LNV TECHNOLOGY P LTD
LINE III PROJECT
Method Statement: PURLING ERECTION
SOP
ERECTION OF PURLING
(Pre heater (Bucket Elevator), Raw Mill Grinding, Hopper and
conveyor Gallery)
AMBUJA, LINE III PROJECT
May 2025
Prepared By Reviewed By Approved By
LNVT LNVT ACL Limited
PROJECT: AMBUJA, LINE III PROJECT
Client: - ACL
Method statement Number: SOP/LNVT/36
Drawings Ref No:
SL NO. DATE Description Prepared By Checked By
of Revision ( SINOMA
LNVT )
PURPOSE
The purpose of this procedure is to provide the method of erection with safety guideline in during
erection of purling in all over project.
SCOPE
Scope contains Purling Erection Work Including shifting of goods, Erection, Fixing with
gallery/structure, etc. Scope of this document also gives guide line for time to time inspection &
documentation as per contract.
REFERENCE DOCUMENT
1) Approved GA Drawing
2) Approved drawings for purling erection in all over project
3) Contract Documents.
4) Relevant IS Codes & standards.
EQUIPMENTS
1. Suitable Cranes/frana (3rd party certification), if required
2. Cherry Picker, (3rd party certification), if required
3. Rope pulley (tested/checked)
4. Sling, Wire Rope & All necessary lifting tools & tackles (3rd party Certification).
5. Safety accessories /PPE required for Erection purpose.
Activities Hazards Control Measures
Work permit Unauthorized Authorized work permit holders shall ensure obtaining and
commencement maintaining valid work permits.
of works
May result in Inform all people regarding permit conditions before work
exposing people starts
and/or potential Supervisors must conduct daily toolbox talk about nature of
to harm or work and associated potential hazards and their essential
damage precautionary
Shifting of Fall of material Purling shall be tied through ratchet belt or chain with trailer
purling from bed. Ensure no knot in the belt.
steel yard to site Hitting to people Trailer driver must be passed all entry procedures from ACC
by trailer or existing concerned departments
properties Signalman/helper/flagman must be available with trailer while
shifting for control the traffic at site
Speed limit should be below 20KM/h inside project premises
After reached at destination stop the engine and ignition key
should be removed from its place and wheel stopper and
hand break must be use of trailer
2
Area should be barricaded
Keep parking light ON of the truck during night operation
Unloading of Placing of frana Ground should be levelled and compacted
purling member Ensure no overhead power cables shall be routed in the
by frana (Toppling of vicinity of the frana
frana) Frana shall be certified by a competent person and the TPI
certificate should be submitted to ACC
SLI, Limit switches should be fitted in the frana and should be
in working condition
frana operator should be trained with valid licence and valid
certificate
Operator will not use frana in wind condition while wind speed
over 25mph
Pinch point Use appropriate PPEs according to work activities
Ensure that the riggers do not place their fingers or hands in
between the slings and the lifting point or D shackles while
lifting is in progress
Fall of materials Lifting tools tackles shall be tested by third party with valid
due to failure of certificates also colour coded
lifting tools and All lifting equipment, tools tackles must be done as visual
tackles inspection at site prior to use
All lifting tools should be attached with the load under
supervision of rigging expert
Rubber padding or suitable arrangements to be made for
protecting slings from sharp edge
Guide rope should be attached with load with sufficient length
to control swing of load
Person injury Guide rope/tag line should be attached on the opposite
directions of the purling
Ensure the portable ladders to be used as means of access
and egress for slinging with purling
Ladder should be supported by another worker while A
worker is using it
Installing of rope Slip/trip hazards Housekeeping should be done
pulley with
gallery structure Workers fall from All gap between gratings and checker plate or between two
height galleries should be covered
Proper hand railing shall be provided at both side
Life line arrangement should be completed before enter in
gallery, if required
All workers should be fit for height work
All workers should be worn FBH and anchored with hand rail
or life line, which is suitable
Fall of rope Rope pulley should be physically checked before carrying to
3
pulley the site
Ground area should be barricaded
Workers should be carrying rope pulley carefully to the
installing point
Rope pulley hook latch should be in working condition
Structure sharp edge should be covered by soft pad before
hanging of rope pulley
Minimum two person required for installing of rope pulley
Lifting of purling Fall of purling Ground area should be barricaded
member member due to WLL clearly marked on pulley body
failure of rope Rope pulley should be physically checked at site prior to
pulley installing with structure
Rope pulley hook latch should be in working condition
Fall of purling Nylon rope should not be less than 30 mm dia
member due to Rope should not be more old.
damage of nylon Rope should be in healthy condition
rope / rope Rope should not higher than pulley grip size
slippage from Rope knot with purling should be perfect and free from
pulling hand slippage
A guide rope should be tie with purling for control the
swinging of load
Minimum two persons required for pulling the rope
Cotton hand gloves should be use for pulling the rope
Personal Injury Appropriate PPEs should be use; cotton hand gloves should
be preferring for pulling the rope
Minimum two persons required for pulling the rope
Fixing/installing Fall of fixing bolt Ground area should be barricaded
of purling and spanner All fixing bolt should be kept inside bags
member with The bags should be secured with gallery structure
gallery structure Workers should not hold too many bolts at one time
All spanner should be tie with workers FBH
Fall of person All gratings/ chakkar plate of gallery should be welded
from height All gap should be covered properly and welded
Life line arrangement should be done, if required
Before enter in gallery, all workers should be worn FBH
Lanyard snap hook should be anchored with hand railing or
life line, whatever possible
During bolting of purling, workers should not come out from
gallery structure
Only medical fit workers should be allowed to work at height
SAFETY GUIDELINES
1. Necessary information about the height work shall be provided to the foreman, frana
operators & riggers through tool box talk & induction training.
4
2. Lifting tools shall be tested by third party and certificate should be submitted to ACL
concerned department.
3. Barricading of area shall be done before lifting of materials
4. The direction to the frana operator shall be given only by identified experienced rigging
foreman.
5. Trained & experienced workmen shall be deployed for height work.
6. Necessary PPE (Safety shoe, certified full body safety harness, hand gloves, goggles,
reflective jacket and safety helmet) shall be used during assembly, erection & welding of
duct
7. Life lines shall be used by workmen while working on height, if required
8. While working at height hand tools shall be tied by rope of adequate strength to prevent its
fall from height.
Management
Line management has the responsibility to implementing the mandatory requirements of this
erection Plan. All line managers and their team dealing in inspection, maintenance, and operation
are responsible for adhering to the procedure for crane, cherry picker, lifting tools and other
equipment and items. These include their contractors and contract workforce. Details of
responsibilities are as under.
Concerned engineer
Check suitability of crane referring to load chart & raise the request in prescribed format including
all details. Load chart will be provided by the crane supplier / contractor. For in house cranes load
charts shall be maintained.
Ensure Area/ground preparation is done wherever required. It is to be done in consultation with
Site - Civil Engineer if crane is required to position on soft soil ensures ground compaction to be
done as per requirement.
Ensure completion of mandatory requirements such as vehicle entry permit, risk assessment,
equipment handling check list as per checking to be done before starting the job.
Ensure use of tested lifting tool-tackles of appropriate capacity (sling / synthetic belt / D shackle
etc.) Ensure tool box talk before all movements & rigging operations.
To discuss rigging plan with the foreman, signal man & crane operator for safe execution of job.
Ensure operating locations are far enough away from shoring, excavations, trenches, buried
utilities, foundations, etc. to eliminate the risk of collapse.
Crane and lifting champion
1. Check & confirm suitability of crane given in request as per load chart and allot in availability
slot.
2. Conduct periodical audit to verify compliance to daily checklist.
3. To hold and/or check documents such as PUC/ RTO registration / Insurance
certificate/certificate from competent person/driving license of crane operator.
4. Repair & maintenance of all cranes for smooth & safe operation and to ensure that record is
maintained.
5. Predictive & proactive maintenance of all cranes for smooth & safe operation and to ensure that
record is maintained.
6. Availability of cranes for allotment
7. Assist for critical lifts in plant
Heavy Equipment Contractor
5
1. Providing qualified safety supervisor & executing supervisor for monitoring operation safely.
Ensuring that the deployed operator is well trained, licensed, experienced, and competent to
operate the particular crane to which they are assigned on the particular job involved.
2. Providing on going, high-quality training and upgrading programs for all personnel to ensure a
consistently high level of competence in all phases of the operations.
3. Ensuring the crane is used in accordance with the manufacturer’s instructions and all
applicable regulations.
4. Ensuring that the log book is maintained and updated.
5. Ensuring that all personnel involved in maintaining, repairing, transporting, and assembling the
equipment are well trained, experienced, and competent to handle their specific jobs in a safe
and efficient manner.
6. Ensuring that a thorough crane maintenance and inspection program is established and
maintained.
Rigging contractor
Rigging contractor ‘s site in-charge is responsible to deploy task based ―Foreman & Signal man
with rigging crew to ensure safe & correct rigging operation & signal to operator.
Rigging foreman/ signal man & riggers
1. Will follow procedure to use crane, best rigging practice for safe operation of crane.
2. Will use only lifting tools which are tested & of appropriate capacity.
3. Rigging foreman/signal man will identify himself by wearing specific jacket.
4. Not to use cell phone during crane operation. Use of Walky-talky preferred.
Crane Operators
1. Check ground condition & position the crane as per procedure
2. Operate crane using his best skill, will also check all interlock & safety devices are in working
condition. He will inform his supervisor & concern plant engineer if any of the safety devices is
not in working condition. (i.e. SLI)
3. Report unsafe conditions or breach of procedural requirements to their supervisor.
4. Comply with procedures and information provided in training and in the Crane safety program.
5. Ask supervisor for assistance or clarification to maintain safe operations of cranes when
necessary
6. Hold copy of valid license
7. Equipment handing checklist should available with operator prior to lift if the load above two
MT.
8. Conduct functional tests prior to using the equipment.
9. At the beginning of each operator's shift, the upper limit switch of each hoist shall be tried out
under no load. Extreme care shall be exercised; the block protection shall be kept in line.
10. While any employee is touching the load or hook, there shall be no hoisting, lowering, or
traveling.
11. Not to use cell phone during crane operation.
Inspection of Wire Rope Slings, Hooks, Shackles and Winches Slings
Slings
6
Should be tested and tagged on a six monthly basis and marked with SWL and inspection date.
They shall be visually inspected by a competent person before all lifting operations.
Slings shall be rejected when there is:
1. Severe deformation - where strands are severely kinked or the core is protruding
2. Severe wear - wear of high points of the sling caused by dragging the sling across decks
contributes to early broken wires. A sling which has wires worn to half normal diameter on
high points should be replaced
3. Termination damage Severe corrosion (be aware of the possibility of internal corrosion)
No SWL indicated or last inspection date/colour code missing.
Hooks and Shackles
1. Check that the SWL is adequate for the lifts
2. Use only hooks and shackles marked with the SWL
3. Check shackle and pin for excessive wear:
4. Make sure that the pin is free, but not loose in the tapped hole. Secure pins with wire to
prevent them vibrating free
5. Threads of the pin should be undamaged and without appreciable wear
6. Never replace the pin of a shackle with a bolt. Bolts may not be to the same standard and
could fail
7. Check shackle and pin for distortion
8. Check alignment of the pin holes; the untapped hole should not be too large.
CATEGORY OF SKILL REQUIRED
1. Rigger Foreman
2. Riggers
3. Fitter
4. Helpers
Emergency Rescue Plan:
In case of any incident, call to emergency Control Room
For emergency 24hr ambulance facility & Paramedical staffs will be available nearby First
Aid Centre.
In case of vehicle break down or in any incident contact to our Plant & Machinery In-
charge for rescue the vehicle/Equipment.
All emergency contact number is displayed at site for immediate communication around the clock.
Further Onsite Emergency response plan to be followed if any emergency situation is
occurred