid, the Contractor shall submit a copy
of receipts to the Owner and shall notify the Owner’s Representative that it has done
so.
(8) The Contractor shall comply with the conditions stipulated in each of the
insurance policies. The Contractor shall make no material alteration to the terms of any
insurance without the prior approval of the Owner. If an insurer makes, or purports to
make, any such alteration, the Contractor shall notify the Owner immediately.
conditions and man-made and other physical obstructions and pollutants, which the
Contractor encounters at the Site when performing of the Design-Build Services,
including sub-surface and hydrological conditions but excluding climatic conditions.
(3) The Contractor’s Notice pursuant to GC Section 9.7(2) shall describe the
physical conditions, so that they can be inspected by the Project Manager, and shall set
out the reasons why the Contractor considers them to be Unforeseeable. The
Contractor shall continue performing the Design-Build Services, using such proper and
reasonable measures as are appropriate for the physical conditions, and shall comply
with any instructions which the Project Manager may give. If an instruction constitutes
a Change GC Section 10.1.3 shall apply.
(4) If and to the extent that the Contractor encounters physical conditions
which are Unforeseeable, gives the notice required by GC Section 9.7(2), and suffers
delay or incurs Cost due to these conditions, the Contractor shall be entitled subject to
GC Section 1.9 to,
(b) payment of any such Cost, which shall be included in the Contract
Price.
(5) After receiving such notice and inspecting or investigating these physical
conditions, the Project Manager shall proceed in accordance with GC Section 7.2.6 to
agree or determine,
(a) beyond the reasonable control of the Owner or of the Contractor, as the
case may be; and
(b) which is unavoidable notwithstanding the reasonable care of the Party
affected.
(2) Force Majeure shall include the events listed below in this GC Section 9.8(2) if
the conditions set out in GC Section 9.8(1)(a) and (b) are satisfied:
(3) If the Parties are prevented, hindered or delayed from or in performing any of
their obligations under the Contract by an event of Force Majeure, then it shall notify
the other in writing of the occurrence of such event and the circumstances thereof
within 14 days after the occurrence of such event.
(4) The Party who has given such notice shall be excused from the performance or
punctual performance of its obligations under the Contract for so long as the relevant
event of Force Majeure continues and to the extent that such Party’s performance is
prevented, hindered or delayed. The Time for Completion shall be extended in
accordance with GC Section 2.3.4(1) for events of Force Majeure during the Design-
Build Period. If the Time for Completion is extended in accordance with GC Section
2.3.4(1), the End Date shall be extended for a period of time equal to the period of
time during which the relevant event of Force Majeure continued.
(5) The Party or Parties affected by the event of Force Majeure shall use reasonable
efforts to mitigate the effect thereof upon its or their performance of the Contract and
to fulfill its or their obligations under the Contract, but without prejudice to either
Party’s right to terminate the Contract under GC Sections 9.8(7) and 9.9(6).
(8) In the event of termination pursuant to GC Section 9.8(7), the rights and
obligations of the Owner and the Contractor shall be as specified in GC Sections
11.2.1(2) and 11.2.2(1).
(9) Notwithstanding GC Section 9.8(6), Force Majeure shall not apply to any
obligation of the Owner to make payments to the Contractor herein.
(1) “War Risks” shall mean any event specified in GC Section 9.8(2)(a) and
(b) and any explosion or impact of any mine, bomb, shell, grenade or other projectile,
missile, munitions or explosive of war, occurring or existing in or near the Country.
Party; or
(c) injury or loss of life,
if such destruction, damage, injury or loss of life is caused by any War Risks, and the
Owner shall indemnify and hold the Contractor harmless from and against any and all
claims, liabilities, actions, lawsuits, damages, costs, charges or expenses arising in
consequence of or in connection with the same.
(3) If the Site, Existing Facility, New Facility or any Plant and Equipment,
Contractor’s Equipment (Design-Build), Contractor’s Equipment (Operations) or any
other property of the Contractor used or intended to be used for the purposes of the
Services sustains destruction or damage by reason of any War Risks, the Owner shall
pay the Contractor for,
(4) If the Owner does not require the Contractor to replace or make good any
such destruction or damage to the Site, Existing Facility or New Facility, the Owner
shall either request a Change in accordance with GC Section 10.1 excluding the
performance of that part of the Existing Facility or New Facility thereby destroyed or
damaged or, where the loss, destruction or damage affects a substantial part of the Site,
Existing Facility or New Facility, shall terminate the Contract, pursuant to GC Section
11.2.1.
(5) Notwithstanding anything contained in the Contract, the Owner shall pay
the Contractor for any increased Costs that are in any way attributable to, consequent
on, resulting from, or in any way connected with any War Risks, if the Contractor
notifies the Owner in writing of any such increased Cost as soon as practicable.
(6) If, during the term of the Contract, any War Risks occur that financially
or otherwise materially affect the execution of the Contract by the Contractor, the
Contractor shall use its reasonable efforts to execute the Contract with due and proper
consideration given to the safety of its and its Subcontractors’ personnel engaged in
the work on the Services. If the execution of the Services becomes impossible or is
substantially prevented for a single period of more than 60 days or an aggregate period
of more than 120 days on account of any War Risks, the Parties will attempt to
develop a mutually satisfactory solution, failing which either Party may terminate the
Contract by giving a notice to the other.
If, after a date which 30 days is prior to the Submission Deadline in the Bidding
Documents, in the Country, any law, regulation, ordinance, order or by-law having the
force of law is enacted, promulgated, abrogated or changed, which shall be deemed to
include any change in interpretation or application by the competent authorities, that
subsequently affects the costs and expenses of the Contractor or the Time for
Completion, the Contract Price shall be correspondingly increased or decreased, or the
Time for Completion shall be reasonably adjusted to the extent that the Contractor has
thereby been affected in the performance of any of its obligations under the Contract.
Notwithstanding the foregoing, such additional or reduced costs shall not be separately
paid or credited if the same has already been accounted for in the Contract Price
adjustment provisions where applicable, in accordance with the SCC.
The Contractor shall indemnify and hold harmless the Owner and its employees and
officers from and against any and all suits, actions or administrative proceedings,
claims, demands, losses, damages, costs, and expenses of whatsoever nature, including
attorney’s fees and expenses, which the Owner may suffer as a result of any
infringement or alleged infringement by the Contractor, Subcontractors, or their
employees, agents, or representatives, of any patent, utilitymodel, registered design,
trademark, copyright or other intellectual property right registered or otherwise
existing.
(1) If any proceedings are brought or any claim is made against the Owner
arising out of the matters referred to in GC Section 9.11.1, the Owner shall promptly
give the Contractor a notice thereof, and the Contractor may at its own expense and in
the Owner’s name conduct such proceedings or claim and any negotiations for the
settlement of any such proceedings or claim.
(2) If the Contractor fails to notify the Owner no later than 30 days after
receipt of such notice that it intends to conduct any such proceedings or claim, then the
Owner shall be free to conduct the same on its own behalf. Unless the Contractor has
so failed to notify the Owner no later than the 30 day period, the Owner shall make no
admission that may be prejudicial to the defense of any such proceedings or claim.
(3) The Owner shall, at the Contractor’s request, give all available assistance
to the Contractor in conducting such proceedings or claim, and shall be reimbursed by
the Contractor for all reasonable expenses incurred in so doing.
The Owner shall indemnify and hold harmless the Contractor and its employees,
officers and Subcontractors from and against any and all suits, actions or
administrative proceedings, claims, demands, losses, damages, costs, and expenses of
whatsoever nature, including attorney’s fees and expenses, which the Contractor may
suffer as a result of any infringement or alleged infringement by the Owner of any
patent, utility model, registered design, trademark, copyright or other intellectual
property right registered or otherwise existing at the Effective Date arising out of or in
connection with any design, data, drawing, specification, or other documents or
materials provided or designed by or on behalf of the Owner.
(1) The Contractor guarantees that during the Tests and Inspection set out in
DBSA Article 5, the New Facility and all parts thereof shall attain the Functional
Guarantees specified in Attachment 1 to the Technical Standards Appendix (the
“Functional Guarantees”), subject to and upon the conditions therein specified.
(2) If, for reasons attributable to the Contractor, the minimum level of the
Functional Guarantees are not met either in whole or in part, the Contractor shall at its
cost and expense make any such changes, modifications or additions to the New
Facility or any part thereof as may be necessary to meet at least the minimum level of
the Functional Guarantees. The Contractor shall notify the Owner upon completion of
the necessary changes, modifications or additions, and shall request the Owner to
repeat the applicable Tests and Inspection until the minimum level of the Functional
Guarantees has been met. If the Contractor eventually fails to meet the minimum level
of Functional Guarantees, the Owner may consider termination of the Contract,
pursuant to GC Section 11.2.3.
(3) If, for any reasons attributable to the Contractor, the Functional
Guarantees are not attained either in whole or in part, but the minimum level of the
Functional Guarantees is met, the Contractor shall, at the Contractor’s option, either
Page 181 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(a) make such changes, modifications or additions to the New Facility or any
part thereof that are necessary to attain the Functional Guarantees at its cost and
expense, and shall request the Owner to repeat the Tests and Inspection; or
(b) pay liquidated damages to the Employer in respect of the failure to meet
the Functional Guarantees in accordance with the provisions of SCC.
(1) Subject to GC Sections 10.1.2(6) and 10.1.2(10), the Owner shall have the
right to propose, and subsequently require, that the Project Manager order the
Contractor from time to time during the performance of the Contract to make any
change, modification, addition or deletion to, in or from the Design-Build Services (the
“Change”), provided that such Change falls within the general scope of the Design-
Build Services and does not constitute unrelated work and that it is technically
practicable, taking into account both the state of advancement of the Design-Build
Services and the technical compatibility of the Change envisaged with the nature of the
Design-Build Services as specified in the Contract.
(2) The Contractor may from time to time during its performance of the
Contract propose to the Owner, with a copy to the Project Manager, any Change that
the Contractor considers necessary or desirable to improve the quality, efficiency or
safety of the Design-Build Services. The Owner may at its discretion approve or reject
any Change proposed by the Contractor.
(4) The procedure on how to proceed with and execute Changes is specified
in GC Section 10.1.2 and 10.1.3, and the Project Manager shall provide Contractor
with further details and sample forms on the Change procedures prior to the Design-
Build Starting Date.
Page 183 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(2) Prior to preparing and submitting the Change Proposal, the Contractor
shall submit to the Project Manager an “Estimate for Change Proposal,” which shall be
an estimate of the cost of preparing and submitting the Change Proposal.
(3) Upon receipt of the Contractor’s Estimate for Change Proposal, the
Owner shall,
(b) advise the Contractor of any part of its Estimate for Change Proposal that
is unacceptable and request the Contractor to review its estimate; or
(c) advise the Contractor that the Owner does not intend to proceed with the
Change.
proceed with the preparation of the Change Proposal, in accordance with GC Section
10.1.2(1).
(6) If, before or during the preparation of the Change Proposal, it becomes apparent
that the aggregate effect of compliance therewith and with all other Change Orders that
have already become binding upon the Contractor under this GC Section 10.1 would
be to increase or decrease the Contract Price by more than 10 per cent, the Contractor
may give a written notice of objection thereto prior to furnishing the Change Proposal.
If the Owner accepts the Contractor’s objection, the Owner shall withdraw the
proposed Change and shall notify the Contractor in writing thereof.
(7) The Contractor’s failure to object pursuant to GC Section 10.1.2(6) shall neither
affect its right to object to any subsequent requested Changes or Change Orders herein,
nor affect its right to take into account, when making such subsequent objection, the
percentage increase or decrease in the Contract Price that any Change not objected to
by the Contractor represents.
(8) Upon receipt of the Change Proposal, the Owner and the Contractor shall
mutually agree upon all matters therein contained. No later than 14 days after such
agreement, the Owner shall, if it intends to proceed with the Change, issue the
Contractor with a Change Order.
(9) If the Owner decides not to proceed with the Change for whatever reason, it
shall notify the Contractor prior to the expiration of 14 days after the agreement on the
Change. Under such circumstances, the Contractor shall be entitled to reimbursement
of all costs reasonably incurred by it in the preparation of the Change Proposal,
provided that these do not exceed the amount given by the Contractor in its Estimate
for Change Proposal submitted in accordance with GC Section 10.1.2(2).
(10) If the Owner and the Contractor cannot reach agreement on the price for the
Page 185 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
Change, an equitable adjustment to the Time for Completion, or any other matters
identified in the Change Proposal, the Owner may nevertheless instruct the Contractor
to proceed with the Change by issue of a “Pending Agreement Change Order.”
(11) Upon receipt of a Pending Agreement Change Order, the Contractor shall
immediately proceed with effecting the Changes covered by such Order. The parties
shall thereafter attempt to reach agreement on the outstanding issues under the Change
Proposal.
(12) If the Parties cannot reach agreement prior to the expiration of 60 days after the
date of issue of the Pending Agreement Change Order, then the matter may be referred
to the Adjudicator in accordance with the provisions of GC Section 1.6.1.
11.1 Suspension
(1) The MPUDC, as applicable, by notice to the Contractor, can order the
Contractor to suspend performance of any or all of its obligations under the Contract.
Such notice shall specify the obligation of which performance is to be suspended, the
effective date of the suspension and the reasons therefor. The Contractor shall
thereupon suspend performance of such obligation, except those obligations necessary
for the care or preservation of the Site, Existing Facility or New Facility, until ordered
in writing to resume such performance by the MPUDC, as applicable.
(a) failed to pay the Contractor any sum due under the Contract within
the period specified in the Contract;
(b) failed to approve any invoice or supporting documents without just
cause under the Contract; or
(c) has committed a substantial breach of the Contract,
The Contractor may give a notice to the Owner that requires payment of such sum,
with interest thereon as stipulated in GC Section 5.2(3) requires approval of an invoice
or supporting documents, or specifies a breach and requires the Owner to remedy the
same, as the case may be.
(2) If the Owner fails to pay the sums required by the Contractor in
accordance with GC Section 11.1.2(1) or fails to remedy the breach or take steps to
remedy the breach no later than 14 days after receipt of the Contractor’s notice, then
the Contractor may, upon giving 14 days’ notice to the Owner, suspend performance
of all or any of its obligations under the Contract, or, in the case of the Design-Build
Services, reduce the Contractor’s rate of progress.
(3) If the Contractor is unable to carry out any of its obligations under the
Contract for any reason attributable to the Owner, including the Owner’s failure to
provide possession of or access to the Site or other areas in accordance with GC
Section 4.2, then the Contractor may, upon giving 14 days’ notice to the Owner,
suspend performance of all or any of its obligations under the Contract, or, in the case
of the Design-Build Services, reduce the Contractor’s rate of progress.
During the period of suspension, the Contractor shall not remove from the Site
or New Facility any Plant and Equipment, Contractor’s Equipment (Design-
Build), Contractor’s Equipment (Operations), or any part of the New Facility,
without the prior written consent of the Owner.
11.2 Termination
(1) The Owner may at any time terminate the Contract for any reason by
giving the Contractor a notice of termination that refers to this GC Section 11.2.1(1).
(a) the Contractor shall, either immediately or upon the date specified in the notice
of termination,
(i) cease all further work, except for such work as the Owner may specify in the
notice of termination for the sole purpose of protecting that part of the Facility already
executed, or any work required to leave the Site in a clean and safe condition;
(ii) terminate all Subcontracts; and
(iii) remove all Contractor’s Equipment (Design-Build) and, except if the Owner
asserts its rights pursuant to GC Section 9.3.1(5), Contractor’s Equipment (Operations)
from the Site, repatriate the Contractor’s Personnel and its Subcontractors’ personnel
from the Site, remove from the Site any wreckage, rubbish and debris of any kind, and
leave the whole of the Site in a clean and safe condition; and
(b) the Contractor, subject to the payment specified in GC Section 11.2.2, shall,
(i) deliver to the Owner the parts of the New Facility executed by the Contractor up
to the date of termination; and
(ii) deliver to the Owner all the Contract Records, including the Design-Build
Page 190 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(a) any portion of the Contract Price payable to the Contractor for Services
satisfactorily performed prior to the date of termination and calculated as set out in GC
Section 5.2;
(b) the Costs reasonably incurred by the Contractor in the removal of the
Contractor’s Equipment (Design-Build) and, except if the Owner asserts its rights
pursuant toGC Section 9.3.1(5), Contractor’s Equipment (Operations) from the Site
and in the repatriation of the Contractor’s Personnel and its Subcontractors’ personnel;
(d) the reasonable Costs incurred by the Contractor in protecting the Site, Existing
Facility and New Facility and leaving the Site in a clean and safe condition pursuant to
GC Section 11.2.1(2)(a)(i); and
(e) the reasonable Cost of satisfying all other obligations, commitments and claims
that the Contractor may in good faith have undertaken with Third Parties in connection
with the Contract and that are not covered by GC Section 11.2.2(1).
(2) The Contractor acknowledges that the only payments to be made to the
Contractor on termination by the Owner are set out in this GC Section 11.2.2. The
Contractor shall not make a claim for lost or foregone profits, revenues, consequential
damages or any other costs, damages, expenses or losses of any kind as a result of or in
Page 191 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(1) The Owner, without prejudice to any other rights or remedies it may
possess, may terminate the Contract forthwith in the following circumstances, by
giving a notice of termination and its reasons therefore to the Contractor, referring to
this GC Section 11.2.3(1):
b) has without valid reason failed to commence work on the Site, Existing
Facility or New Facility promptly or has suspended, other than pursuant
to GC Section 11.1.1(2), the progress of Contract performance for more
than 30 days after receiving a written instruction from the Owner to
proceed
c) persistently fails to carry out the Services in accordance with the Contract
or persistently neglects to carry out its obligations under the Contract
without just cause; or
d) refuses or is unable to provide sufficient materials, services, labour or
personnel to perform the Services
then the Owner may, without prejudice to any other rights it may possess under
the Contract, give a notice to the Contractor stating the nature of the default and
requiring the Contractor to remedy the same. If the Contractor fails to remedy or
to take steps to remedy the same within 14 days after its receipt of such notice,
then the Owner may terminate the Contract forthwith by giving a notice of
termination to the Contractor that refers to this GC Section 11.2.3(2)3) Upon
receipt of the notice of termination under GC Sections 11.2.3(1) or 11.2.3(2) the
Contractor shall, either immediately or upon such date as is specified in the
notice of termination,
i. cease all further work, except for such work as the Owner may
specify in the notice of termination for the sole purpose of protecting that
part of the Site, Existing Facility and New Facility already executed, or
any work required to leave the Site, Existing Facility and New Facility in a
clean and safe condition;
iii. deliver to the Owner the parts of the New Facility executed by the
Page 193 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
iv. deliver to the Owner all Contract Records, including the Design-
Build Documents, prepared by the Contractor or its Subcontractors as of
the date of termination
(3) The Owner may enter the New Facility and upon the Site, expel the Contractor,
and, if the New Facility is not completed, the Owner may complete the Facility
itself or by employing any Third Party at the risk and cost of the Contarctor .
The Owner may take over and use and with an indemnification by the Owner for
all liability including damage or injury to persons arising out of the Owner’s use
of such equipment, any Contractor's Equipment (Design-Build) and Contractor's
Equipment (Operations) owned by the Contractor and on the Site in connection
with the Existing Facility and New Facility for such reasonable period as the
Owner considers expedient for the completion of the New Facility. Upon
completion of the New Facility or at such earlier date as the Owner thinks
appropriate, the Owner shall give notice to the Contractor that such Contractor’s
Equipment (Design-Build) and, except if the Owner asserts its rights pursuant to
GC Section 9.3.1(5), Contractor’s Equipment (Operations) will be returned to
the Contractor at or near the Site and shall return such Contractor’s Equipment
(Design-Build) and Contractor’s Equipment (Operations) to the Contractor in
accordance with such notice. The Contractor shall thereafter without delay and
at its cost remove or arrange removal of the same from the Site.
(a) any portion of the Contract Price payable to the Contractor for
Services satisfactorily performed prior to the date of termination;
(b) the value of any unused or partially used Plant and Equipment on
the Site, except to the extent that such Plant and Equipment have already been paid for
Page 194 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(c) the Costs, if any, incurred by the Contractor in protecting the Site
and New Facility and in leaving the Site in a clean and safe condition pursuant to GC
Section 11.2.3(3)(a).
Any sums due the Owner from the Contractor accruing prior to the date of termination
shall be deducted from the amount to be paid to the Contractor under this Contract.
(i) if such excess is greater than the sums due the Contractor under GC
Section 11.2.4(1), the Contractor shall pay the balance to the Owner; or
(ii) if such excess is less than the sums due the Contractor under GC
Section 11.2.4(1), the Owner shall pay the balance to the Contractor.
(1) If,
(i) failed to pay the Contractor any sum due under the Contract
within the specified period, has failed to approve any invoice or supporting documents
Page 195 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
without just cause pursuant to the corresponding Terms and Procedures of Payment
Appendix, or commits a substantial breach of the Contract, the Contractor may give a
notice to the Owner that requires payment of such sum, with interest thereon as
stipulated in GC Section 5.2(3), requires approval of such invoice or supporting
documents, or specifies the breach and requires the Owner to remedy the same, as the
case may be; and
(ii) failed to pay such sum together with such interest, failed to
approve such invoice or supporting documents or give its reasons for withholding such
approval, failed to remedy the breach or take steps to remedy the breach no later than
14 days after receipt of the Contractor’s notice; or
(b) the Contractor is unable to carry out any of its obligations under the
Contract for any reason attributable to the Owner, including the Owner’s failure to
provide possession of or access to the Site or other areas,
then the Contractor may give a notice to the Owner thereof, and if the Owner has
failed to pay the outstanding sum, to approve the invoice or supporting documents, to
give its reasons for withholding such approval, or to remedy the breach no later than
30 days after receipt of such notice, or if the Contractor is still unable to carry out any
of its obligations under the Contract for any reason attributable to the Owner no later
than 30 days after receipt of the notice, the Contractor may, by a further notice to the
Owner referring to this GC Section 11.2.5(1), forthwith terminate the Contract.
(2) The Contractor may terminate the Contract forthwith by giving a notice to
the Owner to that effect, referring to this GC Section 11.2.5(2),
(i) cease all further work, except for such work as may be
necessary for the purpose of protecting that part of the Site, Existing Facility and New
Facility already executed, or any work required to leave the Site in a clean and safe
condition; and
(ii) terminate all Subcontracts; and
(i) deliver to the Owner the parts of the New Facility executed
by the Contractor up to the date of termination; and
If the Contract is terminated under GC Sections 11.2.5(1) or 11.2.5(2), the Owner shall
pay to the Contractor all payments specified in GC Section 11.2.2(1), and reasonable
compensation for all loss, except for loss of profit, or damage sustained by the
Contractor arising out of, in connection with or in consequence of such termination.
Page 197 of 553
GENERAL CONDITIONS FOR A CONTRACT (GCC)
(1) In this GC Section 11.2, the expression “New Facility executed” shall
include all work executed, Services provided, and all Plant and Equipment acquired, or
subject to a legally binding obligation to purchase by the Contractor and used or
intended to be used for the purpose of the performing the Services, up to and including
the date of termination.
(2) In this GC Section 11.2, in calculating any monies due from the Owner to
the Contractor, account shall be taken of,
(a) any sum previously paid by the Owner to the Contractor under the
Contract, including any advance payment paid pursuant to the Terms and Procedures
of Payment Appendix;
(b) any sum owing by the Contractor to the Owner under the Contract,
including Liquidated Damages – Delay or liquidated damages calculated pursuant to
GC Section 5.4
Appendix 1
FOR A CONTRACT
FOR
SURVEY, REVIEW THE DESIGNS, REDESIGN WHERE NECESSARY AND
BUILD WATER SUPPLY IMPROVEMENT SCHEME FOR KHARGONE
TOWN, KHARGONE DISTRICT OF MADHYA PRADESH AND OPERATE
AND MAINTAIN THE BUILT SYSTEM FOR 5 YEARS
The following Special Conditions of Contract (SCC) shall supplement the General
Conditions. Whenever there is a conflict, the provisions herein shall prevail over those
in the General Conditions. The corresponding article and section numbers of the
General Conditions are indicated in parentheses.
NA
NA
Upon termination or expiration of the Contract, the following rights and obligations of
the Parties survive:
(a) Such rights and obligations as may have accrued or to which the Parties
may be entitled on the date of termination, and any rights which a Party may have
under Applicable Law;
(c) The Contractor’s obligations with respect to Transition Assistance set out
in GC Section 2.4.2;
(d) The Parties’ rights and obligations with respect to copyright set out in GC
Section 6.1;
(f) The Parties’ rights and obligations with respect to defect liability set out
in GC Section 9.1; and
(g) The Parties’ rights and obligations with respect to indemnification set out
in GC Section 9.5.
Address : To be given after the selection of Adjudicator by the contractor from the
Page 201 of 553
Special Conditions of Contract (SCC)
panel of MPUDC.
If the Adjudicator has rendered its decision within the 30 day time limit, and no notice
of intention to commence arbitration has been given by either the Owner or the
Contractor prior to the expiration of 30 days after the reference of the dispute to the
Adjudicator, the Adjudicator’s decision shall become final and binding upon the
Owner and the Contractor. Any decision that has become final and binding shall be
implemented by the Parties forthwith.
The Adjudicator will be paid a fee of Rs. 5,000/- (Rs Five thousand only) per sitting
(per day)plus reimbursable expenses as on actuals.
10. Appointing Authority for New Adjudicator (GC Section 1.6.1(5))
All disputes arising in connection with the Contract shall be finally settled under the
M.P. Madhyastham Abhikaran Adhiniyam, 1983. The venue will be Bhopal, Madhya
Pradesh, India and arbitration shall be conducted in the language for communications
defined in GC Clause 1.3.1 [Language].
If the contract is with a foreign Contractor, disputes arising in connection with this
contract shall be finally settled under the arbitration rules of the United Nations
Commission on International Trade Law (UNICITRAL) by one or more arbitrators
Page 202 of 553
Special Conditions of Contract (SCC)
For the purposes of GC Section 2.1.2(a), the applicable date shall be 84 months after
the Effective Date.
The Design-Build Starting Date shall be no later than 30 days after the Effective Date.
The Contract shall come into force and be binding on the Parties from the date of its
execution (Effective Date). Provided that, the term of this Contract shall be deemed to
commence on the date when all the conditions precedent specified in this Clause 13
have been either satisfied or waived in accordance with the provisions hereof (Design
Build Starting Date).
a) provide a list of its key Design- Build staff, as identified in the Bid, being
available and ready to commence work in the Water Supply Area. The Key
Personnel as listed in Schedule 1.4 (H) may not be changed. However, in the
event that a change in a nominated Key Personnel is inevitable, this shall be
subject to the prior written approval of the MPUDC. Provided that, the person
who replaces any member of the Key Personnel shall have at least equivalent or
higher experience and qualifications as the original member of the Key
Personnel who is being so replaced.
13.1.2 Following are the Conditions Precedent to be fulfilled by the KNP and / or
MPUDC:
a) from the Effective Date, provide the Contractor access to the Water
Supply Area including all parts of the Existing Facility to facilitate the
The Design-Build Phase shall be completed within 24 months and Operations and
Maintenance Phase shall be for 60 months. The total Contract Period shall be for 84
months.
Page 204 of 553
Special Conditions of Contract (SCC)
In the event that the Contractor fails to complete the performance of the Design-Build
Services by the Time for Completion, the Contractor shall pay Liquidated Damages –
0.05% per day of each corresponding payment milestone based on the approved Work
Plan for Design-Build Phase.
The Maximum Liquidated Damages – maximum amount of liquidated damages for the
whole of the works is 10(ten) percent of final contract price.
The Contractor shall have the option of using Existing Facility to provide services as
per Contract.
a. Variation in quantity - The details given in the Detailed Project Report, are
based on surveys and investigations conducted by the owner. However, the Contractor
shall submit his bid after detailed assessment of site conditions and other related
conditions, especially for intake well, water treatment plant and Elevated Service
Reservoirs, and based on his own assessment th contractor shall confirm the quantities.
Hence, variation in quantities for any item shall not be admissible except for pipes.
However, in exceptional circumstances or due to change of scope or locations or other
Page 205 of 553
Special Conditions of Contract (SCC)
changes by the owner, after submission of the details by the Contractor, which will
have an impact on the price, variation may be considered. In such case, the
Independent Verification Team will verify the Contractor’s submission and a decision
based on the findings of the IVT will be taken by the Engineer-in-Chief, MPUDC.
b. Variation in quantities as mentioned in the price bid, beyond 10% for any type
of pipe diameter would be adjusted as per pre-determined rates provided in the bid
documents. Diameter of pipes as mentioned in the price bid will remain unchanged.
Pipe lengths would be measured.
The Contract Price adjustment provisions for Design-Build and Operations and
Maintenance phase are as per the Appendix 5.
For the purposes of GC Section 5.2(3) and the Terms and Procedures of Payment
Appendix, the interest rate that will apply to amounts owed in local currency, is 8%
percent per year for the period of delay until payment has been made in full. In case,
the owner has any objection on the bill, the owner shall ask for a clarification from the
Contractor within 10 days of receipt of the bill. The contractor shall reply within 7
days of receipt of such query from the owner. However, if the owner is not satisfied
with the reply, the owner shall notify the contractor within 7 days of receipt of the
answer.
(c) The Performance Security provided for Design and Build phase shall be
released no later than 45 days after the issuance of completion certificate of the
composite contract, and hold back amount pursuant to Clause 1.2 of Appendix–2 -
Terms and Procedures of Payment of Design Build phase shall be paid no later than 45
days after the expiry of the Defects Liability Period.
24. The Project Manager shall be the Project Manager of the Project Implementation
Unit of MPUDC (PIU) for the Contract period.
The PIU shall obtain the approval of the Owner before exercising its authority in the
following circumstances:
(a) approving assignment of the Contract, or any part thereof, under GC Section
1.7;
Page 207 of 553
Special Conditions of Contract (SCC)
(b) determining an extension of the Time for Completion under GC Section 2.3.4;
(c) certifying additional costs determined under GC Sections 1.9(8)(b) or 9.7; and
(d) issuing a Change Order under GC Section 10.1.2, except:
(i) in an emergency situation, as reasonably determined by the PIU; or
(ii) if such Change Order would increase the Contract Price by more than 1%.
Minimum cover shall be for replacement cost of assets. The Insurance policy shall be
Page 208 of 553
Special Conditions of Contract (SCC)
Appendix 2
FOR A CONTRACT
TO
Engineering College/IIT/NIT
(e) Design Review, Design of
pumps at Intake and WTP,
submission of design and drawings,
getting approval from Government
Engineering College/IIT/NIT
(f) Develop, up-date and maintain
calibrated strategic and DMA
distribution network models using
compatible software (EPANET,
Water CAD, etc.) and, in
accordance with the Specifications,
design / establish District Meter
Areas (DMAs) using the models,
any necessary additional Site
investigations to confirm pipe
condition, valve and pipe sizes,
valve locations; identify (under-
sized, incrustation) pipe
replacement requirements; prepare
and submit DMA design reports
3 Study of Billing System and Submission and Acceptance 365 days
5%
Development and Establishment of of draft report
Grievance Redress System Submission of Final Report 10% 455 days
After the establishment of 730 days
70%
Management Part in total
After successful running for 6 910 days
15%
months
Total 100%
4 (a) Approach Road On completion 100% 620 days
(b) Site Development Works On completion 100% 620 days
5 Raw water intake System After completing foundation 35% 210
comprising of and well steining up-to
(a) Raw water intake System discharge floor level
comprising of RCC 8 M Dia 12 M After construction of R.C.C. 15% 300
High (indicative size) with foot foot bridge and discharge
bridge including 5.5 m ht above floor
floor level constructed over Intake After completing pump house 20% 360
per actual
After submission of Noise 100%
Quality Monitoring report as
per actual
Implementation of EMP Pro rata
excluding the above items basis
(S.No. 1 to 4 of Bill No. 12)
12 Rehabilitation of existing ESRs and Rehabilitation as required 510 days
60%
pipelines based on status assessment
(All works of rehabilitation have to On integrating with existing 620 days
20%
be treated as one package) system
After successful 730 days
20%
commissioning and testing
Total 100%
(b) The Project Manager shall check the details given in the Contractor’s invoice by
following MPUDC’s procedures such as measurements, check measurements,
approving deviations etc. and certify such invoices for payment within 15 days of their
receipt. The Project Manager will certify the amounts to be paid to the Contractor after
making deductions on account of advance payments, recoveries, Hold back, liquidated
damages-delay, and other adjustments in terms of the contract and deduction of taxes
at source, as applicable under the law. However, the Project Manager of PIU shall take
the opinion of the PMC and IVT before certifying the amounts to be paid to contractor.
Payment against the certified invoice shall be made by the owner no later than 45 days
after receipt of such certified invoice from the Contractor. In the event that the owner
fails to make any payment by its respective due date the owner shall pay to the
Contractor interest on the account of such delayed payment at the rate shown in the
SCC for the period of delay until payment has been made in full.
NOTE: In case, the contractor does not comply with the requirements of EMP, he shall
be issued a written warning by the Project Manager, and he shall be under obligation
to comply the required EMP safeguards within 7 days of the issuance of such warning.
However, if the contractor fails to comply, a penalty of an amount equal to the cost of
Page 225 of 553
Terms & Procedures of Payments
EMP safeguards, which have not been complied with,shall be levied on the contractor.
Payment against delivery of non-perishable materials (pipes, pumps, motors, starters,
cables, electric panels etc.) brought to site will be limited, in accordance with the
payment schedule provided above, to 60% of invoice value or market value whichever
is lower and will be subject to following conditions:
1. The quantities of materials are not excessive and shall be certified by the
Contractor to be utilized within a reasonable time (not exceeding 3 months).
2. The materials are in accordance with the requirement and technical
specifications.
3. The materials have been delivered to site and are properly stored and protected
against damage or deterioration to the satisfaction of the owner.
4. The Contractor’s records of the requirement, orders, receipt and use of materials
are kept in a form approved by the owner and such records shall be available for
inspection by the owner.
5. Ownership of such materials shall be deemed to vest in the owner for which the
Contractor shall submit an indemnity bond in a format provided by the owner.
6. The payments for Pipe work shall be made on pro-rata basis.
Any such material that is unlikely to be utilized for the design build services will be
taken back by the Contractor after the owner has adjusted the payment already made
for such materials from the invoice(s) submitted by the Contractor.The amounts to be
paid to the Contractor during the Design-Build Period in accordance with Section I(C)
of this Terms and Procedures of Payment Appendix shall include all costs and
expenses of the Contractor in building the New Facility and providing the Design-
Build Services, including all costs and expenses relating to the Plant and Equipment.
The Owner shall deduct from each payment to the Contractor a Retention Money in
the amount of 5 (five) percent of each payment to the Contractor. The Retention
Money amount may be released to the Contractor, subject to the Contractor furnishing
an irrevocable Bank Guarantee from the nationalized Bank equivalent to the Retention
Money amount. The Owner shall pay the amounts held back no later than 45 days after
Page 226 of 553
Terms & Procedures of Payments
The procedures to be followed in applying for certification and making payments shall
beas follows:
During the Design-Build Period, payment shall be dealt with in accordance with
Section I(C), and
During the total Operations and maintenance Period, the Contractor shall deliver an
invoice quarterly and no later than 15 days after the end of the quarter to which the
invoice applies, along with supporting documents to the MPUDC as specified below:
(a): a statement of performance for every month of the quarter for which the payment
is sought, in duplicate addressed to the MPUDC, (with an additional copy to the
BMC), along-with supporting evidence of achievement of Performance Standards and
records of billing, for the period for which Contractor Fee is sought;
The MPUDC shall require the PMC to validate the achievement of Performance
Standards submitted by the Contractor. For this purpose, the PMC shall submit to the
MPUDC, a certification validating the achievement of the Performance Standards
within fifteen days of submission of invoices by the Contractor. Only upon receiving
such certification from the PMC, the MPUDC will determine and intimate the
Contractor of the amount to be paid to the Contrator.
The MPUDC agrees to make the payments within 45 (forty five) days of submission of
the invoice along with all requisite documents, by the Contractor. In case of delays in
payment beyond such 45 (forty five) days, the Contractor will be entitled to charge
interest at the rate of 8 % per annum (max) on the outstanding amount for the period
exceeding 45 days (net of disputed claims, if any).
DESIGN-BUILD SERVICES
FOR A CONTRACT
DESIGN-BUILD SERVICES
FOR A CONTRACT
Table of Contents
3A(1) Introduction
1.1 Kind and Scope of Work
1.2 Design and Build
1.3 Operation and Maintenance
1.4 Technical Documentation
1.5 Appointment of Independent Verification Team
The Contractor is to undertake review of designs, design (as needed), build, operate
and maintain a complete and fully functioning water supply system in the Water
Supply Area in accordance with the Bid Documents.
The obligations of the Contractor shall be regulated by the Design Build Agreement
and Operation and Maintenance Agreement for the Water Supply Area, of which the
present Technical Specifications form an integral part
The scope of work of the Contractor during the Design Build Period shall include the
following activities:
• Carry out an assessment of the existing customer data base, Undertake a door-
to-door household survey, covering all households in the Water Supply Area to
validate the existing customer data, assess the potential customers and customer
connections within the Water Supply Area, including their existing water supply
arrangements; plot the consolidated customer data obtained through the survey
on the GIS based map (below). Also develop an updated registry of customer
connections, to serve as a base for further updation
• Carry out an assessment of the existing billing system and management
reporting arrangements. Suggest areas of improvement to establish a system for
efficient bill generation, and develop a financial management information
system;
• Study the existing Customer Grievance Redressal system and propose process
improvements required (including appropriate software) to
(a): enable redressal of complaints within the time period specified in OMSA
(b): enable on-line and integrated monitoring of all complaints registered
through Customer Service Centers, call center and web-based system. The
system should be operationalized at start of the Operations and Maintenance
Period. Where required, the Contractor will also have to integrate into any
existing web based customer service system of the Authority or of other
Governments. The Contractor will allow MPUDC real time access to the system
to monitor and track the status of complaints and their redressal.
• Carry out detailed condition assessment of existing infrastructure to decide the
elements which can be viably integrated with the newly designed system and
• Prepare operations and maintenance manuals for the regular and preventive
maintenance of all components of the water supply system and submit for
approval by MPUDC;
• Carry out Tests on Completion and Tests after Completion and commission the
works;
• Provide spare parts for all components of the Water Supply System as required
and all items of equipment including filter media and other accessories; as well
as required parts, lubricants and tools for routine maintenance
• Study existing billing system, suggest areas of improvement, and develop a
financial management information system and a system for efficient bill
generation;
• Ensure and implement the Environmental and Social Management Plant
provided in Annex H, relevant safeguard policies, environment, health and
safety guide lines of The World Bank, Indian and State Government Laws,
Rules, Regulations and Guidelines
• Exact siting of the structures and laying of pipes shall be finalized by the
D(R)BO contractor and DPR shall be revised accordingly. Due to excavation
works for laying of pipes, minor damage to road side properties and loss of
income for certain days and locations are likely during construction phase.
During the review and finalization of DPR, impacts on roadside properties and
loss of income would be assessed and the respective ESA and ESMP will be
updated by D(R)BO contractor based on joint verification with the affected
party and PIU representative. Contractor shall seek approval of updated ESA
and ESMP from MPUDC along with the final DPR. Excavation works for the
specific section shall be initiated only after disbursement of entitlements as per
Resettlement Policy Framework in the ESMF.
manner that minimum number of disruptions as well as the least possible period of
disruption can be achieved.
c) The PIU will help the KNP to prepare an emergency action plan in case of a sudden
disruption. The PIU will also get an action plan from KNP for water supply during
disruptions.
d) In the event of any disruption, KNP shall make alternative arrangement for
continuity of water supply services to Customers.
The design, construction, operation and maintenance of the water supply system shall
be executed in compliance with international best practice and all relevant Indian
legislation.
1.2 Design and Build (Part A)
The Contractor shall be responsible (MPUDC shall facilitate) for the provision of all
relevant permits necessary for construction, the preparation of detailed design and the
construction of the components as defined in the attached Design Build Specifications
(Appendix 3A)
The design and construction of the water supply system shall facilitate future
expansion of the system as the population of the water supply area grows.
The Contractor shall be responsible for the operation and maintenance of the water
supply system as described in the Operations and Maintenance Agreement
• The Operation and Maintenance Services Agreement for the Contractor in the
Water Supply Area with Annexes (Appendix 3B);
• The Contractor’s Technical Proposal on Operation and Maintenance (using the
forms attached as Annex A).
The Contractor shall have familiarized himself with:
• The project area and present water supply (as briefly described in Appendix 4
and supplemented by the Contractors own investigations);
• The Institutional and Financial Arrangements for the Project;
Page 235 of 553
Technical Specifications
2.1.1 General
1 The Contractor shall execute the basic and detailed design of the Project and the
engineering work in respect of that design in compliance with the provisions of the
Contract, or where not so specified, in accordance with good engineering practice.
2 The Contractor shall be responsible for any discrepancies, errors or omissions in
the specifications, drawings and other technical documents that it has prepared,
whether such specifications, drawings and other documents have been approved by the
Project Manager or not.
3 The Contractor shall make their own investigations as deemed necessary to ensure
that the design is adequate for meeting the specifications and shall have full
responsibility for any design, data, drawing, specification or other document,
developed by the Contractor. The Contractor shall be entitled to disclaim any
modification thereof provided or designated by or on behalf of the Owner, by giving a
written notice of such disclaimer to the Project Manager.
2.1.1.2 Key Staff
The Contractor shall provide all expertise needed to carry out the Design Build
services including the key staff as specified in the BDS.
In case the Contractor intends to change the any key staff, such change will be subject
to approval from the owner on justification provided by the Contractor. The proposed
replacement shall have to be of equivalent or higher qualification and experience
specified above for the respective key staff.
2.1.1.3 Design Responsibilities
The Contractor’s design and design-related services shall include:
1. The preparation of a design that meets the criteria set forth in the Design-Build
Documents and that provides for a Water Supply System that meets or exceeds the
Technical Standards;
2. The acquisition of all data and information necessary to prepare the design and
that are required to demonstrate that the Water Supply System meets or exceeds the
Technical Standards;
3. The preparation of schematic design documents to illustrate the scale and
character of the Design-Build Services and how the parts of the Design-Build Services
functionally relate to each other.
4. Estimate design water demand based on existing population given in Appendix
C and population projection rate for the service area
5. The preparation of a design report, based on the schematic design documents
submitted in the Contractor's tender and accepted by the Owner, consisting of
drawings and other documents appropriate to the Project to describe the size and
character of the entire utility and the Water Supply System including architectural,
mechanical, civil works, and electrical systems, materials, operational processes,
landscaping, and such other elements as may be appropriate;
6. The preparation of Design-Build Documents setting forth in detail the
requirements for construction based on the design development documents accepted
by the Owner;
7. Obtaining all approvals, permits, including building permits, and licenses for the
Design-Build Services, except for those approvals, permits or licenses that the Owner
is explicitly required to obtain itself under the Applicable Law in which case the
Contractor shall prepare all documentation and provide assistance to the Owner in
obtaining such approval, permits or licenses;
8. The preparation of assurances required to regulatory authorities respecting
conformance of the design with the applicable building regulations, environmental
standards and occupational health and safety requirements, including construction
safety issues;
9. The coordination required to integrate all parts of the Design-Build Services;
10. Such other Design-Build Services that may be required from time to time that
are agreed to by the Contractor and the Owner in writing; and
11. The conducting of general reviews of the progress of the design process, to the
extent necessary, in order to determine to the Contractor’s satisfaction that the design
services are performed in compliance with the requirements of the Contract and
Applicable Laws.
2.1.1.4 Design Build Documents
1. The Contractor shall prepare all of the Design-Build Documents. The Design-
Build Documents shall include the survey sheets, plans, designs, drawings, detailed list
of requirements, as-built documents, operations manuals, specifications, schematic
design documents, design development documents, and all modifications thereto
required in order to properly and fully test for, analyze for, plan, design and build the
Project as contemplated in the Technical Standards and the remaining provisions of the
Contract.
2. The Design-Build documents to be prepared by the Contractor shall adhere to
the EMP given at Annexure H and the recommendations of Environment Social
Assessment (available on www.mpudc.co.in and mpurban.gov.in). However, the
contractor shall also review the environmental and social management plans and
suggest improvements, as required according to the Environmental and Social
Framework of MPUDP, Indian legislation and World Bank guidelines.
3. The Design Build Documents specially the pipe line laying, to be prepared by
the contractor shall clearly identify and mention the structures, their nature and
ownership, that may be affected, if any, during theconstruction period. The contractor
is also required to assess the type of damage, if any, to the structure and prepare
Resettlement Action Plan for the same, in consultation with the Project Manager. The
Project Manager shall appoint the Community Development Officer of the PIU for this
purpose.
4. The Contractor shall prepare any other document, as may be requested by the
Project Manager, that the Project Manager considers necessary to monitor the progress
of the Design-Build Services and assess the Contractor’s compliance with the
Contract.
5. The Contractor shall also prepare any other documents necessary to instruct the
Contractor’s Personnel.
6. The Contractor shall provide each of the Project Manager and the Owner with
two sets of all of the Design-Build Documents in reproducible form and shall modify
permit, state and protection of the intake box); indicative information concerning water
quality of the proposed water resource is provided in Annexure Bto this Specification.
- Any other source with required information as for other sources.
2. Through detailed topographic/cadastral surveys for project sites, as required for
detailed design, ensure that the water production and distribution facilities can be
designed to operate properly, and so that quantities of work and materials required can
be accurately determined.
3. Field Survey:as detailed in appendix 3A(3)
4. Field Survey Details:as detailed in appendix 3A(3)
5. Preparation of Maps and drawings:as detailed in appendix 3A(3)
project.
6. Storage (clear water sumps, elevated service reservoirs) will be generally
designed for the intermediate Term (2033) Horizon.
7. Process design of water Treatment Plant shall be done as per the design criteria
contained in the Manual on Water Supply and Treatment, published by Ministry of
Urban Development, Government of India. The quality of the treated water reaching
the customer shall fulfill requirements of guidelines for potable water in compliance
with the Indian Standard Specifications for Drinking Water IS:10500: 1992 (latest
revision or update).
8. Raw water and treated water transmission mains shall be designed for the Long
Term (2048) Horizon to cover the demand.
9. Distribution systems shall be designed using peak factor as applicable to the
Long Term (2048) Horizon to cover peak demand.
10. Distribution system piping shall be of such construction and quality that
disinfectant applied at the treatment facility is retained to the furthest points of the
distribution system. The chlorine level at any customer outlets shall be in the range of
0.2 ppm.
11. The water pressure at any customer premises within the supply area depends of
the number of storeys in the buildings, as specified in the Indian manual on water
supply and treatment. However, no parts of the distributions system should have less
pressure than 12 meters. Night time pressures shall not exceed the upper limit of the
manufacturer’s recommendations for the materials used in the system.
12. The quantity of water available at customer level shall be sufficient to satisfy the
peak hour demand, based on peak as given in Indian manual on water supply and
treatment, based on average water demand as given below or such other figure that
shall be established for the particular water supply area by the Owner.
13. The average daily demand is: 135 litres/person
14. Meters of appropriate capacity and rating shall as a minimum be provided at:
- Headwork outlet;
- Outlet of all service reservoirs;
- Individual customer connections
- District Metered Areas
- Any places considered necessary for the Contractor's operation of the water
project.
15. The Contractor shall aim at 24/7 water supply. The Contractor shall design the
entire water supply system as per applicable standards including Indian Manual on
Water Supply and Treatment. The Contractor shall further design the entire system for
extra 15% of the design demand to compensate for all physical losses in the
production, treatment and distribution network.
2.3 Design of Works
1. The Contractor shall, as the first task, prepare a time schedule for the entire
Design-Build period clearly showing submission of Construction Documents to the
Project Manager for review to conform to the Schedule of Works and submission dates
of the various stages.
2. The Contractor shall submit his Works preliminary design as a complete
package for the review, comment, amendment of the Project Manager. The Project
Manager shall agree to the design and drawings after such review. Any changes shall
be discussed and agreed between the Contractor and the Project Manager before the
Contractor proceeds with the works. As a minimum, the preliminary design documents
and drawings shall cover the topics and items that follow.
a) The system installed during the design build period shall provide connections to
serve the population of the KNP area in accordance with the requirements of the
Operations and Maintenance Contract.
b) The design of the system shall clearly show the number of connections served
and its relation to current and projected population and water demand of the system.
c) The Contractor shall calculate the physical sizes of the components to suit the
design water demand.
d) Under the above field survey and the preliminary design period the Contractor
shalldesign the anicut and intake with required capacity. The Contractor shall in his
design assess the necessity of the inclusion of sand traps.
e) The Contractor shall design a new water treatment plant to secure treated water
fulfilling standards given in Government of India’s Manual on water supply and
treatment. The design shall include a clear description of all proposed treatment units
and include a process flow diagrams for the whole Plant showing capacities flow rates,
Layout of component structures, details of treatment process adopted by confirming
raw water quality parameters, analysis of terminal head at end point of Water
Distribution Network and a hydraulic analysis of the Plant under low, normal and high
operating flows; The process design of treatment plant shall have provision for
recirculation of filter backwash water after settling the sludge and disposal of sludge.
f) The Contractor shall investigate the location and assure capacity of storage
requirements and the capacity of elevated service reservoir(s), as given in the DPR.
Location of ESR shall ensure required terminal pressures at all households served by
the ESR. Support the design with calculations of the diurnal demand for water to
determine the reservoir sizes to meet the demand.
g) Double flanged DI K9/CI (LA)pipe shall be used for connections in ESR. Float
type /ultrasonic Water level indicator will be provided. Stairs to go up will be in RCC
dog legged with railings. Stairs to enter ESR will be in aluminium.
h) The distribution systems shall be designed as a network with redundant links to
ensure as far as possible that supplies to customers are interrupted for a minimum time
when maintenance work is done. The system design must ensure that the output
performance criteria can be consistently met throughout the system. Wherever required
separate zones or separate feeders shall be proposed to ensure equitable distribution of
water to all households served by the ESR.
i) Type of valves: (a) Gate valves will be used for Online Control (b) Sluice
Valves for Control of Inlet to ESRs and Control on Branches; (c) Air Valves
conforming to IS 14845; (d) Pressure Reducing Valves will be used to reduce pressure,
and (e) Dismantling joints will be provided for all Meters Gate valves and BF valves.
j) Hydraulic design shall be carried out to ensure that the most cost effective
balance is reached between initial cost and operational and energy costs and include as
a minimum:
i) Hydraulic design calculations for the whole of the Plant from Intake to the
distribution pipelines and to the customers, including friction losses for all pipelines,
fittings, storage and pumping facilities.
ii) Process design of water treatment plant shall be done as per the design criteria
laid down in the Manual on Water supply and Treatment, published by Ministry of
Urban development, Government of India.
iii) NPSH calculations for pumps, and maximum and minimum system curves
referred to pump characteristic curves. The system curve envelopes shall be used to
determine pump duty requirements for the design flow ranges. This section is only
valid in case of modifications of the raw water pumping station or if service is
provided to new areas requiring pumping.
iv) Surge Analysis designs and reports on proposed piping layouts and surge
suppression installations where required.
v) The overall operation of the designed network will be checked using a
numerical modelling tool for 2018, 2033 and 2048 horizons. The tool should be
acceptable to the Project Manager.
k) Mechanical and electrical drawings, schedules and calculations as follows:
i) General arrangement drawings and sectional views, fully dimensioned and
showing all mechanical, electrical equipment together with relevant Schedules.
ii) Electrical single line diagrams and general arrangement drawings for all
switchboards, motor control centers and control panels.
iii) Process and instrumentation diagrams for each section of the Plant together with
full supporting Schedules.
l) Civil and Building Works drawings, schedules and calculations as follows:
i. Anicut
ii. Intake Facilities;
iii. Treatment Plant and Storage and Transmission pumping facilities;
iv. Elevated Service Reservoirs;
v. Distribution System;
vi. Additional Pumping stations;
vii. House connections and metering facilities;
viii. General arrangement drawings and sectional views fully annotated and
dimensioned, for all structures and buildings.
m) SCADA drawings and diagrams:
The Contractor shall as a minimum design and implement SCADA for monitoring of
water meters and operation of attached valves installed with actuators for automatic
operation. Brief description of SCADA to be provided is given below:
(i) To ensure equitable distribution of water SCADA will be provided to control
and measure flow at ESRs and communicate to control center, and pressure
control at critical junctures. The system is designed for ultimate flows and has
to serve the present demand which will progressively increase. The hydraulic
design done for ultimate demand is to be checked for residual heads for present
demand and intermediate demand also. The residual heads (pressures) are also
to be regulated and need to be adjusted for progressive changes in demand. The
inflow into ESRs has to be controlled to the required rate of flow and also to
control the cumulative flow. When the ESRs overflow the level is to be sensed
and the flow into ESR is to be stopped. To achieve this control of inflow into
the ESR with manual operations is infeasible and not desirable. It is necessary
to provide flow and level measurement and control device. Pressure control
devices will have to be installed at critical points in the distribution network.
Apart from the above the flow measurement also helps in analyzing the water
losses and water auditing in the system. The availability of dependable quality
power is always an issue which affects the performance of the control devices.
(ii) Main Components of Flow and pressure measurement and controls are:
Ultrasonic Level (ESR) Sensor and Transmitter, Pressure Sensor and
Transmitter and pressure reducing valve if required, Turbine flow meter with
signal generation, Valve Actuator MotorValve Actuator Drive (MOV),
Programmable Logic Controller/Remote Terminal Unit, Battery power Backup
system including for Motor actuator and with solar back up.
(iii) The flow and pressure are monitored through the flow measured device and it
will be transmitted to RTU. When the flow varies from the set point of flow
then the MOV will operate by automatic command from the RTU to regulate
and achieve the required design flow at inlet of the ESR. The level in the ESR
will be monitored and transmitted to RTU. When the maximum water level
reaches in the ESR MOV at inlet will close by automatic command from RTU.
When the water level falls below maximum water level in the ESR MOV at
inlet will open by automatic command from RTU. The battery back-up system
is required with charger facility with minimum 24 hour battery back-up and
Solar Connectivity enabled.
6. The cost of constructing labour camps at site is the responsibility of the contractor
and no extra cost shall be part of the bid.
Completion.
2.5 Building Responsibilities
1. The Contractor shall have the sole responsibility for the design, erection,
operation, maintenance, and removal of temporary supports, structures and utility
services and the design and execution of construction methods required in their use.
2. The Contractor shall engage and pay for registered professional engineering
personnel skilled in the appropriate disciplines to perform those functions referred to
in Point 1 where required by law or by the Design-Build Documents and in all cases
where such temporary supports, structures and utility services and their designs and
method of construction are of such a nature that professional engineeringskill is
required to produce safe and satisfactory results.
2.5.2 Document Review
The Contractor shall be responsible for all approvals and permits of the Design-Build
Documents of the present specification. If the Contractor during the course of the
construction does discover any error, inconsistency or omission in the Design-Build
Documents, the Contractor shall not proceed with the work affected until the
Contractor has corrected any such errors or inconsistency or supplied any missing
information and these corrections have been approved in writing by the Project
Manager or the Owner.
2.5.3 Plant and Equipment
1. The Contractor shall provide and pay for labour, Plant and Equipment, tools,
construction machinery and equipment, materials and supplies, water, heat, light,
power, transportation, and all other facilities and services necessary for the
performance of the Design-Build Services in accordance with the Design-Build
Documents.
2. The Contractor shall ensure that all Plant and Equipment provided are new.
Plant and Equipment which are not specified shall be of a quality consistent with those
specified and their use shall be acceptable to the Project Manager.
2.5.4 Documents at the Site
The Contractor shall keep site order book, one copy of the Design-Build Documents as
up-dated, submittals, reports and records of meetings at the Site, in good order and
shall make them available to the Owner and the Project Manager and IVT or any
person authorized by the owner, upon request and at any reasonable time.
2.5.5 Use of the Sites and Water Supply System
1. The Contractor shall confine construction machinery and equipment, storage of
Plant and Equipment, Contractor’s Equipment (Design-Build) and Contractor’s
Equipment (Operations), and operations of Contractor’s Personnel to limits indicated
by laws, ordinances, permits or the Design-Build Documents and shall not
unreasonably encumber the Site with Plant and Equipment, Contractor’s Equipment
(Design-Build) or Contractor’s Equipment (Operations). The Contractor shall not load
or permit to be loaded any of the working areas or the Water Supply System with a
weight or force that will endanger the safety of the areas or the Water Supply System.
2. The Contractor shall not store Plant and Equipment, Contractor’s Equipment
(Design-Build) or Contractor’s Equipment (Operations) at the working areas which are
not necessary for the construction of the Project.
2.5.6 Setting Out
1. The Contractor shall be responsible for the true and proper setting-out of the
Sites and the Project in relation to benchmarks, reference marks and lines specified in
the Design-Build Documents.
2. If, at any time during the construction of the Project, any error shall appear in
the position, level or alignment of the Sites and the Water Supply System, the
Contractor shall forthwith notify the Project Manager of such error and, at its own
expense, immediately rectify such error to the reasonable satisfaction of the Project
Manager.
2.5.7 Quality Assurance
1. The Contractor shall institute a quality assurance system to ensure compliance
with the requirements of the Design-Build Documents. Compliance with the quality
assurance system shall not relieve the Contractor of its duties, obligations or
responsibilities.
2. The Contractor shall submit for approval details of all quality assurance
procedures and documents relating to Contractor’s compliance with the quality
assurance system to the Project Manager before each stage of the Design-Build
Services are commenced as set out in the Time Schedule. When any document is
issued to the Project Manager, it shall be accompanied by the signed quality statements
for such document, if any. The Project Manager may audit any aspect of the quality
assurance system and the Contractor shall take any corrective action as the IVT may
deem appropriate.
2.5.8 Contractor's Access Routes and Rights of Way during the Design-Build
Period
1. The Contractor shall satisfy itself as to the suitability and availability of the
access routes it chooses to use during the Design-Build Period for access to and from
the project areas. The Contractor shall, as between the Parties, be responsible for the
maintenance of access routes during the Design-Build Period. The Owner will not be
responsible for any claims which may arise from the use or otherwise of any access
route. The Owner does not guarantee the suitability or availability of any particular
access route, and will not entertain any claim for any non-suitability or non-availability
for continuous use, during the Design-Build Period, of any such route.
2. The Contractor shall design Site Roads to provide access for proper operation
and maintenance of the works and to support the heaviest wheel load expected on the
site under all weather conditions. Arrange road surfaces so that where operating
vehicles enter buildings there is a short ramp and road drainage leads away from
buildings. Ensure road profiles cause no surface ponding and surface water is drained
away in drains to avoid damage to the roads or to the site.
3. The Contractor shall bear all costs and charges for special or temporary rights-
of-way required by it for access to working areas and the Contractor's camp. The
Contractor shall also provide, at its own cost, any additional facilities outside the
project areas required by it for the purposes of the Design-Build Services.
2.5.9 Site Regulations and Safety
1. The Contractor shall establish Site regulations setting out the rules to be
observed in the execution of the Contract at the Sites and shall comply therewith. The
Contractor shall prepare and submit to the Owner, with a copy to the Project Manager,
proposed Site regulations for the Owner’s approval, which approval shall not be
unreasonably withheld. Such Site regulations shall include rules in respect of security,
safety of the Site, Existing Facility and the Water Supply System, gate control,
1. Before starting any excavations, the Contractor shall satisfy himself and the
Project Manager as to the exact position of existing services by exploratory
excavations and shall make his own arrangements with the service providers for any
diversion or removal of services required.
2. The Contractor shall be responsible for liaison with all relevant authorities and
utilities and arrange his construction schedule to minimize inconvenience to all other
parties and the public.
3. Make least possible interference with existing amenities, whether natural or
man-made. Keep Site clearance to minimum. Divert around the perimeter of the sites
any minor watercourses crossing the sites that are needed for agriculture outside the
site boundaries.
4. Discharge or dispose of all water and waste products from the sites to the
satisfaction of the Project Manager and of any authority or person with an interest in
land into which water and waste products may be discharged, without limitation to the
Contractor’s general obligations.
5. Accept responsibility for safeguarding all pipes, cables and other things that
would otherwise be liable to suffer damage without precautionary measures.
6. Complete permanent fencing or other temporary safeguards around electrical
equipment as far as practicable before connection of electricity supply.
7. Ensure that all assemblies and sub-assemblies delivered to the site are of
suitable size and weight for access to the place of installation and pack all items of
plant and materials for transport to avoid damage from handling or weather. It is the
sole responsibility of the Contractor to maintain protection of the equipment.
2.5.14 Physical Cultural Property
1. The Contractor shall take reasonable precautions to prevent its employees,
agents, representatives, Sub-contractors, or other persons from removing or damaging
any fossils, coins, articles of antiquity, and structures and other remains or things of
geological or archaeological interest at the Site. The Contractor shall, immediately
upon discovery of such article or thing, advice the Project Manager, who may issue
instructions for dealing with it. All fossils, coins, articles of value or antiquity, and
structures and other remains or things of geological or archaeological interest
discovered on the Site shall be the property of the Owner.
2. If the Contractor suffers delay or incurs any damages or costs in following any
instructions of the Project Manager pursuant to this document, and if such delay or
damages or costs were Unforeseeable, the Contractor shall give notice to the Project
Manager, with a copy to the Owner. After receipt of such notice, the Project Manager
shall determine if the Contractor is entitled to any extension of time or any
compensation for such damages or costs and shall notify the Contractor accordingly.
2.5.15 Emergency Work
1. If, by reason of an emergency arising in connection with and during the
execution of the Design-Build Services, any protective or remedial work is necessary
as a matter of urgency to prevent damage to the Sites, Existing Facility or Water
Supply System, the Contractor shall immediately carry out such work.
2. If the Contractor is unable or unwilling to do such work immediately, the Owner
may do or cause such work to be done as the Owner may determine is necessary in
order to prevent damage to the Sites, Existing Facility or the Water Supply System. In
such event the Owner shall, as soon as practicable after the occurrence of any such
emergency, notify the Contractor in writing of such emergency, the work done and the
reasons therefore. If the work done or caused to be done by the Owner is work that the
Contractor was liable to do at its own expense under the Contract, the reasonable costs
incurred by the Owner in connection therewith shall be paid by the Contractor to the
Owner. Otherwise, the cost of such remedial work shall be borne by the Owner.
2.5.16 Work at Night and on Holidays
1. Unless otherwise provided in the Contract, no work shall be carried out at night
and on public holidays of the Country without prior written consent of the Owner,
except where work is necessary or required to ensure safety of the Sites, Existing
Facility or the Water Supply System or for the protection of life, or to prevent loss or
damage to property, when the Contractor shall immediately advise the Project
Manager, provided that provisions of this document shall not apply to any work which
is customarily carried out by rotary or double-shifts.
2. Notwithstanding this document, if and when the Contractor considers it
necessary to carry out work at night or on public holidays so as to meet the Time for
Completion and requests the Owner’s consent thereto, the Owner shall not
unreasonably withhold such consent.
2.6 Existing Facility Operation - The Contractor will not be responsible for the
operation and maintenance or repairs and renovation of the existing facilities, unless
stated otherwise.During the operation and maintenance period, the Contractor shall be
operating and maintaining the existing facilities including WTP, ESR, distribution
network, if any existing and used with the new system. However, during the design
build phase all the existing services shall be maintained by the Khargone Municipal
Council who shall be preparing a contingent plan for disruptions during transition
phase. The KNP shall be responsible for supply during transition phase.
2.7 Test and Inspection
1. The Contractor shall at its own expense carry out at the place of manufacture or
on the Site all such tests and inspections of the Plant and Equipment and any part of
the Project as are specified. The Contractor shall, in addition to those tests and
inspections set out in the Contract, develop a plan for all testing and inspection of the
Project that is required in order to complete the Project in accordance with the
Contract.
2. The Owner and the Project Manager or their designated representatives shall be
entitled to attend any test or inspection, provided that the Owner shall bear all costs
and expenses incurred in connection with such attendance including, but not limited to,
all travelling and board and lodging expenses.
3. The Contractor shall obtain from any relevant third party or manufacturer any
necessary permission or consent to enable the Owner and the Project Manager (or their
designated representatives) to attend the test or inspection.
4. If the Owner and the Project Manager, or their designated representatives, fails
to attend the test or inspection, or if it is agreed between the Parties that such persons
shall not do so, then the Contractor may proceed with the test or inspection in the
absence of such persons, and shall provide the Project Manager with a certified report
of the results thereof.
5. The Project Manager may require the Contractor to carry out any test or
inspection not required by the Contract, provided that the Contractor’s reasonable
costs and expenses incurred in the carrying out of such test or inspection shall be
added to the Contract Price. Further, if such test or inspection impedes the progress of
work or the Contractor’s performance of its other obligations under the Contract, due
allowance will be made in respect of the Time for Completion and the other
obligations so affected.
6. If any Plant and Equipment or any part of the Project fails to pass any test or
inspection, the Contractor shall either rectify or replace such Plant and Equipment or
part of the Water Supply System and shall repeat the test or inspection upon giving a
notice under this document.
7. If any dispute or difference of opinion arises between the Parties in connection
with or arising out of the test or inspection of the Plant and Equipment or part of the
Project that cannot be settled between the parties within a reasonable period of time, it
may be referred to an Adjudicator for determination.
8. The Contractor shall give the Owner and the Project Manager, at the Owner’s
expense, access at any reasonable time to any part of the Project or any place where
the Plant and Equipment are being manufactured or installed in the Water Supply
System, in order to inspectthe progress of the work and the manner of manufacture or
installation, provided that the Project Manager shall give the Contractor a reasonable
prior notice.
9. The Contractor agrees that neither the execution of a test or inspection of Plant
and Equipment or any part of the Site and the Water Supply System, nor the
attendance by the Owner and the Project Manager, nor the issue of any test certificate
pursuant to this document, shall release the Contractor from any other responsibilities
under the Contract.
10. No part of the Project or foundations shall be covered up on the Site without the
Contractor carrying out any test or inspection required under the Contract. The
Contractor shall give a reasonable notice to the Project Manager whenever any such
parts of the Project or foundations are ready or about to be ready for test or inspection;
such test or inspection and notice thereof shall be subject to the requirements of the
Contract.
11. The Contractor shall uncover any part of the Project or foundations, or shall
make openings in or through the same as the Project Manager may from time to time
require at the Site, and shall reinstate and make good such part or parts.
12. If any parts of the Project or foundations have been covered up at the Site after
compliance with the requirement of this document and are found to be executed in
accordance with the Contract, the expenses of uncovering, making openings in or
through, reinstating, and making good the same shall be borne by the Owner, and the
Time for Completion shall be reasonably adjusted to the extent that the Contractor has
thereby been delayed or impeded in the performance of any of its obligations under the
Contract.
13. The Contractor shall provide a report for every test carried out to sign and
certify that the test has been carried out and, the result. Tests witnessed by the Project
Manager shall be countersigned. The Contractor shall collect and collate all data into a
bound certified report.
14. The Contractor shall provide all labour, materials, electricity, fuel, stores and
apparatus and instruments necessary to carry out the tests efficiently. Measuring
instruments indicators and other apparatus shall be as approved by the Project
Manager.
15. The type and number of performance and operational tests to demonstrate
compliance of the installations with the output requirements shall be agreed between
the Project Manager and the Contractor. At least 1 week before testing starts the
Contractor shall submit the test schedule, detailed test procedures and method
statements to the Project Manager for approval.
The following tests shall be compulsory but not necessarily sufficient for the Project
and the test plan agreed between the Project Manager and the Contractor:
2.8 Pre-Commissioning Tests:
1) The Contractor will demonstrate the proper function and operation of all
mechanical and electrical plant and confirm compliance of all mechanical and
electrical equipment with the design and specifications, both individually and as part
of a system.
2) Water will be fed through each stream of each process stage in turn and each
item of auxiliary equipment shall be operated in a similar manner. Changeover of
duties of all plant shall be demonstrated. Each item of plant shall take a proportionate
share of the operating duty for a total minimum of 72 hours of continuous satisfactory
operation.
3) The Contractor will systematically demonstrate completion of the plant and that
it is ready for Commissioning.
4) This process shall then be extended to the distribution system, where the specific
procedures for flushing and sterilizing pipelines complying with AWWA C 651, or
other approved international standard, will apply.
In addition to the reports indicated in the Bills (Appendix 3C), the Contractor shall
prepare First, Quarterly and Final Reports. All reports shall be prepared in the English
language in hard and electronic version for submission to the Owner.
2.12.1 First Report (Inception Report)
Not later than in four weeks upon commencement of the assignment, the Contractor
will prepare and submit to the Owner a first report. This report will include the
information about the status of the Project preparation and implementation, any
problems encountered during the project preparation, revised overall procurement plan
and contracting strategy. The expected Project implementation schedule corrected
inaccordance with the realistic status will be attached to the report, as well as a
confirmation on the Contractor’s work schedule for the next quarter.The report shall
also propose content of the schematic design documents with e.g. projected water
demand and water works inventory, design reports, detailed technical specifications,
supervision procedures and supervision reports.
2.12.2 Preliminary Design Report
Not later than two months upon commencement of the assignment
2.12.3 Final Design Reports
Not later than three months upon commencement of the assignment
2.12.4 Quarterly Reports
Throughout the assignment the Contractor shall submit Quarterly Reports to the
Owner by the fifteenth day of the following month. Each report will show events and
progress for the Contractor’s activities of each of the main tasks.
The format of quarterly reports shall be agreed with the Owner and shall include, but
not be limited to, the following:
1. Chart and description of work and goods of each stage: Design, production,
transportation, construction, installation, testing, commissioning, guarantee test and
acceptance;
2. Comparisons of actual and planned progress including percentage completion
achieved for each activity;
3. Details of any aspects which may jeopardize the completion in accordance with
the contracts, and the measures being (or to be) adopted to overcome such aspects;
4. Copies of the assurance documents, test results and certificates of materials;
A. PREAMBLE
i) The Technical Specifications described herein shall be read in conjunction with the
other sections of Bidding Documents.
B. GENERAL REQUIREMENTS
The Technical Specifications, in accordance with which the entire work described
hereinafter shall be constructed and completed by the Contractor, shall comprise the
following:
i) PART - I- General Specifications
The General Specification shall be as described for all materials and works are to be in
conformity with the specification of the Madhya Pradesh P.W.D and the specifications
prescribed in the Indian Standard Codes (I.S. Code) published by the BIS (Bureau of
Indian Standard). While Executing the works all the relevant IS code in general, and
the following I.S. Codes in particular, all with latest amendments, current at the time
of execution are to be referred.
7 1538 (Part 1 Cast iron fittings for pressure pipes for water, gas and sewage.
to24)
8 782 : 1978 Caulking lead
Centrifugally cast (spun) ductile iron pressure pipes for water,
9 8329 : 1977 gas and sewage.
10 Ductile iron fittings for pressure pipes for water, gas and
9523 : 1980 sewage.
11 11606 : 1986 Method of sampling cast iron pipes and fittings.
12 12288 : 1987 Code of practice for lying of ductile iron pipes.
1239
13 (Part 1 and 2) Mild steel tubes
3589: 1981
14 Electrically welded steel pipes for water, gas and sewage.
15 5504: 1969 Spiral welded pipes.
Code of practice for laying of welded steel pipes for
16 5822:1986 water supply.
17 4711:1974 Method of sampling of steel pipes, tubes and fittings.
18 14846 : 2000 Sluice valves for water works purpose
Code of practice for selection, installation and
19 2685:1971 Maintenance of sluice valves.
5312 Swing check type reflux (non return) valves for water
20 (Part 1 and 2) woks
For interpretation of the IS codes decision of the Engineer -in -Chief MPUDC,Madhya
Pradesh shall be final and binding. If for any item of works that may require to
executed the IS code does not exist, and then the particular item will have to be
executed as per the available standard engineering practices and as directed by the
Project Manager.
In case the specification of a particular item of work is not available in the above
mentioned schedule of specifications, the work shall be executed as per sound
engineering practice and/ or as directed by the Engineer –in-Chief, MPUDC, Beej
Bhawan, Arera Hills, BHOPAL-2, Madhya Pradesh.
IS 875 – 1987 Code of practice for design loads other than earthquake for
buildings and structures (part 1 to 5)
C. The scope of work along with the respective technical specifications includes,
but not limited to, construction of the following works:
1.1 Scope of work: The Contractor shall carry out field investigations and surveys
as deemed necessary to obtain sufficient physical conditions as required for the
design. Normally, the following field investigations and surveys may be
required and shall therefore be considered by the Contractor:
i. Water resources survey to review existing water points potential,
includingStreams and rivers (discharge data including references, field
measurements, estimates), water quality, water levels (lowest, highest and
normal operating levels, flood levels);
ii. Detailed topographic/cadastral surveys for project sites, as required for detailed
design of the components to ensure that the water production and distribution
facilities can be designed to operate properly and so that quantities of work and
materials required can be accurately determined.
1.2. Field Survey: Detailed field survey shall be done with Total Station Survey and
co-relate the same with GPS data for raw water source area, pipe line route
along/ across different road network for Raw Water Pumping Main, Clear Water
Pumping Main, Distribution network etc. The details are as under:
i. Survey in the vicinity of proposed intake point of the river source giving
details for accessibility to it, river bank conditions required for planning for type
of intake structure etc.
ii. Net levels at maximum 3.0 meter grid for sites of Source, Intake, WTP
location, sites for service reservoirs
iii. Generation of contour overlay at 1 meter interval for the WTP site.
iv. Longitudinal survey along proposed pipeline routes with spot levels taken
at maximum 30 m intervals and at every changes of road alignment, road
junction etc.
v. Cross sections along the pipeline routes at every 90 meters intervals and
to include road, rail, canal, river crossings and other cross drainage structures
vi. Node to node length of the proposed pipe line route.
vii. RL of the each node (pipe junction; road junction; peak/ valley crest along
the pipe route etc.) above MSL.
viii. Road width (hard crust / side berm); any culvert / bridge; stream / nallah
crossing; trees/ poles etc. that may obstruct the pipe alignment.
ix. Prominent structures along the proposed route viz. Educational Institute,
Govt / Semi Govt. Offices, Hospitals, Religious Institute etc. with their
respective GPS data.
x. Individual dwelling houses, available water body etc. with their respective
GPS data.
xi. Establishing temporary bench marks (TBM) at different locations of the
project area on permanent structures viz., parapet of culvert / bridge; at plinth of
old monument / Govt. offices / structures of existing water supply scheme (if
any), with respect to Geodetic Triangulation Station bench mark (GTS BM,
including co relating the TBM with GPS data.
1.3 Preparation of Maps and drawings:
1.6 Testing of Raw Water for various parameters for potability based on CPHEEO
Manual.
Based on the surveys and soil investigations, the Contractor shall review the
indicative drawings and designs provided by the owner and prepare detailed
designs of each and every component, as may be required. The contractor is
required to prepare sufficient sets of hard copies of each drawing and design
alongwith a reproducible soft copy.
Chief.
The details of designs and drawings required for each component is given in
respective sections.
The present source for the water supply for Khargone town is River Kunda. A system
for water supply is already in place at River Kunda at Umar Khali Road. However,
looking to the increasing demand of Khargone town, the NVDA has reserved water in
its ongoing project of constructing a dam at Village Pipari at a distance of 8 km from
the existing water intake facility (at River Kunda) of Khargone Municipal Council.
NVDA will be providing water to Khargone Municipal Council at its present intake
and the physical arrangements for the same have been included in the scheme of
NVDA. The construction of dam at Pipari is already in progress. However, the present
storage at River Kunda will continue to exist.
3.1.1 General
The job implies all works from detailed investigations to the final
commissioning of the structure including all ancillary works such as
construction of coffer dam for diversion of flow of river Kunda dewatering,
bailing out of water etc. including testing during trial run period and defects
liability and O&M period of this contract.
The contractor’s offer should be technically sound and economically viable.
The contractor is required to arrange complete construction of civil works,
supply and installations of all the pumping sets until the whole structure is
handed over to the authorized by the Engineer-in-Chief. All tests have to be
carried out at contractor’s cost and it will be the responsibility of the contractor
to ensure that respective standards are achieved.
The Intake well is required to house vertical turbine pumps and other
accessories, therefore coordination with the pump Contractors and hydraulic
model studies will be essential for deciding arrangements of pump installations,
the contractor will have to carry out any modification, addition and alteration to
the design and structure to meet such requirement if needed without causing
any extra liabilities on the MPUDC. The contractor will design the Intake well
cum pump house in such a manner that it also meets the efficient vortex free
hydraulic and structural requirements of pumps/motors to be installed to meet
such requirements.
The trash rack of the Intake well should be suitable for ultimate capacity of this
project through different ports at same level. In the Intake well cum pump
house total 3 numbers of vertical turbine pumps which may be replaced in
future after O&M period, for ultimate capacity. These pumps will operate
individually or in all possible combinations. The Civil structure will have to be
such that no vortex is formed and there is no interference or pump starvation by
operating these pumps in any combination or independently. However for
structural design suitable static loading for each motor pump assembly may be
considered at the points where they will be fixed. In addition to this a live load
at motor and discharge pipe floor may also be considered. The essential
vibration effect factors will also be considered.
3.2 Detailed investigation
It will be necessary for the contractor to depute technical personnel to visit the
site of construction to get them acquainted with the prevailing site conditions
and for any additional information contact the office of Project Manager to
collect all relevant information for planning and designing the entire
construction work of said structure. The preliminary topographical,
hydrological and geological information available with the MPUDC are given
below:
(a) Topographical data- A location map and contour map of proposed site of
intake well.
(b) Hydrological data River Flow Records, Rain Fall Records
(c) Geological Data- Soil Strata Chart
A safe Maximum Water Level should be worked out by the contractor for
planning water supply head works at the Intake well.
The data given in this bid document is just for the guidance purpose and the
contractor shall consider this suitably while preparing the bid. No claims on
(v) Protection work against flood and erosion of banks near Intake well.
(vi) Design of inlet ports and/or approach conduit.
thereafter.
Sufficient dowel/ Anchor bars should be provided in the foundation by drilling
suitable diameter holes in the foundation rock and fixing for steel bars and
grouting it with suitable epoxy compounds.
3.6 Construction of trash rack structure, Intake well cum pump house
The R.C.C trash rack structure shall have the minimum suitable floor area, and
for summer and fair weather & monsoon season three inlet ports should be
provided at suitable levels.
Control sluices for lower most and monsoon level ports shall be above HFL at
Intake floor level where as all upper sluices shall be provided in the steining of
the trash rack and inlet lower and operating gears from the approach floor at
top manually and electrically. The opening in the trash rack structure has to be
provided in such a way that it is not obstructed due to any floating logs/ big
boulders or other floating bodies. And it should be able to draw designed flow
from the river at each of the ports. The top level of trash rack structure has to
connect to Intake well with an approach. Rose pieces shall be designed for 50%
clogging.
3.7 Technical Specifications of the Intake Well:-
RCC Intake–cum- Pump house at the bank of River Kunda at a distance of
1.4km u/s of the existing WTP near Umar Khali Road, Khargone to draw raw
water from top most layers in different seasons and also from the lowest level
of water as below-
a) Floor area should be sufficient to have panels, switch gears and
capacitors etc. The floor area shall be increased to the functional requirement
for all these, if necessary.
b) The size of the Intake well should have adequate capacity for installation
and maintenance of the pumps/motors with minimum 8.00 meter internal
diameter, to house the pumping equipment, as per specifications.
c) Intake well shouldhave a proper grit chamber for the retention of half
minute or as required from the design consideration and should have a
mechanical bucket for de-gritting the well.
d) Suitable sluice valves/gates at the entrance of Intake well have to be
provided to control the flow with manual as well electrical operated
arrangement.
Page 279 of 553
Technical Specifications
Pipe floor should be provided to house all discharge pipes, valves and
manifold for all the vertical turbine pumping sets as per requirement.
The floor slab should be designed for a uniformly distributed expected
live load and moving loads, suitably designed openings should be
provided for passing column pipes through the slab. The suitable
provision for concrete bedding and thrust blocks for all discharge pipes
should also be provided. A door entrance opening with steel collapsible
gate should be provided in the well steining above pump discharge floor
Page 280 of 553
Technical Specifications
Cantilever projection not less than 0.3 m should be provided all around on the
inner side of the wall at suitable height from motor floor level to support
Gantry girder crane. Rails of suitable size should be provided all around this
projection over which the gantry girder will move along the circumference.
The gantry girder should be provided with chain pulley with spur gear in such a
manner that it can move along the gantry girder. The length of chain pulley
shall be capable of lifting the machines/pipes/other articles from the bottom of
the Intake well discharge floor, motor floor level or from any height between
the bottoms of Intake to gantry girder level.
The job includes providing, installation and commissioning of de-gritting crane
with grab bucket, rope girder, hoist etc. complete. A suitable Air and water jet
arrangement with suitable compressor for scouring of Intake and trash rack
arrangement is to be made.
3.9 Staircase
a) A R.C.C. staircase of minimum 1.0m width with railing for a live load of
500 kg/sqm from discharge floor level to bottom of the Intake well should be
provided, on the inner circumference of the steining. The stairs shall be
Page 282 of 553
Technical Specifications
(i) Supplying, laying , jointing, installing , testing and commissioning of star rated
vertical turbine pumps of reputed make and conforming BIS mark having discharging
against total head as per DPR including all necessary electrical and other allied
works installation
(ii) Electro mechanical Equipment for Raw water: - Supplying, installation, jointing,
erection, testing and commissioning of 170 KVA transformer and draw dedicated
33KV power line from MPSEB substation to raw water intake and all accessories etc.
all complete including all taxes, duties, royalty etc., as per description of indicative
BOQ & as required for completeness of work.
2 WTP
Clear Water Pumps 2x173 = 346 KW
WTP Plant equipment 20 KW
Suitable diameter M.S. Pipe and specials epoxy coated for delivery piping of
each of turbine pumps in the required length as per specification attached.
Suitable size M.S. epoxy coated pipe for common manifold of required length.
Dismantle joint as per dia. of delivery pipe.
(vi) Valves for delivery piping:
Suitable diameter swing type reflux valve (non-return valve) as per the
specifications.
Suitable dia. butterfly valves as per specifications
Suitable dia. butterfly valve to be installed in the manifold as per the
specifications.
Suitable dia. Swing type reflux valve (non-return valve) for manifold.
(vii) Flow Measuring Device:
Electromagnetic full bore type flow measuring device to be installed at junction
point of pumping main and manifold outside the pump house with remote flow
indication panel to be fixed inside the pump house- one no.
(viii) Electronic Pressure Transducers:
For indication of delivery pressure of each pump electronic pressure
transducers with indication panel.
5 TECHNICAL SPECIFICATIONS OF THE TRANSMISSION MAIN
Raw water pumping main shall start from Raw Water Intake Well-cum-Pump House
and terminate at the inletof WTP. The raw water pumping main shall be provided for
conveying required capacity of water in 23 hours from Raw Water Intake well-cum-
Pump House to water treatment plant near the proposed Intake, which shall comprise
main section as per details below-
Raw water pumping main shall start from Raw Water Intake Well-cum-Pump House
and terminate at the inlet of Water Treatment Plant, having a total length of 1400 m
approximately. This main shall be of D.I. K-9 pipes of 700 mm dia. having cement
mortar in-lining and out-coating as per IS:8329-2000.
Allied Works: All works necessary for providing, laying, jointing, testing,
commissioning and O&M of above pumping mains shall fall under the scope of
works including surge protection works, if any.
Providing , laying and jointing following socket and spigot centrifugally cast (Spun)
Ductile Iron pressure pipes with inside cement mortar lining (class-9) conforming to IS
8329/2000 with suitable Rubber Gasket (Push on) joints as per IS: 5382/85 including
testing of joint (laying conforming to IS:12288:1987).
1. The contractor shall have to carry out confirmatory survey and submit the
detailed layout drawing, sufficient to show the details as mentioned below-
i. R.L. of ground, invert level of pipes and H.G.L. at every 30 m interval.
ii. Location of horizontal and vertical bends.
iii. Degree of bends, degree or radius of curves, tangent distance for curves.
iv. Location and covering length of all valves and other appurtenances.
v. Details and description of all specials.
vi. Location and size of supporting pillars, bridges and culverts to cross the
waterways.
vii. Location and sizes of thrust blocks and anchor blocks.
viii. Location and sizes of valve chambers. Details, dimensions and plan
including complete description of expansion joints and flanges.
2. The layout plan submitted by the contractor, can be altered or modified by the
Project Manager to suit the requirement depending upon the field conditions
before or even after the acceptance of the tender or during the course of
execution of work and the contractor shall not claim for compensation in any
way on this account.
3. Supply and laying, jointing of Ductile Iron pipes and Specials
II. Standards
Except as otherwise specified, the Indian/International Standards and
Codes of Practice in their latest version shall be adhered to for the design,
manufacturing, inspection, factory testing, packing, handling and
transportation of product. Should any product be offered conforming to
other standards, the equipment or products shall be equal to or superior to
those specified and the documentary confirmation shall be submitted for
the prior approval of the Project Manager. DI pipes of ISO standard shall
also be accepted.
IS: 8329 centrifugally cast (spun) ductile iron pressure pipes for water,
gas and sewage
IS: 5382 Rubber sealing rings for gas mains, water mains and
IS: 9523 Specification for DI fittings for pressure pipes for water,
gas, and sewage
BS: 4772 Specification for DI fittings
IS: 11606 Methods of sampling of cast iron pipes and fittings
IS: 1608 Mechanical testing of metals – tensile testing
IS: 12288 Code of practice for use and laying of ductile iron pipes
4. Specifications for Ductile Iron Pipes:
I. Casting
The pipes will be centrifugally cast (spun) Ductile Iron pipes for Water,
confirming to the IS 8329. The pipes used will be with push on joints
(Rubber Gasket Joints). The class of pipe to be used shall be of class K-9.
II. Surface coating
The pipes shall be coated with Metallic Zink coating as per appendix A,
with a finishing layer of bituminous paint, and have factory provided
cement mortar lining in the inside as per the provisions of Appendix B of
the IS 8329.
III. Standard length
The pipes will be supplied in standard lengths of 5.50 and 6.00 meters
with chamfered ends suitable for push-on jointing. Each pipe of the push
on joint variety will also be supplied with a rubber EPDM gasket,
confirming to the IS: 5382. Any change in the stipulated lengths will be
approved by the Project Manager.
IV. Manufacture of Gaskets
The gaskets should also be supplied by the manufacturer of the pipes.
They should preferably be manufactured by the manufacturer of the pipes.
In case they are not, it will be the responsibility of the contractor to see
that the manufacturer of the pipes get them manufactured from a suitable
manufacturer under its own supervision and have it tested at his/sub
contractor’s premises as per the contract. The pipe manufacturer will
however be responsible for the compatibility and quality of the products.
V. Flanged joints
The flanged joints will confirm to the Clause 6.2 of IS 8329. The pipe
supply will also include one rubber gaskets for each flange.
VI. Hydraulic test at works
Each and every pipe shall be tested hydraulically by the manufacturer as
specified under clause 11 for the pressures specified in table 1 of IS: 8329.
The test shall be carried out before application of surface coating and
lining except Zinc coating which may be applied before the hydrostatic
test.
VII. Test for Gaskets
The test reports for the rubber gaskets shall be as per acceptance tests of
the IS 5832 and will be in accordance to Clause 3.8 and contractor shall
submit the test certificate issued by the manufacturer with the pipe supply,
without which payment for pipe supply shall not be released.
VIII. Third party inspection
The inspection and testing of the pipes shall be carried out by the
employer and/ or inspecting agency appointed by the employer, in the
manufacture’s workshop. The pipes will be subjected to following tests for
acceptance:
• Visual and dimensional check as per Clause 13 and 15 of IS 8329 for
length, internal and external diameter, wall thickness, deviation from
straight length and ovality.
• Mechanical Tests as per Clause 10 of IS 8329 for tensile strength and
Brinell hardness test.
• Hydrostatic Test as per Clause 11 of IS: 8329.
The sampling for the above tests shall be as per the provisions under
clause 9 of the IS:8329. All the tests shall be conducted in presence of the
inspecting agency. The pipes shall be dispatched only after issue of the
test certificate by the inspecting agency for satisfactory test results as
required. The inspection charges for such tests shall be paid by the
contractor to the inspecting agency.
IX. Retest
If a test piece representing a batch fails in the tensile or Brinell hardness
test in the first instance, two additional tests shall be made on test pieces
selected from two other pipes from the same batch. If both the test results
satisfy the specified requirements, the batch shall be accepted. Should
either of these additional test pieces fail in the test, the batch shall be
deemed as not complying the required standards and shall be rejected.
X. Marking
• All pipes will be marked as per Clause 18 of IS 8329 and show as below:
• Manufacturer name/ stamp
• Nominal diameter
• Class reference
• A white ring line showing length of insertion at spigot end
XI. Packing and Transport:
The pipes should be preferably transported by road from the factory and
stored as per the manufacturer specifications to protect damage.
5. Specifications for Ductile Iron Fittings (Specials)
I. General
The Ductile Iron (DI) fittings shall be D.I. fittings shall be ISI marked
as per IS : 9523-2000, suitable for Tyton joints to be used with Ductile
Iron pipes with flanged and Tyton jointing system.
II. Types of specials
The following types of DI fittings shall be manufactured and tested in
accordance with IS: 9523 or BS: 4772
• flanged socket
• flanged spigot
• double socket bends (900, 450, 22½0, 11¼0)
• double socket branch flanged tee
• all socket tee
• double socket taper
• All the fittings shall be of PN 1.6 pressure rating
III. Supply
All the DI fittings shall be supplied with one rubber ring for each
socket. The rubber ring (EPDM) shall conform to IS: 12820 and IS:
5382. Flanged fittings shall be supplied with one rubber gasket per
flange and the required number of nuts and bolts.
IV. Manufacture of Fittings / Specials
pipes
• must not have an objectionable odour
• has to inhibit bacterial growth
• must not be harmful to the skin
• must have a shelf live not less than 2 years
III. Acceptance tests
They shall be conducted in line with the provisions of the IS 9523.
IV. Packing for DI specials and Rubber Gaskets
All the DI fittings shall be properly packed with jute cloth. Rubber rings
shall be packed in polyethylene bags. Rubber rings in PE bags and nuts,
bolts etc. shall be supplied in separate jute bags.
7. Laying and jointing of DI pipes and specials
I. Use of tackle
Pipes should be lowered into the trench with tackle suitable for the
weight of pipes. For smaller sizes, up to 200 mm nominal bore, the pipe
may be lowered by the use of ropes but for heavier pipes suitable
mechanical equipment have to be used.
II. Cleaning
All construction debris should be cleared from the inside of the pipe
either before or just after a joint is made. This is done by passing a pull-
through in the pipe, or by hand, depending on the size of the pipe. All
persons should vacate any section of trench into which the pipe is being
lowered.
III. Laying on steep slopes
On gradients of 1:15 or steeper, precautions should be taken to ensure
that the spigot of the pipe being laid does not move into or out of the
socket of the laid pipe during the jointing operations. As soon as the
joint assembly has been completed, the pipe should be held firmly in
position while the trench is back filled over the barrel of the pipe.
The designed anchorage shall be provided to resist the thrusts
developed by internal pressure at bends, tees, etc.
concrete thrust blocks or anchorages, the pressure test shall not be made until at
least five days have elapsed after the concrete was cast. If rapid hardening cement
has been used in these blocks or anchorages, the tests shall not be made until at
least two days, have elapsed. Each section of' the pipe line shall be slowly filled
with water and all air shall be expelled from the pipe by tapping at points of
highest elevation before the test is made plugs inserted after the tests have been
completed. The duration of test shall be 8 hours. No pipe installation shall be
accepted until the leakage is less than the number cm3/hr as determined by the
formula:
QL =ND √ P 3.3
Should any test of pipe laid indicate leakage greater than that specified above, the
defective joints shall be repaired by Contractor at no extra cost to
Owner/Engineer until the leakage is within the specified allowance. Necessary
equipment and water used for testing shall be arranged by Contractor at his own
cost. Damage during testing shall be Contractor's responsibility and shall be
rectified by him at no extra cost to Owner/Engineer. Water used for testing shall
be removed from the pipe and not released in the excavated trenches. After the
tests mentioned above are completed to the satisfaction of Owner/Engineer, the
backfilling of trenches shall be done as per specifications in layers.
The net length of pipes as laid or fixed shall be measured in running meters
correct to a cm. Specials shall be included and measured in the total length.
The portion of the pipe at the joints (inside the joints) shall not be included in
the length of pipe work.
5.4 Excavation and preparation of trenches for laying underground pipeline
I. The trench shall be so dug that the pipe may be laid to the required
alignment and at required depth. When the pipeline is under a roadway, a
minimum cover of 1.2 m shall be provided; in other cases the minimum cover
of 1 m above the crown of the pipe shall be provided. The trench shall be
shored, wherever necessary and kept dry so that the workman may work
therein safely and efficiently. Under roadway and places where it is not
possible to lay pipes upto required depth or laid open on ground should be
encased all round with the 1:2:4 ( M15) cement concrete.
II. Recovery of other serviceable material:-
All serviceable materials such as wood work, bricks, masonry etc. recovered
during the operation of cleaning or excavations, which, in the opinion of the
Project Manager are suitable for reuse in restoring the surface, shall be
separately stacked and disposed-of as directed by Project Manager.
III. Dewatering:-
Dewatering shall be carried out by the contractor, wherever necessary. The
discharge of the trench dewatering pumps shall be conveyed either to drainage
channels or to natural drains and shall not be allowed to spread over in the
vicinity of work place.
IV. Trenching:-
The excavation of trenches shall be carried out by hand or machines. The
width of trench shall be kept to a minimum consistent with the working space
required. At the bottom, between the faces, it shall be minimum 200 mm
clearance on either side of the pipe. However this is for the safety of the
trench, the method of laying and jointing the pipe and the need to avoid
damage to pipe coating.
V. Preparation of bottom of trench:-
The bottom of the trench shall be properly trimmed to permit even bedding of
the pipeline. The curvature of the bottom of the trench should match the
curvature of the pipe as far as possible, subtending an angle of 120o at the
centre of the pipe. Where rock or boulders are encountered, the trench shall be
trimmed to a depth of at least 100 mm below the level at which the bottom of
the pipe is to be laid and filled to a like depth with non-compressible material
like sand or crusher dust or moorum of adequate depth to give the curved
seating.
VI. Special foundation in poor soil:-
Where the bottom of the trench at sub grade is found to consist of material,
which is unstable to such a degree that in the opinion of Project Manager it
cannot be removed and replaced with an approved material thoroughly
compacted in place to support the pipe properly, a suitable foundation for the
pipe, consisting of piling, timbers or other materials, in accordance with the
direction of the Project Manager, shall be constructed.
VII. Excavation in hard rock by blasting:-
Blasting for excavation shall be done only when the contractor obtains the
license for the same and only when proper precautions are taken for the
protection of persons and property. The hours of blasting shall be fixed by the
Project Manager. The procedure of blasting shall conform to the requirement of
licensing authority. The excess excavation by blasting shall be filled up by
1:4:8 cement concrete. The contractor shall have to make his own arrangement
for procurement and storing of explosives required for blasting.
Rubble available from excavation of hard rock, shall be the property of the
contractor, for which recovery of Rs. 65/- per cum of the quantity of hard rock
excavated shall be made from his running account bills.
Project Manager. When it is necessary to cut roots and tree branches such
cutting shall be done under the supervision and direction of the Project
Manager.
XIV Avoidance of the Existing Service:-
As far as possible, the pipeline shall be laid below existing services, such as
water and gas pipes, cables, cable ducts and drains but not below sewers, which
are usually laid at great depth. If it is unavoidable, pipeline should be suitably
protected. A minimum clearance of 150 mm shall be provided between the
pipeline and such other services. Where thrust or auger boring is used for
laying pipeline across road, railways or other utilities, larger clearance as
required by the concerned authority shall be provided. Adequate arrangements
shall be made to protect and support the other services during laying
operations. The pipeline shall be so laid as not to obstruct access to the other
services for inspection, repair and replacement. When such utilities are met
with during excavation the authority concerned shall be intimated and
arrangements made to support the utilities in consultation with them.
XV. Restoration of sewerage system: If the sewer lines are coming in the way
of pipeline alignment, it shall be properly restored either by constructing
manholes on both sides and connecting it with similar sewer line, so as not to
disrupt the services of the sewerage system or by laying the pipeline below or
above the sewerage system as per the directions of Project Manager.
XVI. Preparation of Formation for Sections of pipe line to be laid above
Ground:-
Formation should be prepared by cutting high grounds and filling in low areas.
Care has to be taken while fixing the alignment and gradient of the pipeline, to
balance the cutting and filling quantities, as far as possible, with minimum of
lead. Care should also be taken to ensure that pipe rests fully either on cutting
or on bank.
XVII. Disposal of surplus material:
Excavated material in excess than required for backfilling the trenches, shall be
disposed off as per the directions of Project Manager. Surplus excavated stuff
available at one section shall be used for back filling at other reaches, wherever
required.
The mode of laying the pipeline, crossing road, railway or river in the entire
project shall be determined so as to satisfy the requirement of the authority
concerned. Cost of all such crossings shall be included in the rates and no extra
payment shall be made on that account. Liaising with the concerned authorities
will be under the scope of the contractor. Only the fee/charges, if any payable to
the concerned department/authority for grant of permission will be
paid/reimbursed by MPUDC.
The specifications given below are indicative only. The contractor is free to use proven
technology as per the CPHEEO Manual and the offers for proven technologies
including the one below will be evaluated.
A Civil Work
1 Laboratory cum office ,
2 MCC Room / Panel Room,
3 Inlet Chamber, Cascade aerator
4 Flow measuring channel,
5 Softner Unit
6 Flocculation tank,
ii. Designing, providing and constructing brick masonry boundary wall around WTP
length 100 m, of height not less than 1.95 mtr above plinth band over PCC.
building works, pipe lines and appurtenances from the raw water inlet up to
clear water reservoir and pump house.
The principal requirement is a spacious and convenient layout. The structure
should represent a pleasing appearance with aesthetic features forming a balance
between function and form. The interiors of the structure shall be eye appealing
and in keeping with the objectives of the plant viz., production of potable and
wholesome water.
While designing and constructing, it should be ensured that all materials, design,
construction and fabrication details for different units including doors and
windows conform to the IS-specifications and codes of practice wherever
available and in their absence, to the established standards.
6.2.1 The scope of work includes but shall not be limited to the provision of the
following
i. Study of available data with Owner and if required collection of additional
field data's and site investigations.
ii. Planning and design of most economical type of treatment plant to
generate 30.0 Million liter filtered water in 23 hours, with due
consideration of future expansion (Requirement for the year 2047).
iii. The detailed design including hydraulic and structural design,
development and preparation of detailed plant working drawings,
diagrams and cable schedules and detailed structural steel fabrication
drawings, preparation of design reports, manufacture and testing at places
of manufacture, transport, delivery, erection, building-in, setting to work,
commissioning, testing of all plant required for the Water Treatment
Works,
iv. Leveling the treatment plant site and landscaping.
v. The contract is including but not limited to pipelines, pumping
installations, blowers, compressors, machinery, apparatus, station pipe
work, lifting, handling, ventilation equipment, electrical equipment,
automation and instrumentation, control, compatible PLC, interfacing
lighting systems, earthing, fire safety and lightning protection systems,
materials, articles, fittings and accessories, ancillary works of all kind and
nature required for installations of the highest possible operative standards
and for compliance with the standards prescribed in the Specification and
with the particulars and guarantees entered by the Contractor in the
schedules.
vi. Design and Construction of Cascade Aerator or any other suitable system,
for removal of iron in incoming Raw water if required.
vii. Design and Construction of sedimentation tank if required.
viii. Supply and erection of Dosing equipment of coagulants, including
chemicals with facilities to store Alum and chemicals for 3 months.
ix. Design and construction of Flash mixers.
x. Design and Construction of Distribution chamber for Tube settlers
xi. Design and Construction of Tube settlers.
xii. Design and Construction of Rapid gravity sand filters, filter galleries,
wash water tank, filter back wash system and filter control block.
xiii. Design and Construction of chlorination plant building, facilities for post
and/or pre chlorination and storage of chlorine cylinders for 60 days
requirement.
xiv. The sludge, from plain sedimentation tank, Tube settlers is to be collected
in sludge receiving tanks by gravity and disposed into sludge drying beds
with drainage facilities to reuse at flax mixer/ inlet channel. The back
wash water from filter is to be collected into settling tanks by gravity and
to be recycled after settlement by pumping, raw water inlet channel. The
overflow from various units shall be connected to the storm water drains
for safe disposal to the nearly water bodies with environmental
acceptance.
xv. Monitoring and instrumentation with their housing.
xvi. Electrical works including incoming cable from substation to main control
panel, motor control centers, local control and panels compatible PLC,
interfacing, power and control cabling, plant ventilation and lighting etc.
xvii. Pipe lines, valve chambers, service water installation, sampling and water
quality monitoring, instrumentation and other miscellaneous works
associated with the plant.
xviii. Internal roads with storm water drains, sewers with appurtenances,
Page 302 of 553
Technical Specifications
with laboratory.
xxxv. WASTE WATER COLLECTING SUMP AND WASTE WATER LINE:
The waste water or sludge water from flocculator, Tube settlers and filter
plant and other units shall be collected in waste water collecting tank of at
least suitable detention time and depth according to the levels. It shall
have such level that the waste clear water tank can be cleaned easily. The
overflow of waste water from tank will be directly discharged by gravity
away from treatment plant to the natural Drain. The chambers shall be
provided at maximum 60.00 mt. Internal and at turning and where ever
necessary. The diameter of the pipe should be as per approved design and
minimum class of pipe shall be RCC NP2.
xxxvi. WASTE WATER PIPE FROM FLOCCULATOR, FILTER, and CLEAR
WATER SUMP: The waste water line from all the units R.C.C. class NP2
up to the waste water sump shall be provided.
xxxvii. SLUDGE DRYING BEDS: Sludge drying beds shall be designed for 5 to
7 days cycle, the settled sludge from waste water sumps will be taken to
drying beds and filtrate will again be carried to flash mixer for reuse.
xxxviii. INTERNAL AND EXTERNAL ELECTRIFICATION: It should be done
as per details given and as per IS/I.E. Rules
shall have a side chamber for float. The flume shall be open channel type. The
entire construction shall be in R.C.C. and shall be perfectly water tight and
suitably supported in R.C.C. columns. The walkway of 1.0-meter width with
G.I. pipe railing as per specification given shall be provided. The dial type
flow indicator shall be provided near the flume to indicate the flow. The flow
indicator shall have a capacity of measuring a maximum flow of 50 MLD
including 50% overloading. The weir plate will have brass edges which shall
be graduated to read in liters per hour. The weir shall operate with clear free
fall condition. It shall be ensured that the weir plates do not get submerged
due to afflux. The dial of indicator shall be properly lighted. Necessary
arrangements for proper de-silting of stilling chamber shall be provided.
6.4.4 BY PASS CHANNEL
In order to provide the flexibility in operation the bypass channels shall be
provided. The by-pass channel shall be designed for designed capacity. It
shall connect the following units:-
(i) From raw water channel to floculator by passing primary settling
tank.
(ii) From raw water channel to filters by passing the floculators and
primary settling.
(iii) From floculator to sump by passing filters.
The necessary pens tock with simple operating arrangement shall be provided
as per I.S. 3042-1965 or some alternative arrangement, which suits to the
proposal. It shall be constructed in minimum M-30 grade concrete and
columns shall be minimum M- 25 grade concrete.
6.4.5 RAPID MIXING UNIT:
It shall be flash mixer designed for designed capacity, mixer with mechanical
arrangement as per provision in Manual on water supply and treatment third
edition.
6.4.6 FLASH MIXER:
It shall be designed for detention period of 30 to 60 seconds. It shall be
circular or square tank with ratio of impeller dia to tank diameter 0.20 to 0.40
and the shaft speed of propeller to Impart tangential velocity greater than
3mt/Sec. at the tip of the blade. The ratio of the tank height to the diameter
shall be 3:1. The power-mixing device shall be capable of creating velocity
gradient for 300 per second.
The power requirement of flash mixer shall be as per recommendation given
in I.S. 7090. The paddles made of structural steel confirming to I.S. 226. The
agitator shall be mechanically driven consist of electric motor with continuous
duty operating through a reduction gear. To achieve good results the chemical
should be added just near the tip of blade. The design should be such that
there should be no possibility of short circuiting in the tank. It shall be
designed for a full flow of designed capacity. A de-sludging pipe of R.C.C.
NP2 with sluice valve confirming to B.I.S. shall be provided. The length of
pipe shall be as per requirement of layout plan, it shall be connected to waste
water sump. Hand railing along operating platform (1.0m diameter all around)
of 0.75mt height shall be provided. The M.S. ladder of 0.75 mt. wide shall
also be provided. The specification of ladder and railing are given separately.
It shall be constructed in R.C.C minimum M-25 grade concrete. Protective
cover of G.I Sheet of 8 gauge shall be provided for motor.
Combined units of flocculation and sedimentation shall be provided
immediately after flash mixer but it should be designed on concept of tap
erring velocity gradient and settling velocity with suitable motor operated
mechanical cleaning device.
6.4.7 TUBE SETTLERS-
(a) NUMBER OF UNITS:
Tube Settlers (s) shall be provided for the total designed flow with provision
for 25% overloading under emergent condition as per CPHEEO manual. The
inlet and outlet arrangement will also be designed for 25% overloading.
(b) INFLOW ARRANGEMENT -
Coagulated water from flash mixer will be conveyed to the inlet of Tube
Settlers through precast R.C.C. pressure pipe or CI or DI D/F of suitable dia.
It should be possible to regulate or stop flow, to individual unit. The pipes
shall be laid over firm bedding and at uniform grade. The velocity of flow
through this conduit shall preferably be between 0.25 to 0.45 mps.
(vi) Hydraulic design: The total hydraulic design capacity of the sludge
withdrawal and discharge system shall not be less than 10% by volume of
the Max. Water Flow.
(vii) Sludge disposal pipe work: The pipe work for the plain
sedimentation tanks and TS sludge system (within structures) shall be of
RCC NP3 and shall enable to empty tank into the sludge well by gravity.
Valves shall be of cast iron-rubber lined type, epoxy painted outside. The
valves shall be easily accessible for manual operation. The pipe work for
sludge pumping shall be in cast iron / ductile iron.
(h) Plain Sedimentation Tank and Tube Settlers Sampling:
i. Local sampling taps of approved design shall be installed to take sample
from at least three different points in each plain sedimentation tank and Tube
Settlers.
ii. The three sampling taps for each tank shall be grouped together and shall
discharge into a sink, which shall be connected to the main drainage system.
(j) Drainage of Plain Sedimentation Tanks and Tube Settlers
Each tank shall be provided with facilities for complete gravity drainage of all
water and sludge from both the main body of tank and from sludge
concentrates. All valves, pipe work required for discharge to and connection
with the main drainage system shall be provided, so that a tank may be
emptied within 6 to 8 hours. These drains shall discharge into the main works
drainage duct to be provided by the Contractor.
6.4.8 FILTRATION -
Traces of suspended matter in the clarified water shall be removed by
filtration. Filter designs shall be based on the use of rapid gravity single media
sand filters using quartz sand, type being declining rate filters.
Each filter shall be hydraulically designed for an overload of 20%. Filters
shall be capable of giving a run time of at least 24 hours. The number of
filters shall be in even numbers with stand by units. All filters shall be of
identical shape and size. Each filter shall have 2 half’s. In the case of vertical
flow rapid gravity sand filters; the average rate of filtration shall be 80 to 100
lpm/sqm. The filters will be served by an adjacent filter control block in
Page 311 of 553
Technical Specifications
which shall be housed the air scour and motive power plant for valve
operation and other apparatus. The main clarified water channel shall connect
to the two filter inlet channels if necessary via a chamber. The filters shall be
down-flow open rapid gravity units type or dual media filters of the divided
bed type and shall operate on declining rate principle. All filters shall be
identical in internal dimensions and shall be designed for washing using
filtered water and air scour. The air scour may precede or be concurrent with
the Wash water. The filters shall be designed so that when receiving clarified
water of the standards given in relevant clause, the minimum period between
washes is not less than 24 hours.
(a) NUMBER OF FILTER – The filters should be in even numbers and
designed for economy to filter 50.00 Million liter per day treated water ( in 22
hours working ) plus about 2.0 to 3.0 times of quantity of back wash water.
(b) RATE OF FILTRATION -
The rate of filtration shall be taken as 4.8m/hr (80 lpm/m2). The inlet and
outlet arrangements shall be designed to permit 100% overload for emergency
conditions.
(c) CAPACITY OF FILTER UNITS-
The capacity of filter should be such that the number of unit can take care of
the total quantity of water to be filtered and with optimum efficiency to keep
the filters working without undue overloading at any time.
(d) SIZE OF FILTER UNIT -
Where the filters are located on both sides of pipe gallery the ratio of length to
width of a filter box shall be about 1.25 to 1.33. A minimum 2 mt depth of
water shall be provided above filter media. The filters shall be constructed in
R.C.C. of minimum grade M-30.
(e) FILTER MEDIA -
Filter media will consist ofdual media. The Specification of media shall be as
per CPHEEO manual
(f) UNDER DRAINAGE SYSTEM -
should be designed for washing two filters at a time. It shall be of R.C.C. with
minimum grade M-30. The most preferable shape is Rectangular. The corners
of tank shall be rounded off. The top slab of tank shall be of R.C.C. minimum
grade M-30 with sufficient number of manholes and ventilators of 100mm
dia. C.I. with Cowels and the aluminium ladder of 0.45 mt. wide from top to
bottom of tank.
A float operated mechanical gauge shall be provided. The arrangement should
be fixed in such a way that during excessive wind flow it should not be
disturbed. It shall have meter scale painted with enamel paint with black and
red color on white color back ground. A RCC staircase from ground to top of
tank shall be provided by contractor. It shall have the railing either on both
sides or on one side as per site conditions.
6.4.9 APPURTENANCES -
(a) RATE OF FLOW CONTROLLERS -
Since it is proposed to provide declining rate filtration hence one rate of flow
controller shall be provided. In this case filter influent shall be entered below
the low water level of filters so relatively large influent header pipe or
channel will serve all the filters. It shall be provided with influent valve for
each individual filter.
(b) FILTER GAUGES -
It shall be provided to measure accurately the rate or flow through each filter
box and to determine the loss of head occurring at any time during the filter
run. It must be simple in operation and easy in handling by the maintenance
staff.
(c) WALK WAY -
Walk way all-round the filters minimum 1.50M width shall be provided. it
shall be fitted with railing of 0.75 M height.
(d) PIPE GALLERY-
Effluent wash and waste water pipes all together with the sluice valves are
placed in the pipe gallery should be well designed with minimum 2.00mt
width provided with a ladder or steel rungs to make it for the maintenance
staff easily accessible to the bottom. It should be well ventilated. It should
Page 314 of 553
Technical Specifications
have a sufficient slope to drain out the wash water or other leakage water. The
two pipe galleries shall be provided one gallery for effluent pipe Air and wash
water pipes and other Gallery specially for draining out the wastewater of
filters. It shall be designed by contractor and preferably of R.C.C. pipe. It
shall be connected with wastewater sump. The system will avoid the
unnecessary congestion of the pipes and avoid the hindrances in cleaning of
pipe galleries. One shall be towards the module chambers side and other
towards the influent header pipe side it should be constructed with minimum
R.C.C. grade M-30.
(e) EFFLUENT AND WASH WATER PIPE -
The effluent pipe shall be designed for a velocity of 0.9 to 1.8 mt./second and
wash water pipe for a velocity of 1.5 mt/second. These shall be C.I. double-
flanged class .Pipes confirming to I.S. 7181 - 1984 and C. I. specials shall be
confirming to I.S. 1538-1976. The sluice valve provided shall be confirming
to I.S. 14846-2000.
6.4.10 MODULE CHAMBER OF CLEAR WATER CONTROL
CHAMBER
It shall shave sufficient space to accommodate sluice valves of effluent pipes,
effluent discharge weir and clear water effluent pipe feeding to clear water
sumps. It shall have sufficient circulation space minimum 2.00 mt of ground
floor where the module chambers shall be minimum ceiling height of floor
shall be 4.00 Mt. The ground floor shall be easily accessible by providing
aluminium ladders.
Arrangement for effluent sluice valves, air blowers piping, Wash water tank
etc.: It shall be framed structure of minimum R.C.C. M-30 grade concrete. At
a height of minimum 10.00 Mt. the wash water tank shall be provided for
storing the water for washing the filters. The panels of framed structure shall
be constructed of chimney brick masonry with cement mortal 1:5 and
plastered with mortar 1:5 the ground floor as well as first floor shall have
sufficient ventilation of about 30% of floor area. As for as possible natural
ventilation shall be provided the window shall be of M.S. Z-section provided
with 4 mm thick transparent glass. The gate shall be provided on all the four
sides. The main gate shall be. made of aluminium automatically closing type
fitted with glass and the other gates one towards filter sides and other towards
chlorine room side and open area side shall be made of Z section angle iron of
size 1.20mt x 2.10 fitted with glass. The windows shall be opened outside
fitted with mosquito net with all arrangements of opening and closing the
window stoppers etc. complete. These shall be primed and painted as
approved by the Project Manager. The flooring in chamber shall be mosaic
with good finish upto 30-cm. height. The ground floor shall have drainage
arrangement to easily drain out water in case of cleaning the water from
module chamber.
6.4.11. AIR BLOWER -
The Air blowers shall be designed for a free flow of air at the rate of 36 to 45
Cum/hr at a pressure of 0.35 kg/sqcm for a duration of 5 minutes. Two air
blowers’ including100 % standby arrangements shall be provided. The
material used for the pipe and specials should be anticorrosive preferably DI,
class k-7 or C.I. Class LA double flanged and C.I. Sluice valves confirming to
I.S. 14846. These shall be mounted in clear water control chambers at about
1.00 mt depressed floor from operating floor of effluent sluice valves.
6.4.12. BACK WASH WATER PUMP:-
It shall be designed for 1.00 Hr. i.e. pump shall be in position to fill wash
water tank in 1 Hr. There shall be two pumps in which one will act as stand
by unit. These pumps shall be provided on the air blower floor. The pump
shall be of centrifugal type with a suitable motor to operate on 415+10% volt,
50 Hz. B class of insulation and degree of protection at IP-56, the suitable
Auto Transformer Starter panel, Cable, suitable rating capacitors and
Stabilizer. These pumps shall be provided and fixed by the contractor. The
pump shall be provided suitably NRV, and sluice valve of PN 1.0. The size of
the pipe to fill the wash water tank shall be designed by the contractor. The
pipe shall be C.I. double-flanged class A with bell mouth at the top. The
delivery pipe in wash water tank connecting to different filter to sluice valve
shall be designed by contractor and made of C.I. double-flanged class A
confirming to I.S. code in practice. The scour and over flow pipe also be
designed and provided by the contractor. The overflow pipe shall be
connected with the clear water sump pipeline or clear water sump whichever
in nearer. Scour pipe shall be connected with the waste water line of filter
going to waste water sump of chamber with necessary C.I. sluice valves.
6.4.13. MODULES: -
The module chamber shall be R.C.C. constructed for each filter bed
separately. It shall have two compartments. In one compartment it shall have
clear water effluent pipe with sluice valve. It shall be operated from the
operating platform. The second compartment will be used for collecting the
clear water spill over the weir; the height of weir shall be kept in order to
avoid the negative head. It shall be line with tiles of standard make, preferably
in sky blue colour. The top of the module chamber shall be covered with M.S.
framed cover divided in two parts, fixed with glass of minimum 4mm thick
the cover shall be so fixed that it should be easily opened at the time of
maintenance. The module chamber shall also have arrangement for draining
out the dirty water (at the time of maintenance). The minimum 600mm.
R.C.C. Class NP2 pipe with sluice valves should be provided. The entire
module chamber shall be connected with the one waste water line and finally
disposed of either in drain constructed in front of this block or in waste water
collection sump Sufficient head room above the module chamber shall be
provided a M.S. ladder from floor to the top of the module chamber shall be
provided.
6.4.14 FILTER CONTROL
Filters shall be of the declining rate type with filtration rates varying by +20%
of the average over a filter run length. At the start of the filter run, when the
bed is clear the filtration rate shall be 20% above the average value whilst at
the end of the filter run the filtration rate shall be of 20% below the average
value.
Clarified water shall be fed to each filter from the inlet channel through a
submerged penstock opening. At the outlet of each filter the filtered water
shall flow through an adjustable valve or 'setting valve', which shall limit the
maximum flow to 20% above average flow. The valve setting shall be
adjusted during commissioning in order to achieve the required range of
filtration rates between clean bed and dirty bed conditions to within + 20% of
the average flow though the filters. A separate valve drain shall be provided to
drain the underflow chamber. Emergency access to the underside of the filter
floor shall be provided.
Filter valves and penstocks shall be fitted with electric actuators with facility
for manual operation. Each filter shall be equipped with instruments for
measurement of the differential head across the filter bed. Measurement
accuracy shall be +2% of the measured value. Each measurement instrument
shall be equipped with stainless steel needle isolating and drain valves.
A control console for each filter shall be installed in the gallery.
These consoles shall be equipped such that the Contractor can initiate the
backwashing operation manually.
The control consoles for each filter shall include the following facilities and
indications as a minimum:
a) Start filter wash cycle -key operated push-button;
b) Manual/automatic key operated selector switch;
c) Filter water holding tank full-lamp;
d) Open/close push buttons for each actuated valve and penstock;
e) Open/close indication for each valve and penstock-lamp;
f) Filter ready for wash-lamp;
g) Filter washing - lamp;
h) Filter in service - lamp;
i) Filter out of service
j) Wash water pump tripped - lamp;
k) Air scour blower tripped - lamp
Filters shall be washed in sequence automatically under the control of a preset
timer, adjustable from 12 to 36 hours. Filter backwashing shall be inhibited to
prevent two filters washing simultaneously and also to prevent wash initiation
when the filtered water holding tank has insufficient water in storage.
Programmable Logic Controllers (PLCs) may be used for filter washing
controls, with each filter being controlled by a dedicated PLC with the
initiation controlled by a central PLC. PLCs shall be arranged so that failure
of one unit does not disable the automatic washing of more than one filter.
Lamps in the monitoring room shall indicate the state of each filter, i.e. filter
in service, filter washing and filter wash overdue.
Page 318 of 553
Technical Specifications
Filter washing time cycles shall be manually adjusted to suit the monitored
turbidity levels.
6.4.15 Filter Valves and Motive Power System
a) Butterfly valves shall be used for the filters in preference to penstocks or
sluice valves unless the penstocks or sluice valves proposed are of a size
which can be operated easily by one man.
b) Filter valves which require to be operated as part of the washing cycle
shall be operated by pneumatic power. The system shall be capable of
operation in the event of electric power failure and details shall be provided
by Contractors, as to how this will be done. The time taken to open or close
any valve shall generally be between 10-30 seconds.
c) Compressors for valve/penstocks operation duties shall be in duplicate
with duty/standby units including receivers, provided to serve only the filters.
The standby unit shall be so arranged to automatically operate if the duty unit
fails and also initiate an alarm on the filter block control room annunciator.
The rating/capacity of each compressor shall be designed to serve a total of 3
filters, and to enable valves on at least three filters to be operated
simultaneously.
d) The compressor installation shall be designed to satisfy conditions for
maximum air demand and shall ensure the duty compressor does not start
more than six times in any hour and the running time of the duty compressor
shall not exceed 35 minutes in any one hour. The standby compressor unit and
receiver shall be identical in size.
e) To avoid overheating, an integral cooling system shall be provided for
each compressor unit.
6.4.16 Piezometer Tapings
a) In two filters (to be selected by the Project Manager's Representative), six
piezometer tapings shall be provided for each filter to determine the head loss
gradient across the media.
b) The Contractor shall provide and fix on the two filter front walls in an
accessible position (with standing platform if necessary) all the necessary
puddle pipes, strainers, manometers, tubes, calibrated scales, mounting boards
and fixing brackets, interconnecting small bore tubing, cocks and fittings.
6.4.17 PAVING:-
A paving in front of clear water control chamber 4.0 mt. wide shall be
provided by contractor. The paving shall be in grooved vitrified tiles good in
appearance and color, laid over M-25 cement concrete.
6.4.18 STAIR CASE:-
The stairs made of brick masonry in cement mortar 1:4 with anti-skid tiles
shall be provided. The staircase shall be provided to connect ground level to
the floor of control room and wash water pump or air blower floor to the
operating plate from of control room.
6.4.19 CHEMICAL HOUSE:
(a) The chemicals to be added to raw water for coagulation and flocculation
will be filter alum, hydraulic lime and other coagulant aid if necessary.
Looking to the characteristics of the water only filter alum shall be sufficient.
But in certain conditions where the raw water becomes acidic in nature then
hydraulic lime shall be mixed.
(b) The minimum storage shall be for 3 months for filter alum and 3 months
for hydraulic lime and other chemicals.
(c) Store for the chemicals shall be provided below chemical dosing room.
The minimum ceiling height shall be 4 mt. In order to avoid moisture the
minimum plinth height shall be 0.90 mt. The floor should be made damp
proof and it should be filled about 0.60 mt. with sand and bituminous coating
shall be provided over it in order to avoid the moisture. The flooring shall be
of concrete with acid resistance tiles cladding on the floor and in the sides
upto 2.0 mt. height. The building shall be constructed in R.C.C. framed
structure in M-25 grade concrete and panels shall be of second class brick
masonry in cement mortar 1:6 and plaster in cement mortar 1:4. The
specification of brick shall be as given in the specifications. The roof of this
storage room shall have an opening of 2x2 mt. to facilitate lifting of
chemicals. The arrangement for lifting and weighting of chemicals shall be
provided by contractor from first floor of chemical house. Adequate
ventilation and lighting will be provided. It should be easily accessible to the
trucks for unloading the chemicals. The main entrance shall be 3.00 mt. wide
and 3.50 mt. height with rolling shutter. The height of alum stack should not
be taken more than 2.0m with 30% open space for passage.
(d) EQUIPMENT'S FOR HANDLING CHEMICALS:
The Platform type-weighting machine of standard make of capacity 2.00
tonne for weighing the chemicals shall be provided. For transportation of
chemicals from storeroom to the solution tank, an electric operated hoist of
2.00-ton capacity of approved make shall be provided. The chemical should
be loaded in the steel tray attached to wire rope.
(e) SOLUTION TANK:
A Platform for construction of solution tank at a height of about 2.00 mt. from
first floor level shall be provided. The solution tank will be designed for the
worst condition of Turbidity for alum dosing to the designed flow. The
minimum number of solution tank shall be two so that one will be stand by
unit. The capacity of tank shall be designed for 8 Hr. capacity with 0.30 mt.
free board. The feeding arrangement shall be automatic based on flow. It shall
be designed for 10% strength of solution. The solution tank shall be
constructed in R.C.C. minimum M-30 grade and inside surface shall be lined
with acid resistance material like F.R.P. or epoxy resin. The lime solution
tank shall be designed for a dose of 5% strength of lime solution using 87%
pure hydrated lime for the design flow for the period of 8 hrs. Each tank shall
have platform at least 0.75 mt. wide to allow the worker to stand for handling
the chemicals and preparation of solution the platform shall have railing up to
a minimum height of 0.75 mt. The height of the solution tank shall not be
more than 1.50 mt. from the first floor to the platform aluminum ladder 0.60
mt. wide shall be provided and it shall also be provided from solution tank
platform to top of solution tank.
(f) DISSOLVING TRAYS:
The weighted chemical shall be placed into the tray. These trays shall be
made up of cement concrete with perforations both at sides and at the bottom.
The weight of these trays shall be such so as to handle easily by the workers.
(g) CHEMICAL FEED DEVICES:
The solution feed device will depend upon the point of application. The pump
type of feeder shall be preferred, chemical feeder in which the solution from
the chemical solution tank shall be flown by pump through a strainer and
through the float valve into the orifice box. It shall include the necessary
piping arrangement with G.M. valve for drains, overflow, and delivery pipe as
per I.S. standard. It shall also have necessary agitating arrangement coupled
with motor as per standard. It shall also have the provision to return the
excess flow to solution tank.
(h). CHLORINATION:-
The chlorinator shall be designed for a dosing of 5mg/L. It shall be designed
for designed water flow. The chlorinator shall be vacuum type chlorinator
with 100% stand by.The liquid chlorine shall be supplied in toners. The
contractor shall have to make arrangement for Brand new chlorine tonners
with a nominal capacity of holding one MT of liquid chlorine. The tonners
should be as per relevant IS standard specifications. The contractor should
also submit the required test certificate and other certificate to enable these
cylinders to be put into the use. These tonners shall be taken over by the
department only after these have worked up to the satisfaction of the owner,
after O&M. The chlorinator shall be fixed up by the firm with all required
accessories. Due to corrosive nature of chlorine it should be conveyed through
either heavy wrought or steel pipe on flexible annealed copper to be tested for
35kg/cm2 working pressure. The long pipeline shall be avoided. The chlorine
gas lines shall be used. The gasket used shall be made or antimony lead (with
2 to 3% antimony) or asbestos sheet. Screwed fitting shall be forged steel
construction. Pressure indicators shall have Teflon diaphragms or silver foil
protectors. Pressure reducing valves shall be of bronze or metal with a Teflon
diaphragm.
(1) The dosing rate shall be manually set and each chlorinator shall be
equipped with a 0 to 5 mg/l scale and a manual dose setter over the complete
range.
2. Mal-operation of the duty chlorination system shall be indicated in the
chlorination room and the monitoring room in order that manual
changeover to the standby system can be initiated.
3. Chlorinator shall be fitted with a pressure switch to provide an alarm in
It shall consist of various tools appliances like gasket, Yokes Studs. Tie rods,
hoods, clamps, spanners, mild steel channels kits, screws pins etc. complete.
It shall cover the total precautionary arrangement parts, which shall be
required at the time of chlorine leakage. All the Gadgets shall be designed for
using in controlling or stopping the leakages from valves, fusible plugs, and
sidewalls of cylinder used for handling chlorine.
(m) Chlorine Residual Monitoring
i. One chlorine residual sampling and transmitting unit for settled water
shall be provided at outlet of clarifiers. Residual chlorine monitoring
shall be arranged by collecting water from the clear water reservoir.
ii. The chlorine residual monitoring system shall be designed to measure
free available chlorine. The signal from the measuring cell transmitter
shall be indicated on the panel in the chlorine house with repeat
indication and recording in the Control Block monitoring room.
iii. A chlorine residual recorder shall be installed as a floor mounted unit in
the chlorination room and actuated by a 4 to 20 mA signal from a
residual chlorination measurement cell mounted above ground level in
the clear water reservoir outlet chamber.
iv. This cell shall be fed with a continuous supply of treated water from the
outlet main of the clear water reservoir. A suitable sampling pump shall
be supplied to feed the water to the measuring cell. A signal shall be
transmitted to the monitoring room and shall be used to activate a
chlorine residual indicator to be mounted in the monitoring room panel.
v. High and low chlorine residual level alarms shall be annunciated in
the monitoring room and in the chlorination room.
vi. All necessary sampling pumps, pipe work and isolation valves, for
delivering clear water to the cell shall be provided.
6.4.20 FIRE EXTINGUISHING - ARRANGEMENT:-
Suitable fire extinguishers shall be provided and placed in different position
in pump house and chlorine storage room besides buckets filled with sand and
placed at different places in clear water control chamber, chlorine room pump
house shall also be provided.
6.4.21 Water Sampling:
5) First Aid Facility - Emergency Oxygen Kit 5 No. First Aid Box complete
for artificial respiration to neutralize Inhaled chlorine effect - 4 No. First Aid
printed chart. It shall be mounted on a glass framed wooden board in chlorine
Page 326 of 553
Technical Specifications
room.
6) Weighing Machine - The weighing machine of standard make of two ton
capacity shall be provided to record the weight of cylinder.
7) Emergency safety showers and eye wash- the contractor shall provide two
safety showers and eye bath units. These units shall be installed at location
approved by Project Manager.
6.4.24. UNLOADING ARRANGEMENT: -
An arrangement with chain pulley block of 2 tons capacity at a height of
minimum 5.00 m. supported on M.S. beam section, shall be provided at the
entrance of chlorine storage room to unload the toners.
6.4.25 CLEAR WATER SUMP:-
The clear water from the module chamber shall be conveyed to the clear
water sumps either through pipe or channel designed for a velocity 0.9 to 1.8
m/sec. The selection of pipe or channel shall be made on the basis of
economy. The pipe if openly laid according to level shall be D.I. class K-7
Tyton joints and if covered then R.C.C. if the channel is provided, then it
should be of R.C.C. M-30 grade and covered with the R.C.C. cover slab it
shall be in horse shoe shape as for as possible. The levels shall be so fixed up
so that the tank up to water depth shall be totally underground. The tank shall
be designed for a capacity for a minimum detention period of 30 minutes. A
minimum free board of 0.5 m should be provided below the roof beam. The
floor of sump shall be designed in such way that it shall have a slope of 1:20
towards the inlet end. The shape of tank may be circular or rectangular as per
design and economy consideration preferably sump should have two
compartments connected with each other by sluice valves in order to facilitate
the cleaning of sump. It should be constructed in R.C.C. with a minimum
grade M-30 concrete and shall be provided with pressure release system to
relieve the uplift pressure. The sump should be covered at top with R.C.C.
slab. The top slab shall have adequate number of manhole chambers of size
0.9 x 1.20 m in each compartment fixed with M.S. cover and frame painted
with primer and anticorrosive paint and locking arrangement. There should be
100 mm. dia C.I. or M.S. ventilators painted with primer and anticorrosive
paint with C.I. cowels in each quadrant of beams on the roof shall be
provided. The top of roof shall be sloped out ward to drain out rain water
Page 327 of 553
Technical Specifications
easily. An aluminum ladder 0.45 mt. wide in one-man hole of both chambers
shall be provided by contractor. The inlet and outlet pipes shall be located at a
diagonally opposite end in order to minimize the short-circuiting and
turbulence effect. An overflow pipe designed to maintain level shall be
provided. The scour pipe shall be laid from bottom of clear water sump to
waste water sump. All the pipes shall be fitted with sluice valve as per I.S.
standard and wherever necessary provided with inspection chambers.
A locally mounted dial type float operated level indicator to indicate the water
level shall be provided along with automatic level indication in control room.
6.4.26. CLEAR WATER PUMP HOUSE:-
It should have sufficient space to accommodate at least 4Nos of centrifugal
pumps including cable ducts, surge protection (If so required), NRV, suction
pipe etc. complete. There shall be one pump house of suitable size and the
minimum height shall be provided in order to accommodate the function of
Gantry. The elevation of building should be such as to give an architectural
view. It shall have one additional store room of size 6.00 x 5.00 mt. L.T.
switch gear room of size 3.00 x 6.00 mt. and one office room of size 5.00 x
4.00 and attached toilet block. The size of pump house be decided by
considering the actual space required for providing pump sets and other
ancillary items with provision for future expansion. Additional space shall be
provided for one pump set and also for generator set if used in emergency.
Sufficient minimum space between the two pumps shall be provided for
circulation and the distance of pump from the sidewall should also be
minimum 2.00 mt. The distance of pumps from rear wall shall be decided to
accommodate the suction pipe, NRV, sluice valve to each pump individually.
The level of pump floor may be depressed as compared to the general floor
level in pump house to avoid the negative head or negative suction. Space for
LT/HT ACB / OCB, shall also be provided for generator set if used in
emergency. The ducts for laying of electric cable from substation shall be
provided. It shall be of R.C.C. covered with chequered M.S. Plate and will
have minimum size 0.6 m x 0.9 m or designed M-20 grade and chimney brick
masonry in cement mortar 1:6 and plastered with C.M. 1:4. The capacity of
the gantry crane to be provided under this contract shall be electrically
hoisting and manually moving mounted on the rails or girders to move
on pumps- motors for lifting at the time of maintenance. The floor of
Page 328 of 553
Technical Specifications
pump house and all other units shall be mosaic/ironite laid over 1:2:4 cement
concrete 40mm. thick. The main gate shall be of size 3.00 x 3.50m shall be
rolling shutter, Office room, L.T. switch gear room and store room shall be
with salwood chaukhat and 40mm thick flush doors as per I.S. specification
including doors stoppers, tower bolts etc. complete. The door or the W.C.
block shall be either M.S. Fabricated or flush doors. The window in pump
house shall be about 20% of total area or provided in each panel (except
where doors are provided). The window shall also be the Z-Section fitted with
4 mm thick glass, tower bolts and all other necessary arrangements as per I.S.
specification. Minimum 12 numbers of exhaust fan 450 mm. dia shall be
provided. The exhaust fan shall be of Standard Make. A ramp shall be
provided to connect the Ground level to the floor of pump house in main only
and in other doors and in depressed floor of pump house wherever necessary
steps shall be provided. The minimum plinth height of pump house shall be
0.60 M. It shall provide easy loading and unloading of pumps / motors from
trucks by gantry.
Site roads shall be a minimum of 3.5 m wide with a 1m shoulder either side.
The carriageway shall have camber of 1 in 40 to drain rain water from its
surface. A concrete gutter shall be provided at either side of the road. The
inner radius of bends shall allow the easy passage of large lorries. Parking for
at least 8 Vehicles shall be provided at the administration building.
The sub base shall be 150 mm of hard granite cubes. The base shall be two
layers each a minimum of 75mm thick, the top layer shall be 40mm
downgraded metal of 100mm as placed thickness compacted to 75 mm, the
bottom layer is 65mm downgraded metal of 100mm as placed thickness
compacted to 75mm. The wearing coat will be asphalt concrete 20mm thick
or the contractor may choose to construct CC road.
6.4.34 SITE DRAINAGE: -
The site drainage system shall be designed to dispose of overflows from tanks
and rain water in a manner to prevent damage to any structures. The drainage
may use pipelines, culverts, conduits or open channels to convey the water to
a safe disposal site leading to nearby water body. Open channels shall be
lined.
6.4.35 TELEPHONE SYSTEM:-
A telephone system shall be provided.
6.4.36 PROCESS CONTROL:
(i) General
The Contractor shall monitor summary status of all the treatment works as
follows: water level raw water and clear water reservoirs;
process flows and totalized quantities;
water quality values
status of each process;
External lighting shall be employed throughout the site to illuminate all site
roads, turning areas, car parks, paths, tanks and building perimeters.
The following average levels of illumination are required:
Car Parking areas 5 lux
Access Roads, Pedestrian Walkways 10 lux
Lorry Loading and turning Areas 20 lux
Top of Tanks 50 lux
Building Perimeters 50 lux
The access road lighting scheme shall be designed in accordance with the
requirements of BS 5489: Part 3: 1989 (group B5/6). Column heights shall be
5 meters and each lantern shall incorporate a photocell for control. At each
position where a section of road lighting columns is fed a selector switch shall
be provided having the following functions
ON - Access road lighting permanently
ON OFF - Access road lighting permanently
AUTO - Access road lighting under photocell control
Some flexibility in positioning of road lighting units is allowed but generally
units shall be positioned at intersections and junctions with spacing not
exceeding 30 metres + 10%.
6.5 Test for Water Tightness of Structures : All liquid retaining structures
including underground reservoir, and different units of water treatment plant
like inlet chambers, flocculator, clarifier, filter etc. shall be deemed to be
satisfactory water tightness test as per relevant clause of IS:3370. The
Contractor shall fill the reservoir to MWL for conducting the water tightness
test of the reservoir. The filling of the reservoir shall be gradual and not more
than 15 cm of raise in water level per day shall be permitted. Full water level
is to be maintained for 24 hours. During this period the structure under full
working head of water shall not develop defects which will endanger its
stability nor shall it show signs of any leakage. The fall in water level of the
reservoir shall not be more than 10 mm. in 24 hours after which the
satisfactory test certificate will be issued by the Project Manager. The
Contractor shall rectify the defects noticed and carry out the tests again and
repeat the testing operation till successful result is obtained and accepted by
the Project Manager.
7. ELEVATED SERVICE RESERVOIR:-
height varying from 15 to 18 m including a watchman quarter and compound wall etc.
with but not limited to the following:
(NOTE:- Design requirements may change as per the Location, capacity and staging of
ESR.)
I. Dog legged R.C.C. Stair case and Valve chambers
II. Pipe line arrangement including providing and laying pipes and specials of
required diameter, length.
III. Providing and fixing required Valves and Sluice gates.
IV. Providing and fixing of Lightening Conductor, Water Level Indicator,
Aluminium Ladder, Railing, and Manholes with locking arrangement and
Ventilation hole arrangements, internal lighting arrangement and external
campus electrification etc.
V. Protection work all around the Reservoir, Weather Shield Apex painting,
suitable colour enamel painting, cleaning, finishing and handing over finished
work to the department.
7.2.2 The Contractors shall submit the general drawings of proposed ESRs i/c
pipeline arrangement with the Project Manager. They will further be required to
submit detailed design, drawing, approximated quantities of cement, steel, pipes,
valves, gates and specials etc and calculation in five copies within three months from
the effective date, duly checked from the Government Engineering College, as directed
for scrutiny and approval of the competent authority. The responsibility for design
construction/structural stability and water tightness will however rest solely with the
contractor.
7.2.3 Construction of RCC Elevated Service Reservoirs, which consists of
central ventilation shall be as under:-
I. The reservoir shape should be circular with flat bottom and central
ventilation lantern so as to incorporate architectural effect to give an impressive
view. Any other shape which gives architectural impressive view better than the
above may be considered as per the decision of Project Manager.
II. Free board of minimum 50cm should be provided below lowest part of roof
beam slab structure. The minimum 50cm free board should be everywhere
below bottom of straight beam, ring beam, and roof slab etc.
III. The Contractor should assess the bearing capacity of strata at the proposed
site by conducting the required tests. It is responsibility of contractor to conduct
bearing capacity test if required and bear financial charges towards it. The
department will not make any payment towards it.
7.2.4 Design criteria
(a) Foundation shall be designed as per ascertained S.B.C. of soil as
given above and other soil parameter.
(b) The following load and forces should be considered
(i) Dead Load
(ii) Live Load – static and dynamic load due to flow and falling
of water
(iii) Load due to water
(iv) Wind pressure as per IS 875-1969
[A] PIPES:-
[1] Each compartment shall be provided with Inlet pipe, Outlet pipe, Overflow
pipe and scour pipe. Thus, there will be one Inlet, one Outlet, one Overflow and
one scour pipe in each compartment of the reservoir.
The diameter of different type of pipes is given in Section 7.1
The inlet pipe shall be as far away from the outlet pipe as possible and outlet
should be sufficiently above the floor level so as to keep it above deposited
sediment at bottom of reservoir.
The scour pipe shall be provided at the bottom. The top of bell mouth on inlet
shall be at FTL and overflow about 5 Cms. above the FTL. The overflow in any
case shall not be connected to the outlet pipe.
The cast iron or stainless steel grates of 20 mm x 20 mm on enlarge diameter of
bell mouth of outlet and scour pipes shall be provided in order to avoid the
accident during maintenance.
(2) Specifications:-
The D.I. Double Flanged pipe should be conforming to IS:8329-2000 and
while double flanged cast iron pipe should confirm to IS:7181 latest.
(B) Specials:-
All specials required for this work of pipe line arrangement, such as duck foot
bends, puddle collars, bell mouths, bends, tees and end caps etc. shall be
provided and fixed in position as per relevant I.S.
The bell mouth required to be embedded in the concrete should be specially
manufactured with their collars as per requirement. The duck foot bend of all the
pipe shall be grouted minimum sufficiently below ground level.
Valves and Gates:-
The contractor should provide and fix in desired position the CI/DI valves and
gates for easy and effective working.
All valves should be I.S. mark and inspection and testing certificate should be
produced to Project Manager.
The double-faced sluice gate has been provided to pass water flow from one
compartment to other compartment. In close position gate face should be
capable of resisting water pressure force. There should be no leakage in closed
position when water pressure of full depth is applied on one side and other side
being empty.
For convenience in operation and maintenance of scheme, the flow controller i.e
valves shall be of remote operation type to facilitate their operation from
centralized control room at WTP or any other specified remote location.
7.3 Flow Measurement:-
The arrangement for water quantity reaching to the tanks by providing and
installing in position electromagnetic flow meter of suitable diameter in inlet
pipe should be made by the contractor. Contractor should provide arrangement
such that the flow meters to be installed before each ESR and at other place as
per design shall give their reading on screen at central control room or any other
specified remote location. In addition to the above, arrangements are also to be
made for measuring of three quality parameters – Ph, residual chlorine and
turbidity at the inlet of WTP, Clear water sump and outlet of each tank and
display of the same on screen at control room or any other specified remote
location..
7.4 Lightening conductor, Water level indicator, Aluminum ladder, Railing,
Manholes, ventilation holes arrangement, Internal lighting arrangement
and external campus lighting arrangements etc.
1 Lightening conductor:-
of water in ESR tank on screen at central control room or any other specified
remote location.
3 Aluminium Ladder:-
The aluminium ladder form top of roof to the inside bottom of container shall
be provided. It shall comprise of not less than 600 mm. long double round bar
@ 250- mm. c/c. ladder shall be rigidly fixed.
4 Railing:-
Railing should be provided on the top of roof slab along the whole
circumference and the sides of staircase as per specifications given in relevant
chapter.
5 Manhole covers:-
Manholes of minimum size 0.90 m x 0.75 m shall be provided. The covers
shall comprise of suitable angle iron frame and 10 gauge thick MS sheet,
crossed by suitable flat inside, with locking arrangement.
6 Ventilators:-
The suitable air vent shall be provided as directed by Project Manager.
7 Electrification:-
The electrification inside and outside should be done in such a manner that
standard level of illumination is obtained inside the reservoir and in the
campus. All electrical fixtures, wires etc. shall be ISI marked. The
specifications shall be as given in relevant chapter.
7.5 Protection work all around the Reservoir, Weather Shield Apex painting and
colour enamel painting of approved colour, cleaning, finishing:-
1 Protection work
Protection work all around each ESR shall be provided. It shall be circular in
shape and 2.0 m in width around the outer edge of wall. It shall have 1:60 slope
from center and a drain be constructed all around the reservoir. The protection
work shall be M-15 grade concrete.
2 Weather Shield painting:-
Two and more coats suitable colour Weather Shield as directed by Project
Manager shall be done after the testing of water tightness.
3 Colour enamel painting:-
All iron work, railing and pipes etc. shall be painted with two or more coats of
black Japan or suitable colour enamel paint over primer as directed by Project
Manager.
4 Finishing:-
Although concrete shall be off shutter finish means no plaster shall be applied
over concrete to make it smooth finish, but in unavoidable circumstances if
plaster is done, then no extra payment shall be made.
7.6 Inspection and testing of concrete structure:-
1 In order to ensure that the construction complies with the design and all the
structural requirement, clause No. 17 of IS 456-2000 shall be followed. It should
also be noticed that during construction the settlement of sump due to self
weight during construction should be noticed by proper procedure.
2 Water Tightness Test
After the completion of structure it shall be tested for water tightness. Initially
the sump shall be filled gradually to ensure uniform settlement all over the area.
The full supply should reach in a period of not less than 72 hours. At the time of
testing verticality of sump should be checked by theodolite as per IS 3370 (part I
general requirement) code of practice for concrete structures for the storage of
liquids specifies water tightness test at full supply level.
After seven days period for observation after filling with water the external face
of sump should not show any sign of leakage and remain apparently dry.
3 The water for testing and pump for lifting water shall be arranged by the
contractor at his own cost.
4 The contractor shall give the test for water tightness to the entire
satisfaction of the department. The responsibility of structural stability shall
solely be rest on the contractor.
8. DISTRIBUTION SYSTEM
Providing, laying, Jointing and field testing of Ductile Iron (DI) confirming to
IS 4984/ 14151/ 12786/ 13488 with necessary jointing material like
mechanical connector or jointing pipes by heating to the ends of pipes
with the help of Teflon coated electric mirror/ heater to the required
temperature and then pressing the ends together against each other, to form a
monolithic and leak proof joint by thermosetting process. It may be required to
be done with Jacks/Hydraulic Jacks/ Butt fusion machine. (50mm and above
fusion jointed and below 50mm mechanical jointed) PE – 100.
600 500 450 400 300 280 250 200 160 140 110
2 Colour
The color of the pipe shall be black.
3 Materials
The material used for the manufacturer of pipes should not constitute toxicity
hazard, should not support microbial growth, should not give rise to unpleasant
taste or odour, cloudiness or discoloration of water. Pipe manufacturers shall
obtain a certificate to this effect from the manufacturers of raw material by any
reputed organization as per the satisfaction of the Project Manager.
4 RawMaterial
(a) Resin used to manufacture the HDPE pipes shall be 100% virgin PE
Black pre- compounded confirming to IS: 4984, IS: 7328 and ISO: 4427-2007
(latest version). The resin proposed to be used for manufacturing of the pipes
should also comply with the following norms as per ISO 9080-2003 (latest
version).
(b) The resin should also have been certified by an independent laboratory of
international repute like Bodycote / Slevan / Advantica for having passed 10,000
hour long term hydrostatic strength (LTHS) test extrapolated to 50 years to show
that the resin has a minimum MRS of over 10MPa. There should not be any
brittle knee at 80OC before 5000 hours. Internal certificate of any resin
manufacturer will not be acceptable.
(c) Certificate from reputed organization OR Raw material Contractor for
having passed the full scale rapid crack propagation test as per ISO 13478. High
density Polyethylene (HDPE) used for the manufacture of pipes shall conform to
designation PEEWA-50-T-003 of IS 7328. HDPE conforming to designation
PEEWA-50- T-003 of IS:7328 may also be used with the exception that melt
flow rate (MFR) shall not exceed 1.10 g/10 min. In addition the material shall
also conform to clause 5.6.2 of IS:7328.
(d) The specified base density shall be between 940 kg/ m³ and 958 kg/ m³
(both inclusive) when determined at 27°C according to procedure prescribed in
IS 7328 The value of the density shall also not differ from the nominal value by
more than 3 kg/ m³ as per 5.2.1.1 of IS 7328. The MFR of the material shall be
between 0.20 and1.10 (both inclusive) when tested at 190°C with nominal load
of 5 kgf as determined by method prescribed in IS 2530. The MFR of the
material shall also be within ± 20 percent of the value declared by the
manufacturer.
(e) The resin shall be compounded with carbon black. The carbon black
content in the material shall be within 2.5 ±0.5% and the dispersion of carbon
black shall be satisfactory when tested as per IS:2530.
5 Anti-oxidant
The percentage of anti-oxidant used shall not be more than 0.3 percent by mass
of finished resin. The anti-oxidant used shall be physiologically harm less and
shall be selected from the list given in IS:10141.
6 Reworked Material
Pipes shall be free from all defect including indentations, delaminating, bubbles,
pinholes, cracks, pits, blisters, foreign inclusions that due to their nature degree
or extent detrimentally affect the strength and serviceability of the pipe. The
pipe shall be as uniform as commercially practicable in colour opacity, density
and other physical properties as per relevant IS Code or equivalent International
Code. The inside surface of each pipe shall be free of scouring, cavities, bulges,
dents, ridges and other defects that result in a variation of inside diameter from
that obtained on adjacent unaffected portions of the surface. The pipe ends shall
be cut clearly and square to the axis of the pipe. IS 4984:1995 will be followed
for visual appearance, Handling, Transportation Storage and Lowering of pipes
During handling, transportation, storage and lowering, all sections shall be
handled by such means and in such a manner that no distortion or damage is
done to the section or to the pipes as a whole.
The following procedures should be followed so as to eliminate potential
damage to pipes and fittings and to maintain maximum safety during unloading,
lifting and lowering.
Pipes must not be stored or transported where they are exposed to heat
sources likely to exceed 60 0C.
Pipes shall be stored such that they are not in contact with direct sunlight,
lubricating or hydraulic oils, petrol, solvents and other aggressive materials.
Scores or scratches to a depth of greater than 10% or more of wall thickness
are not permissible; any pipes having such defects should be strictly rejected.
PE pipes should not be subjected to rough handling during loading and
unloading operations. Rollers shall be used to move, drag the pipes across any
surface.
Only polyester webbing slings should be used to lift heavy PE (>315mm)
pipes by crane. Under no circumstances, chains, wire ropes and hooks be used
on PE pipes.
Pipes shall not be dropped to avoid impact or bump. If any time during
handling or during installation, any damage, such as gouge, crack or fracture
occurs, the pipe shall be repaired if so permitted by the competent
authority before installation.
During coiling care should be taken to maintain the coil diameter at or above
the specified minimum to prevent kinks. Coiling shall be done when the pipe
attains the ambient temperature from the extruder. In uncoiling or recoiling care
should be taken that sharp objects do not scour the pipe.
When releasing coils, it must be remembered that the coil is under tension
and must be released in a controlled manner. The end of the coil should be
retained at all times, then the straps released steadily, one at a time. If the coil
has bands at different layers of the coil, then they should be released
sequentially starting from the outer layers. The amount of the energy locked up
in the coil will depend on the size of the pipe, the SDR of the pipe, and the size
of the coil.
Straight lengths should be stored on horizontal racks giving continuous
support to prevent the pipe taking on a permanent set
Bare coils shall be wrapped with hessian cloth for long distance (> 300Kms)
transportation. The truck used for transportation of the PE pipes shall be
exclusively used of PE pipes only with no other material loaded – especially no
metallic, glass and wooden items. The truck shall not have sharp edges that can
damage the Pipe.
Pipes manufactured at factory are to be carried to the site of work directly or
stacked suitably and neatly along the alignment/road side/elsewhere near by the
work site or as directed by the Project Manager.
Damages during transit, handling, storage will be to the Contractor’s account
and replacement for such pipes has to be made by the Contractor without any
extra cost as directed by the Project Manager.
Lowering, Laying of Pipes
Each pipe shall be thoroughly checked for any damages before laying and
only the pipes which are approved by the Project Manager shall be laid.
While installing the pipes in trenches, the bed of the trench should be level
and free from sharp edged stones. In most cases, the bedding is not required, as
long as the sharp and protruding stones are removed, by sieving the dug earth,
before using the same a backfill material. Whilelaying in rocky areas suitable
bed of sand or gravel should be provided. The fill to about 10 to 15 cm above
the pipe should be fine sand or screened excavated material. Where hard rock is
met with, bed concrete M15, 15 cm or 20cm thick sand bed as approved by the
Project Manager may be provided.
As PE pipes are flexible, long lengths of fusion-jointed pipes having joints
made above ground can be rolled or snaked into narrow trenches. Such trenches
Page 350 of 553
Technical Specifications
4 Trenching:-
The excavation of trenches shall be carried out by hand or machines. The width
of trench shall be kept to a minimum consistent with the working space required.
At the bottom, between the faces, it shall be 150 mm clearance on either side of
the pipe or as required at site. However this is for the safety of the trench, the
method of laying and jointing the pipe and the need to avoid damage to pipes.
8.5 Jointing of Pipes
The pipe shall have Butt Welded jointing system that shall provide for fluid
tightness for the intended service conditions.
8.6 Bedding, Backfilling and Compaction
(i) Bedding
In case of sandy strata no separate bedding is required. However the bottom face
/ trench bed where pipe shall be placed shall be compacted to provide a
minimum compaction corresponding to 95% of maximum dry density. The pipe
bedding should be placed so as to give complete contact between the bottom of
the trench and the pipe. The minimum cover over buried pipe should be 1 m.
(ii) Back Filling
Backfilling should be placed in layers not exceeding 15cm thickness per layer,
and should be compacted to a minimum of 95% maximum dry density. The
refilling should be done on both sides of pipe together and height difference in
earth fill on each side should not be more to cause lateral movement of pipe.
Most coarse grained soil are acceptable. This may comprise of gravel or sand.
However silty sand, clayey sand, silty and clayey gravel shall not be used unless
proposed to be used in conjunction with gravel or clean sand.
It is very important that the pipe zone backfill material does not wash away or
migrate in to the native soil. Likewise, potential migration of the native soil in to
the pipe zone backfill must also be prevented.
Heavy earth moving equipment used for backfilling should not be brought until
the minimum cover over the pipe is 90 cm in the case of wide tracked bulldozers
or 120 cm in the case of wheeled roaders or roller compactors.
Compaction
8.10 Manuals
Technical Manual on PE pipes including precautions to be taken during
operation of the pipeline.
8.11 Flanges
All flanges employed in the project must be compatible whatever material used.
8.12 Marking
All pipes shall be marked as per Clause 10 of IS 4984-1995.
8.13 Packing and Transport
The pipes should be preferably transported by road from the factory and stored
as per the manufacturer specifications to protect damage.
8.14 Summary of quality Tests:
1. Quality Mark : Pipe: IS 4984
2. Material : As per IS 4984. However only virgin resin is
allowed, reworked material is not allowed.
3. Grade of Material : PE 100 as per IS 4984 (Certificate from raw
materialmanufacturer is required).
4. Pressure Rating : Minimum PN 10 or above as per requirement.
5. Colour : as per IS 4984
6. Dimensions of Pipe
Diameter : The nominal diameter (outside)
Length :
i. For diameter 90 mm and 110 mm: 100 meter (if pipes are supplied
in length less than 100 m than the cost of extra joints will be borne by the
contractor.)
ii. For diameter more than 110 mm: minimum 6 meter. (Tolerance as
per IS 4984)
7. Visual Appearance : as per IS 4984.
Page 356 of 553
Technical Specifications
11. Quality Assurance : Quality Assurance Plan shall be got approved by the
employer before production start.
Note: All remaining parameters / specifications are as per respective BIS
specifications.
8.15 Inspection and Testing:
The inspection and testing of the sample pipes shall be carried out as per
relevant IS and/or ISO standards (latest version) by the CEIL (Certification
Engineers International Ltd.) or CIPET (Central Institute of Plastic engineering
and Technology) or any other agency approved by the MPJNM, in the
manufacture’s works before dispatch and / or picking random samples of pipe
from the work site.
8.16 Field Hydraulic testing of the pipelines Sectional tests
After laying and jointing the pipeline shall be tested for tightness of barrels and
joints, and stability of thrust blocks in sections approved by the Project
Manager. The length of the sections depends on the topographical conditions.
Preferably the pipeline stretches to be tested shall be between two chambers (air
valve, scour valve, bifurcation, other chamber). At the beginning, the Contractor
shall test stretches not exceeding 1 km. After successful organization and
execution of tests the length may be extended to more than 1 km after approval
of the Project Manager. The hydraulic testing shall have to be commenced
immediately after laying and jointing of 1 km reach is completed.
The water required for testing shall be arranged by the contractor himself. The
Contractor shall fill the pipe and compensate the leakage during testing. The
Contractor shall provide and maintain all requisite facilities, instruments, etc. for
the field testing of the pipelines. The testing of the pipelines generally consists
in three phases: preparation, pre-test/saturation and test, immediately following
the pre-test. Generally, the following steps are required which shall be
monitored and recorded in a test protocol.
Complete setting of the thrust blocks.
Partial backfilling and compaction to hold the pipes in position while leaving
the joints exposed for leakage control
Opening of all intermediate valves (if any)
Fixing the end pieces for tests and after temporarily anchoring them against
the soil (not against the preceding pipe stretch) at the lower end with a precision
pressure gauge and the connection to the reciprocating pump for establishing the
test pressure at the higher end with a valve for air outlet
If the pressure gauge cannot be installed at the lowest point of the pipeline, an
allowance in the test pressure to be read at the position of the gauge has to be
made accordingly
Slowly filling the pipe from the lowest point(s). The water for this purpose
shall be reasonably clear and free of solids and suspended matter
Complete removal of air through air valves along the line.
Slowly raising the pressure to the test pressure while inspecting the thrust
blocks and the temporary anchoring.
Keeping the pipeline under pressure for the duration of the pre-test /
saturation of the lining by adding make-up water to maintain the pressure at the
desired test level. Make up water to be arranged by Contractor himself at his
own cost.
Start the test by maintaining the test pressure at the desired level by adding
more make-up water; record the water added carefully and the pressure in
intervals of 15 minutes at the beginning and 30 minutes at the end of the test
period.The pipeline stretch will pass the test if the water added during the test
period is not exceeding the admissible limits. No section of the pipe work shall
be accepted by the Project Manager until all requirements of the test have been
Page 358 of 553
Technical Specifications
obtained.
Water used for testing should not be carelessly disposed off on land which
would ultimately find its way to trenches
On completion of a satisfactory test any temporary anchor blocks shall be
broken out and stop ends removed. Backfilling of the pipeline shall be
completed.
After testing and commissioning the contractor shall flush the pipes with a
velocity not less than 1 m/s or as approved by the Project Manager. Disinfection
of drinking water pipelines should be done by Contractor.
conforming to IS: 14846 at different locations for emptying the pipeline for
cleaning purposes with locking chambers.
ISI marked Air valves of CI/DI shall be provided, wherever necessary with
locking chambers.
8.20 GM/ Brass Ferrules-
The ferrules for connection with HDPE shall generally conform to IS:
2692/1984 (Reaffirmed 2005). It shall be of nonferrous materials with a CI bell
mouth cover and shall be fitted with a screw and plug or valve capable of
completely shutting off the water supply to the communication pipe, if and when
required.
The size of ferrule should not exceed a quarter of the nominal diameter of the
main and also be less than the size of the service pipe/connection pipe.
8.21 Compression Fittings-
Compression fittings used for House service connection should comply as per
ISO 14236 with Threaded metal inserts –SS 304 with BSP Threads
Pressure Testing-
The pressure rating of compression fittings should be as per clause 8 of ISO
14236 which shall be PN16
Dimensions-
The Dimension of compression fittings shall be as per clause 7.1 of ISO 14236
Performance Requirements-
The compression fittings shall be tested as per ISO 14236. Following Test
methods shall be performed.
Leak tightness under internal pressure.
Leak tightness under Internal Vacuum.
Long term Pressure Test for Leak tightness for assembled joint
MRS Value as per ISO 9080
Resistance to Internal pressure.
The saddles shall be single strap type up-to pipe sizes of NB 600 and service
outlet of ½”,¾” and 1”.The saddles shall be double strap type for pipe sizes
above NB 600 or when the service outlet is 1 ¼”, 1 ½” or 2”. Fasteners shall be
of threaded nut-bolt-washer type. Nut- bolts of size ½” (M12) shall be used for
saddles of size up to 4” (NB 100) and Nut-bolts of size 5/8” (M16) shall be used
for saddles of size 6” (NB 150) and above.
The sealing between the saddle and mains shall be obtained by using a profiled
elastomer seal matching to the curvature of the pipe. The seal shall be of
elastomer type, suitable for all potable water applications. The Material of
construction of the body, straps, fasteners etc. shall be of a non-corrosive
material such as engineering plastic (PE/PP) or stainless steel or a combination
of both or DI with epoxy coating. The design of the saddle body should be such
that, the service connection outlet metal insert shall project out towards pipe side
and align with the hole drilled on the pipe to ensure positive locking against
rocking or creeping on the pipe, as might be caused by vibration, pressure or
excessive external loading. The clamp saddles shall be suitable for maximum
working pressures up-to 10 bars.
(i) Saddle Body: Non corrosive Engineering Plastic body moulded with
Stainless steel/DI with epoxy coating threaded metal insert for tapping outlet.
Also, the stirrup metal plate shall be duly embedded in the plastic body, except
at the place of nut-bolt lugs. Threading size and dimensions shall conform to
IS:554. The body shall have retaining cavity housing for internal and external
retention of the elastomeric seal. Sealing shall be achieved by pressure exerted
by the body while fastening the saddle straps and body on the pipe.
(ii) Saddle Strap: Saddle straps shall be made of stainless steel 304 grade /
plastic strap to prevent corrosion over the long service life.
Strap Insulation: Elastomeric (rubber) insulation / lining shall be such that none
of the Stainless Steel Strap is in direct contact with the pipe. It shall ensure a
firm non slip grip mounting on the pipe to prevent the saddle from rocking or
creeping on the pipe, as might be caused by vibration, pressure or excessive
external loading.
(iii) Saddle Seal: It shall be virgin rubber SBR Grade 30 / NBR (NSF 61
approved). It shall be of type pressure activated hydro-mechanical design. It
shall be contoured gasket to provide a positive initial seal which increases with
increase in the line pressure. Gasket shall be gridded mat, with tapered ends,
with the outlet section having O-ring contacting the saddle body multiple O-
rings contacting the pipe, preferably with a Stainless steel reinforcing ring insert
moulded to prevent expansion under pressure.
All pipes will be marked as per Clause 18 of IS 8329 and show as below:
· Manufacturer name/ stamp
· Nominal diameter
· Class reference
· A white ring line showing length of insertion at spigot
ii) Packing and Transport
The pipes should be preferably transported by road from the factory and stored
as per the manufacturer specifications to protect damage
iii) Hydraulic Testing
Factory test shall be as per IS:8329/ISO standard and field hydraulic test shall be
carried out for the distribution net work at pressure 12 kg/ sq. cm.
iv) Specials for Ductile Iron Pipes
(a) General
This specification covers the general requirements for Ductile Iron (DI) fittings
suitable for Tyton joints to be used with Ductile Iron pipes with flanged and
Tyton jointing system.
(b) Types of specials
The following types of DI fittings shall be manufactured and tested in
accordance with IS: 9523 or BS: 4772/ ISO standard.
· flanged socket
· flanged spigot
· double socket bends (900, 450, 22 1/20, 11 1/40)
· double socket branch flanged tee
· all socket tee
· double socket taper
· retrained joints
. Collars
All the fittings shall be of class K-12
(c) Supply
All the DI fittings shall be supplied with one rubber ring for each socket. The
rubber ring shall conform to IS: 12820 and IS: 5382 as described in the
preceding chapter.
Flanged fittings shall be supplied with one rubber gasket per flange and the
required number of nuts and bolts.
v) Lubricant for ductile iron pipes and specials
(a) General
This section covers the requirements for lubricant for the assembly of Ductile
Iron pipes and specials suitable for Tyton push-in rubber ring joints.
(b) Specification
The lubricant has to have the following characteristics:
· must have a paste like consistency and be ready for use
· has to adhere to wet and dry surfaces of DI pipes and rubber rings
· to be applied in hot and cold weather; ambient temperature 0 - 50°C ,
temperature of exposed pipes up to 70°C
· must be non toxic
· must be water soluble
· must not affect the properties of the drinking water carried in the pipes
· must not have an objectionable odour
· has to inhibit bacterial growth
· must not be harmful to the skin
· must have a shelf live not less than 2 years
(c) Acceptance tests
· They shall be conducted in line with the provisions of the IS 9523
(d) Packing
All the DI fittings shall be properly packed with jute cloth. Rubber rings shall be
packed in polyethylene bags. Rubber rings in PE bags and nuts, bolts etc. shall
be supplied in separate jute bags.
The fittings should also be supplied by the manufacturer of the pipes. They
should preferably be manufactured by the manufacturer of the pipes. In case
they are not, it will be the responsibility of the manufacturer of the pipes to have
them manufactured from a suitable manufacturer under its own supervision and
have it tested at his/sub contractor’s premises as per the contract. The pipe
manufacturer will however be responsible for the compatibility and quality of
the products.
vi) Summary of Quality Tests
(a) Scope:
Supply of Ductile Iron (DI) pipe with EPDM rubber gasket for Drinking water.
(b) Specification
Quality Standard
· Pipe : IS 8329/ ISO standard
· Jointing Material (EPDM rubber gasket) : IS 5382
· Classification of Pipe : Class – K- 7
· Joint : Push-on-Joint (as per IS 8329/ISO standard)
· Sampling: as per respective IS· Test : as per respective IS. Dimensions of
pipe
· Length: standard length of 4.00, 5.00, 5.50 and 6.00 meters (tolerance as
per IS 4984).
· Diameter : The nominal diameter (inside)
· Wall Thickness : as per IS 8329
· Coating : Metallic Zinc with finishing layer of bituminous paint as per
IS : 8329 Lining : Cement Mortar as per IS : 8329
· Type of Cement: Portland Cement or Sulphate Resisting Portland Cement
(as Per IS: 8329)
· Quality Assurance: Quality Assurance Plan shall be got approved from
the Project Manager.
· 9. WATER METER:-
150 mm dia 1
250 mm dia 12
300 mm dia. 6
Lightening Arrester Unit for all the meters 19
MS Panel with Transmitter, Totalizer, etc as per specifications for 19
all meters
Uninterruptible Power Supply 6hr Battery Backup(500 VA) ] for 19
all meters
v.) Submitting detailed work plan for supply and installation of meters
showing all micro activities, within 2 weeks of signing of contract agreement.
The owner will convey approval/ comments in 2 weeks from submission of
detailed work plan.
for all types of pipes, preparation of assembly consisting of meter and necessary
fittings.
vii.) Protection of meter by construction of necessary brick masonry chamber
for protection of woltman type consumer meters of size 100 mm and above,
fixing of strainers as per the requirement for woltmann type meters, Erection of
cabinet housing (MS panel) for converter/totalizer of electromagnetic flow
meter. Where chamber/ box/CI cover is existing same shall be used.
viii.) Installation and Commissioning of meters, training of line department
personnel on maintenance of the meters and Submission of maintenance
schedules both preventive and breakdown maintenance.
ix.) The Contractor has to submit all detailed drawings, material
specifications, operation and repair manuals of all the material to be supplied
under the contract. He also has to submit documents and results of type tests,
routine tests and special tests made during the manufacturing process.
x.) Any other items not specified but required for the completion of the job in
all respect.
1 Scope
The Meter shall be as per ISO 4064/ 1 and EEC approval (Certification). The
meter will be Class B Woltmann type (Helical blades which rotates about the
axis of flow in the meter ) magnetically coupled suitable for cold potable water
meter for water supplies having sizes from 100 mm to 225 mm. Maximum
admissible working pressure (MAP) upto 10 bar. The meter will have
hermetically sealed register press, which will be waterproof, and the unit will be
provided with maximum corrosion protection.
2 Materials
Water meters shall be made of materials of adequate strength and stability
for the purpose for which the water meter is to be used. It must be manufactured
throughout of materials, which are resistant to internal and normal external
corrosion and if necessary be protected by some suitable surface treatment. All
materials of the water meter, which are in contact with water, shall be resistant
to corrosion and shall be nontoxic and non-staining. Use of dissimilar metals in
contact under water should be avoided as far as possible in order to minimize
Page 368 of 553
Technical Specifications
3 General
i.) The register shall be hermetically sealed (IP-68) and Rota table through
360°. The water meters shall be capable of being fitted in any position i.e.
horizontal, vertical or inclined going upward only.
ii.) The meter size, designation and overall dimensions shall conform to ISO
4064 part I class B.
iii.) The water meter shall have flanged connections. The flanged connections
shall comply with IS 1538 part iv and vi for a nominal pressure corresponding to
that of the water meter.
iv.) The manufacturer shall provide a reasonable clearance behind the rear
face of the flange to allow access for installation and removal.
v.) Type of indicating Device: The indication of meter shall be a combination
of analog and digital as per ISO 4064 Part -1.
vi.) Sealing and Marking: Sealing and marking of the water meters shall
conform to 4.10 and 4.11 of ISO 4064 Part I.
vii.) Maximum Permissible errors: q t is + 5 %.
The maximum permissible error in the upper zone from qt inclusive upto and
including qs is + 2 %.
The meters shall be able to retain their accuracy when installed in horizontal,
vertical or inclined planes going upward only.
viii.) The meter performance specification shall be as per ISO 4064/1, Class B.
Copies of the relevant Production Test Certificates are to be provided by the
meter manufacturer.
ix.) The meter shall be able to withstand a maximum working temperature of
50° C.
x.) Meters shall be designed for easy disassembly and re-assembly without
the use of special tools or equipment and shall be easy to maintain and repair.
Meters shall be designed to tamper proof.
xi.) The casing shall be powder coated CI. Workman ship shall be good. All
burns and sharp edges shall be removed and the inside surface should have
Page 369 of 553
Technical Specifications
smooth finish.
xii.) Hydrostatic Test at 16 bars in accordance with ISO 4064 -3: 1999 shall be
witnessed by the owner.
xiii.) Catalog / Literature shall be submitted with the offer. GA and cross
sectional drawings with part numbers, material of construction and major
dimensions, QAP etc. shall be submitted to owner for approval after placement
of order.
xiv.) The Contractor shall submit following documents during inspection.
a.) Chemical Test and mechanical test certificate.
b.) Warranty Certificate.
c.) Hydro Test Certificate.
d.) EEC Certificate.
4 Markings
Each meter shall be marked with the following information:
(a) Manufacturers name or Trade Mark.
(b) Nominal size and class of meter.
(c) Direction of flow of water on both sides of meter.
(d) Year of Manufacturing and Serial No.
(e) EEC Certificate.
5. Strainer
i.) Strainers shall be made of material, which is not susceptible to electrolytic
corrosion. They shall be of corrosion resistant materials. They shall be rigid,
easy to remove and clean and shall be fitted as separate unit before water meter
on the inlet side of the meter. The strainer shall have total area of holes not less
than four times the area of the nominal inlet bore of the pipe to which the meter
is connected. It shall be at installed at such a place that it does not affect the
accurate functioning of the meter.
ii.) A strainer shall be provided upstream of the water meter to avoid any
foreign material entering into the meter. The strainer shall be with flanged
connection as per IS 1538. Body of the strainer shall be of CI conforming to FG
200 of IS 210 – 1978 and filter material shall be of stainless steel AISI304, 40
mesh. Gasket shall be rubber as per IS 638. Bolts and Nuts and washers shall be
as per IS 1367 clause 4.6/4. Tests to be witnessed by owner are Hydro Test of
body at 15kg per cm2 and pressure drop across strainer less than 0.5 kg per cm2.
iii.) Workman ship shall be good. All burrs and sharp edges shall be removed
and the inside surface should have smooth finish. Painting shall be one coat of
primer followed by two coats of enamel paint.
iv.) Catalog / Literature shall be submitted with the offer. Cross sectional
drawings with part numbers, material of construction and major dimensions
shall be submitted to owner for approval after placement of order.
v.) The Contractor shall submit following documents during inspection.
a.) Chemical Test and mechanical test certificate.
b.) Warranty Certificate.
c.) Hydro Test Certificate.
d.) QAP
e.) Performance Test Certificate
vi.) Marking
Strainer shall be clearly and permanently marked with :
a) Manufacturers name or Trade Mark.
(b) Nominal size.
(c) Direction of flow.
(d) Year of Manufacturing and Serial No.
ii.) Dismantling the existing chamber if any and installing the meters with
all necessary fittings as directed by Project Manager is included in scope of
work.
iii.) Brick Chambers are to be constructed for meter size of 100 mm to 225
mm complete as per drawing enclosed.
iv.) All steel fittings and pipes to be coated and lined with fusion bonded
epoxy 250 micron or hot dipped galvanized.
v.) Steel fitting and pipes in contact with soil, shall be additionally
protected.
vi.) All dimensions to be checked on site by the contractor before
construction start.
vii.) All valves and fittings PN 10.
viii.) All steel components (nuts, bolts, access ladder) to be hot dipped
galvanized.
ix.) Drawing to be read in conjunction with specifications.
x.) Dimensions of fabricated fittings are based on butt-weld standards, tees,
bends reducer and weld neck flanges.
9.2.3 Specification for Full Bore Electromagnetic Flow-meter
1 General
a. The full bore electromagnetic flow-meters shall be installed for indication
of flow rate and total flow in pumping mains of water supply system.
b. The flowmeters shall withstand maximum working temperature of about
500C and working pressure.
c. The flowmeters shall be installed with proper protection of terminal box
and cables. The Contractor shall ensure protection of meter from damages due to
overburden.
2 General Technical Particulars
a. Full bore electromagnetic flowmeters shall be designed, manufactured
and calibrated according to internationally accepted standards having bi-
directional flow measurement and totalization facility.
b. The flowmeter shall operate within a velocity range of 0.3 m/sec to 10
m/sec and shall have accuracy of 0.5% of measured value or better.
c. The flowmeter shall be calibrated for the full flow range specified as per
BS EN 29104 (Methods of evaluation of electromagnetic flowmeters). The
calibration method shall be either gravimetric method or volumetric method.
The ‘test bed’ shall be accredited by national / international certifying authority
as per ISO 8316 (Calibration by Volumetric Method) or ISO 4185
(Measurement of fluid flow in closed conduits – Weighing Method). The
Contractor shall produce accreditation certificate of the test rig and calibration
e. Manufacturer / Contractor must have test facilities, spare parts and skilled
personnel to maintain, instruct, train necessary to assure that flowmeters shall be
maintained and kept in good working condition throughout the maintenance
contract period.
f. Each flowmeter shall be tested and calibrated in the presence of Owner’s
Representative.
g. Electronics shall be fully interchangeable irrespective of size of
flowmeter.
h. Each flow meter shall be provided with all the accessories including
software necessary to make it a complete functional system.
i. All equipment mounted in field and inside building shall be protected
from lightning strikes and electrical / electronic surges / harmonics. This type of
Lightning / Surge protection is mandatory and shall be included along with flow
meter.
j. Power supply if available from nearby power source in the water works
shall be tapped with necessary circuit protection / isolation. However, if the
power supply is not available then power supply shall be arranged from
electricity supply authority by the Contractor. The necessary documentation,
charges, cabling, cable laying etc. for obtaining a power supply connection shall
be in Contractor’s scope of work. The meter shall be suitable for 230 VAC ±
15% 50 Hz ± 5% supply. The sensor and converter shall be able to withstand
variation in electric supply. The necessary equipment/device for protection
a. The flow tube (sensor) shall be fabricated from stainless steel SS 304. The
flow tube shall have a constant nominal inside diameter offering no obstruction
to the flow.
b. The coil housing shall be fabricated from stainless steel SS 304 for
corrosion resistance for submerged or buried operation. The junction box shall
be made up of stainless steel SS 304. The flow tube weather protection class
shall be IP 68.
c. The flow meter shall be pulsed DC coil excitation type. The flow
transmitter cum computer shall be remotely mounted away from the flow tube.
f. The cables required for connecting the flow tube with the flow transmitter
shall be capable of transmitting low voltage signals. The cables shall be armored
and shielded. The cable shall be suitable for laying underground and under water
installation.
h. The flow meter shall be installed in such a way that it always remains
filled with water.
i. Gaskets shall be of EPDM and shall be suitable for making flange joints.
The gaskets shall be as per IS 5382 or equivalent standard and drilling of holes
shall be as per IS 1538 or equivalent standard.
j. Nuts and bolt shall be of quality carbon steel and shall be electro-
galvanized. Bolts shall be of accurate length so that only one thread shall show
through the nut in the fully tightened condition. Nuts and bolts shall conform to
IS 1363 and IS 1367.
k. All flanged flow meters shall be supplied with one rubber gasket per
flange and the required number of nuts and bolts as per the meter size. Matching
pair of grounding rings / straps / electrodes shall be supplied with all the meter
tube.
4 Datasheet
a. Process Liquid
Liquid type Potable water / Raw water
Type of solids Silt particles
b. Operating Condition
Operating pressure Max. up to 1.6 Mpa
Operating temperature 0C to 50C
3 The UPS shall incorporate a six pulse rectifier and pulse width
modulation inverter technology with microprocessor control. It shall incorporate
a static bypass switch which shall operate in the event of UPS failure, overload
or manual initiation in order to transfer the output supply to mains without
disturbance to the output supply. The vendor shall demonstrate the operations of
the UPS with instrument load connections.
4 The UPS shall incorporate a DC under voltage trip circuit to
electronically trip the UPS output in order to protect the batteries. The noise
level of the unit shall not exceed 60dB (A) at 1 m from the UPS cabinet. The
output of the inverter shall be a sine wave having less than 2% THD for linear
loads and less than 4% for 50% non linear load. It shall be suitable for load
power factors 0.7 lag to 0.9 lead. The unit shall have a dynamic response such
that a 100% step load causes an output voltage transient of less than ± 4% with a
recovery time of less than 4 minutes. For three phase output units the output
voltage shall not vary by more than ± 1% for an unbalance of 10%. The load
crest factor shall not be less than 3:1. The efficiency at full load and 0.8, power
factor shall be greater than 88%.
5 Indicators to indicate UPS status and UPS alarm conditions shall be
provided.
6 The UPS shall provide a volt free contact output to indicate:
a. Warning, i.e. low battery capacity
b. Fault
c. Static bypass in use
7 The UPS shall have an overload capacity of 150% for 30 seconds and
shall be protected in the event of a short circuit of the output. The batteries shall
be housed, either within the UPS enclosure or within a separate matching battery
cubicle suitable for location adjacent to the UPS. The batteries shall be
maintenance free lead-acid type sealed for life. They shall have life in service of
at least 6 years. Terminals shall be shrouded to prevent accidental contact. The
battery enclosure shall be corrosion resistant and ventilated to prevent the build
up of gases. Warning notices shall be provided for wall mounting to warn of the
presence of charge gases. The battery supply to the UPS shall be via a fused load
break switch disconnecter / circuit breaker.
i. The UPS rectifier shall consist of two branches, one for supplying the
battery and the other for feeding external loads through an inverter.
ii. The 415V AC input to battery charger shall be through suitably rated
MCCBs. On the output side, a 2-pole MCCB of suitable rating shall be
provided.
iii. Each UPS-rectifier shall be suitable for float charging the battery under
normal conditions and boost charging the battery when it has discharged during
service conditions. The changeover from float to boost mode and vice versa
shall be automatic.
iv. The charger shall be designed to have voltage regulation of 1% and ripple
content in the rectified DC supply of less than 2%. Boost charging time for
charging the battery to full capacity from fully discharged condition shall not
exceed 8 hours. The D.C. output voltage during float charging shall be stabilised
within + 1% of the set DC bus voltage for AC input voltage variation of +10%,
frequency variation of + 5% and DC load variation from 0 - 100%. The voltage
regulation shall be achieved by a constant voltage regulator having fast response
SCR control. The ripple content shall be within 1% of D.C. output nominal
voltage with battery disconnected.
v. Each UPS shall be provided with the following alarms / indications:
Rectifier fail.
Load ON bypass
Load ON inverter.
Mains out of synchronization.
AC and DC supply 'ON'
AC and DC supply fail
Modes of charging
Input Over voltage
Under voltage on DC side
Earth fault on DC side
viii. AC Distribution Boards
Multi channel data loggers shall be supplied for logging of flow measurement
data along with electromagnetic flow meters. The logger shall be capable of pre-
programming to record information at regular intervals over long periods.
Type Microprocessor based
Input Universal
No. of channels 4
Functions Acquire and log data in internal non-
volatile memory
Scale data to engineering units
Facility to transfer logged data in real time
directly to notebook computer
Internal real time clock Required
for time stamping
measurements with
date and time
Sampling rate Adjustable, min. 1 minute
Data storage Non-volatile memory to store at the above
sampling rate for all channels simultaneously
Alarms : High and low alarm for each channel
Weatherproof : IP 52
protection class
Data logger : Directly from notebook computer / Data
9.2.9 Cabinets
1 The flow transmitter cum computer and data logger shall be mounted in a
lockable field cabinet. The enclosure for the cabinet shall be constructed from
CRCA sheet of minimum 2.0 mm thick and shall be powder coated with colour
shade RAL 7032. The gland plate thickness shall be 3mm. The cabinet shall be
of suitable size to suit mounting requirement of both the data logger and flow
transmitter cum computer.
2 The cable entry to the cabinet shall be from bottom. Stranded copper
wires shall be used for internal wiring.
4 Suitable steel support as required for mounting the field cabinets shall be
also provided by the Contractor. These field cabinets shall be in addition to the
instrument casing / enclosure.
5 A copper earth bar of adequate size shall be provided inside the cabinet
for terminating the shields of the cables. The Contractor shall use the existing
earthing system for the instruments / equipment supplied by him. In case, the
existing earthing system is inadequate / not suitable / not available, the
Contractor shall provide a new earhing system for the instruments / equipment
supplied. Contractors shall visit the site/s to assess the work and quote
accordingly.
1 General
To the extent possible CI specials shall be used due to their long life. MS
specials be minimised, being corrosive in nature. Flanged fittings shall be
provided as far as possible. The angle of taper shall not exceed 7° wherever
reducers / expanders are used.
2 Flanged CI Specials
ii. The specials shall be internally and externally coated with hot applied
(dip) bituminous paint.
iii. All flanged specials shall be used for working pressure of 10 kg/cm2
(1Mpa).
iv. Flanged specials shall be supplied with the required bolts, nuts and rubber
gaskets. The nut and bolts shall be supplied in jute bag; rubber gasket shall be
supplied in a polyethylene bags.
ii. The working length of double flange pipes shall be 0.5m, 1m, 1.5m, 2m
and 3.0m. The pipes shall be straight and permissible deviation from straight
line shall be in accordance with IS 7181. The pipes of massheavier than the
maximum, shall be accepted provided they comply, in every other respect, with
the requirement of IS 7181.
iii. The pipes shall be supplied with the required bolts, nuts and rubber
gaskets. The flanges and their dimensions of drilling shall be in accordance with
IS 7181.
iv. The working pressure for the double flanged pipes shall be 10
2
kg/cm (1Mpa). For some meters the specials shall be of working pressure as
specified in Annexure A. The pipes shall be tested hydrostatically at a specified
pressure in accordance with IS 7181. The pipes shall not show any sign of
leakage, sweating or other defect of any kind. The factory test pressure for pipe
sizes up to and including 300 mm shall be 20 kg/cm2 and for pipe sizes over 300
mm up to and including 1000 shall be 25 kg/cm2.
The pipes shall be internally and externally coated with hot applied (dip)
bituminous paint in accordance with IS 7181.
c. Dismantling Joints
i. The flexible CI dismantling piece shall be manufactured from cast iron in
such a way that it will allow dismantling of water meter without stress to the
joints of the attached pipe. The dismantling pieces shall provide minimum
clearance of +/- 25 mm (total clearance 50 mm). The pressure class of the
dismantling piece shall be suitable for 10 kg /cm2 pressure rating.
ii. The dimensions of the dismantling pieces shall be suitable to fix with a
water meter for diameter from 100 mm to 1200 mm with flanged joint. The
indicative design details are given below. However, the manufacture may adopt
his own design. The drawing of the dismantling pieces shall be submitted for
review and approval of the owner before production and supply of the product.
d. Supply
All the CI Flanged fittings shall be supplied with one rubber gasket per flange
and the required number of nuts and bolts.
ii. The rubber rings shall be vulcanized from Ethylene Propylene (EPDM).
The colour of material shall be black.
iv. The rings shall be homogeneous, free from porosity, grit, excessive
blooms, blisters, or other visible surface imperfections. The fin or flash shall not
exceed 0.4 mm and width 0.8 mm.
vi. The surface of the rubber rings shall be smooth, free from pitting cracks,
blisters, air marks, and any other imperfection that may affect its behavior in
service. The body of the rubber ring shall be free from porosity and air pockets.
f. Packing
All the rubber rings shall be packed in polyethylene bags. Several PE bags shall
be packed in separate jute bags, according to the size.
Pipes, specials and fittings for MS / PSC pipes shall be made out of steel plate
fabricated to the required dimensions and be as per the specification below:
b. The pipes and specials such as bends, tapers, tees, and branches shall be
fabricated by cutting steel plates of thickness not less than 10 mm and as
suitable to match the existing line and shall be manufactured with flanged spigot
and flanged socket type joints with rubber ring, suitable for jointing with pre-
stressed pipe, as per specifications.
c. The steel for fabricated steel plate fittings is cut, shaped and welded so
that the finished fitting has the required shape and interior dimensions. Adjacent
segment shall be joined by means of lap or butt-welding.
e. The pipes and specials shall be lined inside and outside with liquid epoxy,
liquid epoxy system shall be as per Annexure-B of IS-3589/2001 for food grade
epoxy.
f. All the specials shall be tested for hydrostatic pressure before using as per
clause 8 of IS 7322. In case of specials manufactured at site, they shall be tested
by penetration oil or other approved means.
a) Scope
The galvanized iron pipes and fitting (tees, sockets, elbows, union, end plug)
shall be class B ISI marked in accordance with IS : 1239 part-I and part-II. The
GI pipes class B shall be used as a conduit pipe for signal/power cable between
primary head and signal converter. Also the GI pipes and fittings shall be used
for meters of size 25mm, 40 mm, 50mm.
b) Supply
The medium duty screwed GI pipe and heavy-duty GI fittings of any type
(bends, tapers, tapered bends, tees, unions, male, female, male/female, etc.) of
following sizes shall be supplied.
The length of each pipe shall not be less than 6m. The pipes shall be supplied in
bundles or loose as per diameter.
The ductile iron flanged specials (flanged spigot, flanged socket, flanged tapers,
flanged tees, bends, blank flanges, etc) shall be manufactured and tested
according to IS 9523 or BS:4722. All flanged specials shall be used for working
pressure as specified in Annexure A.
Flanged specials shall be supplied with the required bolts, nuts and rubber
gaskets. The rubber gasket shall confirm to IS:12820 and IS:5382. All the DI
fittings shall be properly packed with jute cloth. The nut and bolts shall be
supplied in jute bag; rubber gasket shall be supplied in a polyethylene bags.
EQUIPMENT CATEGORY
The Contractor / Manufacturer shall inform the Owner about the likely dates of
manufacturing, testing and dispatching. The Contractor / Manufacturer shall
notify the Owner for Inspection and Testing, at least twenty eight (28) days prior
to packing and shipping and shall supply the manufacturer’s test results and
quality control certificates.
For material / Equipment under category “A” and “B”, the Owner will provide
an authorization for packing and shipping after inspection.
4 The Contractor shall make good to the satisfaction of the Owner any
deterioration of the protective coatings, paint, packing etc. that may occur during
transportation.
9 For domestic meters, to avoid damages and over run of the meter due to
intermittent water supply system, it is desirable to install the meter so that the
top of the meter is always below the level of the communication pipe.
10 Before installing the flow meter in the pipeline, it shall be thoroughly
cleaned by installing in the place of the flow meter a pipe of suitable length and
diameter and letting the passage of a fair amount of water flow through the pipe
to avoid formation of air pockets. It is advisable that the level of the pipeline
where the flow meter is proposed to be installed shall be checked by a spirit
level.
11 The flow meter shall be located where it is not liable to get severe shock
of water hammer, which might damage the system of the meter.
12 The installation of electromagnetic flow meters shall be preferably done
in-line, except in those cases where, due to site condition, in-line installation is
not feasible then the meters shall be installed on bypass line. All the installation
shall be done with dismantling joint.
13 The electromagnetic flow meter must remain completely filled with
water, care shall be taken to avoid locations where chances of partial flow are
high, such as pipes laid on slopes. The flow meter shall not be installed close to
the strong electromagnetic fields such as close to power transformer. The
electrode axis of the meter shall be in horizontal plane for horizontal pipe runs.
Care shall be taken to avoid installations of flow meters on the downstream of
the control valves, 90° or 45° elbows or partially opened valves etc. to avoid
cavitations / partial flow conditions. A minimum of 5D straight pipe upstream
and a run of 3D pipe downstream or as per the recommendations of the
manufacture, whichever is on the higher side must be ensured for all the
installation site to avoid turbulent flow profile at the flow meter location. The
flow direction of the water shall correspond to the direction shown by the arrow
on the flow tube.
14 Cutting of pipes shall be necessary for installation and fixing of the flow
meter assembly on the existing pipes. For this purpose, a trench of sufficient
width, depth and length shall be excavated for the underground pipes. Since the
work is to be carried out on the existing pipes of Khargone Municipal Council,
the work shall be properly planned and completed in shortest possible time with
minimum shut down and shall be coordinated with Khargone Municipal
Council.
15 The existing pipes shall be cut and dismantled as per the requirement
without damaging the pipes. In case the pipe is damaged the same shall be
replaced by the Contractor at his cost.
16 Prior to lowering the flow meter assembly in the trench, the bottom of the
trench shall be rammed and a fine gravel bedding of 150 mm (in rocky strata)
only shall be prepared. The meter assembly shall fully rest on the firm and flat
bed. After installation, the trench shall be filled with excavated soil in layer with
proper compaction to the entire satisfaction of the Purcahser’s Representative.
The laying of pipe and fixing of flow meter assembly shall be done as per the
relevant code of practice for laying and fixing of joints for respective pipe
material.
17 It is proposed to install the flow meters on the pipe mains of various pipe
material such as Cast Iron (CI), Mild steel (MS), Ductile Iron (DI) , GI etc. All
the flow meters shall be installed using CI/DI and MS fittings only.
18 It is desirable and advantageous to prepare the assembly of flowmeter and
pipe fittings in advance, which shall be inserted at pre-selected locations in the
system to minimize disturbance of water supplies and to ensure high degree of
workmanship and fast installation.
19 All the flange fittings shall be installed with a proper rubber gasket for
water tight joints.
submit a field validation certificate after completing the field testing stated
above and duly signed by the Owner’s Representative to the concerned authority
for asset transfer.
IS 1538 Cast iron fittings for pressure pipes for water, gas and
sewage (First revision)
IS 2373 Specification of water meters ( type)
IS 2643 Dimensions for pipe threads for fastening purposes
IS 5531 CI specials for asbestos cement pressure pipes for water
gas and sewage (First revision)
IS 6911 Stainless steel plate, sheet and strip
IS 6784 Testing of water meters
b. All equipment shall be new, of proven design, reputed make, and shall be
suitable for continuous operation. Unless otherwise specified, all instruments
shall be tropicalised. The outdoor equipment shall be designed to withstand
tropical rain. Wherever necessary space heaters, dust and waterproof cabinets
shall be provided. Instruments offered shall be complete with all the necessary
mounting accessories.
d. No custom made hybrid type ICs (Integrated Circuits) shall be used in any
circuit in Instruments. Any hybrid circuits or sealed modules or devices which
do not have alternative manufacturer shall be disclosed in the Bid by the
Contractor, so that such devices can be included as component spares in
sufficient quantity in advance.
h. After a power failure, when power supply resumes, the instruments and
associated equipment shall start working automatically without affecting the
readings.
j. The field instruments i.e. the instruments mounted outside the control
panel shall be mounted at a convenient height of approximately 1.2 meters
above grade platform.
n. All field instruments, and cabinets/ panel mounted instruments shall have
tag plates/ name plates permanently attached to them.
r. All wetted parts of the flow meter shall be suitable for water with
presence of chlorine.
s. The flow meters and flow transmitters, indicators and integrators and data
loggers associated with the flow meters shall be microprocessor based and shall
have adjustable ranges. The range indicated in the annexure is for initial setting
only. The final range setting shall be done during commissioning.
associated works and providing, supplying, laying and jointing MDPE pipes of
reputed make and conforming IS with all associated bye work like providing
stop cock chamber etc., all complete.
The scope of the works includes designing, procuring and installing a state of the art
SCADA System for pumping station at the treatment plant. The system essentially
shall comprise of:
One Master Control Stations (MCS) with SCADA Software independently
responsible for centralized acquisition of real time data on the work station
computer and generation of customized reports and data analysis of the entire
pumping station. The MCS shall be provided with a Front End Processor and
GSM communication modem for managing the data traffic of the Remote
Control Units( RTUs);
SCADA Hardware viz. intelligent RTUs (iRTU6000) installed at the pumping
stations; Field instruments supplied shall be integrated with the RTUs at
respective locations.
The RTU’s shall be connected to the Master control station on a wireless GSM
network. Any alarms generated would be transmitted to the pre defined mobile
nos. of the user.
The master control station (MCS) shall be set up at the central control room;
comprising of single computer equipped with GSM supporting SCADA Software;
which will be customized for central control, monitoring and analysis of the pumping
stations under KNP. A dedicated front-end processor shall be provided at the master
control station to carry out all the communication related activities with the
downstream RTU’s. The functionalities available at MCS can be divided into three
categories. These categories include:
Central and Mobile Monitoring,
Central Control and
Management level reports and Data Analysis.
Monitor real time status of all pumps – i.e. whether a particular pump is ON
or OFF
Immediately indicate on MCS if any pump trips due to one reason or the
other
Indicate cause of trip of a pump
Monitor the Intake Sump level in Mtr
Monitor and control the operation of the valve actuators.
Monitor electrical parameters of each intake pump viz. Line and phase
voltages, Line and phase currents, and Power Factor and power consumption.
11.5 Customized Reports and Management Level Analysis:
All operations will be executed from the MCS through extensive graphics support of
the package, which also reduces the learning curve of an average Contractor. User at
a glance can have to total status information of the system. While the operation can
be carried out from the MCS, all the data logged onto the MCS is then analyzed
through representation of this data in various meaningful user defined reports,
graphs, trends and customized analytical requirements of the system.
11.6 Alarms:
Reports can be printed in response to predefined events such as a Pump outage report
or a trip log report. Covered under the Alarm monitoring module, this feature
provides alarm reports for
Limit Cross over (for controlled parameters viz. over pressure, sump
overflow,
Hardware alarm
Communication link alarm
Each alarm will be time stamped and signaled on the MCS. Severity of alarms is
indicated through colour-coded representations of these alarms. Selectable report fields
provided by Report generators are as under:
Graphical trends for all critical parameters for immediate access to the behaviour of a
particular parameter over a period of time. Also covers historical trending of
parameters like total water production; this will help not only in concluding the
pattern of system utility but also production forecasting after scrutiny of say last five
successive years of production.
Communication Subsystem:
Communication system proposed for the SCADA System shall be of wireless type.
The communication network proposed shall be on GSM network connecting each
RTU with the MCS; the data is communicated from all RTUs and received at the
MCS. Data at the MCS is updated at a fixed interval; further the frequency of data
update is user configurable. However, any alarm situation occurring at any of the
RTU station is immediately flashed on the MCS. The data from the MCS would be
transmitted on pre defined mobile nos. Through GSM wireless communication
network.
According to the DPR, about 60 KM of the existing pipe line can be used
with the new distribution system. However, the Contractor has to make
an assessment of the condition of the entire existing distribution network
including valves, specials and connection and submit a condition
assessment report indication the pipes, valves and specials which are to
be discarded and why, providing techno-economic justification.
The existing WTP was built in early 70s for 10.62 MLD. The WTP is in
working condition, however, this needs repairs, rejuvenation and renovation. The
bidder has to:-
(i) Assess the condition of the WTP including the structural (civil), filters
and electro-mechanical parts.
(iii) The owner with the help of IVT shall assess the report submitted by
the contractor. The owner reserves the right to get the renovations done
through the contractor or get this work done by inviting fresh bids.
However, the rejuvenated WTP shall be an integral part of the total
system and shall be operated and maintained by the contractor under this
agreement. It is further clarified that since the O&M is based on the
production of water, no additional cost will be payable to the contractor.
Reinstatement of roads
The road restoration / reinstatement shall be carried out after completion and
necessary testing of all the Works and only after approval of the Engineer.
Contractor shall make good of the road surface to the original grade, level and
specifications
as per Bill of Quantities. Trenches shall be backfilled in layers as per clause
mentioned in this section, well watered and well compacted before road
restoration to avoid settlement of restored strip. In case any settlement of the
road restoration strip, the Contractor has to rectify the surface by redoing the
restoration work at no extra cost to the owner as per Bill of Quantities. Road
restoration shall be done as per the requirements of the concerned local
authorities, requirements specified in this section of Technical specifications,
applicable IRC guidelines and as directed by the Project Manager. The
replacement of road structures shall be carried out as soon as practicable and in
conformity with IRC guidelines after backfilling has been completed. Suitable
excavated road pavement which complies with the requirements of the
Engineer may be used at the sub-base levels. Compaction shall be carried out
with approved mechanical compacting equipment.
The edges of the trench shall be cut to form a straight line consistent with
fixed width of trench. A vertical joint shall be formed between the new
work and the existing road surface and shall be painted with hot bitumen or
rich cement slurry as the case may be, as approved by the Project Manager.
The joint between the base course and wearing course shall be stepped 75
mm.
The finished levels of the completed reinstatement shall conform to the
adjoining carriageway surface. Reinstatement of the wearing courses shall
match as nearly as practicable the colour or other characteristics of the existing
surface.
13.1.1 Scope
This work shall consist of clean, crushed aggregates mechanically interlocked
by rolling and bonding together with screening, binding material where
necessary and water laid on properly backfilled pipeline and manhole trenches
and finished in accordance with the requirements of these specifications and as
directed by the Project Manager.
The scope involves Providing, laying , spreading and compacting stone
aggregates of specific sizes to Water Bound Macadam specification including
spreading in uniform thickness, hand packing, rolling with 3 wheeled
steel/vibratory roller 8-10 tones in stages to proper grade and camber,
applying and brooming requisite type of screening/binding materials to fill
up the interstices of coarse aggregates ,watering and compacting to the
required density with all lead & lifts etc. complete with the following two
layers of materials each compacted to 75 mm thick,
(i). Materials (Refer table 400 - 7, 8 & 9) Using Screening Crushable
type such as Moorum or Gravel Grading-II (Clause: 404 of MORT & H).
(ii). Material (Refer table 400 - 7, 8 & 9) Using Screening Crushable
type such as Moorum or Gravel Grading-III (Clause: 404 of MORT & H).
13.1.2 Materials
(a) Coarse aggregates - Coarse aggregates shall be either crushed or
broken stone, crushed slag, over burnt (Jhama) brick aggregates or any
other naturally occurring aggregates such as kankar and laterite of
suitable quality. Materials other than crushed or broken stone and crushed
slag shall be used in sub-base courses only. If crushed gravel / shingle is
used, not less than 90 per cent by weight of the gravel/shingle pieces
retained on 4.75 mm sieve shall have at least two fractured faces. The
aggregates shall conform to the physical requirements set forth in Table
400-6. The type and size range of the aggregate shall be specified in the
contract or shall be as specified by the engineer. If the water absorption
value of the coarse aggregate is greater than 2 per cent, the soundness
test shall be carried out on the material delivered to site as per IS: 2386
(Part 5).
(b) Crushed or broken stone - The crushed or broken stone shall be hard,
durable and free from excess flat, elongated, soft and distinguished particles,
dirt and other deleterious material.
(c) Crushed slag - Crushed slag shall be made from air-cooled blast furnace
slag. It shall be of angular shape, reasonably uniform in quality and density
and generally free from thin, elongated and soft pieces, dirt or other
deleterious materials. The weight of crushed slag shall not be less than
11.2 KN per m3 and the percentage of glossy material shall not be more
than 20. It should also comply with the following requirements:
(d) Over-burnt brick aggregates -Brick aggregates shall be made from over
burnt bricks or brick bats and be free from dust and other objectionable
and deleterious materials.
for this purpose provided liquid limit and plasticity index of such
material are below 20 and 6 respectively and fraction passing 75
micron sieve does not exceed 10 per cent.
Screenings shall conform to the grading set forth in Table 400-8. The
consolidated details of quantity of screenings required for various grades
of stone aggregates are given in Table 400 – 9. The table also gives
the quantities of materials (loose) required for 10 m2 for sub-base base
compacted thickness of 100/75 mm. The use of screenings shall be
omitted in the case of soft aggregates such as brick metal, kankar, laterites,
etc. as they are likely to get crushed to a certain extent under rollers.
Screenings
(g) Binding material - Binding material to be used for water bound macadam
as a filter material meant for preventing gravelling, shall comprise of a
suitable material approved by the engineer having a Plasticity Index (PI)
value of less than 6 as determined in accordance with IS : 2720 (Part 5).
The quantity of binding material where it is to be used will depend on the
type of screenings. Generally, the quantity required for 75 mm compacted
thickness of water bound macadam will be 0.06 – 0.09 m3 / 10m2 and
0.08 – 0.10 m3/ 10 m2 for 100 mm compacted thickness.
The above mentioned quantities should be taken as a guide only, for
estimation of quantities for construction etc.
Application of binding materials may not be necessary when the
screenings used are of Crushable type such as murrum or gravel.
allowed and the coarse aggregate as spread shall be of uniform gradation with
no pockets of fine material.
The surface of the aggregates spread shall be carefully checked with
templates and all high or low spots remedied by removing or adding
aggregates as may be required. The surface shall be checked frequently with a
straight edge while spreading and rolling so as to ensure a finished surface as
per approved drawings.
The coarse aggregates shall not normally be spread more than 3 days in
advance of the subsequent construction operations.
(d) Rolling - Immediately following the spreading of the coarse aggregate,
rolling shall be started with three wheeled power rollers of 80 to 100 KN
capacity or tandem or vibratory rollers of 80 to 100 KN static weight. The
type of roller to be used shall be approved by the engineer based on trial run.
Except on super-elevated portions where the rolling shall proceed from inner
edge to the outer, rolling shall begin from the edges gradually progressing
towards the centre. First the edge/ edges shall be compacted with roller
running forward and backward. The roller shall then move inward parallel to
the centre line of the road, in successive passes uniformly lapping
preceding tracks by at least one half width.
Rolling shall be discontinued when the aggregates are partially
compacted with sufficient void space in them to permit application of
screenings. However, where screenings are not to be applied, as in the case of
crushed aggregates like brick metal, laterite and kankar, compaction shall be
continued until the aggregates are thoroughly keyed. During rolling, slight
sprinkling of water may be done, if necessary. Rolling shall not be done when
the sub-grade is soft or yielding or when it causes a wave-like motion in the
sub-grade or sub-base course.
The rolled surface shall be checked transversely and longitudinally, with
templates and any irregularities corrected by loosening the surface, adding or
removing necessary amount of aggregates and re-rolling until the entire
surface conforms to desired cross fall (camber) and grade. In no case shall the
use of screenings be permitted to make up depressions.
Material which gets crushed excessively during compaction or becomes
segregated shall be removed and replaced with suitable aggregates.
(e) Application of screenings - After the coarse aggregate has been rolled to
as per above specification, screenings to completely fill the interstices shall be
applied gradually over the surface. These shall not be damp or wet at the
time of application. Dry rolling shall be done while the screenings are being
spread so that vibrations of the roller cause them to settle into the voids of the
coarse aggregates.
The screenings shall not be dumped in piles but be spread uniformly in
successive thin layers either by the spreading motions of hand shovels or by
mechanical spreaders, or directly from tipper with suitable grit spreading
arrangement. Tipper operating for spreading the screenings shall be so driven
as not to disturb the coarse aggregate.
The screenings shall be applied at a slow and uniform rate (in three or more
applications) so as to ensure filling of all voids. This shall be accompanied
by dry rolling with mechanical brooms, hand-brooms or both. In no case
screenings shall be applied fast and thick as to form cakes or ridges on the
surface in such a manner as would prevent filling of voids or prevent the
direct bearing of the roller on the coarse aggregate. These operations shall
continue until no more screenings can be forced into the voids of the coarse
aggregate. The spreading, rolling, and booming of screenings shall be carried
out in only such lengths of the road which could be completed within one
day’s operation.
(f) Sprinkling of water and grouting - After the screenings have been applied,
the surface shall be copiously sprinkled with water, swept and rolled. Hand
brooms shall be used to sweep the wet screenings into voids and to distribute
them evenly. The sprinkling, sweeping and rolling operation shall be
continued, with additional screenings applied as necessary until the coarse
aggregate has been thoroughly keyed, well-bonded and firmly set in its full
depth and a grout has been formed of screenings. Care shall be taken to see
that the base or sub-grade does not get damaged due to the addition of
excessive quantities of water during construction.
In case of lime treated soil sub-base, construction of water bound macadam
on top of it can cause excessive water to flow down to the lime treated sub-
base before it has picked up enough strength (is still “green”) and thus cause
damage to the sub-base layer. The laying of water bound macadam layer in
such cases shall be done after the sub-base attains adequate strength, as
directed by the Project Manager.
(g) Application of binding material - After the application of screenings in
accordance with the above clause, the binding material where it is required
to be used shall be applied successively in two or more thin layers at a slow
and uniform rate. After each application, the surface shall be copiously
sprinkled with water, the resulting slurryswept in with hand brooms, or
mechanical brooms to fill the voids properly, and rolled during which water
shall be applied to the wheels of the rollers if necessary to wash down the
binding material sticking to them. These operations shall continue until the
resulting slurry after filling of voids, forms a wave ahead of the wheels of the
moving roller.
(h) Setting and drying - After the final compaction of water bound macadam
course, the pavement shall be allowed to dry overnight. Next morning hungry
spots shall be filled with screenings or binding material as directed, lightly
sprinkled with water if necessary and rolled. No traffic shall be allowed on the
road until the macadam has set.
The engineer shall have the discretion to stop hauling traffic from using the
completed water bound macadam course, if in his opinion it would cause
excessive damage to the surface. The compacted water bound macadam
course should be allowed to completely dry and set before the next pavement
course is laid over it.
13.3.1 Scope
This specification relates to the operation of priming an absorbent
base course, preparatory to a subsequent bituminous treatment, through
application of a low viscosity bituminous material by spraying. The
specification is intended to indicate what is considered to be a good
practice for priming and shall apply unless modified by special provisions to
take into account any unusual conditions.
The scope involves, Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base of low porosity such as WBM
including clearing of road surface and spraying primer at the rate of 0.75
kg/sqm using mechanical means. As per MORTH specification clause No.
502 complete in all respects with all lead & lifts etc. complete.
13.3.2 Materials
The bituminous primer to be used should be such that it can penetrate into
the base course to perform its intended function.
The primers shall conform to IS: 8887 – 1978 (for cationic emulsions), IS:
217-1961 (for cut-backs), and IS: 215-1981 (for road tars), as applicable.
13.3.4 Viscosity
For selecting the appropriate type of primer out of the materials indicated in
Table 1, the atmospheric temperature during application should be given
consideration. Also, within the range of viscosity specified, the primer for
use may be selected keeping in view the level of porosity of the surface to be
treated.
13.4 Construction
a. Weather and seasonal limitations
Cut-back and road tar primers shall not be applied on wet surface or during
dust storm or when the weather is foggy or rainy. Bitumen emulsion can be
applied on wet surface. However, emulsions shall not be applied during dust
storm or when it is actually raining. Atmospheric temperature during priming
should be above 10 C.
b. Equipment
All equipment required for the execution of work should be in good working
condition at site.
c. Preparation of base course surface
The base course surface to be primed shall be swept clean and free from dust.
All loose materials and other foreign matter on the surface shall be removed
completely, if necessary by using power blowers or sweepers.
blot up the excess bitumen and prevent it being picked up under traffic. If an
excess of bitumen residue is found on the primed surface after bitumen
emulsion has broken, a very light sand dusting may be applied to soak up the
surplus material.
All loose sand should be swept from the base course surface prior to any
subsequent bituminous treatment.
13.6 Specifications for single coat bituminous surface dressing (20mm thick pre-
mix bituminous surfacing).
13.6.1 Scope
This specification is intended to indicate what is considered to be good
practice for construction of single coat bituminous surface dressing and shall
apply unless modified by special provisions to take into account unusual
conditions. The work specified consists of a wearing surface composed of
a single application of bituminous material covered with one application of
cover material of size as specified below, applied on a previously prepared
base or pavement.
The specific scope involves, Providing, laying and rolling of open-graded
premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm
aggregates either using penetration grade bitumen 80/100 or cut-back or
emulsion to required line, grade and level to serve as wearing course on a
previously prepared base, including mixing in suitable plant, laying and
rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required
level and grades. Mechanical method using Penetration grade Bitumen and
HMP of appropriate capacity, as per MORTH specification No.511 complete
in all respects. (Bitumen 1.46kg/sqmt. Metal = 0.027) with 40-60 TPH hot
mix with all lead & lift etc. complete.
13.6.2 Materials
a. Bituminous materials - The bituminous materials shall be of grade 80/100
or cut-back conforming to the requirements as specified and provided for
in the proposal and satisfy the related specification, issued by the Indian
Standards Institution (vide I.S.I Standards 73-1961,215-1961,217-1961 and
454-1961).
b. Cover materials
(i). General requirements - The cover material shall consist of crushed
stone, crushed slag crushed gravel (shingle) or other stones, as specified, and
shall have clean, strong, durable, and fairly cubical fragments free from
disintegrated pieces, salt, alkali, vegetable matter, dust and adherent coatings.
The aggregate shall preferably be hydrophobic in nature and of low porosity.
(ii). Physical requirements - The aggregate shall satisfy the requirements
given in Table below.
Where all these conditions cannot be satisfied, it is left to the Project Manager to
allow reasonable tolerances.
Size - The size of chippings to be used shall depend on whether the treatment is for
the first coat or for the subsequent or renewal coat and shall be as per the size
specified below. For single application of the aggregate, it is desirable to keep the
grading of the various sizes as specified in Table below.
using Type A seal coat as per MORTH specification clause No. 513 complete
in all respects with all lead & lift etc. complete.(Bitumen = 0.98 kg/sqmt.
Metal =0.009).
13.7.1 Scope
This is intended to indicate what is considered to be good practice for the
construction of cement concrete road pavements, including preparation of the
subgrade and sub -base underneath these pavements. This does not however
cover the requirements of fully mechanized constructions.
The scope involves providing specified thickness of 1:3:6 proportion cement
concrete as base course and specified thickness of 1:1.5:3 proportion cement
concrete as wearing course as per approved construction drawings and
specifications.
13.7.2 Materials
a. Ordinary Portland Cement/ PPC/PSC- This should comply with the
requirements of IS – 8112/IS-1489-part-1/IS-455 with latest revisions b.
Aggregates
General - Aggregates should comply with IS - 383 -1970 "Specification for
Coarse and Fine Aggregates from Natural Sources for Concrete (Second
Revision)" with special reference to the additional requirements stipulated for
use in road works excepting in the case of Los Angeles Abrasion Test limit.
The Los Angeles Abrasion Test limits shall be not more than 35 per cent and
50 per cent for concrete wearing course and sub -base course respectively. ln
addition, the limits of deleterious material shall not exceed the requirements
set out in IS - 515 -1959 “Specification for Natural and Manufactured
Aggregates for Use in Mass Concrete." Weathered rock should not be used. In
order to make good concrete, it is important to avoid crushed aggregate of
poor shape. Very angular, flaky, elongated or splintery aggregates give a harsh
mix of low workability. Maximum size of aggregate should not exceed l/4th
of the pavement slab thickness. In case of pavements having reinforcement,
maximum size of aggregate should also not exceed l/4th of minimum clear
spacing between reinforcing bars.
Page 420 of 553
Technical Specifications
c. Coarse aggregates
Continuous grading- Continuously graded coarse aggregate should be
furnished in at least two separate sizes with separation at 20 mm I.S. sieve
when combined material graded from 40 to 4.75 mm is specified, and at 25
mm I.S. sieve when combined material graded from 50 to 4.75 mm is
specified.
d. Fine aggregate - Fine aggregate shall preferably be natural sand. Crushed
stone sand may also be used satisfactorily in concrete. The fine aggregate
shall conform to IS: 383 -
1970, the permissible percentage passing limits on 300 and 150 -micron
sieves shall be
15 -55 per cent and 0 -20 per cent respectively instead of 15 -50 percent and
0 -15 per cent as stipulated in IS Specification. Crushed sand is usually
more angular in shape than naturally occurring sand, and for this reason may
tend to make the mix a little harsher. In some cases, it may prove
advantageous to use a mixture of naturally occurring sand and crushed
stone sand if the former is not obtained in adequate supply or where its
grading is poor. Bulking due to presence of moisture in the fine aggregate
should be accounted for when volumetric batching is employed.
e. Water - Water used in mixing or curing of concrete shall be clean and
free from injurious amounts of oil, salt, acid, vegetable matter or other
substances harmful to the finished concrete. It shall meet the requirements
stipulated in clauses of IS: 456 -2000 "Code of Practice for Plain and
Reinforced Concrete". Potable waters are generally considered satisfactory for
mixing or curing.
f. Dowel and tie bars - Dowel and tie bars shall be plain round steel bars
conforming to the requirements of IS: 432 -1966.
g. Pre-moulded joint filler – Pre-moulded joint filler shall be of the thickness
shown on the drawings within a tolerance of 1.5 mm. It shall be 25 mm
less in depth than the thickness of the slab, within a tolerance of 3 mm and
of the full width between road forms. Holes to accommodate dowel bars shall
be accurately bored or punched out. The joint filler shall comply with the
requirements of IS: 1838 -1961 "Specification for Preformed Fillers for
Expansion Joint in Concrete, Non -extruding and Resilient Type (Bitumen -
impregnated Fiber)."
General
All tools, equipment and appliances necessary for proper preparation of sub-
grade, laying of sub -base and batching, mixing, placing, finishing and
curing of concrete shall be at the project site in good working condition and
shall have been inspected by the engineer before the paving operations are
permitted to start. Throughout the construction of the project, the construction
agency shall maintain all necessary tools, equipment and appliances in first
class working condition to ensure proper execution of the work. Arrangements
shall also be made for requisite number of stand -by units in the event of break
-downs during construction.
List of tools, equipment and appliances
A list of tools, equipment and appliances required for the different phases
of concrete road construction is given below.
This list pertains to semi -mechanised type of construction only, as practised
most in this country.
(a) Subgrade and sub -base compaction -
(i) Compaction equipment (three wheeled or tandem roller, pneumatic
roller, vibratory roller or sheep -foot roller)
(ii) Watering devices as in a (ii) (for ponding operation) (g) Cleaning and
sealing of joints
(i) Iron raker
(ii) Coir brush
(iii) Cycle pump/pneumatic air blower
(iv) Kerosene stove
(v) Thermometer
(vi) Transferring pot
(vii) Painter's brush
(viii) Pouring kettle
(ix) Scraper
13.9 Forms
Steel forms - All side forms shall be of mild steel unless use of wooden
sections is specially permitted. The steel forms shall be mild steel channel
sections of depth equal to the thickness of the pavement. The sections shall
have a length of at least 3 m except on curves of less than 45 m radius,
where shorter sections may be used. When set to grade and staked in place,
the maximum deviation of the top surface of any section from a straight line
shall not exceed 3 mm in the vertical plane and 5 mm in the horizontal plane.
The method of connection between sections shall be such that the joint
formed shall be free from difference in level, play or movement in any
direction. The use of bent, twisted or worn -out forms will not be permitted.
At least three stake pockets for bracing pins or stakes shall be provided for
each 3 m of form and the bracing and support must be ample to prevent
springing of the forms under the pressure of concrete or the weight or thrust
of machinery operating on the forms.
13.10 Joints
General - The location and type of joints shall be as shown in the drawing.
The edge of the slab at all joints shall be rounded off with an edging tool. The
concrete along the face of all joints and around all tie bars and dowels shall be
compacted with an internal vibrator inserted in the concrete and worked along
the joint and around all tie bars and dowels to ensure a concrete free from
honeycombing.
Types of joints - There are three general types of joints. These are –
Expansion joint - Such joint provides the space into which pavement can
expand thus relieving compressive stresses due to expansion and inhibiting
any tendency towards buckling of concrete slabs.
Contraction joint - Such joint relieves tensile stresses in the concrete and
prevents formation of irregular cracks due to restraint in free contraction of
concrete. Contraction joints also relieve stresses due to warping.
Warping joint - Such joint relieves stresses due to warping. These are
commonly used for longitudinal joints dividing the pavement into lanes.
In addition, construction joints are provided whenever construction operations
require them. These are full depth joints and may belong to any of the above
types.
All joints shall be carefully installed in accordance with the location and
details given on the plans.
Transverse joints
General - Transverse joints can be expansion, contraction or construction
joints and shall be placed as indicated on the drawing. They shall make a right
angle with the centre line of the pavement and surface of the sub -
base/subgrade. Contraction and expansion joints shall be continuous from
edge to edge of the pavement through all lanes constructed at the same or
different times.
a. Transverse expansion joints - These shall extend over the entire
width of the pavement. They shall be of the dimensions and spacing as
shown on the construction drawing.
Dowel bars (see Supplementary Note N. 4) as per dimensions, location
and spacing shown on the drawing are required at expansion joints to
transfer wheel loads to the adjacent slab. For slabs of thickness less than
150 mm no dowel bars may be provided (IS: 6509 -1972). The pre-
moulded expansion joint filler, a compressible material used to fill the gap
between adjacent slabs at expansion joint shall conform to IS: 1838 -1961. The
height of the filler board shall be such that its top is 25 mm below the surface
of the pavement. The dowel bars shall be held accurately in position during
spalling of concrete occurs while removing the bar. The edges of the joint
shall be rounded with an edging tool before the concrete hardens.
c. Transverse construction joints - These shall be placed whenever placing of
concrete is suspended for more than 30 minutes. Excepting in the case of
emergency, construction shall always be suspended at the regular site of
expansion or contraction joints. If the construction joint is located at the site
of an expansion joint, regular expansion joint shall be provided; if at the site
of a contraction joint or otherwise, the construction joint shall be of butt type
with dowels.
At all construction joints, bulkhead shall be used to retain the concrete and
care shall be taken in striking off and finishing the surface to the top face
of the bulkhead. When work is resumed, the surface of concrete laid
subsequently, shall conform to the grade and cross -section of previously laid
pavement, and a straight edge 3m in length shall be used parallel to the centre
line, to check any deviation in the surface of the two sections. Any deviation
from the general surface in excess of 3 mm shall be corrected.
Longitudinal joints
These shall be of the plain butt type and shall be formed by placing the
concrete against the face of the slab concreted earlier. The face of the slab
concreted earlier, shall be painted with bitumen before placing of fresh
concrete.
Tie bars shall be used at longitudinal joints and they shall be of the
dimensions and at spacing shown in the construction drawing. Tie bars shall
be supported so as not to be displaced during construction operations. Tie
bars shall be bonded in the slabs across longitudinal joints, and whilst
casting the first slabs, they may be bent so that one end of them lies along the
forms. After removal of the forms, bars shall be straightened so that they
extend into the concrete placed on the other side of the joint.
13.11 Construction
a. Storage and handling of cement
Cement shall not be stored for a long time and should be used normally
within six months of its date of receipt. Even during this period of
storage it is essential that cement shall be protected from moisture by
storing it in suitable sheds. Storage shed with a concrete floor laid on a well
-drained foundation may be satisfactory. Cement in bags shall be stored on
boards raised above the floor level for the purpose of ventilation, and the bags
shall not touch the walls of the shed. Different consignments should be
separately stacked and used in order in which they have been received.
When bulk supply cement is used, special storage facilities such as covered
hopper bins will be required. Supply of cement should be co-coordinated with
its consumption so that it is not stored right through the rainy season, when
normally concreting is discontinued. Cement having lumps which have been
caused due to improper storage or by pressure due to over -loading of bags
shall not be considered for use unless these lumps can be easily powdered
with pressure between fingers. Before such cement is used,
representative sample containing also the lumps in fair proportion shall be
taken and tested as per IS - 269 -1976, 8112 -1976, 1489 -1976, 455 -1967
or 8041E -1976 as the case may be, to fulfill the minimum requirements.
b. Storage and handling of aggregates
The location and preparation of sites, minimum size of stack and the methods
adopted for dumping and stacking to prevent segregation of coarse and fine
material shall be subject to the approval of the engineer. Aggregates from
different sources and/or of different grading shall not be stacked together.
Each separate size of coarse aggregate shall be stacked separately. The
storing of aggregates upon the carriageway or shoulders shall not be
permitted.
If aggregates are stored in conical stacks, segregation will be increased by the
rolling of the coarser particles down the sides of the stacks. To avoid this,
stacks should be built up in approximately horizontal layers. Dry fine
aggregate segregates and gets blown away easily it may be helpful to
moisten it. To assist in controlling the water/cement ratio, large fluctuations
in the moisture content of aggregates may be reduced by storing the bulk of
the material well in advance of use. For this purpose, all washed aggregates
shall be stacked for draining at least 12 hours before being batched. It is also
a good practice to reserve the bottom 150 -300 mm or so of the stacks as a
drainage layer. Where this cannot be done, the aggregates should not be
placed on the ground. In such case, somewhat raised planks, metal sheets or
concrete base should be provided and laid to slopes.
The aggregates shall be handled from the stacks and fed into the mixer in such
a manner as to secure the stipulated grading of the material. Aggregates that
have become mixed with earth or other foreign material shall not be used.
They shall be washed clean before use.
c. Batching of materials
All batching of materials shall be by weight or volume as approved by the
Engineer. The proportion of ingredients shall be as specified in the item of
work in Bill of Quantities, The Engineer may permit the use of fractional bags
of cement provided they are accurately weighed and are handled in a manner
meeting with his approval. Water may be measured by volume. It should,
however, be borne in mind that weigh batching is definitely much more
desirable than volume batching. If batching by volume is permitted, as a
special case, separate measuring boxes shall be provided for the different
aggregates. The boxes shall be of strong construction provided with handles
for convenient lifting and loading into the mixer. They shall be of such size
that it should be possible to measure out the requisite quantity of aggregate
per batch in whole box or by multiples thereof and capable of being lifted by
two men. Each box shall be provided with a straight edge of required length
for striking off after filling. If so directed by the engineer, improved facilities
such as tipping boxes of accurate capacity working on run - out rails arranged
for direct delivery into the hopper of the mixer shall be provided by the
construction agency. In volume batching, suitable allowance shall be
made for the hulking of fine aggregate due to the presence of water. For this
purpose the bulking shall be determined as per relevant Indian Standard
Specification.
d. Mixing
General - The mixing of concrete shall be done in a batch mixer of approved
type, which will ensure a uniform distribution of materials throughout the
mass, so that the mix is uniform in colour and homogeneous. All concrete
shall be mixed in quantities for immediate use.
The mixer shall be equipped with approved water -measuring device capable
of accurate measurement of water required per batch. The mixer shall
preferably be equipped with a mechanically operated pump for filling the
mixer tank.
The concrete shall be mixed in quantities required for immediate use and shall
be deposited on the sub -base to the required depth and width of the pavement
section, in successive batches and in continuous operation without the use of
intermediate forms or bulk -heads between joints. Care shall be taken to see
that no segregation of materials results whilst the concrete is being
transported from the mixer to the place where it is deposited. The usual
method of transport of concrete in India is in pans as head loads or in small
wheel barrows. The spreading shall be as uniform as possible to avoid re-
handling of the concrete. Where, however, a certain amount of re -distribution
is necessary, it shall be done with shovels and not with rakes. While being
placed, the concrete shall be tamped with suitable tools for slab thicknesses of
12.5 cm and less so that formation of voids or honeycomb pockets is
prevented. The concrete shall be particularly well placed and tapped against
the forms and along all joints, for higher thicknesses an internal vibrator shall
be employed in lieu of rodding of the concrete. To effect adequate
compaction, the concrete shall be placed with appropriate surcharge over the
final slab thickness. The amount of surcharge will depend on the mode of
placement of concrete and shall be determined by trial. In general, the
required surcharge is about 20 per cent of the required slab thickness. Any
portion of the batch of concrete that becomes segregated while depositing it
on sub-grade shall be thoroughly mixed with the main body of the batch
during the process of spreading. In case of unavoidable interruption, a full
depth transverse joint shall be made at the point of stoppage of work provided
the section on which the work has been suspended is about 2 to 3 hours long.
In placing of concrete for two course construction, necessitated by either
positioning of the reinforcement, a richer mix for the wearing surface, or
when thickness of the concrete is beyond 20 cm, the bottom layer of concrete
shall be struck off to the required levels by a vibrating screed working on the
side forms with notches corresponding to the depth of the top course of
concrete.
The vibrating screed should have a vibrating unit mounted on it similar to that
of the screed used for compaction of the final surface of concrete. The time
lag between laying of the two courses shall not exceed the initial setting time
of cement.
Placement of steel
a. Reinforcement - Reinforcing steel shall be free from dirt, scale or other
foreign matter and rust of such degree or development as to impair bond of
the steel with the concrete. The width of fabric sheets or bar mats shall be
such that when properly placed into the work the extreme longitudinal bars or
wires of the sheets or mats will be located not less than 50 mm and not more
than 100 mm from the edges of the slab. Except for dummy joints, the
length of fabric sheets or bar mats shall be such that when properly placed
into the work, the reinforcement will be clear of transverse joints by not less
than 50 mm and not more than 100 mm as measured from the centre of
the Joint to the ends of longitudinal bars or wires of the sheet or mat.
While overlapping the sheets or mats in either direction, the overlap shall
be at least equal to the spacing between the bars or wires in the respective
direction or 40 times the diameter of the bar or wire, whichever is more.
Whilst using reinforcement in one layer, the concrete shall be placed in two
stages. Theinitial layer shall be uniformly struck off to a depth corresponding
to the reinforcement shown in the drawings and lightly compacted by a screed
to obtain uniform levels. The reinforcing fabric sheet or bar mat shall then
be placed on the compacted layer of concrete and remaining depth shall be
filled in with concrete thereafter.
In doing this operation, the initial layer of concrete shall be struck off to the
entire width of the slabs and of sufficient length to permit sheet or mat of
reinforcement to be laid full length without further manipulations of the
reinforcement. Displacement of the reinforcement during concreting
operations shall be prevented.
b. Load transfer devices - dowels - Transverse expansion joints shall be
equipped with dowels of the dimension and at the spacing and location
indicated on the drawing. They shall be firmly supported in place, accurately
aligned parallel to the sub-grade/sub -base, parallel to each other and parallel
to the centre line of the pavement, by means of appropriate dowel supports.
The dowel supports shall ensure that the dowels are not displaced during
construction. The permissible tolerances in dowel bar alignment in both
vertical and horizontal directions shall be 1 mm in 100 mm for dowels of 20
mm and smaller diameters and 0.5 mm in 100 mm for dowels of diameter
greater than 20 mm. One -half of each dowel shall be painted with a thin
film of bitumen and equipped with a tight fitting metal sleeve of the
dimensions shown on the drawing to provide space for the dowel when
pavement expands and the join closes. This sleeve shall be partly filled with
cotton waste to prevent it being pushed too far on the dowel during
construction.
These sleeves are not required on dowels, if used, in dummy contraction or
construction joints.
c. Tie bars - Tie bars provided in longitudinal joints of plain butt type to
prevent opening of such joints shall be bonded to the adjacent slabs on both
sides of the longitudinal joint. They are installed by providing appropriate
(drilled) holes in the side forms depending on the size and spacing of bars.
They are bent aside temporarily to avoid obstruction to construction traffic
and straightened later at the time of laying of slab in the adjacent lane.
(v) Immediately after the tamping or screeding has been completed and
before the concrete has hardened, While the concrete is still in a plastic stage, the
surface shall be inspected for irregularities with a profile checking template and
any needed correction made by adding or removing concrete followed by further
compaction and finishing.
Floating - As soon as practicable after the concrete has been compacted, its
surface shall be smoothened by means of a longitudinal float, operated from a
foot -bridge. The longitudinal float shall be worked with a sawing motion,
while held in a floating position parallel to the carriageway centre line and
passed gradually from one side of the pavement to the other. Movements
ahead along the centre line of the carriageway shall be in successive advances
of not more than one half the length of the float.
again in the specified manner. If the irregularity still exceeds the limit
aforesaid, the concrete shall be removed to a depth of 50 mm or up to the top
surface of the reinforcement, if any. The area of concrete to be removed shall
be demarcated by the length of the straight edge in the position of
measurement across the full width of the slab. Where the point of
measurement in default is less than 4.5m from the nearest transverse
expansion joint, the whole area upto the joint shall be removed to the
required depth. The concrete so removed shall not be re - used in the
carriageway. Fresh concrete shall be placed, compacted and finished in the
manner already described in these specifications and shall again be subject to
test for accuracy of finish.
The foregoing procedure shall be adopted at each shifting of the straight
edge and the whole area shall be gone over from one side of the slab to the
other. The straight edge shall advance longitudinally in successive stages of
not more than one -half the length of the straight edge.
No extra payment shall be made for the removal of the rejected concrete and
or laying fresh concrete.
Although the concrete may be removed immediately following measurement
of the irregularity and while it is still wet, this shall not mean any waiver from
complying with the requirements of this clause, if for any reason the concrete
to be removed has already hardened.
After straight edging of the surface, it shall be finished by brooming in the
manner described as mentioned in the following paragraphs.
Brooming - After belting and as soon as surplus water if any has risen to the
surface, the pavement shall be given a broom finish with an approved long
handled steel or fiber broom conforming to the stipulations laid down in
JRC - 43 -1972. The broom shall be pulled gently over the surface of the
pavement from edge to edge. Adjacent strokes shall be slightly overlapped.
Brooming shall be' perpendicular to the centre line of the pavement and
so executed that the corrugations thus produced will be uniform in
character and width, and about 5mm deep. Brooming shall be completed
before the concrete reaches such a stage that the surface is likely to be torn or
unduly roughened by the operation. The broomed surface shall be free from
porous or rough spots, irregularities, depressions and small pockets, such as
Initial curing - After completion of the finishing operations, the surface of the
pavement shall be entirely covered with wet hessian cloth, burlap or jute mats.
The coverings used shall be of such length (or width) that when laid will
extend at least 500 mm beyond the edges of the slab, shall be so placed that
the entire surface and both the edges of the slab are completely covered. They
shall be placed as soon as the concrete has set sufficiently to prevent marring
of the surface. Prior to their being placed, the coverings shall be thoroughly
wetted with water and placed with the wettest side down. They shall be so
weighed down as to cause them to remain in intimate contact with the surface
covered. They shall be maintained fully wetted and in position for 24 hours
after the concrete has been placed, or until the concrete is sufficiently hard to
be walked upon without suffering any damage. To maintain the coverings
wet, water shall be gently sprayed so as to avoid damage to the fresh
concrete. If it becomes necessary to remove the coverings for any reason,
the concrete slab shall not be kept exposed for a period of more than half an
hour.
(a) Curing with wet earth - Exposed edges of the slab shall be banked with a
substantial berm of earth. Upon the slab shall then be laid a system of
transverse and longitudinal dykes of clay about 50 mm high, covered with a
blanket of sandy soil free from stones to prevent the drying up and cracking
of clay. The rest of the slab shall then be covered with sufficient sandy soil
so as to produce a blanket of earth not less than 40 mm depth after wetting.
The earth covering shall be thoroughly wetted while it is being placed on the
surface and against the sides of the slab and kept thoroughly saturated with
water for 14 days and thoroughly wetted down during the morning of the 15th
day and shall thereafter remain in place until the concrete has attained the
required strength and permission is given to open the pavement to traffic.
When such permission is granted, the covering shall be removed and the
pavement swept clean. If the earth covering becomes displaced during the
curing period, it shall be replaced to the original depth and re -saturated,
Removing forms - Forms shall not be removed from freshly placed concrete
until it has set, or at least 12 hours, whichever is later. They shall be
carefully removed in such a manner that no damage is done to the edges of
the pavement. After the forms have been removed, the slab edges shall be
cleaned and any limited honey -combed areas pointed up with 1 -2 cement
sand mortar, after which the sides of the slab shall be covered with earth to the
level of the top of the slab for final curing Slabs with excessive honey -
combing as a result of inadequate compaction shall be removed between
nearest transverse joints.
maintained clearly indicating any lanes open to the traffic. Where, as shown
on the plans or indicated in the special provisions, it is necessary to provide
for traffic across the pavement, suitable and substantial crossings to bridge
over the concrete shall have to be provided. Such crossings, as constructed,
shall be adequate for the traffic and approved by the Project Manager.
Any part of the pavement damaged by traffic or other causes occurring prior
to its final acceptance shall be repaired or replaced in a manner satisfactory
to the Project Manager. The pavement shall be protected against all
traffic usage including that of construction - traffic.
Sealing of joints - After the curing period is over and before the pavement is
opened to traffic, the temporary seal and all other intruded materials in the
transverse expansion and contraction joints as well as longitudinal joints shall
be removed completely and the groove; filled with the approved joint sealing
compound as per IRC - 57 -1974 "Recommended Practice for Sealing of
Joints in Concrete Pavements”. The joint opening shall be thoroughly cleared
of all foreign matter before the primer followed by sealing material is placed.
If necessary, the foreign matter shall be blown out by compressed air pressure.
All contact faces of the joint shall be cleaned with a wire brush to remove
loose material and shall be surface dried before the primer is applied.
14 GeneralCivilSpecifications
Thefollowingcivilspecificationsshallbeapplicableforprovidingandexecutingall
such itemswhicharenotmentioned inforegoing parasbutarenecessary
tobeprovided andfor the itemsin billofquantitieswhich arementioned
abovebutrequiresome elaboration.Noextra
costshallbepaidforsuchitems.Itshouldclearly beunderstoodby
theContractorthatallcivilspecificationsmentionedherebelowshallbetreatedaspart
of
thetechnicalspecificationsalreadymentioned.Thespecificrequirementofdifferent
itemsofwork involvedintheconstruction,completionandcommissioning of
thesystem asawhole,shallbeprovided in accordancewith therequirementgiven
in thesecivil specifications.
14.1 Site Clearance
Before taking up construction,siteshallbe clearedofall
jungles,bushesandunwanted
vegetationgrowth.Aftercompletionofplant,theentiresiteareashallbeclearedofall
leftovermaterialanddebris.Thework shallbecarriedoutinaccordancewith the
specifications inbill ofquantities andpaymentshallbeasperquotedrates for the
respective items.
14.2 Sectionsforexcavationfor allunderground structures and pipelines
Contratorshallpreparesectionaldrawingsshowing thedetailsofexcavation forall
undergroundstructuresand pipe lines, in allkindsofsoils,boulders,softandhard
rock etc., basedon testresultsofsoiltesting and investigation reportscomplying
to specifications in this document for earthwork excavations and shall
submit to the Project Manager for review and approval, prior to starting
ofthework.Ifduring excavationany changeinsectionisconsiderednecessary
forreasonsofsafety ofworkers,theProject Managerwill
issuedirectionsforcomplianceby theContractor. TheContractorshallcomply
withthe Project Manager’s directionswithoutanyextracharge orpayment.
14.3 FormWork
Formwork,shuttering,centering,scaffoldingetc.,shallbeofsteelplatesorplywood,
linedwithMS-sheetsand forscaffolding steeltubularshallbeused. Jointsshouldbe
sufficientlytiedtopreventlossofcementslurry from
theconcrete.Allforms,shuttering shallbe levelled,aligned, andthoroughly
cleaned,before they areused for concreting. Formwork shallbe
removedafterspecifieddays ofcuring with theprior written permissionofthe
Project Manager. Thesurface ofRCCafter removalofformwork /shuttering
shallbesmooth andeven and withouthoneycombingorundulations.
14.4 Procedure andMaterialsused inconcreteworks.
Theprocedureforconcreteworksshallbeinaccordancewiththespecificationsinthe
billofquantities,specifications in thissection andcomplying tostandard practices
14.2 Sections for excavation for all underground structures and pipe lines
Contrator shall prepare sectional drawings showing the details of excavation
for all underground structures and pipe lines, in all kinds of soils, boulders,
soft and hard rock etc., based on test results of soil testing and investigation
reports complying to specifications in this document for earthwork
excavations and shall submit to the Project Manager for review and
approval, prior to starting of the work. If during excavation any change in
section is considered necessary for reasons of safety of workers, the Project
Manager will issue directions for compliance by the Contractor. The
Contractor shall comply with the Project Manager’s directions without any
extra charge or payment.
Aggregates
All aggregates, fine and course used in concreting works shall comply to the
standards laid down in IS: 456-2000 with latest amendments and
specifications in applicable clauses in this section.
Water
The water used in all concreting works shall be of potable quality and tested
before usage in the construction works and shall be confirming to IS: 456-
2000.
Cement
The cement used shall be of sulphate resisting cement/PPC/PSC
confirming to IS: 12330/IS-1489-part-1/IS-455 with latest as specified and
where ever the concrete is coming in contact with sewage. For other
concreting works like encasing pipe, pedestals and other structures where
there is no contact with sewage, it shall be OPC/ PPC/PSC confirming to
IS:8112 with latest amendments and revisions. Minimum clear cover over
Reinforcement Minimum clear cover over the steel reinforcement shall be
50mm for the members contact with soil/ground water. For other faces the
clear cover over the reinforcement shall be as per latest IS Codes.
Tested Steel
Only tested and approved steel shall be used for reinforcement in RCC works,
and the Contractor shall produce the test certificates to the Project Manager.
The type of steel used shall be of TMT of grade of steel Fe: 500 confirming
to relevant IS.
2 Design period
2.1 Intake years 30
2.2 Water treatment plant years 15
2.3 rising mains years 30
2.4 Electrical & Mechanical years 15
2.5 Gravity mains years 30
2.6 Storage years 15
2.7 Distribution system years 30
3 Service level lpcd 135
3.1 Households % With % 100%
houseconnections%
3.2 Terminal pressures atmeters10
Household
3.3 Peak Day Demand Factor 3.0
for Conveyance
3.4 Peak Demand Factor for Distribution
3.5 Supply hours hours 24
3.6 Service storage hours 8
4 Treated water quality To conform to latest revision/update of
IS:10500
4 Power Supply
4.1 Power tariffs for water supply Rs. 5.00 per KwH (July/2016)
4.2 Annual increase in Power Tariffs 3 percent
To be considered for design purposes
4.3 Is dedicated power supply to be provided? No
maintenance of system
Check the operation and maintenance of the entire water supply system on
sample basis and conduct such tests as to ensure the performance of each step of water
treatment as per the design, pressure test at farthest customer end, service
level,residual chlorine at different locations to check the performance indicators.
Review and check the maintenance of appropriate records that present the
verification of the performance indicator.
Conduct sample checks on water quality for all parameters as per standards
Witnessing whether the system pressure tests are carried out by the Contractor
on a systematic basis
The periodicity of IVT to perform sample tests and checks as mentioned above
shall be once in every month.
The IVT will be conducting checks for Operation and Maintenance for the First
Period only. MPUDC will appoint a panel of Engineers independent of the MPUDC
and the contractor, to verify the achievements of the Contractor during the second
period of the Operation and Maintenance.
Suggested construction quality checklists
Sr. No. Attribute Yes/No
MATERIALS
1. Is coarse aggregate as per sample?
2. Is fine aggregate as per sample?
3. Is cement fresh and free from clods?
4. Does the cement set within one hour?
5. Is sand free from silt?
6. Are steel bars of correct diameter?
7. Does the steel bend without breaking?
8. Are the pipes from tested consignment?
9. Is the pumping machinery identical to tested sample?
FOUNDATIONS
1. Are the foundation approved by the Project Manager including SBC?
2. Is sand filling provided?
PLAIN/REINFORCED CONCRETE
1. Is concrete Mixer used?
2. Is water measured for concreting?
3. Is vibrator used?
4. Is slump test done?
MASONARY
1. Are bricks soaked with eater before use?
2. Are joints broken?
3. Whether masonry started from corner?
4. Whether masonry constructed for uniform length?
5. Is mortar applied to each brick before placing the position?
6. Is dressing of stone done before placing?
7. Is watering of stone done before placing?
8. Are bond stones dressed?
9. Is base of face stones more than height?
10. Is the masonry to plumb?
11. Are the joints raked?
RCC WORKS
1. Are cover blocks cast in CM-1:2?
2. Are centering supports spaced less than 0.6 mt and adequate braces
provided?
3. Are the posts resting on firm ground with wooden wedges?
4. Are steel plates used for centering bottoms and sides?
5. Are the gaps in centering closed?
6. Is centering level checked?
MATERIALS
1. Is plumb checked for columns?
2. Is centering checked/ approved before placing reinforcement?
3. Is TOR steel reinforcement as per drawings?
4. Are chairs used to prevent disturbance of reinforcement?
5. Are lap lengths OK and at suitable position?
6. Is reinforcement checked/approved and measurement recorded before
placing concreting?
7. Is water proofing done when roof slabs are green?
8. Is curing being done at the time of visit?
9. Is remolding done after the required period?
10. Are patches of surface touched immediately after de-molding?
PLASTERING
1. Is the sand for plastering free from silt?
2. Is the surface cleaned and watered before plastering?
3. Are the plumb, line and thickness checked and correct?
PIPES SPECIALS AND APPURTENENCE
1. Are the PVC, HDPE etc pipes stored under shade with covers?
Page 457 of 553
Technical Specifications
2. Are the locations as per plans? Are PVC pipes properly protected by
covering during storage?
3. Are the flanged dimensions as per standard thickness, pitch,
circle/diameter?
4. Are the faces of flanges machined?
5. Is rubber indertion of required quality and thickness?
6. Are the bolts and nuts are of good quality and sizes?
7. Are the pipes and specials aligned to gradient and plumb?
8. Are the bolts and nuts tightened properly?
9. Are the specials and valves supported properly?
10. Are thrust blocks provided for bends?
PIPE LAYING
1. Is alignment of pipe lines as per plans?
2. Are trench dimensions and levels as per plans?
3. Is the soil at bottom of pipes good for laying of pipes?
4. Are the pipes and specials lowered and aligned true to gradient and line?
5. Is the required cushion provided?
6. Are pipe ends cleaned before jointing?
7. Has manufacturer’s instruction for jointing (PVC pipes) been followed?
8. Are the pipes cleaned inside before laying?
9. Are the ends of pipeline closed before the day’s work?
10. Are air valves, line valves, scour valves etc provided at stipulated
locations?
11. Are the pipelines sectionally tested as per CPHEEO manual before
commissioning?
12. Is refilling done gently and extent of compaction carried out as per
specification?
Timescale in Months
Task Dura 1 1 1 1 1 1
# Name tion 1 2 3 4 5 6 7 8 9 0 1 2 3 3 4 15 16 17 18 19 20 21 22 23 24
Surve
y,
Geo-
Commis
techni sioning
cal
invest and
igatio 30
1 ns etc Days testing
Desig
n and
of whole
drawi 60 system
2 ng days
Const
ructio
n of INTAKE WELL
Intake 330
3 well Days
Raw
Water 180
4 Pump days
Raw
Water
Risisn
g 120
5 Main Days
Const
ructio
n of
6 Water Water Treatment Plant
Treat
ment 540
Plant Days
CW
7 Pump 180
s days
CW
Risin
g and
8
Feede
r 480
Mains days
Const
ructio
n of
ESR 8
Nos.
Cum.
Capac
ity
15970 510
9 KL Days
Provi
ding,
Layin
g&
jointi
ng of
1
0
distrib
ution
House
520
Days Distribution network
Conn
ection
s:
20000
Nos.
HT
Feede
r Line Physical
& Charging
Works
1 Subst 150
1 ation Days
240
1 SCA DA
2 DA YS
Work Program for Providing House Connections at the start of and during Operation and
Maintenance Period
At the end of Cumulative Number of Connections
No. of New Connections
Year Targeted
0 17000
1 23000 6000
2 25000 2000
3 26500 1500
4 28000 1500
5 29100 1100
detaileddesigndocumentsto
prevent unnecessary
disruptionofservices
duringconstructionphase;and
Require construction
contractors toprepare a
contingency plan to include
actionsto be donein caseof
unintentional interruption
ofservices. Measures are
taken to ensure they are
protected and conserved.
Dust Minimizing the number of contractor Throughout
emissions motorised vehicles on use; construction
Provide scour checks on over- period
15% slopes or when working
in loose soils;
Use predetermined tracks;
Avoiding machinery working
in seasonally marshy areas,
pans and floodplains;
Wet all active construction
areas as and when necessary
to reduce dust;
Prioritizeareaswithinornearest contractor Throughout
Constructio possiblevacant spaceinthe construction
n work subprojectlocation; period
camps, Ifit isdeemednecessary
stockpile tolocate elsewhere,consider
areas, sitesthat willnot
storage promoteinstability andresultin
areas, and destruction of property,
disposal vegetation, irrigation,and
areas drinkingwatersupply systems;
Donotconsider
Page 462 of 553
Technical Specifications
residentialareas;
Take extreme care inselecting
sitestoavoiddirectdisposaltow
ater body which
willinconveniencethe
community.
Air Quality Consult withMPUDC/PMC contractor / Throughout
onthe designated areasfor PIU construction
stockpiling of clay, soils, period
gravel,and other
constructionmaterials;
Dampdownexposedsoil
andany stockpiled onsiteby
sprayingwith
waterwhennecessary
duringdry weather;
Use tarpaulinsto cover sand
and other loose materialwhen
transported bytrucks;and
Fitallheavy equipmentand
machinery withair pollution
control
deviceswhichareoperating
correctly.
peakhours;
Locateentryandexit pointsin
areaswherethereis
lowpotentialfortraffic
congestion;
Keepthesitefreefrom
allunnecessaryobstructions;
CoordinatewithTraffic
Policefortemporaryroad
diversions,wherenecessary,
andforprovisionoftrafficaidsif
transportationactivitiescannot
beavoidedduringpeakhours
Disposal of Maximize the re-use of contractor Throughout
Spoils excavated materials in the construction
works as far as feasible to period
ensure that no permanent
spoil dumps are created
Properly dispose off the spoil
in the identified by the design
team and approved by the
confirmed land owners;
Care should be taken to avoid
spoil location in land that
could otherwise be used for
productive purposes.
Solid Waste Construction waste should be contractor Throughout
recycled or reused as much as and PIU construction
possible to ensure that period
materials that would
otherwise be disposed off as
waste are diverted for
productive uses;
The Proponent shall put in
place measures to ensure that
Page 466 of 553
Technical Specifications
construction materials
requirements are carefully
budgeted and to ensure that
the amount of construction
materials left on site after
construction is kept minimal;
Minimization of solid waste
during construction of the
proposed Project through use
of durable, long-lasting
materials that will not need to
be replaced often, thereby
reducing the amount of
construction waste generated
over time;
Skips and bins should be
strategically placed within the
campsite and construction
site, they should also be
adequately designed and
covered to prevent access by
vermin and minimize odour.
They should also be emptied
regularly;
Measures to ensure that waste
materials from the Project are
disposed at suitable sites will
be taken. These will include
engaging only reputable
truckers and conducting
appropriate spot checks to
verify that disposal are done
in accordance with the
requirements of MPUDC;
The ultimate fate of the
Page 467 of 553
Technical Specifications
chemicals / materials;
During the course of the
construction works,
temporary drainage channels
should be constructed to
encourage dispersal of
meteoric waters
Workers To reduce the workers contractor Throughout
accident and accidents and hazards the construction
hazards Proponent will develop and period
commit the Contractors to
Site Occupational Health and
Safety rules and regulations
as stipulated in the Labour
Law;
All construction workers
should be advised of the
dangers associated with
construction work;
Workers should be provided
with suitable personal
protective equipment (PPE);
Provision of adequate sanitary
facilities to workers;
Train all workers on Safety
Health and Environment
(SHE) with an aim of
improving awareness;
Trenches over 1.5 m deep or
wherever soil conditions
dictate should be shored and
secured against accidental
entry by workers and the
public;
Install safety signage along
Page 469 of 553
Technical Specifications
Asbestos cement pipes often are found in underground utility conduits and municipal
water, sewer and drainage systems. Asbestos cement pipes buried below ground are
considered non-friable if they are in good condition. It should be noted that active
asbestos cement pipe that is exposed and is not intended to be replaced or removed and
is not disturbed by repair or replacement activities may remain in place and be
backfilled.
a. Pre-Demolition/Renovation Survey
Owner and contractor are responsible for determining whether cement pipe in
a particular utility conduit that will be subject to demolition or renovation
contains asbestos. This requires owner and contractor to conduct a “thorough
inspection” to determine the location of asbestos containing materials before
starting demolition or renovation.
b. Handling Practices
When repairing, removing or replacing asbestos cement pipe, it is important to
handle the pipe in a manner that will minimize the risk of making it friable or
releasing asbestos dust into the environment. Start by exposing the asbestos
cement pipe with minimal disturbance. Excavate no closer than 6 inches of the
pipe. Carefully uncover the remainder of the soil surrounding the pipe by hand
or with a shovel. An assessment should then be made to determine if the pipe
is damaged, cracked or broken.
ii. Damaged Asbestos Cement Pipe (deteriorated or not intact) or when cutting
or mechanical breakage (e.g., with saws, snap or blade cutting, and/or
tapping) is necessary:
1. Place 0.006 inch thick polyethylene (“poly”) sheeting under the asbestos
cement pipe to prevent soil contamination.
2. Adequately wet asbestos cement pipe with amended water where cutting or
breaking will occur.
3. Saw cutting of asbestos cement pipe shall only be conducted with a HEPA-
shrouded vacuum attachment or wet cutting equipment, unless it is conducted
within a small enclosure that isolates the area in which the saw cutting is
being conducted to prevent the release of asbestos fibers to ambient air, .
4. Wrap wet asbestos cement pipe in two layers of 0.006polyethylene sheeting,
seal with duct tape and label. This can be done either in the trench or adjacent
to the trench.
Appendix 3B
FORM OF AGREEMENT B
THIS CONTRACT is made and entered into this ____ day of _______, [Year]
Between Managing Director, Madhya Pradesh Urban Development Company
Limited, Madhya Pradesh, a company incorporated under the laws of Indiaand
having its principal place of business at Beej Bhawan, Mother Theresa Marg, Arera
Hills, Bhopal (hereafter the “Owner”)
– and –
[Name of Contractor Company] incorporated under the laws of [place of inCouncil]
with its principal place of business at [Address of the Contractor]
(hereafter the “Contractor”)
– and –
[Name of the Contractor’s Parent Company or any other entities the Owner may be
required to be parties to the Contract]
WHEREAS:
1. The Owner has the jurisdiction to enter into the Contract pursuant to the
Applicable Law;
2. The Owner has received all requisite approvals necessary and has conformed
with all requisite laws in accordance with the Applicable Law to permit the Owner to
enter into the Contract;
4. The Contractor has represented to the Owner that it has the skills and ability
toOPERATE AND MAINTAIN THE BUILT SYSTEM FOR 5 YEARS in an
economical and effective manner with reduced cost and increased profitability and
agrees to do so upon and subject to the terms and conditions of the Contract
Page 477 of 553
OPERATION AND MAINTENANCE AGREEMENT
Documents;
6. The Contractor has the corporate capacity and authority to enter into the
Contract; and
5.1 The Owner hereby appoints the Contractor to be the sole and exclusive
manager of the Water Supply System in the Water Supply Area for the
duration of this OMSA.
5.2 The Contractor shall, in such manner and at such times as it shall in its
absolute discretion see fit, use all its skills and knowledge to manage,
administer, conduct, maintain and develop the water supply system in the
Water Supply Area in an efficient and professional manner, in the best
interests of the Owner, and in accordance with Good Industry Practice and
Applicable Law. In particular but without prejudice to the generality of the
foregoing, Contractor shall carry out the duties and obligations set out in this
Agreement to ensure that the performance of the Water Supply System is in
compliance with the terms and conditions of this Agreement and meets the
Performance Standards specified in Schedule 4.
5.3 The qualification and experience of the key staff as identified in the Bid for
the Operations and Maintenance Period is attached in Schedule 7 to this
OMSA. . The Contractor shall confirm the key staff being available and
ready to start work in the Water Supply Area at least 3 months prior to the
Page 480 of 553
OPERATION AND MAINTENANCE AGREEMENT
6.3 The Contractor shall maintain in good working condition, throughout the
term of this OMSA, the assets referred to in sub-clause 6.1 and shall ensure
that adequate control is maintained over assets owned by, or in the custody
of the Contractor.
6.4 The Contractor shall not dispose of or create any lien, charge or proprietary
interest of any nature whatsoever in favor of the Contractor or a third party
in the assets referred to in sub-clause 6.1, except on the express written
instruction of the Owner.
6.5 The Contractor shall comply with any directions of the Owner to use or
dispose of any asset or any money or other consideration to which the
Owner becomes entitled as a result of disposing of any asset referred to in
sub-clause 6.1.
6.6 The payment to the Contractor during the First period and second period,
shall be governed by the payment mechanism defined in the Second
Schedule
7) OBLIGATIONS OF THE CONTRACTOR
7.1 During the term of this Agreement, the Contractor shall be
responsible for operation and maintenance of all components, including and
without limitation components built new and existing, of the water supply
and distribution system, and including ancillary equipment, in compliance
with the terms and conditions of this Agreement to meet the Performance
Standards specified in Schedule 4. This will include all systems supporting
the provision of services including installed SCADA system, customer
grievance redressal system, billing systems and any other works included
under the contract
7.2 The Contractor shall procure grants, lienses and renewals of, and
keep up to date, all Applicable Permits to enable the Contractor to perform
the Services throughout the term of the Agreement other than those
Applicable Permits that are to be applied for by the MPUDC
7.6 The Contractor shall undertake calibration of all meters for the term
of the Agreement, so as to ensure that the meters operate within an
acceptable range of accuracy not exceeding [±5%]; calibration shall be
undertaken in the presence of a representative of the MPUDC.
7.8 In discharging the duties and obligations referred to in sub-clauses above, the
Contractor shall:
(a) exercise due diligence, efficiency and economy in accordance with generally
accepted professional conduct and practice, and shall employ sound
management practices and appropriate technology in the best interests of the
Owner;
(b) comply with:
(3) provisions of all relevant laws relating to the duties and obligations
referred to in sub-clause 7.1, including as relating to occupational health
safety of employees, to the environment, to the collection and payment of
taxes and to any other matter whatsoever.
(4) the terms of any water or waste discharge permit granted to the Owner.
(5) any notice, instruction or direction issued in accordance with clause 4
(c) familiarize himself and be in confirmation with the terms of the Indian
legislation for Water Supply and any statutory clearances for the Water Supply
System and shall perform the Service in conformity with all of the conditions of
these consents.
(d) pay all taxes, rates, charges, fees, and penalties and provide all returns, files and
documents required of it under applicable tax laws or other laws and discharge
all obligations imposed on it by such laws
Failure by the Contractor to comply with the foregoing provisions shall amount to a
breach of this OMSA, subject to clause 21 at the discretion of the Owner.
8.1 One month prior to the commencement of the operations period, the Contractor
shall prepare and provide MPUDC a plan containing its proposed operating strategy
and programme of preventive and other scheduled maintenance for the first year of
operations (Draft Operations and Maintenance Plan). Subject to approval by the
MPUDC, the plan shall comply with the operation and maintenance manual and safety
requirements. The Draft O & M Plan shall include
(a) implementation plan for effective operations and maintenance, leakage control,
asset management and customer services and emergency repairs.
(b) required and proposed extensions or additions to the water supply systems,
along with the justification and the cost implications
(c) other information that the Contractor may consider appropriate or that may be
specified by the Owner
Upon approval by MPUDC, or expiry of 30 days from submission, the Draft O
& M Plan shall be the approved O & M Plan to be implemented by the Contractor.
8.2 The Plan shall be prepared and submitted for approval annually before the
start of any year of operations.
Page 484 of 553
OPERATION AND MAINTENANCE AGREEMENT
8.3 The Contractor shall be responsible, at its own cost, for managing all
preventive maintenance and normal repairs, major maintenance or replacements
(if any required) to the system as per the O & M Plan, including rectifying
damage to the system due to any act of negligence in performance of its
functions, deemed necessary to maintain the value of the assets included in the
Third Schedule and ensure operations in compliance with the Performance
Standards in the Fourth Schedule. This responsibility extends to Water supply
system for the First Period and for the Water Supply System for the Second
Period.
8.2 If the Contractor is of the opinion that matters have arisen that may prevent, or
significantly affect the implementation of the O & M Plan, the Contractor shall
immediately notify the Owner of its opinion and the reasons thereof.
8.2 In case of occurrence of an insurable event, the Contractor shall be responsible
for informing the insurance agency about the event, complete any survey,
follow-up with the insurance agency for insurance claim settlement and
repair/replacement of assets affected by the insurable event. The expenditure on
repair/replacement shall be certified by the Project Manager. In the event the
expenditure on repair/replacement of assets due to insurable event is more than
the insurance claim settlement, the difference would be borne by the Owner.
9. BILL GENERATION AND DISTRIBUTION
9.1 During the Operation and Maintenance Period, the Contractor shall be
responsible for meter reading; generation of bills to customers as per metered
consumption and water tariff fixed by the Owner and provided in Sixth Schedule; and
delivery of bills to customers.
9.2 The Contractor shall undertake generation of bills in the name of KNP and
distribution of bills on behalf of KNP
9.3 The Contractor shall follow good industry practices including use of modern
technology including but not limited to mobile hand-held devices for billing and
distribution
9.4 The responsibility for collections remains with KNP. Notwithstanding this, the
Contractor shall not accept customer payments.
9.5 The records for billing and collections of water charges shall be updated in real
time in the financial management system and customer data base developed by the
Contractor, and accessible to the BMC. Viewing access for collection records for
each, and all customers in the Water Supply Area shall be provided by the BMC to the
Contractor
10.1 Subject to the provisions of this Contract and in consideration of the Contractor
accepting the rights under this Contract, and undertaking to perform and discharge its
obligations in accordance with the provisions of this Contract, the MPUDC agrees and
undertakes to pay to the Contractor Fees in accordance with Schedule 4.
10.2 The payment of Contractor Fee for services shall be on basis of quarterly
invoices specified in Schedule to this Agreement.
10.3 The Contractor Fee payable shall be subject to meeting Performance Standards
and adjusted in the manner provided in Schedule 4.
10.4 The Contractor should raise invoice within 15 days of completion of a quarter
for services relating to the previous quarter and submit the same to PIU of
MPUDC. The MPUDC shall certify and approve the payment of the invoice within
45 days of submission of the invoice.
10.5 The Owner shall be responsible for making quarterly payment to the Contractor
for services provided.
10.6 During the Operations Period, all requests for new connections will be
submitted to the Contractor, but require to be authorized and approved by the KNP.
The Contractor shall provide such water connections as are approved by the KNP
within a period of 15 (fifteen) days from the receipt of an intimation from the KNP,
provided the distance from the boundary wall of the property to the distribution
network is within a distance of 20 meters.In case of extensions of network, the
contractor shall provide the connection within 15 days for authorization by KNP,
provided that the extension has been authorized and approved six months prior to
such properties requesting connections.
10.7 The Contractor shall be reimbursed by the MPUDC the actual cost of providing
a new connection. The PIU shall estimate the cost of providing a new connection,
Page 486 of 553
OPERATION AND MAINTENANCE AGREEMENT
which may include pipe, material, labor, road cutting and repair, and other relevant
expenses, (except supervision) every year based on the prevailing Schedule of
Rates.
10.8 The Contractor shall not be paid any separate fee for supervision of activities
related to providing a new connection.
10.9 The Contractor shall continuously update the existing customer database to
incorporate new connections installed, disconnections (as may be) and
reconnections.
11.1 The Contractor shall keep proper and adequate accounts and records of
the transactions and affairs of the water supply and shall keep records that are
necessary to explain the financial operations and financial position of the
system.
11.2 During the O&M Period the Contractor shall keep a computerized
database of customer’s records including billing and collection. Collection
information would be updated based on actual collection information for each
customer as available with the accounting system of KNP. The contractor shall
be given access to the water charge collection accounts of KNP. The Contractor
shall keep a record in an electronic format using simple office management
software. There should be suitable controls to prevent unauthorized access to
these records. The Contractor shall be required to allow inspections of these
records to the owner or his authorized representatives.
11.3 The Contractor shall develop and maintain an adequate budgeting and
accounting system. The Contractor shall develop and maintain an adequate
internal accounting control system.
11.4 The accounting period of the Contractor shall coincide with the
accounting period of the Owner.
11.5 Without detracting from sub-clause 11.1, the Contractor shall keep the
records referred to in the Fifth Schedule of this Operations and Maintenance
Aggreement and shall retain those records for the period prescribed in the
Schedule..
11.6 Except as provided below and specified otherwise in any other clause, all
records are confidential to the Contractor and the Owner..
(a) Any customer or former customer of the Contractor may apply to the
Contractor for a copy of all records held by the Contractor concerning that
customer, in such a form as may be prescribed by the Owner.
(b) The Contractor shall provide a customer or former customer under sub-
clause 11.6 (a) with a copy of the relevant records, but may impose a
reasonable charge to cover the costs to the Contractor of making the copy
available in accordance with clause 11.6(a).
12. REPORTING REQUIREMENTS
12.1 The Contractor shall, in respect of each quarter of a financial year and no
later than 15 calendar days after the end of such quarter, prepare a report to the
Owner containing:
(a) information about, and an analysis of, its operations for the quarter and
cumulatively for the year to date; and
(b) Financial statements in accordance with Generally Accepted Accounting
Principles for the quarter and cumulatively for the year to date.
12.2 The report referred to under sub-clause 12.1 shall:
(a) be prepared in a form acceptable to the Owner;
(b) contain the information specified in the Fifth Schedule of this Operations
and Maintenance Agreement and any other information determined by
the Contractor to be appropriate; and
(c) Contain any other information reasonably required bythe Owner.
12.3 The financial statements referred to under sub-clause 12.1 (b) shall:
(a) contain information determined by the Owner to be appropriate;
(b) include an assessment of the cost of carrying out any other obligation
that is imposed on the Contractor under this OMSA and that requires the
Contractor to act otherwise than in accordance with normal commercial
practice;
(c) be prepared in a manner and form approved by the Owner; and
(d) Present fairly the results of the financial transactions of the Contractor
during the financial period to which they relate and the financial position
of the Contractor as at the end of that period.
12.4 The Contractor shall, in respect of each calendar month, and no later than
5 days after the end of such month, prepare a report to the Owner containing:
(a) the billings for the month showing distinctly the net billings, and gross
billings;
(b) collections for the month showing distinctly the net billings, and gross
billings collected;
12.5 The Owner may require and the Contractor, when notified, is obliged to
appear in meetings of the Owner convened to discuss the affairs of the Owner.
The Owner may request the Contractor to make such presentations, reports,
demonstrations or take such actions as the Owner may deem necessary with
reasonable prior notice.
12.6 failure of the Contractor to comply with the provisions of this clause shall
amount to a breach this OMSA, subject to clause 21 at the discretion of the
Owner.
13. INSPECTION BY THE OWNER
The Contractor shall allow the Owner and/ or any person representing the Owner,
access at any time to:
Without detracting from any duties, obligations and rights imposed on or conferred
upon (whether expressly or by implication) the Owner by this Operation and
Maintenance Agreement, or implied by law or commercial custom on persons similar
to the Owner, the Owner shall have duties obligations or rights in the following:
19. WAIVER
19.1 A failure, delay or indulgence on the part of either party in exercising any
power or right under this OMSA does not waive that power or right.
19.2 Any single exercise of a power or right under this OMSA does not
preclude any other or further exercise of it or the exercise of any other power or
right under this OMSA.
20. AMENDMENT OR VARIATION
This OMSA may be amended or supplemented, at any time, in writing signed by both
parties.
22. TRANSFER
22.1 The Contractor shall be responsible for transfer of all assets, equipment,
customer records and other material created or maintained by the Contractor for
the smooth operation and maintenance of the Water Supply System.
22.2 At least three months before expiry of the O&M Agreement, the Project
Manager shall assess, with assistance from IVT and/or PMC, if required, the
useful life of the assets pertaining to the KNP which are part of water supply
area. If the remaining useful life of assets is substantially less than what it
should be if these were operated as per prescribed methodology, the Contractor
shall be responsible for undertaking any refurbishment or replacement as
required before handover of the system at the end of O&M Period. If the
Contractor fails to undertake such refurbishment or replacement, such
reasonable amount as may be recommended by the valuer or otherwise can be
deducted from any payments due to the Contractor including termination
payment or Performance Security.
FIRST SCHEDULE
WATER SUPPLY AREA
Water Supply Area under this contract is the area under the jurisdiction of Khargone
Municipal Council as on the bid submission date. The Contractor shall, for the full
term of the Operation and Maintenance Agreement, have obligations to provide
services in compliance with the terms and conditions of this Agreement to the entire
Water Supply Area.
SECOND SCHEDULE
• The new assets constructed and the rehabilitated existing assets integrated with
the new assets under the Design Build Contract in the delimited water supply area, for
the duration of, and under the terms defined in the Operations and Maintenance
Contract.
1) The Contractor shall ensure that water is always available at consumer end. For
this:
• the Contractor shall deliver 24 hours water supply 7 days a week in the entire
water supply scheme area. He shall make his own assessment of equipment and works
to be part of the project to ensure such requirements – including requirement of power
supply to ensure efficient and effective water supply for 24 hours for all 7 days every
week during the entire contract period.
• there is, or is reasonably likely to be, a risk that would endanger human life or
any part of the environment, or compromise the health or safety of any person, or the
safety of any works of the BMC, or would prevent or disrupt the operation of a water
treatment plant.
3) The Contractor shall not be deemed to have failed to comply with the provision
above whenever an interruption to supply occurs, because of :
• failure of the national grid electricity supply system for more than 12 hours at
any of the Contractor’s head works, treatment works or pumping stations, where no
stand-by generator is installed; or an act of God (force majeure)
The Contractor shall treat all water supplied to in compliance with the Indian Standard
Specifications for Drinking Water IS:10500, Dated 1992.(reaffirmed 1993)
The Contractor shall ensure that the quality of water throughout the water supply
system does not exceed the limits given in this standard.
The Contractor shall ensure that the residual pressure complies with Clause 9.2 of the
Indian Manual on Water Supply and Treatment (third edition - revised and updated) by
Ministry of Urban development, New Delhi, March 1999:
• the pressure in the water supply system is always sufficient to prevent back-
siphoning or infiltration of water into the system;
• compulsory water restrictions are not imposed on customers more than once in every
2 years; and
The Contractor shall ensure that all houses within the water supply scheme area are
covered and provided with water.
The Contractor shall on all works covered under the Operation and Maintenance
agreement:
• maintain and keep the works in good repair and working condition;
• ensure that the water supply system operates effectively at all times; and
• take appropriate action within five hours of any failure in any part of the water
supply system being discovered by it, or brought to its attention.
The Contractor shall ensure that physical losses on the network are as follows
• Losses in the clear water conveyance system (including reservoirs) are less than
5 per cent per reporting period; and
• Losses in the distribution systemsyste are less than 10% per reporting period.
the Contractor shall, therefore, during the fulll period of operations, undertake periodic
leak detection surveys of the network and undertake necessary and prompt
repair/replacements to ensure that losses are contained within the limits specified
above.
The Contractor shall comply with all state and national legislation in relation to
discharges or disposal of any matter for which a waste discharge permit is required.
4.2.1 The contractor shall make arrangements to receive complaints 24 hours a day. In
addition, representatives of the Contractor shall be available at each of the Customer
Page 496 of 553
OPERATION AND MAINTENANCE AGREEMENT
Service Centers, which shall be kept open between 0800 hours and 1900 hours fora
minimum 6 days a week to receive complaints from users who wish to make enquiries
or submit complains during the O&M Period.
1 The cost of providing trouble free operation of the flow meters including labour
and spare parts and other such services incurred by the Contractor during Warranty
and Maintenance period shall be borne by the Contractorand cost will be included in
O&M fee.
2 The warranty and maintenance period shall start after installation and
commissioning of all the flow meters. The warranty period shall be for 1 year after
installation and commissioning of all the flow meters and successful completion of the
work. The maintenance period shall be 60 months including one year warranty period.
The Contractor shall keep all the flow meters in working condition during warranty
and maintenance period with specified accuracy level. Contractor will supply parts for
the repair, and cost will be included in O&M fee. No separate payment shall be
admissible for any parts provided.
3 The Contractor shall ensure trouble free operation of the flow meters during
maintenance period. The spare parts required to run the system smoothly during above
period shall be made available at all the sites without any loss of time.
4 During maintenance period, the Contractor shall arrange and install standby unit
or replace or repair the flow meters at his cost. Payment for this shall be included in
O&M fee.
5 During the maintenance period, Contractor shall check all the flow-meters
monthly and take meter reading once in a month and submit the meter reading
statements to BMC / PIU. The frequency of check shall not be longer than a month and
he shall submit maintenance certificate every month. Contractor shall maintain the
history / job cards for all the flow meter and submit the same at the end of every year.
6 The maintenance staff shall be available at Khargone. All the breakdown calls
shall be attended within 48 hours of the communication. In case of failure to comply
with the requirement to replace / repair faulty or unserviceable flow meters promptly
within seven days, the Contractor shall be liable for compensation of Rs. 1000/- per
day per meter, subject to a maximum of Rs. 10,000/- per meter.
7 The Contractor shall not sublet / subcontract any part of work without prior
approval of Owner.
8 The Contractor shall maintain the system on a continuous basis 365 days in a
year.
9 The Contractor shall bring his own tools and tackles, site-testing equipment
required for normal maintenance of the flow meters.
11 Contractor shall make his own transport arrangement and accommodation of his
staff.
i.) Any fitting or pipe piece required to be replaced (as damaged by the contractor)
to make the fitting satisfactory for the repaired/ replaced meter will have to be
provided by the Contractor at his cost. Transportation and other charges shall also be
borne by the contractor.
ii.) The removed meters will be checked, repaired and tested expeditiously to
maintain a continuous flow of repaired and tested meters for replacement. The meter
so repaired will have accuracy as per ISO/ ISS, which shall be witnessed by PMU,
PIU/ BMC representative.
iii.) The Contractor shall provide a meter repair facility. Contractor shall also
maintain adequate staff to fulfill the maintenance responsibility. An authorized
representative of the Contractor will be responsible for the entire maintenance work.
He shall interact with the PIU/ BMC officials to ensure smooth and satisfactory
performance. The Contractor shall maintain register of complaints of water meter from
PIU Engineer /BMC/ Public and will acknowledge the same with complaint number.
iv.) All the material / spares required for rectification of defective meters during
Maintenance shall be supplied by the Contractor including testing and calibration of
the meter at his own cost as the same is included in his maintenance charges.
v.) The water meters are mechanical devises, which normally deteriorate in
performance over time. The fact that a meter does not show outward signs of any
damage and has a register that appears to be turning does not mean that the meter is
performing in a satisfactory way. It is necessary to ascertain the following preventive
cares for water meter after proper installation.
• To clean the chamber in which the meter is installed and keep it free from
flooding and seepage.
• To remove the meter for further internal repair/ replacement if it does not show
correct reading pattern.
These are the only base breakdowns observed during periodical inspection. If a meter
found to be not working, it shall be removed immediately and replacement installed,
and the removed meter shall be sent to meter service workshop. In the meter
workshop, following steps are normally to be performed to carry you the repairs.
c. Inspect the cleaned parts and replace worn parts and gaskets, if any.
e. Inspect the sealing surface on meter body and paint the meter body, if necessary.
i. Calibrate and test the repaired water meter for leakage and accuracy as per IS
6784.
j. Make an entry in the life register of that water meter for keeping history record.
For electromagnetic flow meters in case of signal converter failure, cable failure and
battery back up failure, these will be replaced by new parts / items. However in case of
primary head failure, the meter shall be removed, another pipe piece put in its place to
keep water supply continuous, take meter body in factory, repair it and calibrate it in
factory.
THIRD SCHEDULE
Upon termination of contract the management of the above assets shall be transferred
to the Owner.
FOURTH SCHEDULE
PERFORMANCE STANDARDS, CONTRACTOR FEE AND INCENTIVES
1. Contractor Fee:
1.1 The Contractor Fee shall comprise the following components during the term of
the operation and maintenance period:
‐ Fixed O&M Fee: Fixed O&M Fee shall be paid as a lumpsum. The amount of
Fixed O&M Fee payable will be subject to the Performance Linked Adjustment
as provided in Para 3.3 of this Schedule 4.
Variable O&M Fee shall be paid per cum of metered water billed to the Customers.
The Variable O&M Fee shall be calculated as per Para 2 of Schedule 6 and will be
linked to adjustment under Appendix 5, Section 1 of this Contract.1.2 The payment of
the Fixed O&M Fee and the Variable O&M Fee shall commence from the start of the
operations and maintenance period. The payments collectively hereinafter are referred
to as “Contractor Fee”
Where:
• CTm = Contractor's Variable O&M Fee (in Rupees) for month 'm'
VOFRn = Variable O&M Fee Rate applicable for the accounting year 'n',
which is equivalent to the Base Rate (i.e. rate expressed in Indian Rupees
per kilolitre of water billed (Rs./kl), quoted by the Contractor in its Bid,
which is provided in Appendix 6, Schedule 1, and accepted by the
MPUDC), duly adjusted for the accounting year ‘n’ pursuant to the
provisions contained in Appendix 5, Section 1.
VBm-1 = aggregate “Volume of water Billed” by the Contractor to
Customers in month ‘m-1’, as determined on the basis of meter reading
records submitted by the Operator within 7 (seven) days from the end of
that month. MPUDC will independently verify the meter readings.
Note: The Variable O&M Fee Rate will exclude the charges payable to the Water
Resources Department or any other Government authority for raw water, which
shall be borne by the KNP.
(ii) Each Performance Standard has a weightage provided for in 3.2 below.
1. Parameter Coverage
Measured By Percentage of houses that have a piped network within
20m from boundary wall.
Monitored By KNP / MPUDC
Allowable - Areas where extension of network has not been
Exclusions approved by the Authority.
- Households which have completed construction
within six months prior to the evaluation period.
Benchmark 95% of all houses in the Service Area
2. Parameter Meeting House Service Connection Requests
1. Coverage 10%
4. Redressal of 40%
Customer Complaints
3.3.1 The Fixed O & M Fee payable for each Performance Parameter
will be calculated using the weightages in section 3.2. A maximum of Fifty
percent (50%) of the Fixed O & M Fee payable for each Performance
Parameter will be deducted for default in meeting Performance Benchmarks
listed in 3.1 above.
Thus, the total Fixed O & M Fee payable for the month would be the
aggregate of Fixed O & M Fee payable for each Performance Parameter
reduced as above.
FIFTH SCHEDULE
REPORTING FORMAT
During the operation period the Contractor shall prepare Quarterly, Annual and final
reports. All reports shall be prepared in the English and Hindi languages in hard and
electronic version for submission to the Owner.
Quarterly Reports
Throughout the assignment the Contractor shall submit Quarterly Reports to the owner
by the fifteenth day of the following month. Each report will show events and
summary operations for the Contractor’s activities for each of the main tasks.
The quarterly progress reports should be short and whenever possible prepared in a
tabular format for easy reference and comparison. A format for this report will be
submitted by the Contractor for approvalby the Project Manager.
(a) the percentage of the population in the Water Supply Area having direct House
Service Connections (HSCs)
(b) the number of new HSCs operationalizedduring the period, and also specifying
the number of new / additional HSCs operationalized in every quarter under
this Operations and Maintenance Agreement since Commencement Date
(c) The electronic registry of dated requests for HSCs received during the period;
date of clearance by KNP and date of connection, as per the signed report of
the Consumer
(d) the number of disconnections and reconnections
(e) the total number of water supply connections under various categories
(a) the total amount of water (in m3) extracted, treated, supplied and sold;
(b) the average amount of water (in m3) sold per connection per month
(c) the metered water consumption for the new connections established as part
of this Operations and Maintenance Agreement; and for any additional
connections agreed upon.
III Unaccounted for Water: This section will present information on Unaccounted
for Water computed
(a) as the difference between water supplied and water sold expressed as a
percentage of net water supplied;
(b) as the volume of water lost per kilometer of water distribution network.
IV Efficiency of Operations
(b) The number of unscheduled water supply stoppages lasting more than 30
minutes
(a): continuity of service expressed as the the percentage of readings measuring more
than or equal to 12 m pressure at the Critical Measuring Points (CMPs), based on a
continuous pressure logged at all CMPs during the period under report.(b): quality of
water supplied, by presenting the aggregated reports of water quality tests undertaken
as well as registry of SCADA data on water quality at WTP and six CMPs for the
period under review
This section will present a summary of the capital works carried out and the
investment incurredduring the period, with a breakdown of type of investments. The
repair and maintenance works undertaken during the reporting period will be presented
separately indicating the type of repair and maintenance work undertaken
The Contractor will prepare a draft of Final report and hand it over to the owner one
month prior to the end of the Operation and Maintenance Period. The report will
present a review of the Contractor’s major obligations under the Contract, as
undertaken andcompleted / deliveredand include the necessary conclusions. Upon
receipt of the owner’s comments and suggestions, the Contractor will prepare the
finalized version of the report
SIXTH SCHEDULE
TARIFFS AND TARIFF CHANGES
Initial Tariff at Commencement Date
At the Commencement Date of this OMSA the following tariffs shall be applicable in
the Water Supply Area. A two part tariff consisting of nominal fixed charge and a
variable volumetric charge (per cu.m) based on actual volume consumed every month
or a Fixed Charge, as the case may be, will be charged for each connection.
The Owner in consultation with the KNP shall be fixing the tariff. However, the owner
shall be disclosing the tariff for billing purpose to the contractor three months in
advance to the start of Operation and Maintenance period. This is further clarified that
the tariff will be for billing purpose and this will not affect the contractor’s payments
for Operation and Maintenance.
Regular Tariff Review and Adjustment
The annual increase in tariffs will be linked to the customer price index (CPI) and will
be effective April1 of each financial year.
SEVENTH SCHEDULE
LIST OF KEY STAFF FOR O&M PERIOD
(as identified by the Operator in the bid in response to contract requirements. List, with
all relevant information, to be appended herewith)
Appendix 3C
FOR A CONTRACT
SURVEY, REVIEW THE DESIGNS, REDESIGN WHERE NECESSARY AND BUILD WATER
SUPPLY IMPROVEMENT SCHEME FOR KHARGONE TOWN, KHARGONE DISTRICT OF
MADHYA PRADESH AND OPERATE AND MAINTAIN THE BUILT SYSTEM FOR 5 YEARS
Amount (In
No Bill No and Name
Lakhs INR)
1 Bill 1:Survey and Investigation
2 Bill 2: Design Review and Preparation of Designs and Drawings
Bill 3: Study of Billing System and Development and Establishment of
3
Grievance Redress System
4 Bill 4: Approach Road and Site Development Works
5 Bill 5: Raw Water Intake Well - cum - Pump House
6 Bill6: Water Treatment Plant and clear water sump - cum - Pump House
Bill 7: Pumping and Electrical Equipment for Raw Water and Clear Water and
7
Electrification
8 Bill 8: Elevated Service Reservoirs
Bill 9: Rising mains and distribution networks including meters and Service
9
connections
10 Bill 10: SCADA systems
11 Bill 11: Implementation of Environmental Safeguards and Management Features
Bill 12: Rehabilitation of Existing Serviceable Components including ESRs and
12
pipelines
Total of Bill No. 1 to Bill No. 12 (A)
B. Provisional Sum
Extension of distribution network and meters and connections in areas beyond
(i) 500.00
the scope defined in this contract
(ii) Restoration of structures and utilities damaged during construction 20.00
(iii) Repair, Rehabilitation and up gradation of Existing WTP 80.00
Implementation of Environmental Management Measures except those covered
(iv) 50.00
in Bill 11
(v) Resettlement and/or Rehabilitation 50.00
Total of Provisional Sum (B) 700.00
Grand Total (A+B)
Bill 13: Contractor Fixed O&M Fee for Operation and Maintenance
Fixed O&M
Fee Rs in
lakhs/ annum
Bill 14: Contractor Variable O&M Fee for Operation and Maintenance
Year 1 2* 3 4 5
Variable Fee
In Rs per cum
of metered
water billed to
customers
*Note: The rates quoted for year 2 shall be the base rate for the next 3 years i.e. Year 3, 4 and
5.
BILL OF QUANTITIES
Bill 2 : Design Review and Preparation of Design and Drawings(Reference clause 2 of 3A(3))
Quan Rate Amount
2 Description Unit
tity Figures Words
Design Review, Design of the
Intake well with pump house,
submission of design and
2.1 drawings in 10 hard copies and Job 1
reproducible soft copy, getting
approval from Government
Engineering College/IIT/NIT
Design Review, Design of all the
components of WTP including
pump house, submission of design
2.2 and drawings in 10 hard copies Job 1
and reproducible soft copy, getting
approval from Government
Engineering College/IIT/NIT
Design Review, Design of all the
ESRs, submission of design and
drawings in 10 hard copies and
2.3 Job 1
reproducible soft copy, getting
approval from Government
Engineering College/IIT/NIT
Design Review, Design of
RWRM, CWRM and feeder
mains, submission of design and
2.4 drawings in 10 hard copies and Job 1
reproducible soft copy, getting
approval from Government
Engineering College/IIT/NIT
Design Review, Design of pumps
at Intake and WTP, submission of
design and drawings in 10 hard
2.5 Job 1
copies and reproducible soft copy,
getting approval from Government
Engineering College/IIT/NIT
Design Review, Design DMA
2.6 Job 1
distribution network using
BILL OF QUANTITIES
Bill 3 :Study of Billing System and Development and Establishment of Grievance Redress
System
Rate Amount
3 Description Unit Quantity
Figures Words
Study the existing Billing System and
the customer grievance redress system,
suggest improvements in the existing
3.1 Job 1
systems with cost implications, submit
the report in 3 hard copies and one
reproducible soft copy
3.2 Management Part
A Computers and Printers
(a) Server Nos. 1
(b) PC's Nos. 3
(c) Printer Nos. 3
(d) Desktop Printer Nos. 3
(e) Handheld Billing Printers Nos. 3
B Software
(a) Billing System Nos. 3
(b) Maintenance Management System Nos. 3
C Customer Service Centers – 2 nos
(a) Tables Nos. 3
(b) Chairs Nos. 3
(e) Interiors Nos. 3
(f) Communications Nos. 3
(g) Networking Costs Nos. 1
(h) Toilet Nos. 3
D Equipment
(a) Leak detection ground phones Nos. 3
(b) Pipe locaters Nos. 2
(c) Portable Flow meter Nos. 2
Total for Bill 3:
BILL OF QUANTITIES
Bill 4 :Approach Roads and Site Development Works
Figures Words
1 Construction of approach road of
carriageway of 4m width with CC
pavement including earthwork as per
specifications m 450
Sub-total of Bill No. 4A
B – Site Developments
Construction of MS bridge of
minimum width 4m with steel
structural members for approach to
intake well location in river to the
specified ground level at river bank
of approx length 50 meters
supported on RCC columns, RCC
floor beams and slab, tie beams of
RCC and supported over proper
foundation system resting on /PCC
including providing 25mm dia GI
(medium class) pipe railing 1.0m
height in three row with all bye
work complete.
BILL OF QUANTITIES
Bill 6: Water Treatment Plant (Reference clause 6 of 3A(3) )
Rate
No. Description of Item Unit Quantity Amount
Figures Words
Design, providing,
construction of water
treatment plant of 30 MLD
capacity, comprising of all
relevant units on basis of
concepts to commissioning
with all units including
testing, trial run and
commissioning, including
necessary electro
1
mechanical equipment and
plants, automation, wiring
cable laying, accessories
such as auxiliary pumps,
etc. including necessary
pipes, valves and flow water
devise on turnkey basis,
based on Dual Filter Media
with all essential units.
BILL OF QUANTITIES
Bill 7: Pump Sets and Electrical Equipment(Reference clause 4of 3A(3))
Item Description of Item Rate
Unit Quantity Amount
No. Figures Words
Transformer / Electrical Sub
Station:-
Design, Supply at Site, Installation,
Construction, Commissioning, Testing
and Trial Run of dedicated electricity
1
power supply system, comprising of
transformers, pole structures, cables etc,
including cost of all civil, mechanical,
electrical and instrumentation works etc
all complete as per Specifications
(i) At Intake Well KVA 200
(ii) At Water Treatment Plant KVA 500
Electro mechanical Equipment for Raw
water: - Supplying, installation, jointing,
erection, testing and commissioning
33KV power line from MPSEB
substation to raw water intake and at
WTP and all accessories including pole
2
structures, cables etc, including cost of
all civil, mechanical, electrical and
instrumentation works etc all complete
including all taxes, duties, royalty etc.,
all complete as per Specifications and as
required for completeness of work.
(i) At Intake Well and WTP M 3000
BILL OF QUANTITIES
Bill .8 Elevated Service Reservoirs (Reference clause 7 of 3 A(3))
Rate Amount
8 Description of Item Unit Quantity
Figures Words
3 2250 18
5 2250 18
7 2250 18
BILL OF QUANTITIES
Bill 9 :Rising Mains and Distribution net work
Bill 9 A : Raw Water and Clear Water Rising Main (Reference clause 5, 9 and 13 of 3 A(3) )
PE - 100
11 Construction of dowel
jointed, PCC pavement in
M-30 grade concrete over a
prepared sub base with 43
grade cement maximum size of
coarse aggregate not
exceeding 25 mm, mixed in
a batching and mixing plant
as per approved mix design,
transported to site, laid with a
fixed form or slip form paver
with spreading the concrete
by shovels, rakes compacted
using needle, screed and plate
vibrator and finished in a
continuous operation
including provision of
contraction, expansion, and
longitudinal joints, joint filler,
separation membrane, sealant
primer, joint sealant, de-
bonding strip, placing of
dowel bar, tie rod admixtures
as approved, curing
compound, finishing to lines
and grades as per approved
drawings as per IRC-15 2002
and as per relevant clauses of
section-602 of specifications
complete but excluding cost of
steel in dowel bar and tie rod 24389.42
etc. cum
13 Supply of all labour, materials,
T and P etc. all complete and
construction of following valve
chambers as per type design.
(i) Sluice valve masonry type
(Size: 1.5 x 1.5 x 2.0m). Nos. 68
(ii) Scour valve masonry type
(Size: 1.5 x 1.5 x 2.0m). Nos. 30
(iii) Constructing one brick
masonry chamber 60x60x75
cm inside, with 25 class
designation brick work in
cement mortar 1:4 (1 cement
: 4 coarse sand) for fire
hydrants with C.I. surface box
Page 535 of 553
BoQ Indicative
BILL OF QUANTITIES
Bill 10 : SCADA System (Reference clause 11 of 3A(3) )
Rate Amount
S.No. Particulars Unit Quantity
Figure Words
Installation, synchronizing, testing
and commissioning of SCADA
system (including five years
maintenance services), of reputed
make and conforming to relevant
BIS Code of Practices with latest
amendment current at the time of
execution for flow control and
monitoring between raw water
intake arrangement, treatment plant,
clear water sump, clear water pump
set and elevated service reservoirs
having main controlling unit for
flow and pressure measurement and
controls at the water works office at
A treatment plant location. Lot 1
g. Ultrasonic level (ESR)
sensor and transmitter
h. Pressure sensor and
transmitter and pressure reducing
valve
i. Turbine flow meter with
signal generation
j. Valve actuator Motor
k. Valve actuator Drive
l. Programmable logic
controller/ remote Terminal Units
m. Pressure sensors and online
water quality monitoring at 6
Critical points as identified by
Project Manager
BILL OF QUANTITIES
Bill 11 : Environmental and Social Safeguard Implementation (Reference annexure H)
Curren Rate
# Particulars Unit Quantity Amount
cy Figure Words
BILL OF QUANTITIES
Bill 12 : Rehabilitation of Existing Reservoirs and Pipeline (Reference clause 12 of 3 A (3))
Curre Rate
# Particulars Unit Quantity Amount
ncy Figure Words
Rehabilitationand integration
13.1
with the whole system
BILL OF QUANTITIES
Bill 13: Contractor Fixed O&M Fee (Base Rates, subject to performance linked
adjustments) for Water Supply Services, including Operation, Maintenance, Repairs,
and Management of all Components from Source to Customer to Ensure Service
Delivery as per Performance Standards Specified, during 5 years of Operation and
Maintenance Period
Fixed O&M
Fee Rs in
lakhs /
annum
BILL OF QUANTITIES
Bill 14: Contractor Variable O&M Fee (Base Rates, linked to adjustment under
Appendix 5, Section 1) for Water Supply Services, including Operation,
Maintenance, Repairs, and Management of all Components from Source to
Customerto Ensure Service Delivery as per Performance Standards Specified,
during 5 years of Operation and Maintenance Period
Year 1 2* 3 4 5
Variable Fee
In Rs per cum
of metered
water billed to
customers
Note: The rates quoted for year 2 shall be the base rate for the next 3 years
i.e. Year 3, 4 and 5.
Appendix 4
FOR A CONTRACT
DPR APPENDIX
The following parts of Detailed Project Report are attached in data room
www.mpudc.co.in:
1. Salient Features indicating the DPR provisions
2. Outlines/ proposed design of various components under the sub
project
3. General Arrangement Drawing and indicative drawings of anicut,
intake, WTP, pipeline alignments showing the diameter
4. Location Plans of Anicut, Intake and WTP and ESRs
Appendix 5
APPENDIX 5
FOR A CONTRACT TO
P1 = P0’ (a + b E1 + c L1 + d M1 )
----- ---- -----
E0 L0 M0
in which:
P1 = adjustment amount payable to the Contractor for Operations and
Maintenance Phase;
per Cu.m price for O&M (base price, as per price bid);
P 0=
a= estimated percent of energy component in Contract price (a =0.43)
b= estimated percent of labour component in Contract price (b =0.27)
c= estimated percent of material and consumables component in Contract price
(c = 0.15);
E0, E1 = energy cost as fixed by State Regulatory Authority on the base
date and the date for adjustment, respectively
L0, L1 = labour indexes, CPI IW (Industrial Workers) for the BHOPAL; on the
base date and the date for adjustment, respectively
M0, M1 = material indexes, WPI on the base date and the date for adjustment,
respectively.
The Base date for price adjustment shall be 20 days prior to the deadline for Bid
submission. Adjustment of the O&M price shall be done on the first day of each year
of the O&M period (First period and second period) based on the indices prevailing on
the last date of the previous calendar month. The O&M price thus adjusted shall be
applicable for the entire year.
Appendix 6
FOR A CONTRACT TO
Appendix 6
CONTRACTOR'S PRICE SCHEDULE
1.0 General
1.2 The Price Schedules do not give a full description of the Plant and
Equipment, Contractor’s Equipment (Operations) and Contractor’s
Equipment (Design-Build) to be supplied and the Services to be
performed under each item. Contractors are deemed to have read the
Draft Contract, including the Technical Specifications Appendix
consisting of the Design-Build Services Appendix and Operations and
Maintenance Services Appendix, and other sections of the Bidding
Documents to ascertain the full scope of the requirements of the Contract
included in each item prior to filling in the prices. The entered prices are
deemed to include the full scope as aforesaid, including overheads and
profit.
2.0 Pricing
2.1 Prices shall be filled in indelible ink, and any alterations necessary
due to errors shall be initialed by the Contractor. As specified in the Bid
Data Sheet, prices shall be fixed and firm for the duration of the Contract,
except as adjusted in accordance with the Contract.
2.2 The Bid Price shall be quoted in the manner indicated and in the
2.3 The Owner will make payments to the Contractor in INR indicated
under each respective item.
The rules relating to adjustments to the Bid Price, if any, are set out
in the Appendix 5, Section 1to the Draft Contract.
Amount
No Bill No and Name (In Lakhs
INR)
1 Bill 1:Survey and Investigation
2 Bill 2: Design Review and Preparation of Designs and Drawings
Bill 3: Study of Billing System and Development and Establishment
3
of Grievance Redress System
4 Bill 4: Approach Road and Site Development Works
5 Bill 5: Raw Water Intake Well - cum - Pump House
Bill6: Water Treatment Plant and clear water sump - cum - Pump
6
House
Bill 7: Pumping and Electrical Equipment for Raw Water and Clear
7
Water and Electrification
8 Bill 8: Elevated Service Reservoirs
Bill 9: Rising mains and distribution networks including meters and
9
Service connections
10 Bill 10: SCADA systems
Bill 11: Implementation of Environmental Safeguards and
11
Management Features
Bill 12: Rehabilitation of Existing Serviceable Components
12
including ESRs and pipelines
Total of Bill No. 1 to Bill No. 12
Note:
1. The Fixed O&M Fee is to include all elements of (a): manpower costs (b):
establishment (incl. vehicle) costs and administrative costs for operation and
maintenance of all components of the water supply system from source to
Customer;
2. The Variable O & M Fee is to include all elements of (a): variable power costs
(b): cost of chemicals and other consumables (c): diesel costs substantially
incurred in the production and distribution of water. The Variable O&M Fee
will be linked to adjustment under Appendix 5, Section 1.
The amount of Fixed O&M Fee payable will be subject to performance linked
adjustment (as provided in Para 3.3 of Schedule 4 to Appendix 3B) to the figures
quoted herewith.
Moulded Case
Siemens, Schneider M.G, Jyoti, L
(MCCB)
&Tor equivalent
RelayandContactors Siemens, Alstom, Jyoti,ABB,L&Tor
equivalent
Tropodur,Finolex,Asian,
Cables
Gloster,Incab,Universal,Polycabor
equivalent
PanelEnclosures Rittal,President,CutlerHammeror
andConsoles equivalent
Switch fuseDisconnector LandT,FNType, Siemens 3 KLType,
GEPC or equivalent
Multi-Function Enercon,LandT, SOCOMEC or
EnergyMeters equivalent