Sitructural Details of Super Structure
01. Typical Bar Notation
02. Concrete Outline Drawing
    In structural drawings, a Concrete Outline Drawing (also called Slab General Arrangements) is a technical
    drawing that shows the shape, size, and layout of concrete structural elements such as:
•   Columns
•   Beams
•   Slabs
•   Staircases
    It focuses only on the concrete parts, before reinforcement and other construction details are added.
    Check List for Concrete Outline Drawing
•   Grid with Dimentions
•   Concreted Area (Outline)
•   Voids (Ducts)
•   Staircase
•   Level Drops
•   Columns with names
•   Beams with names
•   Table for Column and Beam Sizes
•   Sections
•   Slab Symbole ( 1 way span, 2 way span)
•   Slab thickness
•   Elevation of the slab
•   Secondary Concreting parts
•   Beam denoting from bottom to top , and after that left to right.
    Add Staircase Like This
Washroom Level Drop
 •    How can we see that without R/F
Drainage Pipe
 •    Dranaige Pipe arrangement for water closet
 •     For the Dranaige Pipe of squatting pan, can be placed through the beam or through the slab as per
 the instructions of structural engineer.
Waste water Pipe
R/F Supporting Symbole
          01. Cantiliverd Slab
� Simply Supported Edge
   •   The slab rests freely on a beam or wall.
   •   R/F supporting on the beam.
   •   No moment resistance at the edge.
   •   Reinforcement does not need to be bent up or continued far beyond the support.
          02. One way Supporting Slab
� Fixed or Continuous Edge (Full Support)
   •   The slab is supported monolithically with the beam or wall.
   •   Moment resistance is expected at the edge.
   •   R/F supports on two beams. (top and bottom)
   •   Top and bottom reinforcement are extended or hooked.
   •   Used in slabs poured together with beams or frames.
          03. Two way Supporting Slab
� Slab Supported on All Four Sides (2-Way Slab)
   •   This symbol is often used to indicate a 2-way slab behavior.
   •   All four edges are supported (like the edges of a room).
   •   R/F supporting for 4 directions.
   •   Load is distributed in two directions, and reinforcement is placed in both directions.
       04. Slab pannel
•   Normally slab is like this.
•   When add a load it will deform like this.
•   Skin will try to break from critical points.
•   Therefore we must add R/F
•   Breaking Points of top side
•   To avoid the breaking we must add R/F
•   Typical R/F arrangement. (for the middle of the slab no need R/F)
•   If the bar length is not enough to cover the slab, we have to lap the R/F. maximum length of
    a bar is 6m. If it is exceeds, we should lap.
•   Therefore, we can add an U bar.
Length of the top R/F
         •   One third (1/3) or (0.3) from the span. (In between the beam edges)
R/F detail for the bar mark of 20
          •   Sectional View from one direction
          •   Sectional View from the other direction
B1 – Nearest bar to the bottom – Comes for shorter span
T1 - Nearest bar to the top - Comes for shorter span
       05. Cantiliver Slab
•   Cantilever slab bends like this.
                                               This T1 can become B1.
•   If the total bar exceeds 6m. (original bar length is 6m)
•   Need to add a lap and continue the slab r/f.
•   Do not add a lap in critical points.
Typical bar arrangements of cantilever Slabs
How to avoid cracks (defects) in cantilever slab
•   Increase the slab thickness
•   Add more R/F
06.Beams